"Field-phase" coupled transport simulation system for soil pollutants in petrochemical sites
By designing a "field-phase" coupled transport simulation system to simulate the migration and transformation process of soil pollutants in petrochemical sites, it solves the problem of difficulty in effectively simulating the migration and transformation of pollutants in complex multi-media environments in the existing technology, and achieves A systematic understanding of the migration patterns of pollutants in petrochemical sites provides important guidance for the remediation of contaminated sites.
Patent Information
- Application Number
- CN202211700526.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-28
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2042-12-28
AI Technical Summary
Existing technology is difficult to effectively simulate the migration and transformation process of soil pollutants in petrochemical sites in complex multi-media environments, and there is a lack of systematic methods to couple and consider multiple influencing factors.
Design a "field-phase" coupled migration simulation system for soil pollutants in petrochemical sites. By simulating the migration and transformation process of rainwater, wastewater and gaseous pollutants, and combining conditions such as light, temperature and soil physical and chemical properties, the simulated Soil pollutant transport process based on actual conditions at the petrochemical site.
It has realized the systematic simulation of soil pollutant migration process in petrochemical sites, can simulate the coupling effect of multiple influencing factors to a large extent, and provides a more realistic pollutant migration and transformation law, which has important guiding significance for contaminated sites. Restoration and remediation.
Smart Images

Figure CN116124648B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of simulation of the migration and transformation process of soil pollutants in petrochemical sites, and in particular to a "field-phase" coupled migration simulation system of soil pollutants in petrochemical sites. Background Art
[0002] The petrochemical industry is a pillar industry in China, mainly producing more than 3,000 petrochemical products such as gasoline, diesel, lubricating oil, synthetic resin, synthetic rubber, synthetic fiber, etc. As a key industry for soil environmental supervision, petrochemical industry is characterized by high pollution and high risk due to the diversity and complexity of raw materials and production processes. Its pollutant composition is complex, and the pollutants involved include heavy metals, petroleum hydrocarbons, polycyclic aromatic hydrocarbons and volatile organic compounds. Petrochemical sites have the characteristics of large site area, many production units and dense pipelines, and a wide variety of chemicals involved. The risk of environmental pollution is high, so it is necessary to focus on the pollution of soil and groundwater environment on the site. Due to the regional differences in the distribution of petrochemical sites, the petrochemical industry, as a key industry in the Yangtze River Economic Belt, faces the objective problems of site type diversity and spatial heterogeneity at the regional scale.
[0003] Existing simulation technology methods mainly focus on the pollution characteristics within petrochemical sites. There are relatively few simulations on soil pollutants in petrochemical sites, such as petroleum hydrocarbons, polycyclic aromatic hydrocarbons, volatile organic compounds and heavy metals, as well as the migration and transformation of their complex pollutants in the soil of the site. They mainly focus on the diffusion of pollutants in a single medium or the simulation of a single factor. The migration of pollutants in site soil is actually a complex multi-media coupling process that varies in space and time. At present, there is still a lack of systematic technical methods for this process. Summary of the invention
[0004] The purpose of the present invention is to provide a "field-phase" coupled migration simulation system for soil pollutants in petrochemical sites, which can simulate the soil pollutant migration process that fits the actual conditions of petrochemical sites and couples multiple influencing factors.
[0005] To achieve the above object, the present invention provides the following solutions:
[0006] A "field-phase" coupled migration simulation system for soil pollutants in a petrochemical site, comprising: a ceiling, a first box, a second box, and a third box connected in sequence from top to bottom;
[0007] A lighting device is hung in the ceiling; the lighting device is used to simulate lighting conditions;
[0008] A spray device is arranged between the ceiling and the first box; the spray device is connected to a simulated rainwater tank; the ceiling is used to simulate rainfall conditions;
[0009] A gas mixing chamber is provided inside the first box; the gas mixing chamber is connected to a gaseous pollutant storage tank; a plurality of gas sampling holes are provided on one side of the first box; the gas sampling holes are connected to a gas sampling device; the first box is used to simulate gaseous pollution conditions;
[0010] The second box is filled with soil; a plurality of water inlet pipes are provided on one side of the second box; the second box is connected to the simulated wastewater tank through the water inlet pipes; a plurality of drainage pipes are provided at the bottom of the second box; the drainage pipes are used to discharge the water sample seeping out after soil interception into the third box; the second box is used to simulate pollutant pollution conditions;
[0011] The third box is used to collect water samples that seep out after being intercepted by the soil.
[0012] Optionally, a movable partition is provided between the first box body and the second box body;
[0013] The ceiling, the first box, the second box and the third box are all detachable.
