Relay ship power quota determination method and related equipment combined with new energy supply

By calculating the photovoltaic power generation instability coefficient and power consumption prediction power of the relay ship, the quota of energy storage and fuel power generation devices is determined, which solves the shortcomings of the power quota method for determining the relay ship in the existing technology, and realizes the supply of new energy The power system operates stably, avoiding accidents.

CN118040790BActive Publication Date: 2024-11-12TIANJIN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410164561.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2024-11-12
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

The existing technology lacks a method for determining the power quota of relay ships after the introduction of new energy, which leads to the inability to meet the accuracy requirements of the power system after the introduction of new energy, resulting in unstable power supply, which may cause loss of aircraft, ships, etc. ACCIDENT.

Method used

By obtaining the working information of the relay ship, including working environment, design navigation sea area, communication status and external power transmission and distribution information, calculate the instability coefficient of photovoltaic power generation and power consumption prediction power, determine the quota for energy storage devices and fuel power generation devices, Ensure the stable operation of the power system.

Benefits of technology

The power quota for the relay ship after the introduction of new energy has been achieved, the stability and reliability of the power system has been improved, accidents caused by unstable power supply have been avoided, and the ability to operate independently at sea for a long time without a person is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118040790B_ABST
    Figure CN118040790B_ABST
Patent Text Reader

Abstract

The present invention provides a method for determining the power quota of a relay ship combined with new energy supply and related equipment, and relates to the field of new energy technology, wherein the method includes: obtaining the working information of the relay ship to be allocated, the working information including the working environment, the designed navigation area, the communication status information and the external power transmission and distribution information; based on the working environment, determining the photovoltaic power generation instability coefficient of the relay ship to be allocated; based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panel, determining the photovoltaic power generation prediction power, based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated, determining the power consumption prediction power; based on the photovoltaic power generation prediction power and the power consumption prediction power, determining the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated. The present invention provides a method for determining the power system quota of a relay ship that introduces photovoltaic power generation new energy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of new energy technology, and in particular to a method for determining a power quota of a relay ship in combination with new energy supply and related equipment. Background Art

[0002] A relay ship is a ship used to supply power to the outside world in the ocean. Currently, ocean relay ships generally use a single energy supply, that is, they are powered by diesel generators. When using this single energy supply solution, the calculation method of the energy quota only needs to consider the one-to-one energy consumption relationship between the energy supply end and the energy consumption end.

[0003] However, ocean relay ships with a single power supply are often affected by the energy supply structure. For example, when the diesel generator runs out of fuel, not only can the relay ship not continue to function for its auxiliary equipment, but it can also not return to the land base, resulting in a series of accidents such as loss of aircraft and ship. The multi-energy complementary energy supply of ocean relay ships is one of the main means to achieve long-term unmanned autonomous operation at sea. However, the existing overall power system configuration method of relay ships cannot meet the calculation accuracy requirements after introducing the uncertainty factor of new energy. That is, there is no method for determining the power quota of relay ships after introducing new energy in the existing technology. Summary of the invention

[0004] The present invention provides a method for determining the power quota of a relay ship combined with new energy supply and related equipment, so as to solve the defects of the power quota determination method of the relay ship after the introduction of new energy in the prior art, and realize the determination of the power quota of the relay ship after the introduction of new energy.

[0005] The present invention provides a method for determining a relay ship power quota in combination with new energy supply, comprising:

[0006] Obtaining working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The relay ship to be allocated is provided with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated;

[0007] Based on the working environment, determining the photovoltaic power generation instability coefficient of the relay ship to be allocated, wherein the photovoltaic power generation instability coefficient reflects the influence of the working environment on the photovoltaic power generation power of the relay ship to be allocated;

[0008] Based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panel, the photovoltaic power generation forecast power of the relay ship to be allocated is determined; based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated, the power consumption forecast power of the relay ship to be allocated is determined;

[0009] Based on the predicted photovoltaic power generation power and the predicted power consumption power, the quotas of the energy storage device and the fuel power generation device set on the relay ship to be allocated are determined.

[0010] According to a method for determining a power quota of a relay ship combined with a new energy supply provided by the present invention, the photovoltaic power generation instability coefficient of the relay ship to be allocated is determined based on the working environment, including:

[0011] Based on the sunshine duration of the working environment, determining a first coefficient, the first coefficient reflecting the influence of the sunshine duration on the photovoltaic power generation power of the relay ship to be allocated;

[0012] Based on the rainfall conditions of the working environment, a second coefficient is determined, wherein the second coefficient reflects the degree of influence of dust accumulation on the photovoltaic power generation panel of the relay ship to be allocated on the photovoltaic power generation power of the relay ship to be allocated;

[0013] Based on the cloud information of the working environment, determining a third coefficient, wherein the third coefficient reflects the influence of the cloud information on the photovoltaic power generation power of the relay ship to be allocated;

[0014] The photovoltaic power generation instability coefficient is determined based on the first coefficient, the second coefficient and the third coefficient.

