A method and system for optimizing operation of main distribution network of distributed power supply

By screening and allocating distributed power sources, combining weather forecasts and historical data, and adjusting the grid-connected current, the problem of difficulty in absorbing the amount of distributed power sources connected to the grid is solved, and the stability and management efficiency of the power grid are improved.

CN118589608BActive Publication Date: 2024-10-11STATE GRID ZHEJIANG ELECTRIC POWER CO LTD NINGBO POWER SUPPLY CO
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411066855.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-10-11
Estimated Expiration
2044-08-06

AI Technical Summary

Technical Problem

It is difficult to absorb the grid-connected amount of distributed power sources locally, which leads to the impact of power grid power flow and management problems. The existing technology cannot reasonably layout and absorb the grid-connected amount, which affects the safety and stability of the distribution network.

Method used

Screen the power sources to be accommodated by obtaining the grid-connected current and recording the number of stops, determining the ring network distribution method according to the power consumption unit and geographical location, and making predictions based on historical power generation and weather forecast data to determine whether an energy storage station is needed, and based on the grid connection Current adjustment distribution method.

Benefits of technology

It achieves the reasonable layout of distributed power sources and the accommodation of grid-connected amounts, improves the accuracy of forecasting power generation, reduces the impact of power generation fluctuations on the power grid, and improves the practicality of optimized operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118589608B_ABST
    Figure CN118589608B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of distributed power generation, and in particular to a method and system for optimizing the operation of a main distribution network of a distributed power source. The present invention solves the following problems: it is difficult to locally absorb the grid-connected amount of a distributed power source, and how to form a ring network that can absorb the grid-connected amount. To solve the above problem, the present invention provides an operation method, including: obtaining power consumption units around a power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle, screening according to the power consumption of the power consumption units, and obtaining absorbable units; determining the allocation mode of the ring network according to the geographical locations of the absorbable units and the power source to be absorbed, and determining the power adjustment interval of the ring network according to the average power generation; obtaining the power fluctuation of the ring network in each power generation cycle according to the historical power generation, and judging whether it is necessary to install an energy storage station in the ring network according to the power fluctuation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of distributed power generation, and in particular to a method and system for optimizing operation of a main distribution network of a distributed power source. Background Art

[0002] With the large-scale grid connection of low-voltage distributed power sources, the distribution entities will become more complex and diverse, with many problems affecting the safe and stable operation of the distribution network, such as voltage over-limit, three-phase imbalance, excessive harmonic content, and reverse overload. At the same time, the dual fluctuations on the supply side and demand side will lead to a phenomenon of time and space mismatch between the grid-connected amount of distributed power sources and the power load, and it will be difficult to locally consume the grid-connected amount of distributed power sources, and the resulting operation and management problems will become increasingly prominent.

[0003] Regarding the voltage control under the conditions of large-scale access of existing distributed power sources to the distribution network, due to the lack of coordinated control between devices, as well as problems such as complex network, slow learning speed and high computing power requirements, it is impossible to reasonably layout each distributed power source to form a ring network that can absorb the grid-connected capacity and reduce the impact of the grid-connected capacity of distributed power sources on the grid current. Summary of the invention

[0004] The present invention solves the problem that it is difficult to locally absorb the grid-connected amount of distributed power sources, and how to form a ring network that can absorb the grid-connected amount.

[0005] To solve the above problems, an embodiment of the present invention provides a method for optimizing the operation of a main distribution network of a distributed power source, the operation method comprising: obtaining the grid-connected current of the distributed power source in the target area, when the grid-connected current is greater than the grid-connected threshold, the distributed power source stops supplying power to the grid, and records the number of stops of each distributed power source; screening the distributed power sources according to the number of stops, when the number of stops within the target time period is greater than the number threshold, the distributed power source is recorded as a power source to be absorbed; obtaining the power consumption units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle, screening according to the power consumption of the power consumption units, and obtaining the absorbable units; determining the distribution of the ring network according to the geographical locations of the absorbable units and the power source to be absorbed The power adjustment range of the ring network is determined according to the average power generation; the historical power generation of each power source to be consumed in the ring network is obtained, and the future power generation of the power source to be consumed is predicted according to the weather forecast data and the historical power generation to obtain the predicted power generation; the power fluctuation of the ring network in each power generation cycle is obtained according to the historical power generation, and it is judged whether it is necessary to install an energy storage station in the ring network according to the power fluctuation; if so, the grid-connected switch is controlled according to the predicted power generation, and the power can be released from the energy storage station or stored in the energy storage station; if not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the distribution method is changed according to the grid-connected current.

[0006] Compared with the prior art, the technical effects achieved by adopting this technical solution are as follows: the acquisition of grid-connected current can count the power generation of each distributed photovoltaic in the target area, and by setting the number of stops, the distributed power sources that need to be optimized in the target area can be accurately screened out. The screening of the absorptive units makes the establishment of the ring network more reasonable, and the setting of the power adjustment interval fully considers the power generation of each distributed power source. The acquisition of historical power generation and weather forecast data makes the predicted power generation more consistent with the historical working conditions of the distributed power source, thereby improving the accuracy of the predicted power generation. After the ring network allocation is completed, an energy storage station is set according to the overall power generation fluctuation in the ring network to reduce the impact of the power generation fluctuation of the distributed power source. For the ring network without an energy storage station, the grid-connected current is monitored to determine whether the allocation method of the ring network is reasonable, thereby improving the practicality of the optimization operation method.

