Load resource scheduling method, system and medium based on main and distribution coordination
Through multiple interactions and verifications between power grids, the optimal load transfer plan is determined, which solves the problem of insufficient power supply capacity of the power grid under peak loads and extreme weather, realizes resource sharing and flexible mutual assistance, and improves the power supply capacity of the power grid. and safe and stable operation.
Patent Information
- Application Number
- CN202410917773.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-10
AI Technical Summary
During peak load periods and extreme weather conditions, the power supply capacity of the power grid is limited, and the load transfer between the main and distribution network is separated from each other. The traditional transfer resource scheduling method is difficult to adjust the load resources in a timely manner, resulting in the problem of time and space mismatch of supply and demand.
Through multiple interactions and verifications between the main power grid and the distribution network, the optimal load transfer plan is determined. The main power grid and the distribution network each do their best to perform dispatching to improve the power supply capacity of the power grid and the flexible mutual aid capabilities between regions. , to achieve resource sharing.
It effectively alleviates the problem of time and space mismatch between supply and demand, improves the power supply capacity of the power grid and the flexible mutual assistance between regions, reduces the complexity and risks of power grid operation, and improves the level of equipment management and safe and stable operation.
Smart Images

Figure CN118469756B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of resource scheduling, and in particular to a load resource scheduling method, system and medium based on master-distributor coordination. Background Art
[0002] As the power supply capacity of the power grid is increased at full speed, the mismatch between the progress of power grid construction and the needs of power security and social electricity demand is becoming more and more obvious; with the growth of regional GDP, social electricity demand increases; the problem of "hollowing out" of power sources is prominent, and it is difficult to balance power supply and demand during periods of high load; there is an imbalance in the development of the power grid and the load distribution is uneven.
[0003] At present and in the future, the structure and form of the power grid will gradually change, and the power grid cognition, control, and defense systems will face all-round challenges, which will put forward higher requirements for the optimal allocation of power resources and the dispatching and operation of the power grid. Therefore, how to establish intelligent power grid dispatching and operation control means, activate all kinds of resources in the whole network, improve flexible dispatching capabilities, collaborative interaction capabilities, and resource conditions, and how to comprehensively improve the control ability and safe operation level of large power grids have become key issues to be solved at present.
[0004] At present, there are deficiencies in the technical means of grid operation; the grid is in a transition period of rapid construction, and the grid topology has changed greatly. During the transition period, the local grid structure has weakened, the operation characteristics are complex and changeable, the control difficulty is becoming increasingly complex, and the power balance mode has changed. Faced with a large number of dispatching and control objects and operation mode adjustments, traditional grid operation and management methods are difficult to support the new business needs, and are even more unable to cope with the explosive growth in workload during the peak summer load period and continuous extreme weather conditions.
[0005] Electric power dispatching follows the "unified dispatching, hierarchical management" model of the entire network. The main operating mode is arranged from top to bottom by the province, prefecture and county, and the dispatching agencies at all levels independently arrange the operating mode within their dispatching jurisdiction. However, during peak load periods and extreme weather conditions, the power supply capacity of the power grid is limited, the potential tapping measures of the 500 kV main power grid have been exhausted, the key sections are overloaded, and some main transformers and lines are overloaded. The 220 kV operating mode is approved and implemented by the provincial dispatching, and the operating mode of the 110 kV and below main distribution network is independently implemented by the prefecture and county dispatching. There is a separation in the adjustment of load resources on the grid side, the distribution network has a large number of lines and complex connections, and a large number of intertwined operating mode adjustments may not achieve the purpose of adjusting the load distribution between regions, but will increase the operating pressure of the upper heavy-load equipment. Summary of the invention
[0006] The technical problem to be solved by the present invention is: during peak load periods and extreme weather conditions, the power supply capacity of the power grid is limited, and the load transfer between the main and distribution networks is separated, and the traditional transfer resource scheduling method is difficult to timely adjust the load resources; the purpose of the present invention is to provide a load resource scheduling method, system and medium based on main and distribution coordination, to improve the method of traditional transfer resource scheduling technology, and through multiple interactions and verifications between the main power grid and the distribution network, to determine the optimal load transfer plan, the main power grid and the distribution network each do their best to make full use of the scheduling means, to fully enhance the power supply capacity of the power grid and the flexible mutual assistance capabilities between regions, to promote resource sharing, and to alleviate the problem of temporal and spatial mismatch between supply and demand.
