A tunnel surrounding rock pre-support device and support method in karst area and fault fracture zone

By using a combination of keel steel and steel beam mechanism in the karst zone and fault crushing belt tunnel, an arc-shaped support device is designed to solve the problem of deformation stress of surrounding rocks and improve the stability and safety of the equipment.

CN118564266BActive Publication Date: 2024-11-22SHANDONG LUQIAO GROUP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411045668.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-22
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

In karst zones and fault crushing zone tunnels, existing support structures cannot effectively eliminate the stress caused by deformation of surrounding rocks, resulting in equipment damage and reduced safety.

Method used

A surrounding rock pre-support device including keel steel, support mechanism, reinforcement beam mechanism and tension mechanism is designed. Through the arc arrangement of the support mechanism and the use of flexible fillers, concrete support is formed to buffer the collapse and deformation of the surrounding rock. Increase protection strength and stability.

Benefits of technology

It effectively avoids excessive stress and impact force caused by surrounding rock deformation, improves the protection stability and safety of the equipment, and extends the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118564266B_ABST
    Figure CN118564266B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of tunnel engineering, and in particular to a surrounding rock pre-support device and a supporting method for tunnels in karst areas and fault fracture zones. It comprises a plurality of keel steels, a plurality of supporting mechanisms are arranged between the plurality of keel steels, two tension mechanisms are arranged on the supporting mechanisms, a plurality of steel bar bundle mechanisms are arranged between the plurality of keel steels, a plurality of the steel bar bundle mechanisms are located between every two supporting mechanisms, and two bottom fixing mechanisms are arranged between the plurality of keel steels, and the bottom fixing mechanisms are located at both ends of the keel steels. The present invention increases the strength of protection, and can avoid excessive impact on the keel steel when the surrounding rock is deformed, thereby causing damage to the keel steel and subsequent collapse of the equipment, further improving the protection stability of the equipment, indirectly buffering the stress and impact force on the equipment, thereby improving the stability and safety of the equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel engineering, and in particular to a tunnel surrounding rock pre-support device and a supporting method in a karst area and a fault fracture zone. Background Art

[0002] Tunnels in karst areas should adopt information technology design and construction, do a good job in advanced geological forecasting, strengthen support, and ensure tunnel safety. If necessary, the surrounding rock level should be appropriately adjusted according to the actual geological conditions after excavation. For local erosion fissures, small caves, karst grooves (troughs), etc., which are generally small in scale, landfill, spanning and other measures can be taken to deal with them. Generally, surrounding rock and caves will be encountered during tunnel construction. For the safe expansion of tunnels, people will support the tunnel area to prevent blocky foreign objects from falling from the surrounding rock or to avoid tunnel collapse. The existing tunnel support structure generally includes primary lining and secondary lining. The primary lining is the initial support formed by anchor rods, mesh hanging, shotcrete and other means after tunnel excavation. This initial support mainly uses the strength of the surrounding rock to form support; the secondary lining uses reinforced concrete to form a complete steel lining inside the primary lining. Reinforced concrete structure, this protection method still has some disadvantages when used. When the surrounding rock is supported by anchor rod hanging net method, the keel frame and the surrounding rock are in a fitted state, and people are pouring concrete. The concrete is fitted and bonded to the surrounding rock. When the bottom of the surrounding rock is hollowed out, the gravity at the top of the mountain will form a pressure on the lower side. When the surrounding rock is pressed down and deformed, it will cause a stress and impact force to form between the concrete and the surrounding rock. When the surrounding rock and concrete are fitted, there is no gap between the two and no space left for the surrounding rock to deform, which may cause increased stress, thereby causing the support equipment to deform, resulting in inadequate support, which in turn affects the safe use of the equipment.

[0003] Therefore, in view of the above problems, a tunnel surrounding rock pre-support device and a support method for karst areas and fault fracture zones are proposed to solve the above problems. Summary of the invention

[0004] The present invention develops a tunnel surrounding rock pre-support device and support method in karst areas and fault fracture zones to solve the problem in the above background technology that the rock mass deforms and the stress generated by the deformation cannot be fully eliminated, resulting in equipment damage and reduced safety.

