A flower basket system and installation process for a construction platform module of a protective enclosure system
By designing diversified flower basket systems in the frame system of the enclosure system construction platform and adjusting the geometry and prestressed state of the frame, the problems of insufficient stability and torsional stiffness of the frame system in the existing technology are solved, and a higher level of performance is achieved. Structural strength and installation efficiency.
Patent Information
- Application Number
- CN202211542220.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-03
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2042-12-03
AI Technical Summary
The frame system of the existing enclosure system construction platform cannot meet the diverse structural requirements due to the single specifications of the flower basket, resulting in insufficient stability and torsional stiffness of the frame system.
A flower basket system for the construction platform module of the enclosure system is designed, including horizontal flower baskets, cross-section vertical flower baskets and longitudinal section vertical flower baskets. By installing matching flower baskets at different positions of the frame system, the horizontality and verticality of the frame can be adjusted and the opposite angle, which improves the anti-lateral stiffness and stability of the frame, and improves the overall stiffness of the frame through the prestressed function.
By adjusting the position and torque of the flower basket, the plane torsional stiffness and lateral movement stiffness of the frame system are improved, the cantilevering capability is enhanced, the operation requirements of mechanized equipment are met, and the convenience and efficiency of installation are improved.
Smart Images

Figure CN115839162B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of enclosure system construction equipment, and in particular to a basket system and installation process of an enclosure system construction platform module. Background Art
[0002] Liquefied natural gas carriers are ships used to transport liquefied natural gas, also known as "LNG carriers". LNG carriers are difficult to manufacture and have high requirements for the internal environment and construction. When building LNG carriers, a containment system needs to be installed inside the cargo hold. The installation of a containment system inside the cabin of an LNG carrier requires mechanized equipment, and a frame-type construction platform is usually set up in the cabin to provide an operating platform for construction.
[0003] Reference Figure 1 and Figure 2 There is a frame system for installing a flower basket. The frame system mainly includes columns 01, frame nodes 02, transverse trusses 03 and longitudinal frames 04. Columns 01 are vertically arranged inside the cabin. Columns 01 are arranged in a rectangular array in the cabin in several groups, and each group is stacked in the vertical direction. A frame node 02 is provided between two adjacent columns 01 in the vertical direction. The frame node 02 is provided with several buckle plates 05 and several groups of ear plates 06 with connection holes, and each group of ear plates 06 is provided with two pieces. The transverse truss 03 is fixedly connected between two frame nodes 02 arranged along the width direction of the hull, and the longitudinal frame 04 is detachably connected between two frame nodes 02 arranged along the length direction of the hull. Since the two sides of the bottom of the cabin close to the side of the ship are large slopes, a cantilever is connected to the transverse truss 03 close to the left and right sides of the ship.
[0004] In the process of implementing the present application, the inventors discovered that there are at least the following problems in the technology: in order to make the above-mentioned frame system structure more stable, it is necessary to match the flower baskets adapted to the load at different positions of the frame system, but the existing flower baskets have a single specification and cannot meet the diversity requirements of the above-mentioned frame system. Summary of the invention
[0005] In order to install matching flower baskets at different positions of a frame system, the present application provides a flower basket system and an installation process for a construction platform module of an enclosure system.
[0006] In the first aspect, the flower basket system of the enclosure system construction platform module provided by the present application adopts the following technical solution:
[0007] A flower basket system of a construction platform module of an enclosure system includes a horizontal flower basket, wherein two horizontal flower baskets are cross-arranged inside a grid surrounded by two transverse trusses and two longitudinal frames, and two ends of the horizontal flower basket are connected to two diagonal frame nodes, and both ends of the horizontal flower basket are provided with a connecting assembly, and the connecting assembly is used to connect a buckle plate on the frame node;
[0008] A cross-sectional vertical flower basket, wherein the cross-sectional vertical flower basket is arranged between two adjacent transverse trusses in the vertical direction, and the two ends of the cross-sectional vertical flower basket are connected to two diagonal frame nodes, and the cross-sectional vertical flower basket;
[0009] The longitudinal section vertical flower baskets are arranged in two groups in parallel between two adjacent longitudinal frames, each group of the longitudinal section vertical flower baskets has two longitudinal section vertical flower baskets, and the two longitudinal section vertical flower baskets in the same group are arranged crosswise, and the two ends of the longitudinal section vertical flower baskets are connected to the longitudinal frames.
