A cable machine monitoring method, device, electronic equipment and medium

Through intelligent monitoring methods and devices, the transportation efficiency and safety of the cable machine are monitored in real time, and the problems of traditional management lag and inaccuracy are solved, the efficient and safe operation of the cable machine is improved, and the smooth construction of the hydropower project is ensured.

CN118656600BActive Publication Date: 2024-11-08THREE GORGES GROUP IND DEVELOPMENT (BEIJING) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411132954.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-08
Estimated Expiration
2044-08-19

AI Technical Summary

Technical Problem

In the construction of hydropower engineering, the traditional management of cable machines is mainly artificial and has lag and inaccurate, making it difficult to ensure the efficient and safe operation of cable machines. Especially under the harsh natural conditions in the alpine canyon area, it affects the construction progress and personnel. Safety.

Method used

Using intelligent monitoring methods and devices, through link identification models, efficiency analysis models and safety analysis models, obtain full-time location information of the cable machine, identify information on material transportation links, analyze efficiency and safety indicators, provide real-time monitoring and early warning, and build a cable machine group Efficient, safe and intelligent management and control platform.

Benefits of technology

Real-time monitoring and dynamic tracking of cable machines are realized, transportation efficiency and safety are improved, the smooth progress of the dam casting project is ensured, and construction risks are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118656600B_ABST
    Figure CN118656600B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention provides a cable crane monitoring method, device, electronic device and medium, which are applied to cable crane monitoring equipment, and involve link identification models, efficiency analysis models and safety analysis models. The method includes: obtaining the full-time position information of the cable crane, and obtaining the material transportation link information of the cable crane based on the full-time position information through the link identification model; obtaining the efficiency index according to the characteristic value time and / or link time through the efficiency analysis model; obtaining the safety index of the cable crane during operation through the safety analysis model; and issuing an early warning for the operation status of the cable crane based on the efficiency index and the safety spacing control index. By obtaining the full-time position information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, the efficiency analysis model and the safety analysis model, and the corresponding information is output for the management personnel to manage the cable crane, thereby realizing an early warning for the operation status of the cable crane.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of communication technology, and in particular to a cable machine monitoring method, a cable machine monitoring device, a corresponding electronic device, and a corresponding computer-readable storage medium. Background Art

[0002] There are thousands of crisscrossing rivers in western China, which is one of the regions with the richest hydropower resources in the world. However, most of the hydropower stations in the west are located in mountainous canyons or plateaus. The harsh natural conditions, such as dry heat, strong winds, and complex terrain and geological conditions, pose challenges to dam-building technology and restrict the development and progress of the hydropower industry.

[0003] In the process of hydropower project construction, cable cranes are important equipment for the construction of concrete arch dams, especially for ultra-high arch dams, which are mostly located in high mountain valleys. Transport vehicles cannot directly carry out concrete storage operations. As a transfer and transportation equipment, cable cranes are directly related to the progress of dam pouring. At the same time, as special equipment for high-altitude operations, their safe operation is directly related to the personal safety of construction workers. However, the traditional management of cable cranes is mainly manual, which has problems such as lag and inaccuracy, making it difficult to ensure the efficient and safe operation of cable cranes. Summary of the invention

[0004] In view of the above problems, embodiments of the present invention are proposed to provide a cable machine monitoring method, a cable machine monitoring device, a corresponding electronic device and a corresponding computer-readable storage medium that overcome the above problems or at least partially solve the above problems.

[0005] The embodiment of the present invention discloses a cable crane monitoring method, which is applied to a cable crane monitoring device and involves a link identification model, an efficiency analysis model, and a safety analysis model. The method includes:

[0006] Acquire the full-time position information of the cable crane, and acquire the material transportation link information of the cable crane based on the full-time position information through the link identification model; the material transportation link information includes characteristic value time and link time; the characteristic value time is used to indicate the key moment of the cable crane in different operation stages;

[0007] Obtaining an efficiency index according to the characteristic value moment and / or the link time through the efficiency analysis model;

[0008] The safety index of the cable car during operation is obtained through the safety analysis model; the safety index is a safety distance control index, and the safety distance control index is used to indicate whether there is a collision risk and whether the safety distance requirement is met;

[0009] An early warning is given to the operating status of the cable car according to the efficiency index and the safety distance control index.

[0010] The embodiment of the present invention further discloses a cable crane monitoring device, which is applied to cable crane monitoring equipment and involves a link identification model, an efficiency analysis model, and a safety analysis model. The device includes:

[0011] A link identification module is used to obtain the full-time position information of the cable crane, and obtain the material transportation link information of the cable crane based on the full-time position information through the link identification model; the material transportation link information includes a characteristic value moment and a link time; the characteristic value moment is used to indicate the key moment of the cable crane in different operation stages;

[0012] An efficiency analysis module, used to obtain an efficiency index according to the characteristic value moment and / or the link time by using the efficiency analysis model;

[0013] A safety analysis module, used to obtain the safety index of the cable car during operation by using the safety analysis model; the safety index is a safety distance control index, and the safety distance control index is used to indicate whether there is a collision risk and whether the safety distance requirement is met;

[0014] The early warning module is used to warn the operating status of the cable car according to the efficiency index and the safety distance control index.

[0015] An embodiment of the present invention further discloses an electronic device, comprising: a processor, a memory, and a computer program stored in the memory and capable of running on the processor, wherein when the computer program is executed by the processor, any one of the cable machine monitoring methods is implemented.

[0016] The embodiment of the present invention further discloses a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, any of the cable machine monitoring methods is implemented.