[0007] In one embodiment of the present invention, power-consuming units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle are obtained, and the power-consuming units are screened according to the power consumption to obtain absorbable units, specifically including: obtaining the power generation time period of each power source to be absorbed and the time period power consumption of each power-consuming unit within the power generation time period; screening out the minimum time period power consumption, and obtaining the supply difference based on the minimum time period power consumption and the average power generation; when the supply difference is less than the grid-connected threshold, the power unit is recorded as an absorbable unit.

[0008] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the power generation time period is obtained, and the power consuming units are screened according to the time when the distributed power sources can generate power, so that the screened absorbable units are more in line with the working conditions of the distributed power sources, and the power consumption fluctuations of the absorbable units are compared with the grid-connected threshold value, so that the power consumption fluctuations of the absorbable units will not affect the operation of the distribution network.

[0009] In one embodiment of the present invention, the allocation method of the ring network is determined according to the geographical locations of the absorbable units and the power sources to be absorbed, and the power adjustment interval of the ring network is determined according to the average power generation, which specifically includes: determining the ring network planning circle according to the geographical location of each absorbable unit, and grouping the power sources to be absorbed in the ring network planning circle according to the supply difference; when the sum of the supply differences of multiple power sources to be absorbed is less than the grid connection threshold, allocating the multiple power sources to be absorbed to the same ring network planning circle to obtain the basic ring network planning in the target area; calculating the absorption margin of each ring network planning circle according to the basic ring network planning, if there is unallocated power source to be absorbed, correcting the basic ring network planning according to the absorption margin to obtain a corrected ring network planning.

[0010] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the setting of the ring network planning circle can reasonably group all the power sources to be absorbed in the target area according to the distance, and through the calculation of the grid connection threshold, it can ensure that each ring network planning circle can absorb the power generation of the power sources to be absorbed, correct the setting of the basic ring network planning, and reallocate the power sources to be absorbed that have no nearby absorbing units, so that each power source to be absorbed can be absorbed through the ring network, reducing the impact of distributed power sources on the main distribution network after being connected to the grid.

[0011] In one embodiment of the present invention, the historical power generation of each power source to be absorbed in the ring network is obtained, and the future power generation of the power source to be absorbed is predicted based on weather forecast data and historical power generation to obtain predicted power generation, which specifically includes: obtaining the unit power and unit temperature in each historical collection period; obtaining the predicted temperature in the target collection period according to weather forecast data, selecting the historical collection period corresponding to the target collection period, and recording the unit power of the corresponding historical collection period as the target power, and recording the unit temperature of the historical collection period as the target temperature; calculating the power generation variation coefficient of the target collection period according to the predicted temperature and the target temperature, and predicting the future power generation according to the power generation variation coefficient and the target power.

[0012] Compared with the existing technology, the technical effects achieved by adopting this technical solution are as follows: the setting of the historical collection cycle can use the historical power generation of distributed power sources as a reference when obtaining the predicted power generation, so that the obtained predicted power generation is more in line with its own working environment; the setting of the power generation variation coefficient combines the temperature change with the target power, further improving the accuracy of the predicted power generation.

[0013] In one embodiment of the present invention, a power generation variation coefficient of a target acquisition period is calculated according to a predicted temperature and a target temperature, and future power generation is predicted according to the power generation variation coefficient and the target power, specifically including: selecting a historical working day closest to the predicted temperature from a historical acquisition period and recording it as a comparison working day, and recording the unit power of the comparison working day as the comparison power; when there is only one historical acquisition period, calculating the power difference according to the comparison power and the target power, and calculating the power generation variation coefficient according to the power difference and the target power; when there are multiple historical acquisition periods, calculating the temperature variation coefficient of the power source to be consumed according to multiple target temperatures, calculating the temperature difference according to the unit temperature and the predicted temperature, and calculating the power generation variation coefficient according to the temperature difference and the temperature variation coefficient; and predicting future power generation according to the power generation variation coefficient.

[0014] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: by comparing the acquisition of electricity, it is possible to predict future power generation based on the historical power generation of distributed power sources, thereby improving the accuracy of future power generation prediction. At the same time, different power generation calculation methods are selected according to different numbers of historical cycles, so that the predicted future power generation is more in line with the working environment of distributed power sources.

[0015] In one embodiment of the present invention, the power fluctuation of the ring network in each power generation cycle is obtained according to the historical power generation, and it is judged whether it is necessary to install an energy storage station in the ring network according to the power fluctuation, which specifically includes: obtaining the maximum power generation of each power source to be consumed in each historical collection cycle, adding the maximum power generation of each power source to be consumed in the ring network planning circle, and obtaining the periodic power generation corresponding to each future collection cycle; screening out the maximum value of the periodic power generation, recording it as the limit power generation of the ring network planning circle, and calculating the limit grid-connected power of the ring network planning circle according to the difference between the limit power generation and the supply; judging whether it is necessary to install an energy storage station in the ring network according to the limit grid-connected power.

[0016] Compared with the existing technology, the technical effects achieved by adopting this technical solution are: acquisition of maximum power generation, analysis of the extreme working conditions of the power source to be absorbed, setting of periodic power generation, obtaining the corresponding power generation conditions of the power source to be absorbed in each natural month, calculation of the maximum grid-connected power, making the installation judgment of the energy storage station more accurate, and making the working status within the ring network planning circle more reasonable, thereby improving the stability of the internal operation of the ring network planning circle.

