A shield tunneling pile cutting test device

By using a shield tunneling pile cutting test device, stress redistribution in the pile body and segment damage were monitored, which solved the problem of insufficient research on pile deformation and internal stress redistribution during shield tunneling pile cutting, and realized the simulation and damage assessment of secondary lining.

CN117804938BActive Publication Date: 2026-11-17ZHENGZHOU UNIV +2
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410020123.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-07
Publication Date
2026-11-17
Estimated Expiration
2044-01-07

AI Technical Summary

Technical Problem

Existing technologies have failed to effectively study the overall deformation and internal stress redistribution process of the pile body during shield tunneling, make it impossible to directly observe the stress damage to the tunnel segments, and make it difficult to determine the timing of secondary lining application.

Method used

A shield tunneling pile cutting test device was designed, including a loading system, a model box, a model pile and a model tunnel. The stress of the pile is monitored by acrylic balls, screws and strain gauges, the segment damage is simulated by luminescent liquid material, and a secondary lining is formed by photocuring liquid.

Benefits of technology

The simulation demonstrated the entire stress-strain process during shield tunneling pile cutting, revealed internal damage to the tunnel segments, provided an opportunity for secondary lining, and improved the criteria for judging tunnel damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117804938B_ABST
    Figure CN117804938B_ABST
Patent Text Reader

Abstract

This invention discloses a shield tunneling pile cutting test device, comprising a loading system, a model box, a model pile, a model tunnel, and an excavation system. The model pile is placed inside the model box, the excavation system is located in front of a circular opening, and the model tunnel is placed on the excavation system. The model pile is assembled from acrylic balls and bolts, and the model tunnel is assembled by adhering tunnel segments to an inner lining cylinder. During the test, transparent soil is filled into the model box, and the model tunnel is pushed to simulate shield tunneling pile cutting. The electrical and optical signals emitted by the test device are recorded. This invention simultaneously collects electrical and optical signals during the experiment, which can establish the stress-strain characteristics of the model pile under punching shear. When the model tunnel fails, the damaged tunnel segments will emit fluorescence, revealing the damaged parts of the tunnel segments under stress. The liquid inside the inner lining cylinder begins to solidify under the influence of fluorescence, subsequently forming a secondary lining that participates in the structural stress, linking tunnel segment damage and secondary lining reinforcement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of subway engineering, and particularly relates to a shield tunneling pile cutting device and a tunnel segment reinforcement test device. Background Technology

[0002] With the continuous development and expansion of underground building structures and transportation networks, and the needs of tunnel construction and operation, engineering phenomena such as shield tunneling pile cutting and anchoring are common. Shield tunneling pile cutting inevitably changes the stress conditions of the pile, forcing the pile to deform and redistribute stress. After the tunnel cuts through the pile, it will directly bear the pile end pressure, and the internal forces of the tunnel segments will undergo abrupt changes, which is extremely detrimental to the tunnel structure. In terms of model testing, current research on shield tunneling pile cutting mainly focuses on the impact of the pile on the tunnel during the cutting process and the stress and strain on the pile surface. Research on tunnel segment damage includes visual judgment from surface cracks and using acoustic emission technology to detect internal damage to the tunnel segments. Research on tunnel segment reinforcement only involves artificially laying secondary lining at fixed times and quantities.

[0003] In summary, current research lacks model tests to study the overall deformation and internal stress redistribution process of the pile during punching, the stress damage process of the tunnel lining segments cannot be directly observed, and the timing of secondary lining application is difficult to determine. To address these research deficiencies, a shield tunneling pile cutting test device was designed and developed. Summary of the Invention

[0004] The purpose of this invention is to: investigate the overall deformation and internal stress redistribution characteristics of the pile body when it is cut through by the shield tunnel, establish a stress-strain model of the pile body under punching failure, and provide data support for correcting theoretical calculations; reveal the internal damage of the tunnel segment, apply secondary lining in a timely manner, and study the deformation characteristics of the tunnel segment under pile end pressure.

[0005] To achieve the above objectives, the present invention adopts the following technical solution:

[0006] A shield tunneling pile cutting test device, characterized in that it includes a loading system 1, a model box 2, a model pile 3, a model tunnel 4, and an excavation system 5; the model pile 3 is placed inside the model box 2, the excavation system 5 is located in front of the circular opening 12, and the model tunnel 4 is placed on the excavation system 5.

