A temporary power safety and energy consumption control system and method
By designing temporary electricity safety and energy consumption management and control systems in construction projects, real-time data collection of terminal equipment and dynamic monitoring of cloud platforms are realized, which solves potential safety hazards and energy consumption management problems of temporary electricity use in construction projects, and improves construction safety. performance and energy management efficiency.
Patent Information
- Application Number
- CN202410547361.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-06
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-05-06
AI Technical Summary
Temporary power use in construction projects has safety hazards such as wire leakage and overtemperature. Traditional regular inspections are difficult to detect equipment abnormalities in advance, and the frequency of data collection is low and cannot be monitored in real time, resulting in increased energy consumption and difficult to control safety risks.
Design a temporary electricity safety and energy consumption management and control system that collects power parameters through terminal equipment and transmits them to the cloud platform through wireless signals to achieve real-time data analysis and alarms. It combines BIM models for dynamic monitoring and early warning, and supports millisecond-level data collection and Data denoising and filtering technology.
Shorten fault finding time, reduce construction site operation and maintenance workload, improve construction safety and energy consumption management efficiency, reduce power waste, ensure construction reliability and save human resources.
Smart Images

Figure CN118137677B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of temporary power safety and energy consumption management of construction projects, and in particular relates to a temporary power safety and energy consumption management system and method. Background Art
[0002] Temporary electricity for construction projects includes electricity for construction areas and electricity for office and living areas. The construction area may have hidden dangers such as cable cracking, water immersion, failure of leakage protection, equipment overload or operation with defects, long-term line overload, poor contact of cable heads, live wire grounding, and live wire disconnection, which may lead to problems such as wire leakage and overheating. The electricity consumption in the office and living area has problems such as scattered electrical equipment, long-term unmanned operation of air-conditioning equipment, and arbitrary addition of equipment leading to line overload, which leads to increased energy consumption and safety hazards. In addition, the traditional method of regular inspections is to investigate and deal with safety hazards of temporary electricity use. However, due to the complexity of mechanical and electrical equipment on the construction site and the limited technical level of personnel, it is impossible to detect equipment abnormalities in advance, and it is difficult to cover the inspection range 100%, making it difficult to achieve timely and effective inspections, which is not conducive to the early prevention of accidents. Moreover, the existing data collector uses a "one-to-many" wiring method to access meter information, and the data transmission channel is limited. It mostly uses a "polling" method, which cannot achieve real-time data collection; the meter collection frequency is limited, and only minute-level data collection can be achieved, which cannot reproduce the actual occurrence process of the event, which is not conducive to the investigation of the true cause of the event; the equipment online rate is low, and the error is large, and it cannot reflect the true status of the equipment. In response to the above problems, it is urgent to develop relevant safety and energy consumption control systems for temporary power systems to dynamically monitor the relevant power parameters of the power system and improve the safety and energy saving of temporary power system operation. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention provides a temporary electricity safety and energy consumption control system and method, which realizes digital monitoring of temporary power systems on construction sites, shortens fault finding time, and reduces the workload of operation and maintenance of construction site power distribution systems.
[0004] The present invention achieves the above technical objectives through the following technical means.
[0005] A temporary power safety and energy consumption control system includes a terminal installed in a distribution box and an incoming line end of power-consuming equipment. The terminal is used to collect power parameters related to the terminal equipment of the temporary power system and transmit them to a cloud platform via wireless signals. The cloud platform is used to perform data analysis and processing and output temporary power system operation information. The cloud platform is also connected to a client, which is used to access the cloud platform or receive relevant information.
[0006] Furthermore, when the terminal is installed on the housing of the distribution box, a slot is provided on the housing of the distribution box according to the size of the terminal, and the terminal passes through the slot and is fixed by a clamp; the clamp includes an L-shaped plug-in, a locking piece is provided at the rear end of the L-shaped plug-in, the L-shaped plug-in is inserted into the side slot of the terminal, and the locking piece is pressed down to achieve nesting and top tightening with the slot;
[0007] When the terminal is installed on the electrical equipment using a slot box, a plurality of spring plates are symmetrically arranged on the inner wall of the slot box, each of which is provided with a triangular protrusion. A card slot matching the spring plate is arranged on the outer wall of the terminal, each of which is provided with a triangular groove matching the triangular protrusion. The terminal is inserted into the slot box, and the triangular protrusion is embedded in the triangular groove.
[0008] Furthermore, the terminal includes an electric power parameter setting module, a display module, a parameter acquisition module, an on-site alarm module, and a wireless signal transmission module; the electric power parameter setting module is used to manually set the safety limits of current, voltage, etc.; the display module is used to display the electric power parameters monitored in real time; the on-site alarm module is used to sound and light alarm when the electric power parameters exceed the safety limits; the wireless signal transmission module transmits the monitored electric power parameters to the cloud platform in real time through wireless signals; the parameter acquisition module is reserved with a plug port for accessing electric power parameter data, the parameter acquisition module includes a current monitoring module, a voltage monitoring module, a temperature monitoring module, and a leakage current monitoring module, the parameter acquisition module uses data denoising and filtering technology to extract electrical safety-related indicators, event alarm-related records, and the trigger point and end point waveforms of the recorded data, including period, peak value, valley value, phase angle, and frequency; the parameter acquisition module uses data packaging and time-sharing upload technology to avoid large-scale data loss, and supports communication interruption and continuation, including S-level + min-level data event data packaging technology, adaptive waveform data interception technology, data fitting technology, and wavelet analysis technology.