[0014] Optionally, a water flow meter and a water pump are also included;
[0015] The spray device is connected to the simulated rainwater tank through the water flow meter and the water pump.
[0016] Optionally, the first box further includes: a gas control valve, an exhaust hole and a temperature-pressure monitor;
[0017] The exhaust hole is arranged at the bottom of the gas mixing chamber, and the gas control valve is arranged on the exhaust hole;
[0018] The gas mixing chamber is connected to the gaseous pollutant storage tank through a gas flow meter and an air pump; the gaseous pollutants are pumped into the gas mixing chamber through the air pump and the gas flow meter and fully mixed, and the valve of the gas control valve is opened to discharge the mixed gaseous pollutants into the first box;
[0019] The temperature-pressure monitor is arranged inside the first box and is used to monitor the temperature and pressure of the first box.
[0020] Optionally, a metal tube and a sampling valve are provided at the gas sampling hole;
[0021] The sampling valve is arranged on the metal tube; the gas sampling device is connected to the metal tube; the sampling valve is used to control the discharge of the gas in the first box.
[0022] Optionally, the gas sampling device is an activated carbon sampling tube; the activated carbon sampling tube includes a solvent desorption type and a thermal desorption type.
[0023] Optionally, it also includes: a multi-channel peristaltic pump;
[0024] One end of the multi-channel peristaltic pump is connected to the water inlet pipe, and the other end of the multi-channel peristaltic pump is connected to the simulated wastewater tank.
[0025] Optionally, it also includes: soil extractor;
[0026] A plurality of soil-water sampling holes are arranged on the surface of the soil; and the soil sampler collects soil-water samples through the soil-water sampling holes.
[0027] Optionally, the third box has a built-in conical flask or a measuring cylinder;
[0028] The conical flask or the measuring cylinder is arranged below the drain pipe.
[0029] According to the specific embodiments provided by the present invention, the present invention discloses the following technical effects: the present invention simulates the migration and transformation process of different types of pollution entering the environmental medium by simulating rainwater tanks, simulated wastewater tanks and gaseous pollutant storage tanks, and simulates the actual environmental engineering conditions of the petrochemical site to a large extent by changing the rainfall intensity, rainfall pH, wastewater discharge flow rate, gaseous pollutant emission rate, light intensity, soil physical and chemical properties, ambient temperature and other conditions, thereby simulating a soil pollutant migration process that is more in line with the actual conditions of the petrochemical site and coupled with multiple influencing factors. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0031] Figure 1 This is a structural diagram of the "field-phase" coupled migration simulation system for soil pollutants in petrochemical sites provided by the present invention;
[0032] Figure 2 A structural diagram of the ceiling and the first box provided by the present invention;
[0033] Figure 3 This is a structural diagram of the second box and the third box provided by the present invention.
[0034] Explanation of symbols:
[0035] 1-ceiling; 2-first box; 3-second box; 4-third box; 5-gaseous pollutant storage tank; 6-air pump; 7-gas flowmeter; 8-gas mixing chamber; 9-gas control valve; 10-exhaust hole; 11-temperature-pressure monitor; 12-lighting device; 13-sprinkler; 14-gas sampling hole; 15-gas sampling device; 16-water flowmeter; 17-water pump; 18-simulated rainwater tank; 19-simulated wastewater tank; 20-multi-channel peristaltic pump; 21-drain pipe; 22-soil-water sampling hole; 23-box partition; 24-soil sampler; 25-conical flask / measuring cylinder; 26-water inlet pipe. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] The purpose of the present invention is to provide a "field-phase" coupled migration simulation system for soil pollutants in petrochemical sites, which can simulate the soil pollutant migration process that fits the actual conditions of petrochemical sites and couples multiple influencing factors.
[0038] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0039] In the present invention, the field refers to the "site" and the "key area within the site"; the phase state refers to the "phase of pollutants" and the "morphology"; and the coupling is the association between the "field" and the "phase state" to explore the influence mechanism of multiple factors.
