An integral installation tool for barrel foundation and an integral installation method

Through the overall installation tooling of lifting trusses, floating platform and connecting rigging, negative pressure sinking and drop technology is used to achieve efficient installation of the cylinder foundation, solving the problems of complex installation processes and high cost in offshore wind power projects, and reducing transportation and installation Cost, improve construction efficiency and safety.

CN117128140BActive Publication Date: 2024-11-12SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311127478.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-04
Publication Date
2024-11-12
Estimated Expiration
2043-09-04

AI Technical Summary

Technical Problem

In existing offshore wind power projects, the installation process of the cylinder foundation is complex and costly, and depends on sea conditions, which affects construction efficiency and cost.

Method used

The integrated installation tooling of hoisted trusses, floating platform and connecting rigging is adopted to realize the integrated installation of the cylinder foundation through negative pressure sinking technology, reduce offshore construction processes and ship dispatch, and use the self-floating capacity of the floating platform for overall transportation. .

Benefits of technology

It reduces the transportation and installation costs of cylinder foundations, reduces the dependence of construction interfaces and sea conditions, improves construction efficiency and safety, and makes large-scale development of offshore wind farms possible.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117128140B_ABST
    Figure CN117128140B_ABST
Patent Text Reader

Abstract

The present invention relates to an integral installation tool for a barrel foundation, comprising a lifting truss, a floating platform and connecting rigging, wherein the lifting truss is spliced ​​by two sub-trusses, and the center position is spliced ​​into an axially through-going installation hole, an annular clamp assembly is spliced ​​at the installation hole position, a wind turbine is inserted into the installation hole, and the clamp assembly is annularly abutted and fixed with the outer wall of the wind turbine tower, the floating platform is a pontoon structure with a hollow interior and an open top, and the bottom side walls of the floating platform are filled with ballast water, a fixed base is provided at the inner bottom of the floating platform, an annular storage space with an adjustable diameter is provided on the fixed base, the barrel foundation of the wind turbine is axially accommodated in the annular storage space, one end of a plurality of connecting riggings are all arranged on the lifting truss, and the other end is respectively connected to the barrel foundation and the floating platform in a taut state. The installation tool can effectively transport the barrel foundation wind turbine as a whole, and reduce its transportation and installation costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of barrel foundations, and in particular to an integral installation tool for barrel foundations and an integral installation method for barrel foundations using the installation tool. Background Art

[0002] In the offshore wind power projects that have been built at home and abroad, the wind turbine foundation structure is mainly composed of monopile foundation and jacket foundation. The operation method mainly uses a large crane ship to complete the foundation construction of the wind turbine unit at sea, and then the wind turbine is hoisted and installed by the outrigger platform installation ship. Finally, the transport ship transports the parts to the construction location at sea, and the parts are installed in sections to complete the whole machine commissioning. This operation method is not only difficult to locate, complex in construction, and low in installation efficiency, but also requires many ships and machines for construction and installation, and the cost is high. It is also extremely dependent on sea conditions. If there is no continuous good sea condition window period, the construction work will be seriously disturbed, the project will face the impact of delayed construction period, and indirectly increase the construction cost. Since the cost of wind turbine foundation engineering and installation accounts for about 40% of the total investment in offshore wind farm construction projects, if the cost of wind turbine foundation is too high, it will seriously affect the large-scale development of offshore wind farms.

[0003] At present, my country's large-capacity wind turbines have achieved rapid development, and the 10MW+ models among large-capacity wind turbines can effectively reduce the cost of sea expropriation, foundation cost, construction hoisting, and submarine cable laying, and other investment costs, thus becoming the mainstream model in the wind power market. Nowadays, as the scope of use of barrel foundations becomes wider and wider, the size of the supporting barrel foundations is also getting larger while the capacity of wind turbines is increasing, and the diameter of the barrel foundation is often more than 45m. However, construction ships suitable for the overall transportation of large barrel foundations are relatively scarce in the market, and the on-site installation construction process of wind turbines is complicated, and there are certain difficulties in installation technology. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides an integral installation tool for a cylindrical foundation, which can effectively transport the cylindrical foundation wind turbine unit as a whole and reduce the transportation and installation costs thereof.