[0009] Furthermore, the cloud platform is a temporary power management platform built on a cloud server, including a data receiving module, a data storage module, a data analysis module, a temporary power system database, an alarm module, and a display module; the data receiving module receives the power parameter data transmitted from the terminal in real time, and transmits it to the data storage module for storage; the data storage module stores the BIM model and power parameter data; the temporary power system database includes a list of temporary power equipment, the area where the temporary power equipment is located is divided into a construction area and an office and living area, the temporary power equipment in the construction area is divided into fixed equipment and mobile equipment, a GPS locator is installed on the mobile device, and the three-level distribution box and power equipment are encoded, including location information and attribute information, and the location information includes the floor The information, plane area information, and attribute information are written into the BIM model of the data storage module, including the product name of the temporary power equipment, rated current, rated voltage, rated operating temperature, rated leakage protection current, production date, service life, cumulative usage time, and regular maintenance plan; the data analysis module is based on the temporary power system database, and matches the real-time monitored power parameters with the parameter limits in the attribute information in the BIM model, and performs dynamic data comparison analysis, calculation and statistics based on the built-in algorithm; the alarm module issues an alarm based on the analysis of the data analysis module to remind relevant personnel; the display module is used to display the power parameters and status parameters in real time, and is used to set the power parameter threshold, duration and warning level of the terminal.
[0010] The temporary power safety and energy consumption control method using the temporary power safety and energy consumption control system includes the following process:
[0011] The terminal uses the data acquisition module to collect the relevant power parameters of temporary power equipment and sends them to the cloud platform through wireless communication. After the data receiving module of the cloud platform receives the power parameters, it is sent to the data storage module and the data analysis module for storage and analysis. The data analysis module combines the data in the database of the temporary power system to perform calculations and analysis, monitor the overload temperature rise and leakage current of the line in real time, monitor the current, voltage, active power, reactive power, power factor, frequency, and main transformer load rate of temporary power equipment in real time to see if they are within the preset safety range, monitor the power quality in real time, calculate the power consumption and electricity charges in real time, and count the power consumption. The relevant data is sent to the display module for visual display so that relevant personnel can view and understand the various conditions of the power equipment. At the same time, the data analysis module establishes a three-level early warning mechanism to realize automatic early warning and alarm, and displays the alarm data on the display module to remind relevant personnel to check and repair in time. At the same time, the alarm is sent to the remote client through the wireless communication network to notify relevant management personnel to handle it in time.
[0012] The three-level early warning mechanism includes: early warning before the event, warning during the event, and post-event tracing;
[0013] Pre-warning includes two methods: day-ahead forecast and real-time forecast. The day-ahead forecast is based on 0:00 of the day, and forecasts data of 48 points every 30 minutes in the future, providing preliminary guidance for the management work of the day. The real-time forecast is a rolling forecast of 8 points of data every 30 minutes for the next 4 hours, providing dynamic guidance for the management work of the day. There are two forecasting methods, namely the forecasting method based on interval operation and the forecasting method based on affine arithmetic.
[0014] In-process alarm refers to the establishment of an in-process alarm system with three dimensions: threshold, duration, and warning level. The warning levels include level 1, level 2, and level 3. The mutations include load rate, overvoltage, and overcurrent indicators. The corresponding warning level is determined according to the duration, and an alarm form is formed. The alarm form includes the warning time, level, abnormal duration, monitoring point, phenomenon, and cause.
[0015] Post-fault tracing is based on actual monitoring data for fault diagnosis and algorithm analysis of characteristic values. Different characteristic values correspond to different fault types. The fault type is located according to the characteristic value, and countermeasures are given, including single-phase grounding, two-phase grounding, two-phase short circuit, three-phase short circuit, single-phase line break, two-phase line break, and three-phase line break.
[0016] Furthermore, the prediction method based on interval operation is as follows:
[0017] S1: Data preparation: Collect historical temporary power load data, take the historical 7 days as the analysis period, take 30 minutes as the unit, form a time series, and pre-process the data;
[0018] S2: Interval modeling: converting historical temporary power load data into interval representation;
[0019] S3: Interval calculation: Use interval calculation to process the historical data interval and predict the power load in the next n hours. Perform the following interval calculation:
[0020]
[0021]
[0022] Among them, G min is the minimum predicted load for the next n hours; G max is the maximum predicted load in the next n hours; m represents the prediction time range; x min (τ) represents the minimum power load at time τ obtained based on historical data; x max (τ) represents the maximum power load at time τ obtained based on historical data; τ represents the time corresponding to the time step; t represents time;
[0023] In order to more accurately obtain the power load at time τ, the following formula is used for prediction:
[0024] G(τ)=k1x1(τ)+k2x2(τ)+……+k i x i (τ)
[0025] Among them, G(τ) represents the temporary power load at time τ; x1(τ), x2(τ)...x i (τ) represents the different load sizes at time τ obtained based on historical data, k1, k2, ..., k i All represent the ratio of different loads at time τ obtained based on historical data, k1+k2+…k i =1;
[0026] S4: Prediction: Based on the interval calculation results, the interval prediction of future temporary power load is obtained;
[0027] S5: Model evaluation: Evaluate the prediction results, compare the difference between the predicted interval and the actual observed value, calculate the corresponding error index, and adjust and improve the model according to the evaluation results.
[0028] Furthermore, the prediction method based on affine arithmetic is as follows:
[0029] S1: Data preparation: collect historical temporary power load data and perform preprocessing;
[0030] S2: Model establishment: Establish an affine model to fit the historical power load data. The affine model is expressed as:
[0031] Y(t)=aX(t)+b
[0032] Where Y(t) is the predicted power load at time t, X(t) is the historical power load, a is the scaling factor, and b is the offset;
[0033] S3: Parameter estimation: Estimate and optimize the model parameters a and b based on historical data through the least squares method, so that the model fits the historical data best;
[0034] S4: Prediction: Use the optimized model parameters to predict the future temporary power load and predict the power load in the next n hours:
[0035] Y'(t+m)=aX(t)+b
[0036] Among them, Y'(t+m) is the predicted power load at time t+m, and m represents the prediction time range;
[0037] S5: Model evaluation: Evaluate the prediction results, compare the differences between the predicted values and the actual observed values, calculate the corresponding error indicators, and adjust and improve the model based on the evaluation results.