[0017] The embodiments of the present invention include the following advantages:

[0018] In an embodiment of the present invention, the full-time position information of the cable crane is obtained through the cable crane monitoring device, and the material transportation link information of the cable crane is obtained based on the full-time position information through the link identification model. The obtained material transportation link information may include characteristic value time and link time, and then the efficiency analysis model is used to obtain the efficiency index according to the characteristic value time and / or link time, and the safety index of the cable crane during operation is obtained through the safety analysis model. The safety index may be a safety distance control index, which is mainly used to indicate whether there is a collision risk and whether the safety distance requirements are met, so as to give an early warning of the operation status of the cable crane based on the efficiency index and safety distance control index obtained by analysis. By obtaining the full-time position information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, the efficiency analysis model, and the safety analysis model, and the corresponding information is output for the management personnel to manage the cable crane, thereby realizing an early warning of the operation status of the cable crane. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is an integrated schematic diagram of a cable crane monitoring device provided by an example of the present invention;

[0020] Figure 2 is a flow chart of steps of an embodiment of a cable machine monitoring method of the present invention;

[0021] Figure 3 It is a schematic diagram of the cable machine material transportation process provided by an embodiment of the present invention;

[0022] Figure 4 is a schematic diagram of cable crane efficiency analysis provided by an embodiment of the present invention;

[0023] Figure 5 is a schematic diagram of cable crane safety analysis provided by an embodiment of the present invention;

[0024] Figure 6 It is an efficient and safe cable crane control index system provided by an embodiment of the present invention;

[0025] Figure 7 It is a schematic diagram of a dynamic calibration model of cable crane efficiency index provided by an example of the present invention;

[0026] Figure 8 It is a schematic diagram of a cable crane operation early warning control model provided by an embodiment of the present invention;

[0027] Fig. 9 It is a schematic diagram of an application scenario of cable crane monitoring provided by an embodiment of the present invention;

[0028] Fig.10 It is a structural block diagram of an embodiment of a monitoring device for a cable crane of the present invention. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0030] In the process of hydropower engineering construction, the cable crane is an important equipment for the construction of concrete arch dams. In order to ensure the efficient and safe operation of the cable crane, the embodiment of the present invention is based on the intelligent construction theory, and uses network communication technology, Internet of Things technology, high-precision positioning, cross-platform complex information management, big data analysis technology, etc. as means to carry out research on intelligent monitoring equipment, link identification models, comprehensive analysis and hierarchical early warning feedback mechanisms, etc., to build an efficient and safe intelligent management and control platform for cable crane groups, and realize a cable crane intelligent management and control system with real-time monitoring, online analysis, dynamic tracking, and intelligent feedback, effectively improving the efficient and safe operation of the cable crane group. Specifically, by obtaining the operation information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, efficiency analysis model, safety analysis model, cable crane efficiency index dynamic rating model, and early warning control model, and the corresponding information is output for management personnel to manage the cable crane, thereby realizing early warning of the operation status of the cable crane.

[0031] Reference Figure 1 , shows an integrated schematic diagram of the cable monitoring device provided by the example of the present invention, and the cable monitoring device can be integrated based on the positioning antenna 10, the first communication serial port 11 (such as a WIFI serial port), the single-chip microcomputer 12 (such as STM32F103), the specific technical module 13 of the cable monitoring device (such as an M600 module, etc.), the ternary lithium power battery 14, and the second communication serial port (such as a 4G serial port). Specifically, based on satellite differential positioning, Internet of Things communication and other technologies, the cable monitoring device can be developed by integrating satellite positioning, data caching, large-capacity power supply, WIFI or 4G communication. The developed cable monitoring device can realize real-time collection of information such as the position and speed of the cable (for example, in seconds), and realize caching the monitored information and sending it to the server in real time via WIFI or 4G communication.

[0032] Reference Figure 2 , shows a flow chart of the steps of a cable machine monitoring method embodiment of the present invention, which is applied to Figure 1 The cable crane monitoring device shown may specifically include the following steps:

[0033] Step 201, obtaining the full-time position information of the cable crane, and obtaining the material transportation link information of the cable crane based on the full-time position information through a link identification model;

[0034] The cable crane monitoring device provided by the embodiment of the present invention involves a link identification model, an efficiency analysis model, a safety analysis model, a cable crane efficiency index dynamic calibration model, and an early warning control model. In practical applications, in large-scale water conservancy projects, especially during the dam pouring process, the operation status monitoring of the cable crane is extremely important. Specifically, the full-time position information of the cable crane can be obtained, and the link identification model, efficiency analysis model, safety analysis model, and early warning system can be combined to achieve comprehensive monitoring and management of the operation status of the cable crane.

[0035] Among them, the link identification model can be mainly used to identify the key links of the cable crane operation, such as tank stabilization, loading, tank lifting, lifting, positioning, unloading and return; the efficiency analysis model can be mainly used to analyze the operation efficiency of the cable crane in each link; the safety analysis module can be mainly used to monitor whether the safety distance requirements are met during the operation of the cable crane; the dynamic calibration model of the cable crane efficiency index can be mainly used to dynamically adjust the cable crane efficiency index according to the actual operation data to ensure the accuracy and practicality of the index; the early warning and control model can be mainly used to issue early warnings in time when abnormal situations are found, and take corresponding measures for control.

[0036] In one embodiment of the present invention, the operation information of the cable crane can be collected in real time by the cable crane monitoring device, and the collected operation information can refer to the full-time position information of the cable crane.

[0037] The full-time position information refers to the position data of the cable car at every moment during the entire operation process, from the beginning to the end. For example, these position data may generally include the spatial coordinate information and elevation information of the cable car, as well as the timestamp associated therewith.

[0038] The definition of full-time position information can include the following aspects: 1) Real-time position data: At every moment of cable crane operation, the intelligent monitoring equipment collects the current position (x, y, z) and elevation data of the cable crane in real time; 2) Timestamp: Each position data point is accompanied by a timestamp to record the specific time of data collection for subsequent analysis and processing; 3) Continuity: Full-time position information requires that data collection is continuous, that is, during the entire process of cable crane operation, position data is recorded continuously without interruption; 4) Completeness: Full-time position information includes all position data of the cable crane from the start of loading to the start of tank release, covering all material transportation links such as tank stabilization, loading, tank lifting, lifting, alignment, unloading and return; 5) Accuracy: The accuracy of the position data is required to be high enough to ensure that it can accurately reflect the actual position and elevation of the cable crane, thereby supporting the accurate identification of characteristic values ​​and the precise calculation of link time.

[0039] That is, by collecting and analyzing the position information at all times, it is possible to fully monitor the operation status of the cable car, detect problems in time and make adjustments, thereby improving operational efficiency and safety.

