A programmable DC power supply output control method, device, equipment and medium

By introducing programmable control methods into DC power supplies, finely controlling the power supply timing of multiple voltage levels, the problem of inaccurate power supply time and duration control in the prior art is solved, ensuring safe and stable operation of the equipment and improving energy efficiency.

CN118655947BActive Publication Date: 2024-11-19SHENZHEN CASCO ELECTRONICS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411125840.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-19
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

The control of the power supply time and duration of existing DC voltage-regulated power supplies is difficult to accurately control, especially the power-on timing requirements of the equipment in multi-voltage configurations are difficult to meet, and the traditional locking method poses safety risks.

Method used

By introducing a programmable control method in the DC power supply, it is determined whether the device is powered by a single voltage based on the coupling of the power supply circuit, and gradually provides multiple different voltages, finely control the start and stop power supply timing, and use a timer to ensure the sequential start of voltage levels and closure.

Benefits of technology

It realizes fine power supply control of the powered equipment, avoids voltage shock, extends the equipment life, improves energy use efficiency, and enhances the safety and stability of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118655947B_ABST
    Figure CN118655947B_ABST
Patent Text Reader

Abstract

The present invention relates to a programmable direct current power supply output control method, device, equipment and medium, including a key switch being in an open state, responding to coupling with a power supply circuit of a powered device, and determining a plurality of power voltages of different sizes if the powered device is not powered by a single voltage; determining a first interval length of adjacent power voltages in a start power supply sequence and a second interval length of adjacent power voltages in a stop power supply sequence; supplying power to the powered device in sequence in the start power supply sequence when a start power supply condition is met, starting timing when a previous power voltage starts supplying power in the start power supply sequence, and starting supplying power with a subsequent power voltage in the start power supply sequence when the first interval length is reached; and stopping supplying power to the powered device in sequence in the stop power supply sequence when a stop power supply condition is met, starting timing when a previous power voltage stops supplying power in the stop power supply sequence, and stopping supplying power with a subsequent power voltage in the stop power supply sequence when the second interval length is reached.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the field of power supply technology, and in particular to a programmable direct current power supply output control method, device, equipment and medium. Background Art

[0002] The start time and duration of the DC regulated power supply are all manually controlled, which is not suitable for some occasions with special requirements for the power supply duration. At the same time, some products are equipped with two sets of power supplies (DC5V and DC12V), which have requirements for the power-on sequence, that is, one is powered on first and the other is powered on later. In this way, it is difficult to accurately determine the interval between the two in the power-on sequence when the traditional DC regulated power supply is manually turned on. In addition, the DC regulated power supply cannot be turned on and used by anyone. It needs to be authorized before it can be powered on, which is generally achieved through a password lock or a child lock. However, both the password lock and the child lock have certain limitations. For example, it is easy to forget the password or leak the password of the password lock; while the child lock can be unlocked as long as the unlocking method is mastered. Therefore, there are still certain safety risks. Summary of the invention

[0003] The purpose of the present invention is to provide a programmable DC power supply output control method, device, equipment and medium, aiming to reasonably display Metaverse exhibits through the Metaverse exhibition hall, thereby improving the user's immersive viewing experience.

[0004] In order to achieve the above-mentioned object, a first aspect of an embodiment of the present disclosure provides a programmable DC power supply output control method, the method comprising:

[0005] When the key switch of the DC power supply is in the on state, in response to the coupling of the power supply circuit between the DC power supply and the powered device, determining whether the powered device is powered by a single voltage according to the coupling condition of the power supply circuit;

[0006] In the case where the powered device is not powered by the single voltage, determining a plurality of power voltages of different voltages provided by the DC power supply to the powered device;

[0007] Determine a first interval duration between two adjacent power voltages of the plurality of power voltages at a timing of starting power supply, and determine a second interval duration between two adjacent power voltages of the plurality of power voltages at a timing of stopping power supply;

[0008] When the power supply start condition is met, in the power supply start sequence, the corresponding power is provided to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and the first timing is started when the previous power voltage in the power supply start sequence starts supplying power, and when the first timing reaches the corresponding first interval time, the next power voltage in the power supply start sequence is started to supply power;

[0009] When the conditions for stopping power supply are met, in the power supply stop sequence, the corresponding power is stopped from being supplied to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and the second timing is started when the previous power voltage stops supplying power in the power supply stop sequence, and when the second timing reaches the corresponding second interval length, the next power voltage in the power supply stop sequence is stopped from supplying power.

[0010] According to a second aspect of the embodiments of the present disclosure, a programmable DC power supply output control device is provided, comprising:

[0011] A first determination module is configured to determine whether the powered device is powered by a single voltage in response to the coupling of the power supply circuit between the DC power supply and the powered device when the key switch of the DC power supply is in an on state, according to the coupling condition of the power supply circuit;

[0012] A second determination module is configured to determine a plurality of power voltages of different voltages provided by the DC power supply to the powered device when the powered device is not powered by the single voltage;

[0013] A third determining module is configured to determine a first interval duration between two adjacent power voltages at a start power supply timing of the plurality of power voltages, and to determine a second interval duration between two adjacent power voltages at a stop power supply timing of the plurality of power voltages;

[0014] The power supply module is configured to, when the power supply start condition is met, provide corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the start power supply sequence according to the timing, and start the first timing after the previous power voltage starts supplying power in the start power supply sequence, and when the first timing reaches the corresponding first interval time, start the next power voltage in the start power supply sequence to start supplying power;

[0015] The power-off module is configured to, when the power supply stop condition is met, stop providing corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the power supply stop sequence in sequence, and start the second timing after the previous power voltage stops supplying power in the power supply stop sequence, and stop supplying power to the next power voltage in the power supply stop sequence when the second timing reaches the corresponding second interval time.

[0016] According to a third aspect of an embodiment of the present disclosure, a computer-readable storage medium is provided, on which a computer program is stored, and when the program is executed by a processor, the steps of any one of the methods described in the first aspect are implemented.

[0017] According to a fourth aspect of the embodiments of the present disclosure, an electronic device is provided, including:

[0018] a memory having a computer program stored thereon;

[0019] A processor is used to execute the computer program in the memory to implement the steps of any one of the methods in the first aspect.

[0020] The present invention provides a programmable DC power supply output control method, device, equipment and medium. Compared with the prior art, it has the following beneficial effects:

[0021] By determining the interval duration (first interval duration and second interval duration) of adjacent power voltages in the power supply start and stop timing, fine power supply control of the powered device can be achieved. It can ensure that during the startup and shutdown of the device, each voltage level can be carried out according to the predetermined timing, thereby avoiding voltage shock or equipment damage. In addition, for devices that require multiple different voltages for power supply, this timing control method can effectively protect the device from voltage mutations. By starting or shutting down different voltages one by one, the stress of the device when the power state changes can be reduced, extending the service life of the device. In addition, by optimizing the power supply timing, it can be ensured that the device only receives the necessary voltage in different working stages, thereby improving energy efficiency.

[0022] Other features and advantages of the present disclosure will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The accompanying drawings are used to provide a further understanding of the present disclosure and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the present disclosure but do not constitute a limitation of the present disclosure. In the accompanying drawings:

[0024] Figure 1 It is a flow chart of a programmable DC power supply output control method according to an embodiment of the specification.

[0025] Figure 2 It is a block diagram of a programmable DC power supply output control device according to an embodiment of the specification.

[0026] Figure 3 It is a block diagram of another programmable DC power supply output control device shown in an embodiment of the specification. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] The specific implementation of the present disclosure is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described herein is only used to illustrate and explain the present disclosure, and is not used to limit the present disclosure.