[0040] Embodiment 1
[0041] Figure 1 This is a structural diagram of the "field-phase" coupled migration simulation system for soil pollutants in petrochemical sites provided by the present invention, such as Figure 1As shown, a "field-phase" coupled migration simulation system for soil pollutants in a petrochemical site includes: a ceiling 1, a first box 2, a second box 3 and a third box 4 are connected in sequence from top to bottom; a lighting device 12 is hung in the ceiling 1; the lighting device 12 is used to simulate lighting conditions; a spray device 13 is set between the ceiling 1 and the first box 2 to simulate daytime lighting and is closed at night; the spray device 13 is connected to a simulated rainwater tank 18; the ceiling 1 is used to simulate rainfall conditions; a gas mixing chamber 8 is arranged inside the first box 2; the gas mixing chamber 8 is connected to a gaseous pollutant storage tank 5; the third box 4 is connected to the first box 2; the second box 3 is connected to the third box 4; the third box 4 is connected to the first box 2; the third box 4 is connected to the first box 2; the third box 4 is connected to the second box 4; the third box 4 is connected to the first box 2; the third box 4 is connected to the second box 4; the third box 4 is connected to the first box 2; the third box 4 is connected to the second box 4; the third box 4 is connected to the third ... A plurality of gas sampling holes are provided on one side of a box body 2; the gas sampling holes are connected to a gas sampling device 15; the first box body 2 is used to simulate gaseous pollution conditions; the second box body 3 is filled with soil; a plurality of water inlet pipes 26 are provided on one side of the second box body 3; the second box body 3 is connected to a simulated wastewater tank 19 through the water inlet pipes 26; a plurality of drainage pipes 21 are provided at the bottom of the second box body 3; the drainage pipes 21 are used to discharge water samples seeping out after soil interception into the third box body 4; the second box body 3 is used to simulate pollutant pollution conditions; the third box body 4 is used to collect water samples seeping out after soil interception.
[0042] The simulation system is a closed steel frame structure. In order to simulate the actual situation of the petrochemical site, the size of the simulation system is proportional to the size of the petrochemical site / key research area. The simulation system is connected from top to bottom in sequence to the ceiling 1, the first box 2, the second box 3 and the third box 4, and all structures are connected internally. The simulation box is connected to the gas mixing chamber 8, the spray device 13, and the temperature-pressure monitor 11, and is externally connected to the gaseous pollutant storage tank 5, the simulated wastewater tank 19, and the simulated rainwater tank 18.
[0043] In practical applications, a movable partition 23 is provided between the first box 2 and the second box 3; the ceiling 1, the first box 2, the second box 3 and the third box 4 are all detachable. This ensures that the two boxes are not connected and do not interfere with each other before the experimental simulation; and also ensures that the two boxes no longer affect each other after the reaction stops or ends.
[0044] In actual application, the ceiling 1 is a roof structure composed of transparent organic plastic and a stainless steel frame, and a lighting device 12 simulating daylight is hung in the ceiling 1 (the number and wattage of the lighting lamps are determined according to the size of the simulated box). A spray device 13 is mounted between the first box 2 and the ceiling 1, and the number and flow rate of the spray heads can be determined according to the amount and frequency of rainfall in the venue.
[0045] In practical applications, Figure 2 The structure diagram of the ceiling 1 and the first box body 2 provided by the present invention is as follows: Figure 2As shown, the present invention also includes: a water flow meter 16 and a water pump 17; the spray device 13 is connected to the simulated rainwater tank 18 through the water flow meter 16 and the water pump 17. The spray device 13 and the simulated rainwater tank 18 can simulate the rainfall conditions on the site. The simulated rainwater tank 18 is connected to the inlet of the multi-channel conversion interface through the water inlet pipe 26, and the outlet of the multi-channel conversion interface is connected to the sprinkler head. Rainwater is pumped in through the water pump 17 and leached through the sprinkler head. During this period, the rainfall flow is monitored by the flow meter. The rainwater is leached through the sprinkler head, thereby simulating rainfall conditions. The simulation process monitors the rainfall flow through the flow meter.
[0046] In practical applications, the first housing 2 further includes: a gas control valve 9, an exhaust hole 10 and a temperature-pressure monitor 11; the exhaust hole 10 is arranged at the bottom of the gas mixing chamber 8, and the gas control valve 9 is arranged on the exhaust hole 10; the gas mixing chamber 8 is connected to the gaseous pollutant storage tank 5 through the gas flow meter 7 and the air pump 6; the gaseous pollutants are pumped into the gas mixing chamber 8 through the air pump 6 and the gas flow meter 7 and then fully mixed, and the valve of the gas control valve 9 is opened to discharge the mixed gaseous pollutants into the first housing 2; the temperature-pressure monitor 11 is arranged inside the first housing 2 and is used to monitor the temperature and pressure of the first housing 2. The first housing 2 is made of transparent glass.
[0047] The height of the first box 2 is related to the height of the chimney emission of gaseous pollutants in the petrochemical site / key research area. A movable partition 23 is provided between the first box 2 and the second box 3 to ensure that the two boxes are not connected and do not interfere with each other before and after the experimental simulation.
[0048] In the gaseous pollutant storage tank 5, the gaseous pollutants can be pumped into the gas mixing chamber 8 through the air pump 6, and after the gas is evenly mixed, the gas control valve 9 is opened to discharge the gaseous pollutants into the first box 2. The gas tank can store other volatile and semi-volatile organic pollutants and other gaseous pollutants, such as Hg vapor, other heavy metal waste gas and mixed gaseous pollutants.
