A construction method for roadbed overload static pressure earthwork deployment
By using the same overloaded static pressure filler as the branch line base filler, and adopting measures such as nearby transportation and drainage ditches, the problem of repeated transportation and outsourcing during overloaded static pressure earthwork construction was solved, the construction speed and efficiency were improved, and the cost and construction period were reduced.
Patent Information
- Application Number
- CN202410495649.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-04-24
AI Technical Summary
In traffic engineering, the repeated transportation of overloaded statically-pressed earthwork and the waste of purchased earthwork have led to certain drawbacks in the construction process, affecting the construction speed and construction period.
By using the overloaded static pressure filler as the filler for the branch line base and using the branch line base filler as the main line base storage material, outsourcing and repeated transportation are reduced. A nearby transportation plan is adopted, combined with drainage ditch and protective layer measures, to ensure construction quality and efficiency. .
It realizes the transportation of materials nearby, reduces transportation costs and purchase costs, increases construction speed, saves construction period, and avoids the long-distance repeated transportation of traditional overloaded static pressure fillers.
Smart Images

Figure CN118223352B_ABST
Abstract
Description
Technical Field
[0001] The invention specifically relates to a roadbed overload static pressure earthwork allocation construction method, belonging to the technical field of traffic engineering. Background Art
[0002] Transportation engineering is the tertiary industry of my country's national economy. With the development of the national economy, my country's high-speed railways, highways, etc. have developed rapidly. As of 2020, my country's high-speed rail operating mileage is in the leading position in the world, about 38,000 kilometers, and the long-term high-speed rail network will exceed 200,000 kilometers by 2030; the total mileage of national highways is 5.1981 million kilometers, of which the mileage of highways is 161,000 kilometers.
[0003] During the construction of transportation projects, the roadbeds of high-speed railways and highways usually need to be reinforced and treated before they can reach the design bearing capacity and meet the settlement requirements. The usual practice in engineering is to replace soft soil or reinforce the foundation. The main line generally needs to be combined with overload static pressure to drain and consolidate the soil to reduce the later roadbed settlement. The branch line generally only needs foundation reinforcement. During the overload static pressure construction, the earthwork used for static pressure needs to be allocated and piled on the roadbed. The pile height is generally about 3m, and the static pressure time is not less than six months. After the overload static pressure reaches the design requirements, the piled earthwork is transported away and discarded; during the loading and unloading process of the overload static pressure earthwork, repeated transportation is required. When the on-site earthwork is insufficient, additional earthwork needs to be purchased, resulting in repeated transportation of overload static pressure piled soil and waste of purchased earthwork. There are certain disadvantages in the construction process.
[0004] In view of this, the present invention is proposed. Summary of the invention
[0005] The purpose of the present invention is to provide a roadbed overload static pressure earthwork allocation construction method in order to solve the above-mentioned problems, which has the advantages of enabling materials to be transported nearby, greatly reducing the transportation costs of external transportation; avoiding the purchase costs of external earth-piling materials; and at the same time avoiding the long-distance repeated transportation of traditional overload static pressure filling materials, greatly improving the construction speed and saving construction time.
[0006] The present invention achieves the above-mentioned purpose through the following technical scheme, a roadbed overload static pressure earthwork deployment construction method, comprising the following steps:
[0007] Step 1: leveling the construction site and reinforcing the soil under the main line foundation and the first part of the branch line foundation;
[0008] Step 2: constructing the main linebed and the first part of the branch linebed;
[0009] Step 3: constructing the overload static pressure filler above the main line bed, and the overload static pressure filler is the same as the filler of the first part of the branch line bed;
[0010] Step 4: After the overload static pressure in step 3 is completed, the overload static pressure filler is transferred to the top of the first part of the branch line as the second part of the branch line.
[0011] Furthermore, in order to prevent the first part of the branch linebed from being eroded by water through the first drainage ditch, after the construction of the first part of the branch linebed is completed, the first drainage ditch is opened on the site on one side of the first part of the branch linebed.
[0012] Furthermore, in order to prevent the main linebed from being eroded by water through the second drainage ditch, the second drainage ditch is opened at one end of the top of the main linebed after the construction of the main linebed is completed.
