Automated installation device for concrete pipes used for stormwater and sewage

By designing an automated installation device, and utilizing the combination of support frames, hydraulic drive systems, and electric drive systems, the problems of missing edges and corners and loose splicing in reinforced concrete pipe installation were solved, achieving high-quality sewage pipe installation and avoiding leakage.

CN117248604BActive Publication Date: 2026-01-30CHINA 19TH METALLURGICAL CORP CHENGDU CONSTR +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311213566.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-19
Publication Date
2026-01-30
Estimated Expiration
2043-09-19

AI Technical Summary

Technical Problem

In existing technologies, reinforced concrete socket pipes are prone to problems such as missing edges and corners at the joints and poor splicing during the installation of sewage pipes, leading to frequent leakage. The lack of specialized installation equipment makes it difficult to guarantee the installation quality.

Method used

Design an automated installation device, including a support frame, a hydraulic drive system, an electric drive system, and a mobile positioning installation structure. The device can be detachably fixed to the concrete pipe via the hydraulic drive system. In conjunction with the electric drive system and the mobile positioning installation structure, it can accurately lift the pipe and install it according to the specified requirements, ensuring a tight joint.

Benefits of technology

It effectively reduces the risk of chipped edges and corners caused by collisions and manual prying during installation, ensuring installation quality, minimizing sewage pipe leakage, and improving installation accuracy and tightness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117248604B_ABST
    Figure CN117248604B_ABST
Patent Text Reader

Abstract

This invention discloses an automated installation device, specifically an automated installation device for stormwater and sewage concrete pipes, belonging to the field of pipeline installation engineering installation process equipment design and manufacturing technology. It provides an automated installation device for stormwater and sewage concrete pipes that can effectively improve installation quality and reduce problems such as chipped edges, loose joints, and other defects during installation. The automated installation device includes a support frame, a hydraulic drive system, an electric drive system, and a moving positioning installation structure. All three systems are arranged on the support frame. During the installation of the stormwater and sewage concrete pipes, the support frame is detachably fixed to the installed stormwater and sewage concrete pipes via the hydraulic drive system. Adjacent stormwater and sewage concrete pipes requiring installation are lifted and installed in place according to specified requirements by the moving positioning installation structure in cooperation with the hydraulic drive system, the electric drive system, and the support frame.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to an automated installation device, and more particularly to an automated installation device for rainwater and sewage concrete pipes, belonging to the field of design and manufacturing technology of pipeline installation engineering equipment. Background Technology

[0002] With social development, a large number of rural residents are migrating to cities. The construction of supporting facilities such as urban sewage treatment facilities is lagging behind the growth of the urban population. my country attaches great importance to the construction and management of urban sewage pipe networks, as sewage treatment is a major issue for improving urban development. Sewage treatment requires a complete sewage pipe network. Currently, most sewage pipe networks use reinforced concrete socket pipes during construction. These reinforced concrete socket pipes are prone to problems during construction, leading to sewage pipe leaks. The main reason for these leaks is the lack of suitable installation equipment. Therefore, construction workers often use loaders or excavators to install pipes. Because these are not specialized installation equipment, problems such as chipped edges and loose connections at pipe joints are easily caused, leading to leaks during operation. Summary of the Invention

[0003] The technical problem to be solved by the present invention is to provide an automated installation device for rainwater and sewage concrete pipes that can effectively improve installation quality and reduce problems such as missing edges and corners, and loose splicing of pipe joints during the installation process.

[0004] The technical solution adopted to solve the above-mentioned technical problems is: an automated installation device for rainwater and sewage concrete pipes. The automated installation device includes a support frame, a hydraulic drive system, an electric drive system, and a moving positioning installation structure. The hydraulic drive system, the electric drive system, and the moving positioning installation structure are all arranged on the support frame. During the installation of rainwater and sewage concrete pipes, the support frame is detachably fixed to the installed rainwater and sewage concrete pipes through the hydraulic drive system. Adjacent rainwater and sewage concrete pipes that need to be installed are lifted and installed in place according to the specified requirements through the moving positioning installation structure in cooperation with the hydraulic drive system, the electric drive system, and the support frame.

[0005] Furthermore, the support frame includes a main support frame, a front mounting bracket, and a rear balancing bracket. The front mounting bracket and the rear balancing bracket are movably connected to the front and rear ends of the main support frame, respectively, via an electric drive system that allows for reciprocating movement along the length direction. During the installation of stormwater and sewage concrete pipes, the main support frame is detachably fixed to the installed stormwater and sewage concrete pipes via a hydraulic drive system. Adjacent stormwater and sewage concrete pipes that need to be installed are lifted and installed in place according to regulations through a movable positioning installation structure in cooperation with the hydraulic drive system, the front mounting bracket, and the rear balancing bracket. The support frame moves forward along the installation direction via an electric drive system.