[0005] The technical solution to the technical problem solved by the present invention is as follows: on the one hand, a tunnel surrounding rock pre-support device for a karst area and a fault fracture zone is provided, which includes a plurality of keel steels, a plurality of supporting mechanisms are arranged between the plurality of keel steels, two tensioning mechanisms are arranged on the supporting mechanisms, a plurality of steel bar bundle mechanisms are arranged between the plurality of keel steels, the plurality of steel bar bundle mechanisms are located between every two supporting mechanisms, two bottom fixing mechanisms are arranged between the plurality of keel steels, and the bottom fixing mechanisms are located at both ends of the keel steels.

[0006] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, the supporting mechanism includes a fixed shell, a slide groove, a first force-bearing mechanism and a second force-bearing mechanism. The fixed shell is slidably connected between the keel steels. The fixed shell and the keel steel are fixed by bolts. A slide groove is opened in the fixed shell, and a first force-bearing mechanism is arranged in the fixed shell.

[0007] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, the first force-bearing mechanism includes a first sliding column, a first spring, a downward pressure block and a first force plate. The first sliding column is connected to the fixed shell, and the first sliding column is sleeved with a first spring. The first sliding column is located in the fixed shell and a downward pressure block is installed at one end. The downward pressure block is wedge-shaped. The other end of the first sliding column is installed with a first force plate, and the first force plate is arc-shaped.

[0008] On the basis of the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, two second force-bearing mechanisms are provided on the fixed shell, the second force-bearing mechanisms are located on both sides of the first force-bearing mechanism, the second force-bearing mechanism includes a push block, a second spring, a second sliding column, a third spring, an ejection block and a second force plate, the two push blocks are slidably connected in the slide groove, one side and the top of the push block are wedge-shaped, the push block and the lower pressure block are movably connected, the second spring is fixedly connected between the push block and one side of the slide groove, the two second sliding columns are connected to the fixed shell, the second sliding column is sleeved with the third spring, one end of the second sliding column is installed with an ejection block, the ejection block and the push block are movably connected, and the second force plate is installed at the other end of the second sliding column, and when the multiple second force plates and the multiple first force plates are opened, an arc is formed to fit tightly against the side wall of the surrounding rock.

[0009] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, two through holes are opened on the second force-bearing plate, a small guide tube is movably connected in one of the through holes, and a tension mechanism is arranged in the other through hole.

[0010] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, the tension mechanism includes a tension rod, a rotating shaft, a pull plate, a fourth spring and a spike. The tension rod is arranged on the second force plate. The tension rod is rotatably connected to multiple rotating shafts. The pull plate is installed on the rotating shaft. The pull plate is L-shaped. The fourth spring is fixedly connected between the pull plate and the tension rod, and the tension rod is provided with multiple spikes.

[0011] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, the keel steel is arc-shaped, the supporting mechanism is arranged in an arc shape, the supporting mechanism is slidably connected between multiple keel steels, and the bottom fixing mechanism includes a fixing plate and an anchor rod. The fixing plate is fixedly connected between multiple keel steels, and the anchor rod is slidably connected on the fixing plate.

[0012] Based on the above-mentioned karst area and fault fracture zone tunnel surrounding rock pre-support device, the steel bar bundle mechanism includes strip steel and restraining plates, the strip steel is fixedly connected between every two fixed shells, restraining plates are arranged between multiple strip steels, and anti-leakage nets are arranged between multiple strip steels and at the bottom of the restraining plates.

[0013] On the other hand, an embodiment of the present invention provides a method for supporting a tunnel surrounding rock using the karst area and fault fracture zone tunnel surrounding rock pre-support device, comprising the following steps:

[0014] S1. Pass the support mechanism on multiple keel steels, fix the steel bar bundle mechanism on one side of the support mechanism, and then fix the support mechanism again on the side of the steel bar bundle mechanism, and repeat this process until the support mechanism and the steel bar bundle mechanism on the keel steel completely fill the entire keel steel, then pass the tension mechanism through the support mechanism, and insert the tension mechanism into the surrounding rock. At this time, the keel steel, the support mechanism and the steel bar bundle mechanism form an arc, that is, the shape of the tunnel, and then fix the bottom fixing mechanism. The equipment is installed, and the surrounding rock is grouted or the water in the cave is drained through the support mechanism when in use;

[0015] S2. The first force-bearing mechanism in the support mechanism is in contact with the side wall of the surrounding rock, while the second force-bearing mechanism in the support mechanism is in the retracted state. Then, a flexible filler is filled between the upper side of the keel steel and the support mechanism. After the filling is completed, mud is filled into the steel bar bundle mechanism and the keel steel, so that the keel steel and the steel bar bundle mechanism form a concrete support. At this time, the support mechanism, the keel steel and the steel bar bundle mechanism protect the surrounding rock or cave;

