A fire smoke treatment system that meets the smoke exhaust zoning requirements of ultra-long highway tunnels
By setting up a fire smoke treatment system in an ultra-long highway tunnel, including air induction, cooling, dust removal and neutralization adsorption devices to treat pollutants in the smoke, the problem of fire smoke emission in ultra-long tunnels is solved and the difficulty of construction is reduced. and environmental impact, achieving effective treatment of flue gas pollutants.
Patent Information
- Application Number
- CN202410240029.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-03-04
AI Technical Summary
Fire smoke emissions from ultra-long highway tunnels are difficult to meet regulatory requirements. Existing inclined shafts, vertical shafts, and horizontal guide devices are limited by terrain, geology, and ecological conditions, making construction difficult and the concentration of smoke pollutants exceeding standards, affecting the environment.
Design a fire smoke treatment system, including air induction, cooling, dust removal and neutralization adsorption devices arranged longitudinally in the tunnel. Smoke is introduced through the air induction device, the cooling device reduces the temperature, the dust removal device filters particulate matter, and the neutralization adsorption reaction device It processes carbon dioxide, nitrogen oxides, and sulfur oxides, and the exhaust device adjusts the air volume to send the treated flue gas back into the tunnel.
It achieves gas cooling, dust removal and pollutant neutralization and adsorption of fire smoke, reduces the concentration of toxic and harmful substances, replaces traditional smoke exhaust devices, reduces engineering construction difficulty and environmental impact, and meets the smoke exhaust needs of ultra-long tunnels.
Smart Images

Figure CN118257623B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel fire smoke treatment, and in particular to a fire smoke treatment system that meets the smoke exhaust zoning requirements of an ultra-long highway tunnel. Background Art
[0002] At present, the construction of highway tunnels shows a trend of continuously developing towards mountainous areas with higher altitudes and deeper burial depths. The length of tunnels is gradually increasing, and extra-long tunnels and even tunnels over 5 km are constantly emerging. Along with this comes the problem of disaster prevention in super-long tunnels.
[0003] When a fire occurs in a tunnel, the main purpose of the tunnel fire system is to control the flow of fire smoke and effectively discharge it out of the tunnel. According to regulations: the maximum travel of fire smoke in a single-hole two-way traffic tunnel should not be greater than 3km; the maximum travel of fire smoke in a one-way traffic tunnel should not be greater than 5km. Therefore, for super-long tunnels, relying solely on the entrances and exits of the tunnel cannot meet the smoke exhaust travel requirements. It is necessary to set up a number of horizontal guides, inclined shafts, vertical shafts and other devices to meet the smoke exhaust requirements of each section of the super-long tunnel.
[0004] However, due to the limitations of geological, topographical and surface ecological conditions, the selection of inclined shafts, vertical shafts and horizontal guideways is relatively limited, and they often have to cross some unfavorable geological conditions, which not only increases the scale of engineering construction, but also increases the difficulty of engineering construction. In addition, inclined shafts, vertical shafts and horizontal guideways can only achieve direct exhaust function, and the concentration of pollutants in the flue gas is far higher than the limit value in relevant regulations. Direct exhaust of flue gas has a relatively large impact on the environment. Summary of the invention
[0005] In order to solve the above problems, the present invention provides a fire smoke treatment system that meets the smoke exhaust zoning requirements of ultra-long highway tunnels.
[0006] The technical solution adopted by the present invention is:
[0007] A fire smoke treatment system that meets the smoke exhaust zoning of an ultra-long highway tunnel. When the tunnel is a single-hole two-way traffic tunnel, several fire smoke treatment systems are arranged vertically and alternately from left to right; when the tunnel is a separated double-span tunnel, several fire smoke treatment systems are arranged in the middle of the two tunnels and shared by the two tunnels; the number of fire smoke treatment systems to be set is calculated using Formula 1:
[0008]
[0009] Where: L is the tunnel length, d is the longitudinal spacing of the gas treatment system in the tunnel, and n is the number of gas treatment systems in the tunnel;
[0010] Each fire smoke treatment system includes an air entrainment device, a cooling device, a dust removal device, a neutralization adsorption reaction device and an exhaust device which are installed in the same pipeline and arranged in sequence; the smoke generated by the fire is introduced from the main tunnel hole into the pipeline of the fire smoke treatment system through the air entrainment device; the smoke is cooled when passing through the cooling device, the particulate matter in the smoke is filtered when passing through the dust removal device, and the carbon dioxide, nitrogen oxides and sulfur dioxide in the smoke are filtered when passing through the neutralization adsorption reaction device; the concentration of toxic and harmful substances in the smoke after passing through the cooling device, the dust removal device and the neutralization adsorption reaction device has been reduced to below the standard value, and is sent back to the tunnel through the exhaust device.
