A distribution equipment line abnormality monitoring system and method based on big data
Through big data analysis and intelligent control, the problem of insufficient monitoring of abnormal distribution equipment lines is solved, timely assessment and correction of power distribution equipment lines is realized, the reliability and stability of the equipment are improved, and the risk of failure is reduced.
Patent Information
- Application Number
- CN202410231447.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-01
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-03-01
AI Technical Summary
Insufficient monitoring of line anomalies in power distribution equipment leads to inaccurate fault analysis, which may cause equipment short circuits and endanger personnel and property safety.
A monitoring system based on big data is adopted to obtain fault information, historical sensor data and electrical component usage data, analyze the impact of characteristic periods and operating parameters, and use intelligent control devices to perform intelligent adjustments to evaluate and correct line abnormalities.
It achieves timely monitoring and assessment of abnormalities in power distribution equipment lines, reduces the risk of faults, and improves the reliability and stability of equipment.
Smart Images

Figure CN118091319B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power distribution equipment line monitoring, and in particular to a power distribution equipment line anomaly monitoring system and method based on big data. Background Art
[0002] Big data refers to a large-scale, diverse, and high-speed data collection. Distribution equipment usually refers to equipment used to transmit, distribute, and control electric energy, mainly including transformers, switchgear, protection equipment, electric energy metering equipment, etc. Distribution equipment plays a vital role in the power system. Its existence can ensure that electric energy can be safely and efficiently transmitted and distributed, because big data technology can collect, store and process the equipment operation data of distribution equipment in real time, monitor the lines of distribution equipment, detect abnormal situations and respond in time to avoid potential faults. In addition, big data technology can also conduct in-depth analysis of the operating data of distribution equipment, identify abnormal patterns and fault characteristics, help engineers quickly locate the cause of the fault, reduce the time for fault investigation and analysis, and improve the reliability and stability of equipment.
[0003] The main function of the power distribution equipment is to reduce the voltage of the high-voltage electric energy generated by the power plant through the transformer and then distribute it, and transmit it to various users or electrical equipment through lines to meet the electricity needs of different users in different regions. Many electrical components such as switches, fuses, contactors, etc. inside the power distribution equipment are connected through lines. The power distribution equipment lines are very important for the normal operation of the power distribution equipment. However, in the process of analyzing the power distribution equipment, the monitoring of the abnormal power distribution equipment lines inside the power distribution equipment is often ignored, which will not only lead to inaccurate analysis of the power distribution equipment, but also cause the power distribution equipment to malfunction due to the inability to timely analyze the abnormality of the power distribution equipment lines, and even cause the power distribution equipment circuit to short-circuit, thereby endangering the lives and property of personnel. Summary of the invention
[0004] The purpose of the present invention is to provide a distribution equipment line abnormality monitoring system and method based on big data to solve the problems existing in the above-mentioned background technology.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a method for monitoring abnormality of distribution equipment lines based on big data, the method comprising:
[0006] Step S100: when a power distribution device fails, the fault information of each device of the power distribution device is obtained, and from each device fault information, a plurality of device fault information related to the abnormality of the power distribution device line is selected, and the time period when the power distribution device fails is extracted from the plurality of device fault information and marked as the characteristic time period of the power distribution device;
[0007] Step S200: Use sensors to monitor the power distribution equipment, obtain historical sensor data records of the power distribution equipment, divide the historical sensor data records of the power distribution equipment based on characteristic time periods of the power distribution equipment, obtain characteristic historical sensor data records of the power distribution equipment, extract corresponding data of operating parameters of the power distribution equipment from the characteristic historical sensor data records, and analyze the operating parameters that have an abnormal impact on the power distribution equipment line to obtain operating parameter impact data of the power distribution equipment;
[0008] Step S300: Obtain usage data of electrical components in the power distribution equipment from the equipment fault information, select electrical components that affect the operating parameters of the power distribution equipment from the equipment fault information based on the usage data, obtain the usage status of the electrical components of the power distribution equipment in the current cycle, and analyze the degree of influence on the line abnormality of the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle in combination with the influence data of the operating parameters of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment;
[0009] Step S400: According to the line abnormality impact data of the power distribution equipment, the intelligent control device in the power distribution equipment in the current cycle is adjusted, the line abnormality in the power distribution equipment in the current cycle is evaluated, and the intelligent control device is used to intelligently adjust the environment inside the power distribution equipment.
