A grout leakage prevention structure and construction method for the root of high-rise frame shear wall column

By setting steel pipes and fastening components at the root of the shear wall column to extrude the angle steel plate, and using silicone strips to increase sealing, the problem of mud leakage during the pouring of the shear wall is solved, achieving efficient leakage prevention and cost savings.

CN118007934BActive Publication Date: 2025-04-08CHINA MCC17 GRP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410318805.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2025-04-08
Estimated Expiration
2044-03-20

AI Technical Summary

Technical Problem

During the pouring of shear walls, mud is prone to leak out of the gaps at the bottom of the formwork, resulting in mud waste and quality impact. Existing solutions such as the use of mud sealing have problems such as the problem of large amounts of waste and cleaning difficulties.

Method used

By setting steel pipes as support, fastening component adjustment support members to squeeze the angle steel plate, reducing slurry leakage, and increasing sealing through silicone strips instead of mortar sealing, achieving recyclable and simple and convenient installation and disassembly.

Benefits of technology

It effectively prevents mud from overflowing, reduces time and material costs, and realizes a recyclable and highly adaptable slurry-proof structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118007934B_ABST
    Figure CN118007934B_ABST
Patent Text Reader

Abstract

The invention discloses a grout-proof structure and construction method for the root of a high-rise frame shear wall column. The grout-proof structure includes a steel cage and a grout-sealing wooden strip. Grouting templates are respectively arranged above the grout-sealing wooden strips. Side templates are arranged between the two ends of the grouting templates. Multiple secondary keels and multiple pairs of main keels are respectively installed on the outer surface of each grouting template. Each pair of main keels corresponds to each other and is respectively connected by multiple tension reinforcement screws. A grout-sealing assembly is arranged between the grout-sealing wooden strips and the grouting template. The grout-sealing assembly includes steel pipes respectively penetrating the bottom ends of the secondary keels outside the two grouting templates and angle steel plates at the right angles between the bottom ends of each adjacent secondary keel and the grouting template. The two ends of the two steel pipes are connected by a connecting assembly. Multiple mounting holes are evenly installed on each steel pipe, and a fastening assembly is connected in each mounting hole. The application of the invention can effectively prevent slurry from overflowing when the shear wall is poured, saving construction time and cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a slurry leakage prevention structure at the root of a high-rise frame shear wall column and a construction method. Background Art

[0002] Shear wall, also known as wind-resistant wall, earthquake-resistant wall or structural wall, is a wall in a house or structure that mainly bears horizontal loads and vertical loads (gravity) caused by wind loads or earthquakes to prevent structural shear (shear) damage. It is generally made of reinforced concrete. When the shear wall is poured, after the grouting in the formwork, the bottom of the formwork will be subjected to greater pressure, causing the mud to leak out from the gap at the bottom of the formwork, which will not only cause waste of mud and be difficult to clean, but also affect the quality of the shear wall. A common solution is that the operator uses mud on the sealing wood strips to seal in advance to avoid mud leakage. However, the use of mud sealing will not only use a large amount of mud, but also the mud cannot be recycled after solidification, which will lead to a large amount of mud waste, and the solidified mud is difficult to clean, which greatly increases the construction cost and construction time. Therefore, in view of the above phenomenon, a leakage prevention device and construction method for the root of the high-rise frame shear wall column is urgently needed to meet the needs of actual use. Summary of the invention

[0003] In response to the problems existing in the above-mentioned background technology, the present invention provides a leakage-proof structure and construction method for the root of a high-rise frame shear wall column. A steel pipe is set as a support, and a fastening assembly is used as an adjusting support to extrude the angle steel plate to reduce leakage. The silicone strip is set to increase the sealing performance to further prevent mud from overflowing, thereby replacing the current technology of sealing with mortar, achieving recyclability, simple and convenient installation and disassembly, and reducing time and material costs.