[0015] According to a method for determining a power quota of a relay ship combined with a new energy supply provided by the present invention, the external power transmission and distribution information includes the external power transmission and distribution type; the power consumption prediction of the relay ship to be allocated is determined based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated, including:

[0016] Determine the predicted power consumption of communication based on the communication status information and the design parameters of the communication device;

[0017] Determining the predicted power consumption of the ship based on the designed navigation area;

[0018] Determine a calculation method for the external power consumption forecast power based on the external power transmission and distribution type, and determine the external power consumption forecast power based on the calculation method and the design parameters of the external power transmission configuration of the relay ship to be allocated;

[0019] The predicted power consumption of the relay ship to be allocated is determined based on the predicted power consumption for communication, the predicted power consumption for sailing and the predicted power consumption for external power.

[0020] According to a method for determining a relay ship power quota in combination with a new energy supply provided by the present invention, the calculation method for determining the predicted power consumption based on the external power transmission and distribution type includes:

[0021] When the external power transmission and distribution type is a rotation type, the calculation method of the external power consumption prediction power is obtained based on a preset formula. When the external power transmission and distribution type is a rotation type, the multiple external power-consuming devices powered by the quota relay ship to be allocated rotate to obtain power from the quota relay ship to be allocated;

[0022] The preset formula is:

[0023] P all,sup,tur =P per,sup,tur x ope (2-η sup,tur )

[0024] P sup,tur =P all,sup,tur / τ ope

[0025] Among them, P sup,tur represents the predicted external power consumption, P all,sup,tur Represents the total energy consumption of external power-consuming devices, P per,sup,tur Represents the energy consumption of a single external power-consuming device, x ope Indicates the number of external power-consuming devices actually in operation, η sup,tur represents the power supply efficiency of the relay ship to be allocated under the target working condition, τ ope Indicates the available runtime of external power consumers.

[0026] According to a method for determining power quota of a relay ship combined with new energy supply provided by the present invention, the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated is determined based on the photovoltaic power generation prediction power and the power consumption prediction power, including:

[0027] determining a quota of the fuel power generation device based on the predicted power consumption;

[0028] Determine a first energy storage quota based on the power consumption prediction power, the photovoltaic power generation prediction power and the working environment;

[0029] Determining a second energy storage quota based on the designed navigation area and the quota of the fuel power generation device;

[0030] The quota of the energy storage device is determined based on the first energy storage quota and the second energy storage quota.

[0031] According to a method for determining a power quota of a relay ship combined with new energy supply provided by the present invention, after determining the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated based on the photovoltaic power generation forecast power and the power consumption forecast power, the method further includes:

[0032] Based on the predicted photovoltaic power generation power and the quota of the fuel power generation device, determining the photovoltaic power generation participation ratio, the photovoltaic power generation participation ratio reflects the proportion of energy generated by photovoltaic power generation when the relay ship to be allocated quota is working;

[0033] When the photovoltaic power generation participation ratio is lower than a preset threshold, the design parameters of the relay ship to be allocated are updated, and the design parameters of the relay ship to be allocated include at least one of the photovoltaic power generation panels, the communication equipment and the external power transmission configuration set on the relay ship to be allocated;

[0034] The quotas of the energy storage device and the fuel power generation device to be installed on the quota relay ship are re-determined based on the updated design parameters until the photovoltaic power generation participation ratio reaches the preset threshold.

[0035] The present invention also provides a relay ship power quota determination device combined with new energy supply, comprising:

[0036] An information acquisition module is used to acquire working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The relay ship to be allocated is provided with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated;

[0037] An instability determination module, used to determine the photovoltaic power generation instability coefficient of the relay ship to be allocated based on the working environment, wherein the photovoltaic power generation instability coefficient reflects the influence of the working environment on the photovoltaic power generation power of the relay ship to be allocated;

[0038] A power prediction module is used to determine the predicted photovoltaic power generation power of the relay ship to be allocated based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panel, and to determine the predicted power consumption power of the relay ship to be allocated based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated;

[0039] A quota module is used to determine the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated based on the photovoltaic power generation predicted power and the power consumption predicted power.

[0040] The present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, it implements any of the above-described methods for determining the power quota of a relay ship in combination with new energy supply.

[0041] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements any of the above-described methods for determining the power quota of a relay ship in combination with new energy supply.

[0042] The present invention also provides a computer program product, including a computer program, which, when executed by a processor, implements any of the above-mentioned methods for determining the power quota of a relay ship in combination with new energy supply.

[0043] The method and related equipment for determining the power quota of a relay ship combined with new energy supply provided by the present invention obtain working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information, determine the photovoltaic power generation instability coefficient of the relay ship to be allocated based on the working environment, determine the photovoltaic power generation predicted power of the relay ship to be allocated based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, determine the predicted power consumption of the relay ship to be allocated based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of the communication equipment and design parameters of the external power transmission configuration of the relay ship to be allocated, and determine the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated based on the predicted photovoltaic power generation power and the predicted power consumption. The method provided by the present invention takes into account the influence of the working environment of the relay ship on photovoltaic power generation to obtain the predicted photovoltaic power generation power, and comprehensively considers the designed navigation area of ​​the relay ship, communication status information and external power transmission and distribution information to obtain the predicted power consumption power of the relay ship. Finally, based on the predicted photovoltaic power generation power and the predicted power consumption power, the quota of the energy storage device and the fuel power generation device on the relay ship is determined, and a method for determining the power system quota of a relay ship that introduces photovoltaic power generation new energy is provided. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0045] Figure 1 It is a flow chart of a method for determining a power quota of a relay ship combined with a new energy supply provided by the present invention;