[0016] S3. When the surrounding rock collapses or deforms downward, the surrounding rock first squeezes the first force-bearing mechanism in the supporting mechanism. At this time, the first force-bearing mechanism buffers the upward buffering force of the surrounding rock through the cooperation of its parts. When the first force-bearing mechanism is deformed, the second force-bearing mechanism moves upward during the downward movement of the first force-bearing mechanism. At this time, the second force-bearing mechanism opens, so that an arc-shaped protective surface is formed on the upper side of the keel steel, thereby further increasing the strength of the protection;

[0017] S4. When the support mechanism is subjected to force, the first force-bearing mechanism in the support mechanism is pressed downward, thereby causing the second force-bearing mechanism to move upward. At this time, the first force-bearing mechanism and the second force-bearing mechanism form a complete arc surface.

[0018] The effects provided in the content of the invention are only the effects of the embodiments, rather than all the effects of the invention. The above technical solution has the following advantages or beneficial effects:

[0019] 1. The present invention forms a complete casting model when the equipment is in use through the mutual cooperation of the keel steel and the steel bar bundle mechanism, so that it is more stable when protecting the surrounding rock. The support mechanism in the equipment uses the cooperation of the keel steel and the steel bar bundle mechanism to form an upward supporting force at the bottom of the support mechanism. When the surrounding rock collapses or deforms downward, the surrounding rock first squeezes the first force-bearing mechanism in the support mechanism. At this time, the first force-bearing mechanism buffers the upward buffering force of the surrounding rock through the cooperation of its parts, thereby avoiding downward stress and impact when the surrounding rock is deformed. The force is too large, causing the keel steel to deform. When the first force-bearing mechanism is deformed, the second force-bearing mechanism will move upward during the downward movement of the first force-bearing mechanism. At this time, the second force-bearing mechanism opens, so that an arc-shaped protective surface is formed on the upper side of the keel steel, thereby further increasing the strength of the protection and avoiding excessive impact on the keel steel when the surrounding rock is deformed, thereby causing damage to the keel steel and subsequent collapse of the equipment, further improving the protection stability of the equipment, indirectly buffering the stress and impact force on the equipment, thereby improving the stability and safety of the equipment.

[0020] 2. When the supporting mechanism is under stress, the first stress-bearing mechanism in the supporting mechanism is pressed downward, thereby causing the second stress-bearing mechanism to move upward. At this time, the first stress-bearing mechanism and the second stress-bearing mechanism form a complete arc surface. When the second stress-bearing mechanism moves upward, the second stress-bearing plate slides on the tension rod in the tension mechanism. When the second stress-bearing plate passes through the pull plate on the tension rod, since the pull plate is L-shaped, the pull plate will be stressed from the bottom of the second stress-bearing plate, thereby giving the second stress-bearing plate a bottom support force, thereby reducing the stress on the second stress-bearing plate, and then reducing the impact force on the equipment, further increasing the stability and strength of the equipment, and thus improving the safety of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.

[0022] Figure 1 This is a schematic diagram of the structure of the present invention from a front side perspective;

[0023] Figure 2 This is a schematic diagram of the structure of the present invention from a lower side perspective;

[0024] Figure 3 This is a schematic diagram of the partial front side perspective structure of the present invention Figure 1 ;

[0025] Figure 4 This is a schematic diagram of the partial front side view of the present invention. Figure 2 ;

[0026] Figure 5 This is a schematic diagram of the partial front side perspective structure of the present invention Figure 2 ;

[0027] Figure 6 This is a schematic diagram of the partial front side view of the present invention. Figure 2 .