[0038] Furthermore, the specific method of the fault diagnosis is as follows:
[0039] S1: Data collection and preprocessing: collect the actual data including voltage, current and power from the temporary power system in real time, remove noise and abnormal values, and perform smoothing and time synchronization on the data;
[0040] S2: Feature extraction: Extracting fault-related features, including voltage and current waveform features;
[0041] S3: Fault diagnosis model construction: Based on the extracted features, a fault diagnosis model is established;
[0042] S4: Model training and evaluation: Train the fault diagnosis model based on historical data, and evaluate the accuracy, recall rate, and precision indicators of the model through cross-validation technology to ensure its effectiveness in the actual environment;
[0043] S5: Real-time fault diagnosis: Input the real-time collected data into the trained fault diagnosis model to perform real-time fault diagnosis. The model output results indicate the possible fault type, location, and probability.
[0044] S6: Fault location and repair: According to the diagnosis results, determine the specific location and cause of the fault, and take corresponding maintenance measures according to the fault diagnosis results, including replacing damaged equipment, adjusting circuit connections, and cleaning electrical contact points;
[0045] S7: Continuous monitoring and improvement: Continuously monitor the operating status of the temporary power system, collect real-time data, improve and optimize the fault diagnosis algorithm based on actual conditions, and update the model regularly.
[0046] Furthermore, the wavelet analysis technology used in the power parameter data acquisition process of the parameter acquisition module in the terminal (1) is: setting a continuous electrical signal x(t), using wavelet transform to represent it as a wavelet coefficient c j,k and basic wavelet functions Function:
[0047]
[0048] Among them, j represents the scale parameter, k represents the displacement parameter;
[0049] After wavelet transform, c j,k Perform soft threshold processing, set the wavelet coefficients less than the threshold λ to zero, and retain the wavelet coefficients greater than or equal to the threshold λ, expressed as:
[0050]
[0051] Among them, (·)+ represents a positive function, Represents wavelet coefficients greater than or equal to the threshold λ;
[0052] After wavelet coefficient selection, the compressed signal is reconstructed using inverse wavelet transform. The inverse wavelet transform will retain the wavelet coefficients. and basic wavelet functions Perform linear combination to obtain the reconstructed compressed signal x rec (t):
[0053]
[0054] Based on the above process, the electrical signal data compression of the temporary power transmission line is realized, and the degree of compression is controlled by adjusting the threshold λ to meet different compression requirements.
[0055] The present invention has the following beneficial effects:
[0056] The present invention realizes digital monitoring of temporary power systems at construction sites by collecting data on key lines and key equipment, shortens fault finding time, and reduces the workload of operation and maintenance of power distribution systems at construction sites; through millisecond-level data collection, it identifies power safety risks and abnormal working conditions of equipment, reduces construction delays caused by equipment failures, assists operation and maintenance personnel to reasonably arrange maintenance time, improves the reliability of power supply at construction sites, and lays a solid foundation for the timely delivery of projects; through real-time monitoring of leakage current at construction sites, it studies and judges the trend of leakage current changes, guides the operation and maintenance team at construction sites to perform precise operation and maintenance, and ensures the safety of construction at construction sites. It identifies abnormal power consumption behaviors in living areas during construction periods, reduces energy waste, and can reduce the workload of site operation inspections, save human resource costs, and save non-productive expenditures of projects. Based on the platform, it monitors energy usage in real time to understand which equipment or processes are consuming a lot of energy, so as to formulate corresponding optimization strategies; uses timing controllers, sensors, and automation systems to manage the opening and closing time of temporary power equipment, ensuring that the equipment runs when needed and automatically shuts down during non-working hours. By logging in with an authorized account and password through a mobile phone APP, you can understand the company's electricity safety situation anytime and anywhere through your mobile phone, understand the safety status of the power system on your hand, and promptly alert the safety personnel of any abnormalities through early warning. BRIEF DESCRIPTION OF THE DRAWINGS
[0057] Figure 1 This is a schematic diagram of the temporary power safety and energy consumption control system of the present invention;
[0058] Figure 2Schematic diagram of the installation of the intelligent data acquisition terminal and the distribution box housing of the present invention
[0059] Figure 3 This is a schematic diagram of the card structure of the present invention;
[0060] Figure 4 This is a schematic diagram of the installation of the card component of the present invention;
[0061] Figure 5 This is a schematic diagram of the installation and separation of the intelligent data collection terminal and the trough box of the present invention;
[0062] Figure 6 This is a schematic diagram of the tank box structure of the present invention;
[0063] Figure 7 This is a schematic diagram of the cloud platform composition of the present invention;
[0064] In the figure: 1-terminal; 2-cloud platform; 3-client; 4-distribution box housing; 5-card; 501-L-shaped plug-in; 502-locking piece; 6-slot box; 7-spring; 8-triangular groove; 9-rubber protrusion; 10-triangular protrusion. DETAILED DESCRIPTION
[0065] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.
[0066] like Figure 1 As shown, the temporary power safety and energy consumption control system described in the present invention includes an intelligent data acquisition terminal (hereinafter referred to as terminal 1), a cloud platform 2, and a client 3; the terminal 1 collects power parameters related to the terminal equipment of the temporary power system, transmits them to the cloud platform 2 via wireless signals such as 4G / 5G, performs data analysis and processing based on the cloud platform 2, and outputs temporary power system operation information, and accesses the cloud platform 2 or receives relevant information through the client 3.
[0067] Terminal 1 is installed on the distribution box and the incoming line end of the power-consuming equipment. It is installed on the distribution box housing 4 through a special clamp or installed on the power-consuming equipment using a trough box. Its power cord is connected to the incoming line of the distribution box to continuously provide power to terminal 1.