[0007] As a further description of the above technical solution:

[0008] The loading system 1 includes a reaction frame 6, a jack 7, a force transmission plate 8, and a force transmission cylinder 9; a cross slide rail 10 is mounted on the reaction frame 6 using a connector 11, and the jack 7 is mounted at the intersection of the cross slide rail 10; a model box 2 is located on the bottom surface of the reaction frame 6 in the loading system 1, and the model box 2 has a circular opening 12. Water pipes 13 are arranged on the left, right, and bottom of the model box 2, and a permeable stone 14 is placed above the bottom water pipe; the model box 2 is made of acrylic and filled with transparent soil.

[0009] As a further description of the above technical solution:

[0010] The model pile 3 is assembled from acrylic spheres 15, screws 16, strain gauges 17, and wires. The acrylic spheres 15 are made of acrylic and have a circular hole on each of the top, bottom, left, right, front, and back, with threads inside the holes. The screws 16 are made of pure aluminum welding wire and have threads on their surface, which can be inserted into the circular holes of the acrylic spheres 15. Adjacent acrylic spheres 15 are connected and assembled by screws 16 to form a sphere group 19. Strain gauges 17 are attached to the middle of the screws 16 in the sphere group 19. The strain gauges 17 are connected to wires, and each wire is connected upward through the holes of the sphere group 19 to an external acquisition system.

[0011] As a further description of the above technical solution:

[0012] The strain gauges 17 are bonded to the middle of the screw 16, and each strain gauge 17 forms a stress field monitoring system; each conductor is bonded to a bundle of reinforcing wires 18, and the bonded reinforcing wires 18 and the ball group 19 form a tensile system of the model pile 3.

[0013] As a further description of the above technical solution:

[0014] The model tunnel 4 is an assembled structure, with the tube segments 20 glued to the surface of the inner lining cylinder 21 and adjacent tube segments 20 bonded together to form the model tunnel 4; the tube segments 20 are frame structures with several honeycomb spaces inside; the inner lining cylinder 21 is a double-layer structure with equal thickness gaps between the walls; the tube segments 20 and the inner lining cylinder 21 are made of acrylic or plexiglass.

[0015] As a further description of the above technical solution:

[0016] The honeycomb spaces inside the tube 20 are filled with luminescent liquid material, which includes two types: one is a mixture of fluorescent dye and diphenyl oxalate, and the other is hydrogen peroxide. The luminescent liquid material filled in adjacent honeycomb spaces is different. The gaps between the walls of the inner lining cylinder 21 are filled with photocurable liquid material, such as photosensitive resin.

[0017] As a further description of the above technical solution:

[0018] The excavation system 5 is located in front of the model box 2 and is fixedly connected to the model box. The excavation system 5 includes a support device 22, a propulsion device 23 and an excavation device 24. The support device 22 has racks distributed on both sides, the propulsion device 23 is fixed on the racks, one end of the excavation device 24 is fitted into the model tunnel 4, and the other end is connected to the excavation device. Laser displacement sensors 25 are distributed on the excavation device 24.

[0019] As a further description of the above technical solution:

[0020] The test using the shield tunneling pile cutting test device described in this invention includes the following steps:

[0021] Step 1: Make acrylic sphere 15 and screw 16; when making tube 20 using 3D printing technology, fill each honeycomb space with luminescent liquid material after printing a row of honeycomb spaces, ensuring that the luminescent liquid material in adjacent honeycomb spaces is different; when making inner lining cylinder 21, fill the gaps between the walls with light-curing liquid material; make transparent soil.

[0022] Step 2: Erect the model box 2 on the bottom surface of the reaction frame 6, lay water pipes 13 and permeable stones 14, seal the circular opening 12 with steel plates, fill the model box with soil, and assemble the model piles 3 at the same time; use screws 16 to connect acrylic balls to form a ball group 19, attach strain gauges 17 to the middle of the screws 16, and glue wires to form reinforcing wires 18. The reinforcing wires 18 pass through the gaps in the ball group 19, and glue the reinforcing wires 18 to the acrylic balls 15; simultaneously fill with transparent soil and assemble the pipe segments.

[0023] Step 3: Place the force transmission cylinder 9 and force transmission plate 8 on top of the transparent soil and model pile 3, adjust the position of the jack 7, and apply pressure to the top of the transparent image inside the model box 2; connect the water pipe 13 to the external water source and inject water into the model box 2.