[0006] The preferred embodiment of the above scheme is that the main support frame includes two portal-shaped support skeletons, a top mounting platform, and a set of clamping mechanisms. The two portal-shaped support skeletons are connected as a whole through a top mounting platform. The clamping mechanisms are movably arranged inside the two portal-shaped support skeletons. The front mounting bracket and the rear balancing bracket are each composed of a portal-shaped support skeleton. The front mounting bracket and the rear balancing bracket are movably connected to the top mounting platform through an electric drive system. During the installation of the rainwater and sewage concrete pipes, the main support frame can be tightly wrapped around the installed rainwater and sewage concrete pipes through the clamping mechanisms in cooperation with the hydraulic drive system. The rainwater and sewage concrete pipes to be installed are lifted by the movable positioning installation structure arranged on the clamping mechanism and the front mounting bracket and installed in place according to the specified requirements.

[0007] Furthermore, a set of telescopic cylinders of a hydraulic drive system is respectively installed at the lower end of the two vertical sides of each portal support frame. During the movement of the support frame, each telescopic cylinder alternately extends and retracts. The clamping mechanism includes a fixed clamping ring section and a movable clamping ring section group. The fixed clamping ring section is fixedly installed on the horizontal side of the two sets of portal support frames connected as a whole. The movable clamping ring section group, which is hinged to the free end of the fixed clamping ring section, is movably connected to the vertical side of the two sets of portal support frames connected as a whole through telescopic cylinders.

[0008] The preferred embodiment of the above scheme is that the mobile positioning installation structure includes a positioning adjustment component group and a mobile installation component group. The positioning adjustment component group is movably arranged on the front mounting bracket via a telescopic hydraulic cylinder, and the fixed end of the mobile installation component group is arranged on the movable clamping ring section group of the clamping mechanism via a telescopic hydraulic cylinder. During the installation of rainwater and sewage concrete pipes, the coaxiality of the rainwater and sewage concrete pipes to be installed with the already installed rainwater and sewage concrete pipes is adjusted by the positioning adjustment component group with the cooperation of the telescopic hydraulic cylinder. The adjusted rainwater and sewage concrete pipes are then moved and installed into place by the mobile installation component group with the cooperation of the telescopic hydraulic cylinder.

[0009] Furthermore, the positioning adjustment assembly includes three sets of positioning sleeves and three positioning rods. Each set of positioning sleeves is provided with a plug hole. The three positioning rods are detachably fixed to the three sets of positioning sleeves through the three plug holes. At least one set of positioning sleeves is installed in the middle of the two vertical sides of the front mounting bracket through two sets of telescopic hydraulic cylinders.

[0010] The preferred embodiment of the above scheme is that the movable installation assembly includes three sets of fastening moving steel ropes and three sets of connecting hooks. A set of connecting hooks is fixedly installed at the free end of each set of fastening moving steel ropes. The three sets of fastening moving steel ropes are respectively arranged on the clamping mechanism through three sets of telescopic hydraulic cylinders and three sets of positioning sleeves.

[0011] Furthermore, the electric drive system includes a drive motor, a power transmission assembly, and a support frame. The drive motor and the power transmission assembly are arranged in mutually compatible positions on the support frame, which is located on a top mounting platform. The front mounting bracket and the rear balance bracket, located at the front and rear ends of the support frame, can move back and forth relative to the main support frame through the drive motor and the cooperation of the power transmission assembly.

[0012] The preferred embodiment of the above scheme is that the support connecting frame includes two support fixing sleeves, two connecting guide beams, and a movable adjustment bracket. The two connecting guide beams are movably arranged on both sides of the top mounting platform through the two support fixing sleeves. The movable adjustment bracket is movably arranged on the two connecting guide beams between the top mounting platform and the front mounting bracket. The front mounting bracket and the rear balance bracket are arranged in front of and behind the top mounting platform through the two connecting guide beams, respectively. Another set of positioning sleeves of the positioning adjustment component group is arranged at the front end of the movable adjustment bracket through a telescopic hydraulic cylinder. The drive motor includes a frame shifting drive motor and an installation adjustment drive motor. The power transmission component includes four sets of gears, four racks, and two drive shafts. A rack is installed on each of the two connecting guide beams on the front and rear sides of the top mounting platform. The frame shifting drive motor is fixed on the support fixing sleeves, and the installation adjustment drive motor is fixed on the movable adjustment bracket. Two sets of gears are arranged on the power output ends of the frame shifting drive motor and the installation adjustment drive motor through a drive shaft. The four sets of gears mesh with the four racks, respectively.

[0013] Furthermore, a cab is also mounted on the top mounting platform, and an automated control center is also arranged on the top mounting platform inside the cab. The hydraulic drive system also includes a hydraulic station, which is located on the top mounting platform outside the cab. Each set of telescopic cylinders is independently connected to the hydraulic station. The movable adjustment bracket is a grid-shaped truss beam welded from two crossbeams and two longitudinal beams. The installation and adjustment drive motor is arranged on one of the crossbeams, and the other set of positioning sleeves of the positioning adjustment component group is arranged on the other crossbeam.