[0046] Figure 2 It is a structural schematic diagram of a relay ship power quota determination device combined with new energy supply provided by the present invention;

[0047] Figure 3 It is a structural schematic diagram of the electronic device provided by the present invention. DETAILED DESCRIPTION

[0048] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] Combine the following Figure 1 The present invention describes the method for determining the power quota of a relay ship combined with new energy supply. Figure 1 As shown, the method comprises the steps of:

[0050] S110, obtaining working information of the quota relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The quota relay ship to be allocated is equipped with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the quota relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the quota relay ship for external power transmission operation;

[0051] S120, based on the working environment, determining the photovoltaic power generation instability coefficient of the quota relay ship to be allocated, where the photovoltaic power generation instability coefficient reflects the degree of influence of the working environment on the photovoltaic power generation power of the quota relay ship to be allocated;

[0052] S130, based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, determine the photovoltaic power generation forecast power of the quota relay ship to be allocated, based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of communication equipment and design parameters of external power transmission configuration of the quota relay ship to be allocated, determine the power consumption forecast power of the quota relay ship to be allocated;

[0053] S140. Based on the predicted photovoltaic power generation power and the predicted power consumption power, determine the quotas of the energy storage device and the fuel power generation device to be installed on the relay ship to be allocated.

[0054] The method provided by the present invention may be used in the design stage of a quota relay ship before it leaves the factory, and the quotas of energy storage devices and fuel power generation devices installed on the ship may be allocated based on the working information corresponding to the working conditions for which the quota relay ship is designed. It may be used for a quota relay ship with detachable equipment, and before each sea operation, the quotas of energy storage devices and fuel power generation devices on the ship may be allocated based on the working information to be performed.

[0055] Specifically, based on the hardware parameters of the photovoltaic panels installed on the relay ship to be allocated and the work information of the work to be performed by the relay ship to be allocated, the predicted power output of the new energy power generation device where the relay ship to be allocated is located, as well as the predicted power consumption of the relay ship to be allocated can be determined, and the quota of the energy storage device and fuel power generation device on the ship can be realized based on this information.

[0056] The electricity sources on the quota relay ship connected to new energy sources are photovoltaic panels and fuel generators (such as diesel generators), and the electricity consumption includes ship navigation, communication and external power transmission.

[0057] Photovoltaic power generation is often affected by natural weather and environment, and cannot provide stable power output. However, photovoltaic power generation is an important basis for realizing the long-term unmanned autonomous operation function system at sea, because the fuel generator needs to frequently travel back and forth to the base for fuel replenishment. For the predicted power of photovoltaic power generation, it can be determined based on the ideal power generation of the photovoltaic panels and the photovoltaic power generation instability coefficient. Specifically, the full power generation of the photovoltaic panels refers to the power generation that can be generated by the photovoltaic panels on the quota relay ship under ideal conditions, and the photovoltaic power generation instability coefficient reflects the impact of the working environment of the quota relay ship on the power generation of the photovoltaic panels. The full power generation of the photovoltaic panels is determined based on the design parameters of the photovoltaic panels, specifically based on the laying area of ​​the photovoltaic panels, the installation of the photovoltaic panels, and the operating elevation angle. The photovoltaic power generation instability coefficient is determined based on the working environment of the work to be performed by the quota relay ship.

[0058] The area of ​​photovoltaic panels (A sol , m 2 ) is related to the available deck area and the expected photovoltaic laying situation, and should be based on the available deck area A deck The deck photovoltaic panels can be calculated using the laying rate λ. The specific calculation method is detailed in formula (1).

[0059] A sol =A deck ×λ (1)

[0060] The full power generation of the photovoltaic panels of the quota relay ship (K max , W) based on the area occupied by photovoltaic panels per unit power (Aunit , W / m 2 ) and deck photovoltaic panel laying area A sol For calculation, see formulas (2)-(4) for details.

[0061] A rezl =A sol ×cosθ (2)

[0062]

[0063] K max =A real ×A unit (4)

[0064] Among them, A real is the actual effective area of ​​the photovoltaic panel, in m 2 , θ is the installation and operation elevation angle of the photovoltaic panel, the unit is deg, K per is the full power generation of a single photovoltaic panel, in W, A per is the area of ​​a single photovoltaic panel, in m 2 .

[0065] The instability of photovoltaic power generation is mainly related to the sunshine duration, cloud conditions and the surface finish of the photovoltaic panels. Based on the working environment, the photovoltaic power generation instability coefficient of the quota relay ship is determined, including:

[0066] Based on the sunshine duration of the working environment, a first coefficient is determined, and the first coefficient reflects the influence of the sunshine duration on the photovoltaic power generation power of the quota relay ship;

[0067] Based on the rainfall conditions in the working environment, a second coefficient is determined, and the second coefficient reflects the degree of influence of dust accumulation on the photovoltaic power generation power of the quota relay ship to be allocated;

[0068] Based on the cloud information of the working environment, a third coefficient is determined, and the third coefficient reflects the influence of the cloud layer on the photovoltaic power generation power of the quota relay ship;

[0069] A photovoltaic power generation instability coefficient is determined based on the first coefficient, the second coefficient, and the third coefficient.

