Synchronous construction device and method for main tower and main beam of cable-stayed bridge with scaled simulation

By using a scale to simulate the synchronous construction device of the main beam of the cable-stayed bridge cable main tower in the construction of cable-stayed bridge, the synchronous construction of the main beam and the main tower is solved, and the problems of complicated construction steps, low efficiency and high material consumption in the existing construction methods are solved, which improves construction efficiency and reduces costs.

CN115762324BActive Publication Date: 2025-04-01ANHUI HIGHWAY BRIDGE ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211542211.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-03
Publication Date
2025-04-01
Estimated Expiration
2042-12-03

AI Technical Summary

Technical Problem

In the existing cable-stayed bridge construction methods, the construction steps of the main tower and main beam are complicated, resulting in low construction efficiency, high material consumption, and is not conducive to reducing construction costs.

Method used

A synchronous construction device for main beams of main towers of scale-scaling cable-stayed bridge cables is provided, including base, transverse mounting frame, vertical mounting frame, main beam construction component, main tower construction component and synchronous drive component. Through the coordinated work of these components, the synchronous construction of the main beam and the main tower is realized.

Benefits of technology

Through the synchronous construction method, the construction steps are shortened, the construction efficiency is improved, material consumption is reduced, construction costs are reduced, and the smooth construction and reasonable bridge formation status of the cable-stayed bridge are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115762324B_ABST
    Figure CN115762324B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of bridge construction, and specifically to a scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device and construction method, comprising a base, a transverse mounting frame and a vertical mounting frame, and also comprising a main beam construction component, a main tower construction component and a synchronous drive component; the main beam construction component is located in the middle of the transverse mounting frame and is slidably connected to the transverse mounting frame; the main tower construction component is located in the middle of the vertical mounting frame and is slidably connected to the vertical mounting frame; the synchronous drive component is installed on the transverse mounting frame and the vertical mounting frame, and by arranging the main beam construction component, the main tower construction component and the synchronous drive component, the main beam construction component and the main tower construction component can operate synchronously, thereby meeting the requirements of synchronous construction, reasonably optimizing the cable-stayed bridge construction method, improving the cable-stayed bridge construction efficiency, ensuring the smooth construction of the cable-stayed bridge, and achieving a reasonable bridge completion state.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a synchronous construction device and a construction method for a main beam of a cable-stayed bridge with a reduced-scale simulation. Background Art

[0002] A cable-stayed bridge, also known as a cable-tensioned bridge, is a type of bridge in which the main beam is directly pulled on the bridge tower by many cables. It is a structural system composed of a pressure-bearing tower, tensioned cables and a bending beam. As a cable system, the cable-stayed bridge has a greater span capacity than a beam bridge and is the main type of long-span bridge. A cable-stayed bridge is composed of many steel cables directly connected to the tower to lift the bridge deck. It is mainly composed of a main tower, a main beam and cable-stayed cables.

[0003] When constructing a cable-stayed bridge, the general construction method is to construct the main tower first, and then construct the main beam after the main tower construction is completed. However, this construction method will cause complicated construction steps, consume a lot of time, and thus reduce construction efficiency. At the same time, this construction method requires frequent use of various supporting and other building auxiliary structures, consumes more materials, and is not conducive to reducing construction costs. Therefore, in order to reasonably optimize the construction method of the cable-stayed bridge, improve the construction efficiency of the cable-stayed bridge, ensure the smooth construction of the cable-stayed bridge, and achieve a reasonable bridge state, a scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device and construction method are hereby proposed. Summary of the invention

[0004] The object of the present invention is to provide a synchronous construction device and method for a scaled simulation cable-stayed bridge cable main tower and main beam, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] A scaled simulated cable-stayed bridge cable main tower main beam synchronous construction device comprises a base, a transverse mounting frame installed on the upper end of the base, and a vertical mounting frame installed on one side of the upper end of the transverse mounting frame, and also comprises a main beam construction component, a main tower construction component and a synchronous drive component;

[0007] The main beam construction assembly is used to construct the main beam, and the main beam construction assembly is located in the middle of the transverse mounting frame and is slidably connected to the transverse mounting frame;

[0008] The main tower construction assembly is used to construct the main tower, and the main tower construction assembly is located in the middle of the vertical mounting frame and is slidably connected to the vertical mounting frame;

[0009] The synchronous drive assembly is used to realize the synchronous operation of the main beam construction assembly and the main tower construction assembly, and the synchronous drive assembly is installed on the horizontal mounting frame and the vertical mounting frame.

[0010] As a further solution of the present invention: the main beam construction assembly includes a transverse slide plate, a transverse fixing seat and a transverse construction hanging basket;

[0011] The transverse slide plate is located in the middle of the transverse mounting frame, and the transverse slide plate is slidably connected to the transverse mounting frame;

[0012] The transverse fixing seat is located below the transverse slide plate, and a lifting member for driving the transverse slide plate to move up and down is provided between the transverse fixing seat and the transverse slide plate, and two ends of the lifting member are fixedly connected to the transverse fixing seat and the transverse slide plate respectively;

[0013] The horizontal construction hanging basket is located below the horizontal fixing seat, and the two sides of the horizontal fixing seat are provided with a first movable member for driving the horizontal construction hanging basket to move along the length direction of the horizontal fixing seat, and the two sides of the top of the horizontal construction hanging basket are fixedly connected to the first movable member.

[0014] As a further solution of the present invention: the lifting member includes a first electric push rod, and the first electric push rod is provided with multiple groups, and the multiple groups of first electric push rods are evenly distributed between the transverse slide and the transverse fixed seat, the fixed end of the first electric push rod is fixedly connected to the bottom end surface of the transverse slide, and the output end of the transverse slide is fixedly connected to the top end surface of the transverse fixed seat.