[0017] In one embodiment of the present invention, if so, the grid-connected switch is controlled according to the predicted power generation, and power can be released from the energy storage station or stored in the energy storage station, specifically including: when the predicted power generation is greater than the maximum value of the power adjustment interval, the part greater than the supply difference is stored in the energy storage station; when the predicted power generation is within the power adjustment interval, the predicted power generation is absorbed through the ring network planning circle; when the predicted power generation is less than the minimum value of the power adjustment interval, the power is released through the energy storage station to maintain the stability of the distribution network.

[0018] Compared with the existing technology, the technical effect achieved by adopting this technical solution is: by comparing the predicted power generation with the power adjustment range, the opening and closing of the grid-connected switch is reasonably controlled, making the working state within the ring network planning circle more stable.

[0019] In one embodiment of the present invention, if not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the allocation method is changed according to the grid-connected current, specifically including: when the grid-connected current is less than the grid-connected threshold, the allocation method does not need to be changed; when the grid-connected current is greater than or equal to the grid-connected threshold, the number of stops corresponding to the ring network planning circle is recorded and the stop frequency is calculated; when the stop frequency is greater than or equal to the frequency threshold, new absorbable units are added to the ring network planning circle or the number of power sources to be absorbed in the ring network planning circle is reduced; when the stop frequency is less than the frequency threshold, the allocation method does not need to be changed.

[0020] Compared with the existing technology, the technical effect achieved by adopting this technical solution is: the setting of stop frequency and frequency threshold can be realized, and the allocation method of the ring network planning circle can be subsequently controlled after the ring network planning circle is confirmed, and the allocation method can be adjusted in time, which further improves the practicality of the optimization method.

[0021] In one embodiment of the present invention, the present invention also provides a main distribution network optimization operation system of a distributed power source, and the optimization operation method recorded in the above embodiment is applied to the operation system, and the operation system includes: a storage module, in which historical power generation, power consumption units and distributed power sources are stored; a detection module, which is used to detect grid-connected current; a prediction module, which is used to obtain weather forecast data; and a calculation module, which is used to calculate the predicted power generation. The operation system has all the technical features of the above-mentioned optimization operation method, which will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 One of the flow charts of the main distribution network optimization operation method of the distributed power supply of the present invention;

[0023] Figure 2 This is the second flow chart of the method for optimizing the operation of the main distribution network of a distributed power source of the present invention;

[0024] Figure 3 This is the third flow chart of the method for optimizing the operation of the main distribution network of a distributed power source of the present invention;

[0025] Figure 4 This is the fourth flow chart of the main distribution network optimization operation method of the distributed power supply of the present invention;

[0026] Figure 5 A system diagram of the main distribution network optimization operation system for distributed power sources;

[0027] Description of reference numerals:

[0028] 100 - operation system; 110 - storage module; 120 - detection module; 130 - prediction module; 140 - calculation module. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, specific embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0030] [First embodiment]

[0031] See also Figure 1 In a specific embodiment, the present invention provides a method for optimizing the operation of a main distribution network of a distributed power source, the operation method comprising:

[0032] S100, obtaining the grid-connected current of the distributed power sources in the target area. When the grid-connected current is greater than the grid-connected threshold, the distributed power sources stop supplying power to the grid, and the number of times each distributed power source stops is recorded;

[0033] S200, screening the distributed power sources according to the number of stoppages, and when the number of stoppages in the target time period is greater than the number threshold, recording the distributed power sources as power sources to be consumed;

[0034] S300, obtaining the power consumption units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle, and screening the power consumption units according to the power consumption to obtain the absorbable units;

[0035] S400, determining the allocation mode of the ring network according to the geographical locations of the absorbable units and the power sources to be absorbed, and determining the power adjustment interval of the ring network according to the average power generation;

[0036] S500, obtaining the historical power generation of each power source to be consumed in the ring network, and predicting the future power generation of the power source to be consumed based on the weather forecast data and the historical power generation to obtain the predicted power generation;

[0037] S600, obtaining the power fluctuation of the ring network in each power generation cycle according to the historical power generation, and judging whether it is necessary to install an energy storage station in the ring network according to the power fluctuation;

[0038] S700: If yes, the grid-connected switch is controlled according to the predicted power generation, and the power can be released from the energy storage station or stored in the energy storage station;

[0039] S800: If not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the distribution method is changed according to the grid-connected current.

[0040] In step S100, the target area is usually a city, but can also be a village or an administrative planning area. Distributed power sources are usually photovoltaic power sources. With the large-scale grid connection of low-voltage distributed photovoltaics, the distribution entities will become more complex and diverse. For irreversible grid connection, when the reverse current is greater than the grid connection threshold, it is necessary to control the distributed photovoltaics to stop supplying power within two seconds. The grid connection threshold is usually 5% of the rated output. When the distributed photovoltaics stop supplying power because the grid-connected current is greater than the grid connection threshold, the number of times the distributed photovoltaics stop is recorded.

[0041] In step S200, because photovoltaic power sources are greatly affected by meteorological factors and have the characteristics of volatility and randomness, there is a probability that power supply will be stopped during a long period of operation. When the power supply is stopped too frequently, it means that the power generation of the distributed power source cannot be consumed locally. If it is not handled in time, the resulting operation and management problems will become increasingly prominent. Therefore, it is necessary to record the distributed power sources whose stop times are greater than the threshold as power sources to be consumed.

[0042] It should be noted that the number threshold is related to the working time of the distributed power source. Normally, only one power outage is allowed within two months.

[0043] In step S300, the average power generation of the power user is retrieved through the data management library. Usually, a natural year is divided into twelve power generation cycles according to months, and the average power generation of each month is calculated after the end of each month. When the power user needs to provide electricity through the distribution network, the power user is an absorptive unit.