[0011] Furthermore, the air bleed device is composed of an air bleed axial flow fan and an air bleed duct, one end of the air bleed duct extends into the tunnel, and the other end is equipped with an air bleed axial flow fan, and the air volume of the air bleed axial flow fan can be adjusted;
[0012] The air volume adjustment range of the air bleed device and the cross-sectional specifications of the pipeline are calculated using Formula 2 and Formula 3:
[0013] Q 引 ≥A t ·v ft (2)
[0014] A y =A t ·v ft / v y (3)
[0015] Where: Q 引 The air volume introduced by the air bleed device, A y A is the cross-sectional area of the air duct of the air bleed device, t is the clear cross-sectional area of the tunnel, v ft is the design ventilation speed in the tunnel under fire conditions; v y It is the design wind speed at the tunnel air duct outlet under fire conditions.
[0016] Furthermore, the cooling device consists of an air duct and a spray device; the spray device is installed at the top of the air duct, and the spray device sprays fine water mist to reduce the temperature of the flue gas; a spray water collection and recovery pool is provided at the bottom of the air duct.
[0017] Furthermore, alkaline substances are added to the spray device, and the alkaline substances preliminarily neutralize the nitrogen oxides and sulfur dioxide flue gas components in the air that are acidic and soluble in water.
[0018] Furthermore, the dust removal device is composed of an air intake pipe, a dust removal device and an exhaust pipe; one end of the air intake pipe is connected to the cooling device, and the other end is connected to the dust removal device; one end of the exhaust pipe is connected to the dust removal device, and the other end is connected to the neutralization adsorption reaction device; the dust removal device adopts a bag dust collector or an electrostatic dust collector, and the coarser particles in the flue gas fall to the ash hopper at the bottom of the dust removal device under the action of their own weight, and the finer particles are adsorbed on the surface of the dust removal device, and the dust removal device filters the particulate matter in the flue gas.
[0019] Furthermore, the neutralization adsorption reaction device is composed of an oxygen supply pipeline, a neutralization reaction tank and an adsorption reaction pipeline; the oxygen supply pipeline is installed in the exhaust pipe of the dust removal device; the neutralization reaction tank includes a first neutralization reaction tank and a second neutralization reaction tank, the lower part of one side of the first neutralization reaction tank is connected to the exhaust pipe of the dust removal device, and the upper part of the other side is connected to the lower part of one side of the second neutralization reaction tank through a pipeline, and the other side of the second neutralization reaction tank is connected to one end of the adsorption reaction pipeline.
[0020] Furthermore, the oxygen supply pipeline provides oxygen to oxidize the nitric oxide in the flue gas; the oxygen supply amount of the oxygen supply pipeline is calculated according to Formula 4:
[0021]
[0022] Where: Indicates the volume of oxygen that needs to be introduced into the oxygen supply pipeline, η NO Indicates the mass concentration of nitric oxide in the fire smoke that needs to be treated. represents the density of oxygen, Q 烟 is the smoke generation rate corresponding to the maximum heat release rate of the fire, and t is the duration of the tunnel fire.
[0023] Furthermore, a sodium hydroxide aqueous solution is placed in the first neutralization reaction tank, and after the flue gas enters the first neutralization reaction tank, the sodium hydroxide reacts with the carbon dioxide, nitrogen oxides, and sulfur dioxide in the flue gas to generate sodium sulfate, sodium bisulfate, sodium carbonate, and sodium nitrite that are soluble in water;
[0024] A calcium hydroxide aqueous solution is placed in the second neutralization reaction tank, and the calcium hydroxide reacts with the carbon dioxide in the flue gas to generate a water-insoluble calcium carbonate precipitate and water;
[0025] A carbon monoxide adsorbent is arranged in the adsorption reaction pipeline. After the gas is treated by the first neutralization reaction tank and the second neutralization reaction tank, the acidic gas that can be dissolved in water or react with the alkaline solution is eliminated, and the carbon monoxide is introduced into the adsorption reaction pipeline along with the remaining gas. The gas passes slowly at a uniform speed, and the carbon monoxide gas is adsorbed and eliminated.
[0026] Further, the content of sodium hydroxide in the sodium hydroxide aqueous solution and the content of calcium hydroxide in the calcium hydroxide aqueous solution in the first neutralization reaction tank and the second neutralization reaction tank are calculated by Formula 5 and Formula 6:
[0027]
[0028]
[0029] Where: m NaOH Indicates the content of sodium hydroxide in the first reaction tank, Indicates the content of calcium hydroxide in the second reaction tank, Respectively represent the mass concentrations of carbon dioxide, nitrogen dioxide and sulfur dioxide in the fire smoke to be treated;
[0030] The mass of the carbon monoxide adsorbent in the adsorption reaction pipe is calculated using Formula 7:
[0031]
[0032] Where: m y The mass of adsorbent required to adsorb carbon monoxide in flue gas, η CO Indicates the mass concentration of carbon monoxide in the fire smoke to be treated, ρ CO is the density of carbon monoxide gas, ξ CO is the adsorption capacity of carbon monoxide adsorbent.
