A Smart Park Management and Control Method and System Based on Digital Twin
In the smart management and control method of the digital twin park, the change probability and rendering processing difficulty of the update model are evaluated based on the historical changes of weather types and IoT monitoring data, and the update processing sequence is optimized to solve the problem of difficulty in updating the digital twin model. Real-time and accurate digital twin model display is achieved.
Patent Information
- Application Number
- CN202410828226.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-25
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-06-25
AI Technical Summary
Since there are many digital twin models corresponding to different buildings that need to be updated and managed within the park, the amount of data required for rendering processing is large, making it difficult to meet real-time requirements.
By determining the update model based on historical changes in weather types and IoT monitoring data, evaluating the change probability and rendering processing difficulty, determining the update processing sequence, and optimizing the update processing of the digital twin model.
It realizes the screening of digital twin models that change drastically, ensures the real-time and accuracy of digital twin models, avoids the difficulty of update processing, and realizes differentiated rendering processing.
Smart Images

Figure CN118379032B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of digital twins, and in particular relates to a method and system for intelligent park management and control based on digital twins. Background Art
[0002] With the rapid development of digital twin technology, the management of the park has become more intuitive. Through the construction of the digital twin model of the park, park managers can intuitively and accurately determine the real-time situation of different locations within the park. Specifically, in the invention patent application CN202311839970.6 "A smart operation management platform and construction method based on the Internet of Things and digital twins", based on the data and physical connections of each business system, through digital twin technology, a digital model of the smart park is constructed to simulate and predict the operation process of the smart park, but at the same time there are the following technical problems:
[0003] In order to improve the authenticity of digital twins, it is often necessary to update different digital twin models based on real monitoring data. However, since there are many digital twin models corresponding to different buildings that need to be updated and managed within the park, the amount of data required for rendering is large, which inevitably makes it difficult to meet the real-time requirements of rendering processing.
[0004] In response to the above technical problems, the present invention provides a method and system for intelligent park management and control based on digital twins. Summary of the invention
[0005] To achieve the purpose of the present invention, the present invention adopts the following technical solutions:
[0006] According to one aspect of the present invention, a method for intelligent management and control of a park based on digital twins is provided.
[0007] A park smart management and control method based on digital twins, characterized by specifically including:
[0008] S1 determines the update model in the digital twin model inside the park based on the historical changes of the matched IoT monitoring data under different weather types and the appearance data;
[0009] S2 uses the weather type of the current date to determine the matching historical date, obtains the update time of different update models, and determines the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates;
[0010] S3: when the change probability does not meet the requirement, taking the update model whose change probability does not meet the requirement as the update change model, and determining the rendering processing difficulty of different update change models according to the matching situation of the IoT monitoring data of different divided areas;
[0011] S4 obtains the appearance data and types of different update change models, and determines the update processing sequence of different update change models in combination with the rendering processing difficulty and change probability of different update change models, and uses the update processing sequence to perform update processing of different update change models.
[0012] A further technical solution is that the weather types include sunny days, cloudy days, rainy days, haze and snowfall.
[0013] A further technical solution is that the appearance data includes the model volume, height and width of the digital twin model at different viewing angles.
[0014] A further technical solution is that the matching historical date is a historical date with a weather type consistent with the current date.
[0015] On the other hand, the present application provides a park smart management and control system based on digital twins, which adopts the above-mentioned park smart management and control method based on digital twins, and is characterized by specifically including:
[0016] Update model screening module, change probability assessment module, processing difficulty assessment module, and update processing module;
[0017] The update model screening module is responsible for determining the update model in the digital twin model inside the park based on the historical changes of the matched IoT monitoring data under different weather types and the appearance data;
[0018] The change probability evaluation module is responsible for using the weather type of the current date to determine the matching historical date, obtaining the update time of different update models, and determining the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates;
[0019] The processing difficulty evaluation module is responsible for taking the update model whose change probability does not meet the requirements as the update change model, and determining the rendering processing difficulty of different update change models through the matching of IoT monitoring data of different divided areas;
[0020] The update processing module is responsible for obtaining the appearance data and types of different update change models, and determining the update processing order of different update change models based on the rendering processing difficulty and change probability of different update change models, and using the update processing order to perform update processing on different update change models.
[0021] The beneficial effects of the present invention are:
[0022] 1. The update model in the digital twin model of the park is determined based on the historical changes of the matching IoT monitoring data under different weather types and the appearance data, avoiding the technical problem of the difficulty of updating all digital twin models. By combining the historical changes of IoT monitoring data under different weather types, the digital twin models with more drastic changes can be screened, which also ensures the real-time and accuracy of the display results of the digital twin model.