[0044] In step S400, the geographical locations of the absorbable units and the power sources to be absorbed are determined through the map module in the data management library, the fluctuation range of power generation is determined according to the average power generation of the power sources to be absorbed, and based on the fluctuation range, when the ring network is allocated, the power adjustment range is determined according to the fluctuation range of power generation of each power source to be absorbed.

[0045] It should be noted that when selecting the allocation method of the ring network, it should be selected based on the difficulty of building the ring network, while ensuring that the photovoltaic power generation can be absorbed. It is necessary to comprehensively consider the distance between the absorbable unit and the power source to be absorbed, as well as the wiring conditions between the absorbable unit and the power source to be absorbed.

[0046] In step S500, historical power generation is stored in a data management library, and weather forecast data is obtained from a meteorological station. The weather forecast data includes weather types and environmental data. Weather types include sunny days, cloudy days, rainy days, foggy days, snowy days, etc. Environmental data includes solar radiation intensity, maximum temperature, minimum temperature, humidity and wind direction, etc. Future power generation is predicted based on the weather forecast data.

[0047] In step S600, for large-scale distributed photovoltaics, the weather has a greater impact on power generation. If it only relies on fixed absorbable units for absorption, when the power generation is large, the photovoltaic power generation cannot be fully absorbed, and when the power generation is small, it cannot provide enough power generation to the absorbable units, resulting in unstable working conditions and affecting the overall operation of the distribution network. Therefore, for large-scale distributed photovoltaics, energy storage stations can be installed in the ring network.

[0048] In step S700 to step S800, after the allocation method of the ring network is determined, an electric connection is established between the absorbable unit and the power source to be absorbed, and a grid-connected switch is set. When the ring network needs to absorb electricity, the absorbable unit is connected to the power source to be absorbed through the grid-connected switch. For the ring network with an energy storage station, when the photovoltaic power generation is insufficient, the energy storage station can release electricity to maintain the normal operation of the absorbable unit. When the photovoltaic power generation is too large, the photovoltaic power generation can be stored. For the ring network without an energy storage station, the grid-connected switch is controlled according to the predicted power generation, and the distributed photovoltaic power generation is absorbed in time through the ring network.

[0049] The acquisition of grid-connected current can count the power generation of each distributed photovoltaic in the target area. By setting the number of stops, the distributed power sources that need to be optimized in the target area can be accurately screened out. The screening of the absorptive units makes the establishment of the ring network more reasonable. The setting of the power adjustment interval fully considers the power generation of each distributed power source. The acquisition of historical power generation and weather forecast data makes the predicted power generation more consistent with the historical working conditions of the distributed power sources, improving the accuracy of the predicted power generation. After the ring network allocation is completed, the energy storage station is set according to the overall power generation fluctuation in the ring network to reduce the impact of the power generation fluctuation of the distributed power sources. For the ring network without an energy storage station, the grid-connected current is monitored to determine whether the ring network allocation method is reasonable, thereby improving the practicality of the optimization operation method.

[0050] [Second embodiment]

[0051] See also Figure 2 In a specific embodiment, the power consumption units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle are obtained, and the power consumption units are screened according to the power consumption to obtain the absorbable units, which specifically includes:

[0052] S210, obtaining the power generation time period of each power source to be consumed and the power consumption of each power user within the power generation time period;

[0053] S220, filtering out the minimum power consumption in the time period, and obtaining the power supply difference according to the minimum power consumption in the time period and the average power generation;

[0054] S230. When the supply difference is less than the grid connection threshold, the electricity consuming unit is recorded as an absorptive unit.

[0055] In step S210, distributed photovoltaics can only generate electricity smoothly under the irradiation of sunlight. When there is no sunlight, the corresponding power generation of distributed photovoltaics can be ignored. The power generation time period is adjusted according to the power generation cycle. Usually, the time length corresponding to the power generation time period is longer in summer and shorter in winter. The power consumption of each power user during the power generation time period is obtained through the data management library.

[0056] In steps S220 to S230, when the minimum power consumption in the time period is less than the average power generation, it means that the power user may not be able to fully absorb the power generation corresponding to the distributed photovoltaics. When the minimum power consumption in the time period is greater than or equal to the average power generation, the power user can fully absorb the power generation corresponding to the distributed photovoltaics. However, in order to avoid excessive power generation, the supply difference also needs to be less than the grid connection threshold.

[0057] The minimum power consumption in the recording period is V0, the average power generation is V1, the supply difference is △V, the grid connection threshold is V2, and the absorbable unit is determined by the following formula:

[0058] △V=V0-V1;

[0059] When △V<0, the electricity unit is not an absorptive unit;

[0060] When 0≤△V<V2, the electricity unit is an absorptive unit;

[0061] When V2≤△V, the electricity consuming unit is not an absorptive unit.

[0062] The power generation time period is obtained, and the power consuming units are screened according to the time when the distributed power sources can generate power, so that the screened absorbable units are more in line with the working conditions of the distributed power sources. By comparing the supply difference with the grid-connected threshold, the power consumption fluctuations of the absorbable units will not affect the operation of the distribution network.

[0063] [Third embodiment]

[0064] See also Figure 3 In a specific embodiment, the allocation mode of the ring network is determined according to the geographical location of the absorbable units and the power source to be absorbed, and the power adjustment interval of the ring network is determined according to the average power generation, which specifically includes:

[0065] S410, determining a ring network planning circle according to the geographical location of each unit that can be absorbed, and grouping the power sources to be absorbed within the ring network planning circle according to the supply difference;

[0066] S420: when the sum of the supply differences of the multiple power sources to be consumed is less than the grid connection threshold, the multiple power sources to be consumed are allocated to the same ring network planning circle to obtain a basic ring network planning in the target area;

[0067] S430, calculating the absorption margin of each ring network planning circle according to the basic ring network planning, if there is unallocated power to be absorbed, correcting the basic ring network planning according to the absorption margin to obtain a corrected ring network planning.