[0005] The present invention adopts the following technical solution:

[0006] The present invention provides an integral installation tool for a barrel-type foundation, comprising a lifting truss, a floating platform and connecting rigging, wherein the lifting truss is formed by splicing two sub-trusses, and the center position of the lifting truss is spliced ​​to form an axially through-going installation hole, and an annular clamp assembly is spliced ​​at the installation hole position, a wind turbine set is inserted into the installation hole, and the clamp assembly is annularly abutted and fixed to the outer wall of the upper tower of the wind turbine set, the floating platform is a pontoon structure with a hollow interior and an open top, and the bottom side walls of the floating platform are filled with ballast water, a fixed base is provided at the inner bottom of the floating platform, and an annular storage space with adjustable diameter is provided on the fixed base, the barrel-type foundation at the bottom of the wind turbine set is axially accommodated in the annular storage space, one end of a plurality of connecting riggings are all provided on the lifting truss, and the other end of each connecting rigging is respectively connected to the barrel-type foundation and the floating platform in a taut state.

[0007] Preferably, the clamp assembly includes a hoop and an abutment member, the hoop is fixed at the position of the mounting hole, a plurality of abutment members are circumferentially equidistantly arranged on the hoop, and a guide wheel at the end of the abutment member abuts against the tower.

[0008] Preferably, the fixed base includes a M-shaped bottom plate and a sliding block. The M-shaped bottom plate is laid flat on the inner bottom of the floating platform, and the eight protruding ends of the M-shaped bottom plate are respectively provided with strip slide grooves extending along the direction of the protruding ends at the top. The sliding block can be slidably arranged along the strip slide grooves and is correspondingly arranged at the top of the protruding ends of the M-shaped bottom plate. A limiting bolt is screwed on the sliding block to fix the sliding block to the M-shaped bottom plate.

[0009] Preferably, a double-opening automatic door is provided on one side of the floating platform.

[0010] The present invention also provides a method for integrally installing a barrel foundation, which uses the above-mentioned integrally installing tooling for the barrel foundation and comprises the following steps:

[0011] S1: Connect the integral installation tooling of the barrel foundation and the wind turbine generator set into an integral structure;

[0012] S2: The whole structure is towed out from the shipping dock by a tugboat and floated to the target position. After the connection between the lifting truss and the floating platform in the whole structure is released, the lifting truss is lifted by a crane ship to separate the barrel foundation at the bottom of the wind turbine from the floating platform, and the floating platform is towed away from under the wind turbine by a tugboat;

[0013] S3: Then, the barrel foundation at the bottom of the wind turbine is connected to the air compressor on the construction ship, and the continuous negative pressure suction of the air compressor and the slow lowering of the crane ship are controlled at the same time, until the barrel foundation at the bottom of the wind turbine penetrates into the seabed mud surface to the specified design depth;

[0014] S4: Release the connection between the lifting truss and the barrel foundation, and split the lifting truss into two sub-trusses. The two sub-trusses are then lifted off by the crane ship and placed on the transport ship.

[0015] Preferably, step S1 specifically includes:

[0016] S11: hoist the barrel foundation into the annular storage space of the fixed base on the floating platform at the front of the pier or in the dock, and fix it;

[0017] S12: Install the tower, nacelle, hub and blades of the wind turbine set onto the cylindrical foundation step by step to form a complete wind turbine set;

[0018] S13: splicing two sub-truss group pairs to form a hoisting truss mounted on the wind turbine generator set, and fixing the truss with the outer wall of the upper tower of the wind turbine generator set in an annular manner through a hoop assembly;

[0019] S14: one end of each of the plurality of connecting riggings is arranged on the hoisting truss, and the other end of each of the connecting riggings is respectively connected to the barrel foundation and the floating platform in a taut state.

[0020] Preferably, in step S2, when the tugboat floats the entire structure to the target position, the barrel foundation adjusts the draft through the floating platform and its own pumping system, and cooperates with the tugboat to assist in controlling the overall movement posture of the wind turbine.

[0021] Preferably, in step S2, if the height of the lifting truss lifted by the crane ship is low, the double-leaf automatic door on one side of the floating platform is opened, and the floating platform is towed away from the wind turbine generator set from the position of the double-leaf automatic door by a tugboat, and then the double-leaf automatic door is closed.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] The overall installation tooling of the cylindrical foundation of the present invention can be connected to the wind turbine set as a whole through the lifting truss, the floating platform and the connecting rigging, and the wind turbine set can be floated by relying on the self-floating ability of the floating platform, so that the integrated structure of the lifting truss, the floating platform, the connecting rigging and the wind turbine set can be pulled by an external ship, so that the cylindrical foundation wind turbine set can be transported as a whole, without the need to specially dispatch transport ships to transport parts to the construction location at sea for partial construction and installation, thereby reducing the transportation and installation costs of the wind turbine set.

