A waterproof construction equipment and process for house building project

By using the eccentric turntable and linkage mechanism of the waterproofing construction equipment for building projects, the problems of complex structure and safety hazards of high-altitude construction in existing equipment have been solved, and the effect of efficiently excavating annular grooves has been achieved.

CN116872367BActive Publication Date: 2026-01-09QINGDAO ELINK GRP INC CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310982451.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-04
Publication Date
2026-01-09
Estimated Expiration
2043-08-04

AI Technical Summary

Technical Problem

Existing construction equipment has a complex structure, is difficult to maintain, and poses safety hazards when working at heights, making it difficult to effectively excavate complex buildings.

Method used

A waterproofing construction device for building construction is adopted, which uses a stepper motor to drive a linkage mechanism to drive an eccentric turntable and drill rod, so as to realize the torsion and rotation of the eccentric rod and drill rod in a circular trajectory, to drill an annular groove, and then fixes it at a high position for construction through a clamping mechanism.

Benefits of technology

It enables efficient excavation of annular grooves on complex buildings, reducing the risk of equipment damage and improving construction safety and ease of use of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116872367B_ABST
    Figure CN116872367B_ABST
Patent Text Reader

Abstract

The application discloses a kind of house building engineering waterproof construction equipment and process, belong to construction equipment field, the device includes processing frame, the top of the processing frame is provided with plane axle seat, eccentric turntable is rotatably installed in the middle of the plane axle seat, eccentric turntable's axis and the axis of driving turntable coincide.The application is used, after the device is pushed to the side of building, and then the processing frame is erected, the stepping motor is rotated by connecting vertical rod at this time simultaneously driving first driving disc and second driving disc, the second driving disc is rotated by first output belt driving top turntable, driving turntable is rotated with top turntable, first driving disc is rotated by second output belt driving bottom turntable, eccentric turntable is rotated with bottom turntable, eccentric rod and its bottom drill rod are twisted around annular trajectory in the process of rotating.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of construction equipment, in particular to a waterproof construction equipment and process for house building project. BACKGROUND

[0002] With the development of industrial technology, modern construction equipment technology is developing more and more perfect, and professional equipment is needed to open a slot hole on the building. The structure of the previous opening equipment is relatively complex, and it is difficult to maintain if it is damaged during construction.

[0003] Secondly, the previous opening equipment is difficult to debug and difficult to construct complex buildings. If the position to be opened is relatively high, the opening equipment is lifted by the crane to construct, which has certain safety hazards. SUMMARY

[0004] The purpose of the present application is to provide a waterproof construction equipment and process for house building project. When the device is used, the device is pushed to the side of the building and the processing frame is erected. At this time, the stepping motor drives the first drive disc and the second drive disc to rotate through the connecting vertical rod. The second drive disc drives the top turntable to rotate through the first output belt. The drive turntable rotates with the top turntable. The first drive disc drives the bottom turntable to rotate through the second output belt. The eccentric turntable rotates with the bottom turntable. During the rotation of the eccentric turntable, the eccentric rod and the drill rod at the bottom end thereof twist around the annular track. At this time, the drive turntable drives the driven turntable to rotate through the pickling rod at the bottom end thereof. The driven turntable applies a rotating power to the eccentric rod. In turn, the drill rod rotates around the annular track at high speed. This can punch a ring-shaped slot in the wall, and the slot depth of the ring-shaped slot is two centimeters less than the wall thickness. Finally, the columnar waste is knocked down to solve the problems raised in the above background technology.

[0005] To achieve the above purpose, the present application provides the following technical scheme: a waterproof construction equipment and process for house building project, comprising a processing frame, the top end of the processing frame is provided with a plane shaft seat, and the bottom end of the processing frame is provided with a fixed plate, the middle of the plane shaft seat is rotatably installed with a drive turntable, the center of the fixed plate is rotatably installed with an eccentric turntable, the axis of the eccentric turntable coincides with the axis of the drive turntable, the middle of the eccentric turntable is provided with a shaft hole, the shaft hole deviates from the axis of the eccentric turntable, the shaft hole is rotatably installed with an eccentric rod, the bottom end of the eccentric rod is provided with a drill rod, the top end of the eccentric rod is provided with a driven turntable, the bottom end of the drive turntable is provided with six pickling rods arranged in a ring shape, the driven turntable is provided with a butt joint circular port matched with the pickling rod, the eccentric turntable and the drive turntable are connected to a linkage mechanism, and the processing frame is connected to a construction frame.

