Construction safety progress tracking system and method based on video monitoring
By identifying and dividing the construction area, adjusting the status of the monitoring device, generating construction environment and scene coefficients, and identifying abnormal behaviors, the problems of missing construction monitoring data and reduced pertinence in the existing technology are solved, and effective monitoring and control of the construction environment and progress are achieved. Exception handling.
Patent Information
- Application Number
- CN202411107227.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-08-13
AI Technical Summary
Existing construction safety progress tracking methods are difficult to monitor in real time when the construction tasks are heavy and the area is large, resulting in missing monitoring data and reduced pertinence, and cannot effectively respond to the construction progress and risks in the construction area.
By identifying the target scene, the monitoring area is divided into key sub-areas and non-critical sub-areas, the sleep and operating status of the monitoring device is adjusted, the construction environment and scene coefficients are generated, abnormal behaviors and alarm density are identified, and targeted monitoring and alarms are achieved.
It improves the monitoring effect of the construction environment and progress, avoids monitoring omissions and waste of resources, and can handle abnormal situations in a timely manner to ensure construction safety and progress.
Smart Images

Figure CN118646960B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction safety management, and in particular to a construction safety progress tracking system and method based on video monitoring. Background Art
[0002] Construction safety management refers to a series of management activities that aim to reduce or eliminate potential safety hazards at the construction site, protect the personal safety and health of construction workers and surrounding personnel, protect construction equipment and materials from loss, and ensure the smooth progress of construction activities by formulating and implementing a series of safety regulations, operating procedures and preventive measures during the implementation of construction projects. It covers safety education and training, risk assessment and control, accident emergency response, safety inspection and supervision, and is an indispensable and important part of project management.
[0003] In the Chinese invention patent application with application publication number CN117634680A, a method for intelligent tracking of engineering construction progress is disclosed, including: obtaining historical time information of each stage in the engineering construction process; constructing a sample data set with unit type, unit name, unit engineering quantity and historical time information of each stage as data source; based on the sample data set, a construction progress prediction model is established by using a regression analysis method, and the time for each stage and the entire process of engineering construction is predicted by the construction progress prediction model. The construction progress prediction model provided by this application can change the traditional engineering model, and can better predict the time for each construction stage in the engineering project, thereby optimizing engineering supervision, helping owners, supervisors, and construction units to strengthen information sharing, and can timely conduct all-round, full-process, and full-element supervision and control of engineering construction.
[0004] Combined with the above application and the contents of the prior art:
[0005] When the construction task is heavy and the construction area is large, it is difficult to conduct real-time supervision and response, and there is a greater risk of accidents or safety hazards during construction tasks. Therefore, in order to reduce this risk, existing construction sites usually install video surveillance devices, which continuously collect data in the construction area. Based on the analysis and identification of the collected data, the construction progress and construction risks in the construction area can be grasped.
[0006] In the existing construction safety progress tracking methods, video surveillance devices are usually evenly installed in the construction area and are kept in operation for a long time. In this case, there are fewer omissions when collecting data in the construction area, and the monitoring data is more comprehensive. However, there may be large differences in the construction progress and status at various locations in the construction area. In particular, when the construction tasks and number of people at different locations vary greatly and the corresponding construction environment is also poor, if too few video surveillance devices are installed in the corresponding construction area, it may be difficult for the video surveillance devices to obtain effective content during operation, resulting in more invalid monitoring, which greatly reduces the targeted nature of the monitoring and may affect the construction process, etc.
[0007] To this end, the present invention provides a construction safety progress tracking system and method based on video monitoring. Summary of the invention
[0008] 1. Technical issues to be resolved
[0009] In view of the shortcomings of the prior art, the present invention provides a construction safety progress tracking system and method based on video monitoring. By switching some monitoring devices in non-critical sub-areas between sleep and running states according to the identified target scene, abnormal behavior in the monitoring area is identified, and the abnormal degree during construction is generated from the abnormal behavior data. If the abnormal degree exceeds the abnormal threshold, an alarm instruction is generated to the outside, and the corresponding abnormal behavior data is sent out together; the current construction status is evaluated based on the obtained alarm density. Corresponding management measures can be taken for the current construction process, thereby solving the technical problems raised in the background technology.