[0029] In order to achieve the above object, the present disclosure provides a programmable DC power supply output control method. Figure 1 This is a flow chart of a programmable DC power supply output control method according to an embodiment. The method comprises:

[0030] In step S11, when the key switch of the DC power supply is in the on state, in response to the coupling of the power supply circuit between the DC power supply and the powered device, it is determined whether the powered device is powered by a single voltage according to the coupling condition of the power supply circuit;

[0031] Among them, single voltage power supply means that the powered device only needs a fixed voltage value to work normally, and does not need multiple different voltage values ​​to work normally. For example, a simple LED light may only need a fixed voltage, while a complex electronic device, such as a computer, may need multiple different voltages to power different components inside it.

[0032] The power supply circuit coupling is the current path connection established between the DC power supply and the powered device. The key switch is a switch set on the DC power supply that can only be switched to the on state or the off state by inserting the corresponding physical key.

[0033] In the disclosed embodiment, when the key switch of the DC power supply is in the off state, even if the power supply circuit between the DC power supply and the powered device is coupled, the DC power supply will not provide corresponding power to the powered device through the coupled power supply circuit. In this way, it can be ensured that the DC power supply is not turned on and used without authorization.

[0034] Only when the key switch of the DC power supply is in the on state, it can be detected whether the power supply circuit between the DC power supply and the powered device is successfully coupled. According to the connection of the circuit, it can be judged whether the powered device needs a single voltage power supply. If the device is only connected to one power supply circuit, it is a single voltage power supply; if multiple power supply circuits with different voltages are connected, it is not a single voltage power supply.

[0035] In which, when multiple power supply circuits are coupled with powered devices, it is necessary to confirm whether they are the same powered device through, for example, the ID of the powered device. If the corresponding powered devices on any two or more power supply circuits are not the same powered device, the corresponding powered devices on each power supply circuit are powered according to the single voltage power supply provided later in the embodiment of the present disclosure.

[0036] In step S12, when the powered device is not powered by the single voltage, a plurality of power voltages of different voltages provided by the DC power supply to the powered device are determined;

[0037] The power voltage is the voltage value provided by the DC power supply to the powered device.

[0038] In the disclosed embodiment, if the powered device is not powered by a single voltage, it is necessary to further determine the magnitude of the different power voltages required. This is usually obtained through the device's specifications, internal circuit design, or actual measurement. For example, a complex robot may require 12V to drive its motor, 5V to power its control board, and 3.3V to power its sensors.

[0039] In step S13, a first interval duration between two adjacent power voltages in a power supply start sequence is determined, and a second interval duration between two adjacent power voltages in a power supply stop sequence is determined;

[0040] The power supply sequence is the process in which multiple power voltages start or stop supplying power in a specific order and time. The interval duration is the time difference between two adjacent power voltages starting or stopping supplying power.

[0041] In the disclosed embodiments, the start and stop timing of different power voltages can be precisely controlled to avoid voltage conflicts or device damage. This usually involves an in-depth analysis of the device's electrical characteristics and startup / shutdown requirements to determine the optimal interval length. For example, when starting a complex audio device, it may be necessary to first power the control circuit, wait for it to stabilize, and then power the amplifier circuit to ensure that the device starts smoothly.

[0042] It is worth explaining that, whether it is the start power supply sequence or the stop power supply sequence, the size of the power voltage is not limited, but is determined by the actual situation of the powered device. For example, in the start power supply sequence, 5V may be the first power to be provided, 12V may be the second power to be provided, and 3.5V may be the third power to be provided; similarly, in the stop power supply sequence, 3.5V may be the first power to be stopped, 12V may be the second power to be stopped, and 5V may be the third power to be stopped.

[0043] In step S14, when the power supply start condition is met, the corresponding power is provided to the powered device through the power supply circuit corresponding to the corresponding power voltage in the power supply start sequence according to the time sequence, and the first timing is started when the previous power voltage starts to supply power in the power supply start sequence, and when the first timing reaches the corresponding first interval time, the next power voltage in the power supply start sequence is started to supply power;

[0044] In the disclosed embodiment, when the conditions for starting power supply are met (such as the user pressing the power button, or reaching the start power supply time of the first power voltage in the set start power supply sequence), different power voltages are started one by one according to the start power supply sequence. When each power voltage starts supplying power, a timer is started, and when the timer reaches the preset first interval length, the next power voltage is started. For example, when starting a computer, the basic input and output system (BIOS) of the motherboard is powered first, and then after waiting for a period of time to ensure that the BIOS is stable, other components such as the hard disk and graphics card are powered.

[0045] In step S15, when the condition for stopping power supply is met, in the stop power supply sequence, the corresponding power is stopped from being supplied to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and the second timing is started when the previous power voltage stops supplying power in the stop power supply sequence, and when the second timing reaches the corresponding second interval length, the next power voltage in the stop power supply sequence is stopped from supplying power.

[0046] In the disclosed embodiment, when the conditions for stopping power supply are met (such as the user chooses to shut down or the device fails, or the first power voltage in the set power supply stop sequence stops power supply), the system will stop different power voltages one by one according to the predetermined power supply stop sequence. Similar to starting power supply, a timer will be started when each power voltage stops supplying power. When the timer reaches the preset second interval length, the system will stop supplying the next power voltage. For example, when shutting down a server, the power supply to the hard disk may be stopped first, and after the hard disk stops rotating completely, the power supply to the motherboard and other components will be stopped to ensure the security of data and the life of the hardware.

[0047] The whole process is described in detail below through an example:

[0048] When the power-on time reaches 5V, the 5V regulated power switch is turned on, so that the power stored in the DC power supply or the connected DC power is converted into 5V power and output to the charged device;

[0049] When the power stored in the DC power supply is converted into 5V power and output to the charged device, continuously determining whether the power-on time of 12V is reached;

[0050] If the 12V power-on time is not reached, it will continue to determine whether the 5V working time is reached;

[0051] If the working time of 5V is reached, the 5V voltage-stabilized power switch is turned off, so that the power stored in the DC power supply stops being converted into 5V power, so as to stop outputting 5V power to the charged device;

[0052] If the 12V power-on time is reached, the 12V regulated power switch is turned on, so that the power stored in the DC power supply is converted into 12V power and output to the charged device;

[0053] When the power stored in the DC power supply is converted into 12V power and output to the charged device, continuously determining whether the 5V working time is reached and whether the 12V working time is reached;

[0054] If the working time of 5V is reached, the 5V voltage-stabilized power switch is turned off, so that the power stored in the DC power supply stops being converted into 5V power, so as to stop outputting 5V power to the charged device, and / or, if the working time of 12V is reached, the 12V voltage-stabilized power switch is turned off, so that the power stored in the DC power supply stops being converted into 12V power, so as to stop outputting 12V power to the charged device;

[0055] If the power-on time of 5V is not reached, determining whether the power-on time of 12V is reached, and if the power-on time of 12V is reached, turning on the 12V regulated power supply switch, so that the power stored in the DC power supply is converted into 12V power and output to the charged device;

[0056] When the power stored in the DC power supply is converted into 12V power and output to the charged device, continuously determining whether the power-on time of 5V is reached;

[0057] If the 5V power-on time is not reached, it will continue to determine whether the 12V working time is reached;

[0058] If the 12V working time is reached, the 12V voltage-stabilized power switch is turned off, so that the power stored in the DC power supply stops being converted into 12V power, so as to stop outputting 12V power to the charged device;

[0059] If the power-on time reaches 5V, the 5V regulated power switch is turned on, so that the power stored in the DC power supply is converted into 5V power and output to the charged device;

[0060] When the power stored in the DC power supply is converted into 5V power and output to the charged device, continuously determining whether the 12V working time is reached and whether the 5V working time is reached;

[0061] If the working time reaches 5V, the 5V voltage-regulated power switch is turned off, so that the power stored in the DC power supply stops being converted into 5V power, so as to stop outputting 5V power to the charged device, and / or, if the working time reaches 12V, the 12V voltage-regulated power switch is turned off, so that the power stored in the DC power supply stops being converted into 12V power, so as to stop outputting 12V power to the charged device.