[0006] Further, the linkage mechanism comprises a stepping motor fixed on the side wall of the machining frame, a connecting vertical rod is installed on the output end of the stepping motor, a second driving disc is fixedly installed on the top end of the connecting vertical rod, a first driving disc is fixedly installed on the bottom end of the connecting vertical rod, the top end of the driving turntable is fixedly installed with a top turntable, the top turntable and the second driving disc are connected through a first output belt, the top end of the eccentric turntable is provided with a bottom turntable, and the bottom turntable and the first driving disc are connected through a second output belt.

[0007] Further, the diameters of the second driving disc and the top turntable are the same, and the diameters of the first driving disc and the bottom turntable are in a ratio of 1:3.

[0008] Further, the top end of the drill rod is provided with a threaded column, and the bottom end of the eccentric rod is provided with a threaded hole matched with the threaded column.

[0009] Further, the construction frame comprises a base box, four through holes are arranged on the top end of the base box, telescopic rods are slidingly installed in the four through holes, a lifting plate is fixedly installed on the top end of the telescopic rods, and a hinge is arranged on the edge of the lifting plate; the side wall of the machining frame is hingedly connected to the top surface of the lifting plate through the hinge; a pin rod assembly is further arranged between the machining frame and the hinge; a lifting mechanism is arranged between the lifting plate and the base box; four grounding rollers are arranged on the bottom end of the base box; and a cross column clamping mechanism is arranged in the middle of the base box.

[0010] Further, the pin rod assembly comprises a fixed tube on the side wall of the machining frame, and a tension hole is arranged on the top end of the lifting plate, and the tension hole and the fixed tube are connected through a fixed pin rod.

[0011] Further, the lifting mechanism comprises two electric push rods on the inner side wall of the base box, and the output rod of the electric push rod is fixedly connected to the bottom surface of the lifting plate.

[0012] Further, the cross column clamping mechanism comprises a rectangular clamping channel in the middle of the base box, two torsion shaft seats are arranged on the left and right outer side walls of the base box, a threaded rod is rotatably installed in the middle of the torsion shaft seat, a cross handle is arranged on the outward end of the threaded rod, a pressure bearing is arranged on the inward end of the threaded rod, the inner ring of the pressure bearing is fixedly connected to the threaded rod, and a locking plate is arranged on the outer ring of the pressure bearing.

[0013] Further, a plunger hole is arranged on the side wall of the locking plate, a rubber pad is arranged on the side wall of the locking plate, and a rubber plunger matched with the plunger hole is arranged on the rubber pad.

[0014] Further, the method comprises the following steps:

[0015] S1. After the device is pushed to the side of the building, the processing frame is erected, at this time the stepping motor drives the first drive disc and the second drive disc to rotate through the connecting stand, the second drive disc drives the top turntable to rotate through the first output belt, the driving turntable rotates with the top turntable, the first drive disc drives the bottom turntable to rotate through the second output belt, the eccentric turntable rotates with the bottom turntable, in the process of rotation, the eccentric rod and the drill rod at the bottom end thereof twist around the annular track, at this time the driving turntable drives the driven turntable to rotate through the pick rod at the bottom end thereof, the driven turntable applies a rotating power to the eccentric rod, and the drill rod also rotates at high speed around the annular track, which can punch an annular groove on the wall, the groove depth is two centimeters smaller than the wall thickness, and finally the columnar waste is knocked down by knocking;

[0016] S2. When the construction beam end is needed to be fixed, the processing frame is laid horizontally, the fixed pipe is inserted into the fixed pipe and the tension hole, and the rectangular clamping channel in the middle of the base box is installed at the end of the beam, the staff starts to twist the threaded rod until the four locking plates are pressed on the side wall of the beam, at this time the drill rod can be applied to work downward;

[0017] S3. The rubber pad on the side wall of the locking plate is replaced after a long time of use, and according to the specific situation of the construction building, a softer locking material such as sponge is added on the rubber pad.