[0007] The present invention is achieved through the following technical solutions:
[0008] This solution provides a load resource scheduling method based on main and distribution coordination, including:
[0009] Real-time monitoring of the status data of the main power grid;
[0010] Performing a power transfer triggering judgment based on the status data;
[0011] Based on the power transfer trigger judgment result, the main power grid power transfer analysis is started; the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy;
[0012] Resources are scheduled according to the final transfer strategy.
[0013] Working principle of this scheme: During peak load periods and extreme weather conditions, the power supply capacity of the power grid is limited, and the load transfer between the main and distribution networks is separated. The traditional transfer resource scheduling method is difficult to adjust the load resources in a timely manner; the purpose of the present invention is to provide a load resource scheduling method, system and medium based on main and distribution coordination, to improve the method of traditional transfer resource scheduling technology, and through multiple interactions and verifications between the main power grid and the distribution network, to determine the optimal load transfer plan. The main power grid and the distribution network each do their best to make full use of the scheduling means, to fully enhance the power supply capacity of the power grid and the flexible mutual assistance capabilities between regions, to promote resource sharing, and to alleviate the problem of temporal and spatial mismatch between supply and demand.
[0014] A further optimization scheme is that the status data includes: main grid alarm information status, main grid operation mode and main grid equipment load over-limit status; the main grid operation mode includes: the main grid is in working mode and the main grid is in maintenance mode.
[0015] A further optimization scheme is that the method for determining the power transfer trigger includes:
[0016] When any of the following situations occurs, it is determined that the main power grid transfer analysis needs to be started:
[0017] Case a: the main power grid has an alarm message issued; (i.e. the main power grid is in an accident state)
[0018] Case b, the main power grid is in maintenance mode;
[0019] Case c: the main power grid has load-over-limit equipment;
[0020] When it is determined that the main power grid transfer analysis needs to be started in situation a, the load loss at the alarm location is determined; when it is determined that the main power grid transfer analysis needs to be started in situation c, the amount by which the equipment load exceeds the limit is determined.
[0021] A further optimization scheme is that the main power grid power transfer analysis is started based on the power transfer trigger judgment result, including the following method:
[0022] The specific main power grid first calibrates the current power grid risks, maintenance conditions, and defect listing conditions based on the real-time topology, and adopts direct transfer, partial transfer, splitting, replacement, and multi-level transfer to free up the capacity to be transferred.
[0023] The main power grid obtains the busbar to be transferred and calculates the capacity to be transferred, and the main power grid sends the busbar to be transferred and the capacity to be transferred to the distribution network;
[0024] The distribution network performs transfer measurement calculation based on the bus to be transferred and the capacity to be transferred, and the distribution network also generates a transfer plan list based on the transfer measurement calculation result and sends it to the main power grid;
[0025] After receiving the list of transfer plans, the main power grid verifies and evaluates the transfer plans in the list one by one, and uses the transfer plans that have passed the verification as the transfer strategies; the main power grid also archives the transfer equipment information records corresponding to the transfer strategies and sends them to the distribution network.
[0026] A further optimization scheme is that the method for obtaining the transfer scheme list includes:
[0027] Obtain the busbar to be transferred and the capacity to be transferred;
[0028] The distribution network analyzes the connection conditions of the distribution network under the busbar on this side, excludes the single radial line and the listed line in the lower distribution network, and formulates multiple groups of transfer connection methods under the condition of meeting the capacity to be transferred;
[0029] The distribution network screens each group of transfer wiring modes: the distribution network topologically links the current transfer wiring mode with the capacity to be transferred, and determines whether the upper-level equipment on the distribution network side has load over-limit after the topological link. If not, the current transfer wiring mode is used as a transfer plan;
[0030] All the transfer plans are counted to obtain a list of transfer plans.
[0031] A further optimization scheme is to check and evaluate the transfer schemes in the transfer scheme list one by one, including the following method:
[0032] The main power grid is topologically linked with the distribution network according to the current power transfer plan. After the topological link is established, it is determined whether the load of the upper-level equipment on the main power grid side exceeds the limit. If not, the current power transfer plan passes the verification.
[0033] A further optimization scheme is that the transfer equipment information includes: each transfer equipment ID, the limit value of the transfer equipment, the current value of the transfer equipment and the off-line rate of the transfer equipment.
[0034] Further optimization plans also include:
[0035] After resources are dispatched according to the final transfer strategy, if there is still a load gap in the capacity to be transferred, the main power grid will push the load gap to the marketing load control system or the load precision control system.