[0015] As a further solution of the present invention: the first moving member includes a first sliding groove, a first sliding block, a first threaded rod and a first driving member;

[0016] The first slide groove is provided with two groups, and the two groups of the first slide grooves are respectively opened on both sides of the transverse fixing seat, and the first slide groove is provided with a first threaded rod arranged along the length thereof, and both ends of the first threaded rod are rotatably connected to the inner wall of the first slide groove through bearings;

[0017] The first threaded rod is provided with a first slider matched with the first threaded rod, the first slider is located inside the first slide groove, and the first slider is slidably connected to the first slide groove, a first connecting rod is fixed on the surface of the first slider, and the other end of the first connecting rod is fixedly connected to the top end of the horizontal construction hanging basket;

[0018] The first driving member is located at one end of the transverse fixing seat, and the first driving member is used to drive the two groups of first threaded rods to rotate.

[0019] As a further solution of the present invention: the main tower construction assembly includes a vertical slide plate, a vertical fixing seat and a vertical construction hanging basket;

[0020] The vertical slide plate is located in the middle of the vertical mounting frame, and the vertical slide plate is slidably connected to the vertical mounting frame;

[0021] The vertical fixing seat is located on a side of the vertical slide away from the horizontal mounting frame, and an adjusting member for adjusting the position of the vertical fixing seat is provided between the vertical fixing seat and the vertical slide, and two ends of the adjusting member are fixedly connected to the vertical slide and the vertical fixing seat respectively;

[0022] The vertical construction hanging basket is located on the side of the vertical fixed seat away from the vertical slide plate. The upper and lower ends of the vertical fixed seat are provided with a second movable member for driving the vertical construction hanging basket to move along the length direction of the vertical fixed seat. The side of the vertical construction hanging basket close to the vertical fixed seat is fixedly connected to the second movable member.

[0023] As a further solution of the present invention: the adjusting member includes a second electric push rod, and the second electric push rod is provided with multiple groups, and the multiple groups of second electric push rods are evenly distributed between the vertical slide plate and the vertical fixed seat, the fixed end of the second electric push rod is fixedly connected to the vertical slide plate, and the output end of the second electric push rod is fixedly connected to the vertical fixed seat.

[0024] As a further solution of the present invention: the second moving member includes a second slide groove, a second slider and a second driving member;

[0025] The second slide grooves are provided with two groups, and the two groups of second slide grooves are distributed and opened on the upper and lower end surfaces of the vertical fixed seat. The second slide grooves are provided with second threaded rods arranged along the length thereof, and both ends of the second threaded rods are rotatably connected to the inner wall of the second slide grooves through bearings;

[0026] The second threaded rod is provided with a second slider matched with the second threaded rod, the second slider is located inside the second slide groove, and the second slider is slidably connected to the second slide groove, a second connecting rod is fixed on the surface of the second slider, and the other end of the second connecting rod is fixedly connected to the vertical construction hanging basket;

[0027] The second driving member is located at one end of the vertical fixing seat, and the second driving member is used to drive the two groups of second threaded rods to rotate.

[0028] As a further solution of the present invention: the second driving member includes a driving sprocket, a driven sprocket and a motor;

[0029] The driving sprocket and the driven sprocket are both located at one end of the vertical fixing seat, one end of the two groups of the second threaded rods are both arranged through the vertical fixing seat, and the ends of the two groups of the second threaded rods are respectively fixedly connected to the central axes of the driving sprocket and the driven sprocket, and the surfaces of the driving sprocket and the driven sprocket are sleeved with chains matching therewith;

[0030] A motor for driving the driving sprocket to rotate is provided on one side of the driving sprocket away from the vertical fixing seat, the output end of the motor is fixedly connected to the central axis of the driving sprocket, and a motor seat for installing the motor is provided below the motor;

[0031] The structure of the first driving member is consistent with that of the second driving member.

[0032] As a further solution of the present invention: the synchronous drive assembly includes a third electric push rod, a first guide wheel, a second guide wheel and a steel rope;

[0033] The third electric push rod is used to drive one end of the transverse slide, the fixed end of the third electric push rod is fixedly connected to the transverse mounting frame, and the output end of the third electric push rod is fixedly connected to the transverse slide;

[0034] A first mounting seat is installed on one side of the transverse mounting frame close to the transverse slide, the first guide wheel is located in the middle of the first mounting seat, and the first guide wheel is rotatably connected to the first mounting seat;

[0035] A second mounting seat is installed on a side of the vertical mounting frame close to the vertical slide below, the second guide wheel is located inside the second mounting seat, and the second guide wheel is rotatably connected to the second mounting seat;

[0036] The steel rope is wound around the first guide wheel and the second guide wheel in sequence, one end of the steel rope is fixedly connected to the vertical slide plate, and the other end of the steel rope is fixedly connected to the horizontal slide plate.

[0037] The construction method of the scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device comprises the following steps:

[0038] S. Construction equipment installation:

[0039] Before the main tower and main beam are synchronously constructed, a pedestal is built at a suitable position, a vertical mounting frame is fixedly installed on one side of the upper end of the horizontal mounting frame, the main beam construction assembly is installed on the horizontal mounting frame, the main tower construction assembly is installed on the vertical mounting frame, and the synchronous drive assembly is installed between the horizontal mounting frame and the vertical mounting frame, and finally the horizontal mounting frame is fixedly installed on the top of the multiple groups of pedestals;

[0040] S. Adjustment of the horizontal construction hanging basket position:

[0041] After the installation of the horizontal construction hanging basket is completed, the first electric push rod is controlled to work, and the first electric push rod can drive the horizontal fixing seat to rise and fall, thereby driving the horizontal construction hanging basket to rise and fall, and adjusting the height of the horizontal construction hanging basket;

[0042] By controlling the first driving member to work, the first driving member can drive the first threaded rod to rotate, and when the first threaded rod rotates, the first slider can be driven to move inside the first slide slot, and when the first slider moves, the horizontal construction hanging basket can be driven to move through the first connecting rod, and the position of the horizontal construction hanging basket can be adjusted, so as to facilitate the subsequent construction of the cables on both sides of the main beam;

[0043] S. Adjustment of vertical construction hanging basket position:

