A kind of assembly type steel structure building curtain wall connection device and method
By designing prefabricated steel structure building curtain wall connection devices, the coordination of prefabricated frames and multiple institutions is used to solve the tedious problems of the existing curtain wall connection device, realize the rapid installation and sealing of the curtain wall board, and improve the installation efficiency.
Patent Information
- Application Number
- CN202410898403.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2025-01-24
- Estimated Expiration
- 2044-07-05
AI Technical Summary
The existing curtain wall connection devices lack a quick installation mechanism, which leads to the cumbersome installation and fixing process of curtain wall panels, which is time-consuming and labor-intensive.
A prefabricated steel structure building curtain wall connection device is designed, including a prefabricated outer frame, a push-pull mechanism, a gradient expansion mechanism and a self-sealing mechanism. Through the cooperation of these mechanisms, the rapid installation and sealing of curtain wall panels can be achieved.
This device achieves rapid installation and sealing of curtain wall panels through the synergy of prefabricated outer frames and multiple mechanisms, significantly improves installation efficiency and reduces manual operation time and effort.
Smart Images

Figure CN118621943B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building curtain walls, and in particular to a device and method for connecting assembled steel structure building curtain walls. Background Art
[0002] The main building structures in the construction industry are steel structures and concrete structures. Steel structures are structures mainly made of steel materials and are one of the main types of building structures. Curtain walls have been an indispensable part of building production since ancient times. They have the functions of cleaning and wrapping on both sides of the building. They are non-load-bearing and are hung on the exterior wall like a projection screen, so they are also called curtain walls.
[0003] The curtain wall is usually installed by installing multiple horizontal and vertical beams on the exterior wall of the building, forming multiple installation slots by criss-crossing them, and then installing the curtain wall panels in the slots in turn and then fixing them.
[0004] Although this type of curtain wall connection method in the prior art can be used for curtain wall installation, it is inevitable that there are still some shortcomings in the actual use process. For example, the device lacks a quick installation mechanism, so that the installation and placement of the curtain wall panel, as well as its subsequent sealing and fixing processes, will have multiple steps to be carried out in sequence, resulting in the overall installation being time-consuming and labor-intensive. In order to avoid such problems, an assembled steel structure building curtain wall connection device and method are proposed to solve the existing problems. Summary of the invention
[0005] In view of the deficiencies in the prior art, the present invention provides a prefabricated steel structure building curtain wall connection device and method, which solves the problem that the device lacks a quick installation mechanism, resulting in cumbersome installation and fixation of the curtain wall panels, making the overall installation time-consuming and labor-intensive.
[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: an assembled steel structure building curtain wall connection device, including a prefabricated outer frame and an installation slot, wherein a plurality of the installation slots are provided, and the plurality of installation slots are symmetrically arranged inside the prefabricated outer frame in an up-down and left-right manner, an inner wall of the installation slot is fixedly connected with a rear ring edge, a front side of the rear ring edge is fixedly connected with a rear sealing strip, a vertical slide groove is provided on the front side of the prefabricated outer frame, a push-pull mechanism is provided between the vertical slide groove and the prefabricated outer frame, a gradient expansion mechanism is provided between the push-pull mechanism and the prefabricated outer frame, and a self-sealing mechanism is provided between the push-pull mechanism, the gradient expansion mechanism and the prefabricated outer frame.
[0007] Preferably, the push-pull mechanism includes a U-shaped slide groove, which is opened inside the prefabricated outer frame, and two U-shaped slide grooves are arranged in a vertical array, the interior of the U-shaped slide groove is slidably connected to the U-shaped slide, both sides of the front side of the U-shaped slide plate are fixedly connected to a U-shaped receiving frame used in conjunction with the mounting groove, a curtain wall panel is slidably placed inside the U-shaped receiving frame, the rear side of the inner cavity of the vertical slide groove is rotatably connected to a threaded rod through a bearing, the surface of the threaded rod is threadedly connected to a first threaded sleeve, the top and bottom of the first threaded sleeve are provided with a delay vertical plate used in conjunction with the U-shaped slide, and the front end of the threaded rod passes through and extends to the front side of the prefabricated outer frame.
[0008] Preferably, the gradient unfolding mechanism includes a large-span U-shaped frame, which is fixedly arranged on the front side of the top U-shaped slide, and a small-span U-shaped frame is fixedly connected to the front side of the bottom U-shaped slide, and the large-span U-shaped frame and the small-span U-shaped frame are respectively used in conjunction with adjacent delay vertical plates, and second return springs are fixedly connected to both sides of the front side of the U-shaped slide, and the end of the second return spring is fixedly connected to the inner wall of the adjacent U-shaped slide groove.