[0040] In an embodiment of the present invention, the link identification model can identify the material transportation link of the cable crane based on the acquired full-time position information, obtain the material transportation link information, and then obtain the efficiency index for evaluating the operation efficiency of the cable crane.

[0041] Among them, the material transportation link information identified by the link identification model may include characteristic value moments and link times. The characteristic value moments can be used to define the key moments and states of the cable crane in different operation stages, and can mainly be used to indicate the key moments of the cable crane in different operation stages; the link time can be used to know the time consumed / spent by the cable crane in each stage during the operation process, so as to evaluate and monitor the operation efficiency of the cable crane based on the aforementioned characteristic value moments and link times.

[0042] Specifically, the link identification model can be used to identify the characteristic value time of the cable car based on the full-time position information, and then the link time of the cable car for each material transportation link can be calculated based on the characteristic value time of the cable car. The embodiment of the present invention does not limit the specific link identification process of the link identification model.

[0043] Step 202, obtaining an efficiency index according to the characteristic value time and / or link time through an efficiency analysis model;

[0044] The efficiency analysis model can be mainly used to analyze the operating efficiency of the cable crane in each link. Specifically, the efficiency analysis model can evaluate and monitor the operating efficiency of the cable crane based on the characteristic value moment and link time, and then obtain the efficiency index used to determine the operating efficiency of the cable crane.

[0045] Step 203, obtaining safety indicators of the cable car during operation through a safety analysis model;

[0046] The safety analysis module can be mainly used to monitor whether the safety distance requirements are met during the operation of the cable crane. Specifically, the safety analysis model can obtain the safety indicators of the cable crane during operation through real-time detection of the cable crane's operating status.

[0047] Among them, the safety index may be a safety distance control index, which may be mainly used to indicate whether there is a collision risk and whether the safety distance requirement is met.

[0048] Step 204, early warning of the operation status of the cable car is issued according to the efficiency index and the safety distance control index.

[0049] After obtaining the efficiency index for evaluating the operating efficiency of the cable crane and the safety index for evaluating whether the cable crane is at a safe distance, specifically the safety distance control index for indicating whether there is a collision risk and whether the safety distance requirements are met, the operating status of the cable crane can be warned based on the efficiency index and the safety distance control index.

[0050] Exemplarily, the monitoring and early warning of the operation status of the cable crane can be performed by setting a real-time monitoring interface to display the current position, elevation, characteristic value moments and link times of the cable crane, so as to monitor the characteristic value moments, such as monitoring the loading start time, loading end time, lifting start time, alignment start time, unloading start time, unloading end time and tank release start time, to ensure that the time point of each stage meets expectations; and to monitor the link time, such as monitoring the tank stabilization link, loading link, tank lifting link, lifting link, alignment link, unloading link and return link, to ensure that the time of each link is within a reasonable range. In this regard, the embodiments of the present invention are not limited to this.

[0051] In one embodiment of the present invention, in step 201, the identification of the material transport link information of the cable crane can be achieved by using a link identification model. Specifically, the cable crane material transport process can be as follows: Figure 3 As shown, it involves the transfer platform, tank placing platform, heavy tank lifting and empty tank return. Figure 3 The characteristic value moments can be marked in , where ABCDEFG can represent the positions of each stage (including time nodes) respectively.

[0052] The characteristic value moments can be used to indicate the key moments of the cable car in different operation stages. The key moments may include but are not limited to the start time of loading, the end time of loading, the start time of lifting, the start time of positioning, the start time of unloading, the end time of unloading and the start time of tank release.

[0053] The full-time position information is obtained based on the real-time position data of the cable crane. The recognition of the characteristic value moment of the cable crane can be expressed as obtaining the real-time position data of the cable crane through the link recognition model, wherein the real-time position data includes multiple position data points, each of which can be used to indicate the current spatial coordinates and elevation data of the cable crane at each moment during operation, and each position data point (such as Figure 3 ABCDEFG in the figure can carry a timestamp. At this time, in response to the current spatial coordinates and elevation data indicated by the target position data point meeting the preset conditions, the timestamp carried by the target position data point can be used as the characteristic value moment of the cable car.

[0054] For example, after the cable car moves from the warehouse surface to the cable car platform, when the cable car's elevation is above the cable car platform, and the cable car's spatial coordinates (x, y, z) continue to float within a range of 1 meter within 1.5 minutes, it means that the current spatial coordinates and elevation data meet the preset conditions of position G, then the current time can be defined as the loading start time, assuming it is T1; after the cable car starts to leave the cable car platform, when the cable car's elevation is still above the cable car platform, but the cable car's spatial coordinates (x, y, z) continue to float within a range of 1 meter within 1.5 minutes, it means that the current spatial coordinates and elevation data meet the preset conditions of position G, then the current time can be defined as the loading start time, assuming it is T1; z) When it continuously floats outside the range of 1 meter within 1.5 minutes, it means that the current spatial coordinates and elevation data meet the preset conditions of position A, then the current moment can be defined as the end time of loading, assuming it is T2; if the current spatial coordinates and elevation data meet the position where the cable crane leaves the cable crane platform after loading, that is, position B, then the moment when the cable crane leaves the cable crane platform after loading can be defined as the start time of lifting, assuming it is T3; after the cable crane moves from the cable crane platform to the warehouse surface, when the elevation of the cable crane is lower than the cable crane platform but higher than the closing elevation of the casting warehouse by 30 meters, it means that the current spatial coordinates and elevation data meet the preset conditions of position C, then the current moment can be defined as the start time of alignment, assuming it is T4; after the cable crane moves from the cable crane platform to the warehouse surface , when the cable car's elevation is 2.5 meters lower than the lowest point of the cable car's elevation in this cycle and floats up by 2.5 meters, it means that the current spatial coordinates and elevation data meet the preset conditions of position D, then the current time can be defined as the start time of unloading, assuming it is T5; after the cable car moves from the cable car platform to the warehouse surface, when the cable car's elevation is 2.5 meters lower than the lowest point of the cable car's elevation in this cycle and floats up by 2.5 meters, it means that the current spatial coordinates and elevation data meet the preset conditions of position E, then the current time can be defined as the end time of unloading, assuming it is T6; if the current spatial coordinates and elevation data meet the position where the cable car returns to the cable car platform range after unloading, that is, position F, then the time when the cable car returns to the cable car platform range after unloading is completed can be defined as the start time of tank release, assuming it is T7.