[0010] (II) Technical solution
[0011] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0012] The construction safety progress tracking method based on video monitoring includes collecting data in the monitoring area and generating a construction environment coefficient from the acquired construction environment data. , if the construction environment coefficient Exceeding expectations, issuing regional screening instructions to the outside;
[0013] After the monitoring area is divided into multiple sub-areas, the construction scene coefficient is generated from the construction status data in the sub-areas , based on the construction scenario coefficient Divide the monitoring area into non-critical sub-areas and critical sub-areas;
[0014] After monitoring devices are installed in the monitoring area and there are no blind spots, the density of monitoring devices installed in the key sub-areas is restricted, and some monitoring devices in non-key sub-areas are switched between sleep and running states according to the identified target scenarios;
[0015] Identify abnormal behavior in the monitoring area and generate the abnormal degree of construction from the abnormal behavior data , if the abnormality If it exceeds expectations, an alarm instruction will be generated externally, and the corresponding abnormal behavior data will be sent out together with the alarm instruction;
[0016] Generate alarm density based on the alarm command issued , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient Do not exceed expectations and issue progress adjustment instructions.
[0017] Furthermore, data is collected in the monitoring area and a construction environment data set is generated after aggregation; a construction environment coefficient is generated from the construction environment data set , among which, construction noise And dust concentration After being treated as dimensionless, it is then as follows:
[0018] ;
[0019] Weight coefficient, , , is a constant correction factor.
[0020] Furthermore, after receiving the area screening instruction, the monitoring area is divided into multiple sub-areas, the construction status data in the sub-areas are identified, and after the obtained construction status data are aggregated, the construction status data set in each sub-area is obtained; the construction scene coefficient is generated from the construction status data , if the construction scene coefficient If the construction scene coefficient exceeds the scene threshold, the corresponding sub-area is determined as a key sub-area. If the scene threshold is not exceeded, the corresponding sub-region is regarded as a non-critical sub-region.
[0021] Furthermore, the frequency of workers entering and leaving And material consumption rate Perform linear normalization and map the corresponding data values to the interval The construction scenario coefficient is generated as follows: :
[0022] ;
[0023] in, is the number of data detection cycles, It is i The frequency of workers entering and exiting during a detection cycle, is the average frequency of workers entering and leaving, It is i Material consumption rate within a detection cycle, is the average material consumption rate, weight coefficient: , ,and .
[0024] Furthermore, a digital twin model for construction status monitoring is trained and acquired. After the installation position of the monitoring device is determined in the sub-area, the digital twin model for construction status monitoring is used to predict the monitoring effect. If there is a monitoring blind spot in the sub-area, the position of the monitoring device is adjusted.
[0025] Furthermore, after there is no monitoring blind spot in the key sub-area, the construction scene coefficient in the key sub-area is obtained. And construction environment factor The density of monitoring device installation is constrained, and the monitoring device is installed at the installation location that meets the constraints, as follows:
[0026] ;
[0027] in, The number of monitoring devices installed. It is i Monitoring devices to j The shortest distance between monitoring devices, is the average value of the distance.
[0028] Furthermore, after a scene recognition model is obtained by training the collected sample data, the monitoring device in operation obtains corresponding monitoring data in a non-critical sub-area, and the scene recognition model obtained by training is used to identify the current construction scene;
[0029] In non-critical sub-areas, some monitoring devices are placed in a dormant state. If the construction scene is identified as a target scene, the dormant monitoring devices are activated.
[0030] Furthermore, after obtaining the monitoring data of each monitoring node in the sub-area, the trained abnormal behavior recognition model is used to identify the abnormal behavior in the sub-area, and the acquired abnormal behavior data are aggregated to generate an abnormal behavior data set; the abnormal degree of construction during construction is generated from the abnormal behavior data set. , as follows:
[0031] ;
[0032] in, is the number of abnormal behaviors, It is i Abnormal behavior to j The time interval of abnormal behavior, is the average value of the time interval, and the weight coefficient is: , ,and .
[0033] Furthermore, the alarm density is constructed by obtaining the time node at which the alarm instruction is received and the location information at which the alarm instruction is generated during the observation period. , if the alarm density If the density is lower than the preset threshold, a progress tracking instruction will be issued to the outside world; The construction is as follows:
[0034] ;
[0035] Weight coefficient: , ,and ;
[0036] is the number of alarm instructions, It is i Alarm command to j The time interval between alarm instructions, is the average value of the time interval, is the acceptable value for the time interval; It is i Alarm command to j The distance interval of each alarm command, is the average value of the distance interval, are acceptable values for the distance interval.