[0010] By adopting the above technical solution, horizontal flower baskets are cross-arranged inside the square formed by two transverse trusses and two longitudinal frames. The horizontal flower baskets adjust the horizontality and diagonal verticality of the two transverse trusses and two longitudinal frames, so that the square formed by the two transverse trusses and two longitudinal frames forms a standard rectangle, thereby improving the plane torsional rigidity of the frame system. The vertical flower baskets in the cross section and the vertical flower baskets in the longitudinal section adjust the verticality and diagonal verticality of the columns, thereby improving the lateral rigidity and stability of the frame system and improving the cantilever capacity.
[0011] By setting matching flower baskets at different positions, the entire flower basket system also has a prestressed function. The prestress is applied to the frame system through the flower basket system to improve the frame rigidity and deformation resistance, and ultimately the entire frame system meets the operating requirements of mechanized equipment.
[0012] In addition, the horizontal flower basket is directly buckled on the frame node through the connecting assembly, which is convenient to install and has high installation efficiency. The cross-section vertical flower basket is installed on the frame node, which has a more direct force transmission and acts directly on the frame node. The frame node is strong and can withstand stronger tension. The installation node of the longitudinal section vertical flower basket is directly set on the longitudinal frame, which reduces the difficulty of product processing and installation and improves installation efficiency.
[0013] Optionally, the horizontal flower basket includes a first flower basket nut frame, a flower basket pull rod threadedly connected to both ends of the first flower basket nut frame in the length direction, and a connecting plate arranged at the end of the flower basket pull rod away from the first flower basket nut frame. The two flower basket pull rods are coaxially arranged, and when the first flower basket nut frame rotates, the two flower basket pull rods move relative to each other.
[0014] By adopting the above technical solution, a connecting plate is connected to the flower basket pull rod, the connecting plate is connected to the connecting assembly, and the tightening and loosening of the horizontal flower basket is achieved by rotating the first flower basket nut frame.
[0015] Optionally, the connection assembly includes a connection substrate, a snap joint arranged on the connection substrate, and a pin passing through the snap joint, and the snap joint is used to snap onto a snap plate of a frame node.
[0016] By adopting the above technical solution, a connecting component is added to the connecting plate, which is buckled with the buckle plate on the frame node through a buckle joint, and the buckle joint is positioned using a pin, thereby improving the convenience of installation.
[0017] Optionally, the cross-sectional vertical flower basket includes a second flower basket nut frame, a connecting rod threadedly connected to one end of the second flower basket nut frame, and a bidirectional flower basket pull rod connected to the other end of the second flower basket nut frame; a connecting piece is provided at the top end of the cross-sectional vertical flower basket, and the connecting piece is used to be plugged between two ear plates; a connecting head is provided at the bottom end of the cross-sectional vertical flower basket, and the connecting head is sleeved on the outside of the two ear plates.
[0018] By adopting the above technical solution, a connecting piece is inserted between the two ear plates and connected to the two ear plates, and a connecting head is sleeved on the outside of the two ear plates and connected to the two ear plates, thereby improving the connection strength of the two ends of the cross-sectional vertical flower basket and making the cross-sectional vertical flower basket have a stronger carrying capacity.
[0019] Optionally, the connecting head includes two parallel clamping parts and a connecting part connecting two clamping plates, the two clamping parts are used to clamp the ear plates, and the bidirectional basket pull rod is passed through the connecting part at one end close to the connecting head and is threadedly connected to the connecting part.
[0020] By adopting the above technical solution, two clamping plates are used to clamp the two ear plates, and then the connector and the ear plate are connected together, so that the connection between the connector and the ear plate is more reliable. At the same time, the two-way basket pull rod is threadedly connected to the connecting part, which is convenient for removing the connector and replacing other connectors.
[0021] Optionally, a reinforcement sheet is arranged in parallel on the connecting portion.
[0022] By adopting the above technical solution, the strength of the connecting part is strengthened by using the reinforcing sheet, thereby reducing the possibility of deformation of the connecting part after being subjected to tension.
[0023] Optionally, the connecting head includes a threaded sleeve and a connecting ear plate connected to the threaded sleeve, and the threaded sleeve is threadedly connected to the bottom end of the cross-sectional vertical flower basket.