[0023] 2. The update processing order of different update change models is determined by utilizing the appearance data and type, the rendering processing difficulty and the change probability of different update change models. This takes into account the differences in the probability of change and the rendering processing difficulty of the monitoring data of different update change models, as well as the differences in the rendering processing requirements of different update change models due to differences in appearance volume and type, thereby achieving differentiated rendering processing for different update change models.
[0024] Other features and advantages will be described in the following description. The objects and other advantages of the present invention are realized and obtained by the structures particularly pointed out in the description and drawings.
[0025] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the accompanying drawings;
[0027] Figure 1 It is a flow chart of a park smart management and control method based on digital twins;
[0028] Figure 2 is a flow chart of a method for determining an update model in a digital twin model;
[0029] Figure 3 is a flow chart of a method for determining a probability of change of an update model;
[0030] Figure 4is a flow chart of a method for determining rendering processing difficulty of an updated variable model;
[0031] Figure 5 is a flowchart of a method for determining an update processing order for updating a change model;
[0032] Figure 6 It is a framework diagram of a smart park management and control system based on digital twins. DETAILED DESCRIPTION
[0033] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this specification, not all of the embodiments. Based on the embodiments of this specification, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of this specification.
[0034] In order to ensure authenticity, the digital twin models corresponding to different buildings that need to be updated and managed within the park are updated based on the appearance data. Therefore, the amount of data required for rendering is large, which inevitably makes it difficult to meet the real-time requirements of the rendering processing.
[0035] Specifically, the present application determines the digital twin model with a large change by monitoring the frequency of changes in the IoT data, and uses it as the update model in the digital twin model within the park;
[0036] Then, according to the weather data at the current moment of the current period, a matching historical date with a high degree of similarity is determined, and based on the change of the IoT monitoring data at the current moment of the matching historical date, the proportion of the changed date is determined, and the proportion of the changed date is used as the change probability of the update model;
[0037] When the probability of change is relatively large, the updated model is used as the updated change model, and the rendering processing difficulty of different updated change models is determined by the matching of the IoT monitoring data of different divided areas, and the rendering processing difficulty of the updated change model is determined specifically according to the amount of IoT monitoring data;
[0038] The sizes of different updated change models are determined based on the appearance data of the updated change models, and the sizes of the updated change models are used to divide them into different priority levels. At different priority levels, the update processing order of different updated change models is determined according to the different rendering processing difficulties of the updated change models, and the update processing of different updated change models is performed using the update processing order.
[0039] The following will further describe the invention in conjunction with specific embodiments.
[0040] To solve the above problems, according to one aspect of the present invention, Figure 1 As shown, a park smart management and control method based on digital twins is provided, which is characterized by specifically including:
[0041] S1 determines the update model in the digital twin model inside the park based on the historical changes of the matched IoT monitoring data under different weather types and the appearance data;
[0042] Furthermore, the weather types include sunny days, cloudy days, rainy days, haze and snowfall.
[0043] Specifically, the appearance data includes the model volume, height, and width at different viewing angles of the digital twin model.
[0044] Specifically, Figure 2 As shown, the method for determining the update model in the digital twin model is:
[0045] The IoT monitoring data associated with the digital twin model is used as associated monitoring data, and the model change amount of the digital twin model is determined according to the historical changes of the associated monitoring data under different weather types;
[0046] Determine the model volume, height, and width of the digital twin model at different viewing angles using the appearance data of the digital twin model, and determine the necessity of updating the digital twin model using the model volume, height, and width of the digital twin model at different viewing angles;
[0047] The model change amount and the necessity of updating are used to determine the comprehensive update evaluation amount of different digital twin models, and the updated model in the digital twin model is determined by the comprehensive update evaluation amount.
[0048] Further, determining the updated model in the digital twin model by using the comprehensive update evaluation amount specifically includes:
[0049] When the comprehensive update evaluation value of the digital twin model is within a preset range, the digital twin model is determined to be an updated model.
