A high-efficiency multi-row pipe pressure test system
By introducing double-head sealing joints and automated control systems into the pipe discharge detection system, the problems of low pipe pressure detection efficiency and poor accuracy in the existing technology are solved, and more efficient and accurate detection results are achieved.
Patent Information
- Application Number
- CN202311470650.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-07
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2043-11-07
AI Technical Summary
The existing pipe pressure detection method is inefficient and inaccurate, resulting in large deviations in the detection results. In particular, it is difficult to accurately judge the pressure drop caused by the sealing problem of the pipe interface.
A high-efficiency multi-row pipe pressure test system is designed, which uses double-head sealing joints to replace the traditional way of directly connecting the head and tail of the pipes, and realizes automatic inflation and deflation detection through the PLC control box and solenoid valve, combined with the sealing indicator strip and pressure Sensor, real-time monitoring and warning of sealing problems to ensure detection accuracy.
It improves the accuracy and efficiency of inspection, reduces misjudgments caused by sealing problems, ensures that good products are not mistakenly judged as defective products, and reduces the need for manual observation and the risk of air leakage during the inspection process.
Smart Images

Figure CN117470474B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a multi-row pipe pressure testing system, and in particular to a high-efficiency multi-row pipe pressure testing system applied to the field of pipe detection. Background Art
[0002] The existing drainage pipe pressure testing adopts a single drainage pipe that is sealed at both ends with a special clamp, placed in pure water, and filled with compressed air. When the pressure reaches a certain level, the pressure is maintained for a certain period of time according to the process requirements, and the pipe is manually observed for bubbles. The pipe without bubbles is considered a qualified product, and the pipe with bubbles is considered a defective product.
[0003] This method of inspection is inefficient as each tube must be taken out of the cart, put into a sink and then put back into the cart. The risk of bumping into the tubes during transportation is increased, which is not only inefficient but also affects product quality.
[0004] To solve the above problems, multiple pipes are generally connected end to end to increase the pressure testing efficiency. However, there is a sealing requirement at the connection between the ends of two adjacent pipes. When the seal is defective, during pressure maintenance, there will be a pressure drop even if there is no problem with the pipe, resulting in a large deviation in the accuracy of the test results. Summary of the invention
[0005] In view of the above-mentioned prior art, the technical problem to be solved by the present invention is that the existing pressing method has the problem of low accuracy.
[0006] In order to solve the above problems, the present invention provides a high-efficiency multi-row pipe pressure test system, including a bracket, a plurality of pressure components respectively installed on the bracket, and a PLC control box for controlling the inflation and deflation of gas, the PLC control box is provided with, a plurality of test stations respectively corresponding to the plurality of pressure components are arranged in front of the bracket, an end of the bracket close to the test station is fixedly connected with an intake pipe and an exhaust pipe, the intake pipe is located above the exhaust pipe, the upper and lower openings of the plurality of pressure components are respectively connected with the intake pipe and the exhaust pipe, and the upper and lower outer ends of the pressure components are both installed with solenoid valves, the mouth of the pressure component located in the middle is fixedly connected with an air guide pipe, a pressure gauge is also installed at the middle outer end of the pressure component, the solenoid valve and the pressure gauge are both connected to the PLC control box signal, and an alarm is also installed on each pressure component, and the alarm is also connected to the PLC control box signal;
[0007] A pipe cart is parked on each test station. Multiple evenly distributed pipes are stacked on the cart. The multiple pipes are connected head to tail through double connectors. One of the openings of the first pipe on the top is exposed, and the exposed pipe opening is connected to the air guide pipe.
[0008] In the above-mentioned high-efficiency multi-row tube pressure testing system, a special sealing joint is added, which can not only effectively seal the connection between the two tubes, but also has a certain early warning reminder when sealing abnormalities occur at the tube interface. During the pressure maintenance test, it can effectively reduce the error caused by the sealing problem at the end connection and improve the detection accuracy.
