Optimal configuration method of rural integrated energy system based on rice field water-saving irrigation

Through distributed photovoltaic-wind power-pumped storage battery system and whale optimization algorithm, the problems of high investment costs and insufficient power supply reliability in the integrated energy system in remote areas are solved, and the dual optimization of economy and reliability is achieved. Water-saving irrigation control reduces nitrogen leaching in rice fields.

CN117578562BActive Publication Date: 2024-11-05SICHUAN AGRI UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311469600.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-07
Publication Date
2024-11-05
Estimated Expiration
2043-11-07

Smart Images

  • Figure CN117578562B_ABST
    Figure CN117578562B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for optimizing the configuration of a rural integrated energy system based on rice field water-saving irrigation. The method comprehensively uses rice fields and energy-storage hydropower stations as a pumped storage battery to build a distributed photovoltaic-wind power-pumped storage battery HRES system. Based on economic and technical indicators, the number of photovoltaic panels N in the HRES system is used as the optimal configuration method. PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M To optimize the parameters, the energy model of each module is established, the constraints of the main function of HRES system capacity and fitness function are introduced, and the optimal planning scheme generated by the iterative whale optimization algorithm is used to effectively reduce the initial investment cost of the system while ensuring the reliability of power supply. In addition, the hydropower station can be used to control the water level of the rice field according to the water demand of rice in different growth periods, thereby achieving water-saving irrigation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of energy system optimization configuration method, in particular to a rural comprehensive energy system optimization configuration method based on rice field water-saving irrigation. Background Art

[0002] Due to the vast territory of my country, some relatively remote areas have not yet formed a weak connection with the power grid. Compared with the grid-connected integrated energy system with relatively rich research results, the off-grid integrated energy system has the advantages of low cost and flexible deployment. Therefore, using energy storage capacity optimization configuration technology to promote the optimization of wind, solar and storage microgrids has become a current research hotspot.

[0003] The wind, solar, and microgrid energy storage system is the most classic off-grid integrated energy system in the field of power systems. Domestic and foreign scholars have conducted some research on the configuration of energy storage capacity of the power grid. For example, considering the randomness and intermittency of wind, solar, and microgrid energy storage, the system reliability is poor when it is powered alone. Hydropower units with rapid start-up, flexible adjustment, and fast load response can be added to quickly compensate and adjust them. Therefore, it is proposed to develop hydropower in a complementary way with wind power, photovoltaics, and energy storage devices. However, most of the literature does not combine the system with actual scenarios, which may make the planning of integrated energy systems unreasonable when they are actually applied in remote areas, resulting in increased investment costs.

[0004] In addition, although RES for power generation is easy to obtain, it takes a lot of investment to convert renewable energy into electricity. At present, some scholars have proposed a capacity configuration optimization scheme for photovoltaic pumped storage hybrid renewable energy system (HRES) based on particle swarm optimization (PSO). The results show that the investment cost of renewable energy can be effectively reduced. However, the article does not mention the reliability of power supply, and the randomness and uncertainty of photovoltaic power generation. The research content of this article can be further expanded. Summary of the invention

[0005] The purpose of the present invention is to provide an optimization configuration method for a rural integrated energy system based on paddy field water-saving irrigation. On the basis of economic and technical indicators, the probability of load power shortage is introduced for game theory, and an operation plan for a new rural integrated energy system combining wind, solar and storage with paddy field water-saving irrigation is proposed. At the same time, the optimal planning scheme generated by the iteration of the emerging whale optimization algorithm effectively reduces the initial investment cost of the system while ensuring the reliability of power supply.

[0006] The purpose of the present invention is achieved through the following technical solutions:

[0007] A rural integrated energy system optimization configuration method based on rice field water-saving irrigation, characterized in that: the integrated energy system includes a distributed photovoltaic-wind power-pumped storage battery HRES system constructed by taking the rice field and the energy-storage hydropower station as a pumped storage battery, the HRES system provides electric energy to the external power load, when there is surplus electricity in the HRES system, a variable speed pump is used to pump water in the lower reservoir to the upper reservoir, and the surplus electric energy is converted into water potential energy for storage, the upper reservoir drives a turbine to generate electricity during the irrigation process of the rice field, and drives the variable speed pump to pump water for energy storage after the water is collected; the method includes:

[0008] S1, the number of photovoltaic panels in the HRES system N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M To optimize the parameters, the main function of HRES system capacity is constructed as follows:

[0009]

[0010] Where N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV (t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh;

[0011] S2. The fitness function A is constructed based on the load power shortage probability LPSP as follows:

[0012]

[0013] Where P local (t) represents the load power of the local annual load power curve, in kW; N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV (t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh;