[0024] By adopting the above technical solution, the threaded sleeve is used to facilitate the disassembly and replacement of the connector, and the connector with the connecting ear plate is replaced, so that the application scenarios of the connector are more extensive, thereby meeting different usage scenarios.
[0025] On the other hand, the present application also provides a basket system installation process for a construction platform module of an enclosure system, which adopts the following technical solution:
[0026] A basket system installation process for a construction platform module of an enclosure system comprises the following steps:
[0027] S1. After the first layer of the frame system is overlapped, install the horizontal flower basket on the first layer. First, ensure that the two crossed horizontal flower baskets are of equal length. Use the connection components to buckle with the buckle plates on the frame nodes, and then tighten the horizontal flower baskets. The tightening torque of the horizontal flower baskets is 5N•m.
[0028] S2. After lap-joining the next layer of frames, install the cross-section vertical basket between two adjacent transverse trusses in the vertical direction, connect the two ends of the cross-section vertical basket to the frame nodes through bolts and nuts, and then tighten the cross-section vertical basket. The tightening torque of the cross-section vertical basket is 30N•m.
[0029] S3. Install the longitudinal vertical flower basket between two adjacent longitudinal frames. First, ensure that the two crossed longitudinal vertical flower baskets are of equal length. Connect the two ends of the longitudinal vertical flower basket to the longitudinal frame with bolts and nuts, and then tighten the longitudinal vertical flower basket. The tightening torque of the longitudinal vertical flower basket is 15N•m.
[0030] By adopting the above technical solution, during the process of building the frame system, the flower basket system is installed step by step, and the torque of the flower basket system is adjusted according to the stress conditions, so that the flower basket system is used to improve the structural strength of the frame system and improve the convenience of installation.
[0031] Optionally, in step S2, when installing the cross-section vertical flower basket at the large cantilever position of the cross section, the lower end of the cross-section vertical flower basket is connected to the frame node at the cantilever, and the cross-section vertical flower basket is adjusted so that the frame node at the cantilever is 3-5mm higher than the design elevation.
[0032] By adopting the above technical solution, a cross-sectional vertical flower basket is installed at the position of the large cross-sectional cantilever, and the cross-sectional vertical flower basket is directly used to pull the frame node up to 3-5mm higher than the design elevation, so that the cantilever reaches the design elevation after being loaded, thereby ensuring the stability of the frame system structure.
[0033] In summary, the present application includes at least one of the following beneficial technical effects:
[0034] 1. Horizontal flower baskets are cross-set inside the square formed by two transverse trusses and two longitudinal frames. The horizontal flower baskets adjust the horizontality and diagonal verticality of the two transverse trusses and two longitudinal frames, so that the square formed by the two transverse trusses and two longitudinal frames forms a standard rectangle, thereby improving the plane torsional rigidity of the frame system. The vertical flower baskets in the cross section and the vertical flower baskets in the longitudinal section adjust the verticality and diagonal verticality of the columns, thereby improving the lateral rigidity and stability of the frame system and the cantilever capacity. By setting matching flower baskets at different positions, the entire flower basket system also has a prestressed function. The flower basket system applies prestress to the frame system, thereby improving the frame rigidity and anti-deformation ability, and ultimately making the entire frame system meet the operating requirements of mechanized equipment.
[0035] 2. Add a connection component to the connection plate, connect it to the buckle plate on the frame node through the buckle joint, and use the latch to position the buckle joint to improve the convenience of installation;
[0036] 3. In the process of building the frame system, the flower basket system is installed step by step, and the torque of the flower basket system is adjusted according to the stress conditions, so as to use the flower basket system to improve the structural strength of the frame system and improve the convenience of installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 It is a front view of the existing frame system.
[0038] Figure 2 It is a side view of the existing frame system.
[0039] Figure 3 It is a schematic diagram of the overall structure of Example 1 of the present application.
[0040] Figure 4 It is a schematic diagram of the horizontal flower basket structure in Example 1 of the present application.
[0041] Figure 5 It is a schematic diagram of the connection component structure in Example 1 of the present application.
[0042] Figure 6 It is a schematic diagram of the cross-sectional vertical flower basket structure in Example 1 of the present application.
[0043] Figure 7 It is a schematic diagram of the connector structure in Example 1 of the present application.
[0044] Figure 8 It is a schematic diagram of the vertical flower basket structure in longitudinal section in Example 1 of the present application.
[0045] Fig. 9 It is a schematic diagram of the connector structure in Example 2 of the present application.