[0010] Furthermore, step S100 includes:
[0011] Step S101: respectively obtaining equipment failure information of the power distribution equipment when the power distribution equipment fails in each historical period, obtaining the time period when the power distribution equipment fails in the equipment failure information, extracting the equipment failure report of the power distribution equipment from the equipment failure information, and obtaining each line abnormality keyword preset and related to the line abnormality of the power distribution equipment;
[0012] Step S102: Evaluate the similarity between the equipment fault report and each line abnormality keyword through a text similarity algorithm. When the similarity between a equipment fault report and a line abnormality keyword is greater than a preset value, determine that the equipment fault information to which the equipment fault report belongs is related to the abnormality of the distribution equipment line, and record the time period when the distribution equipment fails in the equipment fault information as the characteristic time period of the distribution equipment.
[0013] Further, step S200 includes:
[0014] Step S201: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record;
[0015] Step S202: analyzing the operating parameters and corresponding values of the operating parameters that affect the operation of the power distribution equipment in the characteristic time period to which the characteristic historical sensor data record belongs, wherein the process of analyzing the operating parameters and corresponding values of the operating parameters that affect the operation of the power distribution equipment in the characteristic time period is as follows: dividing the f-th characteristic time period into a number of time periods according to the unit time length, and sorting the several time periods based on the time sequence, recording the several time periods as the marked time periods of the characteristic time periods, and obtaining the average values of the various operating parameters of the power distribution equipment in the last marked time period and the first marked time period in the f-th characteristic time period from the equipment fault information;
[0016] Step S203: Obtain the maximum value of the average values of the first marking period in each characteristic period for each operating parameter in the power distribution equipment, and use the maximum value as the marking control value of each operating parameter; when the average value of a certain operating parameter in the last marking period of the f-th characteristic period is greater than the corresponding marking control value, the average value of a certain operating parameter in the last marking period of the f-th characteristic period is recorded as the marking threshold of the certain operating parameter in the f-th characteristic period, and the certain operating parameter is recorded as the characteristic operating parameter of the power distribution equipment in the f-th characteristic period;
[0017] Step S204: respectively obtain various characteristic operating parameters and marking thresholds of various characteristic operating parameters in each characteristic time period, and collect the obtained various characteristic operating parameters and marking thresholds of various characteristic operating parameters in each characteristic time period to obtain operating parameter influence data of the power distribution equipment.
[0018] Furthermore, step S300 includes:
[0019] Step S301: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record;
[0020] Step S302: Obtain and mark the equipment fault information belonging to the characteristic time period, extract the usage data of each electrical component in the power distribution equipment from the marked equipment fault information, the usage data includes the usage time of each electrical component in the power distribution equipment, and obtain the preset standard service life of each electrical component in the power distribution equipment;
[0021] Step S303: Calculate the characteristic usage value of each electrical component of the power distribution equipment in the marked equipment fault information, where the characteristic usage value of the ath electrical component in the power distribution equipment is :
[0022] ;
[0023] in, is the usage time of the ath electrical component of the power distribution equipment in the marked equipment fault information; is the standard service life of the ath electrical component of the power distribution equipment in the marked equipment fault information;
[0024] Step S304: setting a characteristic usage threshold. When the characteristic usage value of a certain electrical component in the power distribution equipment in the marked device fault information is greater than the characteristic usage threshold, the certain electrical component is recorded as a characteristic electrical component, and the characteristic electrical components in the power distribution equipment in the marked device fault information are collected.
[0025] Step S305: Obtain the usage time of each electrical component in the power distribution equipment in the current cycle, analyze the influence of different values of operating parameters in the current cycle on the line abnormality state of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment, wherein the line abnormality influence state analysis process includes, based on the usage time of each electrical component of the power distribution equipment in the current cycle, calculating the characteristic usage value of each electrical component in the power distribution equipment in the current week, and selecting the characteristic electrical components in the power distribution equipment in the current cycle;
[0026] Step S306: Calculate the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of each characteristic period, wherein the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of the kth characteristic period is calculated. , j represents the characteristic electrical components of the power distribution equipment in the current cycle, and the total number of characteristic electrical components with the same model as the characteristic electrical components of the power distribution equipment in the kth characteristic period, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle in the k-th characteristic period;
[0027] Step S307: Setting a similarity threshold. When the similarity between the current cycle and the electrical component usage status of a certain characteristic period is greater than or equal to the similarity threshold, obtaining the marking threshold of each characteristic operating parameter in a certain characteristic period from the operating parameter influence data of the power distribution equipment and marking them, and taking the marking threshold of each characteristic operating parameter in the characteristic period corresponding to the maximum similarity value as the characteristic threshold of the corresponding characteristic operating parameter of the power distribution equipment in the current cycle.