[0009] Preferably, the self-sealing mechanism includes a second threaded sleeve, which is threadedly connected to the surface of the threaded rod, and the front side of the prefabricated outer frame is provided with a plurality of front ring edges used in conjunction with the curtain wall panel, and the front ring edges on both sides of the same side are fixedly connected by a bracket, and the rear side of the front ring edge is fixedly connected with a front sealing strip used in conjunction with the curtain wall panel, and the rear side of the second threaded sleeve is fixedly connected to the front side of the adjacent front ring edge, and the top and bottom of the front side of the prefabricated outer frame are fixedly connected to the limiting long rod, and the surface of the limiting long rod is slidably connected to the limiting sliding sleeve, and the opposite sides of the two limiting sliding sleeves are respectively fixedly connected to the top and bottom of the second threaded sleeve through the bracket.
[0010] Preferably, guide grooves are provided on both sides of the front and rear sides of the inner cavity of the U-shaped receiving frame, and a guide slider is slidably connected inside the guide groove. A first return spring is fixedly connected between adjacent guide sliders and guide grooves, and an angled pressure block used in conjunction with a curtain wall panel is fixedly connected between the two guide sliders on the same side.
[0011] Preferably, a push-pull plate is fixedly connected to the top of the tilting pressure block, and movable long grooves slidably matched with the push-pull plate are provided on both sides of the top of the U-shaped receiving frame.
[0012] Preferably, the top and bottom of both sides of the front ring edge are fixedly connected with ear plates with holes, the front side of the prefabricated outer frame is provided with threaded holes used in conjunction with the ear plates with holes, and fastening bolts are threadedly connected between adjacent ear plates with holes and threaded holes.
[0013] Preferably, both sides of the rear side of the prefabricated outer frame are fixedly connected with a back plate with holes.
[0014] The present invention also discloses a method for connecting a prefabricated steel structure building curtain wall, which specifically comprises the following steps:
[0015] S1. Several prefabricated outer frames are installed on the outer wall in order through the perforated back plate and bolts, and then the threaded rod is screwed. When the threaded rod rotates, the first threaded sleeve on its surface will move forward, and the first threaded sleeve will synchronously drive the two delayed vertical plates to move. The bottom delayed vertical plate first moves against the front side of the inner cavity of the small-span U-shaped frame, and drives the small-span U-shaped frame and the bottom U-shaped receiving frame to move forward. Along with the movement of the bottom U-shaped receiving frame, the top delayed vertical plate also successively abuts against the front side of the inner cavity of the large-span U-shaped frame, and lags to drive the top U-shaped slide plate and the U-shaped receiving frame to move forward. When the two upper and lower U-shaped receiving frames on the same side move, they move in a stepped staggered and orderly manner until the two U-shaped receiving frames on the same side move out of the inside of the installation slot;
[0016] S2. When the threaded rod is twisted to cause the first threaded sleeve to move forward, the second threaded sleeve on the surface of the threaded rod also moves forward successively. When the second threaded sleeve moves forward, it will move ahead of the U-shaped receiving frame, causing the second threaded sleeve to carry the front ring edge and the front sealing strip in advance and separate from the close fit with the U-shaped receiving frame, leaving enough smooth space for the subsequent placement of the curtain wall panel;
[0017] S3. After the curtain wall panels are moved forward out of the front side of the installation slot, the operator sequentially places multiple curtain wall panels into the U-shaped receiving frame. During the process of lowering the curtain wall panels into the U-shaped receiving frame, the two sides of the curtain wall panels will laterally squeeze the tilt pressing block, so that after the curtain wall panels are placed in place, the tilt pressing block is easy to reset and limit the top of the curtain wall panels;
[0018] S4, seal and reinstall. Finally, the operator reversely rotates the threaded rod to make the first threaded sleeve carry two delayed vertical plates, and gradually push the rear sides of the inner cavities of the large-span U-frame and the small-span U-frame respectively, so that the large-span U-frame and the small-span U-frame respectively drive the U-shaped receiving frame and the curtain wall panel to move backward, until the rear side of the curtain wall panel is sealed with the rear sealing strip. During the reverse rotation of the threaded rod, the second threaded sleeve simultaneously drives the front ring edge and the front sealing strip to fit tightly against the curtain wall panel inside the U-shaped receiving frame, and finally seals and fits the front and rear sides of the curtain wall panel together with the rear sealing strip. Finally, the front ring edge is subsequently reinforced through the threaded fixing cooperation of the perforated ear plate, the threaded hole and the fastening bolt.