[0014] The beneficial effects of this invention are as follows: The technical solution provided in this application involves setting up an automated installation device that includes a support frame, a hydraulic drive system, an electric drive system, and a mobile positioning installation structure. The hydraulic drive system, the electric drive system, and the mobile positioning installation structure are all arranged on the support frame. During the installation of rainwater and sewage concrete pipes, the support frame is detachably fixed to the installed rainwater and sewage concrete pipes through the hydraulic drive system. Adjacent rainwater and sewage concrete pipes that need to be installed are lifted by the mobile positioning installation structure with the cooperation of the hydraulic drive system, the electric drive system, and the support frame, and installed in place according to the specified requirements. Thus, the automated installation device used in this application first hoists the concrete pipes for rainwater and sewage to the installation location using external hoisting equipment. Then, with the support frame and the cooperation of the hydraulic drive system, electric drive system, and mobile positioning installation structure, the pipes are lifted and the longitudinal and transverse center lines are adjusted. Finally, micro-movement installation is performed. This minimizes the occurrence of chipped edges or corners caused by collisions or manual prying during installation. At the same time, the micro-movement installation achieved by the automated installation device of this application can effectively ensure the tightness of the installation joints, thereby minimizing the occurrence of sewage pipe leakage during subsequent use. Attached Figure Description

[0015] Figure 1 This is a three-dimensional structural schematic diagram of the automated installation device for rainwater and sewage concrete pipes according to the present invention;

[0016] Figure 2 This is a front view of the automated installation device for rainwater and sewage concrete pipes according to the present invention;

[0017] Figure 3 for Figure 2 Top view;

[0018] Figure 4 , Figure 5 , Figure 6 for Figure 3 Sectional views 1-1, 2-2, and 3-3.

[0019] The following are marked in the diagram: 1. Rainwater and sewage concrete pipe; 2. Front mounting bracket; 3. Rear balance bracket; 4. Top mounting platform; 5. Telescopic cylinder; 6. Fixed ring section; 7. Movable ring section group; 8. Positioning sleeve; 9. Positioning rod; 10. Fastening moving steel rope; 11. Connecting hook; 12. Support fixing sleeve; 13. Connecting guide beam; 14. Shifting drive motor; 15. Installation and adjustment drive motor; 16. Drive shaft; 17. Cab; 18. Automated control center; 19. Hydraulic station; 20. Crossbeam; 21. Longitudinal beam. Detailed Implementation

[0020] like Figures 1-6The invention illustrates an automated installation device for stormwater and sewage concrete pipes, which effectively improves installation quality and reduces problems such as chipped edges, loose joints, and other defects during installation. The automated installation device includes a support frame, a hydraulic drive system, an electric drive system, and a moving positioning installation structure, all of which are mounted on the support frame. During the installation of the stormwater and sewage concrete pipe 1, the support frame is detachably fixed to the installed stormwater and sewage concrete pipe 1 via the hydraulic drive system. Adjacent stormwater and sewage concrete pipes 1 requiring installation are lifted and installed in place according to specified requirements by the moving positioning installation structure in conjunction with the hydraulic drive system, the electric drive system, and the support frame. This application provides a technical solution by setting up an automated installation device including a support frame, a hydraulic drive system, an electric drive system, and a mobile positioning installation structure. The hydraulic drive system, electric drive system, and mobile positioning installation structure are all arranged on the support frame. During the installation of rainwater and sewage concrete pipes, the support frame is detachably fixed to the installed rainwater and sewage concrete pipes through the hydraulic drive system. The adjacent rainwater and sewage concrete pipes that need to be installed are lifted and installed in place according to the specified requirements by the mobile positioning installation structure in cooperation with the hydraulic drive system, electric drive system, and support frame. Thus, the automated installation device used in this application first hoists the concrete pipes for rainwater and sewage to the installation location using external hoisting equipment. Then, with the support frame and the cooperation of the hydraulic drive system, electric drive system, and mobile positioning installation structure, the pipes are lifted and the longitudinal and transverse center lines are adjusted. Finally, micro-movement installation is performed. This minimizes the occurrence of chipped edges or corners caused by collisions or manual prying during installation. At the same time, the micro-movement installation achieved by the automated installation device of this application can effectively ensure the tightness of the installation joints, thereby minimizing the occurrence of sewage pipe leakage during subsequent use.