[0049] In practical applications, a metal tube and a sampling valve are provided at the gas sampling hole; the sampling valve is provided on the metal tube; the gas sampling device 15 is connected to the metal tube; and the sampling valve is used to control the discharge of the gas in the first box 2.
[0050] In practical applications, the gas sampling device 15 is an activated carbon sampling tube; the activated carbon sampling tube includes a solvent desorption type and a thermal desorption type.
[0051] Solvent desorption type: Specification: 6×75mm, filled with 150mg of 20-40 mesh activated carbon, divided into two sections: 50mg for the front section and 100mg for the rear section, the diameter of the two sections of the solvent seal is about 2mm. This sampling tube is used in conjunction with the sampler. When sampling, use a small grinding wheel to open both ends of the sampling tube at the sampling point, connect the 50mg end to the air inlet of the sampler, and then adjust the sampler flow and sampling time as needed to start sampling. After sampling, put plastic caps on both ends of the sampling tube to seal, and finally use a gas chromatograph for processing and analysis.
[0052] Thermal desorption type: Specification: 6×120mm, filled with 100mg of 20-40 mesh activated carbon and biased to one end, the diameter of the two sections of the sealing mouth is about 2mm. This sampling tube is used in conjunction with the sampler. When sampling, use a small grinding wheel to open both ends of the sampling tube at the sampling point, and connect the end of the activated carbon biased to the air inlet of the sampler. Then adjust the sampler flow and sampling time as needed to start sampling. After sampling, put plastic caps on both ends of the sampling tube to seal it, and finally use a thermal desorption furnace for processing and analysis.
[0053] Compared with sampling via glass absorption bottles, sampling via activated carbon sampling tubes is quick and convenient, has strong absorption capacity, high data accuracy, low cost, and is easy to carry for on-site sampling.
[0054] In practical applications, Figure 3 The structure diagram of the second box body 3 and the third box body 4 provided by the present invention is as follows: Figure 3 As shown, the present invention also includes: a multi-channel peristaltic pump 20; one end of the multi-channel peristaltic pump 20 is connected to the water inlet pipe 26, and the other end of the multi-channel peristaltic pump 20 is connected to the simulated wastewater tank 19. The simulated wastewater is pumped into the surface of the surface soil in the second box body 3 through the water inlet pipe 26 at a certain flow rate by the multi-channel peristaltic pump 20 to simulate the infiltration process of the wastewater in the soil after discharge. In the second box body 3, except for the top layer of soil, soil with a particle size distribution consistent with the actual stratum of the petrochemical site is filled from top to bottom. A plurality of soil-water sampling holes 22 are evenly distributed on the front and back sides of the second box body 3, and sampling is performed using a soil sampler 24. The second box body 3 is made of opaque organic plastic.
[0055] In practical applications, the present invention further includes: a soil sampler 24; a plurality of soil-water sampling holes 22 are provided on the surface of the soil; and the soil sampler 24 collects soil-water samples through the soil-water sampling holes 22.
[0056] A plastic plug is provided at the soil-water sampling hole 22, and soil samples can be obtained from the soil-water sampling hole 22 to analyze its material composition and physical and chemical properties; at the same time, the soil-water sampling holes 22 on both sides are symmetrical, and the soil sampler 24 can be knocked into the box to extract the soil column. By analyzing the distribution of pollutants at different positions in each soil column, the vertical and longitudinal migration characteristics of pollutants in the soil are explored.
[0057] The soil sampler 24 is made of stainless steel 304 material, which will not cause pollution to the soil sample; the material is hard and the shape is not easy to be bent or twisted. The length is about 15-20cm. The soil sampler 24 is marked with scale values on the surface, and each scale is 10mm, so that soil samples of different lengths can be taken.
[0058] In practical applications, the third box 4 has a conical flask 25 or a measuring cylinder built therein; the conical flask 25 or the measuring cylinder is arranged below the drain pipe 21 .
[0059] A door frame that can be opened and closed is provided on one side of the third box body 4, and a conical bottle 25 or a measuring cylinder can be placed in the box body to collect water samples discharged from the drain pipe 21, and the water samples can be collected and processed at different times. The third box body 4 is made of opaque organic plastic.
[0060] The conical flask 25 or the measuring cylinder can collect water samples that flow out after being intercepted and adsorbed by the soil, so as to simulate the properties and characteristics of pollutants entering the groundwater.