[0044] After the vertical construction hanging basket is installed, the second electric push rod is controlled to work, and the second electric push rod can drive the vertical fixing seat to move, and the vertical fixing seat can adjust the distance between the vertical construction hanging basket and the main tower when moving;

[0045] By controlling the operation of the second driving member, the second driving member can drive the second threaded rod to rotate, and when the second threaded rod rotates, the second slider can be driven to move inside the second slide slot, and when the second slider moves, the vertical construction hanging basket can be driven to move through the second connecting rod, and the position of the vertical construction hanging basket can be adjusted, so as to facilitate the subsequent construction of the cables on both sides of the main tower;

[0046] S. Synchronous construction of cables, main towers and main beams:

[0047] When the main beam is under construction, the third electric push rod works, and the third electric push rod drives the horizontal slide plate to move to the side away from the vertical mounting frame to realize the horizontal laying construction of the main beam. At the same time, when the horizontal slide plate moves, the vertical slide plate can be driven to move upward through the first guide wheel, the second guide wheel and the steel rope to realize the vertical construction of the main tower. That is, when the horizontal construction basket moves a certain distance, the vertical construction basket rises a certain distance, that is, when the main beam is constructed for a certain length, the main tower can be constructed to a certain height. At the same time, when the main tower and main beam are under construction, the movable horizontal construction basket and the vertical construction basket are used to realize the construction of the cables on both sides, thereby realizing the synchronous construction of the cables, main tower and main beam on one side of the cable-stayed bridge. Finally, the synchronous construction of the cables, main tower and main beam on the other side of the cable-stayed bridge is completed in the same way.

[0048] Compared with the prior art, the present invention has the following beneficial effects:

[0049] The scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device and construction method of the present invention, by setting a main beam construction component, a main tower construction component and a synchronous drive component, can realize the construction of the main beam by using the main beam construction component, can realize the construction of the main tower by using the main tower construction component, and can realize the synchronous construction of the main tower by using the synchronous drive component while the main beam construction component is constructing the main beam, so that the main beam construction component and the main tower construction component can operate synchronously, meet the requirements of synchronous construction, reasonably optimize the cable-stayed bridge construction method, improve the cable-stayed bridge construction efficiency, ensure the smooth construction of the cable-stayed bridge, and achieve a reasonable bridge completion state.

[0050] The scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device and construction method of the present invention can complete the construction of the cable while the main beam construction assembly and the main tower construction assembly are in operation, thereby realizing the synchronous construction of the cable main tower and the main beam. Due to the synchronous construction, the construction steps are shortened, time is saved, and construction efficiency is improved. At the same time, fewer construction auxiliary devices are used, material consumption is reduced, and it is beneficial to reduce construction costs.

[0051] The scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device and construction method of the present invention ensure the safety of construction personnel by arranging a fully enclosed horizontal construction hanging basket and a vertical construction hanging basket, thereby increasing the protection effect of the device and meeting the use requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 It is a schematic diagram of the structure of the present invention.

[0053] Figure 2 For the present invention Figure 1 Schematic diagram of the enlarged structure of part A.

[0054] Figure 3 For the present invention Figure 1 Schematic diagram of the enlarged structure of part B.

[0055] Figure 4 It is a schematic structural diagram of the transverse guide groove in the present invention.

[0056] Figure 5 For the present invention Figure 4 Schematic diagram of the enlarged structure of part C.

[0057] Figure 6 It is a schematic structural diagram of the vertical mounting frame in the present invention.

[0058] Figure 7 For the present invention Figure 6 Schematic diagram of the enlarged structure of part D.

[0059] Figure 8 For the present invention Figure 7 Schematic diagram of the enlarged structure of part E.

[0060] Among them: 11, base; 12, horizontal mounting frame; 13, horizontal guide groove; 14, horizontal slide plate; 15, first slide groove; 16, first slider; 17, first electric push rod; 18, first threaded rod; 19, first driving member; 20, first connecting rod; 21, horizontal construction hanging basket; 22, vertical mounting frame; 23, vertical guide groove; 24, vertical slide plate; 25, second slide groove; 26, second slider; 27, second electric push rod ; 28. Second threaded rod; 29. ​​Second connecting rod; 30. Vertical construction hanging basket; 31. First guide wheel; 32. Second guide wheel; 33. Steel rope; 34. Third electric push rod; 35. Reinforcement column; 36. First mounting seat; 37. Second mounting seat; 38. Driving sprocket; 39. Driven sprocket; 40. Chain; 41. Motor; 42. Motor seat; 43. Horizontal fixing seat; 44. Vertical fixing seat; 45. Second driving member. DETAILED DESCRIPTION

[0061] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.

[0062] The present invention provides the following preferred embodiments:

[0063] Example 1: Reference Figure 1-Figure 8 As shown,

[0064] The scaled simulated cable-stayed bridge cable main tower main beam synchronous construction device comprises a base 11, a transverse mounting frame 12 mounted on the upper end of the base 11, and a vertical mounting frame 22 mounted on one side of the upper end of the transverse mounting frame 12. Specifically, a reinforcing column 35 for increasing the stability between the transverse mounting frame 12 and the vertical mounting frame 22 is installed between the transverse mounting frame 12 and the vertical mounting frame 22. The device also comprises a main beam construction component, a main tower construction component, and a synchronous drive component.

[0065] The main beam construction assembly is used to construct the main beam, and the main beam construction assembly is located in the middle of the transverse mounting frame 12 and is slidably connected to the transverse mounting frame 12;

[0066] The main tower construction assembly is used to construct the main tower. The main tower construction assembly is located in the middle of the vertical mounting frame 22 and is slidably connected to the vertical mounting frame 22.

[0067] The synchronous drive assembly is used to realize the synchronous operation of the main beam construction assembly and the main tower construction assembly, and the synchronous drive assembly is installed on the horizontal mounting frame 12 and the vertical mounting frame 22.