[0024] Step 4: Adhere the pipe segments 20 to the surface of the inner lining cylinder 21, and glue adjacent pipe segments 20 to form a model tunnel 4; place the model tunnel 4 above the support device 22, fit the excavation device 24 at the end of the model tunnel 4, and set up the propulsion device 23 to form a tunnel excavation system.

[0025] Step 5: Connect the strain gauge 17 and laser displacement sensor 25 to the external monitoring system; use the propulsion device 23 to push the model tunnel 4 and excavation device 24 into the model box 2 through the circular opening 12, and at the same time use tools such as shovels to clean the transparent soil inside the model tunnel 4; as the model tunnel 4 moves forward, take pictures to record the position of the acrylic ball 15 in the model pile 3; when the excavation device 24 touches the model pile 3, use the shovel to remove the acrylic ball 15 layer by layer until the model tunnel 4 is completely pushed into the model box 2.

[0026] Step 6: Adjust the pressure value of jack 7 and take real-time photos to record the position of the light-emitting tube segment 20 in the model tunnel 4; some tube segments 20 emit light to illuminate the inner lining cylinder, and the light-curing liquid material in the irradiated area is cured, forming a secondary lining; during the test, a light source can be used to irradiate specific parts to cure them, and the resulting secondary lining participates in the stress and deformation of the model tunnel.

[0027] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0028] (1) Simulation of the pile body passing under the shield tunnel: A stress-strain process model of the pile body being damaged by shield shearing was established, the trend of bearing capacity change and neutral axis offset characteristics of the pile body during the damage process were explored, and the damage process of the pile body under vibration load was simulated.

[0029] (2) The engineering conditions of a tunnel under vibration load were simulated: the whole process of internal damage and failure of tunnel segments under stress was revealed, and experimental conditions were provided for improving the tunnel damage judgment criteria.

[0030] (3) The process of secondary lining was simulated: After the tunnel segment is damaged, the light-curing liquid between the inner lining cylinder walls is irradiated by the fluorescent light of the segment and locally solidifies, naturally forming a double-layer lining; the light-curing liquid is irradiated with a light source to solidify it in advance to form a secondary lining.

[0031] (4) The compressive and tensile properties of the pile were simulated: the acrylic balls were connected by screws to form a ball group, which provided compressive strength; the strain gauges and reinforcing wires were bonded to the acrylic balls, and the screws and reinforcing wires provided tensile strength.

[0032] (5) This invention provides a test device for simulating shield tunneling through piles. This device can monitor the stress redistribution characteristics when the pile is damaged; reveal the internal damage of tunnel segments and propose a technical means of coupling segment damage and reinforcement; at the same time, it collects the electrical and optical signals fed back by the model, which makes up for the technical deficiency of only being able to collect electrical signals in the past. Attached Figure Description

[0033] Figure 1 This is a three-dimensional structural diagram of the present invention;

[0034] Figure 2 This is a schematic diagram of the loading system and model box;

[0035] Figure 3 This is a schematic diagram of the loading system;

[0036] Figure 4 This is a schematic diagram of the punching model pile for the model tunnel;

[0037] Figure 5 This is a schematic diagram of the model pile assembly;

[0038] Figure 6 This is a schematic diagram of the model tunnel assembly.

[0039] Figure 7 This is a schematic diagram of the excavation system;

[0040] In the diagram: 1-Loading system, 2-Model box, 3-Model pile, 4-Model tunnel, 5-Excavation system, 6-Reaction frame, 7-Jack, 8-Force transmission plate, 9-Force transmission cylinder, 10-Cross slide rail, 11-Connector, 12-Circular opening, 13-Water pipe, 14-Permeable stone, 15-Acrylic ball, 16-Screw, 17-Strain gauge, 18-Firming line, 19-Ball group, 20-Tunnel segment, 21-Inner lining cylinder, 22-Support device, 23-Propulsion device, 24-Excavation device, 25-Laser displacement sensor. Detailed Implementation

[0041] The present invention will be further described below with reference to the accompanying drawings and embodiments:

[0042] It should be noted that the following detailed descriptions are illustrative and intended to provide further explanation of this application. Unless otherwise specified, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains.