[0068] like Figures 2 to 4As shown, when the terminal 1 is installed on the distribution box housing 4, a slot is provided on the distribution box housing 4 according to the size of the terminal 1, and the terminal 1 passes through the slot, and the gap between the slot and the terminal 1 is within 0.5 mm; two card slots are respectively provided on both sides of the terminal 1, and a card member 5 is installed in the card slot, and the terminal 1 is fixed to the distribution box housing 4 through the card member 5. The card member 5 includes an L-shaped plug-in 501 and a locking member 502. First, the L-shaped plug-in 501 is inserted into the card slot for nesting and fixing, and then the locking member 502 at the tail end of the L-shaped plug-in 501 is pressed in force, so that the L-shaped plug-in 501 is completely embedded in the card slot and tightened, and the terminal 1 is fixed based on the interaction force between the card slot, the distribution box housing 4 and the locking member 502.
[0069] like Figure 5 , 6 As shown, when the terminal 1 is installed on the electrical equipment using a slot box 6, the slot box 6 and the terminal 1 are connected through matching card slots and spring sheets 7; specifically, four spring sheets 7 are symmetrically arranged on the inner wall of the slot box 6, and triangular protrusions 10 are arranged on the spring sheets 7. A card slot matching the spring sheets 7 is arranged on the outer wall of the terminal 1, and a triangular groove 8 matching the triangular protrusion 10 is arranged in the card slot, so that the terminal 1 can be inserted into the slot box 6. When the terminal 1 is inserted into the slot box 6, the triangular protrusion 10 is embedded in the triangular groove 8, and the slot box 6 and the terminal 1 are connected; in addition, a conical rubber protrusion 9 is also arranged on the upper part of the terminal 1, and the relative stability between the terminal 1 and the slot box 6 can be ensured by compression of the rubber protrusion 9.
[0070] Terminal 1 includes a power parameter setting module, a display module, a parameter collection module, an on-site alarm module, and a wireless signal transmission module. The power parameter setting module is responsible for manually setting the safety limits of current, voltage, etc. The display module is located on the front of terminal 1 to display the real-time monitored power parameters such as current and voltage. The on-site alarm module will sound and light alarms when the power parameters exceed the safety limits, reminding the operators to deal with safety hazards. The wireless signal transmission module transmits the monitored power parameters to cloud platform 2 in real time through wireless signals such as 4G / 5G, providing a data source for data analysis and processing on cloud platform 2.
[0071] The parameter acquisition module includes a current monitoring module, a voltage monitoring module, a temperature monitoring module, and a leakage current monitoring module; the parameter acquisition module is located on the back of the terminal 1, and a plug-in port is reserved. By plugging the power parameter monitoring device into the port, the relevant power parameter monitoring can be quickly accessed. The parameter acquisition module uses a millisecond-level data acquisition terminal based on the inertia and power frequency of the power system. The data acquisition granularity can reach thousands of times per second to capture small changes; data denoising and filtering technology is used to extract electrical safety-related indicators, event alarm-related records, and the trigger point and end point waveforms of the recording data, including period, peak value, valley value, phase angle, and frequency; data packaging and time-sharing upload are used to avoid large-scale data loss, and support communication interruption and continuation, including S-level + min-level data event data packaging technology, adaptive waveform data interception technology, and data fitting, wavelet analysis and other data compression technologies.
[0072] Among them, the adaptive waveform data interception technology is: setting the extracted feature vector to represent the characteristics of the waveform data, based on the feature vector, using statistical methods, machine learning methods or expert experience to determine the threshold to set an adaptive threshold, real-time monitoring of the waveform data, dynamically adjusting the threshold, and when the feature vector exceeds the threshold, intercepting the corresponding waveform data.
[0073] There are different data fitting methods for different power parameters, as shown in Table 1 below:
[0074] Table 1 Data fitting methods corresponding to different power parameters
[0075]
[0076]
[0077] The wavelet analysis technique is as follows: set a continuous electrical signal x(t) and use wavelet transform to express it as wavelet coefficient c j,k and basic wavelet functions Function:
[0078]
[0079] Among them, j represents the scale parameter, k represents the displacement parameter, and t represents time.
[0080] After wavelet transform, c j,k Perform soft threshold processing, set the wavelet coefficients less than the threshold λ to zero, and retain the wavelet coefficients greater than or equal to the threshold λ, expressed as:
[0081]
[0082] Among them, (·)+ represents a positive function, Represents wavelet coefficients greater than or equal to the threshold λ.
[0083] After wavelet coefficient selection, the compressed signal is reconstructed using inverse wavelet transform. The inverse wavelet transform will retain the wavelet coefficients. and basic wavelet functions Perform linear combination to obtain the reconstructed compressed signal x rec (t):
[0084]
[0085] Based on the above process, the electrical signal data compression of the temporary power transmission line is realized, and the degree of compression is controlled by adjusting the threshold λ to meet different compression requirements.
[0086] Cloud Platform 2 is a temporary power management platform built on a cloud server, with functions such as safety monitoring, power consumption monitoring, power quality monitoring, indicator statistics, indicator statistics, and safety alarm:
[0087] 1) Safety monitoring: real-time monitoring of line overload temperature rise and leakage current indicators.
[0088] 2) Power consumption monitoring: Real-time monitoring of current, voltage, active power, reactive power, power factor, frequency, main transformer load rate, etc. to prevent the main transformer from overloading.
[0089] 3) Power quality monitoring: Real-time monitoring of power quality, including voltage / frequency deviation, three-phase imbalance, harmonics, etc., can effectively prevent the operation of large electromechanical equipment and main transformers on construction sites with defects, and reduce power dispatching electricity expenses.
[0090] 4) Indicator statistics: statistics on the types and quantities of potential safety hazards, calculation of electricity consumption and electricity charges, and statistics on electricity consumption at construction sites in multiple dimensions, such as peak, flat, valley, day, month, year, etc., support export of historical data, etc., to assist users in intelligent electricity management.