[0019] Preferably, a rubber sealing ring gasket matched with the front side of the prefabricated outer frame is fixedly provided on the rear side of the front ring edge in S4.
[0020] The present invention provides a prefabricated steel structure building curtain wall connection device and method. Compared with the existing technology, it has the following beneficial effects:
[0021] (1) The assembly-type steel structure building curtain wall connection device and method pre-prepare a prefabricated outer frame, and set a push-pull mechanism, a gradient expansion mechanism and a self-sealing mechanism inside the prefabricated outer frame, so that when the curtain wall panels in the prefabricated outer frame are installed, the push-pull mechanism, the gradient expansion mechanism and the self-sealing mechanism can be coordinated to quickly complete batch receiving and placement, and the U-shaped receiving frames of different receiving mechanisms are arranged in a gradient manner to facilitate barrier-free placement of the curtain wall panels, and the front and rear sides of the curtain wall panels are sealed and fitted simultaneously, so as to achieve the effect of time-saving and efficient installation.
[0022] (2) The assembly type steel structure building curtain wall connection device and method elastically arranges angled pressure blocks on both sides of the inner cavity of the U-shaped receiving frame, so that when the curtain wall panel is assembled inside the U-shaped receiving frame, the assembly position of the curtain wall panel can be positioned and locked by elastic expansion and contraction of the angled pressure blocks.
[0023] (3) The assembly-type steel structure building curtain wall connection device and method, by arranging a push-pull plate on the top of the angled pressure block, and opening movable long grooves that are slidably matched on both sides of the top of the U-shaped receiving frame, makes it easy for the angled pressure block to slide and cooperate with the push-pull plate and the movable long groove, so as to achieve the effect of easy manual operation, so as to facilitate the subsequent disassembly and assembly of the curtain wall panel.
[0024] (4) The assembly-type steel structure building curtain wall connection device and method, by arranging a perforated ear plate, threaded holes and fastening bolts between the front bezel and the prefabricated outer frame, enables the front sealing strip on the rear side of the front bezel to be sealed and attached to the front side of the curtain wall panel, and can also be used to facilitate the reinforcement of the position of the front bezel and the front sealing strip after they are moved through the cooperation of the perforated ear plate, threaded holes and fastening bolts. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the external structure of the present invention;
[0026] Figure 2 It is a rear view of the prefabricated outer frame structure of the present invention;
[0027] Figure 3 It is a side view of the internal structure of the prefabricated outer frame of the present invention;
[0028] Figure 4 For the present invention Figure 3 A partial enlarged view of the middle A;
[0029] Figure 5 It is a cross-sectional view of the prefabricated outer frame structure of the present invention;
[0030] Figure 6 It is a schematic diagram of the push-pull mechanism structure of the present invention;
[0031] Figure 7 For the present invention Figure 6 A partial enlarged view of point B in the middle;
[0032] Figure 8 For the present invention Figure 6 A partial enlarged view of point C in the middle;
[0033] Fig. 9 It is an expanded view of the U-shaped receiving frame and the curtain wall panel structure of the present invention;
[0034] Fig.10 For the present invention Fig. 9 A partial enlarged view of point D in the middle;
[0035] Fig.11 It is a schematic diagram of the guide chute structure of the present invention;
[0036] Fig.12 A side view of the internal structure of the curtain wall panel of the present invention;
[0037] Fig.13 It is an expanded view of the prefabricated outer frame, rear edge ring, and front edge ring structure of the present invention;
[0038] Fig.14 For the present invention Fig.13 A partial enlarged view of point E in the middle;
[0039] Fig.15 It is a schematic diagram of the push-pull mechanism structure of the present invention.