[0033] Furthermore, the exhaust device consists of an exhaust axial flow fan and an exhaust duct. The exhaust axial flow fan is installed on the side of the exhaust duct close to the tunnel, and the air volume of the exhaust axial flow fan can be adjusted; the exhaust duct specifications and wind speed of the exhaust device are consistent with those of the air induced device.
[0034] The beneficial effects of the present invention are:
[0035] The fire smoke treatment system can not only replace the existing tunnel smoke exhaust devices such as inclined shafts, vertical shafts, and horizontal guides, but also can achieve gas cooling, dust removal, and neutralization and adsorption of pollutants such as carbon dioxide, nitrogen oxides, sulfur dioxide, and carbon monoxide through the air entrainment device, cooling device, dust removal device, neutralization adsorption reaction device, and exhaust device installed in the same pipeline, so that the concentration of toxic and harmful substances in the fire smoke is reduced to the standard value and then sent back to the tunnel. At the same time, the fire smoke treatment system can meet the installation of single-hole two-way traffic tunnels and separated double-width tunnels, solving the problems of tunnel smoke exhaust devices such as inclined shafts, vertical shafts, and horizontal guides being restricted by terrain, geology, and ecological conditions, and the difficulty of construction and engineering construction.
[0036] The fire smoke treatment system replaces direct smoke emission with tunnel smoke treatment in the tunnel, comprehensively considers the main pollutants in the tunnel fire smoke, separates the pollutants from the gas in steps, and has less impact on the environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 A schematic diagram of the location of the fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels installed in a single-hole two-way traffic tunnel;
[0038] Figure 2 A schematic diagram of the location of the fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels installed in a single-hole one-way traffic tunnel;
[0039] Figure 3 This is the structural layout diagram of the fire smoke treatment system that meets the smoke exhaust zoning requirements of the super-long highway tunnel;
[0040] Figure 4 This is a schematic diagram of the structure of the air entrainment device of the fire smoke treatment system that meets the smoke exhaust zoning requirements of an ultra-long highway tunnel;
[0041] Figure 5 This is a schematic diagram of the structure of the cooling device of the fire smoke treatment system that meets the smoke exhaust zoning of the super-long highway tunnel;
[0042] Figure 6 This is a schematic diagram of the structure of the dust removal device of the fire smoke treatment system that meets the smoke exhaust zoning requirements of an ultra-long highway tunnel;
[0043] Figure 7 This is a structural schematic diagram of the neutralization adsorption reaction device of the fire smoke treatment system that meets the smoke exhaust zoning requirements of an ultra-long highway tunnel;
[0044] Figure 8 This is a schematic diagram of the structure of the exhaust device of the fire smoke treatment system that meets the smoke exhaust zoning requirements of the super-long highway tunnel;
[0045] Figure 1 —8, 1—single-hole two-way traffic tunnel, 2—fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels, 3—separated double-width tunnel, 4—air entrainment device, 5—cooling device, 6—dust removal device, 7—neutralization adsorption reaction device, 8—exhaust device, 9—air entrainment duct, 10—air entrainment axial flow fan, 11—air passage duct, 12—spraying device, 13—spray water collection and recovery pool, 14—air inlet pipe, 15—dust removal device, 16—exhaust pipe, 17—neutralization reaction pool, 18—adsorption reaction duct, 19—carbon monoxide adsorbent, 20—exhaust duct, 21—exhaust axial flow fan, 22—air entrainment duct outlet, 23—oxygen supply duct. DETAILED DESCRIPTION
[0046] The following will be combined with the accompanying drawings of the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0047] For ease of description, spatially relative terms such as "upper," "lower," "left," and "right" may be used herein to describe the relationship of one element or feature shown in a figure to another element or feature. It should be understood that, in addition to the orientation shown in the processing figure, the spatial terms are intended to include different orientations of the device in use or operation. For example, if the device in the figure is inverted, elements described as being "below" other elements or features will be defined as being "above" the other elements or features. Therefore, the exemplary term "below" can include both upper and lower orientations. The device can be positioned in other ways, and the spatially relative descriptions used herein can be interpreted accordingly.
[0048] This embodiment proposes a fire smoke treatment system that meets the requirements of smoke exhaust zoning in super-long highway tunnels. Under fire conditions, the fire smoke treatment system adsorbs and neutralizes the main toxic and harmful components in the fire smoke in the tunnel, which not only meets the requirements of tunnel smoke exhaust, but also makes the smoke meet the emission standards, and greatly reduces the scale and difficulty of engineering construction. It can be used as an additional gas treatment system for long tunnels.