[0004] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:

[0005] The present invention discloses a grout leakage prevention structure at the root of a high-rise frame shear wall column, comprising a steel cage and a grout sealing wood strip arranged below the steel cage, wherein grouting templates are respectively vertically arranged on both sides above the grout sealing wood strips, and a side template is vertically arranged between the inner sides of the two ends of the two grouting templates, and a plurality of secondary keels and a plurality of pairs of main keels are respectively evenly installed on the outer surface of each of the grouting templates, and each pair of main keels on the outer sides of the two grouting templates correspond to each other and are respectively connected by a plurality of tension reinforcement screws, and each pair of tension reinforcement screws respectively penetrates the grouting template and the steel cage, and the The two ends of the main keel are reinforced by movable fasteners; a sealing assembly is provided between the sealing wood strip and the grouting template, and the sealing assembly includes steel pipes respectively penetrating the bottom ends of the secondary keels outside the two grouting templates and angle steel plates at the right angles between the bottom ends of the sealing wood strip and the grouting template between each adjacent secondary keel, and the two ends of the two steel pipes are respectively connected by connecting assemblies, and a plurality of mounting holes are evenly penetrated and installed on each of the steel pipes, and a fastening assembly is threadedly connected in each mounting hole, and the angle steel plate can be pressed at the angle when the fastening assembly is tightened.

[0006] Furthermore, the fastening assembly includes a hand nut and a screw rod fixedly mounted on one side of the hand nut, the screw rod is threadedly connected in the mounting hole, and the other end of the screw rod is rotatably connected to a pressure plate, and the pressure plate is pressed against the angle steel plate.

[0007] Furthermore, the cross-section of the pressing plate is an isosceles trapezoid, the acute angle of the isosceles trapezoid is 45°, the inclined surface of the isosceles trapezoid is roughly arranged, and the two inclined surfaces of the isosceles trapezoid are respectively fitted with two adjacent surfaces of the inner angle of the angle steel plate.

[0008] Furthermore, the spacing between adjacent secondary keels is 250 mm.

[0009] Furthermore, at least two silicone strips are inlaid and installed on the outer side and bottom surface of the angle steel plate, the silicone strip on the outer side of the angle steel plate is fitted with the grouting template, the silicone strip on the bottom surface of the angle steel plate is fitted with the sealing wooden strip, and the left and right sides of the angle steel plate are respectively fitted with adjacent secondary keels.

[0010] Furthermore, the connecting assembly includes a first sleeve and a second sleeve, the first sleeve and the second sleeve are respectively movably connected to the steel pipes on both sides of the sealing wood strips, a threaded sleeve is vertically fixedly installed on the side of the first sleeve, and a rotating seat is vertically fixedly installed on the side of the second sleeve, and a rotating column is movably connected to the side of the rotating seat, and an anti-slip pattern structure is integrally formed on the surface of one end of the rotating column close to the rotating seat, and a threaded structure is integrally formed on the surface of one end of the rotating column away from the rotating seat, and the threaded structure is threadedly connected to the threaded sleeve.

[0011] Furthermore, thread grooves are integrally formed on the upper and lower sides of the inner wall of the threaded sleeve, smooth inner walls are integrally formed on the left and right sides of the inner wall of the threaded sleeve, and the threaded structure is threadedly connected to the thread grooves.

[0012] The present invention provides a construction method for a grout-proof structure at the root of a high-rise frame shear wall column based on the technical solution described above. First, grouting wood strips are arranged and steel cages are arranged on the grouting wood strips, grouting templates are respectively installed on the upper surfaces of the grouting wood strips on both sides of the steel cage, and then the secondary keels, main keels and tension reinforcement screws are installed in sequence; then, each angle steel plate is placed at the angle between the grouting wood strips and the grouting template between the bottom ends of adjacent secondary keels, a circular hole with the same diameter as the steel pipe is opened on the side surface of the bottom end of the secondary keel, the steel pipe is inserted into the circular hole, and then the screw, the mounting hole and the pressing plate are installed, one side of the pressing plate is rotatably connected to one end of the screw by using a screw, and then the pressing plate is squeezed by rotating the hand-tightening nut to squeeze the angle steel plate against the top surface of the grouting wood strip and the side surface of the grouting template; finally, the connecting assembly is installed between the two ends of the steel pipe.

[0013] Compared with the prior art, the anti-leakage slurry structure at the root of the high-rise frame shear wall column described in the present invention utilizes the set steel pipe as support and the fastening assembly as an adjusting support to extrude the angle steel plate to reduce leakage, and increases the sealing by the set silicone strip to further prevent mud overflow, thereby replacing the current technology of using mortar to seal, achieving recycling, simple and convenient installation and disassembly, and reducing time and material costs; the length can be quickly adjusted by the used connecting assembly, which is convenient for fixing the two ends of the steel pipe, and it has strong adaptability and is suitable for use on walls of different thicknesses, and is highly practical. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the patent of this invention;

[0015] Figure 2 It is a schematic diagram of a partial structure enlarged in the whole of the patent of the present invention;

[0016] Figure 3 This is a schematic diagram of the overall structure of the sealing slurry assembly of the patent of the present invention;

[0017] Figure 4 This is a schematic diagram of the fastening assembly structure of the patent of the present invention;

[0018] Figure 5 This is a schematic diagram of the cross-sectional structure of the sealing slurry component of the patent of the present invention;

[0019] Figure 6 It is a three-dimensional assembly diagram of the connection component of the patent of the present invention;

[0020] Figure 7 It is a schematic diagram of the cross-sectional structure of the connection component of the patent of the present invention;

[0021] Figure 8 This is a schematic diagram of the cross-sectional structure of the threaded sleeve of the patent of the present invention.