[0018] In summary, due to the adoption of the above-mentioned technology, the beneficial effects of the present application are:

[0019] Firstly, when the device is used, the processing frame is erected after the device is pushed to the side of the building, at this time the stepping motor drives the first drive disc and the second drive disc to rotate through the connecting stand, the second drive disc drives the top turntable to rotate through the first output belt, the driving turntable rotates with the top turntable, the first drive disc drives the bottom turntable to rotate through the second output belt, the eccentric turntable rotates with the bottom turntable, in the process of rotation, the eccentric rod and the drill rod at the bottom end thereof twist around the annular track, at this time the driving turntable drives the driven turntable to rotate through the pick rod at the bottom end thereof, the driven turntable applies a rotating power to the eccentric rod, and the drill rod also rotates at high speed around the annular track, which can punch an annular groove on the wall, the groove depth is two centimeters smaller than the wall thickness, and finally the columnar waste is knocked down by knocking.

[0020] Second, when the construction beam top end needs to be put, the processing frame is placed horizontally, and then the fixed tube is inserted into the fixed tube and the tension hole. Then the rectangular clamping channel in the middle of the base box is installed at the end of the beam. The worker starts to twist the threaded rod until the four locking plates are pressed on the side wall of the beam. At this time, the drill rod can be applied downward.

[0021] Third, the rubber pad on the side wall of the locking plate is replaced after a long time of use. According to the specific situation of the construction building, a softer locking material such as sponge is added to the rubber pad. BRIEF DESCRIPTION OF DRAWINGS

[0022] Figure 1 is a schematic view of the front view of the present application.

[0023] Figure 2 is a schematic view of the side view of the present application.

[0024] Figure 3 is a schematic view of the hinge of the present application.

[0025] Figure 4 is a schematic view of the lifting plate of the present application.

[0026] Figure 5 is a schematic view of the processing frame of the present application.

[0027] Figure 6 is a schematic view of the eccentric turntable of the present application.

[0028] BRIEF DESCRIPTION OF DRAWINGS

[0029] Processing frame 1, grounding roller 101, flat shaft seat 2, driving turntable 201, pick rod 202, fixed plate 3, hinge 4, fixed tube 401, fixed pin 402, lifting plate 5, base box 6, electric push rod 7, telescopic rod 701, twist shaft seat 8, threaded rod 801, pressure bearing 802, locking plate 803, stepping motor 9, first driving disc 901, connecting vertical rod 902, second driving disc 903, first output belt 904, top turntable 905, second output belt 906, bottom turntable 907, driven turntable 10, drill rod 1001, eccentric rod 1002, eccentric turntable 11. DETAILED DESCRIPTION

[0030] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention. Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to represent selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0031] This invention provides, for example Figures 1-6 The waterproofing construction equipment for building construction shown includes a processing frame 1. A planar bearing 2 is provided at the top of the processing frame 1, and a fixing plate 3 is provided at the bottom of the processing frame 1. A drive turntable 201 is rotatably mounted in the middle of the planar bearing 2. An eccentric turntable 11 is rotatably mounted in the center of the fixing plate 3. The axis of the eccentric turntable 11 coincides with the axis of the drive turntable 201. A shaft hole is provided in the middle of the eccentric turntable 11, offset from the axis of the eccentric turntable 11. An eccentric rod 1002 is rotatably mounted in the shaft hole. A drill rod 1001 is provided at the bottom of the eccentric rod 1002. A driven turntable 10 is provided at the top of the eccentric rod 1002. A drive turntable 10 is provided at the bottom of the drive turntable 201. Six propelling rods 202 are arranged in a ring. The driven turntable 10 is provided with a matching docking port for the propelling rods 202. The eccentric turntable 11 and the driving turntable 201 are connected to the linkage mechanism. The processing frame 1 is connected to the construction frame. During the twisting process of the eccentric turntable 11, the eccentric rod 1002 and the drill rod 1001 at its bottom end will twist around the ring track. The driving turntable 201 drives the driven turntable 10 to rotate. The driven turntable 10 still maintains its rotation state when it moves in the horizontal plane. The driven turntable 10 applies rotational power to the drill rod 1001, realizing the effect of opening an annular groove. The groove depth is less than two centimeters of the wall thickness. Finally, the columnar waste is knocked down by hammering.