[0021] Accordingly, in order to simplify the structure of each component of the automated installation device of this application, facilitate manufacturing, installation and subsequent use, and at the same time minimize the size of the entire automated installation device to make it lighter and more flexible, the support frame of this application includes a main support frame, a front mounting bracket 2 and a rear balancing bracket 3. The front mounting bracket 2 and the rear balancing bracket 3 are movably connected to the front and rear ends of the main support frame, respectively, through an electric drive system that allows them to reciprocate along the length direction. During the installation of the rainwater and sewage concrete pipe 1, the main support frame is detachably fixed to the installed rainwater and sewage concrete pipe 1 through a hydraulic drive system. The adjacent rainwater and sewage concrete pipe 1 that needs to be installed is lifted and installed in place according to the specified requirements through a moving positioning installation structure in cooperation with the hydraulic drive system, the front mounting bracket 2 and the rear balancing bracket 3. The support frame moves forward along the installation direction through an electric drive system. At this time, the main support frame includes two portal frame support skeletons, a top mounting platform 4, and a set of clamping mechanisms. The two portal frame support skeletons are connected as a whole through a top mounting platform. The clamping mechanisms are movably arranged inside the two portal frame support skeletons. The front mounting bracket 2 and the rear balancing bracket 3 are each composed of a portal frame support skeleton. The front mounting bracket 2 and the rear balancing bracket 3 are movably connected to the top mounting platform 4 through an electric drive system. During the installation of the rainwater and sewage concrete pipe 1, the main support frame can be tightly wrapped around the installed rainwater and sewage concrete pipe 1 through the clamping mechanism with the cooperation of the hydraulic drive system. The rainwater and sewage concrete pipe 1 to be installed is lifted by the movable positioning installation structure arranged on the clamping mechanism and the front mounting bracket 2 and installed in place according to the specified requirements. Furthermore, to facilitate movement, this application provides a set of telescopic cylinders 5 with hydraulic drive system at the lower end of each of the two vertical sides of each portal frame support. During the movement of the support frame, each telescopic cylinder 5 extends and retracts alternately. The clamping mechanism includes a fixed clamping ring section 6 and a movable clamping ring section group 7. The fixed clamping ring section 6 is fixedly mounted on the horizontal side of the two portal frame support frames connected as a whole. The movable clamping ring section group 7, which is hinged to the free end of the fixed clamping ring section 6, is movably connected to the vertical side of the two portal frame support frames connected as a whole through the telescopic cylinders 5.

[0022] Meanwhile, the mobile positioning installation structure of this application includes a positioning adjustment component group and a mobile installation component group. The positioning adjustment component group is movably arranged on the front mounting bracket 2 via the telescopic cylinder 5, and the fixed end of the mobile installation component group is arranged on the movable clamping ring section group 7 of the clamping mechanism via the telescopic cylinder 5. During the installation of the rainwater and sewage concrete pipe 1, the coaxiality of the rainwater and sewage concrete pipe 1 to be installed and the rainwater and sewage concrete pipe 1 that has been installed is adjusted by the positioning adjustment component group with the cooperation of the telescopic cylinder 5. The adjusted and positioned rainwater and sewage concrete pipe 1 is moved and installed into place by the mobile installation component group with the cooperation of the telescopic cylinder 5. More specifically, the positioning adjustment assembly of this application includes three sets of positioning sleeves 8 and three positioning rods 9. Each set of positioning sleeves 8 is provided with a plug hole. The three positioning rods 9 are detachably fixed to the three sets of positioning sleeves 8 through the three plug holes. At least one set of positioning sleeves 8 is installed in the middle of the two vertical sides of the front mounting bracket 2 through two sets of telescopic cylinders 5. The movable mounting assembly of this application includes three sets of fastening moving steel ropes 10 and three sets of connecting hooks 11. A set of connecting hooks 11 is fixed to the free end of each set of fastening moving steel ropes 10. The three sets of fastening moving steel ropes 10 are arranged on the clamping mechanism in accordance with the positions of the three sets of positioning sleeves 8 through the three sets of telescopic cylinders 5.

[0023] As another component of this application, the electric drive system includes a drive motor, a power transmission assembly, and a support frame. The drive motor and the power transmission assembly are arranged in mutually compatible positions on the support frame, which is mounted on a top mounting platform 4. A front mounting bracket 2 and a rear balance bracket 3, located at the front and rear ends of the support frame, can move back and forth relative to the main support frame via the drive motor and the power transmission assembly. The support frame includes two support fixing sleeves 12, two connecting guide beams 13, and a movable adjustment bracket. The two connecting guide beams 13 are movably arranged on both sides of the top mounting platform 4 via the two support fixing sleeves 12. The movable adjustment bracket is movably arranged on the two connecting guide beams 13 between the top mounting platform 4 and the front mounting bracket 2. The front mounting bracket 2 and the rear balance bracket 3 are arranged in front of and behind the top mounting platform 4 via the two connecting guide beams 13. Another set of positioning sleeves 8 of the positioning adjustment assembly is arranged on the movable adjustment bracket via a telescopic cylinder 5. At the front end of the bracket, the drive motor includes a shifting drive motor 14 and an installation adjustment drive motor 15. The power transmission assembly includes four sets of gears, four racks, and two drive shafts 16. A rack is installed on each of the two connecting guide beams 13 on the front and rear sides of the top mounting platform 4. The shifting drive motor 14 is fixed on the support fixing sleeve 12, and the installation adjustment drive motor 15 is fixed on the movable adjustment bracket. Two sets of gears are arranged on the power output ends of the shifting drive motor 14 and the installation adjustment drive motor 15 through a drive shaft 16. The four sets of gears mesh with the four racks respectively.