[0091] 5) Safety alarm: Display the time, location, duration of abnormality, abnormal problems, safety warning level and possible causes of safety hazards; establish a three-level warning mechanism of pre-warning, in-process warning and post-event tracing, establish parameter limits corresponding to different warning levels, and alarm for data exceeding the threshold.
[0092] 6) The platform provides functions such as alarm records, historical trends, and report analysis. It regularly compiles statistics on electricity consumption data for the current period every week, generates test reports, and selects to view the historical curve of a certain parameter of a single circuit (such as line temperature, leakage current, etc.), compares and analyzes the operating status of several important loads, views the overall electricity load of the day, month, and year, analyzes the peaks and valleys of daily electricity consumption and daily power, and provides alarm cause analysis for abnormal alarm circuits.
[0093] like Figure 7 As shown, the cloud platform 2 includes a data receiving module, a data storage module, a data analysis module, a temporary power system database, an alarm module, and a display module.
[0094] Among them, the temporary power system database includes a list of temporary power equipment, as shown in Table 2 below; the area where the temporary power equipment is located is mainly divided into the construction area and the office and living area. The temporary power equipment in the construction area is divided into fixed equipment and mobile equipment. The fixed equipment is not moved for a long time, and the mobile equipment often changes its working surface. In order to locate the fault location in time and accurately, a GPS locator is installed on the mobile device, and the three-level distribution box and power equipment are encoded, including location information and attribute information, wherein the location information includes floor information and plane area information, and the attribute information includes product name, rated current, rated voltage, rated operating temperature, rated leakage protection current, production date, service life, cumulative use time, regular maintenance plan and other parameters, and the relevant parameters are written into the BIM model attribute information as the basic parameters for safety monitoring, and the BIM model is loaded into the data storage module of the cloud platform 2; as the construction continues, the working surface is constantly adjusted, and the components and locations of the temporary power system change accordingly. It is necessary to manually input and update the model data, and dynamically adjust the BIM model and its attribute parameters of the temporary power system in time to ensure that the temporary power system is consistent with the actual situation.
[0095] Table 2 List of temporary power equipment
[0096]
[0097] Among them, the data receiving module receives the power parameter data transmitted from terminal 1 in real time and transmits it to the data storage module for storage; the data analysis module, based on the temporary power system database, matches the power parameters monitored in real time with the parameter limits in the equipment attributes in the BIM model, and performs dynamic data comparison analysis, calculation and statistics based on the built-in algorithm. The alarm module is used to issue an alarm based on the analysis of the data analysis module to remind relevant personnel; the display module is used to display the power parameters such as terminal voltage, current, power consumption, and status parameters such as switch and fault in real time, and set the power parameter threshold, duration and warning level of the terminal.
[0098] The client 3 includes a PC and a mobile APP, which can access the cloud platform 2 to view relevant power consumption data or receive relevant information sent by the cloud platform 2, and timely grasp the safety and energy consumption of power equipment in the construction area.
[0099] The temporary power safety and energy consumption control method based on the temporary power safety and energy consumption control system of the present invention includes the following process:
[0100] The intelligent data acquisition terminal collects the power parameters related to the temporary power equipment and sends them to the cloud platform 2 through wireless communication. After receiving the power parameters, the data receiving module of the cloud platform 2 sends them to the data storage module and the data analysis module for storage and analysis. The data analysis module combines the data in the database of the temporary power system to perform calculation and analysis, monitor the overload temperature rise and leakage current of the line in real time, monitor the current, voltage, active power, reactive power, power factor, frequency and main transformer load rate of the temporary power equipment in real time to see if they are within the preset safety range, monitor the power quality in real time, calculate the power consumption and electricity fee in real time, count the power consumption, and send the relevant data to the display module for visual display so that the relevant personnel can view and understand the various conditions of the power equipment. At the same time, the data analysis module also establishes a three-level early warning mechanism to realize automatic early warning and alarm, and displays the alarm data on the display module to remind the relevant personnel to check and repair in time. At the same time, the alarm is sent to the remote client 3 through the wireless communication network to notify the relevant management personnel to deal with it in time.
[0101] The three-level early warning mechanism includes: advance warning, in-process warning, and post-event tracing.
[0102] Pre-warning provides two methods: day-ahead forecast and real-time forecast. Day-ahead forecast is based on 0:00 of the day, and forecasts data of 48 points every 30 minutes in the future, providing preliminary guidance for the management work of the day. Real-time forecast is a rolling forecast of 8 points of data every 30 minutes for the next 4 hours, providing dynamic guidance for the management work of the day. There are two forecasting methods, one is based on interval calculation, and the other is based on affine arithmetic.
[0103] Prediction method based on interval calculation (taking power load as an example):
[0104] S1: Data preparation: Collect historical temporary power load data, take the historical 7-day period as the analysis period, take 30 minutes as the unit, form a time series, and clean and process the data, such as removing outliers and filling missing values, to ensure data quality;
[0105] S2: Interval modeling: converting historical temporary power load data into interval representation;
[0106] S3: Interval calculation: Use interval calculation to process the historical temporary power load data interval and predict the power load interval in the next n hours:
[0107]
[0108]
[0109] Among them, G min is the minimum predicted load for the next n hours; G maxis the maximum predicted load in the next n hours; m represents the prediction time range, m = 30min, 60min, 90min..., 60n min; x min (τ) represents the minimum power load at time τ obtained based on historical data; x max (τ) represents the maximum power load at time τ obtained based on historical data; τ represents the time corresponding to the time step.
[0110] Based on the above formula, the load range for the next n hours can be obtained, which can only provide directional guidance for energy scheduling; in order to more accurately obtain the power load at time τ, the following formula is used for prediction:
[0111] G(τ)=k1x1(τ)+k2x2(τ)+…+k i x i (τ)
[0112] Among them, G(τ) represents the temporary power load at time τ; x1(τ), x2(τ)...x i (τ) represents the different load sizes at time τ obtained based on historical data, k1, k2, ... i All represent the ratio of different loads at time τ obtained based on historical data, k1+k2+…k i =1.
