Method, device, computer equipment, readable storage medium and program product for determining slope stability of large-tonnage towers of power transmission lines

By determining the candidate influencing factors and optimizing the neural network model using the Pelican optimization algorithm, the accuracy problem of slope stability prediction around the transmission tower is solved, and the accurate evaluation of slope stability is achieved.

CN118551670BActive Publication Date: 2024-11-05MAINTENANCE & TEST CENTRE CSG EHV POWER TRANSMISSION CO
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411019443.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-05
Estimated Expiration
2044-07-29

AI Technical Summary

Technical Problem

The prior art is difficult to accurately predict the stability of the slope around the transmission tower, and fails to fully consider the impact of transmission tower line direction, line height difference and tower type on slope stability.

Method used

By determining candidate impact factors, including tower impact factors and slope disaster factors, the Pelican optimization algorithm is used to optimize the neural network model, and the target impact factors are processed to obtain the displacement of the cracks around the slope, thereby determining the degree of slope stability.

Benefits of technology

The accuracy of slope stability prediction is improved, and the impact of large-tonnage transmission towers on slope load can be fully considered, and the stability of the slope around the transmission tower can be accurately obtained.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118551670B_ABST
    Figure CN118551670B_ABST
Patent Text Reader

Abstract

The present application relates to a method, device, computer equipment, readable storage medium and program product for determining the slope stability of a large-tonnage transmission line tower. The method comprises: determining candidate influencing factors according to tower data and slope data, determining target influencing factors from the candidate influencing factors, using a neural network model optimized by the Pelican optimization algorithm to process the target influencing factors, obtaining the displacement of cracks around the slope, and determining the slope stability according to the displacement. The method can improve the prediction accuracy of the model, fully consider the influence of the slope load transmitted by the large-tonnage transmission tower on the slope stability, and accurately obtain the slope stability around the transmission tower.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of stability prediction, and in particular to a method, device, computer equipment, readable storage medium and program product for determining the slope stability of a large-tonnage tower of a transmission line. Background Art

[0002] The stability of the slope is closely related to the occurrence of geological disasters such as landslides. The factors that usually affect the occurrence of landslides include both internal factors of the slope, such as slope gradient, slope aspect, soil moisture, NDVI vegetation coverage index, etc. when the landslide occurs, and external factors of the slope, such as short-term heavy rainfall and earthquakes.

[0003] In the related technologies, most of the studies on the prediction of slope stability in mountainous areas have considered internal factors of the slope such as slope gradient, slope aspect, soil moisture, NDVI vegetation coverage, and external factors of the slope such as heavy rainfall and earthquakes. However, few of them have considered the influence of the direction of the transmission tower lines around the mountainous slopes, the line height difference, the tower type, etc. on the slope stability, making it impossible to accurately predict the stability of the slopes around the transmission towers. Summary of the invention

[0004] Based on this, it is necessary to provide a method, device, computer equipment, readable storage medium and program product for determining the slope stability of large-tonnage towers of transmission lines, which can accurately predict the slope stability around transmission towers, in response to the above technical problems.

[0005] In a first aspect, the present application provides a method for determining the slope stability of a large-tonnage tower of a transmission line, comprising:

[0006] Determine candidate influencing factors based on tower data and slope data; candidate influencing factors include tower influencing factors and slope hazard factors;

[0007] Determine the target impact factor from the candidate impact factors;

[0008] The neural network model optimized by the Pelican optimization algorithm is used to process the target influencing factors, obtain the displacement of cracks around the slope, and determine the stability of the slope based on the displacement.

[0009] In one embodiment, the step of determining candidate influencing factors based on tower data and slope data includes:

[0010] The location coordinates of the towers around the slope are obtained based on the tower data, and the tower visualization space is generated in GIS based on the location coordinates;

[0011] Obtain the direction of the tower line within a preset time period from the tower visualization space, and determine the tower type of the tower according to the direction of the tower line; the tower types include a straight tower with height difference along the slope of the line, a straight tower without height difference along the slope of the line, a straight tower with height difference in the vertical slope of the line, a straight tower without height difference in the vertical slope of the line, a tension tower with height difference along the slope of the line, a tension tower without height difference along the slope of the line, a tension tower with height difference in the vertical slope of the line, and a tension tower without height difference in the vertical slope of the line; each tower type is regarded as a tower influencing factor;

[0012] The slope factors that affect the slope stability are determined based on the slope data; the slope factors include short-term rainfall, earthquake, vegetation coverage index, soil moisture, slope gradient and slope direction; each slope factor is regarded as a slope hazard factor.

[0013] In one embodiment, the step of determining a target impact factor from candidate impact factors includes:

[0014] The principal component analysis of tower influence factors and slope hazard factors was performed respectively to obtain the corresponding tower influence ranking and slope hazard ranking;

[0015] The first four tower impact factors in the tower impact ranking and the first two slope hazard factors in the slope hazard ranking are selected as target impact factors.

[0016] In one embodiment, the optimization process of the neural network model includes:

[0017] Determine a matrix expression for a pelican population; the matrix expression is used to represent the individual position of each pelican in the pelican population; each pelican is used to represent a set of weights and thresholds for a neural network model;

[0018] Construct an objective function based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican;

[0019] Determine the expected number of iterations and expected output error of the Pelican optimization algorithm;

[0020] Iterate the Pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error;

[0021] The target function value is determined from the candidate function values ​​corresponding to all pelicans, and a set of weights and thresholds corresponding to the target function value are used as the weights and thresholds after the neural network model is optimized.