[0070] The calculation method of the first coefficient is shown in formula (5).

[0071] ξ sol =(t rise -1) / 24 (5)

[0072] Among them, ξ sol is the first coefficient, t riseThe sunshine duration of the working environment of the quota relay ship to be allocated can be obtained based on the historical weather data of the location of the working environment.

[0073] The second coefficient is determined based on the frequency of rainfall in the working environment. In the method provided by the present invention, a correspondence between the number of consecutive days without rainfall and the second coefficient is established in advance, and the corresponding second coefficient is determined based on the corresponding relationship according to the rainfall conditions at the location of the working environment. In view of the frequent rainfall at sea, only the corresponding relationship of the rainfall interval within 30 days at most can be set in advance, and the corresponding relationship can be shown in formula (6).

[0074]

[0075] Among them, ξ sur is the second coefficient, T as It is the dust accumulation time, that is, the rainfall interval time, and the unit is 24h.

[0076] The third coefficient ξ exp It is an empirical coefficient and takes a value in the range of 0.2-0.4 according to the cloud distribution in the working environment.

[0077] The first coefficient, the second coefficient and the third coefficient are multiplied to obtain the photovoltaic power generation instability coefficient ξ, that is, the calculation formula of the photovoltaic power generation instability is formula (7).

[0078] ξ=ξ sol ξ sur ξ exp (7)

[0079] The predicted photovoltaic power generation power is obtained by multiplying the full power generation power of the photovoltaic panels on the deck surface by the photovoltaic power generation instability coefficient. The calculation method is shown in formula (8).

[0080] K sol =ξK max (8)

[0081] The predicted power consumption of the relay ship should comprehensively consider the navigation, communication and external power transmission and distribution of the ship. The navigation energy consumption of the ship refers to the energy consumption required by the relay ship to resist the ocean current and move towards the target direction during the navigation process. The communication energy consumption is the energy consumption required by the communication equipment when the relay ship communicates with the base. The external power transmission and distribution energy consumption is the energy consumption required by the relay ship when it functions with the outside world.

[0082] The predicted power consumption of the ship is determined based on the designed navigation area. Specifically, the predicted power consumption of the ship (P sail ,W) is the maximum possible energy consumption of the ship in the designed navigation area, which is related to the hull navigation resistance (F,kg), the ocean current velocity (V flo ,m / s), target maximum speed (V max, m / s), and its calculation method is detailed in equations (9)-(11).

[0083] A proj =A fro sinθ fro +A sid sinθ sid (9)

[0084] F=2.62A proj (V flo +V max ) 2 (10)

[0085] P sail =F(V flo +V max ) (11)

[0086] Among them, A proj is the actual frontal area of ​​the hull, in m 2 , A fro is the forward projection area of ​​the hull draft, in m 2 ,θ fro is the angle between the ship and the ocean current, in degrees, θ fro <90°,A sid is the lateral projection area of ​​the hull draft, in m 2 ,θ sid is the angle between the hull and the ocean current impact, in degrees, θ sid <90°.

[0087] The communication energy consumption of relay ships can be divided into two categories: continuous and periodic. The continuous type means that the communication system of the relay ship needs to continuously establish continuity with the base; the periodic type means that the communication connection established between the communication equipment and the base is periodic, that is, long-term uninterrupted communication is not required, and it is suitable for occasions where there is no requirement for continuity of data transmission.

[0088] Therefore, the communication power consumption prediction power (P com ,W), which may include the predicted power consumption of continuous communication (P com,const ,W) and the periodic communication power consumption prediction power (P com,cyc ,W) or one of them. For the predicted power of continuous communication energy consumption, it is the operating energy consumption of the communication equipment installed on the relay ship, which can be directly obtained based on the design parameters of the communication equipment. For the predicted power of periodic communication power consumption, it is related to the communication working cycle (T com ,h), communication working time in a single cycle (τ com ,h) and other design parameters. The calculation method is detailed in formula (12).

[0089] P com,cyc =(24 / T com )τ com P com,const (12)

[0090] External power transmission and distribution information includes external power transmission and distribution types. Different external power transmission and distribution types have different calculation methods for external power consumption forecast power. Specifically, the relay ship's external power transmission and distribution types are divided into three categories: continuous, periodic, and rotational: continuous means that the relay ship needs to continuously provide power to the outside world, periodic means that the relay ship periodically provides power to the outside world, that is, long-term uninterrupted power supply is not required, and it is suitable for occasions where there is no requirement for continuity of power transmission, and rotational means that the relay ship supplies power to several devices at the same time, but is constrained by the operation of the equipment, and cannot be charged during operation, and the equipment operation half price is large and cannot be connected by cable, and the equipment needs to return to the relay ship or near the relay ship for charging. This situation where several devices are running while several devices are charging in or near the relay ship is called rotational operation.

[0091] Therefore, according to the type of external power transmission and distribution in the work to be performed by the quota relay ship, the external power consumption forecast power (P sup ,W) may include continuous external power consumption prediction power, periodic external power consumption prediction power and rotational external power consumption prediction power. These three types may exist at the same time, or only one or two of them may exist.