[0022] Numbers in the figure: 1. Sealing wooden strip; 2. Grouting formwork; 3. Side formwork; 4. Secondary keel; 5. Main keel; 6. Pulling reinforcement screw; 7. Sealing assembly; 71. Steel pipe; 72. Connection assembly; 73. Mounting hole; 74. Fastening assembly; 75. Angle steel plate; 76. Silicone strip; 741. Hand-tightened nut; 742. Screw; 743. Pressing plate; 721. First sleeve; 722. Second sleeve; 723. Threaded sleeve; 724. Rotating seat; 725. Rotating column; 726. Anti-slip pattern structure; 727. Threaded structure; 728. Threaded groove; 729. Smooth inner wall. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention. Unless otherwise defined, the technical terms or scientific terms used herein should be the usual meanings understood by people with general skills in the field to which the present disclosure belongs. "Up", "down", "left", "right", "front", "back" and the like used in the patent application specification and claims of the present disclosure are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship also changes accordingly; "connected" or "connected" and similar words are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. The parts not described in detail in the present invention are all known technologies of technicians in the field of this technology.

[0024] Embodiment 1:

[0025] like Figure 1-8As shown, the present invention provides a grout leakage prevention structure at the root of a high-rise frame shear wall column, comprising a steel cage and a grout sealing wood strip 1 arranged below the steel cage, wherein grouting templates 2 are vertically arranged on both sides above the grout sealing wood strip 1, and a side template 3 is vertically arranged between the inner sides of the two ends of the two grouting templates 2, and a plurality of secondary keels 4 and a plurality of pairs of main keels 5 are evenly installed on the outer surface of each of the grouting templates 2. Each pair of main keels 5 on the outer sides of the two grouting templates 2 corresponds to each other and is connected by a plurality of tension reinforcement screws 6, and each tension reinforcement screw 6 passes through the grouting template 2 and the steel cage, and the two ends of the main keel 5 are respectively connected. A sealing assembly 7 is provided between the sealing wood strip 1 and the grouting template 2 through reinforcement with movable fasteners. The sealing assembly 7 includes steel pipes 71 respectively penetrating the bottom ends of the secondary keels 4 outside the two grouting templates 2 and angle steel plates 75 at the right angles between the sealing wood strip 1 and the grouting template 2 between the bottom ends of each adjacent secondary keel 4. The two ends of the two steel pipes 71 are respectively connected by connecting assemblies 72. A plurality of mounting holes 73 are evenly penetrated and installed on each of the steel pipes 71. A fastening assembly 74 is threadedly connected in each of the mounting holes 73. When the fastening assembly 74 is tightened, the angle steel plate 75 can be pressed at the angle.

[0026] In this embodiment, the fastening assembly 74 includes a hand nut 741 and a screw 742 fixedly installed on one side of the hand nut 741. The screw 742 is threadedly connected in the mounting hole 73. The other end of the screw 742 is rotatably connected to a pressure plate 743, and the pressure plate 743 is pressed against the angle steel plate 75.

[0027] In this embodiment, the cross-section of the pressing plate 743 is an isosceles trapezoid, the acute angle of the isosceles trapezoid is 45°, the inclined surface of the isosceles trapezoid is roughly arranged, and the two inclined surfaces of the isosceles trapezoid are respectively fitted with the two adjacent surfaces of the inner angle of the angle steel plate 75.

[0028] In this embodiment, the distance between adjacent secondary keels 4 is 250 mm.

[0029] In this embodiment, at least two silicone strips 76 are inlaid and installed on the outer side surface and the bottom surface of the angle steel plate 75. The silicone strip 76 on the outer side surface of the angle steel plate 75 is in contact with the grouting template 2, and the silicone strip 76 on the bottom surface of the angle steel plate 75 is in contact with the sealing wood strip 1. The left and right sides of the angle steel plate 75 are respectively in contact with the adjacent secondary keels 4. In this embodiment, the silicone strip 76 can be deformed under the extrusion of the angle steel plate 75, so that the silicone strip 76 is more closely in contact with the sealing wood strip 1 and the secondary keel 4, thereby improving the sealing performance and further preventing mud from overflowing.