[0022] In one embodiment, the method further comprises:

[0023] In the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0024] In one embodiment, the method further comprises:

[0025] When the displacement is greater than a preset threshold, a slope warning message is generated according to the slope stability corresponding to the displacement;

[0026] When the displacement is less than or equal to a preset threshold, slope stability information is generated.

[0027] In a second aspect, the present application also provides a device for determining the slope stability of a large-tonnage tower of a transmission line, comprising:

[0028] A candidate determination module is used to determine candidate influencing factors according to tower data and slope data; the candidate influencing factors include tower influencing factors and slope hazard factors;

[0029] A target determination module, used for determining a target impact factor from candidate impact factors;

[0030] The stability determination module is used to process the target influencing factors using a neural network model optimized by the Pelican optimization algorithm, obtain the displacement of cracks around the slope, and determine the stability of the slope based on the displacement.

[0031] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the method steps of any one of the first aspects are implemented.

[0032] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, which implements any one of the method steps in the first aspect when the computer program is executed by a processor.

[0033] In a fifth aspect, the present application further provides a computer program product, comprising a computer program, which implements any one of the method steps in the first aspect when executed by a processor.

[0034] The above-mentioned method, device, computer equipment, computer-readable storage medium and computer program product for determining the slope stability of large-tonnage towers of transmission lines determine candidate influencing factors based on tower data and slope data, determine target influencing factors from the candidate influencing factors, use a neural network model optimized by the Pelican optimization algorithm to process the target influencing factors, obtain the displacement of cracks around the slope, and determine the slope stability based on the displacement. The neural network model is optimized based on the Pelican optimization algorithm to improve the prediction accuracy of the model. Combined with the tower data and slope data, it can fully consider the influence of the slope load transmitted by the large-tonnage transmission tower on the slope stability, and accurately obtain the slope stability around the transmission tower. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the related technologies, the drawings required for use in the embodiments of the present application or the related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0036] FIG1 is an application environment diagram of a method for determining the slope stability of a large-tonnage tower of a power transmission line in one embodiment;

[0037] FIG2 is a schematic flow chart of a method for determining the slope stability of a large-tonnage tower of a power transmission line in one embodiment;

[0038] FIG3 is a schematic flow chart of a method for determining the slope stability of a large-tonnage tower of a power transmission line in another embodiment;

[0039] FIG4 is a structural block diagram of a device for determining the slope stability of a large-tonnage tower of a power transmission line in one embodiment;

[0040] FIG. 5 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0042] The stability of slopes is closely related to the occurrence of geological disasters such as landslides. Landslides are one of the most serious natural disasters, and the causes of their occurrence are very complex. The factors that usually affect the occurrence of landslides include both internal factors of the slope, such as slope, slope direction, soil moisture, NDVI vegetation coverage index, etc., and external factors of the slope, such as short-term heavy rainfall, earthquakes, etc. In recent years, more and more power transmission line projects have passed through mountainous areas, and the impact of power transmission towers on the stability of mountain slopes has rarely been involved.

[0043] At present, most of the studies on slope stability prediction in mountainous areas have considered internal factors such as slope gradient, slope aspect, soil moisture, NDVI vegetation coverage, and external factors such as heavy rainfall and earthquakes. However, few have considered the impact of the direction of transmission tower lines around mountainous slopes, line height difference, tower type, etc. on slope stability. In addition, the current research on slope stability prediction using artificial intelligence methods such as BP neural networks still has the problem of being easy to fall into local optimality and slow convergence.

[0044] In view of the above problems, the embodiment of the present application proposes a method for determining the slope stability of a large-tonnage tower of a transmission line, which takes into account the effects of the transmission tower line direction, line height difference, tower type, etc., and considers the influence of the transmission tower, and divides the towers around the slope into 8 categories: straight towers with height difference along the slope of the line, straight towers without height difference along the slope of the line, straight towers with height difference in the vertical slope of the line, straight towers without height difference in the vertical slope of the line, tension towers with height difference along the slope of the line, tension towers without height difference along the slope of the line, tension towers with height difference in the vertical slope of the line, and tension towers without height difference in the vertical slope of the line. The principal component analysis (PCA) method is used to process samples of tower slope characteristics and screen the main tower slope influencing factors. The slope stability prediction model based on the Pelican Optimization Algorithm (POA)-BP neural network (Back propagation neural network, BPNN) is used to achieve accurate prediction of slope stability.

[0045] The method for determining the slope stability of a large-tonnage tower of a transmission line provided in an embodiment of the present application can be applied in an application environment as shown in FIG. 1 . Among them, the terminal 102 communicates with the server 104 through a network. The data storage system can store the data that the server 104 needs to process. The data storage system can be integrated on the server 104, or it can be placed on a cloud or other network server. Among them, the terminal 102 is used to obtain tower data and slope data from the server 104, determine candidate influencing factors based on the tower data and slope data, determine the target influencing factors from the candidate influencing factors, and use the neural network model optimized by the Pelican optimization algorithm to process the target influencing factors, obtain the displacement of the cracks around the slope, and determine the slope stability based on the displacement. Among them, the terminal 102 can be, but is not limited to, various personal computers, laptops, smart phones, tablet computers, Internet of Things devices and portable wearable devices, and the Internet of Things devices can be smart speakers, smart TVs, smart air conditioners, smart car-mounted devices, projection devices, etc. Portable wearable devices can be smart watches, smart bracelets, head-mounted devices, etc. The head mounted device may be a virtual reality (VR) device, an augmented reality (AR) device, smart glasses, etc. The server 104 may be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server providing cloud computing services.