[0024] The overall installation method of the cylindrical foundation of the present invention adopts the overall installation tooling of the cylindrical foundation and utilizes the negative pressure sinking method to realize the integrated installation of the cylindrical foundation wind turbine unit. This installation method has fewer offshore construction processes, so fewer large ships need to be dispatched for the operation, fewer construction interfaces, less dependence on sea conditions, and a long available operation window period, which greatly reduces the risk of maritime navigation safety management and minimizes the risk of offshore construction safety, thereby greatly reducing the production, transportation and installation costs, making efficient, low-cost, and large-scale development of offshore wind farms possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of a first usage state of an integral installation tool for a barrel foundation in an embodiment of the present invention.

[0026] Figure 2 It is a schematic diagram of a second usage state of the overall installation tooling of the barrel foundation in an embodiment of the present invention.

[0027] Figure 3 It is a structural schematic diagram of a hoisting truss on an integral installation tooling of a barrel foundation in an embodiment of the present invention.

[0028] Figure 4 It is a structural schematic diagram of a floating platform on an integral installation tool of a barrel foundation in an embodiment of the present invention.

[0029] Figure 5 It is an enlarged view of the details of the slider portion of the fixed base on the overall installation tooling of the barrel foundation in an embodiment of the present invention.

[0030] The reference numerals are described as follows:

[0031] 1. Lifting truss 63, guide wheel

[0032] 2. Floating platform 7. Wind turbine

[0033] 21. Binding clamp 71. Tower

[0034] 22. Double-leaf automatic door 72. Cylindrical foundation

[0035] 3. Connect the rigging 8. Fix the base

[0036] 4. Sub-truss 81, M-shaped bottom plate

[0037] 5. Mounting hole 82, slider

[0038] 6. Hoop assembly 83, strip slide

[0039] 61, hoop 84, limit bolt

[0040] 62. Abutment DETAILED DESCRIPTION

[0041] The specific embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. These embodiments are only used to illustrate the present invention, but not to limit the present invention.

[0042] In the description of the present invention, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0043] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0044] Furthermore, in the description of the present invention, unless otherwise specified, “plurality” means two or more.

[0045] See also Figures 1 to 4 The present embodiment provides an integral installation tool for a barrel foundation, comprising a lifting truss 1, a floating platform 2 and a connecting rigging 3. The lifting truss 1 is formed by splicing two sub-trusses 4. The central position of the lifting truss 1 is spliced ​​to form an axially penetrating mounting hole 5. An annular clamp assembly 6 is spliced ​​at the mounting hole 5. The wind turbine 7 is inserted into the mounting hole 5, and the clamp assembly 6 is circumferentially abutted and fixed to the outer wall of the upper tower 71 of the wind turbine 7. The floating platform 2 is a buoy structure with a hollow interior and an open top, and the bottom side walls of the floating platform 2 are filled with ballast water. A fixed base 8 is provided at the inner bottom of the floating platform 2, and an annular storage space with an adjustable diameter is provided on the fixed base 8. The barrel foundation 72 at the bottom of the wind turbine 7 is axially accommodated in the annular storage space. One end of each of the connecting rigging 3 is provided on the lifting truss 1, and the other end of each of the connecting rigging 3 is respectively connected to the barrel foundation 72 and the floating platform 2 in a taut state.

[0046] The overall installation tooling of the cylindrical foundation of the present embodiment can be connected as a whole with the wind turbine set 7 through the lifting truss 1, the floating platform 2 and the connecting rigging 3, and the wind turbine set 7 can be floated by relying on the self-floating ability of the floating platform 2, so that the integrated structure of the lifting truss 1, the floating platform 2, the connecting rigging 3 and the wind turbine set 7 can be pulled by an external ship to realize the transportation of the cylindrical foundation wind turbine set as a whole, without the need to specially dispatch transport ships to transport parts to the construction location at sea for partial construction and installation, thereby reducing the transportation and installation costs of the wind turbine set 7.

[0047] Preferably, see Figure 3 In this embodiment, the hoisting truss 1 formed by splicing two sub-trusses 4 is a regular hexagonal steel truss structure.