[0040] In the figure: 1, prefabricated outer frame; 2, installation notch; 3, rear edge ring; 4, rear sealing strip; 5, push-pull mechanism; 501, U-shaped slide; 502, U-shaped slide plate; 503, U-shaped receiving frame; 504, curtain wall panel; 505, threaded rod; 506, first threaded sleeve; 507, time-delay vertical plate; 6, gradient expansion mechanism; 601, second return spring; 602, large-span U-shaped frame; 603, small-span U-shaped frame ; 7. Self-sealing mechanism; 701. Front ring edge; 702. Front sealing strip; 703. Second threaded sleeve; 704. Limiting long rod; 705. Limiting sliding sleeve; 8. Vertical slide groove; 9. Guide slide groove; 10. Guide slider; 11. First return spring; 12. Inclination pressure block; 13. Push-pull plate; 14. Movable long groove; 15. Ear plate with hole; 16. Threaded hole; 17. Fastening bolt; 18. Back plate with hole. DETAILED DESCRIPTION
[0041] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0042] See also Figure 1-15 , the present invention provides two technical solutions: Embodiment 1
[0043] A prefabricated steel structure building curtain wall connection device comprises a prefabricated outer frame 1 and an installation slot 2, wherein a plurality of installation slots 2 are provided, and the plurality of installation slots 2 are symmetrically arranged inside the prefabricated outer frame 1 in an up-down and left-right manner, an inner wall of the installation slot 2 is fixedly connected with a rear ring edge 3, a front side of the rear ring edge 3 is fixedly connected with a rear sealing strip 4, a vertical slide groove 8 is provided on the front side of the prefabricated outer frame 1, and both sides of the rear side of the prefabricated outer frame 1 are fixedly connected with a perforated back plate 18.
[0044] As a preferred embodiment: in order to facilitate the rapid placement of the curtain wall panel 504, a push-pull mechanism 5 is arranged between the vertical slide groove 8 and the prefabricated outer frame 1, and the push-pull mechanism 5 includes a U-shaped slide groove 501, the U-shaped slide groove 501 is opened inside the prefabricated outer frame 1, and there are two U-shaped slide grooves 501 in a vertical array, the U-shaped slide groove 501 is internally slidably connected with a U-shaped slide plate 502, both sides of the front side of the U-shaped slide plate 502 are fixedly connected with a U-shaped receiving frame 503 used in conjunction with the installation slot 2, the curtain wall panel 504 is slidably placed inside the U-shaped receiving frame 503, the rear side of the inner cavity of the vertical slide groove 8 is rotatably connected with a threaded rod 505 through a bearing, the surface of the threaded rod 505 is threadedly connected with a first threaded sleeve 506, the top and bottom of the first threaded sleeve 506 are provided with a delay vertical plate 507 used in conjunction with the U-shaped slide plate 502, and the front end of the threaded rod 505 passes through and extends to the front side of the prefabricated outer frame 1.
[0045] As a preferred embodiment: in order to facilitate the gradient arrangement of the U-shaped receiving frame 503 so as to place the curtain wall panel 504 without obstacle, a gradient unfolding mechanism 6 is arranged between the push-pull mechanism 5 and the prefabricated outer frame 1, and the gradient unfolding mechanism 6 includes a large-span U-shaped frame 602, and the large-span U-shaped frame 602 is fixedly arranged on the front side of the top U-shaped slide plate 502, and a small-span U-shaped frame 603 is fixedly connected to the front side of the bottom U-shaped slide plate 502, and the large-span U-shaped frame 602 and the small-span U-shaped frame 603 are respectively used in conjunction with adjacent delay vertical plates 507, and both sides of the front side of the U-shaped slide plate 502 are fixedly connected with a second return spring 601, and the end of the second return spring 601 is fixedly connected to the inner wall of the adjacent U-shaped slide groove 501.
[0046] As a preferred embodiment: in order to facilitate the convenient assembly and sealing of the curtain wall panel 504, a self-sealing mechanism 7 is arranged between the push-pull mechanism 5, the gradient unfolding mechanism 6 and the prefabricated outer frame 1, and the self-sealing mechanism 7 includes a second threaded sleeve 703, and the second threaded sleeve 703 is threadedly connected to the surface of the threaded rod 505. The front side of the prefabricated outer frame 1 is provided with a plurality of front ring edges 701 used in conjunction with the curtain wall panel 504, and the front ring edges 701 on both sides of the same side are fixedly connected by a bracket, and the rear side of the front ring edge 701 is fixedly connected with a front sealing strip 702 used in conjunction with the curtain wall panel 504, and the rear side of the second threaded sleeve 703 is fixedly connected to the front side of the adjacent front ring edge 701, and the top and bottom of the front side of the prefabricated outer frame 1 are fixedly connected to the limited position long rod 704, and the surface of the limited position long rod 704 is slidably connected to the limited position sliding sleeve 705, and the opposite sides of the two limited position sliding sleeves 705 are fixedly connected to the top and bottom of the second threaded sleeve 703 through the bracket. Embodiment 2
[0047] A prefabricated steel structure building curtain wall connection device comprises a prefabricated outer frame 1 and an installation slot 2, wherein a plurality of installation slots 2 are provided, and the plurality of installation slots 2 are symmetrically arranged inside the prefabricated outer frame 1 in an up-down and left-right manner, an inner wall of the installation slot 2 is fixedly connected with a rear ring edge 3, a front side of the rear ring edge 3 is fixedly connected with a rear sealing strip 4, a vertical slide groove 8 is provided on the front side of the prefabricated outer frame 1, and both sides of the rear side of the prefabricated outer frame 1 are fixedly connected with a perforated back plate 18.