[0036] This solution also provides a load resource dispatching system based on main and distribution coordination, which is used to implement the above-mentioned load resource dispatching method based on main and distribution coordination; the system includes:
[0037] Monitoring module, used to monitor the status data of the main power grid in real time;
[0038] A judgment module, used for making a power transfer trigger judgment based on the status data;
[0039] An analysis module is used to start the main power grid power transfer analysis based on the power transfer trigger judgment result, and the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy;
[0040] The scheduling module is used to schedule resources according to the final transfer strategy.
[0041] The present solution also provides a computer-readable medium on which a computer program is stored. The computer program is executed by a processor to implement the load resource scheduling method based on main-distribution coordination as described above.
[0042] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0043] The present invention provides a load resource scheduling method, system and medium based on main-distribution coordination, improves the method of traditional transfer resource scheduling technology, and determines the optimal load transfer plan through multiple interactions and verifications between the main power grid and the distribution network. The main power grid and the distribution network each do their best to make full use of the scheduling means, fully enhance the power supply capacity of the power grid and the flexible mutual assistance capacity between regions, promote resource sharing, and alleviate the problem of temporal and spatial mismatch between supply and demand. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:
[0045] Figure 1 It is a flow chart of a load resource scheduling method based on main and distribution coordination;
[0046] Figure 2 A schematic diagram of the analysis principle of power transfer to the main power grid;
[0047] Figure 3 This is a structural diagram of the load resource scheduling system based on main and distribution coordination. DETAILED DESCRIPTION
[0048] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0049] Embodiment 1: This embodiment provides a load resource scheduling method based on master-distributor coordination, such as Figure 1 As shown, including:
[0050] Step 1: Real-time monitoring of the status data of the main power grid;
[0051] The status data includes: main grid alarm information status, main grid operation mode and main grid equipment load over-limit status; the main grid operation mode includes: main grid in working mode and main grid in maintenance mode.
[0052] Step 2: determining the power transfer trigger based on the status data;
[0053] The method for determining the supply transfer trigger includes:
[0054] When any of the following situations occurs, it is determined that the main power grid transfer analysis needs to be started:
[0055] Case a: the main power grid has an alarm message issued; (i.e. the main power grid is in an accident state)
[0056] Case b, the main power grid is in maintenance mode;
[0057] Case c: the main power grid has load-over-limit equipment;
[0058] When it is determined that the main power grid transfer analysis needs to be started in situation a, the load loss at the alarm location is determined; when it is determined that the main power grid transfer analysis needs to be started in situation c, the amount by which the equipment load exceeds the limit is determined.
[0059] In the traditional load resource dispatching process, whether it is necessary to start the main grid transfer analysis is mainly based on experience, relying on skilled professional experience. Different scenarios require different experience judgments and require a lot of manpower. This solution gives full play to the role of large-scale power grid resource optimization allocation, establishes an integrated power grid dispatching system, and accurately adjusts the operation mode within the network. It can be applied to the main distribution network operation mode linkage and coordination in accident scenarios (main grid has alarm information), daily maintenance scenarios (main grid is in maintenance mode), and over-limit scenarios (main grid has equipment with over-limit load), avoiding the mutual separation between the main grid and the distribution network load transfer. In the event of an accident, timely starting the main grid transfer analysis can automatically and quickly restore the power-off load. In the case of maintenance, timely starting the main grid transfer analysis combined with the inherent risks of the existing power grid and the subsequent maintenance plan can arrange the optimal operation mode to transfer the load in advance. In the case of over-limit or when the contradiction between supply and demand is prominent, timely starting the main grid transfer analysis can maximize the power supply potential of sections, main transformers, and lines, realize the panoramic perception and linkage regulation of various load resources, and comprehensively improve the equipment and load management level and the safe and stable operation level of the power grid.
[0060] Step 3: starting the main power grid power transfer analysis based on the power transfer trigger judgment result; the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy;
[0061] The main power grid power transfer analysis is started based on the power transfer trigger judgment result, such as Figure 2 As shown, including methods:
[0062] The specific main power grid first calibrates the current power grid risks, maintenance conditions, and defect listing conditions based on the real-time topology, and adopts direct transfer, partial transfer, splitting, replacement, and multi-level transfer to free up the capacity to be transferred.
[0063] According to the previous step, the main grid obtains the bus to be transferred and calculates the capacity to be transferred, and the main grid sends the bus to be transferred and the capacity to be transferred to the distribution network; (the first interaction between the main grid and the distribution network)
[0064] In this step, when an alarm message is issued by the main grid or a load-exceeding device is present in the main grid, the capacity to be transferred is determined based on the load loss at the alarm location or the load-exceeding amount.