[0049] The plane layout of the fire smoke treatment system that meets the smoke exhaust zoning of super-long highway tunnels is as follows:
[0050] Since the fire smoke treatment system is mainly to solve the problem that the smoke exhaust travel of long tunnels cannot meet the requirements of relevant specifications without significantly increasing the scale of tunnel construction and controlling project investment, the fire smoke treatment system that meets the smoke exhaust zoning of super-long highway tunnels should be set along the longitudinal direction of the tunnel in accordance with the relevant regulations on the maximum travel of fire smoke in the tunnel; Figure 1 As shown, when the tunnel is a single-hole bidirectional traffic tunnel 1, the fire smoke treatment system 2 can be arranged vertically and horizontally; Figure 2 As shown, when the tunnel is a single-hole one-way traffic tunnel (i.e., a separated double-width tunnel 3), the fire smoke treatment system 2 is arranged in the middle of the two-width tunnels and is shared by the two-width tunnels.
[0051] The structure of the fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels is as follows:
[0052] Fires in vehicles traveling in tunnels are mainly caused by the combustion of gasoline, diesel and other solid fuels, and the products formed are carbon monoxide (CO), carbon dioxide (CO2), nitrogen oxides (NO x ), sulfur dioxide (SO2), carbon black particles, etc.; the above-mentioned harmful substances can be eliminated or their concentrations can be reduced through the fire smoke treatment system that meets the smoke exhaust zoning of super-long highway tunnels, so that the smoke can meet the environmental requirements inside the tunnel or the emission standards outside the tunnel after treatment. Figure 3 As shown, the fire smoke treatment system 2 includes an air induction device 4, a cooling device 5, a dust removal device 6, a neutralization adsorption reaction device 7 and an exhaust device 8 which are installed in the same pipeline and arranged in sequence; the direction in which the fire smoke enters the fire smoke treatment system is shown by the arrow in the figure. Figure 2 As shown, in the separated double-width tunnel 3, the fire smoke treatment system that meets the smoke exhaust zoning of the super-long highway tunnel is provided with two air intake devices 4 on one side and two exhaust devices 8 on the other side.
[0053] Air bleed device 4: Figure 3 and Figure 4 As shown, the air bleed device 4 is mainly composed of an air bleed axial flow fan 10 and an air bleed duct 9. One end of the air bleed duct 9 extends into the tunnel and is provided with an air bleed duct opening 22 for gas to enter. The other end of the air bleed duct 9 is equipped with an air bleed axial flow fan 10, and the air volume of the air bleed axial flow fan 10 should be adjustable. Figure 3 and Figure 4 As shown by the middle arrow, the main function of the air bleed device 4 is to introduce the smoke generated by the fire from the main tunnel into the pipeline of the fire smoke treatment system 2 at a fixed speed. Under fire conditions, in order to prevent the smoke from being "sucked through", the design wind speed of the pipeline port of the air bleed device 4 should be consistent with the design wind speed of the tunnel smoke exhaust port specified in the specification, and the air volume of the bleed air should meet the requirements of the fire smoke generation.
[0054] Cooling device 5: Figure 3 and Figure 5 As shown in FIG. 1 , the cooling device 5 is composed of a gas pipe 11 and a spray device 12. The spray device 12 is installed at the top of the gas pipe 11. When a fire occurs in the tunnel, the smoke temperature in the tunnel is relatively high. The cooling device 5 mainly sprays fine water mist through the spray device 12 to reduce the temperature of the smoke so that the subsequent device can process the harmful substances in the smoke. A spray water collection and recovery pool 13 is provided at the bottom of the gas pipe 11. The direction of the smoke is as follows: Figure 3 and Figure 5 Further, as a preferred technical solution of this embodiment, alkaline substances can also be added to the spray device 12 of the cooling device 5 to preliminarily neutralize the flue gas components such as nitrogen oxides and sulfur dioxide that are acidic and soluble in water in the air.
[0055] Dust removal device 6: Figure 3 and Figure 6 As shown, the dust removal device 6 is composed of an air intake pipe 14, a dust removal device 15 and an exhaust pipe 16. One end of the air intake pipe 14 is connected to the cooling device 5, and the other end is connected to the dust removal device 15; one end of the exhaust pipe 16 is connected to the dust removal device 15, and the other end is connected to the neutralization adsorption reaction device 7. One of the main solid substances in the smoke from a tunnel fire is carbon black particles. The presence of carbon black particles will not only affect the visibility of the tunnel and the driving safety, but also endanger human health when inhaled with the air. At the same time, allowing them to adhere to the inner surface of the tunnel will also affect the appearance of the tunnel. The direction of the smoke after cooling is as follows Figure 3 and Figure 6 In the direction indicated by the middle arrow, after being introduced into the dust removal device 6 through the air inlet pipe 14, the coarser particles fall to the ash hopper at the bottom of the dust removal device 15 under the action of their own weight and are then discharged; the finer particles are adsorbed on the surface of the dust removal device 15 and separated from the gas. The dust-removed flue gas is discharged from the exhaust pipe 16 and sent to the neutralization adsorption reaction device 7.