[0048] As a preferred embodiment: in order to facilitate the rapid placement of the curtain wall panel 504, a push-pull mechanism 5 is arranged between the vertical slide groove 8 and the prefabricated outer frame 1, and the push-pull mechanism 5 includes a U-shaped slide groove 501, the U-shaped slide groove 501 is opened inside the prefabricated outer frame 1, and there are two U-shaped slide grooves 501 in a vertical array, the U-shaped slide groove 501 is internally slidably connected with a U-shaped slide plate 502, both sides of the front side of the U-shaped slide plate 502 are fixedly connected with a U-shaped receiving frame 503 used in conjunction with the installation slot 2, the curtain wall panel 504 is slidably placed inside the U-shaped receiving frame 503, the rear side of the inner cavity of the vertical slide groove 8 is rotatably connected with a threaded rod 505 through a bearing, the surface of the threaded rod 505 is threadedly connected with a first threaded sleeve 506, the top and bottom of the first threaded sleeve 506 are provided with a delay vertical plate 507 used in conjunction with the U-shaped slide plate 502, and the front end of the threaded rod 505 passes through and extends to the front side of the prefabricated outer frame 1.
[0049] As a preferred embodiment: in order to facilitate the gradient arrangement of the U-shaped receiving frame 503 so as to place the curtain wall panel 504 without obstacle, a gradient unfolding mechanism 6 is arranged between the push-pull mechanism 5 and the prefabricated outer frame 1, and the gradient unfolding mechanism 6 includes a large-span U-shaped frame 602, and the large-span U-shaped frame 602 is fixedly arranged on the front side of the top U-shaped slide plate 502, and a small-span U-shaped frame 603 is fixedly connected to the front side of the bottom U-shaped slide plate 502, and the large-span U-shaped frame 602 and the small-span U-shaped frame 603 are respectively used in conjunction with adjacent delay vertical plates 507, and both sides of the front side of the U-shaped slide plate 502 are fixedly connected with a second return spring 601, and the end of the second return spring 601 is fixedly connected to the inner wall of the adjacent U-shaped slide groove 501.
[0050] As a preferred embodiment: in order to facilitate the convenient assembly and sealing of the curtain wall panel 504, a self-sealing mechanism 7 is arranged between the push-pull mechanism 5, the gradient unfolding mechanism 6 and the prefabricated outer frame 1, and the self-sealing mechanism 7 includes a second threaded sleeve 703, and the second threaded sleeve 703 is threadedly connected to the surface of the threaded rod 505. The front side of the prefabricated outer frame 1 is provided with a plurality of front ring edges 701 used in conjunction with the curtain wall panel 504, and the front ring edges 701 on both sides of the same side are fixedly connected by a bracket, and the rear side of the front ring edge 701 is fixedly connected with a front sealing strip 702 used in conjunction with the curtain wall panel 504, and the rear side of the second threaded sleeve 703 is fixedly connected to the front side of the adjacent front ring edge 701, and the top and bottom of the front side of the prefabricated outer frame 1 are fixedly connected to the limited position long rod 704, and the surface of the limited position long rod 704 is slidably connected to the limited position sliding sleeve 705, and the opposite sides of the two limited position sliding sleeves 705 are fixedly connected to the top and bottom of the second threaded sleeve 703 through the bracket.
[0051] Guide grooves 9 are provided on both sides of the front and rear sides of the inner cavity of the U-shaped receiving frame 503, and guide sliders 10 are slidably connected inside the guide grooves 9. A first return spring 11 is fixedly connected between adjacent guide sliders 10 and the guide grooves 9, and an angled pressure block 12 used in conjunction with the curtain wall panel 504 is fixedly connected between the two guide sliders 10 on the same side. A push-pull plate 13 is fixedly connected to the top of the angled pressure block 12, and movable long grooves 14 slidably adapted to the push-pull plate 13 are provided on both sides of the top of the U-shaped receiving frame 503.
[0052] The top and bottom of both sides of the front ring edge 701 are fixedly connected with perforated ear plates 15, and the front side of the prefabricated outer frame 1 is provided with threaded holes 16 used in conjunction with the perforated ear plates 15, and fastening bolts 17 are threadedly connected between adjacent perforated ear plates 15 and threaded holes 16.