[0024] Furthermore, this application also includes a cab 17 mounted on the top mounting platform 4, and an automated control center 18 is arranged on the top mounting platform 4 inside the cab 17. The hydraulic drive system also includes a hydraulic station 19, which is located on the top mounting platform 4 outside the cab 17. Each set of telescopic cylinders 5 is independently connected to the hydraulic station 19. The movable adjustment bracket is a grid-shaped truss beam welded from two crossbeams 20 and two longitudinal beams 21. The installation and adjustment drive motor 15 is arranged on one of the crossbeams 20, and the other set of positioning sleeves 8 of the positioning adjustment component group is arranged on the other crossbeam 20.

[0025] In summary, the automated installation device of this application effectively solves the problems of continuous installation and precise splicing of rainwater and sewage pipes, while reducing damage to precast reinforced concrete pipe sections during the installation process.

[0026] The technical solution of this application will be further described below through specific embodiments:

[0027] Municipal stormwater and sewage pipeline projects involve large-diameter pipes, with total lengths ranging from tens of meters to several kilometers, requiring continuous mechanical installation to improve efficiency. Reinforced concrete stormwater and sewage pipes are widely used in engineering practice due to their lower cost. Each section is typically 2 meters long, and the weight varies from hundreds of kilograms to several tons depending on the pipe diameter. Once the trench for the stormwater and sewage pipelines is excavated and a compacted crushed stone bedding layer is laid, the construction and installation of the pipelines can begin. Transport vehicles deliver the reinforced concrete pipes to the site, and truck-mounted cranes or mobile cranes lift and place the pipe sections one by one along the trench with the crushed stone bedding layer. Then, installation equipment installs the pipe sections into place.

[0028] The reinforced concrete stormwater and sewage pipe installation device consists of three parts: a main support system, a front support system, and a rear support system. The main support system is located in the middle of the equipment, above and on both sides of the already installed reinforced concrete stormwater and sewage pipes. During the installation of the front-end pipe, it is fixed to the upper end of the already installed pipe, serving as support for the installation and tightening of the front-end pipe. A working platform can also be installed on top of the main support system for arranging gas stations and operator workstations. The front support system is located at the front of the equipment, in the forward direction of the reinforced concrete stormwater and sewage pipe installation, above and on both sides of the pipe to be installed. It is used for lifting and positioning the pipe to be installed. The rear support system is located at the rear of the equipment, providing support when the main support system moves forward and balancing the forces when the front support system moves forward.

[0029] The main support system includes a ring system surrounding the circular culvert, comprising front and rear fixed rings and front and rear movable rings on both sides. The front and rear fixed rings and the front and rear movable rings on both sides are connected by hinges on both sides. The front and rear fixed rings constitute the aforementioned fixed ring section, and the front and rear movable rings constitute the aforementioned movable ring section. Each of the three sets of pre-drilled holes is used to install the fastening steel ropes, which consist of three steel wire ropes. Each fastening steel rope has a lifting cylinder at its end, which can move the fastening device forward or backward. The front end of the rope has a hook that can hook onto the pipe wall of the section to be installed. The movable rings on both sides are connected to the main support through three sets of retractable horizontal cylinders. The horizontal cylinders can rotate perpendicular to the movable rings. The front and rear fixed rings are fixedly connected to the main support. The bottom of both sides of the main support is connected to the outrigger cylinders. Each main support, i.e., the aforementioned portal frame support, is composed of horizontal bars, vertical bars, and diagonal braces to maintain the stability of the support. At the same time, the main support is connected by multiple rods to form a stable main support system. In addition, steel plates are laid within the upper support area of ​​the main support to form a platform on the upper part of the main support. A hydraulic station and operator's cab are located on the upper part of this platform. The hydraulic station is used for the centralized supply and control of hydraulic oil required for the horizontal, vertical, and lifting cylinders of this device. The operator's cab is used to house the operator's table and chairs and the automated control console. Also on the same horizontal plane as the operating platform are guide beams and their sleeves within the main support area. A gear rack is located at the lower part of the guide beam, matching a gear set at the bottom inner side of the sleeve. The gear set includes unpowered and powered gears. The powered gears are powered by an electric motor on the platform and its matching reduction gearbox, and the power is transmitted to the powered gear set on the other side via a connecting shaft. A roller assembly is located on the upper inner side of the sleeve, which, together with the lower gear set, fixes the guide beam.