[0062] The method in the above technical solution can achieve fine power supply control of the powered device by determining the interval length (first interval length and second interval length) of adjacent power voltages in the timing of starting and stopping power supply. It can ensure that during the startup and shutdown of the device, each voltage level can be carried out according to the predetermined timing, thereby avoiding voltage shock or equipment damage. In addition, for devices that require multiple different voltages for power supply, this timing control method can effectively protect the device from voltage mutations. By starting or shutting down different voltages one by one, the stress of the device when the power state changes can be reduced, and the service life of the device can be extended. In addition, by optimizing the power supply timing, it can be ensured that the device only receives the necessary voltage in different working stages, thereby improving energy efficiency.

[0063] In step S13, determining a first interval duration between two adjacent power voltages of the plurality of power voltages at the power supply start sequence includes:

[0064] In step S131, the master-slave control relationship information corresponding to each load in the powered device and the duration information of the surge current generated when each load is connected to the corresponding power voltage are obtained;

[0065] The load can be a device that consumes power in the powered device. For example, if the powered device is a computer host, the load can be a display, hard disk, motherboard, etc. The master-slave control relationship can be understood as the startup of some loads (slave loads) may depend on the status of other loads (master loads). This dependency is called the master-slave control relationship.

[0066] For example, there may be dependencies or control relationships between different loads, and the startup of some loads may depend on the status or output of other loads. The startup or stop of the master load may trigger the corresponding action of the slave load. For example, in an automation system, the startup of the master controller may activate multiple slave devices. The circuit schematic of the powered device can be obtained, and then the conduction or cutoff of the electrical components in the circuit schematic, the circuit connection relationship or the startup sequence can be analyzed to obtain the corresponding master-slave control relationship.

[0067] The surge current may be a large instantaneous current that flows through the powered device when the power is first turned on or when the power voltage suddenly increases.

[0068] In the embodiment of the present disclosure, the control relationship between the loads in the device and the duration of the surge current generated by each load when the power is connected are collected. The duration of the surge current can be estimated from the expected surge current value of the powered device, the peak-to-peak current, etc.

[0069] Among them, different types of loads generate different inrush currents at startup. For example, loads such as motors and transformers usually require a large current to overcome static friction and establish a magnetic field at startup, so the inrush current is large. However, some electronic devices, such as LED lights, have relatively small inrush currents at startup.

[0070] Furthermore, the rated power, voltage and current specifications of the load will also affect the size of the inrush current. Generally speaking, the larger the power of the load, the larger the inrush current generated at startup. For loads of the same type or similar specifications, you can refer to their historical data or previous experience to make an estimate of the inrush current.

[0071] Among them, mathematical models can be established to predict the magnitude of inrush current based on the electrical characteristics (rated power, voltage and current specifications) and working principle (type) of the load. These models are usually based on circuit theory, electromagnetic principles, and physical characteristics of the equipment. By inputting the parameters of the equipment (such as voltage, resistance, inductance, etc.), the model can calculate the expected value of the inrush current.

[0072] Furthermore, the peak-to-peak value of the inrush current can be determined by the current change during the startup process in the historical data of the device. For example, the current data of the load from startup to stable operation. By analyzing the measured data, the maximum value (peak value) and minimum value (valley value) of the current can be found to determine the peak-to-peak value.

[0073] Then, according to the predicted current value and the peak-to-peak current of the load, a simulation calculation is performed to obtain the duration of the surge current. By adjusting the simulation parameters and conditions, the duration of the surge current under different conditions can be simulated and calculated.

[0074] In step S132, the loads are hierarchically divided according to the master-slave control relationship between the loads to determine the power supply hierarchical relationship corresponding to the loads, and the power supply hierarchical relationship is used to represent the startup sequence between the loads;

[0075] The hierarchical division may be to divide the loads into different startup hierarchies according to the dependency relationship between the loads. The power supply hierarchical relationship may indicate the startup sequence of the loads.

[0076] In the disclosed embodiment, a startup level can be assigned to each load according to the collected master-slave control relationship information, which ensures that a load that depends on other loads (slave loads) is started after the load it depends on (master load) is started.

[0077] In step S133, the power supply start time of each load is determined according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage;

[0078] The information collected previously and the hierarchical division results are used to determine the specific power supply start time for each load. The system will consider the duration of the inrush current of each load to ensure that the inrush current of the previous load has ended before the next load is started, thereby avoiding grid overload.

[0079] In the disclosed embodiment, a hierarchical division has been performed based on the master-slave control relationship between the loads, and the hierarchical relationship of power supply for each load has been determined. This hierarchical relationship is actually the startup sequence of the loads. Each load will generate a surge current when it is connected to the power voltage. This current is usually much larger than the normal operating current and will last for a period of time. If multiple loads are started at the same time, their surge currents may be superimposed, causing the power grid to overload, and even damage the equipment or trigger the protection device.

[0080] Therefore, based on the start-up sequence of the loads and the duration of the inrush current, the power supply start time for each load is calculated. First, the power supply start time of the first load to be started (usually the load with the highest level) is determined, which is usually set as time zero. Then, for each subsequent load, its power supply start time will be set to the power supply start time of the previous load plus the duration of the inrush current of the load. This ensures that the next load is started after the inrush current of the previous load subsides.

[0081] For example, assume that the powered equipment includes three loads: load A, load B, and load C. Their startup order is A -> B -> C, and it is known that the duration of the surge current when they are connected to the power is 3 seconds, 2 seconds, and 1 second respectively. Load A is the first load to be started, and its power supply start time is set to 0 seconds. The power supply start time of load B is the power supply start time of load A (0 seconds) plus the duration of the surge current of load A (3 seconds), that is, 3 seconds. The power supply start time of load C is the power supply start time of load B (3 seconds) plus the duration of the surge current of load B (2 seconds), that is, 5 seconds.

[0082] In step S134, according to the power supply start time of each of the loads, a first interval duration between two adjacent power voltages in the power supply start sequence of the plurality of power voltages is determined.

[0083] The time interval between the power supply of two adjacent loads is calculated based on the power supply start time of each load. This time interval is necessary to ensure that the power grid remains stable during the power supply process and to avoid overload caused by the simultaneous start of multiple loads. For example, if the main motor starts to supply power at 0 seconds, the surge current lasts for 5 seconds, and the auxiliary motor starts to supply power after 5 seconds, then the power supply interval between the two loads is 5 seconds.

[0084] Through the above steps, power distribution can be optimized to ensure stability and efficiency when starting the load, avoid the concentrated occurrence of surge current and current shock to the powered equipment, thereby improving the safety and life of the powered equipment.

[0085] In a possible implementation, in step S133, determining the power supply start time of each load according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage includes:

[0086] In step S13301, according to the maximum inrush current values ​​of the two loads started adjacently in the start-up sequence, it is determined whether the sum of the maximum inrush current value of the first load and the maximum inrush current value of the second load of the two loads started adjacently in the start-up sequence is less than a preset maximum current tolerance value;

[0087] The maximum surge current refers to the maximum instantaneous current generated by the load when it is connected to the power supply. The preset maximum current withstand value is the maximum surge current value that the powered device can withstand. Exceeding this value may cause device damage or system instability.

[0088] In the disclosed embodiment, it is checked whether the sum of the maximum inrush currents of two loads started adjacent to each other in the start-up sequence exceeds the preset maximum current carrying value of the system. This is to ensure that when two loads are started successively, the sum of the inrush currents they generate will not damage the system or trigger the protection device.