[0028] Step S308: When a certain operating parameter exists in the current cycle and is not in the various characteristic operating parameters in the characteristic time period corresponding to the maximum similarity value, the marking threshold of the characteristic operating parameter identical to the certain operating parameter is obtained from each marked characteristic time period according to the order of similarity, and is used as the characteristic threshold of a certain operating parameter of the power distribution equipment in the current cycle;
[0029] Step S309: When the similarity between the use status of electrical components in the current cycle and each characteristic time period is less than the similarity threshold, the power distribution equipment database is obtained, and the standard thresholds of various operating parameters preset by the power distribution equipment in the power distribution equipment database are used as the characteristic thresholds of various operating parameters, and the characteristic thresholds of various operating parameters in the power distribution equipment in the current cycle are aggregated to obtain the line abnormality impact data of the power distribution equipment in the current cycle;
[0030] In the above steps, the characteristic usage value of the electrical components is obtained by calculating the usage time and the service life of the electrical components in the distribution equipment. This is because the component status of each electrical component in the distribution equipment is different at different usage times. Therefore, it is necessary to analyze the usage status of the electrical components in different characteristic time periods according to the different service lives of the electrical components in different distribution equipment. This is more reasonable and scientific.
[0031] Furthermore, step S400 includes:
[0032] Step S401: obtaining the intelligent control device in the power distribution equipment in the current cycle, and combining the line abnormality impact data of the power distribution equipment in the current cycle, obtaining the characteristic thresholds of various operating parameters of the power distribution equipment in the current cycle, and inputting them into the intelligent control device, and adjusting the thresholds of the operating parameters preset in the intelligent control device;
[0033] Step S402: Use the intelligent control device to monitor the various operating parameters of the power distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the power distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the power distribution equipment, and the intelligent control device is used to intelligently adjust the environment inside the power distribution equipment.
[0034] In order to better implement the above method, a distribution equipment line abnormality monitoring system is also proposed, which includes a characteristic time period module, an operating parameter impact data module, a line abnormality impact module, and an intelligent adjustment module;
[0035] A characteristic time period module is used to extract the time period when the power distribution equipment fails from a number of equipment failure information and mark it as the characteristic time period of the power distribution equipment;
[0036] The operating parameter impact data module is used to analyze the operating parameters that have an abnormal impact on the power distribution equipment line and obtain the operating parameter impact data of the power distribution equipment;
[0037] The line abnormality impact module is used to analyze the impact of line abnormality on the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle, and obtain the line abnormality impact data of the power distribution equipment;
[0038] The intelligent adjustment module is used to evaluate the line anomalies in the power distribution equipment in the current cycle and use the intelligent control device to intelligently adjust the environment inside the power distribution equipment.
[0039] Further, the characteristic period module includes a characteristic period unit;
[0040] The characteristic time period unit is used to evaluate the similarity between the equipment fault report and each line abnormality keyword through a text similarity algorithm. When the similarity between a equipment fault report and a certain line abnormality keyword is greater than a preset value, it is determined that the equipment fault information to which the equipment fault report belongs is related to the abnormality of the distribution equipment line, and the time period when the distribution equipment fails in the equipment fault information is recorded as the characteristic time period of the distribution equipment.
[0041] Further, the operating parameter impact data module includes a characteristic operating parameter unit and an operating parameter impact data unit;
[0042] A characteristic operation parameter unit is used to analyze the operation parameters that affect the operation of the power distribution equipment in the characteristic period to which the characteristic historical sensor data record belongs, and obtain the characteristic operation parameters of the power distribution equipment in the characteristic period;
[0043] The operating parameter impact data unit is used to collect the acquired characteristic operating parameters and the marking thresholds of the characteristic operating parameters in each characteristic time period to obtain the operating parameter impact data of the power distribution equipment.
[0044] Further, the line abnormality impact module includes a characteristic electrical component unit and a line abnormality impact unit;
[0045] A characteristic electrical component unit is used to calculate characteristic usage values of various electrical components of the power distribution equipment in the marked equipment fault information, and obtain characteristic electrical components in the power distribution equipment within a characteristic period;
[0046] The line abnormality impact unit is used to collect characteristic thresholds of various operating parameters in the power distribution equipment in the current cycle to obtain line abnormality impact data of the power distribution equipment in the current cycle.
[0047] Further, the intelligent adjustment module includes an intelligent adjustment unit;
[0048] The intelligent adjustment unit is used to use the intelligent control device to monitor the various operating parameters of the distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the distribution equipment, and the intelligent control device is used to intelligently adjust the internal environment of the distribution equipment.