[0028] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0029] 1. Keel steel; 2. Support mechanism; 3. Fixed shell; 4. Slide groove; 5. First force-bearing mechanism; 6. First sliding column; 7. First spring; 8. Pressing block; 9. First force-bearing plate; 10. Second force-bearing mechanism; 11. Pushing block; 12. Second spring; 13. Second sliding column; 14. Third spring; 15. Ejecting block; 16. Second force-bearing plate; 17. Through hole; 18. Tension mechanism; 19. Tension rod; 20. Rotating shaft; 21. Pull plate; 22. Fourth spring; 23. Protrusion; 24. Steel bar bundle mechanism; 25. Strip steel; 26. Binding plate; 27. Bottom fixing mechanism; 28. Fixing plate; 29. ​​Anchor rod. DETAILED DESCRIPTION

[0030] In order to clearly illustrate the technical features of the present solution, the present invention is described in detail below through specific implementation methods and in combination with the accompanying drawings. The disclosure below provides many different embodiments or examples for realizing different structures of the present invention. In order to simplify the disclosure of the present invention, the components and settings of specific examples are described below. In addition, the present invention may repeat reference numbers and / or letters in different examples. This repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed. It should be noted that the components illustrated in the accompanying drawings are not necessarily drawn to scale. The present invention omits the description of known components and processing technologies and processes to avoid unnecessary limitations on the present invention. The orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used only for descriptive purposes and cannot be understood as indicating or implying relative importance. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0031] Example 1

[0032] like Figures 1 to 6 As shown, a tunnel surrounding rock pre-support device in a karst area and a fault fracture zone comprises a plurality of keel steels 1, a plurality of supporting mechanisms 2 are arranged between the plurality of keel steels 1, two tensioning mechanisms 18 are arranged on the supporting mechanisms 2, a plurality of steel bar bundle mechanisms 24 are arranged between the plurality of keel steels 1, the plurality of steel bar bundle mechanisms 24 are located between every two supporting mechanisms 2, two bottom fixing mechanisms 27 are arranged between the plurality of keel steels 1, and the bottom fixing mechanisms 27 are located at both ends of the keel steels 1.

[0033] In the embodiment of the present invention, the support mechanism 2 includes a fixed shell 3, a slide groove 4, a first force-bearing mechanism 5 and a second force-bearing mechanism 10. The fixed shell 3 is slidably connected between the keel steel 1, and the fixed shell 3 and the keel steel 1 are fixed by bolts. The slide groove 4 is provided in the fixed shell 3, and the first force-bearing mechanism 5 is provided in the fixed shell 3. During operation, when the equipment is subjected to force, the first force-bearing mechanism 5 in the support mechanism 2 is impacted and deformed. When the first force-bearing mechanism 5 is deformed, the first force-bearing mechanism 5 simultaneously impacts the second force-bearing mechanism 10, so that the second force-bearing mechanism 10 has a suitable buffering force, and shares the impact force received by the first force-bearing mechanism 5, so as to ensure the safety of the equipment and improve the practicality of the equipment.

[0034] In the embodiment of the present invention, the first force-bearing mechanism 5 includes a first sliding column 6, a first spring 7, a downward pressure block 8 and a first force-bearing plate 9. The first sliding column 6 is connected to the fixed shell 3, and the first sliding column 6 is sleeved with the first spring 7. The first sliding column 6 is located in the fixed shell 3, and one end of the first sliding column 6 is installed with the downward pressure block 8, and the downward pressure block 8 is wedge-shaped. The other end of the first sliding column 6 is installed with the first force-bearing plate 9, and the first force-bearing plate 9 is arc-shaped.

[0035] In the embodiment of the present invention, two second force-bearing mechanisms 10 are provided on the fixed shell 3, and the second force-bearing mechanisms 10 are located on both sides of the first force-bearing mechanism 5. The second force-bearing mechanism 10 includes a push block 11, a second spring 12, a second sliding column 13, a third spring 14, an ejection block 15 and a second force-bearing plate 16. The two push blocks 11 are slidably connected in the slide groove 4, one side and the top of the push block 11 are wedge-shaped, the push block 11 and the pressing block 8 are movably connected, the second spring 12 is fixedly connected between the push block 11 and one side of the slide groove 4, the two second sliding columns 13 are connected to the fixed shell 3, the second sliding column 13 is sleeved with the third spring 14, one end of the second sliding column 13 is installed with an ejection block 15, the ejection block 15 and the push block 11 are movably connected, and the second force-bearing plate 16 is installed at the other end of the second sliding column 13. When the multiple second force-bearing plates 16 and the multiple first force-bearing plates 9 are opened, an arc is formed to be tightly attached to the side wall of the surrounding rock. During operation, when the first force-bearing plate 9 moves downward, the lower pressing block 8 squeezes the two push blocks 11 at the same time, causing the two push blocks 11 to move to both sides. At this time, the two push blocks 11 squeeze the ejection block 15. When the ejection block 15 moves upward under force, the ejection block 15 drives the second sliding column 13 to move upward. At this time, the third spring 14 is stretched under force, and the second force-bearing plate 16 installed at one end of the second sliding column 13 fits with the first force-bearing plate 9, so that the first force-bearing plate 9 and the second force-bearing plate 16 form an arc. When the device is not under force, When the first load-bearing plate 9 is under stress, the second load-bearing plate 16 is in contact with the surrounding rock at the same time, so that the equipment has a buffering force, and when the equipment is fully opened, the second load-bearing plate 16 can fully share the impact force exerted on the first load-bearing plate 9, thereby ensuring the safety of the equipment. When the second load-bearing plate 16 moves upward, the second load-bearing plate 16 moves on the tensioning mechanism 18, so that the tensioning mechanism 18 can further ensure the stability of the second load-bearing plate 16.