[0089] For example, suppose that load A and load B are started up successively, the maximum inrush current of load A is 5 A, the maximum inrush current of load B is 7 A, and the preset maximum current carrying value of the system is 10 A. In this case, the sum of the maximum inrush currents of the two loads is 12 A, which exceeds the preset maximum current carrying value.

[0090] In step S13302, when the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is greater than or equal to the preset maximum current bearing value, determine the first duration of the duration information of the second load for reaching the maximum inrush current;

[0091] In the embodiment of the present disclosure, if the sum of the maximum inrush currents of two adjacently started loads exceeds the preset maximum current carrying value, the system needs to determine the first time duration required for the latter load to reach its maximum inrush current. This is to understand the duration of the inrush current of the latter load. Continuing with the above example, assuming that it takes 0.5 seconds for load B to reach its maximum inrush current of 7A, this is the first time duration.

[0092] In step S13303, a first difference between the preset maximum current bearing value and the maximum value of the surge current of the latter load is determined, and a second duration in the duration information of the former load for reaching the first difference is determined;

[0093] In the disclosed embodiment, the difference (first difference) between the preset maximum current bearing value and the maximum value of the surge current of the subsequent load is calculated, and the second time required for the previous load to reach this difference is determined. This is to find a time point after which the subsequent load is started to ensure that the total current of the two loads does not exceed the preset maximum current bearing value of the system. Continuing with the above embodiment, the preset maximum current bearing value is 10A, and the maximum surge current of load B is 7A, so the first difference is 3A. Then determine the time required for load A to reach a current of 3A, assuming it is 0.3 seconds, which is the second time.

[0094] In step S13304, it is determined whether the first duration is greater than the second duration, and if the first duration is greater than or equal to the second duration, the second duration is added to the power supply start time of the previous load to obtain the power supply start time of the next load;

[0095] In the disclosed embodiment, the first duration and the second duration are compared. If the first duration is greater than or equal to the second duration (S13304), it means that the current of load A has been reduced to a safe level before load B reaches its maximum inrush current. Therefore, load B can be safely started after the power supply start time of load A plus the second duration. For example, if it takes 0.3 seconds (second duration) for load A to reach 3A (the first difference), and it takes 0.5 seconds (first duration) for load B to reach 7A (the maximum inrush current), then load B can be started 0.3 seconds after load A is started.

[0096] In step S13305, when the first time duration is shorter than the second time duration, the second time duration and the first time duration are added to the power supply start time of the previous load to obtain the power supply start time of the next load.

[0097] If the first duration is less than the second duration, it is necessary to wait for the time required for the surge current of load B to reach the maximum value (the first duration) after the current of load A drops to the first difference, so as to ensure that the total current of the two loads is always within the safe range. For example, it takes 0.5 seconds for load A to reach 3A, while it only takes 0.3 seconds for load B to reach 7A, so it is necessary to start load B 0.5 seconds (the second duration) plus 0.3 seconds (the first duration) after load A is started, that is, 0.8 seconds later.

[0098] The above technical solution calculates the sum of the maximum inrush currents of two adjacently started loads and compares it with the preset maximum current tolerance value, which can ensure that the total current of the system will not exceed the safety limit at any time, thereby preventing equipment damage or system crash caused by current overload. When it is detected that the sum of the inrush currents may exceed the preset limit, the optimal startup time of the latter load is determined by accurately calculating the first time for the latter load to reach the maximum inrush current and the second time for the current of the previous load to drop to the safety difference (first difference). This helps to optimize the startup sequence of multiple loads and reduce the current peak that the system as a whole withstands.

[0099] Moreover, by rationally arranging the power supply start time for each load, the stable operation of the power system can be ensured, and unnecessary losses and efficiency reduction caused by current fluctuations can be reduced. At the same time, this also helps to extend the service life of the equipment and reduce maintenance and replacement costs. The start time of the load can be dynamically adjusted according to the real-time current data and preset parameters. This not only improves the reliability and safety of the system, but also provides the possibility for automation and remote control.

[0100] In summary, by accurately controlling the startup time of the load, the occurrence of current overload is effectively prevented, the stability and efficiency of the power system are improved, and the intelligent management of the load is realized.

[0101] In a possible implementation, the method further includes:

[0102] In step S13306, when the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is less than the preset maximum current carrying value, the load started after the second load in the start-up sequence is determined as an alternative load;

[0103] In the disclosed embodiment, it is checked whether the sum of the maximum inrush currents of two adjacent loads in the startup sequence is less than the preset maximum current bearing value of the system. If so, the system will determine the load started after the latter load as an alternative load. This is to ensure that more loads can be safely started within the current bearing capacity of the system.

[0104] For example, assuming that loads A, B, and C are started in sequence, the maximum inrush current of load A is 3A, the maximum inrush current of load B is 4A, and the preset maximum current withstand value of the system is 10A. Since the sum of the maximum inrush currents of loads A and B (7A) is less than the preset maximum current withstand value (10A), load C is determined as an alternative load.

[0105] In step S13307, determining whether the maximum inrush current of the alternative load is greater than a first target current value, wherein the first target current value is a second difference between the preset maximum current bearing value and the sum of the maximum inrush currents of a plurality of adjacent loads started before the alternative load in the start-up sequence;

[0106] In the disclosed embodiment, it is determined whether the maximum surge current of the alternative load is greater than the first target current value. The first target current value is the preset maximum current bearing value minus the sum of the maximum surge currents of all adjacent loads started before the alternative load. This step is to evaluate whether the system has sufficient current bearing capacity before starting the alternative load. Continuing with the above example, assume that the maximum surge current of load C is 5A. The first target current value is the preset maximum current bearing value (10A) minus the sum of the maximum surge currents of load A and load B (7A), which is equal to 3A. Since the maximum surge current of load C (5A) is greater than the first target current value (3A), it is necessary to consider adjusting the start-up time of the load.

[0107] In step S13308, when the maximum inrush current of the alternative load started after the latter load in the starting sequence is less than the target current value, it is determined that the load started after the alternative load in the starting sequence is a pre-selected load, and it is determined whether the maximum inrush current of the pre-selected load is greater than a second target current value, wherein the second target current value is a difference between the first target current value and the maximum inrush current of the alternative load;

[0108] In the disclosed embodiment, if the maximum inrush current of the alternative load is less than the first target current value, the system will continue to search for the load started after the alternative load (referred to as the pre-selected load) and determine whether its maximum inrush current is greater than the second target current value. The second target current value is the first target current value minus the maximum inrush current of the alternative load. This is to further optimize the startup sequence and time of the loads.

[0109] In the above scenario, the maximum inrush current of load C is 2A (less than the first target current value of 3A), and load D is the preselected load with a maximum inrush current of 4A. The second target current value is the first target current value (3A) minus the maximum inrush current of load C (2A), which equals 1A. Since the maximum inrush current of load D (4A) is greater than the second target current value (1A), further adjustment needs to be considered.

[0110] In step S13309, when the maximum inrush current of the preselected load is greater than or equal to the second target current value, one third of the preset interval time is added to the power supply start time of the previous load to obtain the power supply start time of the next load, and two thirds of the preset interval time is added to the power supply start time of the previous load to obtain the power supply start time of the alternative load;

[0111] In the disclosed embodiment, if the maximum inrush current of the preselected load is greater than or equal to the second target current value, the system will add one third of the preset interval time to the power supply start time of the previous load to obtain the power supply start time of the next load, and add two thirds of the preset interval time to obtain the power supply start time of the alternative load. This is to ensure that the system has enough time to recover and stabilize the current before starting the subsequent load.