[0014] S3. The fitness function B is constructed based on the levelized cost of energy LCOE as follows:

[0015]

[0016] In the formula, C TAC It represents the total cost of the system in one year, including the initial cost and operating cost of wind power generation module, photovoltaic power generation module and pumped storage hydropower module in one year, in $; E served It represents the total energy provided to the load during the life cycle of the system, in kWh;

[0017] S4. Under the constraints of the HRES system capacity main function, fitness function A, and fitness function B, the whale optimization algorithm WOA is used to optimize the system capacity configuration. The optimization parameters of the HRES system capacity main function in step S1 are used to minimize the levelized energy cost in step S3 under the condition that the probability of load power shortage in step S2 is zero. The corresponding optimization parameter value is output as the optimal configuration capacity of the system.

[0018] Furthermore, in the HRES system, the photovoltaic output power model is as follows:

[0019] P PV =[η inv ·η loss ·η ref ·(1-k·(T0-T ref ))]·G β

[0020] In the formula, G β Represents the solar radiation on the surface of the photovoltaic panel, in W / m 2 ; T ref represents 25℃, T0 represents the temperature of the photovoltaic panel, in ℃; η ref Indicates that the photovoltaic panel is at T ref = Reference efficiency at 25°C; k represents the temperature coefficient, η inv Indicates inverter efficiency, unit is %, η loss Represents other power generation losses in %.

[0021] Furthermore, in the HRES system, the wind turbine output power model is as follows:

[0022]

[0023] Where, V represents the wind speed at the height of the wind rotor, in m / s; P R Indicates the rated power of the fan, in kw; V R 、V ci 、V coRespectively represent the fan rated, cut-in and cut-out wind speeds, in m / s.

[0024] Furthermore, in the pumped storage battery, the paddy field water storage height model is as follows:

[0025] H i =H i-1 +P i +M i -ET i -DP i -C i

[0026] V i =H i ×x×y

[0027] V imax =max{V i}

[0028] In the formula, H i represents the water storage height of the paddy field on the i-th day, in mm; H i-1 represents the water storage height of the paddy field on the i-1th day, in mm; P i Indicates the rainfall on the i-th day, in mm; M i Indicates the irrigation water on the i-th day, in mm; ET i Indicates the crop water requirement on day i, in mm; DP i represents the deep leakage on the i-th day, in mm; C i represents the water discharge on the ith day, in mm; V i Represents the volume of the terrace on the i-th day, in mm 3 ; V imax Indicates the maximum volume of all terrace volumes counted, in mm 3 ; x, y represent the length and width of the rice field, respectively, in mm.

[0029] Furthermore, the energy storage hydropower station is mainly composed of a reversible pump turbine and upper and lower reservoirs, wherein the reversible pump turbine can realize the power generation mode of the turbine and the pumping mode of the variable speed pump, the power generation power when it works in the turbine power generation mode is regarded as the power generation power of the pumped storage battery, and the power consumption power when it works in the pumping pump power consumption mode is regarded as the power consumption power of the pumped storage battery, and the total power generation when the upper reservoir is at the maximum capacity is the maximum capacity of the pumped storage battery;

[0030] The relationship model between the amount of water released and the amount of power generated in the power generation mode is as follows:

[0031]

[0032] Vm =V imax +Q dis

[0033] In the formula, Q dis Indicates the amount of water released by the upper reservoir for power generation, in m 3 ; E T The amount of water released is Q dis The electrical energy generated by the turbine is expressed in kWh; g represents the acceleration due to gravity in m / s 2 ;Q T Indicates the throughput of the turbine in m 2 / s; h0 represents the water level drop of the upper reservoir, in m; η T It represents the total efficiency of the turbine in %; ρ represents the density of water in kg / m 3 ; a, b represent the length and width of the upper reservoir, respectively, in meters;

[0034] The relationship model between the energy consumption of the pumping mode and the amount of water pumped is as follows:

[0035]

[0036]

[0037] In the formula, Q pump Indicates the amount of water drawn from the lower reservoir, in m 3 ; E p Indicates that when the pumping volume is Q pump The electric energy consumed by the variable speed water pump, in kWh; Q p Indicates the throughput of the variable speed water pump, in m 3 / s; η p Indicates the overall efficiency of the variable speed water pump in %.