[0113] S4: Prediction: Based on the interval calculation results, the interval prediction and point-in-time prediction of future temporary power load are obtained;
[0114] S5: Model evaluation: Evaluate the prediction results, compare the differences between the predicted values and the actual observed values, and calculate the corresponding error indicators, such as interval length, interval overlap, variance, etc., and adjust and improve the models established in S2 to S4 based on the evaluation results to continuously improve the accuracy and reliability of the prediction.
[0115] Prediction method based on affine arithmetic (taking electricity load as an example):
[0116] S1: Data preparation: Collect historical temporary power load data in units of 30 minutes, and perform preprocessing such as removing outliers and filling missing values;
[0117] S2: Model establishment: Establish an affine model to fit the historical power load data. The affine model is expressed as:
[0118] Y(t)=aX(t)+b
[0119] Where Y(t) is the predicted power load at time t, X(t) is the historical power load, a is the scaling factor, and b is the offset;
[0120] S3: Parameter estimation: Estimate and optimize the model parameters a and b based on historical data through the least squares method, so that the model fits the historical data best;
[0121] S4: Prediction: Use the optimized model parameters to predict the future temporary power load and predict the power load in the next n hours:
[0122] Y'(t+m)=aX(t)+b
[0123] Among them, Y'(t+m) is the predicted power load at time t+m;
[0124] S5: Model evaluation: Evaluate the prediction results, compare the differences between the predicted values and the actual observed values, and calculate the corresponding error indicators, including the root mean square error (RMSE) or mean absolute error (MAE). Adjust and improve the model according to the evaluation results to improve the accuracy and reliability of the prediction.
[0125] Based on the above prediction model, it is possible to solve problems such as leakage warning under different conditions of electrical equipment, potential electrical fire warning, and risk warning of equipment running with defects.
[0126] In-process alarm refers to the establishment of an in-process alarm system with three dimensions: threshold, duration, and warning level. The warning levels include level 1, level 2, and level 3. The mutation includes indicators such as load rate, overvoltage, and overcurrent. The corresponding warning level is determined according to the duration, and an alarm form is formed, including the occurrence time, level, abnormal duration, monitoring point, phenomenon, and cause. The specific division of warning levels is shown in Table 3 below, and the alarm form is shown in Table 4 below:
[0127] Table 3 Warning level classification table
[0128] Parameter Type Threshold Duration grade Overcurrent 115% 60s Level 1 Overpressure 115% 60s Level 1 Voltage total harmonic distortion rate exceeds limit 5% _ Level 1 The single power factor exceeds the lower limit 0.5 60s Level 2 The current total harmonic limit value exceeds the limit 200A _ Level 3 Load rate exceeds limit 85% _ Level 1 Undervoltage 85% 60s Level 1 Three-phase voltage unbalance 2% 60s Level 2 The total power factor exceeds the lower limit 0.5 60s Level 2 Three-phase current unbalance 4.5% 60s Level 3
[0129] Table 4 Alarm form
[0130] Time of occurrence level Abnormal duration Monitoring Points Phenomenon reason — — — — — —
[0131] Post-fault tracing is based on actual data for fault diagnosis. The algorithm analyzes the characteristic values. Different characteristic values correspond to different fault types. The fault type is quickly located according to the characteristic values, and targeted countermeasures are given, including single-phase grounding, two-phase grounding, two-phase short circuit, three-phase short circuit, single-phase disconnection, two-phase disconnection, and three-phase disconnection. The specific fault diagnosis methods are as follows:
[0132] S1: Data collection and preprocessing: collect the actual data of voltage, current, power and other parameters from the temporary power system in real time, remove noise and abnormal values, and perform smoothing and time synchronization on the data;
[0133] S2: Feature extraction: Extract fault-related features, including voltage and current waveform features, such as peak value, mean value, waveform distortion, etc.
[0134] S3: Fault diagnosis model construction: Based on the extracted features, a fault diagnosis model is established using methods such as K nearest neighbor algorithm, support vector machine, and cluster analysis;
[0135] S4: Model training and evaluation: Train the fault diagnosis model based on historical data, and evaluate the model's accuracy, recall rate, precision and other indicators through cross-validation technology to ensure its effectiveness in the actual environment;
[0136] S5: Real-time fault diagnosis: Input the real-time collected data into the trained fault diagnosis model to perform real-time fault diagnosis. The model output results indicate the possible fault type, location, and probability.
[0137] S6: Fault location and repair: According to the diagnosis results, determine the specific location and cause of the fault, and take corresponding maintenance measures according to the fault diagnosis results, such as replacing damaged equipment, adjusting circuit connections, cleaning electrical contact points, etc.;
[0138] S7: Continuous monitoring and improvement: Continuously monitor the operating status of the temporary power system, collect real-time data, improve and optimize the fault diagnosis algorithm according to actual conditions, and regularly update the model to adapt to changes in the temporary power system.
[0139] The fault types, corresponding characteristic values and judgment methods are shown in Table 5 below:
[0140] Table 5 Fault types, corresponding characteristic values and judgment methods
[0141]
[0142] The embodiments are preferred implementations of the present invention, but the present invention is not limited to the above-mentioned implementations. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essential content of the present invention belong to the protection scope of the present invention.