[0112] Continuing with the above scenario, assume that the preset interval is 3 seconds. Since the maximum inrush current of load D (4A) is greater than the second target current value (1A), the system adds 1 second (one-third of the preset interval) to the power-on start time of load B to get the power-on start time of load C, and adds 2 seconds (two-thirds of the preset interval) to get the power-on start time of load D. This ensures that the system has enough recovery time before starting loads C and D.

[0113] In step S13310, when the maximum inrush current of the preselected load is less than the second target current value, the preselected load is used as the alternative load, and the step of determining the load started after the alternative load in the start sequence as the preselected load is re-executed, and the step of adding two-thirds of the preset interval time to the power supply start time of the previous load to obtain the power supply start time of the alternative load;

[0114] In the disclosed embodiment, it is first determined whether the maximum surge current of the preselected load is less than the second target current value. This is to confirm whether the preselected load can be safely started under the current current carrying capacity. If the preselected load meets the above conditions (i.e., its maximum surge current is less than the second target current value), then the preselected load will be regarded as a new candidate load.

[0115] Next, the system will re-execute a series of steps from "determining the load that starts after the alternative load in the startup sequence as the pre-selected load" to "adding two-thirds of the preset interval time to the power supply start time of the previous load to obtain the power supply start time of the alternative load." This is an iterative process to continuously optimize the startup sequence and time of the loads to ensure the stability and safety of the system.

[0116] Assume that load E is started after load D (the original pre-selected load), and the maximum inrush current of load E is less than the second target current value. In this case, load E is considered as a new candidate load. The loads started after load E can be re-evaluated and their startup times adjusted to ensure that the current handling capacity of the entire system is not exceeded.

[0117] In step S13311, when the maximum surge current of the alternative load is greater than the target current value, half of the preset interval is added to the power supply start time of the previous load to obtain the power supply start time of the next load.

[0118] In the disclosed embodiment, it is first determined whether the maximum surge current of the alternative load is greater than the first target current value. If so, it means that directly starting the alternative load may cause current overload under the current system current carrying capacity. In order to avoid this situation, the power supply start time of the previous load can be added with half of the preset interval time to obtain the power supply start time of the next load (i.e., the alternative load). The purpose of this is to provide a buffer period for the system to restore and stabilize the current before starting the next load.

[0119] Assume that load F is an alternative load and its maximum inrush current is greater than the first target current value. To avoid current overload, the system will add half of the preset interval time (for example, 6 seconds) (i.e., 3 seconds) to the power supply start time of the previous load (assuming it is load E), and then start load F. In this way, when load F starts, the system has enough time to recover and stabilize the current, thereby avoiding possible current overload.

[0120] In a possible implementation, a voltage-stabilizing power supply and a plurality of electronic switches are provided on the power supply circuit corresponding to each power voltage; and a voltage-stabilizing power supply and a plurality of electronic switches are provided on each power supply circuit corresponding to a plurality of power voltages. Such a design can ensure that different devices receive a stable and appropriate power supply according to their needs.

[0121] In step S14, when the power supply start condition is met, in the power supply start sequence, the corresponding power is provided to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and the first timing is started after the previous power voltage starts supplying power in the power supply start sequence, and when the first timing reaches the corresponding first interval time, the next power voltage in the power supply start sequence is started to supply power, including:

[0122] In step S141, when the power supply start condition is met, at the power supply start sequence, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply start sequence is closed in sequence, so that the power provided by the DC power supply is voltage stabilized under the voltage stabilization effect of the voltage stabilizing power supply;

[0123] In the disclosed embodiment, when it is determined that the conditions for starting power supply are met, the first electronic switch on the power supply circuit corresponding to the previous power voltage will be closed first according to the power supply start sequence. This is done so that the power provided by the DC power supply can be voltage stabilized under the action of the voltage-stabilized power supply to ensure the stability of the power supply. For example, in a computer host system, when the boot time is reached, the first electronic switch on the control circuit is closed first, and the voltage-stabilized power supply prepares the 5V voltage for voltage stabilization.

[0124] In step S142, when the regulated power supply outputs the regulated voltage, the second electronic switch on the power supply circuit corresponding to the previous power voltage at the start power supply timing is closed to provide the regulated power voltage output by the corresponding regulated power supply to the powered device;

[0125] In the disclosed embodiment, after the voltage-stabilized power supply successfully outputs the regulated voltage, the second electronic switch on the power supply circuit corresponding to the previous power voltage is closed. In this way, the regulated power voltage can be stably provided to the powered device to ensure its normal operation. For example, in a computer host system in the above example, after the 5V voltage is stably output, the first electronic switch on the control circuit is closed to bring the 5V voltage output stably to the host control system.

[0126] In step S143, the first timing is started when the second electronic switch corresponding to the previous power voltage in the power supply start sequence is closed to start power supply;

[0127] In the disclosed embodiment, there are usually multiple power voltage levels, and the power supply timing of these voltage levels is pre-set. In the start power supply timing, when the second electronic switch corresponding to a certain power voltage (referred to as the "previous power voltage") is closed to start power supply, a first timer is started at the same time. The purpose of this timer is to control the power supply time of the next power voltage level. The second electronic switch is a power supply switch for controlling the previous power voltage. When this switch is closed, it means that the corresponding power voltage starts to supply power.

[0128] Assume that there is a power supply system with three power voltage levels, namely V1, V2 and V3, and their power supply timing is carried out in sequence. When V1 starts to supply power, the second electronic switch corresponding to it is closed, and the first timer is started at the same time.

[0129] In step S144, when the first timing reaches the corresponding first interval time, the first electronic switch corresponding to the next power voltage in the power supply start sequence is closed to start power supply with the next power voltage in the power supply start sequence.

[0130] In the embodiment of the present disclosure, the first timer triggers the power supply of the next power voltage level after reaching the preset first interval length. This is achieved by closing the first electronic switch corresponding to the power voltage level. Similar to the second electronic switch, the first electronic switch is a power supply switch for controlling the next power voltage. When this switch is closed, it means that the corresponding power voltage starts to supply power.

[0131] Continuing with the above scenario, assume that after V1 is powered, the first timer starts timing. When the first timer reaches the preset first interval length (for example, 0.5 seconds), the system automatically closes the first electronic switch corresponding to V2, thereby starting the power supply of V2. In this way, V2 starts to supply power. This process will be carried out in sequence until all power voltage levels are powered.

[0132] In summary, accurate power supply timing control is achieved through the cooperation of electronic switches and timers, thereby realizing orderly power supply at multiple power voltage levels.

[0133] In a possible implementation, in step S15, when the power supply stop condition is reached, in the power supply stop sequence, supplying corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage is stopped in sequence, and a second timing is started when the previous power voltage stops supplying power in the power supply stop sequence, and when the second timing reaches the corresponding second interval time, the next power voltage in the power supply stop sequence is stopped from supplying power, including:

[0134] In step S151, when the power supply stop condition is met, at the power supply stop sequence, the second electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected in sequence to stop providing the corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage, and after the second electronic switch corresponding to the previous power voltage at the power supply stop sequence is disconnected, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected;

[0135] In the embodiment of the present disclosure, corresponding to the start power supply timing, the stop power supply also has a predetermined timing. When the stop power supply condition is reached, the system will gradually stop the supply of each power voltage according to this timing. In the stop power supply timing, when one power voltage stops supplying, the system will start the second timer. When the second timer reaches the preset second interval length, the system will stop the supply of the next power voltage.

[0136] When the power supply stop condition is reached, the second electronic switch on the power supply circuit corresponding to the previous power voltage is first disconnected to stop supplying power to the powered device. Subsequently, the first electronic switch on the same power supply circuit is disconnected to ensure that the power supply is completely stopped.