[0068] Reference Figure 4-Figure 5 As shown, the main beam construction assembly includes a transverse slide plate 14, a transverse fixing seat 43 and a transverse construction hanging basket 21;

[0069] The transverse slide plate 14 is located in the middle of the transverse mounting frame 12, and the transverse slide plate 14 is slidably connected to the transverse mounting frame 12. Specifically, a transverse guide groove 13 is provided in the middle of the transverse mounting frame 12, and both ends of the transverse slide plate 14 are located inside the transverse guide groove 13, and the transverse slide plate 14 is slidably connected to the transverse guide groove 13;

[0070] The transverse fixing seat 43 is located below the transverse slide 14. A lifting member for driving the transverse slide 14 to move up and down is provided between the transverse fixing seat 43 and the transverse slide 14. The two ends of the lifting member are respectively fixedly connected to the transverse fixing seat 43 and the transverse slide 14. The lifting member is used to drive the transverse fixing seat 43 to move up and down, thereby driving the transverse construction hanging basket 21 to move up and down, and adjusting the height of the transverse construction hanging basket 21.

[0071] The transverse construction hanging basket 21 is located below the transverse fixing seat 43, and the two sides of the transverse fixing seat 43 are provided with a first movable member for driving the transverse construction hanging basket 21 to move along the length direction of the transverse fixing seat 43. Both sides of the top of the transverse construction hanging basket 21 are fixedly connected to the first movable member, and the first movable member is used to drive the transverse construction hanging basket 21 to move along the length direction of the transverse slide 14, and adjust the position of the transverse construction hanging basket 21, so as to facilitate the subsequent construction of the cables on both sides of the main beam.

[0072] Reference Figure 5 As shown, the lifting member includes a first electric push rod 17, and the first electric push rod 17 is provided with a plurality of groups, and the plurality of groups of first electric push rods 17 are evenly distributed between the transverse slide 14 and the transverse fixing seat 43, the fixed end of the first electric push rod 17 is fixedly connected to the bottom end surface of the transverse slide 14, and the output end of the transverse slide 14 is fixedly connected to the top end surface of the transverse fixing seat 43. When it is necessary to lift the transverse construction hanging basket 21, the first electric push rod 17 is controlled to work, and the transverse fixing seat 43 can be driven to lift by the first electric push rod 17, and the transverse fixing seat 43 can drive the transverse construction hanging basket 21 to lift when lifting. It should be noted here that in actual use, a track for the movement of the transverse fixing seat 43 is provided between the transverse slide 14 and the transverse fixing seat 43, so as to increase the stability of the transverse fixing seat 43 when moving;

[0073] Reference Figure 5 As shown, the first moving member includes a first slide groove 15, a first slider 16, a first threaded rod 18 and a first driving member 19;

[0074] The first slide groove 15 is provided with two groups, and the two groups of the first slide grooves 15 are respectively opened on both sides of the transverse fixing seat 43. The first slide groove 15 is provided with a first threaded rod 18 arranged along its length. Both ends of the first threaded rod 18 are rotatably connected to the inner wall of the first slide groove 15 through bearings.

[0075] The first threaded rod 18 is provided with a first slider 16 matched with the first threaded rod 18. Specifically, the first slider 16 is provided with a first through hole penetrating the first slider 16. The first threaded rod 18 is located inside the first through hole, and the first threaded rod 18 matches the first through hole. The first slider 16 is located inside the first slide groove 15, and the first slider 16 is slidably connected with the first slide groove 15. The surface of the first slider 16 is fixed with a first connecting rod 20, and the other end of the first connecting rod 20 is fixedly connected with the top end of the horizontal construction hanging basket 21. The first connecting rod 20 is used to complete the connection between the first slider 16 and the horizontal construction hanging basket 21.

[0076] The first driving member 19 is located at one end of the transverse fixing seat 43. The first driving member 19 is used to drive the two groups of first threaded rods 18 to rotate. When the position of the transverse construction hanging basket 21 needs to be adjusted, the first driving member 19 can drive the first threaded rod 18 to rotate by controlling the first driving member 19 to work. When the first threaded rod 18 rotates, it can drive the first slider 16 to move inside the first slide groove 15. When the first slider 16 moves, it can drive the transverse construction hanging basket 21 to move through the first connecting rod 20, so as to adjust the position of the transverse construction hanging basket 21, thereby facilitating the subsequent construction of the cables on both sides of the main beam;

[0077] Reference Figure 6-Figure 7 As shown, the main tower construction assembly includes a vertical slide plate 24, a vertical fixing seat 44 and a vertical construction hanging basket 30;

[0078] The vertical slide plate 24 is located in the middle of the vertical mounting frame 22, and the vertical slide plate 24 is slidably connected to the vertical mounting frame 22. Specifically, a vertical guide groove 23 is provided in the middle of the vertical mounting frame 22, and both ends of the vertical slide plate 24 are located inside the vertical guide groove 23, and the vertical slide plate 24 is slidably connected to the vertical guide groove 23;

[0079] The vertical fixing seat 44 is located on a side of the vertical slide 24 away from the horizontal mounting frame 12. An adjusting member for adjusting the position of the vertical fixing seat 44 is provided between the vertical fixing seat 44 and the vertical slide 24. The two ends of the adjusting member are respectively fixedly connected to the vertical slide 24 and the vertical fixing seat 44. The position of the vertical fixing seat 44 can be adjusted by the adjusting member, and the vertical fixing seat 44 can be driven to move. When the vertical fixing seat 44 moves, the distance between the vertical construction hanging basket 30 and the main tower can be adjusted.

[0080] The vertical construction hanging basket 30 is located on a side of the vertical fixed seat 44 away from the vertical slide plate 24. The upper and lower ends of the vertical fixed seat 44 are provided with a second moving member for driving the vertical construction hanging basket 30 to move along the length direction of the vertical fixed seat 44. The side of the vertical construction hanging basket 30 close to the vertical fixed seat 44 is fixedly connected to the second moving member. The second moving member can be used to drive the vertical construction hanging basket 30 to move along the length direction of the vertical fixed seat 44, and the position of the vertical construction hanging basket 30 can be adjusted, so as to facilitate the subsequent construction of the cables on both sides of the main tower.