[0030] The front support system consists of a front support, a guide beam connected to the main support, a front crossbeam, a rear crossbeam, a vertical positioning cylinder, three sets of horizontal positioning cylinders, three sets of positioning sleeves, and two side outrigger cylinders. The front support structure is similar to the two main supports, consisting of horizontal bars, vertical bars, and diagonal bars to maintain its stability. The bottom of the left and right sides of the front support are connected to the outrigger cylinders, and the upper part is connected to the front end of the guide beam. A gear is installed at the lower part of the front section of the guide beam. The front support is connected to the vertical lifting cylinder and two sets of horizontal telescopic cylinders. The ends of the vertical lifting cylinder and the two sets of horizontal telescopic cylinders are connected to the three sets of positioning sleeves. Each positioning sleeve has a socket into which a positioning rod can be inserted. The positioning rod in the top socket can lift the front circular culvert, while the positioning rods in the two side sockets can adjust the circular culvert left and right. The two crossbeams can move back and forth at the front section of the guide beam via their lower sleeves. The lower part of the lower sleeve is equipped with a power gear, which is connected to the gear rack at the lower part of the front section of the guide beam, allowing the two crossbeams to move back and forth. The power gear is powered by an electric motor and its matching gearbox at the lower part of one of the crossbeams, and the power is transmitted to both sides through the connecting shaft.

[0031] The rear support system consists of a rear support, two rear outriggers on both sides, and the rear section of the guide beam. Like the front support, the rear support is composed of horizontal, vertical, and diagonal braces to maintain its stability. The two rear outriggers on both sides are connected to the bottom of the rear support.

[0032] The guide beam is detachable and can be connected into a single unit to facilitate equipment use. The contact surfaces of both the fixed and movable clamps with the circular culvert are made of materials with a high coefficient of friction that will not damage the reinforced concrete culvert.

[0033] Before use, the device will be transported to the reinforced concrete stormwater and sewage pipeline site. At the site, after the first section of stormwater and sewage pipe culvert is installed, the main support system of this device will be placed on top of the installed first section of stormwater and sewage pipe culvert. At this time, the front support system and the rear support system can be installed. The front and rear supports are connected to the main support system through guide beams.

[0034] During pipe section installation, firstly, the height of the fixed clamps is adjusted by controlling the extension and retraction of the outrigger cylinders of the main support system, ensuring that the front and rear fixed clamps are in close contact with the top of the culvert; then, the movable clamps on both sides are adjusted by controlling the extension and retraction of the horizontal cylinders of the main support system, ensuring they are in close contact with the culvert; next, the outrigger cylinders of the main support system are extended and retracted to create a certain contact pressure with the ground; then, the outrigger cylinders of the front and rear support systems are extended and retracted to remove them from contact with the ground; the length of the positioning cylinder of the front support system is adjusted (to be as short as possible) to allow it to move smoothly from the rear end of the pipe section to the front side; the crossbeam near the front support is moved to the front end by controlling the motor of the front support system; the guide beam is moved back and forth by the motor in the main support system controlling the power gear set, adjusting the position of the front and rear supports so that the positioning cylinder of the front support is located in front of the front end of the culvert; finally, the outrigger cylinders of the front and rear support systems are extended and retracted to maintain contact with the ground and a certain contact pressure; By controlling the extension and retraction of the positioning cylinder of the front support system, each set of positioning sleeves is inserted into the inner side of the pipe section wall. Positioning rods are then inserted into the insertion holes of the positioning sleeves. The positioning rod in the top insertion hole should be weighted to accommodate the counterweight required to lift the pipe section. Simultaneously, the crossbeam on the front guide beam at the rear end of the pipe section to be installed, along with its matching hook rope, can be used in conjunction with the positioning cylinder and related equipment to lift the pipe section. By controlling the extension and retraction of the positioning cylinder of the front support system, the pipe section is slightly lifted. At this point, the corresponding crossbeam on the rear guide beam of the pipe section, the cylinder, and its matching hook rope are used to lift the pipe section. By controlling... The positioning cylinder of the front support system adjusts the left and right position of the pipe section to be installed, and construction is carried out according to the predetermined axis. The front and rear crossbeams are moved to hoist the pipe section as close as possible to the front end of the installed pipe section. The cylinder is raised so that the hook rope at the rear end of the pipe section to be installed is removed from the outer wall of the pipe section. The hook at the front end of the steel rope is hooked onto the wall of the pipe section. By controlling the three lifting cylinders at the end of the steel rope, the three fastening steel ropes are moved backward, driving the pipe section to move towards the installed pipe section. Simultaneously, the positioning cylinder, positioning sleeve and positioning rod in the front support system adjust the axis of the pipe section to maintain the accuracy of the axis of the pipe section to be installed.

[0035] When moving the device after the pipe section is installed, the horizontal cylinders on both sides of the main support are extended and retracted to disengage the movable clamps on both sides from the pipe section; the four outrigger cylinders on both sides of the main support system are lifted off the ground by extending and retracting the outrigger cylinders on both sides; the fixed clamps of the main support system are disengaged from the pipe section by extending and retracting the outrigger cylinders of the front and rear support systems; and the main support system motor is controlled to move the lifted main support system forward along the guide beam until it reaches a suitable position on the upper part of the second circular culvert section that has been installed, and then stops.