[0046] Description of reference numerals:
[0047] 01. Column; 02. Frame node; 03. Horizontal truss; 04. Longitudinal frame; 05. Buckle plate; 06. Ear plate; 1. Horizontal flower basket; 11. First flower basket nut frame; 12. Flower basket pull rod; 13. Connecting plate; 14. Connecting assembly; 141. Connecting base plate; 142. Buckle joint; 143. Pin; 2. Vertical flower basket in cross section; 21. Second flower basket nut frame; 22. Connecting rod; 23. Bidirectional flower basket pull rod; 24. Connecting plate; 25. Connecting head; 251. Clamping part; 252. Connecting part; 253. Reinforcing plate; 3. Vertical flower basket in longitudinal section; 41. Threaded sleeve; 42. Connecting ear plate. DETAILED DESCRIPTION
[0048] The following is combined with Figure 3-9 This application is described in further detail.
[0049] The embodiment of the present application discloses a basket system of a construction platform module of an enclosure system.
[0050] Example 1
[0051] Reference Figure 3 A basket system of a construction platform module of an enclosure system includes a horizontal basket 1, a cross-section vertical basket 2 and a longitudinal vertical basket 3. Two horizontal baskets 1 are cross-arranged inside a square surrounded by two transverse trusses 03 and two longitudinal frames 04. The horizontal baskets 1 are arranged along the diagonal of the square, and the two ends of the horizontal baskets 1 are connected to the frame node 02. The cross-section vertical basket 2 is arranged inside a square surrounded by two transverse trusses 03 and two columns 01. The cross-section vertical basket 2 is arranged along the diagonal of the square, and the two ends of the cross-section vertical basket 2 are connected to the frame node 02. Two groups of longitudinal vertical baskets 3 are arranged in parallel between two adjacent longitudinal frames 04. The number of the two longitudinal vertical baskets 3 in each group is two, and the two longitudinal vertical baskets 3 in the same group are cross-arranged.
[0052] Reference Figure 3 The horizontal flower basket 1, the cross-section vertical flower basket 2 and the longitudinal section vertical flower basket 3 are used to form a flower basket system and are distributed according to the requirements of the frame system. The horizontal flower basket 1 adjusts the horizontality and diagonal verticality of the two transverse trusses 03 and the two longitudinal frames 04, and the cross-section vertical flower basket 2 and the longitudinal section vertical flower basket 3 adjust the verticality and diagonal verticality of the column 01, thereby improving the frame stiffness and anti-deformation ability, and finally making the entire frame system meet the operating requirements of mechanized equipment.
[0053] Reference Figure 4 and Figure 5The horizontal flower basket 1 includes a first flower basket nut frame 11, a flower basket tie rod 12 and a connecting plate 13. The flower basket tie rod 12 is threadedly connected to one end at both ends of the first flower basket nut frame 11 in the length direction. The two flower basket tie rods 12 are coaxially arranged, and the ends of the two flower basket tie rods 12 close to each other are provided with external threads. The threads of the two flower basket tie rods 12 are rotated in opposite directions. A connecting plate 13 is welded to one end of each flower basket tie rod 12 away from the first flower basket nut frame 11, and each connecting plate 13 is provided with a through hole. When the first flower basket nut frame 11 rotates, the two flower basket tie rods 12 move relative to each other.
[0054] Reference Figure 4 and Figure 5 A connection assembly 14 is provided on each connection plate 13. Each connection assembly 14 includes a connection base plate 141, a buckle joint 142 and a latch 143. The connection base plate 141 is an L-shaped plate. Each connection base plate 141 has a through hole. The connection base plate 141 is connected to the connection plate 13 by bolts and nuts. The buckle joint 142 is welded on the connection base plate 141. The buckle joint 142 is the buckle joint 142 used in the existing disc buckle scaffolding. The buckle joint 142 is buckled on the buckle plate 05 of the frame node 02. The latch 143 passes through the buckle joint 142 and the buckle plate 05 to position the buckle joint 142.
[0055] Reference Figure 4 The two cross-arranged horizontal flower baskets 1 make the squares formed by the two transverse trusses 03 and the two longitudinal frames 04 form a standard rectangle, thereby improving the plane torsional rigidity of the frame system.