Claims
1. A temporary power safety and energy consumption control system, characterized in that: The system comprises a terminal (1) installed at a distribution box or an incoming line end of an electric power consumption device. The terminal (1) is used to collect power parameters related to the terminal equipment of a temporary power consumption system and transmit the parameters to a cloud platform (2) via wireless signals. The cloud platform (2) is used to perform data analysis and processing and output operation information of the temporary power consumption system. The cloud platform (2) is also connected to a client (3). The client (3) is used to access the cloud platform (2) or receive relevant information. When the terminal (1) is installed on the distribution box housing (4), a slot is provided on the distribution box housing (4) according to the size of the terminal (1), and the terminal (1) passes through the slot and is fixed by a clamp (5); the clamp (5) comprises an L-shaped plug-in (501), a locking piece (502) is provided at the rear end of the L-shaped plug-in (501), the L-shaped plug-in (501) is inserted into the side slot of the terminal (1), and is nested and tightened with the slot by pressing down the locking piece (502); When the terminal (1) is installed on the electrical equipment by using a slot box (6), a plurality of spring plates (7) are symmetrically arranged on the inner side wall of the slot box (6), and each of the spring plates (7) is provided with a triangular protrusion (10). A slot matching the spring plates (7) is arranged on the outer side wall of the terminal (1), and each of the slots is provided with a triangular groove (8) matching the triangular protrusion (10). The terminal (1) is inserted into the slot box (6), and the triangular protrusion (10) is embedded in the triangular groove (8). The terminal (1) internally comprises an electric power parameter setting module, a display module, a parameter collection module, an on-site alarm module, and a wireless signal transmission module; the electric power parameter setting module is used to manually set safety limits including current and voltage; the display module is used to display the electric power parameters monitored in real time; the on-site alarm module is used to issue an audible and visual alarm in case the electric power parameters exceed the safety limits; the wireless signal transmission module transmits the monitored electric power parameters to the cloud platform (2) in real time via wireless signals; the parameter collection module is provided with a plug-in port for accessing electric power parameter data, the parameter collection module comprises a current monitoring module, a voltage monitoring module, a temperature monitoring module, and a leakage current monitoring module, the parameter collection module adopts data packaging and time-sharing uploading technology to avoid large-scale data loss, and supports communication interruption and continuation, including S-level + min-level data event data packaging technology, adaptive waveform data interception technology, data fitting technology, and wavelet analysis technology; wherein different electric power parameters correspond to different data fitting methods; The cloud platform (2) is a temporary power management platform built on a cloud server, comprising a data receiving module, a data storage module, a data analysis module, a temporary power system database, an alarm module, and a display module; the data receiving module receives the power parameter data transmitted from the terminal (1) in real time, and transmits it to the data storage module for storage; the data storage module stores the BIM model and the power parameter data; the temporary power system database comprises a list of temporary power equipment, the area where the temporary power equipment is located is divided into a construction area and an office and living area, the temporary power equipment in the construction area is divided into fixed equipment and mobile equipment, a GPS locator is installed on the mobile device, the three-level distribution box and the power equipment are all encoded, including location information and attribute information, the location information includes floor information and plane area information, the attribute information is written into the BIM model attribute information of the data storage module as the basic parameters for safety monitoring, including the temporary power equipment production Product name, rated current, rated voltage, rated operating temperature, rated leakage protection current, production date, service life, cumulative usage time, regular maintenance plan. As the construction continues, the work surface is constantly adjusted, and the components and positions of the temporary power system change accordingly. The model data is updated by manual input, and the BIM model of the temporary power system and its attribute parameters are dynamically adjusted to ensure that the temporary power system is consistent with the actual situation. The data analysis module is based on the temporary power system database, and the power parameters monitored in real time are matched with the parameter limits in the attribute information in the BIM model. Based on the built-in algorithm, dynamic data comparison analysis, calculation and statistics are performed; the alarm module issues an alarm based on the analysis of the data analysis module to remind relevant personnel; the display module is used to display the power parameters and status parameters in real time, and is used to set the power parameter threshold, duration and warning level of the terminal (1); The cloud platform (2) has the functions of safety monitoring, power consumption monitoring, power quality monitoring, index statistics, safety alarm and alarm record, historical trend, and report analysis; safety monitoring includes real-time monitoring of line overload temperature rise and leakage current index; power consumption monitoring includes real-time monitoring of current, voltage, active power, reactive power, power factor, frequency, and main transformer load rate to prevent the main transformer from overloading; power quality monitoring includes real-time monitoring of power quality, including voltage / frequency deviation, three-phase imbalance, and harmonics to prevent equipment from running with defects and reduce power adjustment electricity fee expenditure; index statistics include statistics on the types and quantities of safety hazards, calculation of electricity consumption and electricity fees, and multi-dimensional statistics on the power consumption of the construction site, while supporting the export of historical data , assisting users in the intelligent management of electric energy; safety alarms include the display of the time, location, duration of abnormalities, abnormal problems, safety warning levels, and possible causes of potential safety hazards, and the establishment of a three-level warning mechanism of pre-warning, in-process warning, and post-event tracing, and the establishment of parameter limits corresponding to different warning levels, and alarms for data exceeding the threshold; alarm records, historical trends, and report analysis include regular weekly statistics of current electricity consumption data, generation of detection reports, and selection of historical curves of a parameter of a single circuit, comparative analysis of the operating status of several important loads, viewing the overall electricity load of the day, month, and year, peak and valley analysis of daily electricity consumption and daily power, and providing alarm cause analysis for abnormal alarm circuits.