[0055] The material transportation process includes tank stabilization, loading, lifting, hoisting, alignment, unloading and return. The identification of the link time can be expressed as calculating the time difference from the start of the cable car to the start of loading, and obtaining the link time of the cable car in the tank stabilization process, that is, ; and / or, calculating the time difference between the start time of the cable machine and the end time of the cable machine to obtain the link time of the cable machine in the loading link, that is, ; and / or, calculating the time difference between the time when the cable crane ends loading and the time when the lifting begins, and obtaining the link time of the cable crane in the tank lifting link, that is, ; and / or, calculating the time difference between the start time of the cable crane hoisting and the start time of the alignment, and obtaining the link time of the cable crane in the hoisting link, that is, ; and / or, calculating the time difference between the cable crane's start time of alignment and the start time of unloading, and obtaining the link time of the cable crane in the alignment link, that is, ; and / or, calculating the time difference between the cable machine's material unloading start time and the cable machine's material unloading end time, and obtaining the link time of the cable machine in the unloading link, that is, ; and / or, calculating the time difference between the end of unloading and the start of can placement, and obtaining the link time of the cable machine in the return link, that is, .

[0056] In practical applications, intelligent monitoring equipment can be used to collect the location information of the cable car in real time, including spatial coordinates (x, y, z) and elevation data. At this time, the characteristic value and link identification algorithm can be written, and the aforementioned algorithm can be implemented through the link identification model to detect and obtain the corresponding characteristic value, and calculate the link time based on the detected moment, and then set up a real-time monitoring interface to display the current position, elevation, characteristic value moments and link time of the cable car.

[0057] In some embodiments of the present invention, in step 202, the identification of the efficiency index can be achieved by using an efficiency analysis model. Specifically, the cable crane efficiency analysis can be as follows: Figure 4 As shown, it can be combined with the real-time analysis information of the cable crane material transportation link, based on the efficiency evaluation index, to construct a comprehensive analysis model of cable crane efficiency for pre-planning, in-process supervision and post-analysis with "process control as the core, comprehensive analysis as the conclusion, and index rating as the basis".

[0058] For example, Figure 4As shown in the figure, ex ante planning involves the setting of evaluation standards, including the setting of link indicator values, three-level warning values ​​(such as red warning, orange warning, yellow warning), etc., which specifically involves ex ante standard analysis. In the ex ante standard analysis, it can be manifested as building a three-level and seven-link efficiency indicator system for the casting unit based on the division of cable crane lifting links. Combined with the current casting silo project characteristics, resource input, casting period and similar silo casting level and other factors, the three-level control indicator thresholds of the current silo casting efficiency process are set according to the multi-factor efficiency indicator dynamic calibration model; for in-process supervision, it involves red push, hourly push and whole-shift push in process control, etc., which can be specifically manifested as a system based on the casting unit evaluation indicator system. The system, combined with the real-time analysis data of the cable crane monitoring, can realize the cable crane pouring process on the hour and in the whole shift, abnormal situation analysis and warning, immediate push of major abnormalities, and message push, so that the front construction personnel, site management personnel, and rear management personnel can timely grasp the real-time situation of the on-site construction; for post-analysis, it involves comprehensive evaluation, link analysis, abnormality positioning, indicator calibration, etc., which can be specifically manifested as an analysis of the pouring process from the perspective of overall pouring efficiency and link time consumption, and a comprehensive evaluation of the progress of the pouring unit and the trend of changes in key indicators; accurately locate the links and equipment with abnormal pouring efficiency, go deep into individual construction machinery, and combine the on-site construction environment to analyze the factors affecting efficiency abnormalities, and provide a reference for on-site construction management. Preferably, the evaluation indicators of similar dam sections or units can also be calibrated in combination with the pouring efficiency of this warehouse, so as to provide indicator support for subsequent pouring warehouses.

[0059] Specifically, the efficiency analysis model can be used to monitor whether the time point of each material transportation link during the operation of the cable crane meets expectations based on the characteristic value moment; and / or, monitor whether the link time of each material transportation link during the operation of the cable crane is within a reasonable range based on the link time; and / or, evaluate the operating efficiency of the cable crane in each material transportation link based on the characteristic value moment and the link time. For example, characteristic value moment monitoring is performed, such as monitoring the start time of loading, the end time of loading, the start time of lifting, the start time of alignment, the start time of unloading, the end time of unloading and the start time of tank placement, to ensure that the time point of each stage meets expectations; and link time monitoring is performed, such as monitoring the tank stabilization link, the loading link, the tank lifting link, the lifting link, the alignment link, the unloading link and the return link, to ensure that the time of each link is within a reasonable range. In this regard, the embodiments of the present invention are not limited to this.

[0060] In some embodiments of the present invention, in step 203, the identification of the safety distance control index can be achieved by using a safety analysis model. Specifically, the cable crane safety analysis can be as follows: Figure 5As shown, the real-time position information of the main and auxiliary towers and hooks of the cable crane can be monitored through intelligent monitoring equipment. Combined with the terrain of the left and right bank slopes and the dam casting information, the distances between the cable crane-cable crane, cable crane-slope, cable crane-high dam block, and cable crane-warehouse surface equipment can be analyzed in real time to provide support for the safe operation of the cable crane.

[0061] In one embodiment of the present invention, the safety index obtained by analyzing the safety analysis model may be a safety distance control index. In order to obtain the safety distance control index, for example Figure 5 As shown, the cable crane hook running trajectory, construction equipment location information, construction warehouse surface information and high slope information can be obtained through the cable crane monitoring equipment, so as to perform safety analysis based on the cable crane hook running trajectory, construction equipment location information, construction warehouse surface information and high slope information through the safety analysis model to obtain the safety distance control index.