[0049] Compared with the prior art, the beneficial effects achieved by the present invention are as follows: the present invention realizes the intermediate monitoring of abnormal lines in the power distribution equipment, and takes into account the influence of the use status of each electrical component in the power distribution equipment on the equipment status of the power distribution equipment and the influence of the lines between each electrical component in the power distribution equipment, obtains the use status of each electrical component in the power distribution equipment in the current cycle, and obtains the threshold values of various operating parameters of the power distribution equipment in the current cycle through intelligent analysis. When the value of a certain operating parameter in the power distribution equipment changes in the current cycle, the environment in the power distribution equipment can be adjusted by the intelligent control device to ensure that the electrical components and lines of the power distribution equipment are normal. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] The accompanying drawings are used to provide a further understanding of the present invention and constitute part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0051] Figure 1 It is a method flow chart of a system and method for monitoring abnormality of power distribution equipment lines based on big data of the present invention;
[0052] Figure 2 It is a module schematic diagram of a distribution equipment line abnormality monitoring system and method based on big data in the present invention. DETAILED DESCRIPTION
[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0054] See also Figure 1-Figure 2 The present invention provides a technical solution: a method for monitoring abnormality of distribution equipment lines based on big data, the method comprising:
[0055] Step S100: when a power distribution device fails, the fault information of each device of the power distribution device is obtained, and from each device fault information, a plurality of device fault information related to the abnormality of the power distribution device line is selected, and the time period when the power distribution device fails is extracted from the plurality of device fault information and marked as the characteristic time period of the power distribution device;
[0056] Wherein, step S100 includes:
[0057] Step S101: respectively obtaining equipment failure information of the power distribution equipment when the power distribution equipment fails in each historical period, obtaining the time period when the power distribution equipment fails in the equipment failure information, extracting the equipment failure report of the power distribution equipment from the equipment failure information, and obtaining each line abnormality keyword preset and related to the line abnormality of the power distribution equipment;
[0058] Step S102: Evaluate the similarity between the equipment fault report and each line abnormality keyword by using a text similarity algorithm. When the similarity between the equipment fault report and a line abnormality keyword is greater than a preset value, determine that the equipment fault information of the equipment fault report is related to the power distribution equipment line abnormality, and record the time period when the power distribution equipment fails in the equipment fault information as the characteristic time period of the power distribution equipment.
[0059] Step S200: Use sensors to monitor the power distribution equipment, obtain historical sensor data records of the power distribution equipment, divide the historical sensor data records of the power distribution equipment based on characteristic time periods of the power distribution equipment, obtain characteristic historical sensor data records of the power distribution equipment, extract corresponding data of operating parameters of the power distribution equipment from the characteristic historical sensor data records, and analyze the operating parameters that have an abnormal impact on the power distribution equipment line to obtain operating parameter impact data of the power distribution equipment;
[0060] For example, operating parameters include temperature and humidity within the power distribution equipment;
[0061] Wherein, step S200 includes:
[0062] Step S201: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record;
[0063] Step S202: analyzing the operating parameters and corresponding values of the operating parameters that affect the operation of the power distribution equipment in the characteristic time period to which the characteristic historical sensor data record belongs, wherein the process of analyzing the operating parameters and corresponding values of the operating parameters that affect the operation of the power distribution equipment in the characteristic time period is as follows: dividing the f-th characteristic time period into a number of time periods according to the unit time length, and sorting the several time periods based on the time sequence, recording the several time periods as the marked time periods of the characteristic time periods, and obtaining the average values of the various operating parameters of the power distribution equipment in the last marked time period and the first marked time period in the f-th characteristic time period from the equipment fault information;
[0064] Step S203: Obtain the maximum value of the average values of the first marking period in each characteristic period for each operating parameter in the power distribution equipment, and use the maximum value as the marking control value of each operating parameter; when the average value of a certain operating parameter in the last marking period of the f-th characteristic period is greater than the corresponding marking control value, the average value of a certain operating parameter in the last marking period of the f-th characteristic period is recorded as the marking threshold of the certain operating parameter in the f-th characteristic period, and the certain operating parameter is recorded as the characteristic operating parameter of the power distribution equipment in the f-th characteristic period;
[0065] Step S204: acquiring each characteristic operation parameter and a marking threshold value of each characteristic operation parameter in each characteristic time period respectively, and collecting each characteristic operation parameter and a marking threshold value of each characteristic operation parameter acquired in each characteristic time period to obtain operation parameter influence data of the power distribution equipment;
[0066] Step S300: Obtain usage data of electrical components in the power distribution equipment from the equipment fault information, select electrical components that affect the operating parameters of the power distribution equipment from the equipment fault information based on the usage data, obtain the usage status of the electrical components of the power distribution equipment in the current cycle, and analyze the degree of influence on the line abnormality of the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle in combination with the influence data of the operating parameters of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment;
[0067] Wherein, step S300 includes:
[0068] Step S301: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record;
[0069] Step S302: Obtain and mark the equipment fault information belonging to the characteristic time period, extract the usage data of each electrical component in the power distribution equipment from the marked equipment fault information, the usage data includes the usage time of each electrical component in the power distribution equipment, and obtain the preset standard service life of each electrical component in the power distribution equipment;
[0070] Step S303: Calculate the characteristic usage value of each electrical component of the power distribution equipment in the marked equipment fault information, where the characteristic usage value of the ath electrical component in the power distribution equipment is :
[0071] ;
[0072] in, is the usage time of the ath electrical component of the power distribution equipment in the marked equipment fault information; is the standard service life of the ath electrical component of the power distribution equipment in the marked equipment fault information;
[0073] Step S304: setting a characteristic usage threshold. When the characteristic usage value of a certain electrical component in the power distribution equipment in the marked device fault information is greater than the characteristic usage threshold, the certain electrical component is recorded as a characteristic electrical component, and the characteristic electrical components in the power distribution equipment in the marked device fault information are collected.