[0056] Neutralization adsorption reaction device 7: Neutralization adsorption reaction device 7 mainly processes carbon dioxide, nitrogen oxides, sulfur dioxide and other substances that will form acidic substances and carbon monoxide after dissolving in water. Figure 3 and Figure 7 As shown, the neutralization adsorption reaction device 7 is divided into three parts, namely, an oxygen supply pipeline 23, a neutralization reaction tank 17 and an adsorption reaction pipeline 18; the oxygen supply pipeline 23 is installed in the exhaust pipe 16 of the dust removal device 6; the neutralization reaction tank 17 includes a first neutralization reaction tank and a second neutralization reaction tank, and the lower part of one side of the first neutralization reaction tank is connected to the exhaust pipe 16 of the dust removal device 6, and the upper part of the other side is connected to the lower part of one side of the second neutralization reaction tank through a pipeline, and the other side of the second neutralization reaction tank is connected to one end of the adsorption reaction pipeline 18.
[0057] Smoke direction Figure 3 and Figure 6 In the direction indicated by the middle arrow, when the flue gas passes through the oxygen supply pipe 23, the nitric oxide in the flue gas is oxidized; then it is introduced into the neutralization reaction tank 17, which is filled with an alkaline aqueous solution. The flue gas and the alkaline aqueous solution undergo a chemical reaction, and the reaction product is in the form of precipitation or dissolution in water, thereby realizing the separation of the main toxic and harmful gases in the flue gas from the flue gas; then the flue gas treated in the first step is introduced into the adsorption reaction pipe 18, and the adsorption reaction pipe 18 is provided with a carbon monoxide adsorbent 19, and the gas passes slowly at a uniform speed, and the carbon monoxide gas is adsorbed and eliminated by the adsorbent.
[0058] Exhaust device 8: Figure 3 and Figure 8As shown, the exhaust device 8 is composed of an exhaust axial flow fan 21 and an exhaust pipe 20; the exhaust axial flow fan 21 is installed on the exhaust pipe 20 near the tunnel side, and the air volume of the exhaust axial flow fan 21 can be adjusted. The concentration of toxic and harmful substances in the treated fire smoke has dropped below the standard value, and the air is sent back to the tunnel by the power provided by the exhaust device 8, as shown in 3 and Figure 8 As shown by the middle arrow, the fire smoke in the tunnel is treated in this way. The exhaust duct specifications and wind speed of the exhaust device 8 are consistent with those of the air bleed device 4 to ensure the balance between the air intake and exhaust volume of the smoke treatment system in the tunnel.
[0059] The fire smoke treatment system is designed according to the actual smoke exhaust requirements of super-long highway tunnels. The design process of the fire smoke treatment system and each device is as follows:
[0060] (1) The longitudinal spacing of the fire smoke treatment system in the tunnel should be determined in combination with the smoke exhaust distance, which is generally 5 km or 3 km. The tunnel length is represented by L, and the number of fire smoke treatment systems in the tunnel can be expressed by formula (1):
[0061]
[0062] In the formula: L is the tunnel length, in m; d is the longitudinal spacing of the gas treatment system in the tunnel, in m; n is the number of gas treatment systems in the tunnel.
[0063] (2) The dynamic parameters of the air bleed device 4 and the size of the air bleed pipe 9 need to be determined by comprehensively considering the design wind speed of the smoke exhaust port and the wind speed of the main tunnel under fire conditions. Under fire conditions, in order to avoid smoke being "sucked through", the design wind speed of the pipe port of the air bleed device 4 should be consistent with the design wind speed of the tunnel smoke exhaust port specified in the specification, that is, it should not be greater than 10m / s; in order to maintain the laminar state of smoke in the main tunnel, the ventilation speed in the tunnel should not be greater than 2m / s. The air volume adjustment range of the air bleed device 4 and the cross-sectional specifications of the pipe can be expressed by formula (2) and formula (3):
[0064] Q 引 ≥A t ·v ft (2)
[0065] A y =A t ·v ft / v y (3)
[0066] Where: Q引 The air volume introduced by the air bleed device 4, in m 3 / s; A y A is the cross-sectional area of the air duct of the air bleed device 4, in m2; t is the clear cross-sectional area of the tunnel, in m2; vft is the design ventilation speed in the tunnel under fire conditions, in m / s; v y It is the design wind speed of the 9 tunnel air ducts under fire conditions, in m / s.