[0081] Reference Figure 7 As shown, the adjusting member includes a second electric push rod 27, and the second electric push rod 27 is provided with a plurality of groups, and the plurality of second electric push rods 27 are evenly distributed between the vertical slide 24 and the vertical fixed seat 44, and the fixed end of the second electric push rod 27 is fixedly connected to the vertical slide 24, and the output end of the second electric push rod 27 is fixedly connected to the vertical fixed seat 44. When it is necessary to adjust the distance between the vertical construction hanging basket 30 and the main tower, the second electric push rod 27 is controlled to work, and the second electric push rod 27 drives the vertical fixed seat 44 to move, and the vertical fixed seat 44 can drive the vertical construction hanging basket 30 to move, thereby adjusting the distance between the vertical construction hanging basket 30 and the main tower, and facilitating the subsequent construction of the main tower. It should be noted here that in actual use, a track for the movement of the vertical fixed seat 44 is provided between the vertical slide 24 and the vertical fixed seat 44, so as to increase the stability of the vertical fixed seat 44 during movement.

[0082] Reference Figure 7 As shown, the second moving member includes a second slide slot 25, a second slider 26 and a second driving member 45;

[0083] The second slide groove 25 is provided with two groups, and the two groups of second slide grooves 25 are distributed and opened on the upper and lower end surfaces of the vertical fixing seat 44. The second slide groove 25 is provided with a second threaded rod 28 arranged along its length inside, and both ends of the second threaded rod 28 are rotatably connected to the inner wall of the second slide groove 25 through bearings;

[0084] The second threaded rod 28 is provided with a second slider 26 matched with the second threaded rod 28. Specifically, the second slider 26 is provided with a second through hole penetrating the second slider 26. The second threaded rod 28 is located inside the second through hole, and the second threaded rod 28 matches the second through hole. The second slider 26 is located inside the second slide groove 25, and the second slider 26 is slidably connected with the second slide groove 25. A second connecting rod 29 is fixed on the surface of the second slider 26, and the other end of the second connecting rod 29 is fixedly connected to the vertical construction hanging basket 30.

[0085] The second driving member 45 is located at one end of the vertical fixing seat 44, and the second driving member 45 is used to drive the two groups of second threaded rods 28 to rotate. By controlling the operation of the second driving member 45, the second driving member 45 can drive the second threaded rods 28 to rotate. When the second threaded rods 28 rotate, they can drive the second slider 26 to move inside the second slide groove 25. When the second slider 26 moves, it can drive the vertical construction hanging basket 30 to move through the second connecting rod 29, and adjust the position of the vertical construction hanging basket 30, so as to facilitate the subsequent construction of the cables on both sides of the main tower.

[0086] Reference Figure 8 As shown, the second driving member 45 includes a driving sprocket 38, a driven sprocket 39 and a motor 41;

[0087] The driving sprocket 38 and the driven sprocket 39 are both located at one end of the vertical fixing seat 44, one end of the two sets of second threaded rods 28 are both arranged through the vertical fixing seat 44, and the ends of the two sets of second threaded rods 28 are respectively fixedly connected to the central axes of the driving sprocket 38 and the driven sprocket 39, and the surfaces of the driving sprocket 38 and the driven sprocket 39 are sleeved with chains 40 that match them;

[0088] A motor 41 for driving the driving sprocket 38 to rotate is provided on one side of the driving sprocket 38 away from the vertical fixing seat 44. The output end of the motor 41 is fixedly connected to the central axis of the driving sprocket 38. A motor seat 42 for mounting the motor 41 is provided below the motor 41. In the present application, the motor seat 42 is fixedly mounted on the surface of the vertical fixing seat 44.

[0089] The structure of the first driving member 19 is consistent with the structure of the second driving member 45. When the motor 41 is working, the motor 41 drives the driving sprocket 38 to rotate. When the driving sprocket 38 rotates, it can drive the driven sprocket 39 to rotate through the chain 40, so that the driven sprocket 39 and the driving sprocket 38 can rotate synchronously, thereby allowing the two groups of second threaded rods 28 to rotate synchronously.

[0090] Reference Figure 1-Figure 3 As shown, the synchronous drive assembly includes a third electric push rod 34, a first guide wheel 31, a second guide wheel 32 and a steel rope 33;

[0091] The third electric push rod 34 is used to drive one end of the transverse slide 14, the fixed end of the third electric push rod 34 is fixedly connected to the transverse mounting frame 12, and the output end of the third electric push rod 34 is fixedly connected to the transverse slide 14;

[0092] A first mounting seat 36 is installed on one side of the transverse mounting frame 12 close to the transverse slide plate 14, the first guide wheel 31 is located in the middle of the first mounting seat 36, and the first guide wheel 31 is rotatably connected to the first mounting seat 36;

[0093] A second mounting seat 37 is installed below the vertical mounting frame 22 on one side close to the vertical slide plate 24, the second guide wheel 32 is located inside the second mounting seat 37, and the second guide wheel 32 is rotatably connected to the second mounting seat 37;

[0094] The steel rope 33 is wound around the first guide wheel 31 and the second guide wheel 32 in sequence, one end of the steel rope 33 is fixedly connected to the vertical slide 24, and the other end of the steel rope 33 is fixedly connected to the transverse slide 14. When the transverse slide 14 moves, the vertical slide 24 can be driven to move upward through the first guide wheel 31, the second guide wheel 32 and the steel rope 33, thereby realizing the vertical construction of the main tower.