[0053] The advantages of the second embodiment over the first embodiment are as follows: by elastically setting the angled pressing blocks 12 on both sides of the inner cavity of the U-shaped receiving frame 503, when the curtain wall panel 504 is assembled inside the U-shaped receiving frame 503, the assembly position of the curtain wall panel 504 can be positioned and locked by elastically expanding and contracting the angled pressing blocks 12; by setting a push-pull plate 13 on the top of the angled pressing block 12, and opening movable long grooves 14 that are slidably adapted on both sides of the top of the U-shaped receiving frame 503, the angled pressing block 12 can be easily moved through the push-pull plate 13 and the movable long grooves. 14 is slidably matched to achieve the effect of easy manual control, so as to facilitate the subsequent disassembly and assembly of the curtain wall panel 504. By arranging a perforated ear plate 15, a threaded hole 16 and a fastening bolt 17 between the front ring edge 701 and the prefabricated outer frame 1, the front sealing strip 702 on the rear side of the front ring edge 701 can be sealed and attached to the front side of the curtain wall panel 504. The perforated ear plate 15, the threaded hole 16 and the fastening bolt 17 can be matched to facilitate the reinforcement of the position of the front ring edge 701 and the front sealing strip 702 after they are moved.
[0054] The present invention also discloses a method for connecting a prefabricated steel structure building curtain wall, which specifically comprises the following steps:
[0055] S1. Several prefabricated outer frames 1 are installed on the outer wall in order through the perforated back plate 18 and bolts, and then the threaded rod 505 is screwed. When the threaded rod 505 rotates, the first threaded sleeve 506 on its surface will move forward, and the first threaded sleeve 506 will synchronously drive the two delayed vertical plates 507 to move. The bottom delayed vertical plate 507 moves and first abuts against the front side of the inner cavity of the small-span U-shaped frame 603, and drives the small-span U-shaped frame 603 and the bottom U-shaped receiving frame 503 to move forward. Along with the movement of the bottom U-shaped receiving frame 503, the top delayed vertical plate 507 also successively abuts against the front side of the inner cavity of the large-span U-shaped frame 602, and lags to drive the top U-shaped slide plate 502 and the U-shaped receiving frame 503 to move forward. When the two upper and lower U-shaped receiving frames 503 on the same side move, they move in a stepped staggered and orderly manner until the two U-shaped receiving frames 503 on the same side move out of the installation slot 2.
[0056] S2, when the threaded rod 505 is screwed to cause the first threaded sleeve 506 to move forward, the second threaded sleeve 703 on the surface of the threaded rod 505 also moves forward successively. When the second threaded sleeve 703 moves forward, it will move ahead of the U-shaped receiving frame 503, causing the second threaded sleeve 703 to carry the front edge 701 and the front sealing strip 702 in advance to break away from the close fit with the U-shaped receiving frame 503, leaving enough smooth space for the subsequent placement of the curtain wall panel 504;
[0057] S3, after the curtain wall panel 504 moves forward out of the front side of the installation slot 2, the operator sequentially places multiple curtain wall panels 504 into the U-shaped receiving frame 503. During the process of lowering the curtain wall panel 504 into the U-shaped receiving frame 503, the two curtain wall panels 504 will laterally squeeze the tilt pressing block 12, so that after the curtain wall panel 504 is placed in place, the tilt pressing block 12 is easy to reset and limit the top of the curtain wall panel 504;
[0058] S4, seal back, finally the operator reversely screws the threaded rod 505, prompting the first threaded sleeve 506 to carry the two delay vertical plates 507, gradually push the rear side of the inner cavity of the large-span U-shaped frame 602 and the small-span U-shaped frame 603, respectively, prompting the large-span U-shaped frame 602 and the small-span U-shaped frame 603 to respectively drive the U-shaped receiving frame 503 and the curtain wall panel 504 to move backward, until the rear side of the curtain wall panel 504 is sealed and attached to the rear sealing strip 4. During the reverse screwing of the threaded rod 505, the second threaded sleeve 506 is screwed to the rear side of the curtain wall panel 504, and the second threaded sleeve 506 is screwed to the rear side of the curtain wall panel 504. The grooved sleeve 703 synchronously drives the front ring edge 701 and the front sealing strip 702 to fit tightly against the curtain wall panel 504 inside the U-shaped receiving frame 503, and finally seals the front and rear sides of the curtain wall panel 504 together with the rear sealing strip 4. Finally, the front ring edge 701 is subsequently reinforced by threaded fixing of the perforated ear plate 15, the threaded hole 16 and the fastening bolt 17, wherein the rear side of the front ring edge 701 is fixedly provided with a rubber sealing ring gasket used in conjunction with the front side of the prefabricated outer frame 1.