[0009] As a further improvement of the present application, the double connector includes two sealing tubes respectively sleeved on the upper and lower adjacent pipe openings and a ventilation tube fixedly connected between the two sealing tubes. Two symmetrical sealing indicator strips are fixedly connected to the front and rear outer ends of the ventilation tubes. The sealing indicator strips include an air ferry tube fixedly connected to the end face of the sealing tube and an indicator strip fixedly connected to the outer end of the ventilation tube.
[0010] As a further improvement of the present application, the pressure test method of the test system on the multi-row pipes includes the following steps:
[0011] S1. First, connect multiple pipes on each pipe-dispensing trolley end to end through double connectors to form a series pipeline. The last opening of the lowest pipe in the series pipeline is also connected to a double connector, and the exposed opening of the double connector is sealed.
[0012] S2. Push multiple pipe-discharging carts into the test station respectively, and connect the air guide pipe to the mouth of the series pipe. After the connection is completed, the PLC control box controls multiple solenoid valves located above to open, and inflate through the air intake main pipe. After a certain pressure is reached according to the process regulations, stop inflating;
[0013] S3. After that, the PLC control box controls the multiple solenoid valves located above to close again to maintain the pressure. During the pressure maintenance process, the pressure gauge detects the pressure change in the series pipeline in real time. When the pressure data on the pressure gauge does not drop significantly after a certain period of pressure maintenance, it is considered a qualified product, otherwise it is a defective product;
[0014] S4. After the test is completed, the PLC control box controls the multiple solenoid valves located below to open, exhaust gas is discharged through the exhaust main pipe, and finally the pressure component is removed and the test station is pushed out.
[0015] As a further improvement of the present application, when a gas leak occurs during the pressure-maintaining process in step S3, an alarm is triggered and the alarm sounds;
[0016] At the same time, the staff needs to check whether the sealing indicator strips at the multiple double connectors on the series pipeline indicate that there are problems with the sealing of the two pipe interfaces. If there are problems with the sealing, the double connectors at the damaged parts need to be replaced and the corresponding multiple pipes need to be retested;
[0017] When the sealing indicator strips at multiple double joints do not indicate that there are sealing problems at two adjacent rows of pipes, it means that there are defective products in the corresponding multiple rows of pipes.
[0018] As a further improvement of the present application, the inner diameter of the end of the sealing tube opposite to the ventilation pipe is small, and the inner diameter of the other end of the sealing tube is large, and embedded annular grooves are opened at the two steps with different inner diameters, and a sealing gasket is placed on the inner wall of the embedded annular groove. The end of the drainage pipe extends into the sealing tube and matches the embedded annular groove, and two air inlet holes are opened on the inner wall of the sealing tube, which correspond to and communicate with the two ferry pipes respectively.
[0019] As a further improvement of the present application, the mouth of the embedded annular groove away from the ferry pipe is located on the side of the blocking pipe centerline away from the ventilation pipe, and the size of the air inlet opening is 3-5 times the size of other parts of the air inlet opening.
[0020] As a further improvement of the present application, the indicator strip includes an outer protective transparent tube, an air-sensing strip located inside the outer protective transparent tube, and two limiting plates respectively fixed to the two ends of the outer protective transparent tube, the limiting plates are fixed to the air-sensing strip, and the air pipe is communicated with the air-sensing strip, a hidden strip is provided inside the air-sensing strip, the hidden strip includes an inner hidden strip and two support rods respectively connected between the inner hidden strip and the limiting plates.
[0021] As a further improvement of the present application, the gas sensing strip is a bright dark color, the outer protective transparent tube is a hard transparent structure, the gas sensing strip is an elastically sealed film structure, and the gas sensing strip is also a dark color.