[0062] Among them, the operation trajectory of the cable crane hook can be used to indicate the real-time position of the main and auxiliary towers of the cable crane, the construction equipment position information can be used to indicate the real-time position of the cable crane hook, the construction warehouse surface information can include warehouse surface design information and pouring progress information, and the high slope information can include slope coordinate information.

[0063] The basic data include the operation track of the cable crane hook, the location information of the construction equipment, the construction warehouse surface information, the high slope information, etc. In practical applications, the collection of basic data can be specifically manifested as obtaining the real-time location information of the cable crane and construction equipment through monitoring equipment; entering the warehouse surface design information through the system input function, and then obtaining the dam section pouring elevation information through the pouring progress information and the warehouse surface design information; and entering the slope coordinate information through the slope excavation and design information.

[0064] In the process of conducting safety analysis through the safety analysis model and obtaining the safety distance control index, such as Figure 5 As shown, it involves real-time process analysis and comprehensive analysis and early warning. For real-time process analysis, it can involve cable crane swing analysis, cable crane operation envelope analysis, construction warehouse surface elevation and boundary analysis, high slope 10*10m grid analysis, etc. through safety analysis model.

[0065] The cable crane swing analysis performed by the safety analysis model can be specifically performed by constructing a cable crane main cable straight line based on the real-time position of the cable crane main and auxiliary towers, and using the cable crane main cable straight line and the real-time position of the cable crane hook to analyze the cable crane hook swing value, that is, the swing value of the cable crane hook on a preset plane. For example, the cable crane main cable straight line can be constructed based on the real-time position of the cable crane main and auxiliary towers, and the swing value of the hook on the xy plane can be analyzed in combination with the real-time position of the cable crane hook.

[0066] The cable crane operation envelope diagram analysis performed by the safety analysis model can be specifically performed by constructing a cable crane operation area envelope diagram based on the cable crane hook swing amplitude value and the cable crane hook real-time position through the safety analysis model. For example, the cable crane operation area envelope diagram can be constructed by analyzing the cable crane hook real-time position information based on the cable crane hook swing amplitude value.

[0067] The construction warehouse surface elevation and boundary analysis conducted by the safety analysis model can be specifically manifested as obtaining the pouring start and end elevation information of the current warehouse based on the pouring progress of each dam section in the pouring progress information through the safety analysis model, and then obtaining the volume of each strip during the warehouse surface pouring process from the pouring progress information, and estimating the current pouring elevation information using the warehouse surface design information and the volume of each strip. Among them, the pouring start and end elevation information can be used to indicate the boundary of the construction warehouse surface, and the current pouring elevation information can be used to indicate the elevation of the construction warehouse surface. Exemplarily, the pouring start and end elevations of the current warehouse can be judged based on the pouring progress of each dam section, and the current pouring elevation can be estimated based on the volume of each strip during the warehouse surface pouring process.

[0068] The high slope gridding (e.g., 10*10m grid) analysis performed by the safety analysis model can be specifically performed by gridding the high slope to obtain grid information for the slope based on the slope coordinate information and the preset cable crane safety spacing control strategy through the safety analysis model. For example, the slope can be converted into a 10*10m basic grid based on the slope coordinates and the cable crane safety spacing control standard.

[0069] Exemplarily, the safety analysis model, i.e., the dam concrete cable crane operation safety analysis model, can also be combined with the above-mentioned process analysis to achieve a comprehensive analysis, including but not limited to analysis of the spacing between adjacent cable cranes, analysis of the distance between the unloading point and the warehouse surface boundary, analysis of the height difference between the cable crane operation trajectory and the high dam block, analysis of the distance between the cable crane operation trajectory and the high slope, and analysis of the distance between the unloading point and the construction equipment. The embodiments of the present invention are not limited to this.

[0070] In one embodiment of the present invention, a safety analysis model can be used to perform real-time analysis of the safety distance of the cable crane based on the above-obtained cable crane hook swing amplitude value, the envelope diagram of the cable crane operation area, the elevation and boundary of the construction warehouse surface, the grid information of the slope, etc., to obtain a safety distance control index and realize real-time analysis and early warning of the safety distance of the cable crane.

[0071] In practical applications, the safety distance control index can be used to indicate whether there is a collision risk and whether the safety distance requirements are met. For comprehensive analysis and early warning, that is, the real-time analysis and early warning process of the cable car safety distance, it is mainly manifested in the analysis and judgment of whether there is a collision risk and whether the safety distance requirements are met, so as to combine the safety distance control indicators of each stage to provide early warning information prompts to the cable car operation safety management personnel.

[0072] Specifically, in one case, the operation area of ​​the cable crane can be predicted based on the change in the straight line position of the main cable of the cable crane and the maximum swing amplitude value of the cable crane in the swing amplitude value of the cable crane hook through the safety analysis model; the distance between adjacent cables is obtained by using the predicted operation area of ​​the cable crane and the envelope diagram of the cable crane operation area; wherein, the distance between adjacent cables is used to indicate the minimum distance between the boundaries of the operation areas of adjacent cables; the minimum distance between the boundaries of the operation areas of adjacent cables is used to determine whether there is a risk of collision between adjacent cables. Exemplarily, the operation area of ​​the cable crane can be predicted in real time based on the change in the straight line position of the main cable and the maximum swing amplitude value of the cable crane, and the minimum distance between the boundaries of the operation areas of adjacent cables, that is, the distance between adjacent cables, is calculated, and then it is determined whether there is a risk of collision between adjacent cables.

[0073] In another case, the safety analysis model can be used to determine the position information of the cable crane hoisting and return trip based on the cable crane hook swing amplitude value, and the distance between the cable crane and the slope can be analyzed based on the position information of the cable crane hoisting and return trip and the slope coordinate information in the grid information of the slope; the distance between the cable crane and the slope can be used to predict whether there is a collision risk when the cable crane is running at this elevation. Exemplarily, the distance between the cable crane and the slope can be analyzed in real time based on the position information of the cable crane hoisting and return trip, combined with the slope coordinate information, to predict whether there is a collision risk when the cable crane is running at this elevation.