[0095] The construction method of the scaled simulation cable-stayed bridge cable main tower main beam synchronous construction device comprises the following steps:

[0096] S1. Construction equipment installation:

[0097] Before the main tower and main beam are synchronously constructed, a base 11 is built at a suitable position, a vertical mounting frame 22 is fixedly mounted on one side of the upper end of the horizontal mounting frame 12, a main beam construction assembly is mounted on the horizontal mounting frame 12, a main tower construction assembly is mounted on the vertical mounting frame 22, and a synchronous drive assembly is mounted between the horizontal mounting frame 12 and the vertical mounting frame 22, and finally the horizontal mounting frame 12 is fixedly mounted on the top of the multiple groups of bases 11;

[0098] S2. Adjustment of the position of the horizontal construction hanging basket 21:

[0099] After the installation of the horizontal construction hanging basket 21 is completed, the first electric push rod 17 is controlled to work, and the first electric push rod 17 can drive the horizontal fixing seat 43 to rise and fall, thereby driving the horizontal construction hanging basket 21 to rise and fall, and adjusting the height of the horizontal construction hanging basket 21;

[0100] By controlling the first driving member 19 to work, the first driving member 19 can drive the first threaded rod 18 to rotate. When the first threaded rod 18 rotates, it can drive the first slider 16 to move inside the first slide groove 15. When the first slider 16 moves, it can drive the horizontal construction hanging basket 21 to move through the first connecting rod 20, and adjust the position of the horizontal construction hanging basket 21, so as to facilitate the subsequent construction of the cables on both sides of the main beam;

[0101] S3. Adjustment of the position of the vertical construction hanging basket 30:

[0102] After the vertical construction hanging basket 30 is installed, the second electric push rod 27 is controlled to work, and the second electric push rod 27 can drive the vertical fixing seat 44 to move, and the vertical fixing seat 44 can adjust the distance between the vertical construction hanging basket 30 and the main tower when moving;

[0103] By controlling the second driving member 45 to work, the second driving member 45 can drive the second threaded rod 28 to rotate, and when the second threaded rod 28 rotates, it can drive the second slider 26 to move inside the second slide groove 25. When the second slider 26 moves, it can drive the vertical construction hanging basket 30 to move through the second connecting rod 29, and adjust the position of the vertical construction hanging basket 30, so as to facilitate the subsequent construction of the cables on both sides of the main tower;

[0104] S4, Synchronous construction of cables, main towers and main beams:

[0105] The construction workers are respectively located in the horizontal construction hanging basket 21 and the vertical construction hanging basket 30;

[0106] When the main beam is being constructed, the third electric push rod 34 works, and the third electric push rod 34 drives the horizontal slide 14 to move to the side away from the vertical mounting frame 22 to realize the horizontal laying construction of the main beam. At the same time, when the horizontal slide 14 moves, the vertical slide 24 can be driven to move upward through the first guide wheel 31, the second guide wheel 32 and the steel rope 33 to realize the vertical construction of the main tower. That is, when the horizontal construction basket 21 moves a certain distance, the vertical construction basket 30 rises a certain distance, that is, when the main beam is constructed for a certain length, the main tower can be constructed for a certain height. At the same time, when the main tower and the main beam are constructed, the movable horizontal construction basket 21 and the vertical construction basket 30 are used to realize the construction of the cables on both sides, thereby realizing the synchronous construction of the cables, the main tower and the main beam.

[0107] The specific working process of the present invention is as follows:

[0108] When constructing a cable-stayed bridge, the construction device needs to be constructed first. Before the main tower and main beam are synchronously constructed, the base 11 is constructed at a suitable position, the vertical mounting frame 22 is fixedly mounted on one side of the upper end of the horizontal mounting frame 12, the main beam construction assembly is mounted on the horizontal mounting frame 12, the main tower construction assembly is mounted on the vertical mounting frame 22, and the synchronous drive assembly is installed between the horizontal mounting frame 12 and the vertical mounting frame 22. Finally, the horizontal mounting frame 12 is fixedly mounted on the top of the multiple groups of bases 11, thereby completing the construction of the construction device;

[0109] Subsequently, when the cable-stayed bridge is being built, the third electric push rod 34 works, and the third electric push rod 34 drives the horizontal slide plate 14 to move to the side away from the vertical mounting frame 22, so as to realize the horizontal laying construction of the main beam. At the same time, when the horizontal slide plate 14 moves, the vertical slide plate 24 can be driven to move upwards through the first guide wheel 31, the second guide wheel 32 and the steel rope 33, so as to realize the vertical construction of the main tower, that is, when the horizontal construction hanging basket 21 moves a certain distance, the vertical construction hanging basket 30 rises a certain distance, that is, when the main beam is constructed for a certain length, the main tower can be constructed for a certain height;

[0110] At the same time, when the main tower and the main beam are under construction, the first electric push rod 17 is controlled to work, and the first electric push rod 17 can drive the horizontal fixing seat 43 to rise and fall, thereby driving the horizontal construction hanging basket 21 to rise and fall, and adjusting the height of the horizontal construction hanging basket 21; by controlling the first driving member 19 to work, the first driving member 19 can drive the first threaded rod 18 to rotate, and when the first threaded rod 18 rotates, it can drive the first slider 16 to move inside the first slide groove 15, and when the first slider 16 moves, it can drive the horizontal construction hanging basket 21 to move through the first connecting rod 20, and adjust the position of the horizontal construction hanging basket 21, so as to facilitate the subsequent construction of the cables on both sides of the main beam;

[0111] The second electric push rod 27 is controlled to work, and the second electric push rod 27 can drive the vertical fixing seat 44 to move. The vertical fixing seat 44 can adjust the distance between the vertical construction hanging basket 30 and the main tower when it moves; the second driving member 45 is controlled to work, and the second driving member 45 can drive the second threaded rod 28 to rotate. When the second threaded rod 28 rotates, it can drive the second slider 26 to move inside the second slide groove 25. When the second slider 26 moves, it can drive the vertical construction hanging basket 30 to move through the second connecting rod 29, and adjust the position of the vertical construction hanging basket 30, so as to facilitate the subsequent construction of the cables on both sides of the main tower;

[0112] The movable horizontal construction hanging basket 21 and the vertical construction hanging basket 30 are used to realize the construction of the cables on both sides, thereby realizing the synchronous construction of the cables, the main tower and the main beam;

[0113] Finally, the same method is used to complete the synchronous construction of the cables, main towers and main beams on the other side of the cable-stayed bridge. Example

[0114] In order to ensure the safety of the construction workers, a protective net is set on the outside of the horizontal construction hanging basket 21 and the vertical construction hanging basket 30, so that the horizontal construction hanging basket 21 and the vertical construction hanging basket 30 are in a fully enclosed state to ensure the safety of the construction workers. At the same time, a layer of dense mesh can be set on the outside of the protective net to prevent small objects or tools from falling from the horizontal construction hanging basket 21 or the vertical construction hanging basket 30, and a safe passage can be built on the main beam after the construction is completed for the construction workers to pass through, further increasing the protection effect of the device.