[0022] As another improvement of the present application, the inner wall in the middle of the indicator strip is fixedly connected to a support rod, and pressure sensors are installed at the upper and lower ends of the support rod. The pressure sensors are connected to the PLC control box signal, and the inner wall of the indicator strip is also fixedly connected to two gas-sensing pieces symmetrical about the support rod. The gas-sensing pieces are close to the support rod but do not contact the support rod, and the gas-sensing pieces are elastic sealing structures.
[0023] In summary, by adding a double connector specially used for sealing between the two drain pipe mouths, replacing the original method of directly connecting the ends of the drain pipes, the sealing of the connection can be effectively guaranteed, so that during the inflation and pressure maintaining process, the connection between the two drain pipes is not prone to leakage. In addition, when leakage occurs, the leakage indicator bar will change significantly, and the leakage at the connection will be clearly indicated, so that during the detection process, the impact of the end sealing problem on the detection results can be effectively reduced, thereby effectively ensuring the accuracy of the detection and reducing the occurrence of mistaking good products for defective products. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a three-dimensional diagram of the first embodiment of the present application;
[0025] Figure 2 for Figure 1 Schematic diagram at A in the middle;
[0026] Figure 3A three-dimensional diagram of a pressing assembly according to a first embodiment of the present application;
[0027] Figure 4 This is a three-dimensional schematic diagram of the first embodiment of the present application after the pipes are connected end to end;
[0028] Figure 5 This is a three-dimensional diagram of a double connector according to the first embodiment of the present application;
[0029] Figure 6 This is a three-dimensional view of the double connector from another perspective of the first embodiment of the present application;
[0030] Figure 7 This is a front cross-sectional view of a double connector according to a first embodiment of the present application;
[0031] Figure 8 This is a top view of a double connector in the first embodiment of the present application;
[0032] Fig. 9 This is a front cross-sectional view of the sealing indicator strip in the first embodiment of the present application;
[0033] Fig.10 This is a front view of the first embodiment of the present application when air leakage occurs at the two pipe joints;
[0034] Fig.11 This is a front view of a sealing indicator strip in the second embodiment of the present application.
[0035] Description of the numbers in the figure:
[0036] 1 bracket, 2 pressure assembly, 31 air intake main pipe, 32 exhaust main pipe, 4 air guide pipe, 5 pipe row trolley, 6 PLC control box, 7 rows of pipes, 8 double connectors, 81 blocking pipe, 82 ventilation pipe, 801 embedded ring groove, 802 air intake hole, 91 indicator strip, 92 air ferry, 911 outer protective tube, 912 air sensing strip, 913 hidden strip, 901 support rod, 10 pressure sensor, 101 air sensing piece, 102 support rod. DETAILED DESCRIPTION
[0037] Two implementation modes of the present application are described in detail below with reference to the accompanying drawings.
[0038] The first implementation method:
[0039] Figure 1-2 A high-efficiency multi-row tube pressure test system is shown, comprising a support 1, a plurality of pressure components 2 respectively mounted on the support 1, and a PLC control box 6 for controlling the inflation and deflation of gas, the PLC control box 6 is provided with, and a plurality of test stations corresponding to the plurality of pressure components 2 are respectively provided in front of the support 1, such as Figure 3, one end of the bracket 1 close to the test station is fixedly connected with an air intake pipe 31 and an exhaust pipe 32, the air intake pipe 31 is located above the exhaust pipe 32, and the upper and lower openings of the multiple pressure components 2 are respectively connected with the air intake pipe 31 and the exhaust pipe 32, and the upper and lower outer ends of the pressure components 2 are both installed with solenoid valves, and the mouth of the pressure component 2 located in the middle is fixedly connected with an air guide pipe 4, and a pressure gauge is also installed at the outer middle end of the pressure component 2, and the solenoid valve and the pressure gauge are both connected to the PLC control box 6 signal, and each pressure component 2 is also installed with an alarm, which is also connected to the PLC control box 6 signal;
[0040] like Figure 4 A pipe trolley 5 is parked on each test station, and a plurality of evenly distributed pipes 7 are stacked on the pipe trolley 5 . The multiple pipes 7 are connected head to tail through double connectors 8 , and one of the openings of the first pipe 7 at the top is exposed, and the exposed opening of the pipe 7 is connected to the air guide pipe 4 .