[0036] Repeat the pipe section installation steps to install the next pipe section to be installed, until the entire rainwater and sewage pipe is installed.

[0037] The hydraulic station and generator of this device are electrically driven. The hydraulic station is connected to each oil cylinder through hydraulic pipelines. The control buttons of the hydraulic station are located on the control panel in the cab for easy operation by the operator.

[0038] Cameras can be installed at appropriate locations on the device to transmit real-time information to the control room or operating room, facilitating automated control during the pipe section installation process.

[0039] Example 1

[0040] Taking a reinforced concrete stormwater and sewage pipe section with a diameter of 1.5 meters and a wall thickness of 15 cm as an example, the device design is as follows:

[0041] The inner radius of the retaining ring is 0.9 meters, allowing for a 240-degree close fit with the outer wall of the circular culvert. The fixed retaining ring can fit with the outer wall at a 120-degree angle, while the two movable retaining rings on either side can fit with the outer wall at a 60-degree angle. The retaining rings are 100mm thick and 60mm wide, made of steel. The pre-drilled holes on both the fixed and movable retaining rings are 30mm in diameter. The horizontal hydraulic cylinder connecting the movable retaining rings is a 1-ton telescopic cylinder, approximately 400mm long. The main support's horizontal, vertical, and diagonal braces are made of 100×60mm steel. The vertical braces on the fixed retaining ring are located at the center of the fixed retaining ring's arc and on the left and right sides. At a 5-degree angle, the diagonal brace connects the outer vertical and horizontal bars of the support frame at a 45-degree angle. The support legs use 3t outrigger cylinders. The guide beam is made of 100×60mm steel, with a lower gear set diameter of 20mm and an upper roller diameter of 10mm. The guide beam sleeve wall thickness is 5mm. The platform plate thickness is 10mm. The upper crossbeam of the guide beam is made of 100×60mm steel. The upper positioning cylinder of the front support system uses a 5t cylinder, and the left and right side positioning cylinders use 1t cylinders. The fastening device uses 16mm steel rope with steel hooks at the ends. The outriggers of the front and rear support systems use 5t outrigger cylinders.

Claims

1. An automated installation apparatus for storm sewer concrete pipes, characterized in that: The automatic installation device comprises a support frame, a hydraulic drive system, an electric drive system and a mobile positioning installation structure, and the hydraulic drive system, the electric drive system and the mobile positioning installation structure are arranged on the support frame; during installation of the rainwater and sewage concrete pipeline (1), the support frame is detachably fixed on the installed rainwater and sewage concrete pipeline (1) by the hydraulic drive system, and the adjacent rainwater and sewage concrete pipeline (1) to be installed is hoisted and installed in place according to the specified requirements by the mobile positioning installation structure under the cooperation of the hydraulic drive system, the electric drive system and the support frame, The support frame comprises a support main frame, a front installation support (2) and a rear balance support (3), the front installation support (2) and the rear balance support (3) are movably connected to the front end and the rear end of the support main frame along the length direction by the electric drive system, the support main frame comprises two door-shaped support skeletons, a top installation platform (4) and a set of clamping mechanisms, the two door-shaped support skeletons are connected as a whole through the top installation platform, the clamping mechanisms are movably arranged in the two door-shaped support skeletons, the front installation support (2) and the rear balance support (3) are each composed of a door-shaped support skeleton, and the front installation support (2) and the rear balance support (3) are movably connected to the top installation platform (4) by the electric drive system, A set of telescopic oil cylinders (5) of the hydraulic drive system are arranged at the lower ends of the two vertical edges of each door-shaped support skeleton, the clamping mechanism comprises a fixed clamping ring section (6) and a set of movable clamping ring sections (7), the set of movable clamping ring sections (7) is movably connected to the vertical edges of the two door-shaped support skeletons connected as a whole through the telescopic oil cylinder (5), and the free end of the fixed clamping ring section (6) is hingedly connected to the set of movable clamping ring sections (7), The mobile positioning installation structure comprises a set of positioning adjustment members and a set of mobile installation members, the set of positioning adjustment members is movably arranged on the front installation support (2) through the telescopic oil cylinder (5), and the fixed end of the set of mobile installation members is arranged on the set of movable clamping ring sections (7) of the clamping mechanism through the telescopic oil cylinder (5), The set of positioning adjustment members comprises three sets of positioning sleeve irons (8) and three positioning rods (9), one insertion hole is arranged on each set of positioning sleeve irons (8), the three positioning rods (9) are detachably fixed on the three sets of positioning sleeve irons (8) through the three insertion holes, and at least one set of positioning sleeve irons (8) is installed on the middle part of each vertical edge of the front installation support (2) through two telescopic oil cylinders (5), The set of mobile installation members comprises three sets of fastening mobile steel ropes (10) and three sets of connecting hooks (11), one set of connecting hooks (11) is fixed on the free end of each set of fastening mobile steel ropes (10), and the three sets of fastening mobile steel ropes (10) are arranged on the clamping mechanism in a position-adaptable manner through the three sets of telescopic oil cylinders (5) and the three sets of positioning sleeve irons (8). The support connecting frame of the electric drive system comprises two support fixed sleeves (12), two connecting guide beams (13) and a moving adjustment support, the two connecting guide beams (13) are movably arranged on the two sides of the top mounting platform (4) through the two support fixed sleeves (12), the moving adjustment support is movably arranged on the two connecting guide beams (13) between the top mounting platform (4) and the front mounting support (2), the front mounting support (2) and the rear balance support (3) are arranged in front of and behind the top mounting platform (4) through the two connecting guide beams (13), and the other set of positioning sleeve irons (8) of the positioning adjustment component group is arranged at the front end of the moving adjustment support through the telescopic oil cylinder (5).