[0115] The beneficial effects of the present invention are specifically embodied in that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A scaled simulated cable-stayed bridge cable main tower main beam synchronous construction device, comprising a base (11), a transverse mounting frame (12) mounted on the upper end of the base (11), and a vertical mounting frame (22) mounted on one side of the upper end of the transverse mounting frame (12), characterized in that: It also includes a main beam construction assembly, a main tower construction assembly, and a synchronous drive assembly; The main beam construction assembly is used to construct the main beam, and the main beam construction assembly is located in the middle of the transverse mounting frame (12) and is slidably connected to the transverse mounting frame (12); The main tower construction component is used to construct the main tower, and the main tower construction component is located in the middle of the vertical mounting frame (22) and is slidably connected to the vertical mounting frame (22); The synchronous drive assembly is used to realize synchronous operation of the main beam construction assembly and the main tower construction assembly, and the synchronous drive assembly is installed on the horizontal installation frame (12) and the vertical installation frame (22); The main beam construction assembly comprises a transverse slide plate (14), a transverse fixing seat (43) and a transverse construction hanging basket (21); The transverse slide plate (14) is located in the middle of the transverse mounting frame (12), and the transverse slide plate (14) is slidably connected to the transverse mounting frame (12); The transverse fixing seat (43) is located below the transverse slide plate (14), and a lifting member for driving the transverse slide plate (14) to move up and down is provided between the transverse fixing seat (43) and the transverse slide plate (14), and two ends of the lifting member are respectively fixedly connected to the transverse fixing seat (43) and the transverse slide plate (14); The transverse construction hanging basket (21) is located below the transverse fixing seat (43), and first moving parts for driving the transverse construction hanging basket (21) to move along the length direction of the transverse fixing seat (43) are provided on both sides of the transverse fixing seat (43), and both sides of the top end of the transverse construction hanging basket (21) are fixedly connected to the first moving parts; The synchronous drive assembly comprises a third electric push rod (34), a first guide wheel (31), a second guide wheel (32) and a steel rope (33); The third electric push rod (34) is used to drive one end of the transverse slide plate (14), the fixed end of the third electric push rod (34) is fixedly connected to the transverse mounting frame (12), and the output end of the third electric push rod (34) is fixedly connected to the transverse slide plate (14); A first mounting seat (36) is mounted on a side of the transverse mounting frame (12) close to the transverse slide plate (14); the first guide wheel (31) is located in the middle of the first mounting seat (36); and the first guide wheel (31) is rotatably connected to the first mounting seat (36); A second mounting seat (37) is installed below the vertical mounting frame (22) on one side close to the vertical slide plate (24); the second guide wheel (32) is located inside the second mounting seat (37), and the second guide wheel (32) is rotatably connected to the second mounting seat (37); The steel rope (33) is sequentially wound around the first guide wheel (31) and the second guide wheel (32); one end of the steel rope (33) is fixedly connected to the vertical slide plate (24); and the other end of the steel rope (33) is fixedly connected to the horizontal slide plate (14).

2. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 1 is characterized in that: The lifting member comprises a first electric push rod (17), wherein a plurality of the first electric push rods (17) are provided, and the plurality of first electric push rods (17) are evenly distributed between the transverse slide plate (14) and the transverse fixing seat (43), wherein a fixed end of the first electric push rod (17) is fixedly connected to a bottom end surface of the transverse slide plate (14), and an output end of the transverse slide plate (14) is fixedly connected to a top end surface of the transverse fixing seat (43).

3. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 1 is characterized in that: The first moving member comprises a first sliding groove (15), a first sliding block (16), a first threaded rod (18) and a first driving member (19); The first slide groove (15) is provided with two groups, and the two groups of the first slide grooves (15) are respectively opened on both sides of the transverse fixing seat (43), and the first slide groove (15) is provided with a first threaded rod (18) arranged along its length, and both ends of the first threaded rod (18) are rotatably connected to the inner wall of the first slide groove (15) through bearings; The first threaded rod (18) is provided with a first slider (16) matched with the first threaded rod (18); the first slider (16) is located inside the first slide groove (15), and the first slider (16) is slidably connected to the first slide groove (15); a first connecting rod (20) is fixed to the surface of the first slider (16); the other end of the first connecting rod (20) is fixedly connected to the top end of the horizontal construction hanging basket (21); The first driving member (19) is located at one end of the transverse fixing seat (43), and the first driving member (19) is used to drive the two groups of first threaded rods (18) to rotate.

4. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 3 is characterized in that: The main tower construction assembly comprises a vertical slide plate (24), a vertical fixing seat (44) and a vertical construction hanging basket (30); The vertical slide plate (24) is located in the middle of the vertical mounting frame (22), and the vertical slide plate (24) is slidably connected to the vertical mounting frame (22); The vertical fixing seat (44) is located on a side of the vertical slide plate (24) away from the horizontal mounting frame (12), and an adjusting member for adjusting the position of the vertical fixing seat (44) is provided between the vertical fixing seat (44) and the vertical slide plate (24), and two ends of the adjusting member are respectively fixedly connected to the vertical slide plate (24) and the vertical fixing seat (44); The vertical construction hanging basket (30) is located on a side of the vertical fixing seat (44) away from the vertical slide plate (24), and the upper and lower ends of the vertical fixing seat (44) are provided with a second moving member for driving the vertical construction hanging basket (30) to move along the length direction of the vertical fixing seat (44), and the side of the vertical construction hanging basket (30) close to the vertical fixing seat (44) is fixedly connected to the second moving member.

5. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 4 is characterized in that: The adjusting member comprises a second electric push rod (27), wherein the second electric push rod (27) is provided in a plurality of groups, and the plurality of groups of second electric push rods (27) are evenly distributed between the vertical slide plate (24) and the vertical fixing seat (44), wherein the fixed end of the second electric push rod (27) is fixedly connected to the vertical slide plate (24), and the output end of the second electric push rod (27) is fixedly connected to the vertical fixing seat (44).

6. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 4 is characterized in that: The second moving member comprises a second sliding groove (25), a second sliding block (26) and a second driving member (45); The second slide groove (25) is provided with two groups, and the two groups of second slide grooves (25) are distributed and opened on the upper and lower end surfaces of the vertical fixing seat (44); the second slide groove (25) is provided with a second threaded rod (28) arranged along its length inside, and both ends of the second threaded rod (28) are rotatably connected to the inner wall of the second slide groove (25) through bearings; The second threaded rod (28) is provided with a second slider (26) matched with the second threaded rod (28); the second slider (26) is located inside the second slide groove (25); the second slider (26) is slidably connected to the second slide groove (25); a second connecting rod (29) is fixed to the surface of the second slider (26); the other end of the second connecting rod (29) is fixedly connected to the vertical construction hanging basket (30); The second driving member (45) is located at one end of the vertical fixing seat (44), and the second driving member (45) is used to drive the two groups of second threaded rods (28) to rotate.

7. The synchronous construction device for the main tower and main beam of a scaled simulated cable-stayed bridge according to claim 6 is characterized in that: The second driving member (45) comprises a driving sprocket (38), a driven sprocket (39) and a motor (41); The driving sprocket (38) and the driven sprocket (39) are both located at one end of the vertical fixing seat (44), one end of the two sets of the second threaded rods (28) are both arranged through the vertical fixing seat (44), and the ends of the two sets of the second threaded rods (28) are respectively fixedly connected to the central axes of the driving sprocket (38) and the driven sprocket (39), and the surfaces of the driving sprocket (38) and the driven sprocket (39) are sleeved with chains (40) matching therewith; A motor (41) for driving the driving sprocket (38) to rotate is provided on one side of the driving sprocket (38) away from the vertical fixing seat (44); an output end of the motor (41) is fixedly connected to the central axis of the driving sprocket (38); and a motor seat (42) for mounting the motor (41) is provided below the motor (41); The structure of the first driving member (19) is consistent with the structure of the second driving member (45).

8. A construction method for a scaled simulation cable-stayed bridge cable main tower and main beam synchronous construction device, comprising the following steps: S1. Construction equipment installation: Before the main tower and main beam are synchronously constructed, a base (11) is built at a suitable position, a vertical mounting frame (22) is fixedly mounted on one side of the upper end of the transverse mounting frame (12), a main beam construction component is mounted on the transverse mounting frame (12), a main tower construction component is mounted on the vertical mounting frame (22), and a synchronous drive component is mounted between the transverse mounting frame (12) and the vertical mounting frame (22), and finally the transverse mounting frame (12) is fixedly mounted on the top of the plurality of bases (11); S2. Adjustment of the position of the horizontal construction hanging basket (21): After the installation of the horizontal construction hanging basket (21) is completed, the first electric push rod (17) is controlled to work, and the first electric push rod (17) can drive the horizontal fixing seat (43) to rise and fall, thereby driving the horizontal construction hanging basket (21) to rise and fall, and adjusting the height of the horizontal construction hanging basket (21); By controlling the first driving member (19) to work, the first driving member (19) can drive the first threaded rod (18) to rotate. When the first threaded rod (18) rotates, it can drive the first slider (16) to move inside the first slide groove (15). When the first slider (16) moves, it can drive the transverse construction hanging basket (21) to move through the first connecting rod (20), so as to adjust the position of the transverse construction hanging basket (21), thereby facilitating the subsequent construction of the cables on both sides of the main beam; S3. Adjustment of the position of the vertical construction hanging basket (30): After the vertical construction hanging basket (30) is installed, the second electric push rod (27) is controlled to work, and the second electric push rod (27) can drive the vertical fixing seat (44) to move, and the vertical fixing seat (44) can adjust the distance between the vertical construction hanging basket (30) and the main tower when moving; By controlling the second driving member (45) to work, the second driving member (45) can drive the second threaded rod (28) to rotate. When the second threaded rod (28) rotates, it can drive the second slider (26) to move inside the second slide groove (25). When the second slider (26) moves, it can drive the vertical construction hanging basket (30) to move through the second connecting rod (29), thereby adjusting the position of the vertical construction hanging basket (30), thereby facilitating the subsequent construction of the cables on both sides of the main tower; S4, Synchronous construction of cables, main towers and main beams: When the main beam is being constructed, the third electric push rod (34) works and drives the transverse slide plate (14) to move to a side away from the vertical mounting frame (22) to achieve transverse laying of the main beam. At the same time, when the transverse slide plate (14) moves, the vertical slide plate (24) can be driven to move upwards by the first guide wheel (31), the second guide wheel (32) and the steel rope (33) to achieve vertical construction of the main tower. That is, when the transverse construction hanging basket (21) moves a certain distance, the vertical construction hanging basket (30) rises a certain distance. That is, when the main beam is constructed for a certain length, the main tower can be constructed for a certain height. At the same time, when the main tower and the main beam are being constructed, the movable transverse construction hanging basket (21) and the vertical construction hanging basket (30) are used to realize the construction of the cables on both sides, thereby realizing the synchronous construction of the cables, the main tower and the main beam on one side of the cable-stayed bridge. Finally, the synchronous construction of the cables, the main tower and the main beam on the other side of the cable-stayed bridge is completed in the same way.