[0041] The pressure test method of the test system for multiple rows of pipes includes the following steps:
[0042] S1. First, connect the multiple pipes 7 on each pipe-dispensing trolley 5 end to end through double connectors 8 to form a series pipeline. The last opening of the lowest pipe 7 in the series pipeline is also connected to the double connector 8, and the exposed opening of the double connector 8 is sealed.
[0043] S2, push multiple pipe-laying carts 5 into the test station respectively, connect the air guide pipe 4 to the mouth of the series pipe, after the connection, the PLC control box 6 controls multiple solenoid valves located above to open, and inflate through the air intake main pipe 31, and stop inflating after a certain pressure is filled according to the process regulations;
[0044] S3, after that, the PLC control box 6 controls the multiple electromagnetic valves located at the top to close again to maintain the pressure. During the pressure maintenance process, the pressure gauge detects the pressure change in the series pipeline in real time. When the pressure data on the pressure gauge does not drop significantly after a certain period of pressure maintenance, it is considered a qualified product, otherwise it is a defective product;
[0045] S4. After the test is completed, the PLC control box 6 controls the multiple solenoid valves located below to open, exhaust air through the exhaust main pipe 32, and finally removes the pressure component 2 and pushes it out of the test station.
[0046] When air leakage occurs during the pressure maintaining process in step S3, the alarm will be triggered and the alarm will sound; at the same time, the staff needs to check whether the sealing indicator strips at the multiple double connectors 8 on the series pipeline indicate that there are sealing problems at the interfaces of the two row pipes 7. When there are sealing problems, it is necessary to replace the damaged double connectors 8 and re-test the corresponding multiple row pipes 7; when the sealing indicator strips at the multiple double connectors 8 do not indicate that there are sealing problems at the two adjacent row pipes 7, it means that there are defective products in the corresponding multiple row pipes 7.
[0047] like Figure 5-6 The double connector 8 includes two sealing tubes 81 respectively sleeved on the mouths of two adjacent upper and lower drain pipes 7 and a ventilation tube 82 fixedly connected between the two sealing tubes 81, one of the sealing tubes 81 is threadedly connected to the drain pipe 7, and the other sealing tube 81 is gap-fitted with the drain pipe 7, and two symmetrical sealing indicator strips are fixedly connected to the front and rear outer ends of the ventilation pipe 82, and the sealing indicator strips include an air ferry 92 fixedly connected to the end face of the sealing tube 81 and an indicator strip 91 fixedly connected to the outer end of the ventilation pipe 82.
[0048] It is worth noting that one of the sealing tubes 81 is threadedly connected to the drain pipe 7, and the other sealing tube 81 is clearance-matched with the drain pipe 7. To ensure that both sealing tubes 81 can be stably connected to the drain pipe 7, fixing rods can be added to the ends of the two sealing tubes 81 that are close to each other to synchronize the two. During pressurization, the sealing tube 81 that is not threadedly connected to the drain pipe 7 can be effectively protected from loosening due to air pressure.
[0049] like Figure 7-8 The inner diameter of the end of the sealing tube 81 opposite to the ventilation tube 82 is small, and the inner diameter of the other end of the sealing tube 81 is large, so that a step is formed at the diameter change point of the sealing tube 81 and the ventilation tube 82, and an embedded annular groove 801 is excavated at the two steps with different inner diameters, and a sealing gasket is placed on the inner wall of the embedded annular groove 801. When connecting the ends of the two row pipes 7, the end face of the row pipe 7 is embedded in the embedded annular groove 801 along the step and contacts the sealing gasket, so as to realize the sealing of the two adjacent row pipes 7. The end of the row pipe 7 extends into the sealing tube 81 and matches with the embedded annular groove 801.