[0013] Furthermore, in order to protect the overloaded static pressure filler through the protective layer and the slope protection, after the overloaded static pressure filler on the main line bed is constructed, the protective layer and the slope protection are added on the overloaded static pressure filler.
[0014] Furthermore, in order to allow water to flow into the second drainage ditch through the slope protection, the second drainage ditch is located at one side of the bottom end of the slope protection.
[0015] Furthermore, in order to meet the design requirements of overload static pressure, the overload static pressure filler is left to stand for no less than six months after reaching the overload static pressure height on the main line bed.
[0016] Furthermore, in order to avoid the disadvantage of the traditional overload static pressure filler being repeatedly transported over long distances, after the overload static pressure design requirements are met, the overload static pressure filler on the upper part of the main line bed will be inspected and accepted. After acceptance, the overload static pressure filler will be backfilled onto the first part of the branch line bed to complete the construction of all branch line beds.
[0017] Furthermore, in order to meet the normal operation of the railway, after the main line bed, the first part of the branch line bed and the second part of the branch line bed are all constructed, the main line track and the branch line track are constructed on the main line bed and the second part of the branch line bed respectively.
[0018] The technical effects and advantages of the present invention are as follows: by using the overload static pressure construction scheme to utilize the branch line bed filler as the main line bed loading material, the material can be transported nearby, greatly reducing the transportation cost of external transportation; avoiding the purchase cost of external earth-piling materials; and at the same time avoiding the traditional long-distance repeated transportation of the overload static pressure filler, greatly improving the construction speed and saving construction time. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1It is a construction process flow chart of the present invention;
[0020] Figure 2 It is a cross-sectional schematic diagram of the overload static pressure construction of the present invention;
[0021] Figure 3 It is a schematic diagram of the structure of the protective layer and slope protection of the present invention;
[0022] Figure 4 This is a schematic diagram of the structure of the branch line subgrade, main line track and branch line track after the construction of the second part of the present invention is completed;
[0023] In the figure: 1. Construction site; 2. Main line bed; 3. First part of branch line bed; 4. Overload static pressure filler; 5. Second part of branch line bed; 6. First drainage ditch; 7. Second drainage ditch; 8. Protective layer; 9. Slope protection; 10. Main line track; 11. Branch line track. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] See also Figure 1-4 As shown, a method for distributing earthwork for roadbed overload static pressure is as follows: leveling the construction site 1 to be constructed, reinforcing the soil below the main linebed 2 and the first part of the branch linebed 3; constructing the main linebed 2 and the first part of the branch linebed 3; constructing the overload static pressure filling material 4 above the main linebed 2, and the overload static pressure filling material 4 is the same as the filling material of the first part of the branch linebed 3; after the overload static pressure in step three is completed, the overload static pressure filling material 4 is transported to the top of the first part of the branch linebed 3 as the second part of the branch linebed 5, and the filling materials of the first part of the branch linebed 3 and the second part of the branch linebed 5 on site are used as the stacking material on the main linebed 2, thereby avoiding the need to purchase the overload static pressure stacking filling material of the traditional main linebed 2 from outside, and the waste of transporting the abandoned soil after unloading; greatly saving the construction material cost and transportation cost.
[0026] As a technical optimization solution of the present invention, after the construction of the first branch linebed 3 is completed, a first drainage ditch 6 is opened on the site on one side of the first branch linebed 3 to facilitate draining the water flow on the first branch linebed 3 to the first drainage ditch 6.
[0027] As a technical optimization solution of the present invention, after the construction of the main linebed 2 is completed, a second drainage ditch 7 is opened at one end of the top of the main linebed 2 to drain the water on the main linebed 2 to the second drainage ditch 7.
[0028] As a technical optimization scheme of the present invention, after the construction of the overload static pressure filler 4 on the main line bed 2 is completed, a protective layer 8 and a slope protection 9 are added to the overload static pressure filler 4. During the construction, covering protection measures such as the protective layer 8 and the slope protection 9 are taken, so that the performance of the overload static pressure filler 4 is not lost during the loading period. When the materials of the first part of the branch line bed 3 and the second part of the branch line bed 5 are transported, material waste is avoided and materials are saved.