[0036] In the embodiment of the present invention, two through holes 17 are provided on the second force-bearing plate 16, wherein a small catheter is movably connected in one of the through holes 17, and a tension mechanism 18 is provided in the other through hole 17. When working, the tension mechanism 18 is located in the second force-bearing plate 16, which can fully guarantee the supporting force of the second force-bearing plate 16 and avoid the rebound of the second force-bearing plate 16. During construction, people can use an advanced small catheter to grout the surrounding rock through the other through hole 17, or drain the liquid in the cave through the through hole 17, which further improves the practicability and diversity of the equipment.

[0037] In the embodiment of the present invention, the pulling mechanism 18 includes a pulling rod 19, a rotating shaft 20, a pulling plate 21, a fourth spring 22 and a spike 23. The pulling rod 19 is arranged on the second force-bearing plate 16. The pulling rod 19 is rotatably connected to multiple rotating shafts 20. The pulling plate 21 is installed on the rotating shaft 20. The pulling plate 21 is L-shaped. The fourth spring 22 is fixedly connected between the pulling plate 21 and the pulling rod 19. The pulling rod 19 is provided with multiple spikes 23.

[0038] In an embodiment of the present invention, the keel steel 1 is arc-shaped, the support mechanism 2 is arranged in an arc shape, the support mechanism 2 is slidably connected between multiple keel steels 1, the bottom fixing mechanism 27 includes a fixing plate 28 and an anchor rod 29, the fixing plate 28 is fixedly connected between multiple keel steels 1, and the anchor rod 29 is slidably connected on the fixing plate 28. During operation, when the tension rod 19 passes through the second force plate 16, the tension rod 19 is inserted into the surrounding rock. At this time, the protrusions 23 on the tension rod 19 contact the surrounding rock, thereby increasing the force on the tension rod 19 and preventing the tension rod 19 from detaching. When the second force plate 16 is subjected to force, the second force plate 16 moves upward and squeezes the tension plate 21. At this time, the tension plate 21 rotates on the rotating shaft 20. When the tension plate 21 rotates, the fourth spring 22 is squeezed. When the second force plate 16 passes through the tension plate 21, the tension plate 21 is reset by the elastic force of the fourth spring 22, thereby blocking the bottom of the second force plate 16, thereby preventing the second force plate 16 from rebounding and falling, thereby reducing the force on the second force plate 16, and further improving the stability and safety of the equipment.

[0039] In the embodiment of the present invention, the steel bar bundle mechanism 24 includes strip steel 25 and a binding plate 26. The strip steel 25 is fixedly connected between every two fixed shells 3. Binding plates 26 are provided between multiple strip steels 25. Anti-leakage nets are provided between multiple strip steels 25 and at the bottom of the binding plates 26. When working, grouting is sprayed between the strip steel 25 and the binding plates 26, so that the slurry forms a solidified concrete between the anti-leakage net and the strip steel 25 and the binding plates 26, thereby protecting the surrounding rock or cave, thereby improving the stability and safety of the equipment.