[0056] Reference Figure 6 , two groups of cross-sectional vertical flower baskets 2 can be arranged inside the square surrounded by the transverse trusses 03 and the columns 01, and the number of the two cross-sectional vertical flower baskets 2 in each group is two, and the two cross-sectional vertical flower baskets 2 in the same group are arranged crosswise. When the cross-sectional vertical flower baskets 2 are arranged inside the square at the cantilever, two cross-sectional vertical flower baskets 2 are arranged in parallel in the square, and the bottom ends of the cross-sectional vertical flower baskets 2 are connected to the frame node 02 at the cantilever, so that the frame node 02 at the cantilever only bears upward tension.
[0057] Reference Figure 5 and Figure 7 The cross-sectional vertical flower basket 2 includes a second flower basket nut frame 21, a connecting rod 22 and a bidirectional flower basket tie rod 23. The connecting rod 22 and the bidirectional flower basket tie rod 23 are coaxially arranged. The ends of the connecting rod 22 and the bidirectional flower basket tie rod 23 that are close to each other are both provided with external threads. The ends of the connecting rod 22 and the bidirectional flower basket tie rod 23 that are close to each other are both threadedly connected with the second flower basket nut frame 21. The diameters of the connecting rod 22 and the bidirectional flower basket tie rod 23 are larger than the flower basket tie rod 12 to ensure the working stability of the cross-sectional vertical flower basket 2 and save the cost of the flower basket system in places with small forces.
[0058] Reference Figure 6 and Figure 7 , a connecting piece 24 is welded to one end of the connecting rod 22 away from the second flower basket nut frame 21. A connecting head 25 is connected to one end of the bidirectional flower basket pull rod 23 away from the second flower basket nut frame 21. The connecting head 25 includes a clamping portion 251 and a connecting portion 252 formed in one piece. Two clamping portions 251 are arranged in parallel. Each clamping portion 251 has a through hole. The connecting portion 252 connects the two clamping portions 251. The clamping portion 251 and the connecting portion 252 are perpendicular. A reinforcing piece 253 is welded to the connecting portion 252. An external thread is arranged at one end of the bidirectional flower basket pull rod 23 close to the connecting head 25. The end of the bidirectional flower basket pull rod 23 close to the connecting head 25 is threadedly connected to the connecting portion 252.
[0059] Reference Figure 6 and Figure 7 When installing the cross-section vertical flower basket 2, the connecting piece 24 is placed higher than the connecting head 25, the connecting piece 24 is inserted between the two ear plates 06, and fixed by bolts and nuts, the connecting head 25 is sleeved outside the two ear plates 06, and the two clamping parts 251 clamp the ear plates 06 and fix them by bolts and nuts. Thus, the cross-section vertical flower basket 2 is stably installed.
[0060] Reference Figure 3 , Figure 7 and Figure 8 The structure of the vertical flower basket 3 in the longitudinal section is consistent with the horizontal flower basket 1, but the vertical flower basket 3 in the longitudinal section is subjected to less force. The two ends of the longitudinal frame 04 are directly connected to the longitudinal frame 04 through bolts and nuts, and the diameter of the flower basket tie rod used in the vertical flower basket 3 in the longitudinal section is smaller than the diameter of the connecting rod 22 and the two-way flower basket tie rod 23, which can reduce production costs and product weight. If the connection node of the vertical flower basket 3 in the longitudinal section and the frame system is set on the frame node 02, the connection node needs to be set perpendicular to the frame node 02, which is difficult to produce and easy to be damaged during use. After the two ends of the vertical flower basket 2 in the cross section are connected to the frame node 02, the processing difficulty and installation difficulty are reduced, and the installation efficiency is improved.
[0061] The implementation principle of the basket system of the enclosure system construction platform module in the embodiment of the present application is as follows: the horizontal baskets 1 are cross-arranged inside the square formed by two transverse trusses 03 and two longitudinal frames 04. The two horizontal baskets 1 make the square formed by the two transverse trusses 03 and the two longitudinal frames 04 form a standard rectangle, which improves the plane torsional rigidity of the frame system. The horizontal basket 1 is directly buckled on the frame node 02 through the connecting assembly 14, which is convenient to install and has high installation efficiency. The cross-section vertical basket 2 is installed on the frame node 02, and the node strength is large. The longitudinal vertical basket 3 is installed on the longitudinal frame 04, and the installation efficiency is high. The cross-section vertical basket 2 and the longitudinal vertical basket 3 adjust the verticality and diagonal verticality of the column 01, improve the lateral rigidity and stability of the frame system, and improve the cantilever capacity.