[0043] It should be noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the exemplary embodiments according to this application. As used herein, the singular form is intended to include the plural form as well, unless the context clearly indicates otherwise. Furthermore, it should be understood that when the terms "comprising" and / or "including" are used in this specification, they indicate the presence of features, steps, operations, devices, components, and / or combinations thereof.

[0044] In this invention, terms such as "upper," "lower," "left," "right," "front," "back," "vertical," "horizontal," "side," and "bottom" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. These terms are only used to facilitate the description of the structural relationships of the various components or elements of this invention and do not specifically refer to any part or element in this invention. They should not be construed as limiting the invention.

[0045] In this invention, terms such as "fixed," "connected," and "linked" should be interpreted broadly, indicating that the connection can be fixed, integral, or detachable; it can be a direct connection or an indirect connection through an intermediate medium. For researchers or technicians in the field, the specific meaning of the above terms in this invention can be determined according to the specific circumstances, and they should not be construed as limitations on this invention.

[0046] This invention provides a technical solution for a shield tunneling pile cutting test device:

[0047] like Figure 1 , 2As shown, a shield tunneling pile cutting test device includes a loading system 1, a model box 2, a model pile 3, a model tunnel 4, and an excavation system 5; the model pile 3 is placed inside the model box 2, the excavation system 5 is located in front of the circular opening 12, and the model tunnel 4 is placed on the excavation system 5.

[0048] like Figure 2 , 3 As shown, the loading system 1 includes a reaction frame 6, a jack 7, a force transmission plate 8, and a force transmission cylinder 9; the cross slide rail 10 is supported on the reaction frame 6 by a connector 11, and the jack 7 is supported at the intersection of the cross slide rail 10; the model box 2 is located on the bottom surface of the reaction frame 6 in the loading system 1, and the model box 2 has a circular opening 12. Water pipes 13 are arranged on the left, right and bottom of the model box 2, and there is a permeable stone 14 above the bottom water pipe; the model box 2 is made of acrylic and filled with transparent soil.

[0049] like Figure 5 As shown, the model pile 3 is assembled from acrylic spheres 15, screws 16, strain gauges 17, and wires. The acrylic spheres 15 are made of acrylic and have a circular hole on each of the top, bottom, left, right, front, and back, with threads inside the holes. The screws 16 are made of pure aluminum welding wire and have threads on their surface, which can be inserted into the circular holes of the acrylic spheres 15. Adjacent acrylic spheres 15 are connected and assembled by screws 16 to form a sphere group 19. Strain gauges 17 are attached to the middle of the screws 16 in the sphere group 19. The strain gauges 17 are connected to wires, and each wire is connected upward through the holes of the sphere group 19 to the external acquisition system.

[0050] Strain gauges 17 are bonded to the middle of screw 16, and each strain gauge 17 forms a stress field monitoring system; each conductor is bonded to a bundle of reinforcing wires 18, and the bonded reinforcing wires 18 and the ball group 19 form a tensile system of model pile 3.

[0051] like Figure 4 , 6 As shown, the model tunnel 4 is an assembled structure, with the pipe segments 20 glued to the surface of the inner lining cylinder 21 and adjacent pipe segments 20 bonded together to form the model tunnel 4; the pipe segments 20 are a frame structure with several honeycomb spaces inside; the inner lining cylinder 21 is a double-layer structure with equal thickness gaps between the walls; the pipe segments 20 and the inner lining cylinder 21 are made of acrylic or plexiglass.

[0052] The honeycomb spaces inside the tube 20 are filled with luminescent liquid material. There are two types of luminescent liquid material: one is a mixture of fluorescent dye and diphenyl oxalate, and the other is hydrogen peroxide. The luminescent liquid material filled in adjacent honeycomb spaces is different. The gaps between the walls of the inner lining cylinder 21 are filled with photocurable liquid material, such as photosensitive resin.

[0053] like Figure 4 , 7As shown, the excavation system 5 is located in front of the model box 2 and is fixedly connected to the model box. The excavation system 5 includes a support device 22, a propulsion device 23 and an excavation device 24. The support device 22 has racks distributed on both sides, the propulsion device 23 is fixed on the racks, one end of the excavation device 24 is fitted into the model tunnel 4, and the other end is connected to the excavation device. Laser displacement sensors 25 are distributed on the excavation device 24.