[0068] In step S410, a ring network planning circle is set with each absorbable unit as the center and one kilometer as the radius, and the power sources to be absorbed within each ring network planning circle are counted, and grouped according to the average power generation corresponding to each power source to be absorbed, and each power source to be absorbed is allocated to the corresponding ring network planning circle.

[0069] It should be noted that it is not necessary for every ring network planning circle to have power sources to be absorbed. Comprehensive consideration should be given to the location of the power sources to be absorbed and the difficulty of wiring, and appropriate absorbent units should be selected for each power source to be absorbed.

[0070] In step S420, the power source to be absorbed that each absorbable unit can receive is calculated according to the sum of multiple supply quantity differences, and the basic ring network planning of the absorbable unit is obtained.

[0071] In step S430, after the basic ring network planning is allocated, the power sources to be absorbed that have not entered the ring network planning circle are searched in the target area. The absorption margin is calculated by first calculating the sum of the supply differences corresponding to each power source to be absorbed in the ring network planning circle, and then subtracting the sum of the supply differences from the grid connection threshold to obtain the absorption margin. The unallocated power sources to be absorbed are recorded as power sources to be allocated, and the ring network planning circles that the power sources to be allocated can join are screened out according to the absorption margin and the ring network difference, and the distances between the power sources to be allocated and each ring network planning circle are calculated, and the power sources to be allocated are added to the ring network planning circle with the shortest distance, and the basic ring network planning is modified to obtain a revised ring network planning.

[0072] It should be noted that, under the premise of being able to absorb the power generation of distributed power sources, the number of ring network planning circles should be reduced as much as possible to reduce the difficulty of building ring network planning circles.

[0073] The setting of the ring network planning circle can reasonably group all the power sources to be absorbed in the target area according to the distance. Through the calculation of the grid connection threshold, it can ensure that each ring network planning circle can absorb the power generation of the power sources to be absorbed, correct the settings of the basic ring network planning, and reallocate the power sources to be absorbed that have no nearby absorbing units, so that each power source to be absorbed can be absorbed through the ring network, reducing the impact of distributed power sources on the main distribution network after being connected to the grid.

[0074] [Fourth embodiment]

[0075] See also Figure 4 In a specific embodiment, the historical power generation of each power source to be consumed in the ring network is obtained, and the future power generation of the power source to be consumed is predicted based on the weather forecast data and the historical power generation to obtain the predicted power generation, which specifically includes:

[0076] S510, obtaining unit power and unit temperature in each historical collection cycle;

[0077] S520, obtaining a predicted temperature within a target collection period according to weather forecast data, selecting a historical collection period corresponding to the target collection period, and recording the unit power of the corresponding historical collection period as the target power, and recording the unit temperature of the historical collection period as the target temperature;

[0078] S530, calculating the power generation variation coefficient of the target acquisition period according to the predicted temperature and the target temperature, and predicting the future power generation according to the power generation variation coefficient and the target power.

[0079] In step S510, the unit power is the average power generation in the historical collection period, and the unit temperature is the average temperature in the historical collection period.

[0080] In step S520, the target collection period is the current natural month, and the corresponding historical collection period refers to a period with the same month as the target collection period but a different year. The power generation of the target collection period is predicted by the unit electricity and target temperature of previous years to improve the accuracy of the prediction.

[0081] It should be noted that if the distributed power source has not been working for a long time and there is no corresponding historical collection cycle, the data of similar distributed power sources in the target area will be used as a reference. When judging whether the distributed power sources are similar, the scale and model of the distributed power sources will be mainly used for judgment.

[0082] In step S530, based on the target power quantity, the power generation variation coefficient is calculated through the difference between the target temperature and the predicted temperature, so as to predict the future power generation.

[0083] It should be noted that because the historical collection cycle and the target collection cycle have the same month, the difference in solar altitude angles between the two is small in the target area. The power generation of distributed photovoltaics is also closely related to the solar altitude angle. The accuracy of the predicted power generation can be improved by calculating the predicted power generation through the target power.

[0084] The setting of the historical collection cycle can use the historical power generation of distributed power sources as a reference when obtaining the predicted power generation, so that the predicted power generation is more in line with its own working environment. The setting of the power generation variation coefficient combines the temperature change with the target power, further improving the accuracy of the predicted power generation.

[0085] [Fifth embodiment]

[0086] In a specific embodiment, the power generation variation coefficient of the target acquisition period is calculated according to the predicted temperature and the target temperature, and the future power generation is predicted according to the power generation variation coefficient and the target power, specifically including:

[0087] S531. Filter out the historical working day closest to the predicted temperature from the historical collection cycle, record it as the comparison working day, and record the unit power of the comparison working day as the comparison power;

[0088] S532, when there is only one historical collection cycle, the power difference is calculated based on the comparison power and the target power, and the power generation change coefficient is calculated based on the power difference and the target power;

[0089] S533. When there are multiple historical collection cycles, the temperature variation coefficient of the power source to be absorbed is calculated according to multiple target temperatures, the temperature difference is calculated according to the unit temperature and the predicted temperature, the power generation variation coefficient is calculated according to the temperature difference and the temperature variation coefficient, and the future power generation is predicted according to the power generation variation coefficient.

