Security management method and system based on digital security twin

By constructing the initial model and standard model of the safety digital twin, combined with virtual roaming technology, the problem of intelligent and digital transformation of safety management in building construction is solved, the efficient discovery and correction of safety hazards during the construction process is achieved, and construction safety and security are improved. efficiency.

CN118469765BActive Publication Date: 2024-10-25郑州宝冶钢结构有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410706419.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-03
Publication Date
2024-10-25
Estimated Expiration
2044-06-03

AI Technical Summary

Technical Problem

Existing technology makes it difficult to effectively intelligently and digitally manage safety during the construction process, making it difficult to detect and correct potential safety hazards in a timely manner during the construction process, affecting construction efficiency and safety.

Method used

Adopting a safety management method based on digital safety twins, by building an initial safety digital twin model, a safety management model and a safety digital twin standard model of the construction process, combined with virtual roaming technology, early warning and output of safety hazards in the construction process are carried out based on Different personnel, environment and stage characteristics build corresponding safe digital twin standard models for lightweight compression and display.

Benefits of technology

It has realized the digital intelligence of the safety management process during the construction process, improved the accuracy and efficiency of safety hazards, ensured the safe and smooth progress of all stages of construction, and enhanced the accuracy and efficiency of construction management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118469765B_ABST
    Figure CN118469765B_ABST
Patent Text Reader

Abstract

The safety management method based on digital safety twins builds an initial safety digital twin model of the construction process based on design data, builds a safety management model based on the safety protection measures and specifications corresponding to the construction process, and then builds a safety digital twin standard model. The virtual roaming body is used to perform virtual roaming on the safety digital twin standard model, and early warning and output of safety hazards in the roaming results are carried out. This can more accurately and efficiently complete the safety management process and early warning output process of the engineering construction, and can improve the accuracy and efficiency of the model display.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the safety management of engineering management, in particular to the field of safety management in processes such as building construction. Background Art

[0002] Safety management of construction projects is an important part of ensuring the safe and smooth completion of the project. Safety management involves all aspects of the construction process and is a global and systematic project. BIM (building information model) is an emerging technical means to manage buildings and their construction processes in a digital way. It can play an important role in improving project management capabilities and improving construction efficiency. It is the development direction of digital transformation of construction processes.

[0003] Digital twin is an emerging technology that maps physical equipment in cyberspace to manage the entire life cycle of physical equipment. It is the technical foundation for intelligent manufacturing and intelligent construction.

[0004] In order to adapt to the development direction of intelligent construction process, ensure the safe and smooth completion of the construction process and improve construction efficiency, it is urgently necessary to carry out intelligent and digital transformation of the safety management process of construction. Summary of the invention

[0005] The purpose of the present invention is to provide a safety management method and system based on digital safety twins to improve the digital and intelligent level of the construction safety management process and ensure the safe and smooth progress of all stages of engineering construction.

[0006] The present invention provides a security management method based on digital security twins, comprising the following steps:

[0007] 1. Build a safe digital twin initial model of the construction process based on design data.

[0008] The design data includes design document data and BIM data. The design document data and BIM data are processed to obtain construction personnel data, construction material data, construction environment data, and construction stage data; 2. Based on the safety protection measures and safety protection specifications of the construction process, a safety management model is constructed.

[0009] Specifically, different types of projects and different stages of construction face different safety risks, so the safety protection measures and safety protection specifications that need to be taken are also different. Based on the project type of the current project, the safety protection measures and safety protection specifications corresponding to the project type are obtained, and based on the safety protection measures and safety protection specifications, a safety management model is constructed, and the safety management model is divided into different safety stages based on the project progress and construction stage.

[0010] 3. Build a safety digital twin standard model of the construction process and display the safety digital twin standard model in a lightweight manner.