[0061] Based on the idea of microcosmic experiment, the present invention integrates the results of laboratory research batch test, column test and laboratory model simulation to construct a "field-phase" coupled migration simulation system and method for soil pollutants in petrochemical sites. This technology collects basic information such as environmental conditions (including hydrogeology, rainfall and light, etc.) in the area where the petrochemical site is located, soil type, enterprise production characteristics, pollutant types and their emission characteristics, and constructs a "field-phase" coupled migration simulation system.
[0062] Combined with the production characteristics of the petrochemical site, the device is equipped with an atmospheric emission source and a wastewater emission source. Atmospheric pollutants can enter the surface soil through dry deposition and wet deposition, and wastewater pollutants can enter the surface soil of the site through point sources or surface sources. The soil will also serve as a pollution source, and the pollutants will migrate and diffuse vertically and horizontally in the device. During the simulation process, the concentration of pollutants in the gas phase, liquid phase and solid phase soil in the simulation system can be monitored continuously for a long time through the gas sampling device 15 and the soil-water sampling hole 22. The isotope tracer technology is used to study the changes in the chemical form of pollutants during the migration process, so as to explore the three-phase interface flux exchange process and migration and transformation laws of pollutants. After clarifying the migration and transformation characteristics of pollutants, the influence of different hydrogeological conditions and different hydrothermal conditions such as precipitation and light on the migration and transmission process of pollutants under microbial or non-biological conditions can be further investigated.
[0063] Embodiment 2
[0064] Simulation experiment on the pollution behavior of benzene series in surface soil:
[0065] 1.1 Soil filling: To simulate the thickness of natural surface soil, the soil height is set to 20 cm and the soil bulk density is 1.39 g / cm 3 When filling, fill in layers according to the actual soil bulk density, fill every 2cm in sequence, and calculate the soil mass required for a height of 2cm based on the soil bulk density. After each corresponding mass of soil is filled, the soil needs to be compacted to a thickness of 2cm. After each layer is completed, the upper layer of soil needs to be roughened with a glass rod to prevent the formation of interlayer flow and wall flow.
[0066] 1.2 Leachate preparation: Based on the actual pollution situation of petrochemical sites, leachates with different BTEX pollution intensities and BTEX and metal Co composite pollution were prepared. A total of 7 groups of experiments were set up by changing the single experimental conditions. ① When the pH of the leaching liquid is 7.0, the pollution intensity of BTEX is 30mg / L, and the leaching time is 14d; ② When the pH of the leaching liquid is 7.0, the pollution intensity of BTEX is 30mg / L, and the leaching time is 7d; ③ When the pH of the leaching liquid is 7.0, the pollution intensity of BTEX is 30mg / L, and the leaching time is 3d; ④ When the pH of the leaching liquid is 4.0, the pollution intensity of BTEX is 30mg / L, and the leaching time is 14d; ⑤ When the pH of the leaching liquid is 9.0, the pollution intensity of BTEX is 30mg / L, and the leaching time is 14d; ⑥ When the pH of the leaching liquid is 7.0, the pollution intensity of BTEX is 180mg / L, and the leaching time is 14d; ⑦ When the pH of the leaching liquid is 7.0, the pollution intensity of BTEX is 30mg / L + the pollution intensity of metal Co is 10mg / L, and the leaching time is 14d. The ionic strength of all leaching liquids is 0.01mol / L (in terms of CaCl 2 count).
[0067] 1.3 Saturated soil, determination of the theoretical pore volume (PV) of the packed soil: First, soak the soil from top to bottom with deionized water to saturate the soil, and continue to supply water to allow the solution to reach a relatively stable flow rate in the soil. Then stop supplying water until no solution flows out from under the packed soil. Subtract the volume of the effluent from the volume of the leaching liquid to get the theoretical pore volume of the packed soil (PV = 180 mL). Then let the soil stand for a while before starting the experiment.
[0068] 1.4 Leaching experiment: The leaching liquid was discharged into the soil by a multi-flux peristaltic pump to control the leaching speed to be consistent. During the experiment, the experimental temperature was kept at room temperature (20±0.5℃).
[0069] 1.5 Determination of pollutant content in soil: After stopping leaching, take out the soil after standing for a period of time, and collect soil at different depths by soil slicing for xylene content analysis. Each 4 cm is a layer, and the soil column is cut layer by layer. Four parallel samples are taken from each layer of soil sample to determine the BTEX / BTEX+Co content of the soil sample. At the same time, the moisture content of each layer of soil samples is determined. This further analyzes the pollution behavior of BTEX in the soil.