[0074] In another case, the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section can be obtained through the safety analysis model based on the elevation and boundary of the construction warehouse surface. Based on the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section, the height difference between the cable crane hook and the high dam block below the operation can be predicted; the height difference between the cable crane hook and the high dam block below the operation can be used to judge whether the height difference between the cable crane and the high dam section meets the safety spacing requirements. Exemplarily, the height difference between the cable crane hook and the high dam block below the operation can be predicted based on the real-time elevation information of the cable crane lifting link, combined with the casting elevation of each dam section, to further judge whether the height difference between the cable crane and the high dam section meets the safety spacing requirements.

[0075] In another case, the real-time position information of the cable crane entering the alignment link and the coordinate information of the warehouse surface boundary can be obtained through the safety analysis model based on the elevation and boundary of the construction warehouse surface. Based on the real-time position information of the cable crane entering the alignment link and the coordinate information of the warehouse surface boundary, the horizontal distance between the cable crane and the preset template can be analyzed; the horizontal distance between the cable crane and the template can be used to predict whether there is a collision risk between the cable crane and the preset template. Exemplarily, the horizontal distance between the cable crane and the template can be analyzed in real time based on the real-time position information of the cable crane entering the alignment link and the coordinate information of the warehouse surface boundary, so as to predict whether there is a collision risk between the cable crane and the template.

[0076] In another case, the safety analysis model can be used to predict the distance between the cable crane and the casting surface and construction equipment based on the cable crane alignment and material unloading link position information, and the warehouse surface casting elevation and construction equipment position information; the distance between the cable crane and the casting surface and construction equipment is used to determine whether there is a collision risk between the cable crane and the casting surface and construction equipment. For example, based on the cable crane alignment and material unloading link position information, combined with the warehouse surface casting elevation and construction equipment position information, the distance between the cable crane and the casting surface and construction equipment can be predicted, and then it can be determined whether there is a collision risk between the cable crane and the casting surface and construction equipment.

[0077] In one embodiment of the present invention, the early warning of the operation status of the cable crane in step 204 can be implemented with the help of an early warning control model. Specifically, the efficiency index and the safety index can be used as the basis for early warning of the operation status of the cable crane, such as Figure 6 As shown, the efficiency index and safety index can be used to form an efficient and safe management and control index system for cable cranes. That is, the cable crane group efficient and safe operation early warning index system can be divided into two categories, three levels and 14 indicators according to the cable crane transportation link division and safety analysis content.

[0078] In practical applications, in order to dynamically adjust the cable crane efficiency index according to the actual operation data and ensure the accuracy and practicality of the index, when performing early warning analysis through the early warning control model, it is also necessary to use the efficiency index dynamic calibration model. Specifically, the control index threshold of the current silo pouring efficiency process can be set through the efficiency index dynamic calibration model, and then the early warning control model can push the early warning prompt information for the operation status of the cable crane based on the control index threshold, efficiency index and safety spacing control index. Exemplarily, the three-level early warning can be expressed as a yellow threshold, an orange threshold and a red threshold. The safety indicators can include the wind speed in the dam area, the cable crane rate, the cable crane swing amplitude, the cable crane spacing, the cable crane-slope, the cable crane-dam block and the cable crane-machinery, etc. The efficiency index can include the tank stabilization time, the tank lifting time, the loading time, the lifting time, the alignment time, the unloading time, the return time, etc., and the embodiments of the present invention are not limited to this.

[0079] In one embodiment of the present invention, it can be specifically manifested as determining the cable crane efficiency benchmark value through an efficiency index dynamic calibration model, and then constructing a control index threshold value divided into preset levels based on the cable crane efficiency benchmark value.

[0080] Among them, the cable crane efficiency benchmark value can be used to reflect the efficiency level of each current pouring dam section. Its rationality directly affects the accuracy of the three-level warning indicators. Since the cable crane efficiency benchmark value may increase with the increase of dam elevation, project management level, construction organization ability, and construction personnel quality, the cable crane efficiency benchmark value calculated using a single historical average or monthly average cannot truly reflect the current pouring level.

[0081] For determining the cable crane efficiency benchmark value, historical monitoring data can be obtained through the efficiency index dynamic calibration model, and the cable crane efficiency benchmark value can be calibrated based on the historical monitoring data using the piecewise weight method; and / or, the cable crane efficiency benchmark value can be calibrated using the similar dam section analogy method according to the cable crane transportation distance and casting bin characteristics of each dam section through the efficiency index dynamic calibration model.

[0082] Reference Figure 7 , shows a schematic diagram of a cable crane efficiency index dynamic calibration model provided by an example of the present invention. The efficiency evaluation index calculation model can use an index dynamic inversion analysis method to achieve a cable crane efficiency benchmark value. The index dynamic inversion analysis method can be specifically manifested as after starting the index setting through the efficiency evaluation index calculation model, it can be determined whether the setting is for a complex warehouse, and different segmented weight methods are used to calibrate the evaluation index based on different judgment results. Among them, the segmented weight method can be manifested as a historical data segmented weight method and a similar dam section analogy analysis method.

[0083] In one case, when the judgment result is that it is not set up for a complex warehouse, the control index of the warehouse surface construction on a single day (on the hour) can be calculated and used as the evaluation index. At this time, the historical data segmentation weight method is specifically used; in another case, when the judgment result is that the setting is set up for a complex warehouse, the control index of the warehouse surface construction on a single day (on the hour) can be calculated and used as the evaluation index. At this time, the historical data segmentation weight method and the similar dam section analogy analysis method are specifically used, which is manifested in that the evaluation index calculated by the historical data segmentation weight method is used as the historical mean for the calculation of the evaluation index of the similar dam section analogy analysis method. It should be noted that the historical data segmentation weight method and the similar dam section analogy analysis method both belong to the segmentation weight method, and their calculation process involves weighted calculation.

[0084] Exemplarily, the historical data segmented weight method can be expressed as determining the cable crane efficiency benchmark value based on historical monitoring data using the segmented weight method, and the formula is: index value = monitoring warehouse average * 0.2 + historical average * 0.2 + historical optimal value * 0.2 + average of the past three months * 0.4, thereby truly reflecting the current cable crane casting efficiency level, wherein the monitoring warehouse average may refer to the current or most recent average value, the historical average may refer to the average value of the past period of time, the historical optimal value may refer to the best value in the past period of time, the average of the past three months may refer to the average value of the past three months, 0.2 and 0.4 may refer to the weights of the corresponding variables, and the specific weights may be determined based on actual needs or experiments, and the embodiments of the present invention are not limited to this.