[0038] Furthermore, in the whale optimization algorithm, an optimization parameter is represented by a whale individual in the optimization of system capacity configuration, and the parameter value of the optimization parameter corresponds to the position of the whale in space. In this method, there are five optimization parameters x1, x2, x3, x4, and x5, which represent the number of photovoltaic panels N respectively. PV 、Number of fans WT , turbine power P T , variable speed water pump power P P and the capacity of the upper reservoir V M , the specific optimization process is as follows:

[0039] Initialize the whale group: After calculating the capacity of the HRES system, assume that the current optimal optimization parameter X in the five-dimensional space of the HRES system is * The parameter value is At this time, the number of iterations k = 1, given the initial optimization parameter X j The value of Then, under the influence of the best optimization parameter, initialize the optimization parameter X j The next parameter value closer to the best optimized parameter The calculation formula is as follows:

[0040]

[0041] C1=2r2

[0042] A1=2a·r1-a

[0043] In the formula, Represents the spatial coordinate X j+1 The kth optimization parameter of D, in this method, k≤5; k Indicates that the absolute value of || in the calculation formula is calculated; a decreases linearly from 2 to 0 as the number of iterations increases; r1 and r2 are both random numbers between 0 and 1;

[0044] Fitness function calculation: the parameter value Set as the number of photovoltaic panels N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M The optimization parameters are obtained, and the load power shortage probability LPSP is calculated according to the fitness function A. If the load power shortage probability is not 0, the optimization parameters need to be updated again. If the load power shortage probability is 0, the investment cost data is substituted to calculate the levelized energy cost. The number of iterations N is accumulated successively in the above two processes of comparison with the fitness function. In the program loop, through continuous searching and iteration, when the number of iterations N is greater than the specified value, the five optimization parameter values ​​corresponding to the minimum levelized energy cost are output.

[0045] The present invention has the following advantages: by constructing a distributed photovoltaic-wind power-pumped storage battery HRES system, on the basis of economic and technical indicators, an energy model of each module is established, and the constraints of the HRES system production capacity main function and fitness function are introduced. The optimal planning scheme generated by the iterative use of the whale optimization algorithm can effectively reduce the initial investment cost of the system while ensuring the reliability of power supply. In addition, the hydropower station can be used to control the water level of the rice field according to the water demand of rice in different growth periods, thereby realizing water-saving irrigation. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 This is a flow chart for optimizing the integrated energy system of the present invention.

[0047] Figure 2 This is a graph showing the change in levelized energy cost with the number of iterations. DETAILED DESCRIPTION

[0048] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0049] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features of the embodiments may be combined with each other.

[0051] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0052] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the invention is usually placed when in use, or the positions or positional relationships commonly understood by those skilled in the art, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0053] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0054] The present invention provides a method for optimizing the configuration of a rural integrated energy system based on water-saving irrigation of rice fields. The integrated energy system includes a distributed photovoltaic-wind power-pumped storage battery HRES system that uses the rice field and the energy-storage hydropower station as a pumped storage battery. The HRES system provides electric energy to external power loads. When there is surplus electricity in the HRES system, a variable-speed pump is used to pump water in a lower reservoir to an upper reservoir, and the surplus electric energy is converted into water potential energy for storage. The upper reservoir drives a turbine to generate electricity during the irrigation process of the rice field, and then drives a variable-speed pump to pump water for energy storage after the water is collected.

[0055] Specifically, the energy storage hydropower station is mainly composed of a reversible pump turbine and upper and lower reservoirs. When the total power generation of photovoltaic and wind power generation is greater than the local load demand, because the electric energy cannot be stored in large quantities, in order to improve the utilization rate of electric energy for power generation, the excess electric energy drives the variable-speed pump to pump the water from the lower reservoir to the upper reservoir for dumping. When the total power generation of photovoltaic and wind power generation is not enough to meet the local load demand, the water is discharged downward through the upper reservoir to drive the turbine to generate electricity. When the demand for irrigation of rice fields and crops is large, priority is given to releasing the stored water into the rice fields, and a control connecting rod float liquid level switch is set in the rice fields to control the water level. The method includes:

[0056] S1, the number of photovoltaic panels in the HRES system N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M To optimize the parameters, the main function of HRES system capacity is constructed as follows:

[0057]

[0058] Where N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV(t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh;

[0059] S2. The fitness function A is constructed based on the load power shortage probability LPSP as follows:

[0060]

[0061] Where P local (t) represents the load power of the local annual load power curve, in kW; N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV (t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh;

[0062] S3. The fitness function B is constructed based on the levelized cost of energy LCOE as follows:

[0063]

[0064] In the formula, C TAC It represents the total cost of the system in one year, including the initial cost and operating cost of wind power generation module, photovoltaic power generation module and pumped storage hydropower module in one year, in $; E served It represents the total energy provided to the load during the life cycle of the system, in kWh;

[0065] S4. Under the constraints of the HRES system capacity main function, fitness function A, and fitness function B, the whale optimization algorithm WOA is used to optimize the system capacity configuration. The optimization parameters of the HRES system capacity main function in step S1 are used to minimize the levelized energy cost in step S3 under the condition that the probability of load power shortage in step S2 is zero. The corresponding optimization parameter value is output as the optimal configuration capacity of the system.