[0092] Forecast power consumption for continuous external power consumption (P sup,const ,W), which is the energy consumption that the outside world requires the quota relay ship to continuously output. The calculation method is detailed in formula (13).

[0093] P sup,const =P dem,const (2-η sup,const ) (13)

[0094] Among them, P dem,const is the continuous power output required by the outside world, in W, η sup,const It is the power supply efficiency for continuous power supply under target working conditions, expressed as a percentage.

[0095] For the periodic external power consumption prediction power (P sup,cyc ,W), and the power supply working cycle (T sup ,h), power supply working time in a single cycle (τ sup ,h) and other parameters. The calculation method is detailed in formula (14).

[0096] P sup,cyc =(24 / T sup )τsup P sup,cyc (2-η sup,cyc ) (14)

[0097] Among them, P sup,cyc is the periodic power output required by the outside world, in W, η sup,cyc It is the power supply efficiency of the cycle power supply under the target working condition, which is a percentage.

[0098] Forecast power consumption of the rotary type (P su,tur ,W), which is equal to the total number of external power-consuming devices (x all ,pcs), the actual number of running units (x ope ,pcs), available operating time of external power-consuming devices (τ ope ,h) and other parameters. The calculation method is detailed in equations (15)-(16).

[0099] P all,sup,tur =P per,sup,tur x ope (2-η sup,tur ) (15)

[0100] P sup,tur =P all,sup,tur / τ ope (16)

[0101] Among them, P all,sup,tur Indicates the total energy consumption of external power-consuming devices, in W, P per,sup,tur Indicates the energy consumption of a single external power-consuming device in W, x ope Indicates the number of external power-consuming devices actually in operation, η su,tur It represents the power supply efficiency of the relay ship to be allocated under the target working condition, which is a percentage, τ ope Indicates the available operating time of external power-consuming equipment in hours.

[0102] Based on the above parameters, the output energy consumption P of each power interface of the quota relay ship can also be obtained: port,sup,tur , the calculation formula is: port,sup,tur =P sup,tur / (x all -x ope ).

[0103] The predicted power consumption of communication, the predicted power consumption of ship navigation and the predicted power consumption of external power are added together to obtain the predicted power consumption of the relay ship to be allocated.

[0104] Based on the predicted photovoltaic power generation and power consumption, the quotas of energy storage devices and fuel power generation devices to be installed on the quota relay ship are determined, including:

[0105] Determining the quota of fuel-fired power generation equipment based on the predicted power consumption;

[0106] Determine a first energy storage quota based on the predicted power consumption, the predicted power of photovoltaic power generation, and the working environment;

[0107] Determining a second energy storage quota based on the designed navigation area and the quota of the fuel power generation device;

[0108] The quota of the energy storage device is determined based on the first energy storage quota and the second energy storage quota.

[0109] Fuel generators are the main means of balancing the power production and consumption of relay ships. Their quota will play a decisive role in the continuous and stable operation of relay ships. The power quota of fuel generators (P dyn ,W) should meet the overall energy consumption requirements for the relay ship operation when photovoltaic power generation fails, see formula (17) for details.

[0110] P dyn >=P sail +P com +P sup (17)

[0111] The energy storage device is used as a storage device for the surplus electricity of the relay ship's photovoltaic power generation and fuel power generation. It is mainly responsible for storing electricity during the low-power consumption period and delivering electricity to each energy consumption unit during the peak power consumption period. The conventional operation modes of the relay ship's energy storage are to participate in receiving photovoltaic power generation and storing energy, and to participate in receiving fuel power generation and storing energy. When participating in receiving photovoltaic power generation and storing energy, the operation of the fuel generator is not restricted. When participating in receiving fuel power generation and storing energy, the photovoltaic power supply is interrupted.

[0112] For the energy storage mode that participates in receiving photovoltaic power generation and storing energy: in this mode, when charging the energy storage device, the photovoltaic power generation works normally, the fuel generator may not work, or it may actively replenish power to the energy storage. The first energy storage quota (W stor,sol ,Wh) calculation method is detailed in formula (18).

[0113] W stor,sol =1.25[K sol -(P sail +P com +P sup )]t rise (18)

[0114] For the energy storage method that participates in receiving fuel for power generation and storing energy: in this method, when charging the energy storage device, the photovoltaic power generation is interrupted and the fuel generator works. The calculation method of the second energy storage quota corresponding to this method is detailed in formulas (19) and (20).

[0115] t jou =S / 3600Vmax (19)

[0116] W stor,nsol =1.25P dyn t jou (20)

[0117] Where S is the distance between the quota relay ship and the base when working, in meters, t jou It is the time required for the quota relay ship to return to the base when working, in h.

[0118] The quota of the energy storage device on the quota relay ship is W stor Take the first energy storage quota W stor,sol and the second energy storage quota W stor,nsol The maximum value in is shown in formula (21).