[0085] The similar dam section analogy method can be expressed as follows: according to the cable crane transportation distance and casting bin characteristics of each dam section, the cable crane efficiency benchmark value is calibrated by the similar dam section analogy method, and the formula is: index value = monitoring bin average value * 0.2 + historical average value * 0.2 + similar bin surface optimal value * 0.2 + similar bin surface average value * 0.4, thereby truly reflecting the transportation efficiency of special dam sections such as different transportation distances and complex structure bin surfaces (middle holes, bottom holes), among which the monitoring bin average value may refer to the current or most recent average value, the historical average value may refer to the average value over a period of time in the past, the optimal value of similar bin surfaces may refer to the best value of other bin surfaces similar to the current situation, the similar bin surface average value may refer to the average value of other bin surfaces similar to the current situation, 0.2 and 0.4 may refer to the weights of the corresponding variables, and the specific weights may be determined based on actual needs or experiments, and the embodiments of the present invention are not limited to this.

[0086] Optionally, when constructing control index thresholds divided according to preset levels based on the cable crane efficiency benchmark value, control index thresholds of preset first level, preset second level and preset third level can be constructed based on the cable crane efficiency index benchmark value, wherein the preset first level can be higher than the preset second level, and the preset second level can be higher than the preset third level. For example, the control index threshold of the preset first level can be a red warning index value, the control index threshold of the preset second level can be an orange warning index value, and the control index threshold of the preset third level can be a yellow warning index value. That is, based on the constructed yellow, orange and red three-level warning index values, in order to finely reflect the cable crane transportation efficiency level, the cable crane transportation efficiency change law according to season, day shift, night shift and hourly time can be calculated, and the cable crane operation efficiency value at the hourly time can be calculated, thereby realizing fine setting and control of cable crane indicators. This is not limited in this regard by the embodiments of the present invention.

[0087] Dam construction involves many parties involved and a complex personnel structure. In order to meet the requirements of efficient and safe management and control of cable crane groups, an early warning and control model for cable crane operation can be constructed. Specifically, when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset first level, the early warning prompt information is pushed immediately; when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset second level, the early warning prompt information is pushed at a scheduled time, such as an hourly warning; when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset third level, the early warning prompt information is pushed in batches, such as a shift warning.

[0088] See also Figure 8 , showing a schematic diagram of a cable crane operation early warning control model provided by an embodiment of the present invention, the cable crane early warning control model is specifically manifested as an early warning feedback model, involving process control and comprehensive evaluation process.

[0089] Exemplarily, in process control, early warnings can be issued based on the results of cable crane efficiency and safety analysis combined with three-level early warning indicators. For example, red early warning information is pushed in real time so that timely rectification can be carried out on site to achieve immediate early warning; statistics on the operation of yellow, orange and hourly cable crane groups are pushed so that all construction parties can grasp the on-site construction situation in a timely manner and achieve hourly early warnings and shift early warnings. It should be noted that the message pushers include on-site construction workers, on-site supervisors, on-site production office managers, rear management, leadership (such as construction department leaders, supervision department leaders), etc. The push method can be mainly mobile APP, which is not limited by the embodiments of the present invention.

[0090] In the comprehensive evaluation process, the overall operation of the cable crane can be analyzed in combination with the on-site construction situation, and the abnormal operation of the cable crane can be accurately located and analyzed, key influencing factors can be identified, and reported to the owner, design, supervision, and construction parties for analysis to provide reference for subsequent construction. For example, the comprehensive evaluation of cable crane operation includes but is not limited to efficiency evaluation, abnormality analysis, utilization rate, and safety analysis, and the evaluation results can be comprehensively appraised by three parties after the comprehensive evaluation of cable crane operation. The three parties can include leadership and construction personnel.

[0091] This embodiment of the present invention is not limited to this.

[0092] In an embodiment of the present invention, the full-time position information of the cable crane is obtained through the cable crane monitoring device, and the material transportation link information of the cable crane is obtained based on the full-time position information through the link identification model. The obtained material transportation link information may include characteristic value time and link time, and then the efficiency analysis model is used to obtain the efficiency index according to the characteristic value time and / or link time, and the safety index of the cable crane during operation is obtained through the safety analysis model. The safety index may be a safety distance control index, which is mainly used to indicate whether there is a collision risk and whether the safety distance requirements are met, so as to give an early warning of the operation status of the cable crane based on the efficiency index and safety distance control index obtained by analysis. By obtaining the full-time position information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, the efficiency analysis model, and the safety analysis model, and the corresponding information is output for the management personnel to manage the cable crane, thereby realizing an early warning of the operation status of the cable crane.

[0093] In order to facilitate those skilled in the art to understand the cable crane monitoring method proposed in the embodiment of the present invention, the embodiment of the present invention is described as follows by combining the application scenario of cable crane monitoring:

[0094] Reference Fig. 9, showing a schematic diagram of an application scenario of cable crane monitoring provided by an embodiment of the present invention. The cable crane monitoring solution provided by an embodiment of the present invention can be mainly implemented by being deployed on an intelligent management and control platform for safe construction of dam concrete. The intelligent management and control platform for safe construction of dam concrete can be a digital platform.

[0095] For a certain dam pouring project, the cable crane monitoring equipment can be controlled through the safe construction intelligent management and control platform to achieve comprehensive monitoring of the cable crane's operating status. Specifically, it can be manifested in using the link identification model to automatically identify the link in which the cable crane is currently located, using the efficiency analysis module to calculate the efficiency indicators of each link, using the safety analysis model to monitor potential safety risks, using the cable crane efficiency indicator dynamic calibration model to dynamically adjust the efficiency indicator, and using the early warning management and control model to issue early warnings in time when abnormal situations are found. Through the comprehensive application of the above-mentioned models, the efficient and safe operation of the cable crane can be ensured, and the smooth progress of the dam pouring project can be guaranteed.