[0066] The HRES system is composed of multiple modules including photovoltaic power stations, wind power stations, energy-storage hydropower stations, and rice fields. Therefore, the research on the mathematical model construction of each module is more conducive to the overall planning of the HRES system.

[0067] In the HRES system, the photovoltaic power generation is determined by factors such as light intensity, temperature and tilt angle. In the planning stage, a more accurate photovoltaic array model is used to evaluate the actual performance of the photovoltaic panel. The specific photovoltaic output power model is as follows:

[0068] P PV =[η inv ·η loss ·η ref ·(1-k·(T0-T ref ))]·G β

[0069] In the formula, G β Represents the solar radiation on the surface of the photovoltaic panel, in W / m 2 ; T ref represents 25℃, T0 represents the temperature of the photovoltaic panel, in ℃; η ref Indicates that the photovoltaic panel is at T ref = Reference efficiency at 25°C; k represents the temperature coefficient, η inv Indicates inverter efficiency, unit is %, η loss Represents other power generation losses in %.

[0070] The objective function N is introduced into this model: the number of photovoltaic panels PV Optimize photovoltaic power generation modules. PV Represents the number of photovoltaic panels. By optimizing this parameter, the optimal size of photovoltaic power generation in the system can be determined. Based on the available solar resources and power demand, the number of photovoltaics is determined to maximize the energy demand while minimizing the total cost of system construction and operation.

[0071] In the HRES system, the wind turbine output power model includes the wind turbine basic power equation model and the wind turbine power output curve model. The wind power generation of the wind turbine can be calculated from the power output curve, the wind speed at the wind turbine installation location, and the height of the tower. The wind turbine output power is represented by a piecewise function of the power output curve. The specific wind turbine output power model is as follows:

[0072]

[0073] Where, V represents the wind speed at the height of the wind rotor, in m / s; P R Indicates the rated power of the fan, in kw; V R 、V ci 、V co Respectively represent the fan rated, cut-in and cut-out wind speeds, in m / s.

[0074] In this model, the objective function, the number of fans N, is introduced. WTOptimize. The number of wind turbines is the number of wind power generation equipment in the system. By optimizing the number of wind turbines, the most suitable wind power generation scale can be determined to maximize power production. This requires considering the available wind resources, the performance characteristics of the wind turbines, and the power demand. Optimizing this parameter helps improve the energy efficiency of the system and the reliability of power supply.

[0075] In the rice field module of the HRES system, the amount of water storage required for rice crops at different time periods during a growth cycle is also different, and the water storage capacity of the rice field is a consideration for the optimal configuration of the integrated energy system. Therefore, it is necessary to study the impact of the water storage height of the rice field at different growth stages on the system optimization strategy.

[0076] At the same time, due to the high level of nitrogen fertilizer application in rice fields, unreasonable irrigation and drainage management during agricultural production causes nitrogen in rice fields to enter groundwater through leaching, which in turn leads to serious groundwater pollution. In this regard, in order to reduce the amount of nitrogen leaching in rice fields and reduce groundwater pollution, it is necessary to reasonably control the water storage height of rice fields. In response to this problem, in the constructed pumped storage battery, this application constructs a water delivery-outlet pool with a bottom surface equal to the surface of the rice field between the upper reservoir with a large amount of water storage and the rice field. It can not only serve as a buffer zone when the hydropower station delivers water to the rice field, preventing the problem of excessive valve water flow causing the rice field crops to be washed away and flooded, but also conveniently adopts a 3-point connecting rod float liquid level control switch here to set the highest and lowest water levels. When the float system reaches the predetermined position with the liquid level, the sluice gate is closed to realize real-time monitoring of the water level in the rice field. At the same time, a return water pool is set up next to the outlet pool to treat the large amount of water stored in the rice fields where the unabsorbed pesticides and fertilizers are stored: when wind and solar energy resources are sufficient and wind and photovoltaic power generation have surplus electricity, the terrain difference between the return water pool and the outlet water pool is used to collect rice field wastewater in the return water pool. When the rice fields need irrigation, the wastewater rich in nutrients such as nitrogen, phosphorus, potassium, and zinc flows back to the rice fields, which not only saves water costs but also greatly improves the utilization rate of nitrogen fertilizers, reduces leaching rate, and improves soil fertility, especially for the dry-wet alternating period of rice growth. When the power stations supported by wind and solar energy are insufficient to supply local load demand, the hydropower station in the upper reservoir will open the valve to transport a large amount of water resources to the rice fields. In order to prevent the rice fields from storing too much water, the wastewater in the return water pool is treated and discharged in time to prevent the nitrogen element in the wastewater from entering the surrounding soil and water bodies through leaching, surface runoff, etc. The present application realizes water irrigation control by pumping water from a hydropower station in a superior reservoir, thereby achieving water-saving irrigation and reducing nitrogen leaching loss from rice fields.