[0050] Two air inlet holes 802 are bored on the inner wall of the blocking tube 81, which correspond to and communicate with the two ferry pipes 92 respectively. When there is an abnormality in the sealing between the end of the drain pipe 7 and the sealing gasket at the air inlet hole 802, air leakage will occur. Due to the high pressure in the series pipeline, the leaked gas overflows with a certain speed. When passing through the mouth of the air inlet hole 802, it can smoothly enter the air inlet hole 802 and enter the sealing indicator strip, causing obvious changes in the sealing indicator strip. The mouth of the embedded annular groove 801 away from the ferry pipe 92 is located on the side of the center line of the blocking tube 81 away from the ventilation pipe 82, and the size of the mouth of the air inlet hole 802 is 3-5 times the size of the other parts of the air inlet hole 802. When the leaked gas passes through this place, due to the larger opening of the air inlet hole 802, a larger storage space is provided for the leaked gas, which is convenient for guiding more of it to enter the sealing indicator strip, making the sealing abnormality reminder more obvious and the effect better.
[0051] like Fig. 9 The indicator strip 91 includes an outer protective transparent tube 911, an air sensing strip 912 located inside the outer protective transparent tube 911, and two limiting plates respectively fixed to the two ends of the outer protective transparent tube 911, the limiting plates are fixed to the air sensing strip 912, and the air ferry 92 is communicated with the air sensing strip 912, a hidden strip is arranged inside the air sensing strip 912, the hidden strip includes an inner hidden strip 913 and two support rods 901 respectively connected between the inner hidden strip 913 and the limiting plates, the air sensing strip 912 is a bright dark color, the outer protective transparent tube 911 is a hard transparent structure, which is convenient for directly observing the changes of the internal air sensing strip 912, the air sensing strip 912 is an elastically sealed film structure, and the air sensing strip 912 is also a dark color, so that it can play a certain shielding role on the internal inner hidden strip 913, such as Fig.10 When air leakage occurs, the air sensing strip 912 will expand to a certain extent. At this time, due to the expansion, the color of the air sensing strip 912 becomes lighter, and the shielding force on the inner hidden strip 913 becomes weaker, so that the abnormality at this location can be clearly observed by the naked eye. Furthermore, when detecting and maintaining pressure, when the pressure gauge data changes significantly, it can be confirmed in time whether it is caused by the sealing problem at the end connection of the two exhaust pipes 7, which effectively avoids the situation where qualified products are mistakenly judged as defective products, and effectively improves the accuracy of the test results.
[0052] In summary, by adding a double connector 8 specially used for sealing between the mouths of the two row tubes 7, instead of the original method of directly connecting the ends of the row tubes 7, the sealing of the connection can be effectively guaranteed, so that during the inflation and pressure maintaining process, the connection between the two row tubes 7 is not prone to leakage. In addition, when leakage occurs, the leakage indicator bar will change significantly, and the leakage at the connection will be clearly indicated, so that during the detection process, the influence of the end sealing problem on the detection result can be effectively reduced, thereby effectively ensuring the detection accuracy and reducing the occurrence of mistaking good products for defective products.
[0053] The second implementation method:
[0054] Compared with the first embodiment, the present embodiment replaces the specific structure in the indicator bar 91 with the following method, and the rest of the structure remains the same as the first embodiment.
[0055] Fig.11 As shown, a support rod 102 is fixedly connected to the inner wall in the middle of the indicator bar 91, and pressure sensors 10 are installed at the upper and lower ends of the support rod 102. The pressure sensor 10 is connected to the PLC control box 6 signal. Two gas-sensing sheets 101 symmetrical about the support rod 102 are also fixedly connected to the inner wall of the indicator bar 91. The gas-sensing sheets 101 are close to the support rod 102 but do not contact the support rod 102, and the gas-sensing sheets 101 are elastic sealing structures.