[0046] In an exemplary embodiment, as shown in FIG2 , a method for determining the slope stability of a large-tonnage tower of a transmission line is provided, and the method is applied to the terminal 102 in FIG1 as an example for description, including the following steps 202 to 206. Among them:

[0047] S202: Determine candidate influencing factors according to the tower data and the slope data; the candidate influencing factors include tower influencing factors and slope hazard factors.

[0048] Optionally, the tower data includes the position coordinates of the large-tonnage towers of the transmission line, and the slope data includes the internal factors of the slope that affect the stability of the slope. Among them, the large-tonnage towers of the transmission line refer to the high-voltage direct current transmission towers, that is, the towers around the slope. Among them, the tower influencing factors include indicators related to the role of the tower, which usually include factors of the tower characteristics, and the slope hazard factors include external factors and internal factors of the slope that affect the stability of the slope, among which the external factors of the slope usually include external weather factors, and the internal factors of the slope usually include the stability parameters of the slope itself, such as soil moisture, slope and slope direction.

[0049] S204: Determine a target impact factor from the candidate impact factors.

[0050] Optionally, the target influencing factor is the main influencing factor affecting the slope stability. By performing principal component analysis on all candidate influencing factors, multiple correlated indicator variables are recombined into a new set of independent comprehensive indicator variables. These comprehensive indicator variables (i.e., principal components) can reflect the main information of the original variables (i.e., candidate influencing factors). Through dimensionality reduction, principal component analysis can reduce the number of predicted variables and ensure that these variables are independent of each other, which can simplify the data to be analyzed and ensure the accuracy of stability prediction.

[0051] S206: Using the neural network model optimized by the Pelican optimization algorithm, the target influencing factors are processed to obtain the displacement of cracks around the slope, and the slope stability is determined according to the displacement.

[0052] Optionally, the Pelican Optimization Algorithm (POA) is a heuristic intelligent optimization algorithm based on the foraging behavior of pelicans. By simulating the foraging behavior of pelicans, it can quickly converge to the vicinity of the optimal solution. Among them, the neural network model is a BP neural network model. By using the POA algorithm to optimize the parameters of the BP neural network to form an optimized POA-BP neural network model, the accuracy of the POA-BP neural network model can be ensured.

[0053] Optionally, the target influencing factor is the input data of the POA-BP neural network model, and the output is the displacement of cracks around the slope. The stability of the slope can be determined according to the displacement, which usually includes three types: stable, relatively stable and unstable.

[0054] In the above-mentioned method for determining the slope stability of large-tonnage towers of transmission lines, candidate influencing factors are determined based on tower data and slope data, target influencing factors are determined from the candidate influencing factors, and the target influencing factors are processed using a neural network model optimized by the Pelican optimization algorithm to obtain the displacement of cracks around the slope, and the slope stability is determined based on the displacement. The neural network model is optimized based on the Pelican optimization algorithm to improve the prediction accuracy of the model. Combined with the tower data and slope data, it can fully consider the influence of the slope load transmitted by the large-tonnage transmission tower on the slope stability, and accurately obtain the slope stability around the transmission tower.

[0055] In an exemplary embodiment, the step of determining candidate influencing factors based on tower data and slope data includes: obtaining the position coordinates of towers around the slope based on the tower data, and generating a tower visualization space in GIS based on the position coordinates; obtaining the tower line direction within a preset time period from the tower visualization space, and determining the tower type of the tower based on the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference perpendicular to the slope, straight towers without height difference perpendicular to the slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference perpendicular to the slope, and tension towers without height difference perpendicular to the slope; each tower type is regarded as a tower influencing factor; slope factors affecting slope stability are determined based on the slope data; slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is regarded as a slope hazard factor.

[0056] Optionally, according to the position coordinates of the towers around the slope, a tower visualization space can be generated in GIS, in which the tower logo can be displayed, and the line direction of the tower can be determined. At the same time, the internal factors of the slope can be analyzed through the GIS system. Based on the GIS system, a remote monitoring system for the slope and the towers around the slope can be established. By collecting the line direction of the towers within a specified time period, the towers are divided into 8 categories as 8 tower influencing factors of the tower effect. Similarly, by collecting the external factors of the slope within a specified time period and combining the internal factors of the slope, 6 slope disaster factors are used as disaster effects.

[0057] Optionally, the direction of the transmission tower line is determined by dynamic measurement using GPS integrated aerial survey technology. When the angle between the line direction and the slope is between 0° and 45°, the line is determined to be along the slope; when the angle between the line direction and the slope is between 45° and 90°, the line is determined to be perpendicular to the slope; the line height difference is determined by a total station. When the vertical height difference angle formed by two adjacent towers is between 0° and 20°, the line is determined to have no height difference; when the vertical height difference angle formed by two adjacent towers is between 20° and 80°, the line is determined to have a height difference; the types of towers are divided into straight towers and tension towers, which are determined according to the design specifications of the pole towers.