[0077] The amount of water in the rice field during different growth periods of the crop depends on the increase and decrease of water supply and water consumption during the period. Therefore, in the pumped storage battery, the water storage height of the rice field is modeled as follows:

[0078] H i =H i-1 +Pi +M i -ET i -DP i -C i

[0079] V i =H i ×x×y

[0080] V imax =max{V i}

[0081] In the formula, H i represents the water storage height of the paddy field on the i-th day, in mm; H i-1 represents the water storage height of the paddy field on the i-1th day, in mm; P i Indicates the rainfall on the i-th day, in mm; M i Indicates the irrigation water on the i-th day, in mm; ET i Indicates the crop water requirement on day i, in mm; DP i represents the deep leakage on the i-th day, in mm; C i represents the water discharge on the ith day, in mm; V i Represents the volume of the terrace on the i-th day, in mm 3 ; V imax Indicates the maximum volume of all terrace volumes counted, in mm 3 ; x, y represent the length and width of the rice field, respectively, in mm.

[0082] In the process of rice field irrigation control, since the hydropower station of the upper reservoir is built on a higher ground, there is no need to pump water to the rice field. When the water demand of the rice field increases, the hydropower station opens the gate and transports water to the rice field through the pipeline, and drives the turbine part of the reversible pump turbine to generate electricity. The outlet pool is also used to adjust the water temperature and stabilize the water level. On the one hand, it increases the drying time to increase the water temperature, and on the other hand, it can weaken the interference of drainage shock fluctuations on the water level monitoring equipment. When irrigating the rice field, the backwater baffle should be closed to prevent the irrigation water from flowing to the backwater pool. When the water level of the rice field needs to be lowered by drainage after the rice in the rice field is harvested, the backwater baffle is opened to allow the rice field wastewater to flow into the backwater pool and then be treated. When the water demand for rice sowing increases again, the nutrient-rich wastewater is pumped from the backwater pool into the rice field to achieve the reuse of wastewater until the water in the backwater pool can no longer be irrigated. The sewage can be self-flowing to the sewage treatment center through the pipeline for centralized treatment, so that irrigation and drainage rely on the gravity of water.

[0083] The energy storage hydropower station is mainly composed of a reversible pump turbine and upper and lower reservoirs. The reversible pump turbine can realize both the power generation mode of the turbine and the pumping mode of the variable speed pump. When the reversible pump turbine is running, the water levels of the upper and lower reservoirs will change. The power generation water released by the upper reservoir every hour cannot exceed the throughput of the turbine in the power generation mode and the remaining water in the upper reservoir, and the water pumped by the lower reservoir cannot exceed the throughput of the variable speed pump in the power consumption mode and the upper limit of the upper reservoir. Therefore, the water level of the upper reservoir needs to be updated every hour. Since the process of irrigation of rice fields by water release from the upper reservoir is a self-flow of water, and the water released from the upper reservoir during irrigation can drive the turbine part of the reversible pump turbine to generate electricity, the electric energy collected in the hydropower station can drive the reversible pump turbine to pump water to the upper reservoir, that is, the power generation and electricity consumption process of the rice field and the energy storage hydropower station has a strong correlation, therefore, in this method, the two are regarded as a pumped storage battery. And in this pumped storage battery model, the turbine power generation mode power P is introduced T , variable speed water pump power P P and the capacity of the upper reservoir V M , optimize these three parameters. The power generation of the reversible pump turbine when working in the turbine power generation mode is regarded as the power generation of the pumped storage battery, the power consumption of the reversible pump turbine when working in the pumping power consumption mode is regarded as the power consumption of the pumped storage battery, and the total power generation when the upper reservoir is at the maximum capacity is the maximum capacity of the pumped storage battery;

[0084] By optimizing turbine power, the most appropriate turbine size can be selected to maximize the use of water resources for power generation; by optimizing pump power, the appropriate energy storage capacity and the size of the energy storage system can be determined. This is very important for balancing power supply and demand, storing energy, and releasing electricity. Through reasonable energy storage system planning, the stability and flexibility of the system can be improved; by optimizing the capacity of the upper reservoir, the most appropriate reservoir capacity can be determined according to the seasonal water volume changes in the rice fields and the pumping and release needs of the hydropower station, which helps to determine the maximum capacity of the pumped storage battery composed of the rice fields and the energy storage hydropower station to meet the water demand in different seasons and maximize the power generation potential of the hydropower station.