[0067] (3) The design concentration of smoke in the tunnel is generally expressed as 100m transmittance, which is related to the particle size of the smoke, the number of particles per unit volume of air, and the tunnel lighting environment. Therefore, the dust removal effect of the dust removal device 6 should be based on the design concentration of the tunnel smoke (see "Highway Tunnel Design Specifications Volume 2" Article 5.2.2 for details). The dust removal device 15 can be a bag dust collector or an electrostatic dust collector. The dust removal efficiency should be tested before installation, and the equipment that meets the requirements should be selected.
[0068] (4) In the neutralization adsorption reaction device 7, the oxygen supply of the oxygen supply pipe 23 should be calculated and determined according to the content of nitrogen monoxide in the flue gas; the concentration and content of the alkaline aqueous solution should be determined according to the content of acidic gas in the fire smoke, and the adsorption effect of carbon monoxide gas should be determined in combination with the adsorption capacity of the activated carbon adsorbent and the carbon monoxide content. Sodium hydroxide aqueous solution and calcium hydroxide aqueous solution are placed in the two neutralization reaction pools 17 respectively, and the number of reaction pools can also be adjusted according to the actual chemical composition of the flue gas or the flue gas treatment requirements.
[0069] The working principle of the neutralization adsorption reaction device 7 is as follows:
[0070] The nitric oxide in the fire smoke will be oxidized into nitrogen dioxide (Equation 1) after passing through the oxygen supply pipe 23, and then the gas will be passed into the first neutralization reaction tank, where the alkaline solution reacts with carbon dioxide, nitrogen oxides, and sulfur dioxide. The nitrogen oxides are mainly: nitrogen dioxide and unoxidized nitric oxide; finally, water-soluble products such as sodium sulfate, sodium bisulfate, sodium carbonate and sodium nitrite are generated (Equations 2 to 7). The carbon dioxide generated due to excessive sulfur dioxide is passed into the second neutralization reaction tank 17 with the gas, and reacts with the calcium hydroxide aqueous solution to generate water-insoluble calcium carbonate precipitate and water (Equation 8), thereby separating the pollutants from the gas.
[0071] 2NO+O2=2NO2 (Equation 1)
[0072] 2NaOH+SO2=Na2SO3+H2O (Equation 2)
[0073] SO2+Na2SO3+H2O=2NaHSO3 (Equation 3)
[0074] 2NaOH+CO2=Na2CO3+H2O (Equation 4)
[0075] 2SO2+Na2CO3+H2O=2NaHSO3+CO2↑ (Equation 5)
[0076] NO2+NO+2NaOH=2NaNO2+H2O (Equation 6)
[0077] 2NO2+2NaOH=NaNO3+NaNO2+H2O (Equation 7)
[0078] Ca(OH)2+CO2=CaCO3↓+H2O (Equation 8)
[0079] After the gas is post-treated with an alkaline solution, acidic gases that are soluble in water or that can react with an alkaline solution are eliminated, and carbon monoxide is introduced into the adsorption reaction pipeline 18 along with the remaining gas. The carbon monoxide adsorbent 19 is evenly laid in the adsorption reaction pipeline 18, and the gas passes slowly at a uniform speed, and the carbon monoxide gas is adsorbed and eliminated.
[0080] Furthermore, the amount of each reagent added in the neutralization adsorption reaction device 7 can be calculated by the following method:
[0081] Considering the oxidation of all nitric oxide in the fire smoke, the oxygen supply required by equation 1 can be expressed by equation (4):
[0082]
[0083] Where: represents the volume of oxygen to be introduced into the oxygen supply pipeline 23, in L; η NO Indicates the mass concentration of nitric oxide in the fire smoke to be treated, in g / m 3 ; Indicates the density of oxygen in g / L; Q 烟 is the smoke generation rate corresponding to the maximum heat release rate of the fire, in m 3 / s; t is the duration of the tunnel fire, in seconds; the corresponding smoke generation rate Q under the condition of maximum heat release rate of the fire 烟 The tunnel fire duration t can be determined according to Articles 10.2.1 and 10.2.3 of the "Highway Tunnel Ventilation Design Code".