[0011] Specifically, the safety management model is mapped to the personnel safety digital twin initial model, the material safety digital twin initial model, and the environmental safety digital twin initial model to construct a safety digital twin standard model; the safety digital twin standard model includes a personnel safety digital twin standard model, a material safety digital twin standard model, and an environmental safety digital twin standard model;

[0012] Based on the resource type of the display terminal, the safety digital twin standard model is lightweight compressed, and the lightweight safety digital twin standard model is displayed on the display terminal.

[0013] 4. Perform virtual roaming on the constructed secure digital twin standard model.

[0014] Specifically, based on the safety stage of the safety management model and the personnel safety digital twin standard model, a virtualized roaming body is constructed; using the virtualized roaming body, virtualized roaming is performed on the safety digital twin standard model to obtain virtualized roaming results corresponding to different construction stages.

[0015] 5. Based on the virtualized roaming results, early warnings are issued for potential safety hazards in the safety digital twin standard model, and the design data is corrected.

[0016] Specifically, the virtualized roaming results are analyzed, and warning information is output in real time for the reflected safety hazards, including personnel safety hazards, material safety hazards, and environmental safety hazards. The warning information is displayed through a display device, and a safety management report is output based on the safety management model and archived.

[0017] Corresponding to the security management method based on digital security twins, the present invention also provides a security management system based on digital security twins, including:

[0018] The initial construction unit builds a safe digital twin initial model of the construction process based on the design data.

[0019] The model building unit builds a safety management model based on the safety protection measures and safety protection specifications of the construction process.

[0020] Standardize and display units, build a safe digital twin standard model of the construction process, and display the safe digital twin standard model in a lightweight manner.

[0021] The virtualization roaming unit performs virtualization roaming on the constructed secure digital twin standard model.

[0022] The early warning and correction unit, based on the virtualized roaming results, warns of safety hazards in the safety digital twin standard model and corrects the design data.

[0023] The present invention also provides a security management device based on digital security twins, comprising a memory and a processor, the memory being used to store a computer program, and the processor being used to execute the computer program to implement the steps of the security management method based on digital security twins as described above.

[0024] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the security management method based on digital security twins as described above.

[0025] The safety management method based on digital safety twins provided by the present invention builds a safety digital twin initial model of the construction process based on design data, builds a safety management model based on the safety protection measures and specifications corresponding to the construction process, and then builds a safety digital twin standard model, uses a virtualized roaming body to perform virtualized roaming on the safety digital twin standard model, warns and outputs safety hazards in the roaming results, and corrects the design data. Based on different personnel characteristics, environmental characteristics, and stage characteristics, the present invention constructs a corresponding safety digital twin standard model and executes a corresponding virtualized roaming process, which can more accurately and efficiently complete the safety management process and warning output process of the engineering construction. Based on the resource type of the display terminal and different safety stages, the safety digital twin standard model is lightweight compressed and displayed, which can improve the accuracy and efficiency of the model display. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a flow chart of the security management method based on digital security twin of the present invention;

[0027] Figure 2 This is a system block diagram of the security management system based on digital security twins of the present invention. DETAILED DESCRIPTION

[0028] The present invention will be further described below in conjunction with the embodiments.

[0029] A safety management method and system based on digital safety twins is provided to improve the digital and intelligent level of the construction safety management process and ensure the safe and smooth progress of all stages of engineering construction.

[0030] like Figure 1 As shown, a security management method based on digital security twins includes the following steps:

[0031] 1. Build a safe digital twin initial model of the construction process based on design data.

[0032] Specifically, the design data includes design document data and BIM data, and the design document data and BIM data are processed to obtain construction personnel data, construction material data, construction environment data, and construction stage data;

[0033] Optionally, an initial safety digital twin model of the construction process can be constructed based on the real-time data generated during the construction process of the project that has already started. Specifically, it includes: arranging data acquisition equipment such as sensors and cameras for construction personnel, construction materials, construction environment and other elements, using the data acquisition equipment to collect data generated during the construction process in real time, and saving the collected data into the corresponding database; based on the collected data, constructing the initial personnel safety digital twin model corresponding to the construction personnel, the initial material safety digital twin model corresponding to the construction materials, and the initial environmental safety digital twin model corresponding to the construction environment.