[0058] In this embodiment, by determining candidate influencing factors based on tower data and slope data, it is possible to combine tower data and slope data, fully consider the impact of transmission towers on slope stability, and accurately obtain the stability of slopes around transmission towers.

[0059] In an exemplary embodiment, the step of determining the target influencing factor from the candidate influencing factors includes: performing principal component analysis on the tower influencing factors and the slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings; selecting the first four tower influence factors in the tower influence rankings and the first two slope hazard factors in the slope hazard rankings as target influencing factors.

[0060] Optionally, the principal component analysis method is used to rank the tower influencing factors and slope hazard factors respectively, and the top four tower influencing factors in the tower influencing ranking and the top two slope hazard factors in the slope hazard ranking are selected as the target influencing factors that mainly affect slope stability.

[0061] In some embodiments, principal component analysis can be implemented through statistical analysis software, and the data corresponding to the 8 types of tower influencing factors are imported into the statistical analysis software, the index value data is preprocessed, the index value data after processing is calculated, and then the principal component analysis method is used to eliminate the problem of information overlap, and the index data is processed for data dimension reduction to obtain the corresponding tower influence ranking. Similarly, the data corresponding to the 6 types of slope hazard factors are imported into the statistical analysis software, the index value data is preprocessed, the index value data after processing is calculated, and then the principal component analysis method is used to eliminate the problem of information overlap, and the index data is processed for data dimension reduction to obtain the corresponding slope hazard ranking.

[0062] In this embodiment, principal component analysis is performed on tower influencing factors and slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings. The first four tower influence factors in the tower influence rankings and the first two slope hazard factors in the slope hazard rankings are selected as target influencing factors. This can screen out the main influencing factors affecting slope stability and improve the accuracy of the determined slope stability.

[0063] In an exemplary embodiment, the optimization process of the neural network model includes: determining a matrix expression for a pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds of the neural network model; constructing an objective function based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; determining the expected number of iterations and expected output error of the pelican optimization algorithm; iteratively solving the pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; determining the objective function value from the candidate function values ​​corresponding to all pelicans, and using the set of weights and thresholds corresponding to the objective function value as the weights and thresholds after the optimization of the neural network model.

[0064] Optionally, taking the neural network model as a BP neural network as an example, first, it is necessary to determine the structure of the BP neural network, including input layer nodes, output layer nodes and hidden layer nodes. Among them, since the target influencing factors include 4 tower influencing factors and 2 slope hazard factors, there are a total of 6 types of input data, and the output is the displacement of the cracks in the towers around the slope. Therefore, the number of input layer nodes of the BP neural network is 6, and the number of output layer nodes is 1.

[0065] Furthermore, the number of hidden layer nodes is related to the number of input layer nodes and the number of output layer nodes, as shown in the following formula:

[0066]

[0067] Among them, m is the number of hidden layer nodes, n is the number of input layer nodes, l is the number of output layer nodes, and α is the adjustment constant, usually 1~10.

[0068] Furthermore, the Pelican Optimization Algorithm (POA) is used to optimize the weights and thresholds of the BP neural network, and the optimal weights and thresholds are found in the solution space, thereby improving the performance of the BP neural network. In the BP neural network, the weights represent the connection strength between each neuron, and the threshold represents that the neuron will be activated only when the input signal reaches a certain value. By adjusting these two parameters, the output of the network can be closer to the actual value, thereby improving the performance of the network.

[0069] Specifically, we first need to initialize the POA parameters, where the pelican population can be represented in the form of a matrix. The matrix expression X of the pelican population is as follows:

[0070]

[0071] Among them, X i is the individual position of the i-th pelican, represents each candidate solution in the solution space (i.e., a set of candidate weights and thresholds), X i,j represents the j-dimensional position of the i-th pelican.

[0072] Furthermore, for each pelican’s position x within the population i,j Perform random initialization, the initialization formula is as follows:

[0073]

[0074] Where i=1,2,…,n, j=1,2,…,m, rand is a random number in the range [0,1], u j and l j are the upper and lower boundaries of the population dimension j to be optimized.

[0075] Furthermore, in POA, each pelican can be regarded as a candidate solution to the problem being solved. Therefore, the objective function of the given problem can be evaluated based on each candidate solution. The objective function is constructed based on the matrix expression, and its expression is as follows:

[0076]

[0077] Among them, F is the objective function vector, F i is the candidate function value corresponding to the i-th pelican.

[0078] Optionally, in order to ensure the optimization effect of the Pelican optimization algorithm, it is necessary to determine the expected number of iterations and the expected output error of the Pelican optimization algorithm. When the expected number of iterations is reached or the output value of the objective function is less than or equal to the expected output error, the algorithm stops. The optimal candidate function value of the individuals in the current Pelican population is used as the objective function value, and a set of optimal weights and thresholds are obtained as the weights and thresholds for initializing the BP neural network.

[0079] In this embodiment, by optimizing the neural network model based on the Pelican optimization algorithm, the prediction accuracy of the model can be improved. The optimized neural network model is prone to fall into the local optimum and has a slow convergence speed, so as to accurately obtain the stability of the slope around the transmission tower.