[0070] 1.6 After the leaching, it was found that: ① The migration ability of benzene series is strong, and the soil's adsorption and fixation ability of benzene series is relatively weak. The benzene series can reach adsorption saturation at the beginning of leaching, and then it is in a state of equilibrium. ② A certain amount of ethylbenzene was detected in the soil under different pollution intensities, and the content reached 1.59mg / kg, 1.67mg / kg, and 1.63mg / kg respectively, but ethylbenzene was not introduced during the pollution input process, so it is speculated that ethylbenzene may be a reaction product in the system. ③ The content level of benzene series in the soil under different pH leaching conditions is very different, which is 13.32mg / kg, 13.20mg / kg, and 13.45mg / kg respectively. The natural soil system has a strong buffering capacity. The physical and chemical properties of benzene series show that it is basically not affected by the acid-base characteristics of the solution. It is speculated that the pH value of the leaching solution will not affect the pollution behavior and vertical distribution of benzene series in the soil. ④ After 14 days of leaching, compared with the single BTEX pollution condition, the BTEX content in the soil under the BTEX-Co composite pollution condition decreased by 6.8% to 10.1%, and the average contents were 13.20 mg / kg and 12.04 mg / kg, respectively. There may be competitive adsorption between BTEX and Co in the soil. Co may weaken the adsorption and fixation capacity of BTEX in the soil and promote the vertical migration of BTEX in the soil.
[0071] Embodiment 3
[0072] Simulation experiment of leaching of BTEX-contaminated soil under natural rainfall conditions:
[0073] 1.1 Soil filling: Combined with the actual pollution characteristics of the site, the thickness of the surface contaminated soil is simulated and the soil height is set to 6cm. When filling, fill in layers according to the actual soil bulk density, fill every 2cm in sequence, and calculate the soil mass required for a height of 2cm based on the soil bulk density. For each corresponding mass of soil filled, the soil needs to be compacted to a thickness of 2cm. After each layer is completed, the upper layer of soil needs to be roughened with a glass rod to prevent the formation of interlayer flow and wall flow.
[0074] 1.2 Rainwater preparation: Based on the composition of rainfall in the actual petrochemical site, rainwater with different rainfall pollution intensities was prepared. First, SO 4 2- :NO 3 -The molar ratio of acid rain mother solution is 5:1, and calcium chloride is used to prepare a solution with an ionic strength of 0.01mol / L, and then the pH value of the solution is adjusted to 6.0 or 3.5 using the acid rain mother solution, and finally the simulated rainwater preparation of different experimental groups is completed. A total of 4 groups of experiments were set up. ① Rainfall pH = 6.0, soil BTEX pollution intensity 19.2mg / kg, rainfall intensity 10mm / h, leaching time 48h; ② Rainfall pH = 3.5, soil BTEX pollution intensity 19.2mg / kg, rainfall intensity 10mm / h, leaching time 48h; ③ When the leaching solution pH = 6.0, the soil BTEX pollution intensity 19.2mg / kg, rainfall intensity 20mm / h, leaching time 48h; ④ When the leaching solution pH = 6.0, the soil BTEX pollution intensity 39.7mg / kg + metal Co concentration 105.7mg / kg, rainfall intensity 10mm / h, leaching time 48h. The ionic strength of all rainwater is 0.01 mol / L (in terms of CaCl 2 count).
[0075] 1.3 Saturated soil, determination of the theoretical pore volume (PV) of the packed soil: First, soak the soil from top to bottom with deionized water to make the soil saturated, and continue to supply water to make the solution reach a relatively stable flow rate in the soil. Then stop supplying water until no solution flows out from under the packed soil. Subtract the volume of the effluent from the volume of the leached liquid to get the theoretical pore volume of the packed soil. Then let the soil stand for a period of time before starting the experiment.
[0076] 1.4 Leaching experiment: The leaching liquid was discharged into the soil by a multi-flux peristaltic pump to control the leaching speed to be consistent. During the experiment, the experimental temperature was kept at room temperature (20±0.5℃).
[0077] 1.5 Determination of pollutant content in soil: After stopping leaching, the soil was taken out after standing for a period of time. Soil at different depths was collected by soil slicing for xylene content analysis. Each 2 cm layer was cut into soil columns layer by layer. Two parallel samples were taken from each soil layer to determine the BTEX / BTEX+Co content of the soil samples. At the same time, the moisture content of each layer of soil samples was determined. This further explored the pollution behavior of BTEX in soil under natural environmental conditions.