[0074] Step S305: Obtain the usage time of each electrical component in the power distribution equipment in the current cycle, analyze the influence of different values of operating parameters in the current cycle on the line abnormality state of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment, wherein the line abnormality influence state analysis process includes, based on the usage time of each electrical component of the power distribution equipment in the current cycle, calculating the characteristic usage value of each electrical component in the power distribution equipment in the current week, and selecting the characteristic electrical components in the power distribution equipment in the current cycle;
[0075] Step S306: Calculate the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of each characteristic period, wherein the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of the kth characteristic period is calculated. , j represents the characteristic electrical components of the power distribution equipment in the current cycle, and the total number of characteristic electrical components with the same model as the characteristic electrical components of the power distribution equipment in the kth characteristic period, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle in the k-th characteristic period;
[0076] For example, the total number j of characteristic electrical components of the power distribution equipment in the current cycle that have the same model as the characteristic electrical components of the power distribution equipment in the first characteristic period is 2, and the first characteristic electrical component in the current cycle that has the same model as the first characteristic period is is 0.3, the second characteristic electrical component with the same model as the first characteristic period in the current cycle =0.6, the first characteristic electrical component with the same model as the first characteristic period in the current cycle, the characteristic usage value in the first characteristic period =0.4, the characteristic usage value of the second characteristic electrical component with the same model as the first characteristic period in the current cycle in the first characteristic period =0.5, the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of the first characteristic period ;
[0077] Step S307: Setting a similarity threshold. When the similarity between the current cycle and the electrical component usage status of a certain characteristic period is greater than or equal to the similarity threshold, obtaining the marking threshold of each characteristic operating parameter in a certain characteristic period from the operating parameter influence data of the power distribution equipment and marking them, and taking the marking threshold of each characteristic operating parameter in the characteristic period corresponding to the maximum similarity value as the characteristic threshold of the corresponding characteristic operating parameter of the power distribution equipment in the current cycle.
[0078] Step S308: When a certain operating parameter exists in the current cycle and is not in the various characteristic operating parameters in the characteristic time period corresponding to the maximum similarity value, the marking threshold of the characteristic operating parameter identical to the certain operating parameter is obtained from each marked characteristic time period according to the order of similarity, and is used as the characteristic threshold of a certain operating parameter of the power distribution equipment in the current cycle;
[0079] Step S309: When the similarity between the use status of electrical components in the current cycle and each characteristic time period is less than the similarity threshold, the power distribution equipment database is obtained, and the standard thresholds of various operating parameters preset by the power distribution equipment in the power distribution equipment database are used as the characteristic thresholds of various operating parameters, and the characteristic thresholds of various operating parameters in the power distribution equipment in the current cycle are aggregated to obtain the line abnormality impact data of the power distribution equipment in the current cycle;
[0080] Step S400: adjusting the intelligent control device in the power distribution equipment in the current cycle according to the line abnormality impact data of the power distribution equipment, evaluating the line abnormality in the power distribution equipment in the current cycle, and using the intelligent control device to intelligently adjust the environment inside the power distribution equipment;
[0081] For example, intelligent control devices include intelligent humidity control devices and intelligent temperature control devices;
[0082] Wherein, step S400 includes:
[0083] Step S401: obtaining the intelligent control device in the power distribution equipment in the current cycle, and combining the line abnormality impact data of the power distribution equipment in the current cycle, obtaining the characteristic thresholds of various operating parameters of the power distribution equipment in the current cycle, and inputting them into the intelligent control device, and adjusting the thresholds of the operating parameters preset in the intelligent control device;
[0084] Step S402: Use the intelligent control device to monitor various operating parameters of the power distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the power distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the power distribution equipment, and the intelligent control device is used to intelligently adjust the environment inside the power distribution equipment;
[0085] In order to better implement the above method, a distribution equipment line abnormality monitoring system is also proposed, which includes a characteristic time period module, an operating parameter impact data module, a line abnormality impact module, and an intelligent adjustment module;
[0086] A characteristic time period module is used to extract the time period when the power distribution equipment fails from a number of equipment failure information and mark it as the characteristic time period of the power distribution equipment;
[0087] The operating parameter impact data module is used to analyze the operating parameters that have an abnormal impact on the power distribution equipment line and obtain the operating parameter impact data of the power distribution equipment;
[0088] The line abnormality impact module is used to analyze the impact of line abnormality on the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle, and obtain the line abnormality impact data of the power distribution equipment;