[0050] In another embodiment, the method for determining the updated model in the digital twin model is:
[0051] Determine the model volume of the digital twin model using the appearance data of the digital twin model, and judge whether the model volume of the digital twin model is greater than a preset volume threshold; if so, determine that the digital twin model is an updated model; if not, proceed to the next step;
[0052] Determine whether the model volume of the digital twin model is within a preset volume range, if so, proceed to the next step, if not, determine that the digital twin model does not belong to an updated model;
[0053] Obtaining the appearance data of the digital twin model, and using the model volume, height, and width of the digital twin model at different viewing angles to determine the necessity of updating the digital twin model, judging whether the necessity of updating the digital twin model is greater than a preset necessity threshold, if so, determining that the digital twin model is an updated model, if not, proceeding to the next step;
[0054] The IoT monitoring data associated with the digital twin model is used as the associated monitoring data, and the historical change amount of the associated monitoring data between different divided time periods under different weather types is determined according to the historical change of the associated monitoring data under different weather types, and the change frequency of the associated monitoring data of the digital twin model under different weather types is determined based on the historical change amount, and it is judged whether there is a weather type whose change frequency does not meet the requirements, and if so, the digital twin model is determined to be an updated model, and if not, the next step is entered;
[0055] The model change amount is determined by the frequency of changes in the associated monitoring data of the digital twin model under different weather types, and the comprehensive update evaluation amounts of different digital twin models are determined using the model change amount and the necessity of updating. The updated model in the digital twin model is determined based on the comprehensive update evaluation amount.
[0056] In another embodiment, the method for determining the updated model in the digital twin model is:
[0057] Determine the model volume of the digital twin model using the appearance data of the digital twin model, and determine the necessity of updating the digital twin model using the model volume, height, and width of different viewing angles of the digital twin model, and judge whether the necessity of updating the digital twin model is within a preset necessity interval. If so, proceed to the next step; if not, determine whether the digital twin model is an updated model using the necessity of updating;
[0058] The IoT monitoring data associated with the digital twin model is used as the associated monitoring data, and the historical change amount of the associated monitoring data between different divided time periods under different weather types is determined according to the historical change of the associated monitoring data under different weather types, and the change frequency of the associated monitoring data of the digital twin model under different weather types is determined based on the historical change amount, and it is judged whether there is a weather type with a change frequency greater than a preset frequency, if so, proceed to the next step, if not, it is determined that the digital twin model does not belong to the update model;
[0059] Determine the basic weight values of different weather types based on the date proportions of different weather types, and determine the frequency of corrections based on the frequency of changes in the associated monitoring data of the digital twin model under different weather types, and determine whether there is a weather type with a frequency of correction greater than the preset frequency limit value. If so, proceed to the next step; if not, determine that the digital twin model does not belong to an update model;
[0060] The model change amount is determined by the frequency of change of the associated monitoring data of the digital twin model under different weather types and the basic weight values of different weather types, and the comprehensive update evaluation amount of different digital twin models is determined by using the model change amount and the necessity of updating. The updated model in the digital twin model is determined by the comprehensive update evaluation amount.
[0061] It should be noted that the necessity of updating is used to determine whether the digital twin model is an updated model, specifically including:
[0062] When the updating necessity of the digital twin model is greater than a preset necessity threshold, the digital twin model is determined to be an updated model;
[0063] When the updating necessity of the digital twin model is not greater than a preset necessity threshold, it is determined that the digital twin model does not belong to an updated model.
[0064] S2 uses the weather type of the current date to determine the matching historical date, obtains the update time of different update models, and determines the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates;
[0065] Furthermore, the matching historical date is a historical date having a weather type consistent with the current date.
[0066] Specifically, Figure 3 As shown, the method for determining the change probability of the update model is:
[0067] Determine the comprehensive similarity coefficients of different matching historical dates based on the deviation of weather data of different matching historical dates, and the deviation of months and dates;
[0068] Determine the amount of change of monitoring data of different matching historical dates by comparing the change of IoT monitoring data between the current time and the update time of different matching historical dates;
[0069] The reference change probabilities of different matching historical dates are determined by utilizing the comprehensive similarity coefficients of the digital twin model and the changes in the monitoring data, and the change probability of the updated model is determined based on the reference change probabilities of different matching historical dates.
[0070] Further, when the change probability meets the requirement, it is determined that the update model does not need to be updated.