[0030] In this embodiment, the connection assembly 72 includes a first sleeve 721 and a second sleeve 722, the first sleeve 721 and the second sleeve 722 are respectively movably sleeved on the steel pipes 71 on both sides of the pulp sealing wood strip 1, a threaded sleeve 723 is vertically fixedly installed on the side of the first sleeve 721, a rotating seat 724 is vertically fixedly installed on the side of the second sleeve 722, and a rotating column 725 is movably sleeved on the side of the rotating seat 724, and an anti-skid pattern structure 726 is integrally formed on the surface of one end of the rotating column 725 close to the rotating seat 724, and a threaded structure 727 is integrally formed on the surface of one end of the rotating column 725 away from the rotating seat 724, and the threaded structure 727 is threadedly connected with the threaded sleeve 723. In this embodiment, the overall length of the connection assembly 72 can be adjusted by holding the anti-skid pattern structure 726 and rotating the rotating column 725, and the steel pipe 71 can be further fixed by sleeved on the steel pipes 71 on both sides of the first sleeve 721 and the second sleeve 722 respectively.

[0031] In this embodiment, the upper and lower sides of the inner wall of the threaded sleeve 723 are integrally formed with thread grooves 728, and the left and right sides of the inner wall of the threaded sleeve 723 are integrally formed with smooth inner walls 729, and the threaded structure 727 is threadedly connected with the thread grooves 728. In this embodiment, the threaded structure 727 can move arbitrarily in the smooth inner wall 729, and after stopping at a desired position, the position adjustment of the rotating column 725 can be completed by rotating the rotating column 725 ninety degrees, which facilitates the rapid adjustment of the length of the connecting component 72.

[0032] Embodiment 2:

[0033] The construction method of a leakage-proof structure at the root of a high-rise frame shear wall column described in Example 1 is as follows: first, a sealing wood strip 1 is set and a steel cage is set on the sealing wood strip 1, and a grouting template 2 is installed on the upper surface of the sealing wood strip 1 on both sides of the steel cage, and then the secondary keel 4, the main keel 5 and the tension reinforcement screw 6 are installed in sequence; then each angle steel plate 75 is placed at the angle between the sealing wood strip 1 and the grouting template 2 between the bottom ends of adjacent secondary keels 4, a circular hole with the same diameter as the steel pipe 71 is opened on the side of the bottom end of the secondary keel 4, the steel pipe 71 is inserted into the circular hole, and then the screw 742, the mounting hole 73 and the pressing plate 743 are installed, and one side of the pressing plate 743 is rotatably connected to one end of the screw 742 by using a screw, and then the pressing plate 743 is squeezed by rotating the hand-tightening nut 741, thereby squeezing the angle steel plate 75 against the top surface of the sealing wood strip 1 and the side of the grouting template 2; finally, the connecting assembly 72 is installed between the two ends of the steel pipe 71.

Claims

1. A grout leakage prevention structure at the root of a high-rise frame shear wall column, comprising a steel cage and a grout sealing wood strip (1) arranged below the steel cage, wherein grouting templates (2) are vertically arranged on both sides above the grout sealing wood strip (1), and a side template (3) is vertically arranged between the inner sides of the two ends of the two grouting templates (2), and the outer surface of each grouting template (2) is evenly installed with a plurality of mutually perpendicular secondary keels (4) and a plurality of pairs of main keels (5), and each pair of main keels (5) on the outer side of the two grouting templates (2) corresponds to each other and is respectively connected by a plurality of tension reinforcement screws (6), and each tension reinforcement screw (6) passes through the grouting template (2) and the steel cage, and the two ends of the main keel (5) are reinforced by movable fasteners, characterized in that: A grout sealing assembly (7) is provided between the grout sealing strip (1) and the grouting template (2), the grout sealing assembly (7) comprising steel pipes (71) respectively penetrating the bottom ends of the secondary keels (4) outside the two grouting templates (2) and angle steel plates (75) at the right angle between the grout sealing strip (1) and the grouting template (2) between the bottom ends of each adjacent secondary keel (4), the two ends of the two steel pipes (71) are respectively connected by a connecting assembly (72), a plurality of mounting holes (73) are evenly penetrated and installed on each of the steel pipes (71), and a fastening assembly (74) is threadedly connected in each of the mounting holes (73), and when the fastening assembly (74) is fastened, the angle steel plate (75) can be pressed at the angle.