[0085] The relationship model between the amount of water released and the amount of power generated in the power generation mode is as follows:

[0086]

[0087] V m =V imax +Q dis

[0088] In the formula, Q dis Indicates the amount of water released by the upper reservoir for power generation, in m3 ; E T The amount of water released is Q dis The electrical energy generated by the turbine is expressed in kWh; g represents the acceleration due to gravity in m / s 2 ;Q T Indicates the throughput of the turbine in m 2 / s; h0 represents the water level drop of the upper reservoir, in m; η T It represents the total efficiency of the turbine in %; ρ represents the density of water in kg / m 3 ; a, b represent the length and width of the upper reservoir, respectively, in meters;

[0089] Specifically, the relationship model between the energy consumption of the pumping mode and the amount of water pumped is as follows:

[0090]

[0091]

[0092] In the formula, Q pump Indicates the amount of water drawn from the lower reservoir, in m 3 ; E p Indicates that when the pumping volume is Q pump The electric energy consumed by the variable speed water pump, in kWh; Q p Indicates the throughput of the variable speed water pump, in m 3 / s; η p Indicates the overall efficiency of the variable speed water pump in %.

[0093] Considering the probability of power shortage of the integrated energy system load and the constraints of each component of the system model, the whale optimization algorithm is used to optimize the system capacity configuration. In the whale optimization algorithm to optimize the system capacity configuration, an optimization parameter is represented by a whale individual, and the parameter value of the optimization parameter corresponds to the position of the whale in space. In this method, there are five optimization parameters x1, x2, x3, x4, and x5, which represent the number of photovoltaic panels N respectively. PV 、Number of fans WT , turbine power P T , variable speed water pump power P P and the capacity of the upper reservoir V M , the specific optimization process is as follows:

[0094] Initialize the whale group: After calculating the capacity of the HRES system, assume that the current optimal optimization parameter X in the five-dimensional space of the HRES system is * The parameter value is At this time, the number of iterations k = 1, given the initial optimization parameter X j The value of Then, under the influence of the best optimization parameter, initialize the optimization parameter X j The next parameter value closer to the best optimized parameter The calculation formula is as follows:

[0095]

[0096] C1=2r2

[0097] A1=2a·r1-a

[0098] In the formula, Represents the spatial coordinate X j+1 The kth optimization parameter of D, in this method, k≤5; k Indicates that the absolute value of || in the calculation formula is calculated; a decreases linearly from 2 to 0 as the number of iterations increases; r1 and r2 are both random numbers between 0 and 1;

[0099] Fitness function calculation: the parameter value Set as the number of photovoltaic panels N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M The optimization parameters are obtained, and the load power shortage probability LPSP is calculated according to the fitness function A. If the load power shortage probability is not 0, the optimization parameters need to be updated again. If the load power shortage probability is 0, the investment cost data is substituted to calculate the levelized energy cost. The number of iterations N is accumulated successively in the above two processes of comparison with the fitness function. In the program loop, through continuous searching and iteration, when the number of iterations N is greater than the specified value, the five optimization parameter values ​​corresponding to the minimum levelized energy cost are output.

[0100] like Figure 1 As shown in the figure, in the main function of the HRES system capacity, the integer variables (number of wind turbines and number of photovoltaic panels) will be processed as integers after updating the position of the whale group using the above formula; first, the fitness function load power shortage probability is calculated to evaluate whether the target is met. If the target is not met, the individual whale (position and speed) will be updated again. When the target is met, the fitness function levelized energy cost is calculated. Then repeat the above steps until all iterations are completed. Finally, under the condition of ensuring power supply reliability, the system investment cost is minimized by comparing economic and technical indicators, thereby obtaining the optimal planning result of the system.

[0101] By analyzing the duration, power supply reliability, and system cost of the whale optimization algorithm, the number of photovoltaic panels N can be obtained. PV 、Number of fans WT, turbine power P T , variable speed water pump power P P and the capacity of the upper reservoir V M The optimal planning strategy ultimately achieves the dual optimization of the economy and reliability of the integrated energy system based on rice field irrigation. WT and the number of photovoltaic panels N PV These two parameters can change the power generation of these two parts. After substituting the entire model into the system, the power demand of users in previous years is used as the search space. Then, taking the economic optimum as the objective function, the power P of the turbine power generation mode is T , variable speed water pump power P P and the capacity of the upper reservoir V M These three parameters are optimized by optimizing the data iteration of the whale algorithm, judging whether the constraints are met, and constantly comparing the system economy to finally obtain the five optimized parameters in the system model.