[0054] In this embodiment, the position and thrust of the jack 7 can be adjusted, and 7 can be replaced with an impact hammer capable of applying impact loads, thereby applying vibration loads to the soil surface and creating experimental conditions for exploring the internal force response mechanism of the model pile 3 under vibration loads.

[0055] In this embodiment, the model pile 3 is assembled from acrylic spheres 15, screws 16, strain gauges 17, and reinforcing wires 18. The acrylic spheres 15 have non-through holes in the top, bottom, left, right, front, and back directions, and these holes contain threads. The screws 16 are made of pure aluminum welding wire with threads on their surface; the number and spacing of these threads can be predetermined. When the pile is subjected to tension or compression, the acrylic spheres 15 will correspondingly pull and compress the screws 16. The strain gauges 17 are attached to the middle of the screws 16 to monitor their strain. The reinforcing wires 18 not only transmit electrical signals to the external monitoring system but also bond with the acrylic spheres 15 along their path, providing tensile strength to the model pile.

[0056] In this embodiment, the model tunnel 4 is an assembled structure, formed by attaching the tube segments 20 to the surface of the inner lining cylinder 21. The tube segments 20 are manufactured using 3D printing technology and have honeycomb-like spaces inside. During the manufacturing process, a mixture of fluorescent dye and diphenyl oxalate or hydrogen peroxide is added to the honeycomb spaces, with only one type added to each honeycomb space, and adjacent spaces have different types added. The inner lining cylinder 21 is made of acrylic or plexiglass, with equal-thickness gaps between the walls, which are filled with a photocurable liquid material, such as photosensitive resin. When the tube segments are subjected to stress, the honeycomb space walls may break or crack. The liquids in adjacent honeycomb spaces become connected, and the two liquids react to emit fluorescence, irradiating the photocurable liquid material between the walls of the inner lining cylinder 21. The irradiated portion of the photocurable liquid material gradually solidifies, forming a secondary lining that participates in the stress distribution of the model tunnel. A light source can be manually used to irradiate specific areas from the inner lining cylinder 21 to create a secondary lining working area.

[0057] In this embodiment, before the model tunnel 4 is excavated, the circular opening 12 is sealed on the outside with steel plates, etc. When the model tunnel 4 is excavated, the steel plates are removed, the model tunnel 4 is erected, the propulsion device 23 pushes the excavation device 24, the soil seeps into the model tunnel 4, and the soil is removed with tools such as shovels. When the model tunnel cuts the model pile 3, the acrylic ball 15 that has slid into the excavation device is removed with a shovel. It is considered that this part of the model pile 3 has been damaged and is no longer in operation.

[0058] The present invention also provides a test method for a shield tunneling pile cutting test device, the specific steps of which are as follows:

[0059] Step 1: Make acrylic sphere 15 and screw 16; when making tube 20 using 3D printing technology, fill each honeycomb space with luminescent liquid material after printing a row of honeycomb spaces, ensuring that the luminescent liquid material in adjacent honeycomb spaces is different; when making inner lining cylinder 21, fill the gaps between the walls with light-curing liquid material; make transparent soil.

[0060] Step 2: Erect the model box 2 on the bottom surface of the reaction frame 6, lay water pipes 13 and permeable stones 14, seal the circular opening 12 with steel plates, fill the model box with soil, and assemble the model piles 3 at the same time; use screws 16 to connect acrylic balls to form a ball group 19, attach strain gauges 17 to the middle of the screws 16, and glue wires to form reinforcing wires 18. The reinforcing wires 18 pass through the gaps in the ball group 19, and glue the reinforcing wires 18 to the acrylic balls 15; simultaneously fill with transparent soil and assemble the pipe segments.

[0061] Step 3: Place the force transmission cylinder 9 and force transmission plate 8 on top of the transparent soil and model pile 3, adjust the position of the jack 7, and apply pressure to the top of the transparent image inside the model box 2; connect the water pipe 13 to the external water source and inject water into the model box 2.

[0062] Step 4: Adhere the pipe segments 20 to the surface of the inner lining cylinder 21, and glue adjacent pipe segments 20 to form a model tunnel 4; place the model tunnel 4 above the support device 22, fit the excavation device 24 at the end of the model tunnel 4, and set up the propulsion device 23 to form a tunnel excavation system.