[0071] In another embodiment, the method for determining the change probability of the update model is:
[0072] Determine the monitoring data change amount of different matching historical dates by the change of the matching IoT monitoring data between the current time and the update time of different matching historical dates, and use the monitoring data change amount to determine whether there is a matching historical date on which the monitoring data changes. If so, proceed to the next step; if not, determine whether the change probability of the update model meets the requirements;
[0073] The matching historical dates on which the monitoring data has changed are used as the changed historical dates, and it is determined whether the number of the changed historical dates is less than the preset number of dates. If so, the next step is entered; if not, it is determined that the change probability of the updated model meets the requirements;
[0074] Determine the comprehensive similarity coefficients of different matching historical dates based on the deviation of weather data of different matching historical dates, and the deviation of months and dates, and judge whether the number of matching historical dates whose comprehensive similarity coefficients meet the requirements meets the requirements, if so, proceed to the next step, if not, determine whether the change probability of the update model meets the requirements;
[0075] Determine the comprehensive reference value of the change history date according to the comprehensive similarity coefficients of different change history dates and the number of change history dates, and judge whether the comprehensive reference value of the change history date meets the requirements. If so, proceed to the next step; if not, determine whether the change probability of the update model meets the requirements;
[0076] The reference change probabilities of different matching historical dates are determined by utilizing the comprehensive similarity coefficients of the digital twin model and the changes in the monitoring data, and the change probability of the updated model is determined based on the reference change probabilities of different matching historical dates.
[0077] In another embodiment, the method for determining the change probability of the update model is:
[0078] S21 determines the comprehensive similarity coefficients of different matching historical dates based on the deviation of weather data of different matching historical dates, the deviation of months and dates, and uses the comprehensive similarity coefficients to determine similar matching historical dates, and determines whether the number of similar matching historical dates is greater than the preset number of historical dates. If so, proceed to step S23, if not, proceed to the next step;
[0079] S22 determines a similarity coefficient evaluation amount according to the number of similar matching historical dates and the comprehensive similarity coefficients of different similar matching historical dates, and judges whether the similarity coefficient evaluation amount meets the requirements. If so, proceed to the next step; if not, determine whether the change probability of the update model meets the requirements;
[0080] S23 determines the monitoring data change amount of different matching historical dates by the change of the IoT monitoring data matched between the current time and the update time of different matching historical dates, and uses the monitoring data change amount to judge whether the similar matching historical date has a changed historical date, if so, proceed to the next step, if not, determine whether the change probability of the update model meets the requirements;
[0081] S24 uses the comprehensive similarity coefficients of different matching historical dates of the digital twin model and the monitoring data change amount to determine the reference change probability of different matching historical dates, and judges whether there is a matching historical date whose reference change probability is greater than the preset probability. If so, proceed to the next step; if not, determine whether the change probability of the updated model meets the requirements;
[0082] S25 determines the change probability of the update model based on the reference change probabilities of different matching historical dates.
[0083] S3: when the change probability does not meet the requirement, taking the update model whose change probability does not meet the requirement as the update change model, and determining the rendering processing difficulty of different update change models according to the matching situation of the IoT monitoring data of different divided areas;
[0084] Specifically, Figure 4 As shown, the method for determining the rendering processing difficulty of the update change model is:
[0085] The updated change model and the preset area are used to divide the updated change model into a plurality of divided areas, and the regional rendering processing difficulty of the different divided areas is determined according to the matching conditions of the IoT monitoring data of the different divided areas;
[0086] The rendering processing difficulty of the updated change model is determined by using different regional rendering processing difficulties.
[0087] Furthermore, the value range of the difficulty of rendering the updated change model is between 0 and 1, wherein the greater the difficulty of rendering the updated change model, the greater the difficulty of rendering the updated change model.
[0088] S4 obtains the appearance data and types of different update change models, and determines the update processing sequence of different update change models in combination with the rendering processing difficulty and change probability of different update change models, and uses the update processing sequence to perform update processing of different update change models.
[0089] Specifically, Figure 5 As shown, the method for determining the update processing order of the update change model is:
[0090] Determine the model volume, height and width of different updated change models at different viewing angles according to the appearance data of different updated change models, and determine the update processing requirements of different updated change models in combination with different types of updated change models;
[0091] The update processing priority values of different update processing models are determined by the update processing requirements, rendering processing difficulty and change probability of different update processing models, and the update processing order of the update change model is determined using the update processing priority values.
[0092] Further, determining the update processing order of the update change model by using the update processing priority value specifically includes:
[0093] Determine the update processing priorities of different update change models by using the intervals in which the update processing priority values are located;
[0094] The update processing order of different update change models is determined based on the update processing priorities and update processing priority values of different update change models.
[0095] In another embodiment, the method for determining the update processing order of the update change model is:
[0096] S41: using the mapping object of the update change model in reality to determine the type of the update change model, and judging whether the type of the update change model is a preset type, if yes, proceeding to the next step, if no, proceeding to step S44;
[0097] S42 determines the model volume of different updated change models according to the appearance data of different updated change models, and judges whether the model volume of the updated change model is greater than the preset volume limit value. If so, the update processing priority of the updated change model is set to the first level, and the update processing order of the updated change model is determined according to the change probability of the updated change model. If not, proceed to the next step.