[0137] In step S152, the second timing is started when the second electronic switch corresponding to the previous power voltage in the power supply stop sequence is turned off and the power supply is stopped;

[0138] In the embodiment of the present disclosure, after the second electronic switch corresponding to the previous power voltage is successfully disconnected and the power supply is stopped, the second timer is immediately started. The purpose of this timer is to control the time when the next power voltage stops supplying power.

[0139] In step S153, when the second timing reaches the corresponding second interval time, the first electronic switch corresponding to the next power voltage in the power supply stop sequence is disconnected to stop the power supply of the next power voltage in the power supply stop sequence.

[0140] In the embodiment of the present disclosure, when the second timer reaches the preset second interval time, the system will disconnect the first electronic switch corresponding to the next power voltage, thereby stopping the power supply of the power voltage. The second interval time can be configured according to the type of load and the master-slave control relationship.

[0141] In a possible implementation, the method further includes:

[0142] In step S21, when the powered device is powered by the single voltage, the rated power supply voltage of the powered device is obtained:

[0143] In the embodiment of the present disclosure, when the powered device requires a single voltage, the rated power supply voltage of the device needs to be obtained first. This is a standard voltage value set to ensure that the device can operate normally. Assuming there is a wireless router that requires 12V power supply, then the rated power supply voltage of the router is obtained, that is, 12V.

[0144] In step S22, according to the rated power supply voltage, a standard power supply voltage having the smallest difference with the rated power supply voltage is determined from a plurality of standard power supply voltages of the DC power supply as a target power supply voltage, wherein the standard power supply voltage is a stable voltage provided by the DC power supply when converting input DC power into any single voltage;

[0145] In the disclosed embodiment, the DC power supply is generally capable of providing multiple standard power supply voltages. In this step, the system selects a standard power supply voltage with the smallest difference from the rated power supply voltage from the standard power supply voltages of the DC power supply as the target power supply voltage according to the rated power supply voltage of the device. For example, if the standard power supply voltages provided by the DC power supply are 9V, 12V, and 15V, and for the above-mentioned wireless router, its rated power supply voltage is 12V, then the system will select 12V as the target power supply voltage because it has the smallest difference from the rated power supply voltage (i.e., 0V).

[0146] In step S23, determining whether the target power supply voltage matches a standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply;

[0147] In the disclosed embodiment, it is checked whether the selected target power supply voltage matches the standard power supply voltage of the power supply circuit coupled to the device on the DC power supply. This is to ensure that the power supply circuit can provide the correct voltage required by the device. For example, assuming that the standard power supply voltage of the power supply circuit coupled to the wireless router on the DC power supply is also 12V, then in step S23, it is confirmed that the target power supply voltage (12V) matches the standard power supply voltage of the power supply circuit.

[0148] In step S24, when the target power supply voltage matches the standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply, power is provided to the powered device through the power supply circuit coupled to the powered device on the DC power supply;

[0149] In the disclosed embodiment, if the target power supply voltage matches the standard power supply voltage of the power supply circuit, the system will provide power to the device through the power supply circuit. This ensures that the device can receive a correct and stable voltage supply. In the above example of a wireless router, since the target power supply voltage (12V) matches the standard power supply voltage of the power supply circuit, the system will provide 12V power to the wireless router through the power supply circuit.

[0150] In step S25, when the target power supply voltage does not match the standard power supply voltage of the power supply circuit on the DC power supply coupled to the powered device, a prompt is provided to switch the power supply circuit on the DC power supply coupled to the powered device.

[0151] In the disclosed embodiment, if the target power supply voltage does not match the standard power supply voltage of the power supply circuit, the system will prompt to switch the power supply circuit to ensure that the device can receive the correct voltage supply. This is to prevent device damage or performance degradation caused by voltage mismatch.

[0152] The present disclosure also provides a programmable DC power supply output control device. Figure 2 As shown, including:

[0153] The first determination module 210 is configured to determine whether the powered device is powered by a single voltage according to the coupling of the power supply circuit between the DC power supply and the powered device when the key switch of the DC power supply is in the on state;

[0154] The second determination module 220 is configured to determine a plurality of power voltages of different voltages provided by the DC power supply to the powered device when the powered device is not powered by the single voltage;

[0155] The third determining module 230 is configured to determine a first interval duration between two adjacent power voltages at a start power supply timing of the plurality of power voltages, and determine a second interval duration between two adjacent power voltages at a stop power supply timing of the plurality of power voltages;

[0156] The power supply module 240 is configured to, when the power supply start condition is met, provide corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the start power supply sequence according to the time sequence, and start the first timing after the previous power voltage starts supplying power in the start power supply sequence, and when the first timing reaches the corresponding first interval time, start the next power voltage in the start power supply sequence to start supplying power;

[0157] The power-off module 250 is configured to, when the power supply stop condition is met, stop providing corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the power supply stop sequence in sequence, and start the second timing after the previous power voltage stops supplying power in the power supply stop sequence, and stop supplying power to the next power voltage in the power supply stop sequence when the second timing reaches the corresponding second interval time.

[0158] In a possible implementation, the third determining module 230 is configured to:

[0159] Acquire the master-slave control relationship information corresponding to each load in the powered device and the duration information of the surge current generated when each load is connected to the corresponding power voltage;

[0160] According to the master-slave control relationship between the loads, the loads are divided into levels to determine the power supply order relationship corresponding to the loads, and the power supply order relationship is used to indicate the startup sequence between the loads;

[0161] Determine the power supply start time of each load according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage;

[0162] According to the power supply start time of each of the loads, a first interval duration between two adjacent power voltages in a power supply start sequence of the plurality of power voltages is determined.

[0163] In a possible implementation, the third determining module 230 is configured to:

[0164] According to the maximum inrush current values ​​of the two loads started adjacently in the starting sequence, determining whether the sum of the maximum inrush current value of the first load and the maximum inrush current value of the second load of the two loads started adjacently in the starting sequence is less than a preset maximum current bearing value;

[0165] In the case where the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is greater than or equal to the preset maximum current bearing value, determining the first duration for reaching the maximum inrush current in the duration information of the second load;

[0166] Determine a first difference between the preset maximum current bearing value and the maximum value of the surge current of the latter load, and determine a second duration in the duration information of the former load for reaching the first difference;

[0167] Determine whether the first duration is greater than the second duration, and if the first duration is greater than or equal to the second duration, add the second duration to the power supply start time of the previous load to obtain the power supply start time of the next load;

[0168] When the first time duration is shorter than the second time duration, the second time duration and the first time duration are added to the power supply start time of the previous load to obtain the power supply start time of the next load.

[0169] In a possible implementation, the third determining module 230 is configured to:

[0170] In the case where the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is less than the preset maximum current bearing value, determining the load started after the second load in the start-up sequence as an alternative load;

[0171] Determining whether the maximum inrush current of the alternative load is greater than a first target current value, wherein the first target current value is a second difference between the preset maximum current bearing value and the sum of the maximum inrush currents of a plurality of adjacent loads started before the alternative load in the start-up sequence;

[0172] In the case where the maximum inrush current of the alternative load started after the latter load in the start-up sequence is less than the target current value, determining that the load started after the alternative load in the start-up sequence is a pre-selected load, and determining whether the maximum inrush current of the pre-selected load is greater than a second target current value, wherein the second target current value is a difference between the first target current value and the maximum inrush current of the alternative load;

[0173] When the maximum inrush current of the preselected load is greater than or equal to the second target current value, one third of the preset interval duration is added to the power supply start time of the previous load to obtain the power supply start time of the next load, and two thirds of the preset interval duration is added to the power supply start time of the previous load to obtain the power supply start time of the alternative load;

[0174] In the case where the maximum inrush current of the preselected load is less than the second target current value, the preselected load is used as the alternative load, and the step of determining the load started after the alternative load in the start sequence as the preselected load is re-executed, and the step of adding two-thirds of the preset interval time to the power supply start time of the previous load to obtain the power supply start time of the alternative load;

[0175] When the maximum inrush current of the candidate load is greater than the target current value, the power supply start time of the next load is obtained by adding half of the preset interval time to the power supply start time of the previous load.