2. The automated installation apparatus for storm sewer concrete pipes according to claim 1, characterized in that: In the installation process of the rainwater and sewage concrete pipeline (1), the support main frame is detachably fixed on the installed rainwater and sewage concrete pipeline (1) through the hydraulic drive system, the adjacent rainwater and sewage concrete pipeline (1) to be installed is hoisted and installed in place according to the specified requirements through the moving positioning and mounting structure under the cooperation of the hydraulic drive system, the front mounting support (2) and the rear balance support (3), and the support frame moves forward along the installation direction through the electric drive system.

3. The automated installation apparatus for storm sewer concrete pipes according to claim 2, characterized in that: In the installation process of the rainwater and sewage concrete pipeline (1), the support main frame is detachably fixed on the installed rainwater and sewage concrete pipeline (1) through the hydraulic drive system, the adjacent rainwater and sewage concrete pipeline (1) to be installed is hoisted and installed in place according to the specified requirements through the moving positioning and mounting structure arranged on the front mounting support (2) and the rear balance support (3).

4. The automated installation apparatus for storm sewer concrete pipes according to claim 3, characterized in that: In the moving process of the support frame, each telescopic oil cylinder (5) is alternately extended and retracted.

5. An automated installation apparatus for storm sewer concrete pipes as claimed in claim 1, 2, 3 or 4, characterized in that: In the installation process of the rainwater and sewage concrete pipeline (1), the coaxiality of the rainwater and sewage concrete pipeline (1) to be installed and the installed rainwater and sewage concrete pipeline (1) is adjusted through the positioning adjustment component group under the cooperation of the telescopic oil cylinder (5), and the installed rainwater and sewage concrete pipeline (1) is moved and installed in place through the moving mounting component group under the cooperation of the telescopic oil cylinder (5).

6. The automated installation device for storm sewer concrete pipes of claim 1, wherein: The electric drive system further comprises a drive motor and a power transmission assembly, the drive motor and the power transmission assembly are arranged on the support connecting frame in a positionally adaptive manner, the support connecting frame is arranged on the top mounting platform (4), and the front mounting support (2) and the rear balance support (3) arranged at the front end and the rear end of the support connecting frame can move forward and backward relative to the support main frame through the drive motor under the cooperation of the power transmission assembly.

7. The automated installation apparatus for storm sewer concrete pipes according to claim 6, characterized in that: The drive motor comprises a rack moving drive motor (14) and an installation adjusting drive motor (15), the power transmission assembly comprises four pairs of gears, four racks and two transmission shafts (16), one rack is arranged on each of the two connecting guide beams (13) on the front and rear sides of the top mounting platform (4), the rack moving drive motor (14) is fixedly arranged on the support fixed sleeve (12), the installation adjusting drive motor (15) is fixedly arranged on the moving adjustment support, two pairs of gears are arranged on the power output ends of the rack moving drive motor (14) and the installation adjusting drive motor (15) through one transmission shaft (16) respectively, and the four pairs of gears are meshed with the four racks respectively.

8. The automated installation apparatus for storm sewer concrete pipes according to claim 7, characterized in that: A cab (17) is further connected to the top mounting platform (4), and an automatic control center (18) is further arranged on the top mounting platform (4) in the cab (17). The hydraulic drive system further comprises a hydraulic station (19) arranged on the top mounting platform (4) outside the cab (17). Each group of telescopic oil cylinders (5) is respectively and independently connected to the hydraulic station (19). The moving and adjusting support is a cross-shaped truss beam formed by welding two cross beams (20) and two longitudinal beams (21). The adjusting drive motor (15) is arranged on one of the cross beams (20), and the other group of positioning sleeve irons (8) of the positioning and adjusting component group is arranged on the other cross beam (20).

Citation Information

Patent Citations

  • Mounting device of bell and spigot concrete drain pipeline and construction method thereof

    CN106638898A

  • Connection and installation equipment for concrete drain pipe

    CN111705892A