[0090] In step S531, when selecting historical working days, first select the historical working day with the same predicted temperature. If there is no historical working day, first select the historical working day with a temperature close to the predicted temperature. When there are multiple historical working days with the same or similar temperature to the predicted temperature, determine it based on the date difference and select the one with the smallest date difference as the comparison working day.

[0091] For example, the target collection period is July 2024, and the temperature on July 15, 2024 is being predicted. The historical collection period shows that the temperatures on July 14, 2023 and July 18, 2023 are the same as the predicted temperature on July 15, 2024. At this time, July 14, 2023 is selected as the comparison working day because the date difference between the two is small and the solar altitude angle is closer.

[0092] In step S532, there is only one historical collection cycle, that is, there is only one comparison power. At this time, the power difference can be used to calculate the change in the power generation of distributed photovoltaics at the same temperature. The comparison power is A1, the target power is A0, and the power generation change coefficient is S1. The power generation change coefficient is calculated by the following formula:

[0093] When (A1-A0)÷A0<0, S1=0.98;

[0094] When 0≤(A1-A0)÷A0<2%, S1=1;

[0095] When 2%≤(A1-A0)÷A0<5%, S1=1.02;

[0096] When 5%≤(A1-A0)÷A0, S1=1.05.

[0097] In step S533, there are multiple historical collection cycles. In each historical collection cycle, a target temperature is selected, and the variance of the multiple target temperatures is calculated. The temperature variation coefficient is calculated based on the variance. The temperature variation coefficient is recorded as T1, and the variance of the multiple target temperatures is recorded as T0. The temperature variation coefficient and the variance of the multiple target temperatures satisfy the following relationship:

[0098] When 0≤T0<2, T1=1;

[0099] When 2≤T0<5, T1=1.01;

[0100] When 5≤T0, T1=1.02.

[0101] After the temperature variation coefficient is obtained, the predicted temperature is converted according to the temperature difference and the temperature variation coefficient to obtain the converted temperature. The converted power corresponding to the converted temperature is selected from the historical collection period, and the future power generation is predicted based on the converted power. The multiple target temperatures corresponding to multiple historical collection periods are recorded as T a1 To T an , the predicted temperature is T a0 , converted to temperature T b , the converted temperature, predicted temperature and multiple target temperatures satisfy the following relationship:

[0102] T b =T1×[1+(T a1 +T a2 +……T an )÷n-T a0 ].

[0103] After the conversion temperature is obtained, the power generation corresponding to the conversion temperature in the historical collection period is used as the converted power. When there is a historical working day with the same conversion temperature in the historical collection period, the converted power is directly used as the future power generation. When there is no historical working day with the same conversion temperature in the historical collection period, the historical working day closest to the conversion temperature is selected, and the future power generation is calculated based on the converted power.

[0104] By comparing the acquisition of electricity, it is possible to predict future power generation based on the historical power generation of distributed power sources, thereby improving the accuracy of future power generation predictions. At the same time, different power generation calculation methods are selected according to different numbers of historical cycles, so that the predicted future power generation is more in line with the working environment of distributed power sources.

[0105] [Sixth embodiment]

[0106] In a specific embodiment, the power fluctuation of the ring network in each power generation cycle is obtained according to the historical power generation, and it is determined whether it is necessary to install an energy storage station in the ring network according to the power fluctuation, which specifically includes:

[0107] S610, obtaining the maximum power generation of each power source to be consumed in each historical collection cycle, adding the maximum power generation of each power source to be consumed in the ring network planning circle, and obtaining the periodic power generation corresponding to each future collection cycle;

[0108] S620, filter out the maximum value of the periodic power generation, record it as the limit power generation of the ring network planning circle, and calculate the limit grid-connected power of the ring network planning circle according to the difference between the limit power generation and the supply;

[0109] S630: Determine whether it is necessary to install an energy storage station in the ring network according to the maximum grid-connected power.

[0110] In step S610, the maximum power generation can obtain the power generation of distributed power sources under extreme conditions, and the extreme conditions that the ring network planning circle may face are obtained according to the extreme conditions of each power source to be consumed. In order to prevent such extreme conditions, it is necessary to calculate the periodic power generation corresponding to the future collection period.

[0111] In step S620, the periodic power generation is divided according to the natural month, and the ring network planning circle, after being established, needs to cope with the changes in power generation throughout the natural year. Therefore, it is necessary to screen out the maximum value of the periodic power generation and calculate the limit grid-connected power.

[0112] It should be noted that when calculating the maximum value of periodic power generation, the maximum value of the corresponding quantity cannot be directly filtered out according to the year, but should be filtered out according to the maximum value of each natural month.

[0113] In step S630, the limit grid-connected power can reflect the fluctuation of power generation within the ring network planning circle. When the limit grid-connected power is large, it is usually necessary to install an energy storage station to store power. When the distributed power source cannot provide power, the energy storage station will discharge the power. When the limit grid-connected power is small, the energy storage station may not be installed. At this time, the fluctuation of power generation will not interfere with the normal operation of the main distribution network.

[0114] The maximum power generation is obtained, the extreme working conditions of the power source to be consumed are analyzed, the periodic power generation is set, and the corresponding power generation conditions of the power source to be consumed in each natural month are obtained. The calculation of the maximum grid-connected power makes the installation judgment of the energy storage station more accurate, and also makes the working status within the ring network planning circle more reasonable, thereby improving the stability of the internal operation of the ring network planning circle.