[0032] The linkage mechanism comprises a stepping motor 9 fixed on the side wall of the processing frame 1, a connecting vertical rod 902 is installed on the output end of the stepping motor 9, a second driving disc 903 is fixedly installed on the top end of the connecting vertical rod 902, a first driving disc 901 is fixedly installed on the bottom end of the connecting vertical rod 902, the top end of the driving turntable 201 is fixedly installed with a top turntable 905, the top turntable 905 and the second driving disc 903 are connected through a first output belt 904, the top end of the eccentric turntable 11 is provided with a bottom turntable 907, the bottom turntable 907 and the first driving disc 901 are connected through a second output belt 906, the stepping motor 9 drives the first driving disc 901 and the second driving disc 903 to rotate together through the connecting vertical rod 902, the second driving disc 903 drives the top turntable 905 to rotate through the first output belt 904, the driving turntable 201 rotates together with the top turntable 905, the first driving disc 901 drives the bottom turntable 907 to rotate through the second output belt 906, and the eccentric turntable 11 rotates together with the bottom turntable 907, and the eccentric rod 1002 and the drill rod 1001 at the bottom end thereof are twisted around the annular track to perform the construction work in the process of rotation.

[0033] The diameters of the second driving disc 903 and the top turntable 905 are the same, the diameters of the first driving disc 901 and the bottom turntable 907 are in the ratio of one to three, the self-rotation speed of the eccentric rod 1002 and the drill rod 1001 at the bottom end thereof is three times the torsion speed, and the drill rod 1001 can automatically drill a ring-shaped groove on the building.

[0034] The top end of the drill rod 1001 is provided with a threaded column, the bottom end of the eccentric rod 1002 is provided with a threaded hole matched with the threaded column, and the drill rod 1001 needs to be replaced after a long time, and the threaded column on the drill rod 1001 is screwed off by a handle to replace a new one.

[0035] The construction frame comprises a base box 6, four through holes are arranged at the top end of the base box 6, and telescopic rods 701 are slidingly installed in the four through holes, a lifting plate 5 is fixedly installed at the top end of the telescopic rod 701, and a clasp 4 is arranged at the edge of the lifting plate 5; the side wall of the processing frame 1 is hinged to the top surface of the lifting plate 5 through the clasp 4; a pin rod assembly is further arranged between the processing frame 1 and the clasp 4; a lifting mechanism is arranged between the lifting plate 5 and the base box 6; four grounding rollers 101 are arranged at the bottom end of the base box 6; and a cross column clamping mechanism is arranged in the middle of the base box 6; when the top end of the construction cross beam needs to be placed, the processing frame 1 is placed horizontally, so that the drill rod 1001 can be downwardly constructed, and the cross column clamping mechanism on the base box 6 loads the top end of the cross beam.

[0036] The pin rod assembly includes a fixed tube 401 on the side wall of the processing frame 1, the top end of the lifting plate 5 is provided with a tension hole, the tension hole and the fixed tube 401 are connected through a fixed pin rod 402, the fixed tube 401 is inserted into the fixed tube 401 and the tension hole, and the processing frame 1 and the base box 6 can be kept in a vertical state.

