BIM-based assembly type c-type stockyard construction method

By using a BIM-based prefabricated construction method, the C-shaped material yard unloading platform is divided into modular beam and slab modules, and prefabricated support slabs are assembled on site. This solves the problems of long construction period and high-altitude operations in existing technologies, and achieves shorter construction period and lower cost.

CN115874813BActive Publication Date: 2026-01-02CHINA MCC20 GRP CORP LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202211498032.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-28
Publication Date
2026-01-02
Estimated Expiration
2042-11-28

AI Technical Summary

Technical Problem

The existing C-type material yard has a long construction period, involves a lot of high-altitude work, and poses significant safety hazards. In particular, the construction of the upper unloading cantilever platform has problems such as large material consumption and long construction period.

Method used

The prefabricated construction method based on BIM is adopted, which divides the unloading platform into multiple concrete beam and slab modules. The prefabricated support slabs are manufactured in the factory and assembled on site. Modular construction is carried out using BIM technology, avoiding the erection of scaffolding and allowing direct pouring on the support slabs.

Benefits of technology

Shorten the construction period, reduce high-altitude operations, lower costs, improve construction efficiency, avoid complex scaffolding erection and dismantling processes, and ensure construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115874813B_ABST
    Figure CN115874813B_ABST
Patent Text Reader

Abstract

The present application relates to a kind of based on BIM assembly type C yard construction method, comprising: a. using BIM technology, the unloading platform of upper part of yard is divided into multiple concrete beam slab modules.b. the construction of reinforced concrete retaining wall structure in lower part of yard is carried out.c. while carrying out reinforced concrete retaining wall construction, according to the prefabricated processing of support plate in the concrete beam slab module segmented in step a in site outside.d. the construction of column and main beam combination of unloading platform is carried out.e. install secondary beam between adjacent two main beams.f. install support plate on secondary beam.g. tie up reinforcement on support plate and install embedded part, after setting side mould, the pouring construction of concrete beam slab module is carried out.h. after unloading platform construction is completed, the construction of ground floor slab reinforced concrete structure is carried out.The present application can carry out the construction of unloading platform without using scaffold, reduce high-altitude operation, upper structure and lower structure can be constructed in parallel, greatly reduce cost and shorten construction period.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to a C-type stockyard construction technology, in particular to an assembly type C-type stockyard construction method based on BIM. BACKGROUND

[0002] In the metallurgical system closed stockyard reconstruction project, the C-type stockyard occupies an important position, generally several hundred meters long longitudinal intermediate concrete retaining wall and transverse partition wall are arranged in the C-type stockyard, the longitudinal partition wall is generally divided into upper and lower two layers, the lower part is a thick reinforced concrete structure wall, and the upper half is a discharging cantilever platform of frame structure, generally the discharging platform is more than 20 meters high from the ground, which belongs to super dangerous large project, in the traditional construction method, when the upper discharging cantilever platform is constructed, the scaffold is erected from the bottom, and the formwork is erected on the scaffold to pour and construct the cantilever platform, the turnover material consumption is very large in the whole construction process, the construction period is also very long, there are many high-altitude operations, and the safety hidden danger is large. SUMMARY

[0003] The purpose of the present application is to provide an assembly type C-type stockyard construction method based on BIM, so as to solve the problems of long construction period, many high-altitude operations and large safety hidden danger of the existing C-type stockyard.

[0004] The present application is implemented as follows: an assembly type C-type stockyard construction method based on BIM, comprising the following steps.

[0005] a. Using BIM technology, the discharging platform on the upper part of the stockyard is divided into a plurality of concrete beam plate modules.

[0006] b. The construction of the lower part of the reinforced concrete retaining wall structure of the stockyard is carried out.

[0007] c. While the reinforced concrete retaining wall is constructed, the supporting plate is prefabricated according to the concrete beam plate module divided in step a outside the site.

[0008] d. The construction of the column and main beam combination of the discharging platform is carried out.

[0009] e. The secondary beam is installed between the two adjacent main beams.

[0010] f. The supporting plate is installed on the secondary beam.

[0011] g. The steel bars are tied on the supporting plate, the embedded parts are installed, the edge form is erected, and the pouring construction of the concrete beam plate module is carried out.

[0012] h. After the construction of the discharging platform is completed, the construction of the ground floor reinforced concrete structure is carried out.

[0013] During construction of the lower reinforced concrete retaining wall structure, the reinforced concrete retaining wall is divided into several regions by using BIM technology, is divided into several layers along the height direction, and is divided into several segments along the length direction, is constructed in layers from bottom to top, and is constructed in segments at intervals in each layer.

[0014] Every 3.6 meters along the height direction is a layer, and every 40 meters along the length direction is a segment.