[0029] As a technical optimization solution of the present invention, the second drainage ditch 7 is located at one side of the bottom end of the slope protection 9 to facilitate water flow through the slope protection 9 into the second drainage ditch 7.
[0030] As a technical optimization solution of the present invention, after the overload static pressure filler 4 reaches the overload static pressure height on the main line subgrade 2, the static time is not less than six months, which meets the design requirements of the overload static pressure and improves the overall quality of the subgrade construction.
[0031] As a technical optimization scheme of the present invention, after the overload static pressure design requirements are met, the overload static pressure filler 4 on the main line bed 2 is inspected and accepted. After the acceptance is passed, the overload static pressure filler 4 is backfilled onto the first part of the branch line bed 3 to complete the construction of all branch line beds, avoiding the traditional overload static pressure filler 4 The repeated long-distance transportation is avoided, greatly improving the construction speed and saving construction time.
[0032] As a technical optimization solution of the present invention, after the main linebed 2, the first part of the branch linebed 3 and the second part of the branch linebed 5 are all constructed, the main line track 10 and the branch line track 11 are constructed on the main linebed 2 and the second part of the branch linebed 5 respectively, and the overall railway construction is completed to facilitate subsequent opening to traffic.
[0033] When the present invention is in use, firstly, the construction site 1 is leveled, the soil below the main linebed 2 and the first part of the branch linebed 3 is reinforced, and the main linebed 2 and the first part of the branch linebed 3 are constructed; then, the overload static pressure filler 4 above the main linebed 2 is constructed, and the protective layer 8 of the overload static pressure filler 4, the second drainage ditch 7 and the slope protection 9 are constructed. After the overload static pressure is completed, the overload static pressure filler 4 is transferred to the top of the first part of the branch linebed 3 as the second part of the branch linebed 5; finally, after the construction of the main linebed 2, the first part of the branch linebed 3 and the second part of the branch linebed 5 is completed, the main line track 10 and the branch line track 11 are constructed to complete the overall construction.
[0034] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0035] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A roadbed overload static pressure earthwork deployment construction method, characterized in that , including the following steps: Step 1: leveling the construction site (1) and reinforcing the soil beneath the main line foundation (2) and the first part of the branch line foundation (3); Step 2: constructing the main line bed (2) and the first part of the branch line bed (3); Step 3: constructing an overload static pressure filler (4) above the main line bed (2), wherein the overload static pressure filler (4) is the same as the filler of the first part of the branch line bed (3); Step 4: After the overload static pressure in step 3 is completed, the overload static pressure filler (4) is transferred as the second part of the branch line bed (5) to the top of the first part of the branch line bed (3); After the construction of the first branch line embankment (3) is completed, a first drainage ditch (6) is opened on a site on one side of the first branch line embankment (3); After the construction of the main line bed (2) is completed, a second drainage ditch (7) is opened at one end of the top of the main line bed (2); After the construction of the overload static pressure filler (4) on the main line bed (2) is completed, a protective layer (8) and a slope protection (9) are added on the overload static pressure filler (4); The second drainage ditch (7) is located at one side of the bottom end of the slope protection (9); After the overload static pressure filler (4) reaches the overload static pressure height on the main line bed (2), the static time is not less than six months; After the overload static pressure design requirements are met, the overload static pressure filler (4) on the upper part of the main line bed (2) is inspected and accepted. After passing the acceptance, the overload static pressure filler (4) is backfilled onto the first part of the branch line bed (3), completing the construction of the entire branch line bed.
2. A roadbed overload static pressure earthwork deployment construction method as claimed in claim 1, characterized in that: After the main line bed (2), the first part of the branch line bed (3) and the second part of the branch line bed (5) are all constructed, a main line track (10) and a branch line track (11) are constructed on the main line bed (2) and the second part of the branch line bed (5), respectively.
Citation Information
Patent Citations
Construction structure and method of plastic drainage board and CFG pile soft foundation treatment transition section
CN110185022A
Soft mud layer geological area roadbed treatment structure and construction method thereof
CN115538236A
Seawall soft soil roadbed reinforcement treatment method
CN115627669A