[0098] S43 determines the update processing requirements of different update change models by using the model volumes, heights, widths of different viewing angles and types of different update change models, and judges whether the update processing requirements of the update change models are greater than a preset requirement limit value. If so, sets the update processing priority of the update change model to the second level, and determines the update processing order of the update change model by using the change probability of the update change model. If not, proceeds to the next step.
[0099] S44 sets the update processing priority of the update change model to the third level, determines the update processing priority values of different update processing models by weighting the update processing requirements, rendering processing difficulty and change probability of different update processing models, and uses the update processing priority values to determine the update processing order of the update change model.
[0100] On the other hand, Figure 6 As shown, the present application provides a park smart management and control system based on digital twins, which adopts the above-mentioned park smart management and control method based on digital twins, and is characterized by specifically including:
[0101] Update model screening module, change probability assessment module, processing difficulty assessment module, and update processing module;
[0102] The update model screening module is responsible for determining the update model in the digital twin model inside the park based on the historical changes of the matched IoT monitoring data under different weather types and the appearance data;
[0103] The change probability evaluation module is responsible for using the weather type of the current date to determine the matching historical date, obtaining the update time of different update models, and determining the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates;
[0104] The processing difficulty evaluation module is responsible for taking the update model whose change probability does not meet the requirements as the update change model, and determining the rendering processing difficulty of different update change models through the matching of IoT monitoring data of different divided areas;
[0105] The update processing module is responsible for obtaining the appearance data and types of different update change models, and determining the update processing order of different update change models based on the rendering processing difficulty and change probability of different update change models, and using the update processing order to perform update processing on different update change models.
[0106] Through the above embodiments, the present invention achieves the following beneficial effects:
[0107] 1. The update model in the digital twin model of the park is determined based on the historical changes of the matching IoT monitoring data under different weather types and the appearance data, avoiding the technical problem of the difficulty of updating all digital twin models. By combining the historical changes of IoT monitoring data under different weather types, the digital twin models with more drastic changes can be screened, which also ensures the real-time and accuracy of the display results of the digital twin model.
[0108] 2. The update processing order of different update change models is determined by utilizing the appearance data and type, the rendering processing difficulty and the change probability of different update change models. This takes into account the differences in the probability of change and the rendering processing difficulty of the monitoring data of different update change models, as well as the differences in the rendering processing requirements of different update change models due to differences in appearance volume and type, thereby achieving differentiated rendering processing for different update change models.
[0109] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device, equipment, and non-volatile computer storage medium embodiments, since they are basically similar to the method embodiments, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
[0110] The above is a description of a specific embodiment of the specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0111] The above description is only one or more embodiments of this specification and is not intended to limit this specification. For those skilled in the art, one or more embodiments of this specification may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of one or more embodiments of this specification shall be included in the scope of the claims of this specification.
Claims
1. A park smart management and control method based on digital twins, characterized in that: Specifically include: Determine the update model in the digital twin model of the park based on the historical changes of the matched IoT monitoring data and the appearance data under different weather types; Using the weather type of the current date to determine the matching historical date, obtaining the update time of different update models, and determining the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates; When the change probability does not meet the requirements, the update model whose change probability does not meet the requirements is used as the update change model, and the rendering processing difficulty of different update change models is determined by the matching of IoT monitoring data in different divided areas; Obtaining the appearance data and types of different update change models, and determining the update processing sequence of different update change models in combination with the rendering processing difficulty and change probability of different update change models, and performing the update processing of different update change models using the update processing sequence; The method for determining the updated model in the digital twin model is: The IoT monitoring data associated with the digital twin model is used as associated monitoring data, and the model change amount of the digital twin model is determined according to the historical changes of the associated monitoring data under different weather types; Determine the model volume, height, and width of the digital twin model at different viewing angles using the appearance data of the digital twin model, and determine the necessity of updating the digital twin model using the model volume, height, and width of the digital twin model at different viewing angles; Determine the comprehensive update evaluation amount of different digital twin models by using the model change amount and the update necessity, and determine the update model in the digital twin model by using the comprehensive update evaluation amount; The method for determining the change probability of the update model is: S21 determines the comprehensive similarity coefficients of different matching historical dates based on the deviation of weather data of different matching historical dates, the deviation of months and dates, and uses the comprehensive