[0048] Specifically, in this embodiment, a plurality of lifting ears are respectively arranged at intervals on the two sub-trusses 4. When the overall installation tooling of the cylindrical foundation of this embodiment is used to install and construct the cylindrical foundation 72, the crane ship can lift the lifting truss 1 by connecting the lifting ears on the two sub-trusses 4.

[0049] Furthermore, in this embodiment, the two sub-trusses 4 are connected and fixed by bolts.

[0050] Preferably, in this embodiment, the connecting rigging 3 includes a steel wire rope, a tensioning ratchet and a shackle, and corresponding fastening points are arranged on the lifting truss 1, the floating platform 2 and the barrel foundation 72. One end of a part of the steel wire rope is connected to the fastening point on the lifting truss 1 through a shackle, and the other end is connected to the fastening point on the barrel foundation 72 through a shackle; one end of the other part of the steel wire rope is connected to the fastening point on the lifting truss 1 through a shackle, and the other end is connected to the fastening point on the floating platform 2 through a shackle, and the ends of the steel wire rope are locked by the tensioning ratchet, so that the lifting truss 1, the barrel foundation 72 and the floating platform 2 form a tightly connected whole.

[0051] Specifically, see Figure 4 In this embodiment, the fastening point on the lifting truss 1 is the frame of the lifting truss 1, the fastening point of the floating platform 2 is the lashing clamp 21 set on the floating platform 2, and the fastening point of the barrel foundation 72 is the lifting ear set on the top of the barrel foundation 72.

[0052] Preferably, see Figure 3 The hoop assembly 6 includes a hoop ring 61 and abutment 62. The hoop ring 61 is fixed at the position of the mounting hole 5. A plurality of abutment 62 are circumferentially arranged at equal intervals on the hoop ring 61. A guide wheel 63 at the end of the abutment 62 abuts against the tower 71. The guide wheel 63 is arranged to stabilize the wind turbine 7.

[0053] Preferably, see Figure 4 and Figure 5 The fixed base 8 includes a crisscross bottom plate 81 and a slider 82. The crisscross bottom plate 81 is laid flat on the inner bottom of the floating platform 2, and the eight outwardly extending ends of the crisscross bottom plate 81 are respectively provided with strip-shaped slide grooves 83 extending along the outwardly extending ends at the top. The slider 82 can be slidably arranged along the strip-shaped slide grooves 83 corresponding to the top of the outwardly extending ends of the crisscross bottom plate 81. The slider 82 is screwed with a limit bolt 84 for fixing the slider 82 on the crisscross bottom plate 81. This design form of the fixed base 8 allows the fixed base 8 to be fixedly connected to the barrel foundation 72 of different diameters by moving the setting position of the slider 82.

[0054] Preferably, see Figure 4 A double-opening automatic door 22 is provided on one side of the floating platform 2 to facilitate entry and exit of the barrel foundation 72.

[0055] This embodiment also provides a method for installing a barrel foundation as a whole, using the barrel foundation installation tool as described above, and including the following steps: Figure 1 and Figure 2 :

[0056] S1: Connecting the integral installation tooling of the barrel foundation and the wind turbine generator set 7 into an integral structure;

[0057] S2: The whole structure is towed out from the shipping dock by a tugboat and floated to the target position. After the connection of the connecting rigging 3 between the hoisting truss 1 and the floating platform 2 in the whole structure is released, the hoisting truss 1 is lifted by a crane ship to separate the barrel foundation 72 at the bottom of the wind turbine 7 from the floating platform 2, and the floating platform 2 is towed away from under the wind turbine 7 by a tugboat;

[0058] S3: Then, the cylindrical foundation 72 at the bottom of the wind turbine 7 is connected to the air compressor on the construction vessel, and the continuous negative pressure suction of the air compressor and the slow lowering of the crane vessel are controlled at the same time, until the cylindrical foundation 72 at the bottom of the wind turbine 7 penetrates into the seabed mud surface to the specified design depth;

[0059] S4: Release the connection between the connecting rigging 3 between the hoisting truss 1 and the barrel foundation 72, and split the hoisting truss 1 into two sub-trusses 4, and then use the crane ship to lift the two sub-trusses 4 and place them on the transport ship.