[0102] In terms of system planning efficiency, Figure 2 As shown in the figure, the image data shows that the WOA algorithm and the PSO algorithm gradually reduce the value of the system's levelized energy cost during the optimization process. When we observe the two algorithms for 250 iterations of optimization, we can clearly see that the average energy cost gradually decreases and eventually stabilizes, which indicates that the algorithm has successfully found the optimal solution for the capacity planning of each part of the system. As can be seen from the drawing, within the same number of iterations, the WOA algorithm can find the five optimal parameter values ​​related to the minimum average energy cost more quickly and accurately. This is due to the bionic characteristics of the WOA algorithm, which simulates the behavior of whales and has excellent global search capabilities. In addition, the WOA algorithm also continuously adjusts the position and search radius of the whale, which helps to find the best solution more quickly. Therefore, using the WOA algorithm for system planning will significantly improve the efficiency of system planning.

[0103]

[0104] It can be seen from the table above that as the number of iterations increases, the optimized parameters such as the number of photovoltaic panels, the power of the reversible pump turbine and the capacity of the upper reservoir will be significantly reduced. This reduction trend is caused by optimizing the capacity of three parts in the system: wind power generation, photovoltaic power generation, and pumped storage batteries composed of hydropower stations and rice fields. This series of optimizations not only effectively cuts the initial investment cost, but also reduces the subsequent operation and maintenance expenses, bringing significant improvements to the sustainability and economic benefits of the entire system.

[0105] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A rural integrated energy system optimization configuration method based on rice field water-saving irrigation, characterized by: The integrated energy system includes a distributed photovoltaic-wind power-pumped storage battery HRES system that uses a rice field and a storage hydropower station as a pumped storage battery. The HRES system provides electric energy to external power loads. When there is surplus electricity in the HRES system, a variable-speed pump is used to pump water from a lower reservoir to an upper reservoir, and the surplus electric energy is converted into water potential energy for storage. The upper reservoir drives a turbine to generate electricity during the irrigation process of the rice field, and then drives a variable-speed pump to pump water for energy storage after the water is collected. The method includes: S1, the number of photovoltaic panels in the HRES system N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M To optimize the parameters, the main function of HRES system capacity is constructed as follows: Where N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV (t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh; S2. The fitness function A is constructed based on the load power shortage probability LPSP as follows: Where P local (t) represents the load power of the local annual load power curve, in kW; N WT P represents the number of fans expected to be installed in the system. WT (t) represents the average annual power output of a single wind turbine, in kW; N PV Indicates the number of photovoltaic panels expected to be installed in the system, P PV (t) represents the annual power that a single photovoltaic panel can generate, in kW; E T (t) represents the energy stored in the pumped storage battery, in kWh; S3. The fitness function B is constructed based on the levelized cost of energy LCOE as follows: In the formula, C TAC It represents the total cost of the system in one year, including the initial cost and operating cost of wind power generation module, photovoltaic power generation module and pumped storage hydropower module in one year, in $; E served It represents the total energy provided to the load during the life cycle of the system, in kWh; S4. Under the constraints of the HRES system capacity main function, fitness function A, and fitness function B, the whale optimization algorithm WOA is used to optimize the system capacity configuration. The optimization parameters of the HRES system capacity main function in step S1 are used to minimize the levelized energy cost in step S3 under the condition that the probability of load power shortage in step S2 is zero. The corresponding optimization parameter value is output as the optimal configuration capacity of the system.

2. The method for optimizing the configuration of a rural integrated energy system based on water-saving irrigation of rice fields according to claim 1, characterized in that: In the HRES system, the photovoltaic output power model is as follows: P PV =[η inv ·η loss ·η ref ·(1-k·(T0-T ref ))]·G β In the formula, G β Represents the solar radiation on the surface of the photovoltaic panel, in W / m 2 ; T ref represents 25°C, T0 represents the temperature of the photovoltaic panel in °C; η ref Indicates that the photovoltaic panel is at T ref = Reference efficiency at 25°C; k represents the temperature coefficient, η inv Indicates inverter efficiency, unit is %, η loss Represents other power generation losses in %.

3. The method for optimizing the configuration of a rural integrated energy system based on rice field water-saving irrigation according to claim 1, characterized in that: In the HRES system, the wind turbine output power model is as follows: Where, V represents the wind speed at the height of the wind rotor, in m / s; P R Indicates the rated power of the fan, in kw; V R 、V ci 、V co Respectively represent the fan rated, cut-in and cut-out wind speeds, in m / s.