[0037] Furthermore, after receiving the progress tracking instruction, the construction progress recognition model is trained and acquired. After acquiring the monitoring data in each sub-area, the trained progress recognition model is used to identify the construction progress in the sub-area, and the obtained recognition result is compared with the project schedule to generate a progress tracking report.
[0038] Furthermore, after obtaining the progress tracking report, the progress coefficient is generated according to the obtained gap ratio. , among which, the gap ratio Perform linear normalization and map the corresponding data values to the interval In the following way:
[0039] ;
[0040] in, is the number of sub-regions, It is i The difference ratio within each sub-region, is the average value of the gap ratio, is the qualified target value of the gap ratio; weight coefficient: , ,and .
[0041] The construction safety progress tracking system based on video monitoring includes an environmental analysis unit, which collects data in the monitoring area and generates a construction environment coefficient based on the acquired construction environment data. , if the construction environment coefficient Exceeding expectations, issuing regional screening instructions to the outside;
[0042] The area screening unit divides the monitoring area into multiple sub-areas and generates the construction scene coefficient based on the construction status data in the sub-areas. , based on the construction scenario coefficient Divide the monitoring area into non-critical sub-areas and critical sub-areas;
[0043] The monitoring device control unit, after installing the monitoring devices in the monitoring area and making sure that there are no monitoring blind spots, constrains the installation density of the monitoring devices in the key sub-areas, and switches some monitoring devices in the non-key sub-areas between the sleep state and the running state according to the identified target scene;
[0044] The abnormal alarm unit identifies abnormal behaviors in the monitoring area and generates the abnormal degree of construction from the abnormal behavior data. , if the abnormality When the abnormal threshold is exceeded, an alarm instruction is generated externally, and the corresponding abnormal behavior data is sent out together with the alarm instruction;
[0045] The construction progress tracking unit generates alarm density according to the issued alarm instructions , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient Do not exceed expectations and issue progress adjustment instructions.
[0046] (III) Beneficial effects
[0047] The present invention provides a construction safety progress tracking system and method based on video monitoring, which has the following beneficial effects:
[0048] 1. Based on the construction environment coefficient Evaluate the current construction environment. When the current construction environment is poor, adjust the construction environment to facilitate targeted treatment.
[0049] 2. Based on the construction scene coefficient By classifying each sub-area, dividing the construction area into key sub-areas and non-key sub-areas, and adopting different monitoring methods when monitoring them, better monitoring results can be obtained, and omissions or gaps can be avoided when tracking construction progress and safety.
[0050] 3. Through training, a digital twin model for construction status monitoring is obtained to predict the monitoring effect of the monitoring device and determine whether there is a monitoring blind spot. If there is a monitoring blind spot, the installation position can be adjusted to ensure the monitoring effect. The installation position and number of the monitoring device are adapted to the current construction environment and status. When entering the construction state in the key sub-area, the monitoring effect can be avoided from being affected and the acquired monitoring data can be avoided from being missed.
[0051] 4. The monitoring devices are divided into working state and sleeping state. When a target event occurs or a target scene exists in a non-critical sub-area, the monitoring devices in the sleeping state are activated. By adjusting the working state of the monitoring devices and reducing unnecessary monitoring, the effect of resource saving can be achieved.
[0052] 5. By analyzing and identifying abnormal behaviors, when there are abnormal behaviors or non-compliant scenarios in the corresponding area, it can promptly issue an alarm to the outside and handle them; Determine whether it is necessary to issue an alarm command to the outside, and send the corresponding monitoring data when an alarm is needed, complete the abnormal alarm process, and be able to deal with it quickly and specifically when an abnormality occurs to avoid affecting the construction environment and construction process.
[0053] 6. Record and obtain alarm density , it is possible to evaluate the current construction status based on the alarm density obtained Appropriate management measures can be taken for the current construction process.