[0089] An intelligent adjustment module is used to evaluate the line anomalies in the power distribution equipment in the current cycle and use intelligent control devices to intelligently adjust the environment inside the power distribution equipment;
[0090] Wherein, the characteristic period module includes a characteristic period unit;
[0091] The characteristic time period unit is used to evaluate the similarity between the equipment fault report and each line abnormality keyword through a text similarity algorithm. When the similarity between the equipment fault report and a line abnormality keyword is greater than a preset value, it is determined that the equipment fault information of the equipment fault report is related to the abnormality of the power distribution equipment line, and the time period when the power distribution equipment fails in the equipment fault information is recorded as the characteristic time period of the power distribution equipment;
[0092] Among them, the operating parameter impact data module includes a characteristic operating parameter unit and an operating parameter impact data unit;
[0093] A characteristic operation parameter unit is used to analyze the operation parameters that affect the operation of the power distribution equipment in the characteristic period to which the characteristic historical sensor data record belongs, and obtain the characteristic operation parameters of the power distribution equipment in the characteristic period;
[0094] The operating parameter impact data unit is used to collect various characteristic operating parameters and marking thresholds of various characteristic operating parameters acquired in various characteristic time periods to obtain operating parameter impact data of the power distribution equipment;
[0095] Among them, the line abnormality impact module includes a characteristic electrical component unit and a line abnormality impact unit;
[0096] A characteristic electrical component unit is used to calculate characteristic usage values of various electrical components of the power distribution equipment in the marked equipment fault information, and obtain characteristic electrical components in the power distribution equipment within a characteristic period;
[0097] The line abnormality impact unit is used to collect characteristic thresholds of various operating parameters in the power distribution equipment in the current cycle to obtain line abnormality impact data of the power distribution equipment in the current cycle;
[0098] Wherein, the intelligent adjustment module includes an intelligent adjustment unit;
[0099] The intelligent adjustment unit is used to use the intelligent control device to monitor the various operating parameters of the distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the distribution equipment, and the intelligent control device is used to intelligently adjust the internal environment of the distribution equipment.
[0100] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0101] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for monitoring abnormality of power distribution equipment lines based on big data. It is characterized in that The method comprises: Step S100: when a power distribution device fails, the fault information of each device of the power distribution device is obtained, and from the fault information of each device, a plurality of pieces of equipment fault information related to the abnormality of the power distribution device line are selected, and the time period when the power distribution device fails is extracted from the plurality of pieces of equipment fault information and marked as the characteristic time period of the power distribution device; Step S200: Use sensors to monitor the power distribution equipment, obtain historical sensor data records of the power distribution equipment, divide the historical sensor data records of the power distribution equipment based on characteristic time periods of the power distribution equipment, obtain characteristic historical sensor data records of the power distribution equipment, extract corresponding data of operating parameters of the power distribution equipment from the characteristic historical sensor data records, and analyze the operating parameters that have an abnormal impact on the power distribution equipment line to obtain operating parameter impact data of the power distribution equipment; Step S300: Obtain usage data of electrical components in the power distribution equipment from the equipment fault information, select electrical components that affect the operating parameters of the power distribution equipment from the equipment fault information based on the usage data, obtain the usage status of the electrical components of the power distribution equipment in the current cycle, and analyze the degree of influence on the line abnormality of the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle in combination with the influence data of the operating parameters of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment; Step S400: According to the line abnormality impact data of the power distribution equipment, the intelligent control device in the power distribution equipment in the current cycle is adjusted, the line abnormality in the power distribution equipment in the current cycle is evaluated, and the intelligent control device is used to intelligently adjust the environment inside the power distribution equipment.
2. According to the method for monitoring abnormality of power distribution equipment lines based on big data according to claim 1, It is characterized in that The step S100 includes: Step S101: respectively obtaining equipment failure information of the power distribution equipment when the power distribution equipment fails in each historical period, obtaining the time period when the power distribution equipment fails in the equipment failure information, extracting the equipment failure report of the power distribution equipment from the equipment failure information, and obtaining each line abnormality keyword preset and related to the line abnormality of the power distribution equipment; Step S102: Evaluate the similarity between the equipment fault report and the various line abnormality keywords through a text similarity algorithm. When the similarity between the equipment fault report and a certain line abnormality keyword is greater than a preset value, determine that the equipment fault information to which the equipment fault report belongs is related to the abnormality of the distribution equipment line, and record the time period when the distribution equipment fails in the equipment fault information as the characteristic time period of the distribution equipment.