4. The method for optimizing the configuration of a rural integrated energy system based on rice field water-saving irrigation according to claim 1, characterized in that: In the pumped storage battery, the paddy field water storage height model is as follows: H i =H i-1 +P i +M i -AND i -DP i -C i V i =H i ×x×y V imax =max{V i } In the formula, H i represents the water storage height of the paddy field on the i-th day, in mm; H i-1 represents the water storage height of the paddy field on the i-1th day, in mm; P i Indicates the rainfall on the i-th day, in mm; M i Indicates the irrigation on the i-th day, in mm; ET i Indicates the crop water requirement on day i, in mm; DP i represents the deep leakage on the i-th day, in mm; C i represents the displacement on the i-th day, in mm; V i Represents the volume of the terrace on the i-th day, in mm 3 ; V imax Indicates the maximum volume of all terrace volumes counted, in mm 3 ; x, y represent the length and width of the rice field, respectively, in mm.

5. The method for optimizing the configuration of a rural integrated energy system based on rice field water-saving irrigation according to claim 4, characterized in that: The energy storage hydropower station is mainly composed of a reversible pump turbine and upper and lower reservoirs, wherein the reversible pump turbine can realize both the power generation mode of the turbine and the pumping mode of the variable speed pump. The power generation power when it works in the turbine power generation mode is regarded as the power generation power of the pumped storage battery, and the power consumption power when it works in the pumping pump power consumption mode is regarded as the power consumption power of the pumped storage battery. The total power generation when the upper reservoir is at the maximum capacity is the maximum capacity of the pumped storage battery. The relationship model between the amount of water released and the amount of power generated in the power generation mode is as follows: V m =V imax +Q dis In the formula, Q dis Indicates the amount of water released by the upper reservoir for power generation, in m 3 ; E T The amount of water released is Q dis The electrical energy generated by the turbine is expressed in kWh; g represents the acceleration due to gravity in m / s 2 ;Q T Indicates the throughput of the turbine in m 2 / s; h0 represents the water level drop of the upper reservoir, in m; η T It represents the total efficiency of the turbine in %; ρ represents the density of water in kg / m 3 ; a, b represent the length and width of the upper reservoir, respectively, in meters; The relationship model between the energy consumption of the pumping mode and the amount of water pumped is as follows: In the formula, Q pump Indicates the amount of water drawn from the lower reservoir, in m 3 ; E p Indicates that when the pumping volume is Q pump The electric energy consumed by the variable speed water pump, in kWh; Q p Indicates the throughput of the variable speed water pump, in m 3 / s; η p Indicates the overall efficiency of the variable speed water pump in %.

6. The method for optimizing the configuration of a rural integrated energy system based on water-saving irrigation of rice fields according to claim 1, characterized in that: In the whale optimization algorithm, an optimization parameter is represented by a whale individual in the optimization of system capacity configuration. The parameter value of the optimization parameter corresponds to the position of the whale in space. In this method, there are five optimization parameters x1, x2, x3, x4, and x5, which represent the number of photovoltaic panels N respectively. PV 、Number of fans WT , turbine power P T , variable speed water pump power P P and the capacity of the upper reservoir V M , the specific optimization process is as follows: Initialize the whale group: After calculating the capacity of the HRES system, assume that the current optimal optimization parameter X in the five-dimensional space of the HRES system is * The parameter value is At this time, the number of iterations k = 1, given the initial optimization parameter X j The value of Then, under the influence of the best optimization parameter, initialize the optimization parameter X j The next parameter value closer to the best optimized parameter The calculation formula is as follows: C1=2r2 A1=2a·r1-a In the formula, Represents the spatial coordinate X j+1 The kth optimization parameter of D, in this method, k≤5; k Indicates that the absolute value of || in the calculation formula is calculated; a decreases linearly from 2 to 0 as the number of iterations increases; r1 and r2 are both random numbers between 0 and 1; Fitness function calculation: the parameter value Set as the number of photovoltaic panels N PV 、Number of fans WT , turbine power generation mode P T , variable speed water pump power P P and the capacity of the upper reservoir V M The optimization parameters are obtained, and the load power shortage probability LPSP is calculated according to the fitness function A. If the load power shortage probability is not 0, the optimization parameters need to be updated again. If the load power shortage probability is 0, the investment cost data is substituted to calculate the levelized energy cost. The number of iterations N is accumulated successively in the above two processes of comparison with the fitness function. In the program loop, through continuous searching and iteration, when the number of iterations N is greater than the specified value, the five optimization parameter values ​​corresponding to the minimum levelized energy cost are output.