[0040] The working principle of the present invention is as follows: the support mechanism 2 is passed through a plurality of keel steels 1, and the fixing shell 3 in the support mechanism 2 is fixed on the keel steel 1. Each time a group of support mechanisms 2 is passed through, the steel bar bundle mechanism 24 is fixed on one side of the support mechanism 2, and then the support mechanism 2 is fixed again on one side of the steel bar bundle mechanism 24, and this is repeated until the support mechanism 2 and the steel bar bundle mechanism 24 on the keel steel 1 completely fill the entire keel steel 1, and then the tension rod 19 in the tension mechanism 18 is passed through the support mechanism 2, and the tension rod 19 is inserted into the surrounding rock. At this time, the keel steel 1, the support mechanism 2 and the steel bar bundle mechanism 24 form an arc, that is, the shape of the tunnel, and then the bottom fixing mechanism 27 is fixed, and the equipment is installed. People can use the advance small catheter to grout the surrounding rock or drain the water in the cave through the through hole 17 in the support mechanism 2. When the equipment is installed, the first force-bearing mechanism 5 in the support mechanism 2 is in contact with the side wall of the surrounding rock, and the second force-bearing mechanism 10 is in the storage state. Then, a flexible filler is filled between the upper side of the keel steel 1 and the support mechanism 2. After the filler is filled, mud is filled into the steel bar bundle mechanism and the keel steel 1, so that the keel steel 1 and the steel bar bundle mechanism form a concrete support. At this time, the support mechanism 2, the keel steel 1 and the steel bar bundle mechanism protect the surrounding rock or the cave. When the equipment is stressed, the first force-bearing mechanism 5 moves downward under force. At this time, the first force-bearing mechanism 5 is equipped with The second force-bearing mechanism 10 rises, so that the multiple first force-bearing mechanisms 5 and the second force-bearing mechanisms 10 form a complete arc, thereby weakening the downward pressure and stress of the surrounding rock and improving protection; the present invention uses the mutual cooperation of the keel steel 1 and the steel bar bundle mechanism 24 to enable the equipment to form a complete casting model when in use, so that it is more stable when protecting the surrounding rock, and the support mechanism 2 in the equipment uses the cooperation of the keel steel 1 and the steel bar bundle mechanism 24 to form an upward supporting force at the bottom of the support mechanism 2. When the surrounding rock collapses or deforms downward, the surrounding rock first squeezes the first force-bearing mechanism 5 in the support mechanism 2. At this time, the first force-bearing mechanism 5, through the cooperation of its parts, makes the surrounding The upward buffering force of the rock is buffered, so that when the surrounding rock is deformed, the downward stress and impact force are too large, causing the keel steel 1 to deform. When the first force-bearing mechanism 5 is deformed, the second force-bearing mechanism 10 will move up during the downward movement of the first force-bearing mechanism 5. At this time, the second force-bearing mechanism 10 is opened, so that an arc-shaped protective surface is formed on the upper side of the keel steel 1, thereby further increasing the strength of the protection, and avoiding excessive impact on the keel steel 1 when the surrounding rock is deformed, thereby causing the keel steel 1 to be damaged and then causing the equipment to collapse, further improving the protection stability of the equipment, indirectly buffering the stress and impact force on the equipment, thereby improving the stability and safety of the equipment.

[0041] Example 2

[0042] A method for supporting a tunnel surrounding rock by using the karst area and fault fracture zone tunnel surrounding rock pre-support device comprises the following steps:

[0043] S1. Pass the support mechanism 2 through a plurality of keel steels 1. Each time a group of support mechanisms 2 is passed through, a steel bar bundle mechanism 24 is fixed on one side of the support mechanism 2. Then, the support mechanism 2 is fixed again on one side of the steel bar bundle mechanism 24. This is repeated until the support mechanism 2 and the steel bar bundle mechanism 24 on the keel steel 1 completely fill the entire keel steel 1. Then, the tension mechanism 18 is passed through the support mechanism 2, and the tension mechanism 18 is inserted into the surrounding rock. At this time, the keel steel 1, the support mechanism 2 and the steel bar bundle mechanism 24 form an arc, that is, the shape of the tunnel. Then, the bottom fixing mechanism 27 is fixed. The equipment installation is completed, and the support mechanism 2 supports the surrounding rock at the same time, thereby ensuring the stability of the equipment and improving the safety of the equipment. When in use, the surrounding rock is grouted or the water in the cave is drained through the support mechanism 2;

[0044] S2. The first force-bearing mechanism 5 in the support mechanism 2 is in contact with the side wall of the surrounding rock, while the second force-bearing mechanism 10 in the support mechanism 2 is in the storage state. Then, a flexible filler is filled between the upper side of the keel steel 1 and the support mechanism 2. After the filling is completed, mud is filled into the steel bar bundle mechanism 24 and the keel steel 1, so that the keel steel 1 and the steel bar bundle mechanism 24 form a concrete support. At this time, the support mechanism 2, the keel steel 1 and the steel bar bundle mechanism protect the surrounding rock or cave;