3. According to the method for monitoring abnormality of power distribution equipment lines based on big data in claim 2, It is characterized in that The step S200 includes: Step S201: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record; Step S202: analyzing the operating parameters that affect the operation of the power distribution equipment and the corresponding values of the operating parameters in the characteristic time period to which the characteristic historical sensor data record belongs, wherein the process of analyzing the operating parameters that affect the operation of the power distribution equipment and the corresponding values of the operating parameters in the characteristic time period is to divide the f-th characteristic time period into a number of time periods according to the unit time length, and sort the several time periods based on the time sequence, record the several time periods as the marked time periods of the characteristic time periods, and obtain the average values of the various operating parameters of the power distribution equipment in the last marked time period and the first marked time period in the f-th characteristic time period from the equipment fault information; Step S203: obtaining the maximum value of the average values of the first marking period in each characteristic period for each operating parameter in the power distribution equipment, and taking the maximum value as the marking control value of each operating parameter; when the average value of a certain operating parameter in the last marking period of the f-th characteristic period is greater than the corresponding marking control value, the average value of a certain operating parameter in the last marking period of the f-th characteristic period is recorded as the marking threshold of the certain operating parameter in the f-th characteristic period, and the certain operating parameter is recorded as the characteristic operating parameter of the power distribution equipment in the f-th characteristic period; Step S204: respectively obtain various characteristic operating parameters and marking thresholds of the characteristic operating parameters in each characteristic time period, and collect the obtained various characteristic operating parameters and marking thresholds of the characteristic operating parameters in each characteristic time period to obtain operating parameter influence data of the power distribution equipment.
4. According to the method for monitoring abnormality of power distribution equipment lines based on big data according to claim 3, It is characterized in that The step S300 includes: Step S301: Acquire each historical sensor data record of the power distribution equipment, acquire each characteristic time period of the power distribution equipment, record the historical sensor data record of the power distribution equipment in the characteristic time period as a characteristic historical sensor data record, and extract corresponding data of each operating parameter of the power distribution equipment from the characteristic historical sensor data record; Step S302: Obtaining and marking the equipment failure information belonging to the characteristic time period, extracting the usage data of each electrical component in the power distribution equipment from the marked equipment failure information, wherein the usage data includes the usage time of each electrical component in the power distribution equipment, and obtaining the preset standard service life of each electrical component in the power distribution equipment; Step S303: Calculate the characteristic usage value of each electrical component of the power distribution equipment in the marked equipment fault information, where the characteristic usage value of the ath electrical component in the power distribution equipment is : ; in, is the usage time of the ath electrical component of the power distribution equipment in the marked equipment fault information; is the standard service life of the ath electrical component of the power distribution equipment in the marked equipment fault information; Step S304: setting a characteristic usage threshold, when the characteristic usage value of a certain electrical component in the power distribution equipment in the marked device fault information is greater than the characteristic usage threshold, the certain electrical component is recorded as a characteristic electrical component, and the characteristic electrical components in the power distribution equipment in the marked device fault information are collected; Step S305: Obtain the usage time of each electrical component in the power distribution equipment in the current cycle, analyze the influence of different values of operating parameters in the current cycle on the line abnormality state of the power distribution equipment, and obtain the line abnormality influence data of the power distribution equipment, wherein the line abnormality influence state analysis process includes, based on the usage time of each electrical component of the power distribution equipment in the current cycle, calculating the characteristic usage value of each electrical component in the power distribution equipment in the current week, and selecting the characteristic electrical components in the power distribution equipment in the current cycle; Step S306: Calculate the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of each characteristic period, wherein the similarity between the usage status of the electrical components of the power distribution equipment in the current cycle and the usage status of the power distribution equipment in the equipment fault information of the kth characteristic period is calculated. , j represents the characteristic electrical components of the power distribution equipment in the current cycle, and the total number of characteristic electrical components with the same model as the characteristic electrical components of the power distribution equipment in the kth characteristic period, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle, Indicates the characteristic usage value of the i-th characteristic electrical component with the same model as the k-th characteristic period in the current cycle in the k-th characteristic period; Step S307: Setting a similarity threshold. When the similarity between the current cycle and the electrical component usage status of a certain characteristic time period is greater than or equal to the similarity threshold, obtaining and marking the marking thresholds of the characteristic operating parameters in the characteristic time period from the operating parameter influence data of the power distribution equipment, and marking the marking thresholds of the characteristic operating parameters in the characteristic time period corresponding to the maximum similarity value as the characteristic thresholds of the corresponding characteristic operating parameters of the power distribution equipment in the current cycle. Step S308: When there is a certain operating parameter in the current cycle that is not in the various characteristic operating parameters in the characteristic time period corresponding to the maximum similarity value, the marking threshold of the characteristic operating parameter identical to the certain operating parameter is obtained from each marked characteristic time period according to the order of similarity, as the characteristic threshold of the certain operating parameter of the power distribution equipment in the current cycle; Step S309: When the similarity between the usage status of electrical components in the current cycle and each characteristic time period is less than the similarity threshold, obtain the distribution equipment database, and use the standard thresholds of the preset operating parameters of the distribution equipment in the distribution equipment database as the characteristic thresholds of the operating parameters. The characteristic thresholds of the operating parameters in the distribution equipment in the current cycle are aggregated to obtain the line abnormality impact data of the distribution equipment in the current cycle.