[0078] 1.6 The results showed that: ① After 48 hours of continuous rainfall, the cumulative release rates of the three BTEXs under the simulated acid rain leaching at pH 3.5 were 15.4%, 16.0%, and 23.8%, respectively, which were lower than 17.7%, 18.3%, and 26.7% under the rain leaching conditions of pH 6.0, indicating that the acid rain action inhibited the release of BTEXs in the contaminated soil to a certain extent. The acid rain action weakened the vertical migration ability of BTEXs in the soil. ② After 48 hours of leaching, the cumulative release rates of the three BTEXs under the rainfall intensity of 20 mm / h were as high as 26.0%, 26.8%, and 35.7%, respectively, which were significantly higher than 17.7%, 18.3%, and 26.7% under the rainfall leaching conditions of 10 mm / h, indicating that the release of BTEXs in the soil under strong rainfall conditions was significantly enhanced. ③ After 48 hours of rainfall leaching, the cumulative release rates of the three BTEXes in the BTEX-Co composite contaminated soil were 32.0%, 30.5% and 33.4%, respectively, which were significantly higher than the release rates of 17.7%, 18.3% and 26.7% in the BTEX single contaminated soil, indicating that the presence of Co in the soil significantly promoted the release of BTEXes.
[0079] Embodiment 4
[0080] Simulation experiment on volatilization of xylene contaminated soil under different environmental conditions:
[0081] 1.1 Preparation of xylene-contaminated soil: Soil and xylene / methanol solution were prepared in a ratio of 1:1, and methanol and xylene were prepared in a ratio of 10:1. After volatilization for 36 hours, the mass concentration of xylene in the soil was measured to obtain the xylene-contaminated soil under the initial conditions.
[0082] 1.2 Compare the content of xylene volatilized into the air and the content of xylene remaining in the soil under shading conditions at 10, 20, 25 and 30°C. There are 3 experimental groups in total.
[0083] 1.3 Compare the content of xylene volatilized into the air and the content of xylene in the soil under room temperature (20±0.3℃), shading and lighting conditions.
[0084] 1.4 The results show that: ① With the increase of temperature, the content of three types of xylene volatilized into the air gradually increased, and the content of xylene released from the soil also gradually increased. Before and after volatilization, the total amount of xylene decreased: p-xylene decreased by 1.50%; m-xylene decreased by 5.12%; o-xylene decreased by 10.09%. ② The content of xylene volatilized into the air under light conditions was lower than that under shading conditions; the content of xylene in the soil under light conditions was higher than that under shading conditions. The total amount of xylene under light conditions was lower than that under shading conditions, indicating that xylene was decomposed by photolysis under light conditions.
[0085] Embodiment 5
[0086] Simulation experiment on the migration and transformation of production reagents in soil after leakage at petrochemical sites:
[0087] 1.1 Simulation system sealing test: Close all sampling holes and all valves. First, close the partition 23 between the first box body 2 and the second box body 3, inject water into the first box body 2, and observe whether the first box body 2 leaks. Open the partition 23, inject water into the second box body 3, and observe whether the second box body 3 leaks. When there is no water dripping from each joint and opening, proceed to the next step of the test.
[0088] 1.2 Filling soil: close the soil-water sampling hole 22, open the partition 23 between the first box body 2 and the second box body 3, and fill the second box body 3 with soil in layers from top to bottom. The particle size distribution of the soil refers to the actual soil geological conditions of the petrochemical site.
[0089] 1.3 Reagent leakage simulation: ① Prepare a xylene and metal Co composite solution according to the composition of the production raw materials on site, and put the composite contaminated solution into the simulated wastewater tank 19. ② Turn on the multi-flux peristaltic pump to discharge the simulated wastewater to the soil surface at a certain flow rate.
[0090] 1.4 Sampling and analysis: After the polluted solution has been discharged for a period of time, the gas sampling hole 14 is opened, and the polluted gas volatilized from the soil is sampled using the activated carbon sampling device. At the same time, the soil-gas sampling hole is opened, and the soil sampling device 24 is used to perform layered and zoned sampling and testing of the soil.
[0091] 1.5 Setting of environmental conditions: During the operation of the system, the lighting device 12 is operated according to the actual environmental conditions to simulate the daytime lighting conditions. At the same time, the simulated rainwater tank 18 and the spray device 13 can be used to simulate the influence of rainfall conditions on the migration and transformation of pollutants in the environmental medium, and samples are regularly taken from the gas sampling holes 14, the soil-water sampling holes 22 and the drainage pipe 21 in the third box 4 for monitoring, and the volatilization flux of pollutants in the closed system, the adsorption amount of the soil and the content of pollutants infiltrating into the groundwater are calculated.
[0092] 1.6 After the soil in the second box 3 is saturated and the environmental condition test is completed, the multi-flux peristaltic pump can be turned off, and the contaminated solution that has infiltrated into the third box 4 stops flowing out, and then the test is ended, the test materials are processed, and the test device is cleaned. The tightness of the device still needs to be checked before the next experiment.