[0056] During the detection process, when a pressure gauge shows an obvious data drop, if the phenomenon is caused by leakage, since the gas in the series pipeline formed by the multiple row pipes 7 is under high pressure, when it leaks, part of the gas passes through the air inlet hole 802, and its larger mouth will first enter the indicator bar 91 along the air inlet hole 802, causing the gas sensing piece 101 to deform toward the support rod 102, thereby causing the pressure sensor 10 on the support rod 102 to generate obvious pressure data, and then it can be judged that there is an obvious sealing problem at the connection between the two row pipes 7, and the pressure sensor 10 generates The pressure data can be automatically fed back to the PLC control box 6, so that the PLC control box 6 can automatically determine that the abnormality of the series pipeline may not be entirely due to the existence of defective products. When the PLC control box 6 does not receive obvious data changes from the pressure sensor 10, it means that the sealing of the connections of the multiple pipes 7 is good, that is, the decrease in pressure gauge data is due to the existence of defective products. Compared with the first embodiment, in this embodiment, whether the pressure gauge data decrease is caused by a sealing problem does not require manual observation, the degree of automation is higher, the amount of manual labor is reduced, and the labor cost can also be effectively reduced, which speeds up the detection process.
[0057] It is also worth noting that in this embodiment, a carbon dioxide sensor can be directly installed in the indicator strip 91, and the gas filled during pressurization is carbon dioxide gas. When the carbon dioxide sensor in the indicator strip 91 detects a sudden increase in the carbon dioxide concentration, it indicates that there is a sealing problem at the end connection of the two pipes 7.
[0058] In view of current practical needs, the above-mentioned implementation mode adopted in this application is not limited to the scope of protection. Various changes made within the knowledge scope of technical personnel in this field without departing from the concept of this application still fall within the scope of protection of the present invention.
Claims
1. A high-efficiency multi-row tube pressure test system, characterized by: The invention comprises a support (1), a plurality of pressure components (2) respectively mounted on the support (1), and a PLC control box (6) for controlling inflation and deflation. A plurality of test stations respectively corresponding to the plurality of pressure components (2) are arranged in front of the support (1). An end of the support (1) close to the test station is fixedly connected to an air intake pipe (31) and an air exhaust pipe (32). The air intake pipe (31) is located above the air exhaust pipe (32). The upper and lower openings of the plurality of pressure components (2) are respectively connected to the air intake pipe (31) and the air exhaust pipe (32). Solenoid valves are installed at the upper and lower outer ends of the pressure components (2). An air guide pipe (4) is fixedly connected at the opening of the pressure components (2) in the middle. A pressure gauge is also installed at the middle outer end of the pressure components (2). The solenoid valve and the pressure gauge are both connected to the PLC control box (6) by signal. An alarm is also installed on each of the pressure components (2). The alarm is also connected to the PLC control box (6) by signal. A pipe arrangement trolley (5) is parked on each of the test stations, and a plurality of evenly distributed pipes (7) are stacked on the pipe arrangement trolley (5), and the plurality of pipes (7) are connected head to tail via a double connector (8), and one of the openings of the first pipe (7) at the top is exposed, and the exposed pipe (7) opening is connected to the air guide pipe (4); The double connector (8) comprises two plugging tubes (81) respectively sleeved on the openings of two upper and lower adjacent rows of tubes (7) and a venting tube (82) fixedly connected between the two plugging tubes (81); the front and rear outer ends of the venting tube (82) are fixedly connected to two mutually symmetrical sealing indicator strips; the sealing indicator strip comprises a ferry tube (92) fixedly connected to the end surface of the plugging tube (81) and an indicator strip (91) fixedly connected to the outer end of the venting tube (82); the inner diameter of one end of the plugging tube (81) opposite to the venting tube (82) is small, and the inner diameter of the other end of the plugging tube (81) is large, and the two different inner diameters are fixedly connected to each other. An embedded