[0054] 7. Through the collection and identification of monitoring data, the construction progress in each sub-area is evaluated and judged. After comparing the construction progress with the construction plan, the progress coefficient is constructed based on the progress deviation data. , by the progress coefficient By evaluating the current construction progress as a whole, it is possible to make targeted adjustments to the overall construction progress, which can not only ensure construction safety, but also ensure the construction progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 It is a flow chart of a construction safety progress tracking method based on video monitoring of the present invention;
[0056] Figure 2 It is a structural schematic diagram of the construction safety progress tracking system based on video monitoring of the present invention. DETAILED DESCRIPTION
[0057] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0058] See also Figure 1 The present invention provides a construction safety progress tracking method based on video monitoring, comprising:
[0059] Step 1: Collect data in the monitoring area and generate the construction environment coefficient from the acquired construction environment data , if the construction environment coefficient Exceeding expectations, issuing regional screening instructions to the outside;
[0060] The step 1 includes the following contents:
[0061] Step 101: When it is necessary to monitor the construction process, the area covered by the construction task is defined as a monitoring area, and data is collected in the monitoring area, including noise and dust concentration during construction in the monitoring area, and the degree of overlap of various construction tasks between construction areas, etc., and then the data is summarized to generate a construction environment data set;
[0062] Step 102: Generate construction environment coefficients from the construction environment data set , among which, construction noise And dust concentration After being treated as dimensionless, the corresponding weight coefficient is determined by referring to the hierarchical analysis method, and then according to the following method:
[0063] ;
[0064] Weight coefficient, , , is a constant correction coefficient whose value falls within ;
[0065] Based on the management expectations of the construction environment in the construction area based on historical data, the environmental threshold is set in advance; if the construction environment coefficient If the pre-set environmental threshold is exceeded, it means that the construction environment in the current construction area is poor. At this time, an area screening instruction is issued to the outside;
[0066] When using, combine the contents in steps 101 and 102:
[0067] When it is necessary to monitor and track the construction progress and construction safety, the construction environment data is collected and the construction environment coefficient is constructed. , based on the construction environment coefficient Evaluate the current construction environment. When the current construction environment is poor, adjust the construction environment to facilitate targeted treatment.
[0068] Combined with the above application and the contents of the prior art:
[0069] When the construction task is heavy and the construction area is large, it is difficult to conduct real-time supervision and response, and there is a greater risk of accidents or safety hazards during construction tasks. Therefore, in order to reduce this risk, existing construction sites usually install video surveillance devices, which continuously collect data in the construction area. Based on the analysis and identification of the collected data, the construction progress and construction risks in the construction area can be grasped.
[0070] In the existing construction safety progress tracking methods, video surveillance devices are usually evenly installed in the construction area and are kept in operation for a long time. In this case, there are fewer omissions when collecting data in the construction area, and the monitoring data is more comprehensive. However, there may be large differences in the construction progress and status at various locations in the construction area. In particular, when the construction tasks and number of people at different locations vary greatly and the corresponding construction environment is also poor, if too few video surveillance devices are installed in the corresponding construction area, it may be difficult for the video surveillance devices to obtain effective content during operation, resulting in more invalid monitoring, which greatly reduces the targeted nature of the monitoring and may affect the construction process, etc.
[0071] Step 2: After dividing the monitoring area into multiple sub-areas, the construction scene coefficient is generated from the construction status data in the sub-areas , based on the construction scenario coefficient Divide the monitoring area into non-critical sub-areas and critical sub-areas;
[0072] The step 2 includes the following contents:
[0073] Step 201: After receiving the area screening instruction, the monitoring area is divided into multiple sub-areas, and the construction status data in the sub-areas are identified, including the frequency of workers entering and exiting, the material consumption rate, etc.; after the obtained construction status data is aggregated, the construction status data set in each sub-area is obtained;
[0074] Step 202: After obtaining the construction status data set in each sub-area, the construction scene coefficient is generated from the construction status data. , based on the construction scenario coefficient Each sub-area is marked, and the frequency of workers entering and leaving is And material consumption rate Perform linear normalization and map the corresponding data values to the interval In the following way:
[0075] ;
[0076] in, is the number of data detection cycles, It is i The frequency of workers entering and exiting during a detection cycle, is the average frequency of workers entering and leaving, It is i Material consumption rate within a detection cycle, is the average material consumption rate, weight coefficient: , ,and ;The weight coefficient can be obtained by referring to the hierarchical analysis method;
[0077] Based on historical data and management expectations for construction scenarios, scenario thresholds are pre-set; if the construction scenario coefficient If the scene threshold is exceeded, it means that the construction in the corresponding sub-area is relatively busy. In this case, the corresponding sub-area is determined as a key sub-area. If the scene threshold is not exceeded, the corresponding sub-area is regarded as a non-critical sub-area;
[0078] When using, combine the contents in steps 201 and 202:
[0079] By collecting construction status data, such as the flow data of workers and materials, and using it to construct construction scene coefficients in each sub-area , based on the construction scenario coefficient By classifying each sub-area and dividing the construction area into key sub-areas and non-key sub-areas, different monitoring methods can be adopted when monitoring them, which can obtain better monitoring results and avoid omissions or gaps when tracking construction progress and safety.