[0034] 2. Build a safety management model based on the safety protection measures and safety protection specifications of the construction process.

[0035] Specifically, different types of projects and different stages of construction face different safety risks, so the safety protection measures and safety protection specifications that need to be taken are also different. Based on the project type of the current project, the safety protection measures and safety protection specifications corresponding to the project type are obtained, and based on the safety protection measures and safety protection specifications, a safety management model is constructed, and the safety management model is divided into different safety stages based on the project progress and construction stage.

[0036] Specifically, based on the security protection measures and security protection specifications, a security management model is constructed, including: performing semantic segmentation, parameterization and other processing on the security protection measures and security protection specifications to obtain model construction parameters that meet the conditions, and constructing a security management model based on the model construction parameters.

[0037] 3. Build a safety digital twin standard model of the construction process and display the safety digital twin standard model in a lightweight manner.

[0038] Specifically, different construction personnel, different construction materials, and different construction environments require different safety protection measures and protection specifications, and as the construction proceeds to different stages, the corresponding safety protection measures and protection specifications will also change accordingly. By mapping the safety management model divided into different safety stages to the personnel safety digital twin initial model, the material safety digital twin initial model, and the environmental safety digital twin initial model, a standardized safety digital twin standard model is obtained. The safety digital twin standard model includes a personnel safety digital twin standard model, a material safety digital twin standard model, and an environmental safety digital twin standard model; the safety digital twin standard model can accurately reflect the safety management status of personnel, materials, and environment during the construction stage.

[0039] Furthermore, based on the resource type and construction stage of the display terminal, the safety digital twin standard model is lightweight compressed, and the lightweight safety digital twin standard model is displayed at the display terminal, and different construction stages correspond to different display methods. The lightweight compression includes any one or more of model optimization, triangular face simplification, texture data compression, etc., and the present invention is not limited to this. Based on the resource type and construction stage of the display terminal, the safety digital twin standard model is lightweight compressed, including: adjusting the lightweight compression method based on the resource type and construction stage of different display terminals.

[0040] 4. Perform virtual roaming on the constructed secure digital twin standard model.

[0041] Different construction workers are in different construction stages, in different construction environments, and need to take different safety protection measures and specifications when performing construction operations on different construction materials. Based on the safety stage of the safety management model and the personnel safety digital twin standard model, a virtualized roaming body is constructed. The virtualized roaming body is divided into different roaming stages based on different construction stages. The virtualized roaming bodies of different roaming stages are used to perform roaming operations on the material safety digital twin standard model and the environmental safety digital twin standard model to obtain virtualized roaming results corresponding to different construction stages.

[0042] 5. Based on the virtualized roaming results, early warnings are issued for potential safety hazards in the safety digital twin standard model, and the design data is corrected.

[0043] Specifically, the virtualized roaming results corresponding to the different construction stages are analyzed to obtain analysis results, and the analysis results are displayed through a display device. When there are no safety hazards in the analysis results, the lightweight safety digital twin standard model is displayed; when there are safety hazards in the analysis results, the lightweight safety digital twin standard model and warning information are displayed. The warning information is real-time warning information reflecting the safety hazards, and the safety hazards include personnel safety hazards, material safety hazards, and environmental safety hazards.

[0044] Furthermore, the display method of the warning information is adjusted based on the different construction stages. Different construction personnel in different construction stages, in different construction environments, and when performing construction operations on different construction materials, need to take different safety protection measures and specifications. The display methods of the safety digital twin standard models corresponding to different construction stages are also different, and therefore the display methods of the warning information required are also different. Adjusting the display method of the warning information based on the construction stage can enable the safety hazards of the construction stage to be accurately displayed and corrected as soon as possible.