[0037] The lifting mechanism includes two electric push rods 7 on the inner side wall of the base box 6, the output rod of the electric push rod 7 is fixedly connected with the bottom surface of the lifting plate 5, and the two electric push rods 7 drive the base box 6 to lift, so that the construction height of the processing frame 1 is adjusted at a time.

[0038] The cross column clamping mechanism includes a rectangular clamping channel in the middle of the base box 6, two torsion shaft seats 8 are arranged on the left and right outer side walls of the base box 6, a threaded rod 801 is rotatably installed in the middle of the torsion shaft seat 8, a cross handle is arranged at the outward end of the threaded rod 801, a pressure bearing 802 is arranged at the inward end of the threaded rod 801, the inner ring of the pressure bearing 802 is fixedly connected with the threaded rod 801, a locking plate 803 is arranged on the outer ring of the pressure bearing 802, and workers start to twist the threaded rod 801 until the four locking plates 803 are pressed against the side walls of the cross beam, so that the device can be locked on the cross beam at a high position.

[0039] A plunger hole is arranged on the side wall of the locking plate 803, a rubber pad is arranged on the side wall of the locking plate 803, a rubber plunger matched with the plunger hole is arranged on the rubber pad, the rubber pad is torn off and replaced with a new one after a long time of use, and according to the specific conditions of the construction building, a softer locking material such as sponge is additionally arranged on the rubber pad.

[0040] The method comprises the following steps:

[0041] S1. After the device is pushed to the side of the building, the processing frame 1 is erected, at this time, the stepping motor 9 drives the first driving disc 901 and the second driving disc 903 to rotate at the same time through the connecting vertical rod 902, the second driving disc 903 drives the top rotating disc 905 to rotate through the first output belt 904, the driving rotating disc 201 rotates together with the top rotating disc 905, the first driving disc 901 drives the bottom rotating disc 907 to rotate through the second output belt 906, the eccentric rotating disc 11 rotates together with the bottom rotating disc 907, in the rotating process of the eccentric rotating disc 11, the eccentric rod 1002 and the drill rod 1001 at the bottom end thereof twist around the annular track, at this time, the driving rotating disc 201 drives the driven rotating disc 10 to rotate through the pick rod 202 at the bottom end thereof, the driven rotating disc 10 applies a rotating power to the eccentric rod 1002, and in turn, the drill rod 1001 rotates at a high speed while rotating around the annular track, so that an annular groove is punched on the wall, the groove depth of the annular groove is two centimeters smaller than the wall thickness, and finally, the columnar waste is knocked down.

[0042] S2. When the top of the construction beam needs to be put, the processing frame 1 is laid horizontally, the fixed pipe 401 is inserted into the fixed pipe 401 and the tension hole, the rectangular clamping channel in the middle of the base box 6 is installed at the end of the beam, the workers start to twist the threaded rod 801 until the four locking plates 803 are pressed on the side wall of the beam, at this time the drill rod 1001 can be used for work downward;

[0043] S3. The rubber pad on the side wall of the locking plate 803 is torn off and replaced after a long time of use, and according to the specific situation of the construction building, a softer locking material such as sponge is added on the rubber pad.