[0080] In an exemplary embodiment, the method also includes: in the process of iteratively solving the pelican optimization algorithm, updating the candidate function value corresponding to the pelican according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0081] Optionally, in the process of iteratively solving the pelican optimization algorithm, the search characteristics of the pelican population are considered. In order to simulate the global search process of the pelican, the individual position of the pelican can be expressed as:

[0082]

[0083] in, is the position of the i-th pelican in the j-th dimension, x i,j is the j-dimensional position of the i-th pelican, P j is the j-th dimension position of the pelican prey, I is a random integer with a value of 1 or 2, F p is the objective function value corresponding to the pelican prey, F i is the candidate function value corresponding to the i-th pelican, and rand is a random number in the range [0,1]. It should be noted that the pelican prey represents the optimal solution that the algorithm wants to find in the search space, that is, the optimal set of weights and weights.

[0084] Furthermore, to simulate the local search process of the pelican, the individual position of the pelican can be expressed as:

[0085]

[0086] in, is the position of the ith pelican in the jth dimension, R is a constant of 0.2, t is the current iteration number, t max is the maximum number of iterations set, and rand is a random number in the range of [0,1].

[0087] In this embodiment, by updating the corresponding candidate function value of the pelican according to the current individual position of the pelican and the preset simulation coefficient during the iterative solution of the pelican optimization algorithm, the optimization effect of the pelican optimization algorithm can be improved, thereby accurately obtaining the stability of the slope around the transmission tower.

[0088] In an exemplary embodiment, the method further includes: generating slope warning information according to the slope stability corresponding to the displacement when the displacement is greater than a preset threshold; and generating slope stability information when the displacement is less than or equal to the preset threshold.

[0089] Optionally, for the displacement output by the neural network model, feedback information can be quickly generated by setting a threshold. For example, when the displacement is less than or equal to a preset threshold, the slope is considered to be in a stable state, and no stability analysis is required, and slope stability information is directly generated. When the displacement is greater than the preset threshold, different levels of slope warning information can be generated according to the slope stability corresponding to the current displacement, to prompt relevant personnel to perform maintenance.

[0090] In this embodiment, when the displacement is greater than a preset threshold, slope warning information is generated according to the slope stability corresponding to the displacement, and when the displacement is less than or equal to the preset threshold, slope stability information is generated, so that the state of the slope can be fed back in time to ensure the stability of the slope.

[0091] In an exemplary embodiment, as shown in FIG3 , a method for determining the slope stability of a large-tonnage tower of a transmission line is provided, the method comprising the following steps:

[0092] The location coordinates of the towers around the slope are obtained according to the tower data, and the tower visualization space is generated in GIS according to the location coordinates; the tower line direction within the preset time period is obtained from the tower visualization space, and the tower type of the tower is determined according to the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference perpendicular to the slope, straight towers without height difference perpendicular to the slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference perpendicular to the slope, and tension towers without height difference perpendicular to the slope; each tower type is regarded as a tower influencing factor; the slope factors affecting the slope stability are determined according to the slope data; the slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is regarded as a slope hazard factor.

[0093] Principal component analysis was performed on tower influencing factors and slope hazard factors respectively to obtain the corresponding tower influence ranking and slope hazard ranking; the first four tower influencing factors in the tower influence ranking and the first two slope hazard factors in the slope hazard ranking were selected as target influencing factors.

[0094] Determine a matrix expression for the pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds of the neural network model; construct an objective function based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; determine the expected number of iterations and the expected output error of the pelican optimization algorithm; iteratively solve the pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; determine the objective function value from the candidate function values ​​corresponding to all pelicans, and use the set of weights and thresholds corresponding to the objective function value as the weights and thresholds after the optimization of the neural network model.

[0095] The neural network model optimized by the Pelican optimization algorithm is used to process the target influencing factors, obtain the displacement of cracks around the slope, and determine the stability of the slope based on the displacement.

[0096] In the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0097] When the displacement is greater than a preset threshold, slope warning information is generated according to the slope stability corresponding to the displacement; when the displacement is less than or equal to the preset threshold, slope stability information is generated.

[0098] In this embodiment, candidate influencing factors are determined based on tower data and slope data, and target influencing factors are determined from the candidate influencing factors. The target influencing factors are processed using a neural network model optimized by the Pelican optimization algorithm to obtain the displacement of cracks around the slope, and the slope stability is determined based on the displacement. The neural network model is optimized based on the Pelican optimization algorithm to improve the prediction accuracy of the model. Combined with the tower data and slope data, it can fully consider the impact of the slope load transmitted by the large-tonnage transmission tower on the slope stability, and accurately obtain the slope stability around the transmission tower.

[0099] It should be understood that, although the steps in the flowcharts involved in the above embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above embodiments may include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0100] Based on the same inventive concept, the embodiment of the present application also provides a device for determining the stability of the slope of a large-tonnage pole tower of a transmission line, which is used to implement the above-mentioned method for determining the stability of the slope of a large-tonnage pole tower of a transmission line. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above-mentioned method, so the specific limitations in the embodiments of one or more devices for determining the stability of the slope of a large-tonnage pole tower of a transmission line provided below can refer to the limitations of the method for determining the stability of the slope of a large-tonnage pole tower of a transmission line above, and will not be repeated here.