[0045] Furthermore, based on the analysis results and the safety management model, a safety management report is output and archived. Based on the analysis results, the safety report specifications corresponding to the safety management models at different safety stages are used to automatically generate and output a safety management report, and the safety management report is saved. Furthermore, the saved safety management report is used to generate an adjustment factor to adjust the design data, thereby eliminating construction hazards in a timely manner.

[0046] The method provided by the present invention constructs a safety digital twin initial model of the construction process based on design data, constructs a safety management model based on the safety protection measures and specifications corresponding to the construction process, and then constructs a safety digital twin standard model, performs virtualized roaming on the safety digital twin standard model using a virtualized roaming body, and warns and outputs safety hazards in the roaming results. The present invention constructs corresponding safety digital twin standard models and executes corresponding virtualized roaming processes based on different personnel characteristics, environmental characteristics, and stage characteristics, and can more accurately and efficiently complete the safety management process and warning output process of engineering construction. Based on the resource type of the display terminal and different safety stages, the safety digital twin standard model is lightweight compressed and displayed, which can improve the accuracy and efficiency of model display.

[0047] Corresponding to the security management method based on digital security twins, such as Figure 2 As shown, the present invention also provides a safety management system based on digital safety twins, including:

[0048] The initial construction unit builds a safe digital twin initial model of the construction process based on the design data.

[0049] The model building unit builds a safety management model based on the safety protection measures and safety protection specifications of the construction process.

[0050] Standardize and display units, build a safe digital twin standard model of the construction process, and display the safe digital twin standard model in a lightweight manner.

[0051] The virtualization roaming unit performs virtualization roaming on the constructed secure digital twin standard model.

[0052] The early warning and correction unit, based on the virtualized roaming results, warns of safety hazards in the safety digital twin standard model and corrects the design data.

[0053] The present invention also provides a security management device based on digital security twins, comprising a memory and a processor, the memory being used to store a computer program, and the processor being used to execute the computer program to implement the steps of the security management method based on digital security twins as described above.

[0054] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the security management method based on digital security twins as described above.

[0055] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A security management method based on digital security twins, comprising the following steps: Based on the design data, build a safe digital twin initial model of the construction process; Based on the safety protection measures and safety protection specifications of the construction process, a safety management model is constructed; specifically including: Performing semantic segmentation and parameterization processing on the security protection measures and security protection specifications to obtain model building parameters, and building a security management model based on the model building parameters; Construct a safety digital twin standard model of the construction process and display the safety digital twin standard model in a lightweight manner; Perform virtual roaming on the constructed secure digital twin standard model; Based on the virtual roaming results, early warnings are issued for potential safety hazards in the safety digital twin standard model, and the design data is corrected; Constructing an initial safety digital twin model of the construction process, specifically including: the design data includes design document data and BIM data, the design document data and BIM data are processed to obtain construction personnel data, construction material data, and construction environment data; constructing an initial personnel safety digital twin model corresponding to the construction personnel, constructing an initial material safety digital twin model corresponding to the construction materials, and constructing an initial environmental safety digital twin model corresponding to the construction environment; Performing virtualized roaming on the constructed safety digital twin standard model, specifically including: constructing a virtualized roaming body based on the safety stage of the safety management model and the personnel safety digital twin standard model, dividing the virtualized roaming body into different roaming stages based on different construction stages, and using the virtualized roaming bodies of different roaming stages to perform roaming operations on the material safety digital twin standard model and the environmental safety digital twin standard model to obtain virtualized roaming results corresponding to different construction stages; Based on the virtualized roaming results, early warning is given for safety hazards in the safety digital twin standard model, specifically including: analyzing the virtualized roaming results corresponding to the different construction stages to obtain analysis results, and displaying the analysis results through a display device; when there are no safety hazards in the analysis results, displaying the lightweight safety digital twin standard model; when there are safety hazards in the analysis results, displaying the lightweight safety digital twin standard model and early warning information, wherein the early warning information is early warning information reflecting the safety hazards, and the safety hazards include personnel safety hazards, material safety hazards, and environmental safety hazards; based on different construction stages, adjusting the display method of the early warning information; The design data is modified, specifically including: based on the analysis results, using the safety report specifications corresponding to the safety management models of the different safety stages, automatically generating and outputting a safety management report, and saving the safety management report; using the saved safety management report to generate an adjustment factor to adjust the design data.