[0084] Considering the worst case, all the carbon dioxide absorbed by sodium hydroxide is released, that is, the carbon dioxide generated by the reaction of equation 5 is eliminated in the second reaction tank with calcium hydroxide aqueous solution. represents the mass concentration of each pollutant in the fire smoke to be treated, then the content of sodium hydroxide in the first reaction tank and the content of calcium hydroxide in the second reaction tank are expressed by formula (5) and formula (6):
[0085]
[0086]
[0087] Where: m NaOH It indicates the content of sodium hydroxide in the first reaction tank, in g; It indicates the content of calcium hydroxide in the second reaction tank, in g; η NO , Respectively represent the mass concentration of carbon dioxide, nitric oxide, nitrogen dioxide, and sulfur dioxide in the fire smoke to be treated, in g / m 3 Among them, the mass concentration of carbon dioxide in fire smoke is about 12-15g / m 3 The mass concentration of carbon monoxide is about 0.5 to 0.8 g / m 3 The mass concentration of nitrogen dioxide is about 0.1-0.2 g / m 3 The mass concentration of nitric oxide is about 0.75-0.95 g / m 3 The mass concentration of sulfur dioxide is about 1.2 to 1.6 g / m 3 The smoke composition and its content are related to factors such as the climate conditions in the actual project area and the type of fire vehicle. Before designing, it should be determined in combination with measured data or experiments of projects under similar conditions at home and abroad.
[0088] The design is based on the principle that the adsorbent absorbs all carbon monoxide in the flue gas. The mass of the adsorbent can be expressed by formula (7):
[0089]
[0090] Where: m y The mass of adsorbent required to adsorb carbon monoxide in flue gas, in g; η CO Indicates the mass concentration of carbon monoxide in the fire smoke to be treated, in g / m 3 ρ CO is the density of carbon monoxide gas, in g / m 3 ξ CO is the adsorption capacity of carbon monoxide adsorbent 19, in m 3 / g, the adsorption capacity of carbon monoxide adsorbent 19 can generally reach 2×10 -5 ~1×10 -4 m 3 / g, before design, it should be measured in combination with the climatic conditions of the actual project area.
[0091] In the above-mentioned calculation formula for the addition amount of each reagent in the neutralization reaction adsorption device, only two representative nitrogen oxides, nitric oxide and nitrogen dioxide, in the flue gas are processed. When other nitrogen oxides exist in the flue gas and need to be processed, equations 4 and 5 can be adjusted accordingly based on their relevant chemical properties.
[0092] The volume of sodium hydroxide and calcium hydroxide aqueous solutions in the reaction tank can be expressed by formula (8) and formula (9):
[0093]
[0094]
[0095] Where: V NaOH It represents the volume of the sodium hydroxide solution in the first reaction tank, in L; c1 represents the optimal concentration of the sodium hydroxide solution that reacts with nitrogen oxides under the specific climatic environment of the tunnel project, in mol / L. The optimal concentration of the sodium hydroxide solution that reacts with nitrogen oxides is generally in the range of 0.25 to 1 mol / L, and its specific value is determined by indoor tests before design; M1 represents the molar mass of sodium hydroxide, in g / mol.
[0096] It represents the volume of calcium hydroxide solution in the second reaction tank, in L; c2 represents the optimal concentration of calcium hydroxide solution reacting with carbon dioxide under the specific climatic environment of the tunnel project, in mol / L; the optimal concentration of calcium hydroxide solution reacting with carbon dioxide generally ranges from 0.013 to 0.022 mol / L, and its specific value is determined by indoor tests before design; M2 represents the molar mass of calcium hydroxide, in g / mol.
[0097] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A fire smoke treatment system that meets the smoke exhaust zoning requirements of ultra-long highway tunnels. Features: When the tunnel is a single-hole two-way traffic tunnel, several fire smoke treatment systems are arranged alternately from left to right in the longitudinal direction; when the tunnel is a separated double-span tunnel, several fire smoke treatment systems are set in the middle of the two tunnels and shared by the two tunnels; the number of fire smoke treatment systems to be set is calculated using formula 1: Where: L is the tunnel length, d is the longitudinal spacing of the gas treatment system in the tunnel, and n is the number of gas treatment systems in the tunnel; Each fire smoke treatment system includes an air entrainment device, a cooling device, a dust removal device, a neutralization adsorption reaction device and an exhaust device which are installed in the same pipeline and arranged in sequence; the smoke generated by the fire is introduced from the main tunnel of the tunnel into the pipeline of the fire smoke treatment system through the air entrainment device; the smoke is cooled when passing through the cooling device, the particulate matter in the smoke is filtered when passing through the dust removal device, and the carbon dioxide, nitrogen oxides and sulfur dioxide in the smoke are filtered when passing through the neutralization adsorption reaction device; the concentration of toxic and harmful substances in the smoke after passing through the cooling device, the dust removal device and the neutralization adsorption reaction device has been reduced to below the standard value, and is sent back to the tunnel through the exhaust device; The air bleed device is composed of an air bleed axial flow fan and an air bleed duct. One end of the air bleed duct extends into the tunnel, and the other end is equipped with an air bleed axial flow fan. The air volume of the air bleed axial flow fan can be adjusted. The air volume adjustment range of the air bleed device and the cross-sectional specifications of the pipeline are calculated using Formula 2 and Formula 3: Q 引 ≥A t ·v ft (2) And y =A t ·in ft / in y (3) Where: Q 引 The air volume introduced by the air bleed device, A y A is the cross-sectional area of the air duct of the air bleed device, t is the clear cross-sectional area of the tunnel, v ft is the design ventilation speed in the tunnel under fire conditions; v y The design wind speed at the tunnel air duct outlet under fire conditions; The cooling device is composed of a gas pipeline and a spray device; the spray device is installed at the top of the gas pipeline, and the spray device sprays fine water mist to reduce the temperature of the flue gas; the bottom of the gas pipeline is provided with a spray water collection and recovery pool; The spray device is added with alkaline substances, which preliminarily neutralize the water-soluble acidic nitrogen oxides and sulfur dioxide flue gas components in the air; The dust removal device consists of an air intake pipe, a dust removal device and an exhaust pipe; one end of the air intake pipe is connected to a cooling device, and the other end is connected to a dust removal device; one end of the exhaust pipe is connected to a dust removal device, and the other end is connected to a neutralization adsorption reaction device; the dust removal device adopts a bag dust collector or an electrostatic dust collector, and the coarser particles in the flue gas fall to the ash hopper at the bottom of the dust removal device under the action of their own weight, and the finer particles are adsorbed on the surface of the dust removal device, and the dust removal device filters the particulate matter in the flue gas.