[0063] Step 5: Connect the strain gauge 17 and laser displacement sensor 25 to the external monitoring system; use the propulsion device 23 to push the model tunnel 4 and excavation device 24 into the model box 2 through the circular opening 12, and at the same time use tools such as shovels to clean the transparent soil inside the model tunnel 4; as the model tunnel 4 moves forward, take pictures to record the position of the acrylic ball 15 in the model pile 3; when the excavation device 24 touches the model pile 3, use the shovel to remove the acrylic ball 15 layer by layer until the model tunnel 4 is completely pushed into the model box 2.

[0064] Step 6: Adjust the pressure value of jack 7 and take real-time photos to record the position of the light-emitting tube segment 20 in the model tunnel 4; some tube segments 20 emit light to illuminate the inner lining cylinder 21, and the light-curing liquid material in the irradiated area is cured, forming a secondary lining; during the test, a light source can be used to illuminate specific parts to cure them, and the resulting secondary lining participates in the stress and deformation of the model tunnel.

Claims

1. A shielded pile cutting test device characterized by, Includes a loading system (1), a model box (2), model piles (3), a model tunnel (4), and an excavation system (5); the model piles (3) are placed inside the model box (2), the excavation system (5) is located in front of the circular opening (12), and the model tunnel (4) is placed on the excavation system (5); The model tunnel (4) is an assembled structure, with the segments (20) glued to the surface of the inner lining cylinder (21) and adjacent segments (20) bonded together to form the model tunnel (4); the segments (20) are frame structures with several honeycomb spaces inside; the inner lining cylinder (21) is a double-layer structure with equal-thickness gaps between the walls; the segments (20) and the inner lining cylinder (21) are made of acrylic or plexiglass. The honeycomb spaces inside the tube (20) are filled with luminescent liquid material. There are two types of luminescent liquid material: one is a mixture of fluorescent dye and diphenyl oxalate, and the other is hydrogen peroxide. The luminescent liquid material filled in adjacent honeycomb spaces is different. The gaps between the walls of the inner lining cylinder (21) are filled with photosensitive resin.

2. The shield cutting pile test device according to claim 1, characterized in that, The loading system (1) includes a reaction frame (6), a jack (7), a force transmission plate (8), and a force transmission cylinder (9); a cross slide rail (10) is mounted on the reaction frame (6) using a connector (11), and the jack (7) is mounted at the intersection of the cross slide rail (10); the model box (2) is located on the bottom surface of the reaction frame (6) in the loading system (1), and the model box (2) has a circular opening (12). Water pipes (13) are arranged on the left, right and bottom of the model box (2), and there is a permeable stone (14) above the bottom water pipe; the model box (2) is made of acrylic and filled with transparent soil.

3. The shield cutting pile test device according to claim 1, characterized in that, The model pile (3) is assembled from an acrylic ball (15), a screw (16), a strain gauge (17), and a wire. The acrylic ball (15) is made of acrylic and has a round hole on each of its top, bottom, left, right, front, and back, with threads in the round holes. The screw (16) is made of pure aluminum welding wire and has threads on its surface, which can be inserted into the round hole of the acrylic ball (15). Adjacent acrylic balls (15) are connected and assembled by the screw (16) to form a ball group (19). In the ball group (19), a strain gauge (17) is attached to the middle of the screw (16), and the strain gauge (17) is connected to a wire. Each wire is connected upward through the gap of the ball group (19) to the external acquisition system.

4. The shield cutting pile test device according to claim 3, characterized in that, The strain gauges (17) are bonded to the middle of the screw (16), and each strain gauge (17) forms a stress field monitoring system; each conductor is bonded to a bundle of reinforcing wires (18), and the bonded reinforcing wires (18) and the ball group (19) form a tensile system of the model pile (3).

5. The shield cutting pile test device according to claim 1, characterized in that, The excavation system (5) is located in front of the model box (2) and is fixedly connected to the model box. The excavation system (5) includes a support device (22), a propulsion device (23) and an excavation device (24). The support device (22) has racks distributed on both sides, the propulsion device (23) is fixed on the racks, one end of the excavation device (24) is fitted into the model tunnel (4), and the other end is connected to the excavation device. The excavation device (24) is equipped with laser displacement sensors (25).

Citation Information

Patent Citations

  • Test system platform for cutting pile body of composite foundation in shield tunneling

    CN109060395A