[0115] [Seventh embodiment]

[0116] In a specific embodiment, if yes, the grid-connected switch is controlled according to the predicted power generation, and the power can be released from the energy storage station or stored in the energy storage station, specifically including:

[0117] S710, when the predicted power generation is greater than the maximum value of the power adjustment interval, the portion greater than the power supply difference is stored in the energy storage station;

[0118] S720, when the predicted power generation is within the power adjustment range, the predicted power generation is consumed through the ring network planning circle;

[0119] S730: When the predicted power generation is less than the minimum value of the power adjustment interval, the power storage station is used to release power to maintain the stability of the distribution network.

[0120] In step S710 to step S730, in order to stabilize the working state of the distribution transformer and reduce the volatility of the distribution transformer, the working state of the energy storage station is controlled by the power adjustment interval. When the predicted power generation is greater than the maximum value of the power adjustment interval, the energy storage station needs to store the excess power generation. When the predicted power generation is within the power adjustment interval, the power generation can be consumed in the ring network by turning on the grid-connected switch. When the predicted power generation is less than the minimum value of the power adjustment interval, the energy storage station can also release electric energy for compensation.

[0121] It should be noted that after the predicted power generation is determined, the actual power generation will be recorded in real time on the current working day. The fluctuation of the current working day will be judged based on the actual power generation and the predicted power generation. The opening time of the grid-connected switch will be calculated based on the fluctuation of the current working day. In this way, the power generation of the absorbable power source will be absorbed in real time. The predicted power generation can not only provide a reference indicator for the actual power generation, but also screen out the grid-connected switches that may need to be turned on in advance, thereby reducing the difficulty of operation on the current working day.

[0122] By comparing the predicted power generation with the power adjustment range, the opening and closing of the grid-connected switch can be reasonably controlled to make the working state within the ring network planning circle more stable.

[0123] [Eighth embodiment]

[0124] In a specific embodiment, if not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the distribution mode is changed according to the grid-connected current, specifically including:

[0125] S810, when the grid-connected current is less than the grid-connected threshold, the allocation method does not need to be changed;

[0126] S820, when the grid-connected current is greater than or equal to the grid-connected threshold, record the number of stops corresponding to the ring network planning circle and calculate the stop frequency;

[0127] S830. When the stop frequency is greater than or equal to the frequency threshold, add new absorbable units within the ring network planning circle or reduce the number of power sources to be absorbed within the ring network planning circle. When the stop frequency is less than the frequency threshold, the allocation method does not need to be changed.

[0128] In steps S810 to S830, when the fluctuation of the grid-connected current does not cause the number of stoppages, it means that the absorption effect of the ring network planning circle is good. When the grid-connected current causes the power supply to stop, it means that the voltage fluctuation of the distributed power source has affected the operation of the main distribution network. When the stop frequency is too large, it means that the allocation method of the ring network planning circle is not reasonable.

[0129] At this time, new energy-absorbent units need to be added to the ring network planning circle, or energy storage stations need to be set up within the ring network planning circle to avoid a further increase in the number of stops.

[0130] The setting of the stop frequency and the frequency threshold can perform subsequent control over the allocation method of the ring network planning circle after the ring network planning circle is confirmed, and adjust the allocation method in time, further improving the practicality of the optimization method.

[0131] [Ninth embodiment]

[0132] See also Figure 5 In a specific embodiment, the present invention further provides a main distribution network optimization operation system 100 of a distributed power source, and the optimization operation method recorded in the above embodiment is applied to the operation system 100, and the operation system 100 includes: a storage module 110, in which historical power generation, power consumption units and distributed power sources are stored; a detection module 120, in which the detection module 120 is used to detect grid-connected current; a prediction module 130, in which the prediction module 130 is used to obtain weather forecast data; a calculation module 140, in which the calculation module 140 is used to calculate the predicted power generation. The operation system 100 has all the technical features of the above-mentioned optimization operation method, which will not be repeated here.

[0133] Although the present invention is disclosed as above, the present invention is not limited thereto. Any person skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the scope defined by the claims.

Claims

1. A method for optimizing the operation of a main distribution network of a distributed power source, characterized in that: The operation method comprises: Obtaining the grid-connected current of the distributed power source in the target area, when the grid-connected current is greater than the grid-connected threshold, the distributed power source stops supplying power to the grid, and the number of times each distributed power source stops is recorded; The distributed power sources are screened according to the number of stoppages, and when the number of stoppages within the target time period is greater than a number threshold, the distributed power sources are recorded as power sources to be absorbed; Obtain the power consumption units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle, and filter them according to the power consumption of the power consumption units to obtain the absorbable units; Determine the allocation mode of the ring network according to the geographical locations of the absorbable units and the power sources to be absorbed, and determine the power adjustment interval of the ring network according to the average power generation; Obtaining the historical power generation of each of the power sources to be consumed in the ring network, and predicting the future power generation of the power sources to be consumed based on weather forecast data and the historical power generation to obtain predicted power generation; Obtaining the power fluctuation of the ring network in each power generation cycle according to the historical power generation, and judging whether it is necessary to install an energy storage station in the ring network according to the power fluctuation; If yes, the grid-connected switch is controlled according to the predicted power generation, and the power can be released from the energy storage station or stored in the energy storage station; If not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the distribution method is changed according to the grid-connected current.

2. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 1, characterized in that: The step of obtaining the power consumption units around the power source to be absorbed and the average power generation of the power source to be absorbed in each power generation cycle, and filtering the power consumption units according to the power consumption to obtain the absorbable units specifically includes: Obtaining the power generation time period of each of the power sources to be consumed and the power consumption of each of the power users during the power generation time period; Filter out the minimum value of power consumption in the time period, and obtain the power supply difference according to the minimum value of power consumption in the time period and the average power generation; When the supply difference is less than the grid connection threshold, the electricity consuming unit is recorded as the absorptive unit.

3. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 2, characterized in that: The determining of the allocation mode of the ring network according to the geographical locations of the absorbable units and the power sources to be absorbed, and the determining of the power adjustment interval of the ring network according to the average power generation, specifically includes: Determine a ring network planning circle according to the geographical location of each of the absorbable units, and group the power sources to be absorbed within the ring network planning circle according to the supply difference; When the sum of the supply differences of the multiple power sources to be consumed is less than the grid connection threshold, the multiple power sources to be consumed are allocated to the same ring network planning circle to obtain the basic ring network planning in the target area; The absorption margin of each ring network planning circle is calculated according to the basic ring network planning. If there is unallocated power to be absorbed, the basic ring network planning is corrected according to the absorption margin to obtain a corrected ring network planning.

4. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 3, characterized in that: The acquiring of the historical power generation of each of the power sources to be consumed in the ring network, and predicting the future power generation of the power sources to be consumed according to weather forecast data and the historical power generation to obtain the predicted power generation specifically includes: Obtain the unit power and unit temperature in each historical collection cycle; Acquire the predicted temperature within the target collection period according to the weather forecast data, select the historical collection period corresponding to the target collection period, and record the unit power of the corresponding historical collection period as the target power, and record the unit temperature of the historical collection period as the target temperature; The power generation variation coefficient of the target acquisition period is calculated according to the predicted temperature and the target temperature, and the future power generation is predicted according to the power generation variation coefficient and the target power.

5. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 4, characterized in that: The calculating the power generation variation coefficient of the target acquisition period according to the predicted temperature and the target temperature, and predicting the future power generation according to the power generation variation coefficient and the target power specifically includes: Selecting a historical working day closest to the predicted temperature from the historical collection period and recording it as a comparison working day, and recording the unit power of the comparison working day as the comparison power; When there is only one historical collection cycle, the power difference is calculated according to the comparison power and the target power, and the power generation variation coefficient is calculated according to the power difference and the target power; When there are multiple historical collection cycles, the temperature variation coefficient of the power source to be absorbed is calculated according to the multiple target temperatures, the temperature difference is calculated according to the unit temperature and the predicted temperature, and the power generation variation coefficient is calculated according to the temperature difference and the temperature variation coefficient; The future power generation is predicted according to the power generation variation coefficient.

6. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 4, characterized in that: The obtaining of power fluctuations of the ring network in each power generation cycle according to the historical power generation, and judging whether it is necessary to install an energy storage station in the ring network according to the power fluctuations, specifically includes: Obtain the maximum power generation of each of the power sources to be consumed in each of the historical collection cycles, add the maximum power generation of each of the power sources to be consumed in the ring network planning circle, and obtain the periodic power generation corresponding to each future collection cycle; The maximum value of the periodic power generation is screened out and recorded as the limit power generation of the ring network planning circle, and the limit grid-connected power of the ring network planning circle is calculated according to the difference between the limit power generation and the supply; Whether the energy storage station needs to be installed in the ring network is determined according to the limit grid-connected power.

7. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 6, characterized in that: If so, the grid-connected switch is controlled according to the predicted power generation, and the power can be released from the energy storage station or stored in the energy storage station, specifically including: When the predicted power generation is greater than the maximum value of the power adjustment interval, the portion greater than the power supply difference is stored in the energy storage station; When the predicted power generation is within the power adjustment interval, the predicted power generation is consumed through the ring network planning circle; When the predicted power generation is less than the minimum value of the power adjustment interval, the energy storage station releases power to maintain the stability of the distribution network.

8. The method for optimizing the operation of the main distribution network of a distributed power source according to claim 6, characterized in that: If not, the grid-connected switch is controlled according to the predicted power generation, and the grid-connected current in the ring network is obtained in real time when the grid-connected switch is turned on, and the distribution mode is changed according to the grid-connected current, specifically including: When the grid-connected current is less than the grid-connected threshold, the allocation mode does not need to be changed; When the grid-connected current is greater than or equal to the grid-connected threshold, the number of stops corresponding to the ring network planning circle is recorded and the stop frequency is calculated; When the stop frequency is greater than or equal to the frequency threshold, adding a new unit that can be absorbed in the ring network planning circle or reducing the number of the power sources to be absorbed in the ring network planning circle; When the stop frequency is less than the frequency threshold, the allocation mode does not need to be changed.

9. A main distribution network optimization operation system of distributed power source, characterized in that: The optimized operation method according to any one of claims 1 to 8 is applied to the operation system, and the operation system comprises: A storage module, in which the historical power generation, the power consumption unit and the distributed power source are stored; A detection module, the detection module is used to detect the grid-connected current; A prediction module, the prediction module is used to obtain the weather forecast data; A calculation module is used to calculate the predicted power generation.

Citation Information

Patent Citations

  • Distributed power supply consumption capacity evaluation method and system

    CN109995089A

  • Power grid regional distributed photovoltaic consumption potential long-term prediction method and system, and medium

    CN115293468A

  • Distributed power supply grid-connected scheduling method and device and power grid operation system

    CN115333170A

  • Distributed power supply penetration power distribution network and photovoltaic consumption method

    CN115579871A

  • Distributed photovoltaic power grid and photovoltaic consumption method

    CN115940265A