[0062] By setting matching flower baskets at different positions and applying prestress to the frame system through the flower basket system, the frame stiffness and deformation resistance are improved, and ultimately the entire frame system meets the operating requirements of mechanized equipment.
[0063] The embodiment of the present application also discloses a basket system installation process for the enclosure system construction platform module.
[0064] A basket system installation process for a construction platform module of an enclosure system comprises the following steps:
[0065] S1. After the first layer of the frame system is overlapped, install the horizontal flower basket 1 on the first layer. First, ensure that the two crossed horizontal flower baskets 1 are of equal length. Use the connection assembly 14 to buckle with the buckle plate 05 on the frame node 02, and then tighten the horizontal flower basket 1. The tightening torque of the horizontal flower basket 1 is 5N•m.
[0066] S2. After lap-joining the next layer of frames, install the cross-section vertical flower basket 2 between two adjacent transverse trusses 03 in the vertical direction, connect the two ends of the cross-section vertical flower basket 2 to the frame node 02 through bolts and nuts, and then tighten the cross-section vertical flower basket 2. The tightening torque of the cross-section vertical flower basket 2 is 30N•m; when installing the cross-section vertical flower basket 2 at the cross-section large cantilever position, the lower end of the cross-section vertical flower basket 2 is connected to the frame node 02 at the cantilever position, and adjust the cross-section vertical flower basket 2 so that the frame node 02 at the cantilever position is 3-5mm higher than the design elevation;
[0067] S3. Install the longitudinal vertical flower basket 3 between two adjacent longitudinal frames 04. First, ensure that the two crossed longitudinal vertical flower baskets 3 are of equal length. Connect the two ends of the longitudinal vertical flower basket 3 to the longitudinal frame 04 through bolts and nuts, and then tighten the longitudinal vertical flower basket 3. The tightening torque of the longitudinal vertical flower basket 3 is 15N•m.
[0068] The implementation principle of the basket system installation process of the enclosure system construction platform module in the embodiment of the present application is: during the construction of the frame system, the basket system is installed step by step in order, and the torque of the basket system is adjusted according to the force conditions, so as to facilitate installation and improve the structural strength of the frame system by using the basket system. The vertical basket 2 of the cross section at the large cantilever position of the cross section pulls up the frame node 02 3-5mm higher than the design elevation, so that the cantilever reaches the design elevation after being loaded.
[0069] Embodiment 2, this embodiment is different from embodiment 1 in that, referring to Fig. 9 The connector 25 includes a threaded sleeve 41 and a connecting ear plate 42 welded together. The threaded sleeve 41 is threadedly connected to the bidirectional basket rod 23 . The connecting ear plate 42 is located at one end of the threaded sleeve 41 away from the bidirectional basket rod 23 .
[0070] The implementation principle of Example 2 is: different connectors 25 are connected by threads, so that the connectors 25 can be easily replaced to meet different installation conditions.
[0071] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A basket system for a construction platform module of an enclosure system, characterized in that: It comprises a horizontal flower basket (1), wherein two horizontal flower baskets (1) are cross-arranged inside a square formed by two transverse trusses (03) and two longitudinal frames (04), wherein two ends of the horizontal flower basket (1) are connected to two diagonal frame nodes (02), and both ends of the horizontal flower basket (1) are provided with a connecting assembly (14), and the connecting assembly (14) is used to connect a buckle plate (05) on the frame node (02); A cross-sectional vertical flower basket (2), the cross-sectional vertical flower basket (2) being arranged between two adjacent transverse trusses (03) in the vertical direction, the two ends of the cross-sectional vertical flower basket (2) being connected to two diagonal frame nodes (02), the cross-sectional vertical flower basket (2); A vertical flower basket (3) in longitudinal section, wherein two groups of the vertical flower baskets (3) in longitudinal section are arranged in parallel between two adjacent longitudinal frames (04), the number of the vertical flower baskets (3) in each group is two, the two vertical flower baskets (3) in longitudinal section in the same group are arranged crosswise, and the two ends of the vertical flower baskets (3) in longitudinal section are connected to the longitudinal frames (04); the horizontal flower basket (1) comprises a first flower basket nut frame (11), a flower basket pull rod (12) threadedly connected to both ends of the first flower basket nut frame (11) in the length direction, and