[0059] The above embodiments are only used to illustrate the present invention and are not intended to limit the technical solutions described in the present invention. Although the present invention has been described in detail with reference to the above embodiments, the present invention is not limited to the above specific implementation methods. Therefore, any modification or equivalent replacement of the present invention; and all technical solutions and improvements thereof that do not depart from the spirit and scope of the invention are included in the scope of the claims of the present invention.
[0060] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. An assembled steel structure building curtain wall connection device, comprising a prefabricated outer frame (1) and a mounting notch (2), wherein a plurality of the mounting notches (2) are provided, and the plurality of mounting notches (2) are symmetrically arranged in the interior of the prefabricated outer frame (1), characterized in that: The inner wall of the installation slot (2) is fixedly connected to a rear edge (3), the front side of the rear edge (3) is fixedly connected to a rear sealing strip (4), the front side of the prefabricated outer frame (1) is provided with a vertical slide groove (8), a push-pull mechanism (5) is provided between the vertical slide groove (8) and the prefabricated outer frame (1), a gradient expansion mechanism (6) is provided between the push-pull mechanism (5) and the prefabricated outer frame (1), and a self-sealing mechanism (7) is provided between the push-pull mechanism (5), the gradient expansion mechanism (6) and the prefabricated outer frame (1); The push-pull mechanism (5) comprises a U-shaped slide groove (501), wherein the U-shaped slide groove (501) is opened inside the prefabricated outer frame (1), and two U-shaped slide grooves (501) are arranged in a vertical array, the U-shaped slide groove (501) is slidably connected to a U-shaped slide plate (502) inside, and both sides of the front side of the U-shaped slide plate (502) are fixedly connected to a U-shaped receiving frame (503) used in conjunction with the installation slot (2), and a curtain wall panel (504) is slidably placed inside the U-shaped receiving frame (503), and the rear side of the inner cavity of the vertical slide groove (8) is rotatably connected to a threaded rod (505) through a bearing, and the surface of the threaded rod (505) is threadedly connected to a first threaded sleeve (506), and the top and bottom of the first threaded sleeve (506) are provided with a time-delay vertical plate (507) used in conjunction with the U-shaped slide plate (502), and the front end of the threaded rod (505) passes through and extends to the front side of the prefabricated outer frame (1); The gradient unfolding mechanism (6) comprises a large-span U-shaped frame (602), wherein the large-span U-shaped frame (602) is fixedly arranged on the front side of the top U-shaped slide plate (502), and a small-span U-shaped frame (603) is fixedly connected to the front side of the bottom U-shaped slide plate (502), and the large-span U-shaped frame (602) and the small-span U-shaped frame (603) are respectively used in conjunction with adjacent time-delay vertical plates (507), and both sides of the front side of the U-shaped slide plate (502) are fixedly connected to second return springs (601), and the ends of the second return springs (601) are fixedly connected to the inner walls of adjacent U-shaped slide grooves (501).
2. The assembly type steel structure building curtain wall connection device according to claim 1, characterized in that: The self-sealing mechanism (7) comprises a second threaded sleeve (703), the second threaded sleeve (703) being threadedly connected to the surface of the threaded rod (505); a plurality of front edges (701) for use with the curtain wall panel (504) are arranged on the front side of the prefabricated outer frame (1), and the front edges (701) on both sides of the same side are fixedly connected via a bracket; a front sealing strip (702) for use with the curtain wall panel (504) is fixedly connected to the rear side of the front edge (701); the rear side of the second threaded sleeve (703) is fixedly connected to the front side of an adjacent front edge (701); the top and bottom of the front side of the prefabricated outer frame (1) are fixedly connected to the limiting long rod (704); the surface of the limiting long rod (704) is slidably connected to the limiting sliding sleeve (705); and opposite sides of the two limiting sliding sleeves (705) are respectively fixedly connected to the top and bottom of the second threaded sleeve (703) via a bracket.
3. The assembly type steel structure building curtain wall connection device according to claim 2, characterized in that: Guide grooves (9) are provided on both sides of the front and rear sides of the inner cavity of the U-shaped receiving frame (503); guide sliders (10) are slidably connected inside the guide grooves (9); first return springs (11) are fixedly connected between adjacent guide sliders (10) and guide grooves (9); and an angled pressing block (12) matched with the curtain wall panel (504) is fixedly connected between two guide sliders (10) on the same side.