[0119] W stor =(W stor,sol ,W stor,nsol ) max (twenty one)

[0120] Furthermore, the method provided by the present invention, after obtaining the quotas of the energy storage device and the fuel power generation device, also verifies them, including:

[0121] Based on the predicted power of photovoltaic power generation and the quota of fuel power generation equipment, the participation ratio of photovoltaic power generation is determined. The participation ratio of photovoltaic power generation reflects the proportion of energy generated by photovoltaic power generation when the quota relay ship is working;

[0122] When the participation ratio of photovoltaic power generation is lower than a preset threshold, the design parameters of the relay ship to be allocated are updated, and the design parameters of the relay ship to be allocated include at least one of the design parameters of the photovoltaic panels, communication equipment and external power transmission configuration installed on the relay ship to be allocated;

[0123] Based on the updated design parameters, the quotas of energy storage devices and fuel power generation devices to be installed on the quota relay ship are re-determined until the participation ratio of photovoltaic power generation reaches the preset threshold.

[0124] After obtaining the quota calculation results of the energy storage device and the fuel power generation device, they are verified and the photovoltaic power generation participation ratio (ψ,%) is introduced to measure the overall new energy supply proportion of the relay ship. The calculation formula for the photovoltaic power generation participation ratio is formula (22).

[0125] ψ=K sol t periodic,sol / P dyn t periodic,dyn (twenty two)

[0126] where t periodic,solThe total duration of photovoltaic power generation in the unit monitoring cycle, in h, t periodic,dyn The total duration of fuel power generation in the unit monitoring period, in h. periodic,sol and t periodic,dyn It can be determined based on the photovoltaic power generation time, fuel power generation time and the total time for the relay ship to perform one work under the current quota of the energy storage device and the fuel power generation device.

[0127] If the proportion of photovoltaic power generation participation does not reach the preset threshold, it means that the proportion of new energy supply in the quota relay ship does not meet the design standard, then re-check A sol 、V max , T com , T sup 、x ope , P per,sup,tur , ship communication type, external power transmission and distribution type and other design parameters, until the photovoltaic power generation participation ratio ψ reaches the preset threshold.

[0128] By verifying the quota, we can improve the supply ratio of new energy electricity on the basis of realizing long-term unmanned and autonomous operation of relay ships at sea, realize the calculation of power quota of relay ships with priority new energy functions, and improve the utilization rate of new energy for long-term unmanned and autonomous operation equipment in deep sea.

[0129] The following is a description of the relay ship power quota determination device combined with new energy supply provided by the present invention. The relay ship power quota determination device combined with new energy supply described below and the relay ship power quota determination method combined with new energy supply described above can be referred to each other. Figure 2 As shown, the device comprises:

[0130] The information acquisition module 210 is used to obtain the working information of the relay ship to be allocated, which includes the working environment, the designed navigation area, the communication status information and the external power transmission and distribution information. The relay ship to be allocated is equipped with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated;

[0131] The instability determination module 220 is used to determine the photovoltaic power generation instability coefficient of the quota relay ship to be allocated based on the working environment, and the photovoltaic power generation instability coefficient reflects the influence of the working environment on the photovoltaic power generation power of the quota relay ship to be allocated;

[0132] The power prediction module 230 is used to determine the predicted photovoltaic power generation power of the relay ship to be allocated based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, and to determine the predicted power consumption power of the relay ship to be allocated based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of communication equipment and design parameters of external power transmission configuration of the relay ship to be allocated;

[0133] The quota module 240 is used to determine the quota of the energy storage device and the fuel power generation device set on the relay ship to be allocated based on the predicted photovoltaic power generation power and the predicted power consumption power.

[0134] Figure 3 An example of a physical structure diagram of an electronic device is shown in FIG. Figure 3 As shown, the electronic device may include: a processor 310, a communications interface 320, a memory 330 and a communications bus 340, wherein the processor 310, the communications interface 320 and the memory 330 communicate with each other through the communications bus 340. The processor 310 may call the logic instructions in the memory 330 to execute a method for determining the power quota of a relay ship in combination with new energy supply, the method comprising: obtaining the working information of the relay ship to be allocated, the working information comprising the working environment, the designed navigation area, the communication status information and the external power transmission and distribution information, the relay ship to be allocated is provided with a photovoltaic power generation panel, an energy storage device and a fuel power generation device, the communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated; based on the working environment, determining the photovoltaic power generation of the relay ship to be allocated The electricity instability coefficient and the photovoltaic power generation instability coefficient reflect the influence of the working environment on the photovoltaic power generation of the quota relay ship; based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, the predicted photovoltaic power generation of the quota relay ship is determined; based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of the communication equipment and the design parameters of the external power transmission configuration of the quota relay ship, the predicted power consumption of the quota relay ship is determined; based on the predicted photovoltaic power generation power and the predicted power consumption power, the quota of the energy storage device and the fuel power generation device installed on the quota relay ship is determined.

[0135] In addition, the logic instructions in the above-mentioned memory 330 can be implemented in the form of a software functional unit and can be stored in a computer-readable storage medium when it is sold or used as an independent product. Based on such an understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.