[0101] In an exemplary embodiment, as shown in FIG4 , a device for determining the slope stability of a large-tonnage tower of a transmission line is provided, comprising: a candidate determination module 10, a target determination module 20 and a stability determination module 30, wherein:

[0102] The candidate determination module 10 is used to determine candidate influencing factors according to the tower data and the slope data; the candidate influencing factors include tower influencing factors and slope hazard factors.

[0103] The target determination module 20 is used to determine a target impact factor from candidate impact factors.

[0104] The stability determination module 30 is used to process the target influencing factors using a neural network model optimized by the Pelican optimization algorithm, obtain the displacement of cracks around the slope, and determine the stability of the slope according to the displacement.

[0105] In an exemplary embodiment, the candidate determination module 10 is also used to obtain the position coordinates of the towers around the slope according to the tower data, and generate a tower visualization space in the GIS according to the position coordinates; obtain the tower line direction within a preset time period from the tower visualization space, and determine the tower type of the tower according to the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference perpendicular to the slope, straight towers without height difference perpendicular to the slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference perpendicular to the slope, and tension towers without height difference perpendicular to the slope; each tower type is used as a tower influencing factor; slope factors affecting slope stability are determined according to the slope data; slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is used as a slope hazard factor.

[0106] In an exemplary embodiment, the target determination module 20 is also used to perform principal component analysis on the tower influence factors and slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings; the first four tower influence factors in the tower influence rankings and the first two slope hazard factors in the slope hazard rankings are selected as target influence factors.

[0107] In an exemplary embodiment, the stability determination module 30 is also used to determine a matrix expression for a pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds for a neural network model; an objective function is constructed based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; the expected number of iterations and the expected output error of the pelican optimization algorithm are determined; the pelican optimization algorithm is iteratively solved until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; the objective function value is determined from the candidate function values ​​corresponding to all pelicans, and the set of weights and thresholds corresponding to the objective function value are used as the weights and thresholds after the neural network model is optimized.

[0108] In an exemplary embodiment, the stability determination module 30 is also used to update the candidate function value corresponding to the pelican according to the current individual position of the pelican and the preset simulation coefficient during the iterative solution of the pelican optimization algorithm; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0109] In an exemplary embodiment, the stability determination module 30 is also used to generate slope warning information according to the slope stability corresponding to the displacement when the displacement is greater than a preset threshold; and to generate slope stability information when the displacement is less than or equal to the preset threshold.

[0110] Each module in the above-mentioned device for determining the slope stability of a large-tonnage tower of a transmission line can be implemented in whole or in part by software, hardware, or a combination thereof. Each of the above-mentioned modules can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute operations corresponding to each of the above modules.

[0111] In an exemplary embodiment, a computer device is provided, which may be a terminal, and its internal structure diagram may be shown in FIG5. The computer device includes a processor, a memory, an input / output interface, a communication interface, a display unit, and an input device. The processor, the memory, and the input / output interface are connected via a system bus, and the communication interface, the display unit, and the input device are connected to the system bus via the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner may be implemented through WIFI, a mobile cellular network, near field communication (NFC) or other technologies. When the computer program is executed by the processor, a method for determining the slope stability of a large-tonnage tower of a transmission line is implemented. The display unit of the computer device is used to form a visually visible picture, and can be a display screen, a projection device, or a virtual reality imaging device. The display screen can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covered on the display screen, or a key, trackball, or touchpad provided on the computer device housing, or an external keyboard, touchpad, or mouse, etc.

[0112] Those skilled in the art will understand that the structure shown in FIG. 5 is merely a block diagram of a partial structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than shown in the figure, or combine certain components, or have a different arrangement of components.

[0113] In an exemplary embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and the processor implements the following steps when executing the computer program: determining candidate influencing factors based on tower data and slope data; the candidate influencing factors include tower influencing factors and slope hazard factors; determining target influencing factors from the candidate influencing factors; using a neural network model optimized by the Pelican optimization algorithm to process the target influencing factors, obtain the displacement of cracks around the slope, and determine the stability of the slope based on the displacement.

[0114] In one embodiment, the processor determines candidate influencing factors based on tower data and slope data when executing a computer program, including: obtaining position coordinates of towers around the slope based on the tower data, and generating a tower visualization space in the GIS based on the position coordinates; obtaining the tower line direction within a preset time period from the tower visualization space, and determining the tower type of the tower based on the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference in the vertical slope, straight towers without height difference in the vertical slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference in the vertical slope, and tension towers without height difference in the vertical slope; each tower type is used as a tower influencing factor; slope factors affecting slope stability are determined based on the slope data; slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is used as a slope hazard factor.

[0115] In one embodiment, the processor determines the target influencing factor from the candidate influencing factors when executing the computer program, including: performing principal component analysis on the tower influencing factors and the slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings; selecting the first 4 tower influence factors in the tower influence rankings and the first 2 slope hazard factors in the slope hazard rankings as target influencing factors.

[0116] In one embodiment, the optimization process of the neural network model involved in the execution of the computer program by the processor includes: determining a matrix expression of a pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds of the neural network model; constructing an objective function according to the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; determining the expected number of iterations and expected output error of the pelican optimization algorithm; iteratively solving the pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; determining the objective function value from the candidate function values ​​corresponding to all pelicans, and using the set of weights and thresholds corresponding to the objective function value as the weights and thresholds after the optimization of the neural network model.