[0080] Step 3: After monitoring devices are installed in the monitoring area and there are no blind spots, the density of monitoring devices in the key sub-areas is constrained, and some monitoring devices in non-key sub-areas are switched between sleep and running states according to the identified target scenarios;
[0081] The step three includes the following contents:
[0082] Step 301: collect the size, shape and construction status data in the sub-area as sample data, train a convolutional neural network with the sample data, obtain a construction status monitoring digital twin model, determine the installation position of the monitoring device in the sub-area, and use the construction status monitoring digital twin model to predict the monitoring effect. If there is a monitoring blind spot in the sub-area, adjust the position of the monitoring device to ensure that each area is covered and there is no monitoring blind spot.
[0083] When in use, after the installation location of the monitoring device is preliminarily determined, the construction status monitoring digital twin model is obtained through training, which can predict the monitoring effect of the monitoring device and determine whether there is a monitoring blind spot. If there is a monitoring blind spot, the installation location can be adjusted to ensure the monitoring effect;
[0084] Step 302: After there is no monitoring blind spot in the key sub-area, the construction scene coefficient in the key sub-area is obtained. And construction environment factor The density of monitoring device installation is constrained, and the monitoring device is installed at the installation location that meets the constraints, as follows:
[0085] ;
[0086] in, The number of monitoring devices installed. It is i Monitoring devices to j The shortest distance between monitoring devices, is the average value of the distance;
[0087] When in use, the installation position of the monitoring device is constrained in the key sub-area, so that the installation position and number of the monitoring device are adapted to the current construction environment and state. When the construction state is entered in the key sub-area, the monitoring effect can be avoided from being affected and the acquired monitoring data can be avoided from being missed;
[0088] Step 303: After a scene recognition model is obtained through training with the collected sample data, the monitoring device in operation obtains corresponding monitoring data in the non-critical sub-area, and the current construction scene is recognized by the scene recognition model obtained through training;
[0089] Put some monitoring devices in a dormant state in non-critical sub-areas, and if the construction scene is identified as a target scene, start the dormant monitoring devices;
[0090] When using, combine the contents in steps 301 to 303:
[0091] For non-critical sub-areas, the monitoring devices are divided into working state and sleep state. When a target event occurs or a target scene exists in a non-critical sub-area, the monitoring devices in the sleep state are activated. By adjusting the working state of the monitoring devices, unnecessary monitoring is reduced, thereby achieving the effect of resource saving.
[0092] Step 4: Identify abnormal behaviors in the monitoring area and generate the abnormal degree during construction from the abnormal behavior data , if the abnormality When the abnormal threshold is exceeded, an alarm instruction is generated externally, and the corresponding abnormal behavior data is sent out together with the alarm instruction;
[0093] The step 4 includes the following contents:
[0094] Step 401: After training the machine learning algorithm with the sample data, the trained abnormal behavior recognition model is obtained. After obtaining the monitoring data on each monitoring node in the sub-area, the trained abnormal behavior recognition model is used to identify abnormal behaviors in the sub-area, for example, monitoring the wearing of safety equipment of workers and similar behaviors, including the wearing of safety helmets and goggles, etc. The acquired abnormal behavior data is aggregated to generate an abnormal behavior data set;
[0095] When in use, based on the acquisition of monitoring data, by analyzing and identifying abnormal behaviors, when there are abnormal behaviors or non-compliant scenarios in the corresponding area, it can promptly issue an alarm to the outside and handle them;
[0096] Step 402: Generate the abnormal degree during construction from the abnormal behavior data in the abnormal behavior data set , as follows:
[0097] ;
[0098] in, is the number of abnormal behaviors, It is i Abnormal behavior to jThe time interval of abnormal behavior, is the average value of the time interval, and the weight coefficient is: , ,and ;The value of the weight coefficient remains consistent with the previous value;
[0099] Based on historical data and abnormal management during construction, the abnormal threshold is set in advance; if the abnormal degree If the abnormal threshold is exceeded, it means that the frequency of abnormal behavior in the corresponding sub-area is high and needs to be processed in time. At this time, an alarm instruction is generated to the outside;
[0100] When an alarm instruction needs to be issued to the outside, the corresponding abnormal behavior data, such as the corresponding monitoring image data, is sent together, for example, the alarm information is pushed to the management personnel in real time via SMS, email or mobile phone application;
[0101] When using, combine the contents in steps 401 and 402:
[0102] When abnormal behaviors occur several times continuously, the corresponding abnormality degree is calculated by recording the time and location of the abnormal behavior. , according to the degree of abnormality Determine whether it is necessary to issue an alarm command to the outside, and send the corresponding monitoring data when an alarm is needed, so as to complete the abnormal alarm process. When an abnormality occurs, it can be handled quickly and specifically to avoid affecting the construction environment and construction process.