[0093] In summary, the present invention can achieve the following effects:
[0094] (1) The simulation system provided by the present invention can simulate the entry of organic and inorganic pollutants into the soil through different pollution modes such as precipitation, atmospheric deposition and wastewater discharge, and further explore the emission characteristics of different pollutants and the identification of pollution sources when the soil acts as a "source" and "sink".
[0095] (2) The simulation system provided by the present invention can simulate the migration and transformation processes (leaching, volatilization, rainfall and adsorption, etc.) of different types of pollutants (VOC, SVOC and heavy metals, etc.) in a multi-media environment and the transformation products of pollutants at the three-phase interface.
[0096] (3) The simulation system provided by the present invention can make the operating characteristics and operating parameters of the device as close as possible to the actual petrochemical site by changing the types and emission concentrations of pollutants emitted by atmospheric emission sources, changing the wastewater discharge flow, changing the soil porosity, soil type, soil organic carbon content, simulating surface runoff, etc., so as to simulate the migration and transformation laws of pollutants, thereby reflecting the pollution impact that may be caused by the petrochemical site in the actual production process.
[0097] (4) The simulation system provided by the present invention can simulate the migration and transformation process of different types of pollution into the environmental medium by simulating rainwater tanks, simulated wastewater tanks and gaseous pollutant storage tanks, and can simulate the actual environmental engineering conditions of the petrochemical site to a large extent by changing conditions such as rainfall intensity, rainfall pH, wastewater discharge flow rate, gaseous pollutant emission rate, light intensity, soil physical and chemical properties, and ambient temperature.
[0098] (5) The simulation system provided by the present invention explores the distribution characteristics, migration and transformation characteristics of different pollutants in the soil of the contaminated site, which has important guiding significance for the subsequent in-situ remediation of the actual site, and the remediation and treatment of the contaminated site.
[0099] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0100] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites, characterized in that: include: Connect the ceiling, the first box, the second box and the third box in sequence from top to bottom; A lighting device is hung in the ceiling; the lighting device is used to simulate lighting conditions; A spray device is arranged between the ceiling and the first box; the spray device is connected to a simulated rainwater tank; the ceiling is used to simulate rainfall conditions; A gas mixing chamber is provided inside the first box; the gas mixing chamber is connected to a gaseous pollutant storage tank; a plurality of gas sampling holes are provided on one side of the first box; the gas sampling holes are connected to a gas sampling device; the first box is used to simulate gaseous pollution conditions; The second box is filled with soil; a plurality of water inlet pipes are provided on one side of the second box; the second box is connected to the simulated wastewater tank through the water inlet pipes; a plurality of drainage pipes are provided at the bottom of the second box; the drainage pipes are used to discharge the water sample seeping out after soil interception into the third box; the second box is used to simulate pollutant pollution conditions; The third box is used to collect water samples that seep out after soil interception; a movable partition is provided between the first box and the second box; The ceiling, the first box, the second box and the third box are all detachable.
2. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: It also includes a water flow meter and a water pump; The spray device is connected to the simulated rainwater tank through the water flow meter and the water pump.
3. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: The first box body further includes: a gas control valve, an exhaust hole and a temperature-pressure monitor; The exhaust hole is arranged at the bottom of the gas mixing chamber, and the gas control valve is arranged on the exhaust hole; The gas mixing chamber is connected to the gaseous pollutant storage tank through a gas flow meter and an air pump; the gaseous pollutants are pumped into the gas mixing chamber through the air pump and the gas flow meter and fully mixed, and the valve of the gas control valve is opened to discharge the mixed gaseous pollutants into the first box; The temperature-pressure monitor is arranged inside the first box and is used to monitor the temperature and pressure of the first box.
4. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: The gas sampling hole is provided with a metal tube and a sampling valve; The sampling valve is arranged on the metal tube; the gas sampling device is connected to the metal tube; the sampling valve is used to control the discharge of the gas in the first box.
5. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: The gas sampling device is an activated carbon sampling tube; the activated carbon sampling tube includes a solvent desorption type and a thermal desorption type.
6. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: Also includes: Multi-channel peristaltic pump; One end of the multi-channel peristaltic pump is connected to the water inlet pipe, and the other end of the multi-channel peristaltic pump is connected to the simulated wastewater tank.
7. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: Also includes: earth extractor; A plurality of soil-water sampling holes are arranged on the surface of the soil; and the soil sampler collects soil-water samples through the soil-water sampling holes.
8. The "field-phase" coupled transport simulation system for soil pollutants in petrochemical sites according to claim 1 is characterized in that: The third box is equipped with a conical flask or a measuring cylinder; The conical flask or the measuring cylinder is arranged below the drain pipe.