2. The anti-leakage slurry structure at the root of a high-rise frame shear wall column according to claim 1 is characterized in that: The fastening assembly (74) comprises a hand-tightening nut (741) and a screw rod (742) fixedly mounted on one side of the hand-tightening nut (741); the screw rod (742) is threadedly connected in the mounting hole (73); the other end of the screw rod (742) is rotatably connected to a pressure plate (743); the pressure plate (743) is pressed against the angle steel plate (75).

3. The anti-leakage slurry structure at the root of a high-rise frame shear wall column according to claim 2 is characterized in that: The cross section of the pressing plate (743) is an isosceles trapezoid, the acute angle of the isosceles trapezoid is 45°, the inclined surface of the isosceles trapezoid is roughly arranged, and the two inclined surfaces of the isosceles trapezoid are respectively fitted with two adjacent surfaces of the inner angle of the angle steel plate (75).

4. The anti-leakage slurry structure at the root of a high-rise frame shear wall column according to claim 2, characterized in that: The spacing between adjacent secondary keels (4) is 250 mm.

5. A slurry leakage prevention structure at the root of a high-rise frame shear wall column according to any one of claims 1 to 4, characterized in that: At least two silicone strips (76) are inlaid and installed on the outer side surface and the bottom surface of the angle steel plate (75); the silicone strip (76) on the outer side surface of the angle steel plate (75) is in contact with the grouting template (2); the silicone strip (76) on the bottom surface of the angle steel plate (75) is in contact with the sealing wood strip (1); and the left and right sides of the angle steel plate (75) are respectively in contact with adjacent secondary keels (4).

6. The anti-leakage slurry structure at the root of a high-rise frame shear wall column according to claim 1, characterized in that: The connecting assembly (72) comprises a first sleeve (721) and a second sleeve (722), wherein the first sleeve (721) and the second sleeve (722) are respectively movably sleeved on the steel pipe (71) on both sides of the pulp sealing wood strip (1), a threaded sleeve (723) is vertically fixedly installed on the side of the first sleeve (721), a rotating seat (724) is vertically fixedly installed on the side of the second sleeve (722), a rotating column (725) is movably sleeved on the side of the rotating seat (724), an end surface of the rotating column (725) close to the rotating seat (724) is integrally formed with an anti-slip pattern structure (726), and an end surface of the rotating column (725) away from the rotating seat (724) is integrally formed with a threaded structure (727), and the threaded structure (727) is threadedly connected to the threaded sleeve (723).

7. The anti-leakage slurry structure at the root of the high-rise frame shear wall column according to claim 6 is characterized in that: The upper and lower sides of the inner wall of the threaded sleeve (723) are integrally formed with thread grooves (728), the left and right sides of the inner wall of the threaded sleeve (723) are integrally formed with smooth inner walls (729), and the thread structure (727) is threadedly connected to the thread groove (728).

8. A construction method for the anti-leakage slurry structure at the root of the high-rise frame shear wall column according to any one of claims 1 to 7, characterized in that: First, the sealing wood strips (1) are arranged and a steel cage is arranged on the sealing wood strips (1), and the grouting templates (2) are respectively installed on the upper surfaces of the sealing wood strips (1) on both sides of the steel cage, and then the secondary keels (4), the main keels (5) and the tension reinforcement screws (6) are installed in sequence; then, each angle steel plate (75) is placed at the angle between the sealing wood strips (1) and the grouting template (2) between the bottom ends of adjacent secondary keels (4), and a circular hole with the same diameter as the steel pipe (71) is opened on the side of the bottom end of the secondary keel (4). The steel pipe (71) is inserted into the circular hole, and then the screw rod (742), the mounting hole (73) and the pressing plate (743) are installed. One side of the pressing plate (743) is rotatably connected to one end of the screw rod (742) by using a screw, and then the pressing plate (743) is squeezed by rotating the hand-tightening nut (741) to squeeze the angle steel plate (75) toward the top surface of the sealing wood strip (1) and the side surface of the grouting template (2); finally, the connecting assembly (72) is installed between the two ends of the steel pipe (71).

Citation Information

Patent Citations

  • Wall template bottom plugging device, template supporting system and formwork construction method

    CN111502247A

  • Template root anti -leakage device

    CN208294080U