2. The fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels according to claim 1, Features: The neutralization adsorption reaction device consists of an oxygen supply pipeline, a neutralization reaction tank and an adsorption reaction pipeline; the oxygen supply pipeline is installed in the exhaust pipe of the dust removal device; the neutralization reaction tank includes a first neutralization reaction tank and a second neutralization reaction tank, the lower part of one side of the first neutralization reaction tank is connected to the exhaust pipe of the dust removal device, the upper part of the other side is connected to the lower part of one side of the second neutralization reaction tank through a pipeline, and the other side of the second neutralization reaction tank is connected to one end of the adsorption reaction pipeline.
3. The fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels according to claim 2, Features: The oxygen supply pipeline provides oxygen to oxidize the nitric oxide in the flue gas; the oxygen supply amount of the oxygen supply pipeline is calculated according to Formula 4: Where: Indicates the volume of oxygen that needs to be introduced into the oxygen supply pipeline, η NO Indicates the mass concentration of nitric oxide in the fire smoke that needs to be treated. represents the density of oxygen, Q 烟 is the smoke generation rate corresponding to the maximum heat release rate of the fire, and t is the duration of the tunnel fire.
4. The fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels according to claim 2, Features: A sodium hydroxide aqueous solution is placed in the first neutralization reaction tank. After the flue gas enters the first neutralization reaction tank, the sodium hydroxide reacts with carbon dioxide, nitrogen oxides, and sulfur dioxide in the flue gas to generate sodium sulfate, sodium bisulfate, sodium carbonate, and sodium nitrite that are soluble in water; A calcium hydroxide aqueous solution is placed in the second neutralization reaction tank, and the calcium hydroxide reacts with the carbon dioxide in the flue gas to generate a water-insoluble calcium carbonate precipitate and water; A carbon monoxide adsorbent is arranged in the adsorption reaction pipeline. After the gas is treated by the first neutralization reaction tank and the second neutralization reaction tank, the acidic gas that can be dissolved in water or react with the alkaline solution is eliminated, and the carbon monoxide is introduced into the adsorption reaction pipeline along with the remaining gas. The gas passes slowly at a uniform speed, and the carbon monoxide gas is adsorbed and eliminated.
5. The fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels according to claim 4, Features: The content of sodium hydroxide in the sodium hydroxide aqueous solution and the content of calcium hydroxide in the calcium hydroxide aqueous solution in the first neutralization reaction tank and the second neutralization reaction tank are calculated by Formula 5 and Formula 6: Where: m NaOH Indicates the content of sodium hydroxide in the first reaction tank, Indicates the content of calcium hydroxide in the second reaction tank, Respectively represent the mass concentrations of carbon dioxide, nitrogen dioxide and sulfur dioxide in the fire smoke to be treated; The mass of the carbon monoxide adsorbent in the adsorption reaction pipe is calculated using Formula 7: Where: m y The mass of adsorbent required to adsorb carbon monoxide in flue gas, η CO Indicates the mass concentration of carbon monoxide in the fire smoke to be treated, ρ CO is the density of carbon monoxide gas, ξ CO is the adsorption capacity of carbon monoxide adsorbent.
6. The fire smoke treatment system that meets the smoke exhaust zoning requirements of super-long highway tunnels according to claim 1, Features: The exhaust device consists of an exhaust axial flow fan and an exhaust duct. The exhaust axial flow fan is installed on the side of the exhaust duct close to the tunnel. The air volume of the exhaust axial flow fan can be adjusted. The exhaust duct specifications and wind speed of the exhaust device are consistent with those of the air induced device.