[0065] The distribution network performs transfer measurement calculation based on the bus to be transferred and the capacity to be transferred, and the distribution network also generates a transfer plan list based on the transfer measurement calculation result and sends it to the main grid; (the second interaction between the main grid and the distribution network)
[0066] After receiving the transfer plan list, the main grid verifies and evaluates the transfer plans in the transfer plan list one by one, and uses the transfer plans that pass the verification as the transfer strategy; the main grid also records and archives the transfer equipment information corresponding to the transfer strategy and sends it to the distribution network. (The third interaction between the main grid and the distribution network)
[0067] The method for obtaining the transfer scheme list includes:
[0068] The distribution network screens each group of transfer wiring modes: the distribution network topologically links the current transfer wiring mode with the capacity to be transferred, and determines whether the upper-level equipment on the distribution network side has load over-limit after the topological link. If not, the current transfer wiring mode is used as a transfer plan;
[0069] All the transfer plans are counted to obtain a list of transfer plans.
[0070] The method of checking and evaluating the transfer plans in the transfer plan list one by one includes:
[0071] The main power grid is topologically linked with the distribution network according to the current power transfer plan. After the topological link is established, it is determined whether the load of the upper-level equipment on the main power grid side exceeds the limit. If not, the current power transfer plan passes the verification.
[0072] Based on the deep integration of main and distribution coordinated loads, the main power grid and distribution network adjust the operating mode through three interactions and verifications. This is the core innovation of the key technology of intelligent dispatching resource optimization configuration based on main and distribution coordination. It can realize accurate and intelligent adjustment of the operating mode, ensure the safety of power grid operation, and effectively control the load. At the same time, it does not generate new over-limit or power grid risks, and realizes artificial load reduction. After the main power grid mode is adjusted, there is still a gap, and the distribution network transfer plan needs to be superimposed to form a combined strategy. The transfer equipment information includes: each transfer equipment ID, the limit value of the transfer equipment, the current value of the transfer equipment, and the over-line rate of the transfer equipment. The transfer equipment information facilitates the rapid positioning of the access transfer equipment according to the transfer equipment ID during the resource scheduling process, and reasonably sets the access status according to the limit value of the transfer equipment, the current value of the transfer equipment, and the over-line rate of the transfer equipment.
[0073] Step 4: Perform resource scheduling according to the final transfer strategy.
[0074] Step 5: After resources are dispatched according to the final transfer strategy, if there is still a load gap in the capacity to be transferred, the main power grid pushes the load gap to the marketing load control system or the load precision control system.
[0075] In order to ensure the safe and stable operation of the power grid, when resources are dispatched according to the final transfer strategy and after the transfer plan list is generated, a confirmation interface can pop up at key node locations to interact with the dispatcher, and the next step can be performed after confirmation by the dispatcher.
[0076] The main power grid and the distribution network have conducted three interactions and verifications to determine the optimal load transfer plan. On the distribution network side, the distribution network topology is used to transfer load resources between stations and regions. The main power grid and the distribution network have each done their best to fully utilize the dispatching means, fully enhance the power supply capacity of the power grid and the flexible mutual assistance capacity between regions, promote flexible resource sharing, and alleviate the problem of time and space mismatch between supply and demand.
[0077] Embodiment 2: This embodiment provides a load resource scheduling system based on master-distributor coordination, which is used to implement the load resource scheduling method based on master-distributor coordination of embodiment 1; Figure 3 As shown, the system includes:
[0078] Monitoring module, used to monitor the status data of the main power grid in real time;
[0079] A judgment module, used for making a power transfer trigger judgment based on the status data;
[0080] An analysis module is used to start the main power grid power transfer analysis based on the power transfer trigger judgment result, and the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy;
[0081] The scheduling module is used to schedule resources according to the final transfer strategy.
[0082] Embodiment 3: This embodiment provides a computer-readable medium having a computer program stored thereon, and the computer program is executed by a processor to implement the load resource dispatching method based on main-distribution coordination as described in Embodiment 1; the key technology for power supply guarantee is put into pilot construction, and the load resource dispatching method based on main-distribution coordination has been trial-operated for 6 months; the achievements mainly include: building a large power grid protection control system based on main-distribution coordination; realizing the intelligent generation of functions such as operation mode potential tapping, load transfer and absorption, accident emergency avoidance, and power supply equipment operation mode generation, and playing the role of real-time configuration of large power grid resources; on the basis of ensuring the safe and stable operation of the power grid, the power supply potential of 980,000 kilowatts is tapped to the limit, the power transmission and transformation capacity of key equipment is improved, and the power supply is increased by 49 million kilowatt-hours; the operation mode adjustment instructions are issued online, and the dispatch call time is reduced by 362 minutes in total, the accident handling time is shortened by 70%, and the indirect losses caused by power outages and the investment in power supply manpower and equipment are reduced.