5. According to the method for monitoring abnormality of power distribution equipment lines based on big data in claim 1, It is characterized in that The step S400 includes: Step S401: obtaining an intelligent control device in the power distribution equipment in the current cycle, and combining the line abnormality impact data of the power distribution equipment in the current cycle, obtaining characteristic thresholds of various operating parameters of the power distribution equipment in the current cycle, and inputting them into the intelligent control device, and adjusting the thresholds of the operating parameters preset in the intelligent control device; Step S402: Use the intelligent control device to monitor the various operating parameters of the power distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the power distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the power distribution equipment, and the intelligent control device is used to intelligently adjust the environment inside the power distribution equipment.
6. A distribution equipment line abnormality monitoring system using a distribution equipment line abnormality monitoring method based on big data as described in any one of claims 1 to 5, It is characterized in that The monitoring system includes a characteristic time period module, an operating parameter impact data module, a line abnormality impact module, and an intelligent adjustment module; The characteristic time period module is used to extract the time period when the power distribution equipment fails from the plurality of equipment failure information and mark it as the characteristic time period of the power distribution equipment; The operating parameter impact data module is used to analyze the operating parameters that have an abnormal impact on the power distribution equipment line to obtain the operating parameter impact data of the power distribution equipment; The line abnormality impact module is used to analyze the influence degree of line abnormality on the power distribution equipment under different values of the operating parameters of the power distribution equipment in the current cycle, and obtain the line abnormality impact data of the power distribution equipment; The intelligent adjustment module is used to evaluate the line anomalies in the power distribution equipment in the current cycle, and use the intelligent control device to intelligently adjust the environment inside the power distribution equipment.
7. The power distribution equipment line abnormality monitoring system according to claim 6, It is characterized in that The characteristic period module includes a characteristic period unit; The characteristic time period unit is used to evaluate the similarity between the equipment fault report and each line abnormality keyword through a text similarity algorithm. When the similarity between the equipment fault report and a certain line abnormality keyword is greater than a preset value, it is determined that the equipment fault information to which the equipment fault report belongs is related to the abnormality of the distribution equipment line, and the time period when the distribution equipment fails in the equipment fault information is recorded as the characteristic time period of the distribution equipment.
8. The power distribution equipment line abnormality monitoring system according to claim 6, It is characterized in that The operating parameter impact data module includes a characteristic operating parameter unit and an operating parameter impact data unit; The characteristic operation parameter unit is used to analyze the operation parameters that affect the operation of the power distribution equipment in the characteristic period to which the characteristic historical sensor data record belongs, and obtain the characteristic operation parameters of the power distribution equipment in the characteristic period; The operating parameter impact data unit is used to collect the acquired characteristic operating parameters in each characteristic time period and the marking thresholds of the characteristic operating parameters to obtain the operating parameter impact data of the power distribution equipment.
9. The power distribution equipment line abnormality monitoring system according to claim 6, It is characterized in that The line abnormality impact module includes a characteristic electrical component unit and a line abnormality impact unit; The characteristic electrical component unit is used to calculate the characteristic usage value of each electrical component of the power distribution equipment in the marked equipment fault information, and obtain the characteristic electrical components in the power distribution equipment within the characteristic time period; The line abnormality impact unit is used to collect characteristic thresholds of various operating parameters in the power distribution equipment in the current cycle to obtain line abnormality impact data of the power distribution equipment in the current cycle.
10. The power distribution equipment line abnormality monitoring system according to claim 6, It is characterized in that The intelligent adjustment module includes an intelligent adjustment unit; The intelligent adjustment unit is used to use an intelligent control device to monitor various operating parameters of the distribution equipment in the current cycle. When the intelligent control device detects that the corresponding value of the operating parameter of the distribution equipment in the current cycle is greater than the corresponding threshold, it is determined that there is a line abnormality risk in the distribution equipment, and the intelligent control device is used to intelligently adjust the internal environment of the distribution equipment.