[0044] Working principle: in the process of twisting, the eccentric rod 1002 and the drill rod 1001 at the bottom end of the eccentric rod 1002 twist around the annular track, the driving disc 201 drives the driven disc 10 to rotate, the driven disc 10 keeps rotating when it moves in the horizontal plane, the driven disc 10 applies rotary power to the drill rod 1001, realizes the effect of opening the annular groove, the opening depth of the annular groove is two centimeters smaller than the wall thickness, and finally the columnar waste is knocked down, the stepping motor 9 drives the first driving disc 901 and the second driving disc 903 to rotate through the connecting vertical rod 902, the second driving disc 903 drives the top disc 905 to rotate through the first output belt 904, the driving disc 201 rotates with the top disc 905, the first driving disc 901 drives the bottom disc 907 to rotate through the second output belt 906, the eccentric disc 11 rotates with the bottom disc 907, in the process of rotation, the eccentric rod 1002 and the drill rod 1001 at the bottom end of the eccentric rod 1002 twist around the annular track to work, the speed of the eccentric rod 1002 and the drill rod 1001 at the bottom end of the eccentric rod 1002 is three times that of the twisting speed, the drill rod 1001 can drill a circular groove on the building, the drill rod 1001 needs to be replaced after a long time, the threaded column on the drill rod 1001 is twisted off with the handle to replace a new one, when the top of the construction beam needs to be put, the processing frame 1 is laid horizontally, the drill rod 1001 can be used for construction downward, the fixed pipe 401 is inserted into the fixed pipe 401 and the tension hole, the processing frame 1 and the base box 6 can be kept in a vertical state, the two electric push rods 7 drive the base box 6 to rise and fall, the construction height of the processing frame 1 is adjusted once, the workers start to twist the threaded rod 801 until the four locking plates 803 are pressed on the side wall of the beam, so that the device can be locked on the high beam, the rubber pad on the side wall of the locking plate 803 is torn off and replaced after a long time of use, and according to the specific situation of the construction building, a softer locking material such as sponge is added on the rubber pad.

[0045] The above merely provides the preferred embodiments of the present application, but the protection scope of the present application is not limited thereto, and any person skilled in the art, according to the technical scheme and the inventive concept of the present application, makes equivalent replacement or change within the technical range disclosed by the present application, should be covered within the protection scope of the present application.

[0046] It is to be noted that, in the present text, relational terms such as first and second and the like can merely be used to differentiate one entity or action from another, without necessarily requiring or implying any actual such relationship or order between or among the entities or actions. Also, the terms "comprises", "comprising", or any other variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but can include other elements not expressly listed or inherent to such process, method, article, or apparatus.

Claims

1. A waterproofing construction equipment for a housing construction work, characterized by: The utility model provides a kind of drilling machine, including processing frame (1), the top of the processing frame (1) is provided with plane axle seat (2), and the bottom of the processing frame (1) is provided with fixed plate (3), the middle rotation of the plane axle seat (2) is equipped with driving turntable (201), the center of the fixed plate (3) is rotationally installed with eccentric turntable (11), the axis of eccentric turntable (11) and the axis of driving turntable (201) coincide, the middle of the eccentric turntable (11) is provided with shaft hole, shaft hole deviates the axis of eccentric turntable (11), eccentric rod (1002) is rotationally installed in the shaft hole, the bottom of eccentric rod (1002) is provided with drill rod (1001), the top of the eccentric rod (1002) is provided with driven turntable (10), the bottom of the driving turntable (201) is provided with six picking rods (202) in annular arrangement, driven turntable (10) is provided with and picks up the butt joint round mouth of rod (202) matching, the eccentric turntable (11) and driving turntable (201) are connected to linkage mechanism, the processing frame (1) is connected to construction frame; Wherein: the linkage mechanism includes stepping motor (9) fixed on the side wall of processing frame (1), the output end of stepping motor (9) is installed with connecting vertical rod (902), the top of connecting vertical rod (902) is fixedly installed with second driving disc (903), the bottom of connecting vertical rod (902) is fixedly installed with first driving disc (901), the top of the driving turntable (201) is fixedly installed with top turntable (905), and top turntable (905) is connected between second driving disc (903) through first output belt (904), the top of the eccentric turntable (11) is provided with bottom turntable (907), and bottom turntable (907) is connected between first driving disc (901) through second output belt (906).

2. The waterproof construction equipment for house building project according to claim 1, characterized in that: The diameter of the second driving disc (903) and top turntable (905) is same, and the diameter ratio of the first driving disc (901) and bottom turntable (907) is one to three.

3. The waterproof construction equipment for house building project according to claim 1, characterized in that: The top of the drill rod (1001) is provided with threaded column, and the bottom of the eccentric rod (1002) is provided with threaded hole matched with the threaded column.