[0136] On the other hand, the present invention also provides a computer program product, which includes a computer program, which can be stored on a non-transitory computer-readable storage medium. When the computer program is executed by a processor, the computer can execute the method for determining the power quota of a relay ship combined with new energy supply provided by the above methods, the method including: obtaining working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The relay ship to be allocated is provided with photovoltaic power generation panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when it is working, and the external power transmission and distribution information reflects the power supply status of the relay ship to be allocated. Configuration information of external power transmission operation of the relay ship; based on the working environment, determine the photovoltaic power generation instability coefficient of the relay ship to be allocated, and the photovoltaic power generation instability coefficient reflects the degree of influence of the working environment on the photovoltaic power generation power of the relay ship to be allocated; based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, determine the photovoltaic power generation forecast of the relay ship to be allocated; based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of communication equipment and design parameters of the external power transmission configuration of the relay ship to be allocated, determine the power consumption forecast of the relay ship to be allocated; based on the photovoltaic power generation forecast power and the power consumption forecast power, determine the quota of the energy storage device and fuel power generation device installed on the relay ship to be allocated.

[0137] On the other hand, the present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which is implemented when the computer program is executed by the processor to execute the relay ship power quota determination method combined with the new energy supply provided by the above methods, the method comprising: obtaining the working information of the relay ship to be allocated, the working information including the working environment, the designed navigation area, the communication status information and the external power transmission and distribution information, the relay ship to be allocated is provided with a photovoltaic power generation panel, an energy storage device and a fuel power generation device, the communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated; Based on the working environment, the photovoltaic power generation instability coefficient of the quota relay ship is determined, and the photovoltaic power generation instability coefficient reflects the degree of influence of the working environment on the photovoltaic power generation power of the quota relay ship; based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panels, the photovoltaic power generation predicted power of the quota relay ship is determined; based on the designed navigation area, communication status information, external power transmission and distribution information, design parameters of communication equipment and design parameters of the external power transmission configuration of the quota relay ship, the power consumption predicted power of the quota relay ship is determined; based on the photovoltaic power generation predicted power and the power consumption predicted power, the quota of the energy storage device and the fuel power generation device installed on the quota relay ship is determined.

[0138] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.

[0139] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.

[0140] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for determining power quota of a relay ship in combination with new energy supply, characterized in that: include: Obtaining working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The relay ship to be allocated is provided with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated; Based on the working environment, determining the photovoltaic power generation instability coefficient of the relay ship to be allocated, wherein the photovoltaic power generation instability coefficient reflects the influence of the working environment on the photovoltaic power generation power of the relay ship to be allocated; Based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panel, the photovoltaic power generation forecast power of the relay ship to be allocated is determined; based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated, the power consumption forecast power of the relay ship to be allocated is determined; Based on the predicted photovoltaic power generation power and the predicted power consumption power, determining the quota of the energy storage device and the fuel power generation device provided on the to-be-quota relay ship; The determining, based on the working environment, the photovoltaic power generation instability coefficient of the to-be-quota relay ship comprises: Based on the sunshine duration of the working environment, determining a first coefficient, the first coefficient reflecting the influence of the sunshine duration on the photovoltaic power generation power of the relay ship to be allocated; Based on the rainfall conditions of the working environment, a second coefficient is determined, wherein the second coefficient reflects the degree of influence of dust accumulation on the photovoltaic power generation panel of the relay ship to be allocated on the photovoltaic power generation power of the relay ship to be allocated; Based on the cloud information of the working environment, determining a third coefficient, wherein the third coefficient reflects the influence of the cloud information on the photovoltaic power generation power of the relay ship to be allocated; Determine the photovoltaic power generation instability coefficient based on the first coefficient, the second coefficient and the third coefficient; The external power transmission and distribution information includes the external power transmission and distribution type; the predicted power consumption of the to-be-quota relay ship is determined based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the to-be-quota relay ship, including: Determine the predicted power consumption of communication based on the communication status information and the design parameters of the communication device; Determining the predicted power consumption of the ship based on the designed navigation area; Determine a calculation method for the external power consumption forecast power based on the external power transmission and distribution type, and determine the external power consumption forecast power based on the calculation method and the design parameters of the external power transmission configuration of the relay ship to be allocated; Determine the predicted power consumption of the relay ship to be allocated based on the predicted power consumption for communication, the predicted power consumption for sailing and the predicted power consumption for external power; The calculation method for determining the predicted power consumption based on the external power transmission and distribution type includes: When the external power transmission and distribution type is a rotation type, the calculation method of the external power consumption prediction power is obtained based on a preset formula. When the external power transmission and distribution type is a rotation type, the multiple external power-consuming devices powered by the quota relay ship to be allocated rotate to obtain power from the quota relay ship to be allocated; The preset formula is: P.S all,sup,tur JP per,sup,tur x ope (2-η sup,tur ) P sup,tur =P all,sup,tur / t ope Among them, P sup,tur represents the predicted external power consumption, P all,sup,tur Represents the total energy consumption of external power-consuming devices, P per,sup,tur Represents the energy consumption of a single external power-consuming device, x ope Indicates the number of external power-consuming devices actually in operation, η sup,tur represents the power supply efficiency of the relay ship to be allocated under the target working condition, τ ope Indicates the available runtime of external power consumers.

2. The method for determining the power quota of a relay ship combined with new energy supply according to claim 1 is characterized in that: The determining of the quota of the energy storage device and the fuel power generation device provided on the to-be-quota relay ship based on the photovoltaic power generation prediction power and the power consumption prediction power comprises: determining a quota of the fuel power generation device based on the predicted power consumption; Determine a first energy storage quota based on the power consumption prediction power, the photovoltaic power generation prediction power and the working environment; Determining a second energy storage quota based on the designed navigation area and the quota of the fuel power generation device; The quota of the energy storage device is determined based on the first energy storage quota and the second energy storage quota.