[0176] In a possible implementation, a voltage-stabilizing power supply and a plurality of electronic switches are provided on the power supply circuit corresponding to each of the power voltages;

[0177] The power supply module 240 is configured as follows:

[0178] When the power supply start condition is met, at the power supply start sequence, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply start sequence is closed in sequence, so that the power provided by the DC power supply is voltage stabilized under the voltage stabilization effect of the voltage stabilizing power supply;

[0179] When the regulated power supply outputs the regulated voltage, closing the second electronic switch on the power supply circuit corresponding to the previous power voltage at the start of power supply timing, so as to provide the corresponding regulated power voltage output by the regulated power supply to the powered device;

[0180] The first timing is started when the second electronic switch corresponding to the previous power voltage in the power supply start sequence is closed to start power supply;

[0181] When the first timing reaches the corresponding first interval time, the first electronic switch corresponding to the next power voltage in the power supply start sequence is closed to start power supply with the next power voltage in the power supply start sequence.

[0182] In a possible implementation, the power-off module 250 is configured to:

[0183] When the power supply stop condition is reached, at the power supply stop sequence, the second electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected in sequence to stop supplying the corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage, and after the second electronic switch corresponding to the previous power voltage at the power supply stop sequence is disconnected, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected;

[0184] The second timing is started when the second electronic switch corresponding to the previous power voltage in the power supply stop sequence is disconnected and the power supply is stopped;

[0185] When the second timing reaches the corresponding second interval time, the first electronic switch corresponding to the next power voltage in the power supply stop sequence is disconnected to stop the power supply of the next power voltage in the power supply stop sequence.

[0186] In a possible implementation, the power supply module 240 is configured as follows:

[0187] When the powered device is powered by the single voltage, obtaining the rated supply voltage of the powered device:

[0188] According to the rated power supply voltage, determine, from among a plurality of standard power supply voltages of the DC power supply, a standard power supply voltage having the smallest difference with the rated power supply voltage as a target power supply voltage, wherein the standard power supply voltage is a stable voltage provided by the DC power supply when converting input DC power into any single voltage;

[0189] Determining whether the target power supply voltage matches a standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply;

[0190] When the target power supply voltage matches a standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply, power is provided to the powered device through the power supply circuit coupled to the powered device on the DC power supply;

[0191] When the target power supply voltage does not match the standard power supply voltage of the power supply circuit on the DC power supply coupled to the powered device, a prompt is provided to switch the power supply circuit on the DC power supply coupled to the powered device.

[0192] The present disclosure also provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps of the method described in any one of the aforementioned embodiments are implemented.

[0193] The present disclosure also provides an electronic device, including:

[0194] a memory having a computer program stored thereon;

[0195] A processor is used to execute the computer program in the memory to implement the steps of the method in any one of the aforementioned embodiments.

[0196] Figure 3 The programmable DC power output control device 100 shown includes: a processor 1001 and a memory 1003. The processor 1001 and the memory 1003 are connected, such as through a bus 1002. Optionally, the programmable DC power output control device 100 may also include a communication component, which can be used for data interaction between the device 100 and other devices, such as data transmission and / or data reception. It should be noted that the communication component is not limited to one in actual scheduling, and the structure of the programmable DC power output control device 100 does not constitute a limitation on the embodiments of the present application.

[0197] Processor 1001 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. Processor 1001 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.

[0198] The bus 1002 may include a path to transmit information between the above components. The bus 1002 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 1002 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 3 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0199] The memory 1003 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), magnetic disk storage medium, other magnetic storage devices, or any other medium that can be used to carry or store program code and can be read by a computer, without limitation herein.

[0200] The memory 1003 is used to store program codes for executing the embodiments of the present disclosure, and the execution is controlled by the processor 1001. The processor 1001 is used to execute the program codes stored in the memory 1003 to implement the steps shown in the embodiment of the programmable DC power supply output control method.

[0201] The embodiment of the present disclosure also provides a computer-readable storage medium having program code stored thereon. When the program code is executed by a processor, the steps and corresponding contents of the aforementioned programmable DC power supply output control method embodiment can be implemented.

[0202] The preferred embodiments of the present disclosure are described in detail above in conjunction with the accompanying drawings; however, the present disclosure is not limited to the specific details in the above embodiments; within the technical concept of the present disclosure, various changes, modifications, substitutions and variations may be made to these embodiments, and these changes, modifications, substitutions and variations all fall within the protection scope of the present disclosure.

[0203] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any appropriate manner without contradiction, and they should also be regarded as the contents disclosed in this disclosure. In order to avoid unnecessary repetition, this disclosure will not further describe various possible combinations. The technical scope of this application is not limited to the contents in the specification, and its technical scope must be determined according to the scope of the claims.

Claims

1. A programmable DC power supply output control method, characterized in that: The method comprises: When the key switch of the DC power supply is in the on state, in response to the coupling of the power supply circuit between the DC power supply and the powered device, determine whether the powered device is powered by a single voltage according to the coupling condition of the power supply circuit; In the case where the powered device is not powered by the single voltage, determining a plurality of power voltages of different voltages provided by the DC power supply to the powered device; Determine a first interval duration between two adjacent power voltages of the plurality of power voltages at a timing of starting power supply, and determine a second interval duration between two adjacent power voltages of the plurality of power voltages at a timing of stopping power supply; When the power supply start condition is met, in the power supply start sequence, the corresponding power is provided to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and the first timing is started when the previous power voltage in the power supply start sequence starts supplying power, and when the first timing reaches the corresponding first interval time, the next power voltage in the power supply start sequence is started to supply power; When the power supply stop condition is reached, in the power supply stop sequence, the corresponding power supply circuit corresponding to the corresponding power voltage is stopped from supplying the corresponding power to the powered device in sequence, and the second timing is started when the previous power voltage in the power supply stop sequence stops supplying power, and when the second timing reaches the corresponding second interval time, the next power voltage in the power supply stop sequence is stopped from supplying power; The determining of a first interval duration between two adjacent power voltages at the start of power supply timing of the plurality of power voltages comprises: Acquire the master-slave control relationship information corresponding to each load in the powered device and the duration information of the surge current generated when each load is connected to the corresponding power voltage; According to the master-slave control relationship between the loads, the loads are divided into levels to determine the power supply order relationship corresponding to the loads, and the power supply order relationship is used to indicate the startup sequence between the loads; Determine the power supply start time of each load according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage; Determining, according to the power supply start time of each of the loads, a first interval length between two adjacent power voltages in a power supply start sequence of the plurality of power voltages; The step of determining the power supply start time of each load according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage includes: According to the maximum inrush current values ​​of the two loads started adjacently in the starting sequence, determining whether the sum of the maximum inrush current value of the first load and the maximum inrush current value of the second load of the two loads started adjacently in the starting sequence is less than a preset maximum current bearing value; In the case where the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is greater than or equal to the preset maximum current bearing value, determining the first duration for reaching the maximum inrush current in the duration information of the second load; Determine a first difference between the preset maximum current bearing value and the maximum value of the surge current of the latter load, and determine a second duration in the duration information of the former load for reaching the first difference; Determine whether the first duration is greater than the second duration, and if the first duration is greater than or equal to the second duration, add the second duration to the power supply start time of the previous load to obtain the power supply start time of the next load; When the first time duration is shorter than the second time duration, the second time duration and the first time duration are added to the power supply start time of the previous load to obtain the power supply start time of the next load.