4. The waterproof construction equipment for house building project according to claim 1, characterized in that: The construction frame includes base box (6), the top of the base box (6) is provided with four perforations, four perforations are slidably installed with telescopic rod (701), the top of the telescopic rod (701) is fixedly installed with lifting plate (5), the edge of the lifting plate (5) is provided with hinge (4), and the side wall of the processing frame (1) is hinged through the top surface of the lifting plate (5) and the hinge (4), the processing frame (1) and the hinge (4) are further provided with pin rod assembly, the lifting mechanism is arranged between the lifting plate (5) and the base box (6), the bottom of the base box (6) is provided with four grounding rollers (101), and the middle of the base box (6) is provided with cross column clamping mechanism.

5. The waterproofing construction equipment for house building work according to claim 4, characterized in that: The pin rod assembly includes fixed tube (401) on the side wall of the processing frame (1), the top of the lifting plate (5) is provided with tension hole, and the fixed tube (401) is connected between the tension hole and the fixed pin rod (402).

6. The waterproofing construction equipment for house building work according to claim 4, characterized in that: The lifting mechanism comprises two electric push rods (7) on the inner side wall of the base box (6), and the output rod of the electric push rod (7) is fixedly connected with the bottom surface of the lifting plate (5).

7. The waterproofing construction equipment for house building work according to claim 5, characterized in that: The cross column clamping mechanism comprises a rectangular clamping channel in the middle of the base box (6), two torsion shaft seats (8) are arranged on the left and right outer side walls of the base box (6), a threaded rod (801) is rotatably installed in the middle of the torsion shaft seat (8), a cross handle is arranged on the outward end of the threaded rod (801), a pressure bearing (802) is arranged on the inward end of the threaded rod (801), the inner ring of the pressure bearing (802) is fixedly connected with the threaded rod (801), and a locking force plate (803) is arranged on the outer ring of the pressure bearing (802).

8. The waterproofing construction equipment for house building work according to claim 7, characterized in that: A plunger hole is arranged on the side wall of the locking force plate (803), a rubber pad is arranged on the side wall of the locking force plate (803), and a rubber plunger matched with the plunger hole is arranged on the rubber pad.

9. The process for waterproofing construction of a house building work according to claim 8, wherein The method comprises the following steps: S1. After the device is pushed to the side of the building, the processing frame (1) is erected, at this time the stepping motor (9) drives the first driving disc (901) and the second driving disc (903) to rotate through the connecting vertical rod (902), the second driving disc (903) drives the top rotating disc (905) to rotate through the first output belt (904), the driving rotating disc (201) rotates together with the top rotating disc (905), the first driving disc (901) drives the bottom rotating disc (907) to rotate through the second output belt (906), the eccentric rotating disc (11) rotates together with the bottom rotating disc (907), in the process of rotation, the eccentric rod (1002) and the drill rod (1001) at the bottom end thereof twist around the annular track, at this time the driving rotating disc (201) drives the driven rotating disc (10) to rotate through the pick rod (202) at the bottom end thereof, the driven rotating disc (10) applies a rotating power to the eccentric rod (1002), and then the drill rod (1001) rotates at a high speed while rotating around the annular track, so that a ring-shaped groove is punched on the wall, the groove depth is two centimeters smaller than the wall thickness, and finally the columnar waste is knocked down; S2. When the construction cross beam needs to be fixed, the processing frame (1) is placed horizontally, the fixed pipe (401) is inserted into the fixed pipe (401) and the tension hole, the rectangular clamping channel in the middle of the base box (6) is installed on the end of the cross beam, the staff starts to twist the threaded rod (801) until the four locking force plates (803) are pressed against the side wall of the cross beam, at this time the drill rod (1001) can apply work downward; S3. After the rubber pad on the side wall of the locking force plate (803) is used for a long time, the rubber pad is torn off and replaced with a new one, and according to the specific conditions of the construction building, sponge is additionally arranged on the rubber pad as a locking material.

Citation Information

Patent Citations

  • Anchorage engineering eccentric pipe-following drilling construction structure and construction method

    CN111764818A

  • Drilling support for constructional engineering

    CN112571635A