3. The method for determining the power quota of a relay ship combined with new energy supply according to claim 1 is characterized in that: After determining the quota of the energy storage device and the fuel power generation device provided on the to-be-allocated relay ship based on the photovoltaic power generation forecast power and the power consumption forecast power, the method further includes: Based on the predicted photovoltaic power generation power and the quota of the fuel power generation device, determining the photovoltaic power generation participation ratio, the photovoltaic power generation participation ratio reflects the proportion of energy generated by photovoltaic power generation when the relay ship to be allocated quota is working; When the photovoltaic power generation participation ratio is lower than a preset threshold, the design parameters of the relay ship to be allocated are updated, and the design parameters of the relay ship to be allocated include at least one of the photovoltaic power generation panels, the communication equipment and the external power transmission configuration set on the relay ship to be allocated; The quotas of the energy storage device and the fuel power generation device to be installed on the quota relay ship are re-determined based on the updated design parameters until the photovoltaic power generation participation ratio reaches the preset threshold.

4. A relay ship power quota determination device combined with new energy supply, characterized in that: include: An information acquisition module is used to acquire working information of the relay ship to be allocated, the working information including working environment, designed navigation area, communication status information and external power transmission and distribution information. The relay ship to be allocated is provided with photovoltaic panels, energy storage devices and fuel power generation devices. The communication status information reflects the communication status of the relay ship to be allocated with the base when working, and the external power transmission and distribution information reflects the configuration information of the external power transmission operation of the relay ship to be allocated; An instability determination module, used to determine the photovoltaic power generation instability coefficient of the relay ship to be allocated based on the working environment, wherein the photovoltaic power generation instability coefficient reflects the influence of the working environment on the photovoltaic power generation power of the relay ship to be allocated; A power prediction module is used to determine the predicted photovoltaic power generation power of the relay ship to be allocated based on the photovoltaic power generation instability coefficient and the design parameters of the photovoltaic power generation panel, and to determine the predicted power consumption power of the relay ship to be allocated based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the relay ship to be allocated; A quota module, used for determining the quota of the energy storage device and the fuel power generation device provided on the relay ship to be allocated based on the photovoltaic power generation forecast power and the power consumption forecast power; The determining, based on the working environment, the photovoltaic power generation instability coefficient of the to-be-quota relay ship comprises: Based on the sunshine duration of the working environment, determining a first coefficient, the first coefficient reflecting the influence of the sunshine duration on the photovoltaic power generation power of the relay ship to be allocated; Based on the rainfall conditions of the working environment, a second coefficient is determined, wherein the second coefficient reflects the degree of influence of dust accumulation on the photovoltaic power generation panel of the relay ship to be allocated on the photovoltaic power generation power of the relay ship to be allocated; Based on the cloud information of the working environment, determining a third coefficient, wherein the third coefficient reflects the influence of the cloud information on the photovoltaic power generation power of the relay ship to be allocated; Determine the photovoltaic power generation instability coefficient based on the first coefficient, the second coefficient and the third coefficient; The external power transmission and distribution information includes the external power transmission and distribution type; the predicted power consumption of the to-be-quota relay ship is determined based on the designed navigation area, the communication status information, the external power transmission and distribution information, the design parameters of the communication equipment and the design parameters of the external power transmission configuration of the to-be-quota relay ship, including: Determine the predicted power consumption of communication based on the communication status information and the design parameters of the communication device; Determining the predicted power consumption of the ship based on the designed navigation area; Determine a calculation method for the external power consumption forecast power based on the external power transmission and distribution type, and determine the external power consumption forecast power based on the calculation method and the design parameters of the external power transmission configuration of the relay ship to be allocated; Determine the predicted power consumption of the relay ship to be allocated based on the predicted power consumption for communication, the predicted power consumption for sailing and the predicted power consumption for external power; The calculation method for determining the predicted power consumption based on the external power transmission and distribution type includes: When the external power transmission and distribution type is a rotation type, the calculation method of the external power consumption prediction power is obtained based on a preset formula. When the external power transmission and distribution type is a rotation type, the multiple external power-consuming devices powered by the quota relay ship to be allocated rotate to obtain power from the quota relay ship to be allocated; The preset formula is: P.S all,sup,tur JP per,sup,tur x ope (2-η sup,tur ) P sup,tur =P all,sup,tur / t ope Among them, P sup,tur represents the predicted external power consumption, P all,sup,tur Represents the total energy consumption of external power-consuming devices, P per,sup,tur Represents the energy consumption of a single external power-consuming device, x ope Indicates the number of external power-consuming devices actually in operation, η sup,tur represents the power supply efficiency of the relay ship to be allocated under the target working condition, τ ope Indicates the available runtime of external power consumers.

5. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein: When the processor executes the program, the method for determining the power quota of a relay ship in combination with new energy supply as described in any one of claims 1 to 3 is implemented.

6. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method for determining the power quota of a relay ship in combination with new energy supply as described in any one of claims 1 to 3 is implemented.

7. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the method for determining the power quota of a relay ship in combination with new energy supply as described in any one of claims 1 to 3 is implemented.