similarity coefficients to determine similar matching historical dates, and determines whether the number of similar matching historical dates is greater than the preset number of historical dates. If so, proceed to step S23, if not, proceed to the next step; S22 determines a similarity coefficient evaluation amount according to the number of similar matching historical dates and the comprehensive similarity coefficients of different similar matching historical dates, and judges whether the similarity coefficient evaluation amount meets the requirements. If so, proceed to the next step; if not, determine whether the change probability of the update model meets the requirements; S23 determines the monitoring data change amount of different matching historical dates by the change of the IoT monitoring data matched between the current time and the update time of different matching historical dates, and uses the monitoring data change amount to judge whether the similar matching historical date has a changed historical date, if so, proceed to the next step, if not, determine whether the change probability of the update model meets the requirements; S24 uses the comprehensive similarity coefficients of different matching historical dates of the digital twin model and the monitoring data change amount to determine the reference change probability of different matching historical dates, and judges whether there is a matching historical date whose reference change probability is greater than the preset probability. If so, proceed to the next step; if not, determine whether the change probability of the updated model meets the requirements; S25: determining the change probability of the update model based on the reference change probabilities of different matching historical dates; The method for determining the update processing order of the update change model is: S41: using the mapping object of the update change model in reality to determine the type of the update change model, and judging whether the type of the update change model is a preset type, if yes, proceeding to the next step, if no, proceeding to step S44; S42 determines the model volume of different updated change models according to the appearance data of different updated change models, and judges whether the model volume of the updated change model is greater than the preset volume limit value. If so, the update processing priority of the updated change model is set to the first level, and the update processing order of the updated change model is determined according to the change probability of the updated change model. If not, proceed to the next step. S43 determines the update processing requirements of different update change models by using the model volumes, heights, widths of different viewing angles and types of different update change models, and judges whether the update processing requirements of the update change models are greater than a preset requirement limit value. If so, sets the update processing priority of the update change model to the second level, and determines the update processing order of the update change model by using the change probability of the update change model. If not, proceeds to the next step. S44 sets the update processing priority of the update change model to the third level, determines the update processing priority values of different update processing models by weighting the update processing requirements, rendering processing difficulty and change probability of different update processing models, and uses the update processing priority values to determine the update processing order of the update change model.
2. The park smart management and control method based on digital twins according to claim 1 is characterized in that: The weather types include sunny, cloudy, rainy, foggy and snowy.
3. The park smart management and control method based on digital twins according to claim 1 is characterized in that: The appearance data includes the model volume, height, and width at different viewing angles of the digital twin model.
4. The park smart management and control method based on digital twins according to claim 1 is characterized in that: Determining the updated model in the digital twin model by using the comprehensive update evaluation amount specifically includes: When the comprehensive update evaluation value of the digital twin model is within a preset range, the digital twin model is determined to be an updated model.
5. The park smart management and control method based on digital twins according to claim 1 is characterized in that: The matching historical date is a historical date with a weather type consistent with the current date.
6. The park smart management and control method based on digital twins according to claim 1 is characterized in that: When the change probability meets the requirement, it is determined that the update model does not need to be updated.
7. A park smart management and control system based on digital twins, adopting a park smart management and control method based on digital twins as described in any one of claims 1 to 6, characterized in that: Specifically include: Update model screening module, change probability assessment module, processing difficulty assessment module, and update processing module; The update model screening module is responsible for determining the update model in the digital twin model inside the park based on the historical changes of the matched IoT monitoring data under different weather types and the appearance data; The change probability evaluation module is responsible for using the weather type of the current date to determine the matching historical date, obtaining the update time of different update models, and determining the change probability of the update model according to the change of the matching IoT monitoring data between the current time and the update time under different matching historical dates; The processing difficulty evaluation module is responsible for taking the update model whose change probability does not meet the requirements as the update change model, and determining the rendering processing difficulty of different update change models through the matching of IoT monitoring data of different divided areas; The update processing module is responsible for obtaining the appearance data and types of different update change models, and determining the update processing order of different update change models based on the rendering processing difficulty and change probability of different update change models, and using the update processing order to perform update processing on different update change models.
Citation Information
Patent Citations
Intelligent operation management platform based on Internet of Things and digital twinning and construction method
CN117993845A
Head count prediction device, facility management system, and program
CN109791638A
Processing method and computer equipment
CN111428882A
Method, device and equipment for evaluating health state of fan foundation and medium
CN114757048A
Intelligent vibratory digital twinning system and method for industrial environments
CN115039045A