annular groove (801) is bored at the step of the diameter, a sealing gasket is placed on the inner wall of the embedded annular groove (801), the end of the drain pipe (7) extends into the plugging pipe (81) and matches the embedded annular groove (801), the inner wall of the plugging pipe (81) is bored with two air inlet holes (802) which correspond to and communicate with the two ferry pipes (92), the mouth of the air inlet hole (802) away from the ferry pipe (92) is located on the side of the midline of the plugging pipe (81) away from the ventilation pipe (82), and the size of the mouth of the air inlet hole (802) is 3-5 times the size of other parts of the air inlet hole (802); The indicator bar (91) comprises an outer protective tube (911), an air sensing bar (912) located inside the outer protective tube (911), and two limit plates respectively fixed to two ends of the outer protective tube (911), the limit plates are fixed to the air sensing bar (912), and the air pipe (92) is in communication with the air sensing bar (912), a hidden bar is provided inside the air sensing bar (912), and the hidden bar comprises an inner hidden bar (913) and two support rods (901) respectively connected between the inner hidden bar (913) and the limit plates; A support rod (102) is fixedly connected to the inner wall of the middle part of the indicator bar (91), and pressure sensors (10) are installed at both upper and lower ends of the support rod (102). The pressure sensors (10) are connected to the PLC control box (6) for signal connection. Two gas sensing sheets (101) symmetrical about the support rod (102) are also fixedly connected to the inner wall of the indicator bar (91), and the gas sensing sheets (101) are close to the support rod (102) but do not contact the support rod (102), and the gas sensing sheets (101) are elastic sealing structures.
2. A high-efficiency multi-row tube pressure test system according to claim 1, characterized in that: The pressure test method of the test system on multiple rows of pipes includes the following steps: S1. First, multiple rows of pipes (7) on each pipe-laying trolley (5) are connected end to end through double connectors (8) to form a series pipeline. The last opening of the lowest row of pipes (7) in the series pipeline is also connected to a double connector (8), and the exposed opening of the double connector (8) is sealed; S2, pushing a plurality of pipe arrangement carts (5) into the test station respectively, connecting the air guide pipe (4) to the mouth of the series pipe, after which the PLC control box (6) controls a plurality of solenoid valves located above to open, and inflating is performed through the air inlet main pipe (31), and the inflation is stopped after a certain pressure is reached according to the process regulations; S3. After that, the PLC control box (6) controls the multiple electromagnetic valves located at the top to close again to maintain the pressure. During the pressure maintenance process, the pressure gauge detects the pressure change in the series pipeline in real time. When the pressure data on the pressure gauge does not drop significantly after the pressure is maintained for a certain period of time, it is considered a qualified product, otherwise it is a defective product. S4. After the test is completed, the PLC control box (6) controls the multiple solenoid valves located below to open, exhaust gas is discharged through the exhaust main pipe (32), and finally the pressure component (2) is removed and pushed out of the test station.
3. A high-efficiency multi-row tube pressure test system according to claim 2, characterized in that: When air leakage occurs during the pressure-maintaining process in step S3, an alarm is triggered and sounds an alarm; At the same time, the staff needs to check whether the sealing indicator strips at the multiple double connectors (8) on the serial pipeline indicate that there is a problem with the sealing at the interface of the two pipes (7). If there is a problem with the sealing, the double connector (8) at the damaged part needs to be replaced, and the corresponding multiple pipes (7) need to be retested. When the sealing indicator strips at the plurality of double joints (8) do not indicate that there is a sealing problem at two adjacent rows of tubes (7), it indicates that there are defective products in the corresponding plurality of rows of tubes (7).
4. The high-efficiency multi-row tube pressure test system according to claim 1, characterized in that: The gas sensing strip (912) is a bright dark color, the outer protective transparent tube (911) is a hard transparent structure, the gas sensing strip (912) is an elastically sealed film structure, and the gas sensing strip (912) is also a dark color.