[0045] S3. When the surrounding rock collapses or deforms downward, the surrounding rock first squeezes the first force-bearing mechanism 5 in the supporting mechanism 2. At this time, the first force-bearing mechanism 5 buffers the upward buffering force of the surrounding rock through the cooperation of its parts. When the first force-bearing mechanism 5 is deformed, the second force-bearing mechanism 10 moves upward during the downward movement of the first force-bearing mechanism 5. At this time, the second force-bearing mechanism 10 opens, so that an arc-shaped protective surface is formed on the upper side of the keel steel, thereby further increasing the strength of the protection;

[0046] S4. When the supporting mechanism is under stress, the first stress-bearing mechanism 5 in the supporting mechanism 2 is pressed downward, so that the second stress-bearing mechanism 10 moves upward. At this time, the first stress-bearing mechanism 5 and the second stress-bearing mechanism 10 form a complete arc surface. When the equipment is not under stress, the first stress-bearing plate 9 fits with the surrounding rock. When the first stress-bearing plate 9 is under stress, the second stress-bearing plate 16 fits with the surrounding rock at the same time, so that the equipment has a buffering force, and when the equipment is fully opened, the second stress-bearing plate 16 can fully share the impact force of the first stress-bearing plate 9, thereby ensuring the safety of the equipment. When the second stress-bearing plate 16 moves upward, the second stress-bearing plate 16 moves on the tensioning mechanism 18, so that the tensioning mechanism 18 can further ensure the stability of the second stress-bearing plate 16.

[0047] Although the above describes the specific implementation mode of the invention in conjunction with the drawings, it is not intended to limit the scope of protection of the invention. Based on the technical solution of the present invention, various modifications or variations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.

Claims

1. A tunnel surrounding rock pre-support device in a karst area and a fault fracture zone, comprising a plurality of keel steels (1), Features: A plurality of support mechanisms (2) are arranged between the plurality of keel steels (1), two tension mechanisms (18) are arranged on the support mechanisms (2), a plurality of steel bar bundle mechanisms (24) are arranged between the plurality of keel steels (1), the plurality of steel bar bundle mechanisms (24) are located between every two support mechanisms (2), two bottom fixing mechanisms (27) are arranged between the plurality of keel steels (1), and the bottom fixing mechanisms (27) are located at both ends of the keel steels (1); The support mechanism (2) comprises a fixed shell (3), a slide groove (4), a first force-bearing mechanism (5) and a second force-bearing mechanism (10); the fixed shell (3) is slidably connected to the keel steel (1); the fixed shell (3) and the keel steel (1) are fixed by bolts; the slide groove (4) is provided in the fixed shell (3); and the first force-bearing mechanism (5) is provided in the fixed shell (3); The first force-bearing mechanism (5) comprises a first sliding column (6), a first spring (7), a lower pressure block (8) and a first force-bearing plate (9), the first sliding column (6) being connected to the fixed shell (3), the first spring (7) being sleeved on the first sliding column (6), one end of the first sliding column (6) being located in the fixed shell (3) being installed with a lower pressure block (8), the lower pressure block (8) being wedge-shaped, the other end of the first sliding column (6) being installed with a first force-bearing plate (9), the first force-bearing plate (9) being arc-shaped; Two second force-bearing mechanisms (10) are provided on the fixed shell (3), and the second force-bearing mechanisms (10) are located on both sides of the first force-bearing mechanism (5). The second force-bearing mechanism (10) includes a push block (11), a second spring (12), a second sliding column (13), a third spring (14), an ejection block (15) and a second force-bearing plate (16). The two push blocks (11) are slidably connected in the slide groove (4), and one side and the top of the push block (11) are wedge-shaped. The push block (11) and the lower pressing block (8) are movably connected. The push block (11) ) and one side of the slide groove (4), a second spring (12) is fixedly connected, two second sliding columns (13) are connected to the fixed shell (3), a third spring (14) is sleeved on the second sliding column (13), an ejection block (15) is installed at one end of the second sliding column (13), the ejection block (15) and the push block (11) are movably connected, and a second force plate (16) is installed at the other end of the second sliding column (13), and the plurality of second force plates (16) and the plurality of first force plates (9) form an arc when they are opened and closely adhere to the side wall of the surrounding rock; The keel steel (1) is arc-shaped, the support mechanism (2) is arranged in an arc shape, the support mechanism (2) is slidably connected between the plurality of keel steels (1), the bottom fixing mechanism (27) comprises a fixing plate (28) and an anchor rod (29), the fixing plate (28) is fixedly connected between the plurality of keel steels (1), and the anchor rod (29) is slidably connected to the fixing plate (28); The steel bar bundle mechanism (24) comprises strip steel (25) and a restraining plate (26); the strip steel (25) is fixedly connected between every two fixed shells (3); a restraining plate (26) is provided between a plurality of strip steels (25); and anti-leakage nets are provided between the plurality of strip steels (25) and at the bottom of the restraining plate (26).