[0117] In one embodiment, the processor also implements the following steps when executing the computer program: in the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0118] In one embodiment, when the processor executes the computer program, the following steps are also implemented: when the displacement is greater than a preset threshold, slope warning information is generated according to the slope stability corresponding to the displacement; when the displacement is less than or equal to the preset threshold, slope stability information is generated.

[0119] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the following steps are implemented: candidate influencing factors are determined based on tower data and slope data; the candidate influencing factors include tower influencing factors and slope hazard factors; a target influencing factor is determined from the candidate influencing factors; a neural network model optimized by the Pelican optimization algorithm is used to process the target influencing factor to obtain the displacement of cracks around the slope, and the slope stability is determined based on the displacement.

[0120] In one embodiment, when the computer program is executed by a processor, the steps involved in determining candidate influencing factors based on tower data and slope data include: obtaining the position coordinates of towers around the slope based on the tower data, and generating a tower visualization space in the GIS based on the position coordinates; obtaining the tower line direction within a preset time period from the tower visualization space, and determining the tower type of the tower based on the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference perpendicular to the slope, straight towers without height difference perpendicular to the slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference perpendicular to the slope, and tension towers without height difference perpendicular to the slope; each tower type is regarded as a tower influencing factor; slope factors affecting slope stability are determined based on the slope data; slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is regarded as a slope hazard factor.

[0121] In one embodiment, when a computer program is executed by a processor, the steps involved in determining a target influencing factor from candidate influencing factors include: performing principal component analysis on tower influencing factors and slope hazard factors respectively to obtain corresponding tower influencing rankings and slope hazard rankings; selecting the first four tower influencing factors in the tower influencing rankings and the first two slope hazard factors in the slope hazard rankings as target influencing factors.

[0122] In one embodiment, the optimization process of the neural network model involved when the computer program is executed by the processor includes: determining a matrix expression of a pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds of the neural network model; constructing an objective function based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; determining the expected number of iterations and expected output error of the pelican optimization algorithm; iteratively solving the pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; determining the objective function value from the candidate function values ​​corresponding to all pelicans, and using the set of weights and thresholds corresponding to the objective function value as the weights and thresholds after the optimization of the neural network model.

[0123] In one embodiment, when the computer program is executed by the processor, the following steps are also implemented: in the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0124] In one embodiment, when the computer program is executed by the processor, the following steps are also implemented: when the displacement is greater than a preset threshold, slope warning information is generated according to the slope stability corresponding to the displacement; when the displacement is less than or equal to the preset threshold, slope stability information is generated.

[0125] In one embodiment, a computer program product is provided, including a computer program, which implements the following steps when executed by a processor: determining candidate influencing factors based on tower data and slope data; the candidate influencing factors include tower influencing factors and slope hazard factors; determining target influencing factors from the candidate influencing factors; using a neural network model optimized by the Pelican optimization algorithm to process the target influencing factors, obtain the displacement of cracks around the slope, and determine the stability of the slope based on the displacement.

[0126] In one embodiment, when the computer program is executed by a processor, the steps involved in determining candidate influencing factors based on tower data and slope data include: obtaining the position coordinates of towers around the slope based on the tower data, and generating a tower visualization space in the GIS based on the position coordinates; obtaining the tower line direction within a preset time period from the tower visualization space, and determining the tower type of the tower based on the tower line direction; the tower types include straight towers with height difference along the slope, straight towers without height difference along the slope, straight towers with height difference perpendicular to the slope, straight towers without height difference perpendicular to the slope, tension towers with height difference along the slope, tension towers without height difference along the slope, tension towers with height difference perpendicular to the slope, and tension towers without height difference perpendicular to the slope; each tower type is regarded as a tower influencing factor; slope factors affecting slope stability are determined based on the slope data; slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is regarded as a slope hazard factor.

[0127] In one embodiment, when a computer program is executed by a processor, the steps involved in determining a target influencing factor from candidate influencing factors include: performing principal component analysis on tower influencing factors and slope hazard factors respectively to obtain corresponding tower influencing rankings and slope hazard rankings; selecting the first four tower influencing factors in the tower influencing rankings and the first two slope hazard factors in the slope hazard rankings as target influencing factors.

[0128] In one embodiment, the optimization process of the neural network model involved when the computer program is executed by the processor includes: determining a matrix expression of a pelican population; the matrix expression is used to characterize the individual position of each pelican in the pelican population; each pelican is used to characterize a set of weights and thresholds of the neural network model; constructing an objective function based on the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; determining the expected number of iterations and expected output error of the pelican optimization algorithm; iteratively solving the pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; determining the objective function value from the candidate function values ​​corresponding to all pelicans, and using the set of weights and thresholds corresponding to the objective function value as the weights and thresholds after the optimization of the neural network model.

[0129] In one embodiment, when the computer program is executed by the processor, the following steps are also implemented: in the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

[0130] In one embodiment, when the computer program is executed by the processor, the following steps are also implemented: when the displacement is greater than a preset threshold, slope warning information is generated according to the slope stability corresponding to the displacement; when the displacement is less than or equal to the preset threshold, slope stability information is generated.

[0131] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, an artificial intelligence (AI) processor, etc., but are not limited to this.