[0103] Step 5: Generate alarm density based on the issued alarm command , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient If the schedule does not exceed expectations, a progress adjustment instruction will be issued.
[0104] The step five includes the following contents:
[0105] Step 501: After setting the observation period, obtain the time node of receiving the alarm instruction and the location information of generating the alarm instruction within the observation period and then construct the alarm density , as follows:
[0106] ;
[0107] is the number of alarm instructions, It is i Alarm command to j The time interval between alarm instructions, is the average value of the time interval, is the acceptable value for the time interval; It is i Alarm command to j The distance interval of each alarm command, is the average value of the distance interval, is the acceptable value of the distance interval; weight coefficient: , ,and ;
[0108] If the alarm intensity If the frequency is lower than the preset density threshold, it means that the frequency of abnormal behavior is within an acceptable range. At this time, a progress tracking instruction is issued to the outside.
[0109] When in use, when the frequency of alarm instructions issued in the construction area is low, it means that fewer behaviors are generated, and the construction process and progress are less affected. Therefore, by recording and obtaining the alarm density , it is possible to evaluate the current construction status based on the alarm density obtained Appropriate management measures can be taken for the current construction process.
[0110] Step 502: After receiving the progress tracking instruction, the convolutional neural network is trained to obtain a construction progress recognition model. After obtaining the monitoring data in each sub-area, the trained progress recognition model is used to identify the construction progress in the sub-area, and the obtained recognition result is compared with the project schedule to generate a progress tracking report.
[0111] Step 503: After obtaining the progress tracking report, analyze the gap between the actual progress and the planned progress, and generate a progress coefficient based on the obtained gap ratio. , among which, the gap ratio Perform linear normalization and map the corresponding data values to the interval In the following way:
[0112] ;
[0113] in, is the number of sub-regions, It is i The difference ratio within each sub-region, is the average value of the gap ratio, is the qualified target value of the gap ratio; weight coefficient: , ,and ;The weight coefficient can be obtained by referring to the hierarchical analysis method;
[0114] If the progress coefficient If the progress does not exceed the preset progress threshold, a progress adjustment instruction is issued. After receiving the progress adjustment instruction, the construction progress in each sub-area can be adjusted in a timely manner according to the actual situation of the construction site, for example, the construction tasks can be adjusted, the number of construction personnel can be dispatched, etc.;
[0115] When using, combine the contents in steps 501 to 503:
[0116] When managing the current construction progress, the construction progress data in each sub-area can be obtained through the collection and identification of monitoring data, so as to evaluate and judge the construction progress in each sub-area. After comparing the construction progress with the construction plan, the progress coefficient can be constructed based on the progress deviation data of each sub-area. , by the progress coefficient By evaluating the current construction progress as a whole, it is possible to make targeted adjustments to the overall construction progress, which can not only ensure construction safety, but also ensure the construction progress.