2. A temporary power safety and energy consumption control method using the temporary power safety and energy consumption control system of claim 1, characterized in that: The process includes the following: The terminal (1) uses a data acquisition module to collect power parameters related to temporary power equipment and sends them to the cloud platform (2) via wireless communication. After receiving the power parameters, the data receiving module of the cloud platform (2) sends them to the data storage module and the data analysis module for storage and analysis. The data analysis module combines the data in the database of the temporary power system to perform calculation and analysis, monitor the overload temperature rise and leakage current of the line in real time, monitor the current, voltage, active power, reactive power, power factor, frequency, and main transformer load rate of the temporary power equipment in real time to see if they are within a preset safety range, monitor the power quality in real time, calculate the power consumption and electricity fee in real time, and count the power consumption. The relevant data is sent to the display module for visual display so that relevant personnel can view and understand the temporary power equipment. At the same time, the data analysis module establishes a three-level early warning mechanism to realize automatic early warning and alarm, and displays the alarm data on the display module to remind relevant personnel to check and repair in time. At the same time, the alarm is sent to the remote client (3) through the wireless communication network to notify relevant management personnel to handle it in time. The three-level early warning mechanism includes: early warning before the event, warning during the event, and post-event tracing; Pre-warning includes two methods: day-ahead forecast and real-time forecast. The day-ahead forecast is based on 0:00 of the day, and forecasts data of 48 points every 30 minutes in the future, providing preliminary guidance for the management work of the day. The real-time forecast is a rolling forecast of 8 points of data every 30 minutes for the next 4 hours, providing dynamic guidance for the management work of the day. There are two forecasting methods, namely the forecasting method based on interval operation and the forecasting method based on affine arithmetic. In-process alarm refers to the establishment of an in-process alarm system with three dimensions: threshold, duration, and warning level. The warning level is determined according to the duration of the sudden change. The sudden change includes load rate, overvoltage, and overcurrent indicators. After the warning, an alarm form is formed. The alarm form includes the warning occurrence time, level, abnormal duration, monitoring point, phenomenon, and cause. Post-fault tracing is based on actual monitoring data for fault diagnosis. The characteristic values are analyzed based on algorithms. Different characteristic values correspond to different fault types. The fault type is located based on the characteristic values, and countermeasures are given. The prediction method based on interval operation is as follows: S1: Data preparation: Collect historical temporary power load data, take the historical 7 days as the analysis period, take 30 minutes as the unit, form a time series, and pre-process the data; S2: Interval modeling: converting historical temporary power load data into interval representation; S3: Interval calculation: Use interval calculation to process the historical data interval and predict the power load in the next n hours; In order to accurately obtain the power load at time τ, the following formula is used for prediction: G(τ)=k1x1(τ)+k2x2(τ)+…+k i x i (t) Among them, G(τ) represents the temporary power load at time τ; x1(τ), x2(τ)...x i (τ) represents the different load sizes at time τ obtained based on historical data, k1, k2, ... i All represent the ratio of different loads at time τ obtained based on historical data, k1+k2+…k i =1; S4: Prediction: Based on the interval calculation results, the interval prediction of future temporary power load is obtained; S5: Model evaluation: Evaluate the prediction results, compare the difference between the predicted interval and the actual observed value, calculate the corresponding error index, and adjust and improve the model according to the evaluation results.
3. The temporary power safety and energy consumption control method according to claim 2 is characterized in that: The prediction method based on affine arithmetic is as follows: S1: Data preparation: collect historical temporary power load data and perform preprocessing; S2: Model establishment: Establish an affine model to fit the historical power load data. The affine model is expressed as: Y(t)=aX(t)+b Where Y(t) is the predicted power load at time t, X(t) is the historical power load, a is the scaling factor, and b is the offset; S3: Parameter estimation: Estimate and optimize the model parameters a and b based on historical data through the least squares method to make the model fit the historical data best; S4: Prediction: Use the optimized model parameters to predict the future temporary power load and predict the power load in the next n hours; S5: Model evaluation: Evaluate the prediction results, compare the differences between the predicted values and the actual observed values, calculate the corresponding error indicators, and adjust and improve the model based on the evaluation results.
4. The temporary power safety and energy consumption control method according to claim 2 is characterized in that: The specific method of fault diagnosis is as follows: S1: Data collection and preprocessing: collect the actual data including voltage, current and power from the temporary power system in real time, remove noise and abnormal values, and perform smoothing and time synchronization on the data; S2: Feature extraction: Extracting fault-related features, including voltage and current waveform features; S3: Fault diagnosis model construction: Based on the extracted features, a fault diagnosis model is established; S4: Model training and evaluation: Train the fault diagnosis model based on historical data, and evaluate the accuracy, recall rate, and precision indicators of the model through cross-validation technology to ensure its effectiveness in the actual environment; S5: Real-time fault diagnosis: Input the real-time collected data into the trained fault diagnosis model to perform real-time fault diagnosis. The model output results indicate the possible fault type, location, and probability. S6: Fault location and repair: Based on the diagnosis results, determine the specific location and cause of the fault, and take appropriate maintenance measures based on the fault diagnosis results, including replacing damaged equipment, adjusting circuit connections, and cleaning electrical contact points; S7: Continuous monitoring and improvement: Continuously monitor the operating status of the temporary power system, collect real-time data, improve and optimize the fault diagnosis algorithm based on actual conditions, and update the model regularly.
5. The temporary power safety and energy consumption control method according to claim 2 is characterized in that: The wavelet analysis technology used in the power parameter data acquisition process of the parameter acquisition module in the terminal (1) is as follows: a continuous electric signal x(t) is set and represented as a wavelet coefficient c by wavelet transformation. j,k and basic wavelet functions Function: Among them, j represents the scale parameter, k represents the displacement parameter; t represents time; After wavelet transform, c j,k Perform soft threshold processing, set the wavelet coefficients less than the threshold λ to zero, and retain the wavelet coefficients greater than or equal to the threshold λ, expressed as: Among them, (·)+ represents a positive function, Represents wavelet coefficients greater than or equal to the threshold λ; After wavelet coefficient selection, the compressed signal is reconstructed using inverse wavelet transform. The inverse wavelet transform will retain the wavelet coefficients. and basic wavelet functions Perform linear combination to obtain the reconstructed compressed signal x rec (t): Based on the above process, the electrical signal data compression of the temporary power transmission line is realized, and the degree of compression is controlled by adjusting the threshold λ to meet different compression requirements.
Citation Information
Patent Citations
Spectral analysis type high-precision on-line detector for gas and liquid detection
CN104062264A
Power safety hidden danger supervision and management system based on safety cloud platform and working method thereof
CN110323836A
Fault diagnosis method
CN117150414A