[0083] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A load resource scheduling method based on master-distributor coordination is characterized in that: include: Real-time monitoring of the status data of the main power grid; The status data includes: main grid alarm information status, main grid operation mode and main grid equipment load over-limit status; the main grid operation mode includes: main grid is in working mode and main grid is in maintenance mode; The power transfer trigger judgment is performed based on the status data; the power transfer trigger judgment method includes: When any of the following situations occurs, it is determined that the main power grid transfer analysis needs to be started: Case a, the main power grid has an alarm message issued; Case b, the main power grid is in maintenance mode; Case c: the main power grid has load-over-limit equipment; When it is determined that the main power grid transfer analysis needs to be started in case a, the load loss at the alarm location is determined; when it is determined that the main power grid transfer analysis needs to be started in case c, the amount of equipment load exceeding the limit is determined; Based on the result of the power transfer trigger judgment, the main power grid power transfer analysis is started; the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy; The method of starting the main power grid power transfer analysis based on the power transfer trigger judgment result includes: The main power grid obtains the busbar to be transferred and calculates the capacity to be transferred, and the main power grid sends the busbar to be transferred and the capacity to be transferred to the distribution network; The distribution network performs transfer measurement calculation based on the bus to be transferred and the capacity to be transferred, and the distribution network also generates a transfer plan list based on the transfer measurement calculation result and sends it to the main power grid; The method for obtaining the transfer scheme list includes: Obtain the busbars to be transferred and the capacity to be transferred; the specific main grid first calibrates the current grid risk, maintenance status, and defect listing status based on the real-time topology, and uses direct transfer, partial transfer, splitting, replacement or multi-level transfer to free up the capacity to be transferred; The distribution network analyzes the connection conditions of the distribution network under the busbar on this side, excludes the single radial line and the listed line in the lower distribution network, and formulates multiple groups of transfer connection methods under the condition of meeting the capacity to be transferred; The distribution network screens each group of transfer wiring modes: the distribution network topologically links the current transfer wiring mode with the capacity to be transferred, and determines whether the upper-level equipment on the distribution network side has load over-limit after the topological link. If not, the current transfer wiring mode is used as a transfer plan; Count all the transfer plans to obtain a list of transfer plans; After receiving the list of power transfer schemes, the main power grid verifies and evaluates the power transfer schemes in the list of power transfer schemes one by one, and uses the verified power transfer schemes as power transfer strategies; the main power grid also records and archives the power transfer equipment information corresponding to the power transfer strategies and sends them to the distribution network; The method of checking and evaluating the transfer plans in the transfer plan list one by one includes: The main grid is topologically linked with the distribution network according to the current power transfer plan, and it is determined whether the load of the upper-level equipment on the main grid side exceeds the limit after the topological link. If not, the current power transfer plan passes the verification; Resources are scheduled according to the final transfer strategy.
2. The load resource scheduling method based on master-distributor coordination according to claim 1 is characterized in that: The transfer equipment information includes: each transfer equipment ID, the limit value of the transfer equipment, the current value of the transfer equipment and the off-line rate of the transfer equipment.
3. The load resource scheduling method based on master-distributor coordination according to claim 2 is characterized in that: Also includes: After resources are dispatched according to the final transfer strategy, if there is still a load gap in the capacity to be transferred, the main power grid will push the load gap to the marketing load control system or the load precision control system.
4. The load resource dispatching system based on main and distribution coordination is characterized by: Used to implement the load resource scheduling method based on main and distribution coordination as described in any one of claims 1 to 3; the system includes: Monitoring module, used to monitor the status data of the main power grid in real time; A judgment module, used for making a power transfer trigger judgment based on the status data; An analysis module is used to start the main power grid power transfer analysis based on the power transfer trigger judgment result, and the main power grid power transfer analysis includes a process: the main power grid interacts with the distribution network multiple times to generate a final power transfer strategy; The scheduling module is used to schedule resources according to the final transfer strategy.
5. A computer readable medium having a computer program stored thereon, characterized in that: The computer program is executed by a processor to implement the load resource scheduling method based on main-distribution coordination as described in any one of claims 1 to 3.