[0060] The overall installation method of the barrel foundation of this embodiment adopts the overall installation tooling of the barrel foundation and realizes the integrated installation of the barrel foundation wind turbine by negative pressure sinking. This installation method has fewer offshore construction processes, fewer large ships to be dispatched, fewer construction interfaces, less dependence on sea conditions, and a long available operation window, which greatly reduces the risk of maritime navigation safety management and minimizes the safety risk of offshore construction, thereby greatly reducing the production, transportation and installation costs, making it possible to develop offshore wind farms efficiently, at low cost, and on a large scale. In addition, the two sub-trusses 4 can be recycled after being placed on the transport ship.

[0061] It should be noted that after the wind turbine set 7 and the integral installation tooling of the barrel foundation are connected into an integral structure in step S1, the wind turbine set 7 is debugged, and the filling amount of ballast water in the bottom side wall of the floating platform 2 is adjusted so that the floating platform 2 still has the self-floating ability when supporting the wind turbine set 7. After the overall structure has the self-floating ability, the overall structure is connected to the tugboat by a tow rope, and the tugboat tows the overall structure away from the shipping terminal.

[0062] Preferably, in this embodiment, in step S4 , a diver goes into the water to release the connection between the connecting rigging 3 between the hoisting truss 1 and the barrel foundation 72 , and removes the bolts on the hoisting truss 1 , so that the hoisting truss 1 is split into two sub-trusses 4 .

[0063] Preferably, step S1 specifically includes:

[0064] S11: hoisting the barrel foundation 72 into the annular storage space of the fixed base 8 on the floating platform 2 at the front of the pier or in the dock, and fixing it;

[0065] S12: installing the tower 71, the nacelle, the hub and the blades of the wind turbine set step by step onto the cylindrical foundation 72 to form a complete wind turbine set 7;

[0066] S13: splicing two sub-truss groups 4 to form a hoisting truss 1 mounted on the wind turbine 7, and fixing the truss 1 to the outer wall of the upper tower 71 of the wind turbine 7 in an annular manner through a hoop assembly 6;

[0067] S14: one end of each of the plurality of connecting riggings 3 is disposed on the hoisting truss 1, and the other end of each of the connecting riggings 3 is connected to the barrel foundation 72 and the floating platform 2 in a taut state.

[0068] Preferably, in step S2, when the tugboat floats the entire structure to the target position, the barrel foundation 72 adjusts the draft through the floating platform 2 and its own pumping system, and cooperates with the tugboat to assist in controlling the overall movement posture of the wind turbine 7.

[0069] It should be noted that if the overall installation tooling of the cylindrical foundation and the wind turbine set 7 are connected as an integral structure in the dock, then after the wind turbine set 7 is debugged, the dock gate is opened to release water, and as the water level in the dock rises, the floating platform 2 gradually has the ability to float on its own; after the wind turbine set 7 and the floating platform 2 are in a floating state, the tugboat is connected to the wind turbine set 7 through a tow rope, and the wind turbine set 7 is towed away from the dock by the tugboat; after the undocking is completed, the auxiliary tugboat is tied to the floating platform 2 through a cable to assist in controlling the movement posture of the wind turbine set 7 during floating, and the tugboat slowly tows the wind turbine set 7 to the target position.

[0070] Preferably, in step S2, if the height of the lifting truss 1 lifted by the crane ship is relatively low, the double-leaf automatic door 22 on one side of the floating platform 2 is opened, and then the floating platform 2 is towed away from the wind turbine 7 from the position of the double-leaf automatic door 22 by a tugboat, and then the double-leaf automatic door 22 is closed.

[0071] Specifically, in this embodiment, the amount of ballast water filled in the bottom side wall of the floating platform 2 is adjusted first to make the floating platform 2 drop to a certain height, then the double-leaf automatic door 22 on one side of the floating platform 2 is opened, and the floating platform 2 is towed away from the wind turbine 7 from the position of the double-leaf automatic door 22 by a tugboat.

[0072] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.