2. The method according to claim 1, characterized in that Based on the safety protection measures and safety protection specifications of the construction process, a safety management model is constructed, including: Based on the project type of the current project, obtain the safety protection measures and safety protection specifications corresponding to the project type, build a safety management model based on the safety protection measures and safety protection specifications, and divide the safety management model into different safety stages based on the project progress and construction stage.

3. The method according to claim 1, characterized in that Construct a safety digital twin standard model for the construction process, including: The safety management model divided into different safety stages is mapped to the personnel safety digital twin initial model, the material safety digital twin initial model, and the environmental safety digital twin initial model to obtain a standardized safety digital twin standard model. The safety digital twin standard model includes a personnel safety digital twin standard model, a material safety digital twin standard model, and an environmental safety digital twin standard model.

4. The method according to claim 3, characterized in that The lightweight presentation of the safety digital twin standard model includes: Based on the resource type and construction stage of the display terminal, the safety digital twin standard model is lightweight compressed, and the lightweight safety digital twin standard model is displayed on the display terminal; The lightweight compression of the safety digital twin standard model based on the resource type and construction stage of the display terminal includes: adjusting the lightweight compression method based on the resource type and construction stage of different display terminals.

5. A safety management system based on digital safety twins, comprising: The initial construction unit builds a safe digital twin initial model of the construction process based on the design data; The model building unit builds a safety management model based on the safety protection measures and safety protection specifications of the construction process; specifically, it includes: performing semantic segmentation and parameterization processing on the safety protection measures and safety protection specifications to obtain model building parameters, and building a safety management model based on the model building parameters; Standardization and display unit, building a safety digital twin standard model of the construction process, and lightweight display of the safety digital twin standard model; A virtualized roaming unit, which performs virtualized roaming on the constructed secure digital twin standard model; The early warning and correction unit, based on the virtualized roaming results, warns of potential safety hazards in the safety digital twin standard model and corrects the design data; The model building unit is further used to: the design data includes design document data and BIM data, and the design document data and BIM data are processed to obtain construction personnel data, construction material data, and construction environment data; construct a personnel safety digital twin initial model corresponding to the construction personnel, construct a material safety digital twin initial model corresponding to the construction materials, and construct an environmental safety digital twin initial model corresponding to the construction environment; The virtualized roaming unit is further used to: construct a virtualized roaming body based on the safety stage of the safety management model and the personnel safety digital twin standard model, divide the virtualized roaming body into different roaming stages based on different construction stages, and use the virtualized roaming bodies of different roaming stages to perform roaming operations on the material safety digital twin standard model and the environmental safety digital twin standard model to obtain virtualized roaming results corresponding to different construction stages; The early warning correction unit is also used to: analyze the virtualization roaming results corresponding to the different construction stages to obtain analysis results, and display the analysis results through a display device; when there are no safety hazards in the analysis results, display the lightweight safety digital twin standard model; when there are safety hazards in the analysis results, display the lightweight safety digital twin standard model and early warning information, and the early warning information is early warning information reflecting the safety hazards, and the safety hazards include personnel safety hazards, material safety hazards, and environmental safety hazards; based on different construction stages, adjust the display method of the early warning information; based on the analysis results, use the safety report specifications corresponding to the safety management models of the different safety stages to automatically generate and output a safety management report, and save the safety management report; use the saved safety management report to generate an adjustment factor to adjust the design data.

6. A non-transitory computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the method according to any one of claims 1 to 4 when executed by a processor.