a connecting plate (13) arranged at the end of the flower basket pull rod (12) away from the first flower basket nut frame (11), the two flower basket pull rods (12) are coaxially arranged, and when the first flower basket nut frame (11) rotates, the two flower basket pull rods (12) move relative to each other; the connecting assembly (14) comprises a first flower basket nut frame (11), a flower basket pull rod (12) threadedly connected to both ends of the first flower basket nut frame (11) in the length direction, and a connecting plate (13) arranged at the end of the flower basket pull rod (12) away from the first flower basket nut frame (11), the two flower basket pull rods (12) are coaxially arranged, and when the first flower basket nut frame (11) rotates, the two flower basket pull rods (12) move relative to each other; the connecting assembly (14) comprises The invention comprises a connecting base plate (141), a buckle joint (142) arranged on the connecting base plate (141) and a latch (143) passing through the buckle joint (142), wherein the buckle joint (142) is used for buckling on a buckle plate (05) of a frame node (02); the cross-sectional vertical flower basket (2) comprises a second flower basket nut frame (21), a connecting rod (22) threadedly connected to one end of the second flower basket nut frame (21) and a bidirectional flower basket pull rod (23) connected to the other end of the second flower basket nut frame (21); a connecting piece (24) is arranged at the top end of the cross-sectional vertical flower basket (2), wherein the connecting piece (24) is used for plugging between two ear plates (06); a connecting head (25) is connected to the bottom end of the cross-sectional vertical flower basket (2), wherein the connecting head (25) is sleeved on the outside of the two ear plates (06).
2. The basket system of the enclosure system construction platform module according to claim 1, characterized in that: The connecting head (25) comprises two clamping parts (251) arranged in parallel and a connecting part (252) connecting two clamping plates, the two clamping parts (251) are used to clamp the ear plate (06), and the connecting part (252) is passed through one end of the bidirectional basket pull rod (23) close to the connecting head (25) and is threadedly connected to the connecting part (252).
3. The basket system of the enclosure system construction platform module according to claim 2, characterized in that: A reinforcing sheet (253) is arranged in parallel on the connecting portion (252).
4. The basket system of the enclosure system construction platform module according to claim 3 is characterized by: The connecting head (25) comprises a threaded sleeve (41) and a connecting ear plate (42) connected to the threaded sleeve (41), and the threaded sleeve (41) is threadedly connected to the bottom end of the cross-sectional vertical basket (2).
5. A basket system installation process for a construction platform module of an enclosure system, characterized in that: The following steps are involved: S1. After the first layer of the frame system is overlapped, install the horizontal flower basket (1) on the first layer. First, ensure that the two crossed horizontal flower baskets (1) are of equal length. Use the connection assembly (14) to buckle the buckle plate (05) on the frame node (02), and then tighten the horizontal flower basket (1). The tightening torque of the horizontal flower basket (1) is 5N•m. S2. After the next layer of frames is overlapped, a cross-sectional vertical flower basket (2) is installed between two adjacent transverse trusses (03) in the vertical direction, and both ends of the cross-sectional vertical flower basket (2) are connected to the frame node (02) by bolts and nuts, and then the cross-sectional vertical flower basket (2) is tightened, and the tightening torque of the cross-sectional vertical flower basket (2) is 30N•m; S3. Install the longitudinal vertical flower basket (3) between two adjacent longitudinal frames (04). First, ensure that the two crossed longitudinal vertical flower baskets (3) are of equal length. Connect the two ends of the longitudinal vertical flower basket (3) to the longitudinal frame (04) through bolts and nuts. Then tighten the longitudinal vertical flower basket (3). The tightening torque of the longitudinal vertical flower basket (3) is 15 N·m.
6. The basket system installation process of the enclosure system construction platform module according to claim 5 is characterized by: In step S2, when the cross-section vertical flower basket (2) is installed at the cross-section large cantilever position, the lower end of the cross-section vertical flower basket (2) is connected to the cantilever frame node (02), and the cross-section vertical flower basket (2) is adjusted so that the cantilever frame node (02) is 3-5 mm higher than the design elevation.
Citation Information
Patent Citations
Telescopic ring-lock type steel pipe support system and construction method
CN110130633A
Construction platform of enclosure system
CN115817758A
Shock absorption type pipeline lifting device
CN203392714U
Structural frame and connection structure of lapping position of beam column frame
CN203769062U