[0117] See also Figure 2 The present invention provides a construction safety progress tracking system based on video monitoring, comprising:
[0118] The environmental analysis unit collects data in the monitoring area and generates the construction environment coefficient based on the acquired construction environment data. , if the construction environment coefficient Exceeding expectations, issuing regional screening instructions to the outside;
[0119] The area screening unit divides the monitoring area into multiple sub-areas and generates the construction scene coefficient based on the construction status data in the sub-areas. , based on the construction scenario coefficient Divide the monitoring area into non-critical sub-areas and critical sub-areas;
[0120] The monitoring device control unit, after installing the monitoring devices in the monitoring area and making sure that there are no monitoring blind spots, constrains the installation density of the monitoring devices in the key sub-areas, and switches some monitoring devices in the non-key sub-areas between the sleep state and the running state according to the identified target scene;
[0121] The abnormal alarm unit identifies abnormal behaviors in the monitoring area and generates the abnormal degree of construction from the abnormal behavior data. , if the abnormality When the abnormal threshold is exceeded, an alarm instruction is generated externally, and the corresponding abnormal behavior data is sent out together with the alarm instruction;
[0122] The construction progress tracking unit generates alarm density according to the issued alarm instructions , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient Do not exceed expectations and issue progress adjustment instructions.
[0123] The Analytic Hierarchy Process (AHP) is a decision-making method that decomposes decision-related elements into levels such as goals, criteria, and plans, and conducts qualitative and quantitative analysis on this basis. It is particularly suitable for dealing with target systems with hierarchical and staggered evaluation indicators, and when the target value is difficult to describe quantitatively, the AHP is an effective decision-making tool.
[0124] The core of the hierarchical analysis method is to decompose the decision problem into multiple levels to form a hierarchical structure, which usually includes the target level, the criterion level, the sub-criterion level and the solution level. By solving the eigenvector of the judgment matrix, the priority weight of each element of each level to an element of the previous level is obtained, and the final weight of each alternative solution to the total goal is recursively merged by the weighted sum method, so as to find the optimal solution.
[0125] The above embodiments can be implemented in whole or in part by software, hardware, firmware or any other combination. When implemented by software, the above embodiments can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions or computer programs. When the computer instructions or computer programs are loaded or executed on a computer, the process or function described in the embodiment of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from one website, computer, server or data center to another website, computer, server or data center by wired (e.g., infrared, wireless, microwave, etc.). The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or data center that contains one or more available media sets. The available medium can be a magnetic medium (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a semiconductor medium. The semiconductor medium can be a solid-state hard disk.
[0126] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0127] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0128] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only some logical function divisions. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0129] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0130] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0131] If the function is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, and other media that can store program codes.
[0132] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A construction safety progress tracking method based on video monitoring, characterized in that: include, Data collection is carried out in the monitoring area, and the construction environment coefficient is generated from the acquired construction environment data , if the construction environment coefficient If the number of construction environment data exceeds expectations, a regional screening instruction is issued to the outside; data is collected in the monitoring area, and a construction environment data set is generated after aggregation; a construction environment coefficient is generated from the construction environment data set , among which, construction noise And dust concentration After being treated as dimensionless, it is then as follows: ; in, and is the weight coefficient, , , is the constant correction factor; After the monitoring area is divided into multiple sub-areas, the construction scene coefficient is generated from the construction status data in the sub-areas , based on the construction scenario coefficient The monitoring area is divided into non-critical sub-areas and critical sub-areas; among them, the frequency of workers entering and leaving And material consumption rate Perform linear normalization and map the corresponding data values to the interval The construction scenario coefficient is generated as follows: : ; in, is the number of data detection cycles, is the frequency of workers entering and leaving during the i1th detection period, is the average frequency of workers entering and leaving, is the material consumption rate in the i1th detection cycle, is the average material consumption rate, weight coefficient: , ,and ; After monitoring devices are installed in the monitoring area and there are no blind spots, the density of monitoring devices installed in the key sub-areas is restricted, and some monitoring devices in non-key sub-areas are switched between sleep and running states according to the identified target scenarios; Identify abnormal behavior in the monitoring area and generate the abnormal degree of construction from the abnormal behavior data , if the abnormality If the number of abnormal behaviors exceeds expectations, an alarm instruction is generated to the outside, and the corresponding abnormal behavior data is sent out together with the alarm instruction; wherein, after