[0015] The support plate comprises a reinforced concrete plate, the length of the reinforced concrete plate is equal to the spacing between two adjacent main beams, a plurality of columns of binding steel bars are arranged on the upper plate surface of the reinforced concrete plate, and outrigger steels are arranged on the side edges at both ends of the reinforced concrete plate.

[0016] When the support plate is installed on the secondary beam, the two ends of the reinforced concrete plate are aligned with two adjacent main beams respectively, and the outrigger steels are connected with the reserved steels at the top of the main beams.

[0017] In step g, the steel bars are bound on the binding steel bars.

[0018] When the construction of steps f and g is performed, the construction is sequentially performed in segments according to the positions of the beam plate modules divided in step a.

[0019] The application utilizes BIM technology to divide the C-shaped stockyard into modules and perform construction according to the modules, especially for the unloading platform of the cantilever structure, the prefabricated support plate is used to replace the existing pouring formwork, the support plate is directly used for pouring of the unloading platform after installation, and the support plate becomes part of the unloading platform after pouring, without subsequent form removal operation.

[0020] The support plate is manufactured in a manufacturing factory, the factory manufacturing is used to ensure manufacturing quality and reduce on-site workload, the modules are mainly assembled on site, the automobile crane is used for hoisting and positioning in the assembling process, and high-altitude operation is reduced.

[0021] The upper structure can be constructed in parallel with the lower structure in time, and the construction time is shortened. The prefabricated support plate can avoid the erection, removal, transportation, maintenance and storage of the scaffold with thousands of tons, and can also avoid the complex procedures of super-dangerous engineering. Meanwhile, the upper structure construction is completed without waiting for the curing to reach 100% strength before removing the bearing frame, and the ground civil construction and equipment installation process construction can be arranged in between. Finally, the effect of greatly reducing the cost and shortening the construction period is achieved. BRIEF DESCRIPTION OF DRAWINGS

[0022] Figure 1 It is a structural diagram of the C-shaped stockyard of the application.

[0023] Figure 2is a schematic diagram of the column and main beam combination construction of the present application.

[0024] Figure 3 is a schematic diagram of the installation of the secondary beam and support plate of the present application.

[0025] Figure 4 is a structural diagram of the support plate of the present application.

[0026] Figure 5 is Figure 4 a side view.

[0027] In the figure: 1, reinforced concrete retaining wall; 2, column; 3, main beam; 4, secondary beam; 5, unloading platform; 6, support plate; 7, binding steel; 8, external steel. DETAILED DESCRIPTION

[0028] As shown in Figure 1 , the C-type stockyard includes a ground part, a lower reinforced concrete retaining wall 1 part and an upper unloading platform 5 part, the present application introduces a BIM-based assembly type C-type stockyard construction method, which includes the following steps.

[0029] a. Using BIM technology, the upper unloading platform 5 of the stockyard is divided into a plurality of concrete beam plate modules.

[0030] b. Perform the construction of the lower reinforced concrete retaining wall 1 structure of the stockyard.

[0031] c. While performing the reinforced concrete retaining wall 1 construction, the support plate 6 is prefabricated outside the site according to the concrete beam plate modules divided in step a.

[0032] d. Perform the construction of the column 2 and main beam 3 combination of the unloading platform 5, as shown in Figure 2 .

[0033] e. Install the secondary beam 4 between the adjacent two main beams 3.

[0034] f. Install the support plate 6 on the secondary beam 4, as shown in Figure 3 .

[0035] g. Tie the steel on the support plate 6 and install the embedded parts, and then perform the pouring construction of the concrete beam plate module.

[0036] h. After the unloading platform 5 construction is completed, the ground floor reinforced concrete structure is constructed.

[0037] Before performing the C-type stockyard construction, the C-type stockyard is divided into modules using BIM technology, including dividing the reinforced concrete retaining wall 1 and dividing the unloading platform 5.

[0038] The reinforced concrete retaining wall 1 is divided into several regions by using the BIM technology, is divided into several layers along the height direction, and is divided into several segments along the length direction for each layer. During the construction of the reinforced concrete retaining wall 1, the layers are constructed from bottom to top, and the segments are constructed in the middle of each layer at intervals. Through the construction at intervals, the two adjacent regions are not continuously constructed, but are constructed at intervals, so that the stress of the already poured part is fully released, and after the stress is released, the subsequent region can be directly poured, without the need of reserving a post-pouring gap, and the construction efficiency is improved.

[0039] In the division of the reinforced concrete retaining wall 1, every 3.6 meters along the height direction is a layer, and every 40 meters along the length direction is a segment.