2. A tunnel surrounding rock pre-support device in a karst area and a fault fracture zone as claimed in claim 1, Features: The second force-bearing plate (16) is provided with two through holes (17), wherein a small conduit is movably connected in one of the through holes (17), and a tension mechanism (18) is disposed in the other through hole (17).

3. A tunnel surrounding rock pre-support device in a karst area and a fault fracture zone according to claim 1, Features: The pulling mechanism (18) comprises a pulling rod (19), a rotating shaft (20), a pulling plate (21), a fourth spring (22) and a spike (23); the pulling rod (19) is arranged on the second force-bearing plate (16); the pulling rod (19) is rotatably connected to a plurality of rotating shafts (20); the pulling plate (21) is mounted on the rotating shaft (20); the pulling plate (21) is L-shaped; the fourth spring (22) is fixedly connected between the pulling plate (21) and the pulling rod (19); and the pulling rod (19) is provided with a plurality of spikes (23).

4. A method for supporting a tunnel in a karst area or a fault zone by using the tunnel surrounding rock pre-support device according to any one of claims 1 to 3, It is characterized in that The following steps are involved: S1. The support mechanism (2) is passed through a plurality of keel steels (1), a steel bar bundle mechanism (24) is fixed on one side of the support mechanism (2), and then the support mechanism (2) is fixed again on one side of the steel bar bundle mechanism (24), and this is repeated until the support mechanism (2) and the steel bar bundle mechanism (24) on the keel steel (1) completely fill the entire keel steel (1), and then the tension mechanism (18) is passed through the support mechanism (2), and the tension mechanism (18) is inserted into the surrounding rock. At this time, the keel steel (1) and the support mechanism (2) and the steel bar bundle mechanism (24) form an arc, that is, the shape of the tunnel, and then the bottom fixing mechanism (27) is fixed. The equipment is installed, and when in use, grouting is performed on the surrounding rock or water in the cave is drained through the support mechanism (2); S2. The first force-bearing mechanism (5) in the support mechanism (2) is in contact with the side wall of the surrounding rock, while the second force-bearing mechanism (10) in the support mechanism (2) is in a retracted state. Then, a flexible filler is filled between the upper side of the keel steel (1) and the support mechanism (2). After the filling is completed, mud is filled into the steel bar bundle mechanism (24) and the keel steel (1), so that the keel steel (1) and the steel bar bundle mechanism (24) form a concrete support. At this time, the support mechanism (2), the keel steel (1) and the steel bar bundle mechanism protect the surrounding rock or the cave; S3. When the surrounding rock collapses or deforms downward, the surrounding rock first squeezes the first force-bearing mechanism (5) in the supporting mechanism (2). At this time, the first force-bearing mechanism (5) buffers the upward buffering force of the surrounding rock through the cooperation of its parts. When the first force-bearing mechanism (5) is deformed, the first force-bearing mechanism (5) moves downward, causing the second force-bearing mechanism (10) to move upward. At this time, the second force-bearing mechanism (10) opens, so that the upper side of the keel steel forms an arc-shaped protective surface, thereby further increasing the strength of the protection. S4. When the support mechanism is subjected to force, the first force-bearing mechanism (5) in the support mechanism (2) is pressed downward, thereby causing the second force-bearing mechanism (10) to move upward. At this time, the first force-bearing mechanism (5) and the second force-bearing mechanism (10) form a complete arc surface.

Citation Information

Patent Citations

  • Large-deformation strong supporting device for tunnel excavation

    CN112963169A

  • Underground excavation hole-entering supporting structure and supporting method thereof

    CN115075844A

  • Shallow-buried bias tunnel surrounding rock broken section excavation protection device and protection method

    CN115653655A

  • Tunnel lining inspection and repair trolley and method for repairing structural defects

    WO2023082614A1