obtaining the monitoring data on each monitoring node in the sub-area, the abnormal behavior in the sub-area is identified by the trained abnormal behavior recognition model, and the acquired abnormal behavior data is aggregated to generate an abnormal behavior data set; Generate the abnormal degree of construction from the abnormal behavior data set , as follows: ; in, is the number of abnormal behaviors, is the time interval from the i3th abnormal behavior to the j3th abnormal behavior, is the average value of the time interval, and the weight coefficient is: , ,and ; Generate alarm density based on the alarm command issued , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient If the alarm is received within the observation period, the alarm density is constructed. , if the alarm density If the density is below the threshold, a progress tracking instruction is issued to the outside world; Among them, the alarm density The construction is as follows: ; Weight coefficient: , ,and ; is the number of alarm instructions, is the time interval from the i4th alarm instruction to the j4th alarm instruction, is the average value of the time interval, is the acceptable value for the time interval; is the distance interval from the i4th alarm instruction to the j4th alarm instruction, is the average value of the distance interval, is the acceptable value of the distance interval; After receiving the area screening instruction, the monitoring area is divided into multiple sub-areas, the construction status data in the sub-areas are identified, and after the obtained construction status data is aggregated, a set of construction status data in each sub-area is obtained; Generate construction scenario coefficients from construction status data , if the construction scene coefficient If the construction scene coefficient exceeds the scene threshold, the corresponding sub-area is determined as a key sub-area. If the scene threshold is not exceeded, the corresponding sub-area is regarded as a non-critical sub-area; After there is no monitoring blind area in the key sub-area, according to the construction scene coefficient in the key sub-area And construction environment factor The density of monitoring device installation is constrained, and the monitoring device is installed at the installation location that meets the constraints, as follows: ; in, The number of monitoring devices installed. is the shortest distance from the i2th monitoring device to the j2th monitoring device, is the average value of the distance; After obtaining the progress tracking report, generate the progress coefficient based on the obtained gap ratio , among which, the gap ratio Perform linear normalization and map the corresponding data values to the interval In the following way: ; in, is the number of sub-regions, is the gap ratio within the i5th sub-region, is the average value of the gap ratio, is the qualified target value of the gap ratio; weight coefficient: , ,and .
2. The construction safety progress tracking method based on video monitoring according to claim 1 is characterized in that: The digital twin model for construction status monitoring is trained and acquired. After the installation location of the monitoring device is determined in the sub-area, the digital twin model for construction status monitoring is used to predict the monitoring effect. If there is a monitoring blind spot in the sub-area, the location of the monitoring device is adjusted.
3. The construction safety progress tracking method based on video monitoring according to claim 2 is characterized in that: After a scene recognition model is obtained through training with collected sample data, and the monitoring device in operation obtains corresponding monitoring data in a non-critical sub-area, the current construction scene is identified by using the scene recognition model obtained through training; In non-critical sub-areas, some monitoring devices are placed in a dormant state. If the construction scene is identified as a target scene, the dormant monitoring devices are activated.
4. The construction safety progress tracking method based on video monitoring according to claim 3 is characterized in that: After receiving the progress tracking instruction, the construction progress recognition model is trained. After obtaining the monitoring data in each sub-area, the trained progress recognition model is used to identify the construction progress in the sub-area, and the obtained recognition results are compared with the project schedule to generate a progress tracking report.
5. A construction safety progress tracking system based on video monitoring, applying the method according to any one of claims 1 to 4, characterized in that: include, The environmental analysis unit collects data in the monitoring area and generates the construction environment coefficient based on the acquired construction environment data. , if the construction environment coefficient Exceeding expectations, issuing regional screening instructions to the outside; The area screening unit divides the monitoring area into multiple sub-areas and generates the construction scene coefficient based on the construction status data in the sub-areas. , based on the construction scenario coefficient Divide the monitoring area into non-critical sub-areas and critical sub-areas; The monitoring device control unit, after installing the monitoring devices in the monitoring area and making sure that there are no monitoring blind spots, constrains the installation density of the monitoring devices in the key sub-areas, and switches some monitoring devices in the non-key sub-areas between the sleep state and the running state according to the identified target scene; The abnormal alarm unit identifies abnormal behaviors in the monitoring area and generates the abnormal degree of construction from the abnormal behavior data. , if the abnormality When the abnormal threshold is exceeded, an alarm instruction is generated to the outside, and the corresponding abnormal behavior data is sent out together with the alarm instruction; The construction progress tracking unit generates alarm density according to the issued alarm instructions , if the alarm density If the construction progress in the sub-area is lower than expected, the construction progress in the sub-area is identified and a progress tracking report is generated. The progress coefficient is generated based on the progress tracking report. , if the progress coefficient Do not exceed expectations and issue progress adjustment instructions.