2. The programmable DC power supply output control method according to claim 1, characterized in that: The method further comprises: In the case where the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is less than the preset maximum current bearing value, determining the load started after the second load in the start-up sequence as an alternative load; Determining whether the maximum inrush current of the alternative load is greater than a first target current value, wherein the first target current value is a second difference between the preset maximum current bearing value and the sum of the maximum inrush currents of a plurality of adjacent loads started before the alternative load in the start-up sequence; In the case where the maximum inrush current of the alternative load started after the latter load in the start-up sequence is less than the target current value, determining that the load started after the alternative load in the start-up sequence is a pre-selected load, and determining whether the maximum inrush current of the pre-selected load is greater than a second target current value, wherein the second target current value is a difference between the first target current value and the maximum inrush current of the alternative load; When the maximum inrush current of the preselected load is greater than or equal to the second target current value, one third of the preset interval duration is added to the power supply start time of the previous load to obtain the power supply start time of the next load, and two thirds of the preset interval duration is added to the power supply start time of the previous load to obtain the power supply start time of the alternative load; In the case where the maximum inrush current of the preselected load is less than the second target current value, the preselected load is used as the alternative load, and the step of determining the load started after the alternative load in the start sequence as the preselected load is re-executed, and the step of adding two-thirds of the preset interval time to the power supply start time of the previous load to obtain the power supply start time of the alternative load; When the maximum inrush current of the candidate load is greater than the target current value, the power supply start time of the next load is obtained by adding half of the preset interval time to the power supply start time of the previous load.

3. The programmable DC power supply output control method according to claim 1, characterized in that: A voltage-stabilizing power supply and a plurality of electronic switches are provided on the power supply circuit corresponding to each power voltage; When the power supply start condition is met, in the power supply start sequence, corresponding power is provided to the powered device through the power supply circuit corresponding to the corresponding power voltage in sequence, and a first timing is started after the previous power voltage starts supplying power in the power supply start sequence, and when the first timing reaches the corresponding first interval time, the next power voltage in the power supply start sequence is started to supply power, including: When the power supply start condition is met, at the power supply start sequence, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply start sequence is closed in sequence, so that the power provided by the DC power supply is voltage stabilized under the voltage stabilization effect of the voltage stabilizing power supply; When the regulated power supply outputs the regulated voltage, closing the second electronic switch on the power supply circuit corresponding to the previous power voltage at the start of power supply timing, so as to provide the corresponding regulated power voltage output by the regulated power supply to the powered device; The first timing is started when the second electronic switch corresponding to the previous power voltage in the power supply start sequence is closed to start power supply; When the first timing reaches the corresponding first interval time, the first electronic switch corresponding to the next power voltage in the power supply start sequence is closed to start power supply with the next power voltage in the power supply start sequence.

4. The programmable DC power supply output control method according to claim 3, characterized in that: When the power supply stop condition is reached, in the power supply stop sequence, supplying corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage is stopped in sequence, and a second timing is started when the previous power voltage stops supplying power in the power supply stop sequence, and when the second timing reaches the corresponding second interval time, the next power voltage in the power supply stop sequence is stopped from supplying power, including: When the power supply stop condition is reached, at the power supply stop sequence, the second electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected in sequence to stop supplying the corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage, and after the second electronic switch corresponding to the previous power voltage at the power supply stop sequence is disconnected, the first electronic switch on the power supply circuit corresponding to the previous power voltage at the power supply stop sequence is disconnected; The second timing is started when the second electronic switch corresponding to the previous power voltage in the power supply stop sequence is disconnected and the power supply is stopped; When the second timing reaches the corresponding second interval time, the first electronic switch corresponding to the next power voltage in the power supply stop sequence is disconnected to stop the power supply of the next power voltage in the power supply stop sequence.

5. The programmable DC power supply output control method according to any one of claims 1 to 4, characterized in that: The method further comprises: When the powered device is powered by the single voltage, obtaining the rated supply voltage of the powered device: According to the rated power supply voltage, determine, from among a plurality of standard power supply voltages of the DC power supply, a standard power supply voltage having the smallest difference with the rated power supply voltage as a target power supply voltage, wherein the standard power supply voltage is a stable voltage provided by the DC power supply when converting input DC power into any single voltage; Determining whether the target power supply voltage matches a standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply; When the target power supply voltage matches a standard power supply voltage of the power supply circuit coupled to the powered device on the DC power supply, power is provided to the powered device through the power supply circuit coupled to the powered device on the DC power supply; When the target power supply voltage does not match the standard power supply voltage of the power supply circuit on the DC power supply coupled to the powered device, a prompt is provided to switch the power supply circuit on the DC power supply coupled to the powered device.

6. A programmable DC power supply output control device, characterized in that: include: A first determination module is configured to determine whether the powered device is powered by a single voltage in response to the coupling of the power supply circuit between the DC power supply and the powered device when the key switch of the DC power supply is in an on state, according to the coupling condition of the power supply circuit; A second determination module is configured to determine a plurality of power voltages of different voltages provided by the DC power supply to the powered device when the powered device is not powered by the single voltage; A third determining module is configured to determine a first interval duration between two adjacent power voltages at a start power supply timing of the plurality of power voltages, and to determine a second interval duration between two adjacent power voltages at a stop power supply timing of the plurality of power voltages; The power supply module is configured to, when the power supply start condition is met, provide corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the start power supply sequence according to the timing, and start the first timing after the previous power voltage starts supplying power in the start power supply sequence, and when the first timing reaches the corresponding first interval time, start the next power voltage in the start power supply sequence to start supplying power; The power-off module is configured to, when the power supply stop condition is reached, stop supplying corresponding power to the powered device through the power supply circuit corresponding to the corresponding power voltage in the power supply stop sequence in accordance with the time sequence, and start the second timing after the previous power voltage stops supplying power in the power supply stop sequence, and stop supplying power to the next power voltage in the power supply stop sequence when the second timing reaches the corresponding second interval time; Wherein, the third determination module is configured as follows: Acquire the master-slave control relationship information corresponding to each load in the powered device and the duration information of the surge current generated when each load is connected to the corresponding power voltage; According to the master-slave control relationship between the loads, the loads are divided into levels to determine the power supply order relationship corresponding to the loads, and the power supply order relationship is used to indicate the startup sequence between the loads; Determine the power supply start time of each load according to the startup sequence between the loads and the duration information of the surge current generated when each load is connected to the corresponding power voltage; Determining, according to the power supply start time of each of the loads, a first interval length between two adjacent power voltages in a power supply start sequence of the plurality of power voltages; Wherein, the third determination module is further configured to: According to the maximum inrush current values ​​of the two loads started adjacently in the starting sequence, determining whether the sum of the maximum inrush current value of the first load and the maximum inrush current value of the second load of the two loads started adjacently in the starting sequence is less than a preset maximum current bearing value; In the case where the sum of the maximum inrush current of the first load and the maximum inrush current of the second load of the two loads started adjacently in the start-up sequence is greater than or equal to the preset maximum current bearing value, determining the first duration for reaching the maximum inrush current in the duration information of the second load; Determine a first difference between the preset maximum current bearing value and the maximum value of the surge current of the latter load, and determine a second duration in the duration information of the former load for reaching the first difference; Determine whether the first duration is greater than the second duration, and if the first duration is greater than or equal to the second duration, add the second duration to the power supply start time of the previous load to obtain the power supply start time of the next load; When the first time duration is shorter than the second time duration, the second time duration and the first time duration are added to the power supply start time of the previous load to obtain the power supply start time of the next load.

7. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of the method described in any one of claims 1 to 5 are implemented.

8. An electronic device, characterized in that: include: a memory having a computer program stored thereon; A processor, configured to execute the computer program in the memory to implement the steps of the method according to any one of claims 1 to 5.