[0040] As shown in Figure 4 , Figure 5 The support plate 6 includes a reinforced concrete plate, the length of the reinforced concrete plate is equal to the interval between two adjacent main beams 3, so that after the support plate 6 is placed on the secondary beam 4, the two ends of the support plate 6 are just lapped on the two main beams 3. A plurality of rows of binding steel bars 7 are arranged on the upper plate surface of the reinforced concrete plate, and the outer steel bars 8 are arranged on the side edges of the two ends of the reinforced concrete plate, respectively.

[0041] When the support plate 6 is installed on the secondary beam 4, the two ends of the reinforced concrete plate are aligned with the two adjacent main beams 3, respectively, and the outer steel bars 8 are connected with the reserved steel bars on the top of the main beams 3, and the part is poured together during pouring, so as to realize the connection between the support plate 6 and the main beams 3, and the support plate 6 is supported by the secondary beam 4 below at the same time.

[0042] In step g, when the steel bars are bound before pouring, the steel bars are bound on the binding steel bars 7, so that when pouring, the newly poured concrete and the reinforced concrete plate of the support plate 6 can be integrated.

[0043] When the steps f and g are constructed, the beam plate modules divided in step a are sequentially constructed in segments until the construction of the entire unloading platform 5 is completed.

[0044] The present application utilizes the BIM technology to divide the C-shaped stockyard into modules, and constructs according to the modules, especially for the unloading platform 5 of the cantilever structure, the prefabricated support plate 6 is used instead of the existing pouring formwork, and the scaffold is not needed to be erected for the pouring formwork as usual, after the support plate 6 is installed, the pouring of the unloading platform 5 is directly performed on the support plate 6, and after the pouring is completed, the support plate 6 becomes a part of the unloading platform 5, without the need of subsequent form removal operation.

[0045] The support plate 6 is manufactured in a factory, and the manufacturing quality is ensured through the factory manufacturing, and the on-site workload is reduced; on site, mainly the modules are assembled, the assembling process is hoisted into position by using a car crane, and high-altitude operation is reduced.

[0046] The upper structure in time can be constructed in parallel with the lower structure, and the construction time is shortened. The prefabricated support plate 6 can avoid the erection, removal, transportation, maintenance and storage of the scaffold body of thousands of tons, and can also avoid the complex procedures of the super-dangerous project. At the same time, after the upper structure construction is completed, the load-bearing frame does not need to wait for maintenance to reach 100% strength before removal, and the ground civil construction and equipment installation process construction can be arranged. Finally, the effect of greatly reducing the cost and shortening the construction period is achieved.

Claims

1. A BIM-based prefabricated C-type material yard construction method, characterized in that, Includes the following steps: a. Using BIM technology, the unloading platform above the material yard is divided into multiple concrete beam and slab modules; b. Construct the reinforced concrete retaining wall structure under the material yard; c. While constructing the reinforced concrete retaining wall, prefabricate the support plate outside the site according to the concrete beam and slab modules divided in step a. d. Construct the assembly of the columns and main beams of the unloading platform; e. Install secondary beams between two adjacent main beams; f. Install a support plate on the secondary beam; the support plate includes a reinforced concrete slab, the length of which is equal to the spacing between two adjacent main beams, and several rows of connecting steel bars are provided on the upper surface of the reinforced concrete slab, and protruding steel bars are provided on the sides at both ends of the reinforced concrete slab; when installing the support plate on the secondary beam, align the two ends of the reinforced concrete slab with the two adjacent main beams respectively, and connect the protruding steel bars with the reserved steel bars at the top of the main beams; g. Tie the reinforcing bars on the support plate and install the embedded parts, then tie the reinforcing bars to the connecting reinforcing bars; after setting up the side formwork, carry out the pouring of the concrete beam and slab modules; h. After the unloading platform is completed, the reinforced concrete structure of the ground slab will be constructed.

2. The BIM-based prefabricated C-type material yard construction method according to claim 1, characterized in that, When constructing the lower reinforced concrete retaining wall structure, BIM technology is used to divide the reinforced concrete retaining wall into several areas, several layers along the height direction, and several segments along the length direction. Construction is carried out layer by layer from bottom to top, with segment construction at intervals in each layer.

3. The BIM-based prefabricated C-type material yard construction method according to claim 2, characterized in that, Each floor is 3.6 meters high, and each section is 40 meters long.

4. The BIM-based prefabricated C-type material yard construction method according to claim 1, characterized in that, During the construction of steps f and g, the construction is carried out in segments according to the positions of the beam and slab modules divided in step a.

Citation Information

Patent Citations

  • Steel beam-concrete composite floor slab combined assembly system

    CN111411724A

  • Construction method for C type stock ground upper structure

    CN111535628A

  • Steel beam platform structure for C-shaped stockyard

    CN113089843A