[0132] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.

[0133] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A method for determining the slope stability of a large-tonnage tower of a transmission line, characterized in that: The method comprises: Obtaining the position coordinates of the towers around the slope according to the tower data, and generating a tower visualization space in the GIS according to the position coordinates; Obtain the direction of the tower line within a preset time period from the tower visualization space, and determine the tower type of the tower according to the tower line direction; the tower types include a straight tower with height difference along the slope of the line, a straight tower without height difference along the slope of the line, a straight tower with height difference in the vertical slope of the line, a straight tower without height difference in the vertical slope of the line, a tension tower with height difference along the slope of the line, a tension tower without height difference along the slope of the line, a tension tower with height difference in the vertical slope of the line, and a tension tower without height difference in the vertical slope of the line; each tower type is used as a tower influencing factor; Determine the slope factors affecting the slope stability according to the slope data; the slope factors include short-term rainfall, earthquake, vegetation cover index, soil moisture, slope and slope direction; each slope factor is regarded as a slope hazard factor; the slope data includes the internal factors of the slope affecting the slope stability; the position coordinates are used to display the tower logo in the tower visualization space generated in the GIS system, and the GIS system is used to analyze the internal factors of the slope and to establish a remote monitoring system for the slope and the towers around the slope; Performing principal component analysis on the tower influence factors and the slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings; The first four tower impact factors in the tower impact ranking and the first two slope hazard factors in the slope hazard ranking are selected as target impact factors; the target impact factors are the main impact factors affecting slope stability; The target influencing factors are processed by using a neural network model optimized by the Pelican optimization algorithm to obtain the displacement of cracks around the slope, and the slope stability is determined based on the displacement.

2. The method according to claim 1, characterized in that The optimization process of the neural network model includes: Determine a matrix expression of a pelican population; the matrix expression is used to represent the individual position of each pelican in the pelican population; each pelican is used to represent a set of weights and thresholds of the neural network model; Constructing an objective function according to the matrix expression; the objective function is used to characterize the candidate function value corresponding to each pelican; Determining an expected number of iterations and an expected output error of the Pelican optimization algorithm; Iteratively solving the Pelican optimization algorithm until the current number of iterations reaches the expected number of iterations or the output value of the objective function is less than or equal to the expected output error; The objective function value is determined from the candidate function values ​​corresponding to all pelicans, and a set of weights and thresholds corresponding to the objective function value are used as the weights and thresholds after the neural network model is optimized.

3. The method according to claim 2, characterized in that The method further comprises: In the process of iteratively solving the pelican optimization algorithm, the candidate function value corresponding to the pelican is updated according to the current individual position of the pelican and the preset simulation coefficient; the preset simulation coefficient is used to characterize the local search process of the pelican.

4. The method according to claim 1, characterized in that: The method further comprises: When the displacement is greater than a preset threshold, generating slope warning information according to the slope stability corresponding to the displacement; When the displacement is less than or equal to a preset threshold, slope stability information is generated.

5. A device for determining the slope stability of a large-tonnage tower of a transmission line, characterized in that: The device comprises: The candidate determination module is used to obtain the position coordinates of the towers around the slope according to the tower data, and generate a tower visualization space in the GIS according to the position coordinates; obtain the tower line direction within a preset time period from the tower visualization space, and determine the tower type of the tower according to the tower line direction; the tower types include a straight tower with height difference along the slope of the line, a straight tower without height difference along the slope of the line, a straight tower with height difference in the vertical slope of the line, a straight tower without height difference in the vertical slope of the line, a tension tower with height difference along the slope of the line, a tension tower without height difference along the slope of the line, a tension tower with height difference in the vertical slope of the line, and a line Vertical slope direction non-height difference tension tower; each tower type is used as a tower influencing factor; slope factors affecting slope stability are determined based on slope data; the slope factors include short-term rainfall, earthquake, vegetation coverage index, soil moisture, slope and slope direction; each slope factor is used as a slope hazard factor; the slope data includes internal factors of the slope that affect slope stability; the position coordinates are used to display the tower logo in the tower visualization space generated in the GIS system, and the GIS system is used to analyze the internal factors of the slope and to establish a remote monitoring system for the slope and the towers around the slope; A target determination module is used to perform principal component analysis on the tower influence factors and the slope hazard factors respectively to obtain corresponding tower influence rankings and slope hazard rankings; the first four tower influence factors in the tower influence rankings and the first two slope hazard factors in the slope hazard rankings are selected as target influence factors; the target influence factors are the main influencing factors affecting slope stability; The stability determination module is used to process the target influencing factors using a neural network model optimized by the Pelican optimization algorithm to obtain the displacement of cracks around the slope and determine the stability of the slope according to the displacement.

6. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 4 are implemented.

7. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 4 are implemented.

8. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 4 are implemented.

Citation Information

Patent Citations

  • Landslide and collapse disaster classification method and electronic equipment

    CN114881454A

  • Inversion method for position and intensity of carbon dioxide emission source in industrial park

    CN115879367A

  • Power transmission line slope operation and maintenance management system based on Beidou No.3 and implementation method

    CN118396594A

  • Construction method of tower structure

    JP2002030615A

  • Mountainous area slope displacement prediction method based on mi-GRA and improved PSO-lstm

    WO2024001942A1