Claims

1. An overall installation method for a barrel foundation. It is characterized in that An integral installation tool using a barrel foundation is provided, the integral installation tool comprising a lifting truss (1), a floating platform (2) and a connecting rigging (3), the lifting truss (1) being formed by splicing two sub-trusses (4), the central position of the lifting truss (1) being spliced ​​to form an axially through-going installation hole (5), the installation hole (5) being spliced ​​with an annular clamp assembly (6), the wind turbine generator set (7) being inserted into the installation hole (5), and the clamp assembly (6) being annularly abutted and fixed to the outer wall of the upper tower (71) of the wind turbine generator set (7), the floating platform (2) being a pontoon structure having a hollow interior and an open top, and the The bottom and side walls of the floating platform (2) are filled with ballast water, the inner bottom of the floating platform (2) is provided with a fixed base (8), the fixed base (8) is provided with an annular storage space with adjustable diameter, the cylindrical foundation (72) at the bottom of the wind turbine (7) is axially accommodated in the annular storage space, one end of a plurality of connecting rigging (3) is provided on the hoisting truss (1), and the other end of each connecting rigging (3) is respectively connected to the cylindrical foundation (72) and the floating platform (2) in a taut state, a double-leaf automatic door (22) is provided on one side of the floating platform (2), and the following steps are included: S1: connecting the integral installation tool of the barrel foundation and the wind turbine generator set (7) into an integral structure; S2: The overall structure is towed out from the shipping dock by a tugboat and floated to the target position. After the connection between the connecting rigging (3) between the hoisting truss (1) and the floating platform (2) in the overall structure is released, the hoisting truss (1) is lifted by a crane ship to separate the barrel foundation (72) at the bottom of the wind turbine (7) from the floating platform (2), and the floating platform (2) is towed away from below the wind turbine (7) by a tugboat; S3: Then, the barrel-shaped foundation (72) at the bottom of the wind turbine generator set (7) is connected to the air compressor on the construction vessel, and the continuous negative pressure suction of the air compressor and the slow lowering of the crane vessel are controlled to be performed simultaneously, until the barrel-shaped foundation (72) at the bottom of the wind turbine generator set (7) penetrates into the seabed mud surface to a specified design depth; S4: releasing the connection between the connecting rigging (3) of the lifting truss (1) and the barrel foundation (72), and splitting the lifting truss (1) into two sub-trusses (4); and then lifting the two sub-trusses (4) by a crane ship and placing them on a transport ship.

2. The overall installation method of the barrel foundation according to claim 1, It is characterized in that In the integral installation tool of the barrel foundation, the clamp assembly (6) comprises a clamp ring (61) and an abutment member (62); the clamp ring (61) is fixed at the position of the installation hole (5); a plurality of abutment members (62) are circumferentially arranged at equal intervals on the clamp ring (61); and a guide wheel (63) at the end of the abutment member (62) abuts against the tower (71).

3. The overall installation method of the barrel foundation according to claim 1, It is characterized in that In the overall installation tooling of the barrel foundation, the fixed base (8) comprises a cross-shaped bottom plate (81) and a slider (82); the cross-shaped bottom plate (81) is laid flat on the inner bottom of the floating platform (2); and the eight extended ends of the cross-shaped bottom plate (81) are respectively provided with strip slide grooves (83) extending along the extended end direction at the top; the slider (82) can be slidably arranged along the strip slide grooves (83) corresponding to the top of the extended end of the cross-shaped bottom plate (81); and the slider (82) is screwed with a limit bolt (84) for fixing the slider (82) on the cross-shaped bottom plate (81).

4. The overall installation method of the barrel foundation according to claim 1, It is characterized in that Step S1 is specifically as follows: S11: hoisting the barrel foundation (72) into the annular storage space of the fixed base (8) on the floating platform (2) at the front of the pier or in the dock, and fixing it; S12: installing the tower (71), the nacelle, the hub, and the blades of the wind turbine generator set step by step onto the cylindrical foundation (72) to form a complete wind turbine generator set (7); S13: splicing two sub-trusses (4) in pairs to form a hoisting truss (1) sleeved on the wind turbine generator set (7), and fixing the truss in an annular manner to the outer wall of the upper tower (71) of the wind turbine generator set (7) via a hoop assembly (6); S14: one end of each of the plurality of connecting riggings (3) is arranged on the hoisting truss (1), and the other end of each of the connecting riggings (3) is connected to the barrel foundation (72) and the floating platform (2) in a taut state.

5. The overall installation method of the barrel foundation according to claim 1, It is characterized in that In step S2, while the tugboat is floating the entire structure to the target position, the barrel foundation (72) adjusts its draft through the floating platform (2) and its own pumping system, and cooperates with the tugboat to assist in controlling the overall movement posture of the wind turbine set (7).

6. The overall installation method of the barrel foundation according to claim 1, It is characterized in that In step S2, if the height at which the lifting truss (1) is lifted by the crane ship is relatively low, the split automatic door (22) on one side of the floating platform (2) is opened, and the floating platform (2) is then towed away from the wind turbine generator set (7) from the position of the split automatic door (22) by a tugboat, and then the split automatic door (22) is closed.