4. The assembly type steel structure building curtain wall connection device according to claim 3, characterized in that: A push-pull plate (13) is fixedly connected to the top of the tilting pressure block (12), and movable long grooves (14) slidably matched with the push-pull plate (13) are provided on both sides of the top of the U-shaped receiving frame (503).
5. The assembly type steel structure building curtain wall connection device according to claim 4, characterized in that: The top and bottom of both sides of the front ring edge (701) are fixedly connected with ear plates with holes (15), and the front side of the prefabricated outer frame (1) is provided with threaded holes (16) matched with the ear plates with holes (15), and fastening bolts (17) are threadedly connected between adjacent ear plates with holes (15) and threaded holes (16).
6. The assembly type steel structure building curtain wall connection device according to claim 5, characterized in that: Both sides of the rear side of the prefabricated outer frame (1) are fixedly connected with a back plate (18) with holes.
7. A method for connecting a prefabricated steel structure building curtain wall, using a prefabricated steel structure building curtain wall connection device as claimed in claim 6, characterized in that: The specific steps include: S1. A plurality of prefabricated outer frames (1) are sequentially installed on the outer wall through a perforated back plate (18) and bolts, and then the threaded rod (505) is screwed. When the threaded rod (505) rotates, a first threaded sleeve (506) on its surface moves forward, and the first threaded sleeve (506) simultaneously drives two delayed vertical plates (507) to move. The bottom delayed vertical plate (507) moves to first abut against the front side of the inner cavity of the small-span U-shaped frame (603), and drives the small-span U-shaped frame (603) and the bottom delayed vertical plate (507). The U-shaped receiving frame (503) moves forward, and along with the movement of the bottom U-shaped receiving frame (503), the top delay vertical plate (507) also successively abuts against the front side of the inner cavity of the large-span U-shaped frame (602), and lags to drive the top U-shaped slide plate (502) and the U-shaped receiving frame (503) to move forward, and the two upper and lower U-shaped receiving frames (503) on the same side move in a step-by-step staggered and orderly manner until the two U-shaped receiving frames (503) on the same side move out of the installation slot (2); S2, when the threaded rod (505) is rotated to cause the first threaded sleeve (506) to move forward, the second threaded sleeve (703) on the surface of the threaded rod (505) also moves forward successively. When the second threaded sleeve (703) moves forward, it moves ahead of the U-shaped receiving frame (503), causing the second threaded sleeve (703) to carry the front ring edge (701) and the front sealing strip (702) in advance to break away from the close fit with the U-shaped receiving frame (503), leaving enough smooth space for the subsequent placement of the curtain wall panel (504); S3, after the curtain wall panel (504) is moved forward out of the front side of the installation slot (2), the operator sequentially places the plurality of curtain wall panels (504) into the interior of the U-shaped receiving frame (503). During the process of lowering the curtain wall panel (504) into the interior of the U-shaped receiving frame (503), the two curtain wall panels (504) will laterally squeeze the tilting pressing block (12), so that after the curtain wall panel (504) is placed in place, the tilting pressing block (12) is easy to reset and limit the top of the curtain wall panel (504); S4, seal reinstallation, finally the operator reversely rotates the threaded rod (505), causing the first threaded sleeve (506) to carry the two delayed vertical plates (507), gradually pushing the rear side of the inner cavity of the large-span U-shaped frame (602) and the small-span U-shaped frame (603), respectively, causing the large-span U-shaped frame (602) and the small-span U-shaped frame (603) to respectively drive the U-shaped receiving frame (503) and the curtain wall panel (504) to move backward, until the rear side of the curtain wall panel (504) is sealed and attached to the rear sealing strip (4). During the reverse screwing of the threaded rod (505), the second threaded sleeve (703) simultaneously drives the front ring edge (701) and the front sealing strip (702) to be closely attached to the curtain wall panel (504) inside the U-shaped receiving frame (503), and finally seals and fits the front and rear sides of the curtain wall panel (504) together with the rear sealing strip (4), and finally, the front ring edge (701) is subsequently reinforced by threaded fixing cooperation of the perforated ear plate (15), the threaded hole (16) and the fastening bolt (17).
8. The method for connecting a prefabricated steel structure building curtain wall according to claim 7, characterized in that: A rubber sealing ring gasket matched with the front side of the prefabricated outer frame (1) is fixedly arranged on the rear side of the front ring edge (701) in S4.
Citation Information
Patent Citations
Large-span curtain wall system with rigid-flexible buffer structure
CN118390721A