[0096] In the safe construction intelligent management and control platform, display interfaces related to information such as cable crane safety, cable crane material transportation process, pouring quality, transportation intensity, warehousing intensity, transportation efficiency, and efficiency warning can be displayed.

[0097] For example, suppose that in a dam pouring project, an elliptical concrete hyperbolic arch dam is used, the dam crest elevation is 834.00m, the maximum dam height is 289.0m, and the total volume is about 8.1 million m 3 The dam body is provided with transverse joints but no longitudinal joints, and is divided into 31 dam sections. The peak pouring monthly design strength is 236,300 m 3 ; and, assuming that there are 7 cable cranes in total, and a high-line and low-line double-layer layout is adopted, the main rail length of the high cable crane is 310m, the maximum span is 1186.756m, the main rail length of the low cable crane is 245m, the maximum span is 1110.49m, and the dam valley is windy all year round, with a maximum wind speed of 29.8m / s. At this time, in the process of realizing the operation and control of the cable crane group through the intelligent control platform for the safe construction of dam concrete, the large-screen system of the digital control system for the efficient and safe construction of dam concrete throughout the process can be used to realize real-time monitoring of key efficiency and safety indicators; mobile supervision can also be realized through the monitoring and early warning platform.

[0098] Taking other construction interference affecting the cable crane operation efficiency as an example, the cable crane efficiency analysis table can be shown in Table 1:

[0099] type Waiting for material min Loading min Transport min Discharging min Return trip min Single cycle min Baseline value (a) 4.32 0.9 7.58 0.86 3.32 16.98 Week 1 5.54 0.83 7.48 0.81 3.46 18.12 Week 2 6.17 0.89 7.32 0.75 3.45 18.58 Week 3 5.77 0.85 7.58 0.82 3.24 18.26 Week 4 4.82 0.9 7.36 0.7 3.67 17.45

[0100] Table 1 Cableway efficiency analysis table

[0101] From the above, it can be seen that the site conditions in the first three weeks were higher than the benchmark values. After a joint investigation, it was found that the construction of the cable car platform caused the transport vehicle passage to be blocked, causing the cable car to wait for materials for about 1 to 2 minutes. At this time, a dedicated channel for transport vehicles can be proposed to avoid affecting the dam pouring efficiency as much as possible. After verification and analysis in the fourth week, it was found that the waiting time for materials was significantly reduced and the overall pouring efficiency was significantly improved.

[0102] The embodiment of the present invention introduces new thinking of the industrial Internet, adopts technologies such as "Internet of Things, sensors, and big data", proposes a cable machine analysis and control system of "control objectives, evaluation indicators, dynamic control, and comprehensive evaluation", and a new hydropower engineering construction system that is fully connected with all elements, the entire industrial chain, and the entire value chain. An efficient, safe, and intelligent control platform for cable machine groups that integrates "intelligent monitoring, real-time analysis, feedback warning, and dynamic tracking" has been developed. With large-screen systems, mobile APPs, and smart terminals as media, multi-dimensional collaborative control covering owners, designers, supervisors, construction, and scientific research units is achieved to make up for the construction management deficiencies of difficult supervision, coordination, and traceability. Although domestic research on intelligent construction of hydropower projects has achieved certain results, there are still many difficulties and difficulties that need to be tackled in the refined control of the entire process of concrete dam construction, and it is necessary to closely combine the needs of engineering construction with continuous in-depth exploration and innovation. With the continuous maturity of emerging technologies such as the Beidou positioning system, engineering digital construction technology, big data technology, and new infrastructure, and the continuous deepening of research on intelligent analysis and control technology in the hydropower industry, the sustainable development of intelligent dam construction technology in my country and even the world will be promoted.

[0103] In the embodiment of the present invention, in order to ensure the efficient and safe operation of the cable crane, the embodiment of the present invention is based on the intelligent construction theory, and uses network communication technology, Internet of Things technology, high-precision positioning, cross-platform complex information management, big data analysis technology, etc. as means to carry out research on intelligent monitoring equipment, link identification models, comprehensive analysis and hierarchical early warning feedback mechanisms, etc., to build an efficient and safe intelligent management and control platform for cable crane groups, and realize a cable crane intelligent management and control system with real-time monitoring, online analysis, dynamic tracking, and intelligent feedback, effectively improving the efficient and safe operation of the cable crane group. Specifically, by obtaining the operation information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, efficiency analysis model, safety analysis model, cable crane efficiency index dynamic rating model, and early warning control model, and the corresponding information is output for management personnel to manage the cable crane, thereby realizing early warning of the operation status of the cable crane.

[0104] It should be noted that, for the sake of simplicity, the method embodiments are described as a series of action combinations, but those skilled in the art should be aware that the embodiments of the present invention are not limited by the order of the actions described, because according to the embodiments of the present invention, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions involved are not necessarily required by the embodiments of the present invention.

[0105] Reference Fig.10 , shows a structural block diagram of an embodiment of a cable crane monitoring device of the present invention, which is applied to cable crane monitoring equipment, involves a link identification model, an efficiency analysis model and a safety analysis model, and can specifically include the following modules:

[0106] The link identification module 1001 is used to obtain the full-time position information of the cable crane, and obtain the material transportation link information of the cable crane based on the full-time position information through the link identification model; the material transportation link information includes the characteristic value moment and the link time; the characteristic value moment is used to indicate the key moment of the cable crane in different operation stages;

[0107] An efficiency analysis module 1002, configured to obtain an efficiency index according to the characteristic value moment and / or the link time by using the efficiency analysis model;

[0108] A safety analysis module 1003 is used to obtain a safety index of the cable car during operation using the safety analysis model; the safety index is a safety distance control index, and the safety distance control index is used to indicate whether there is a collision risk and whether the safety distance requirement is met;

[0109] The early warning module 1004 is used to issue an early warning on the operation status of the cable car according to the efficiency index and the safety distance control index.

[0110] In one embodiment of the present invention, the link identification module 1001 may include the following submodules:

[0111] The link identification submodule is used to obtain the characteristic value time of the cable car based on the full-time position information identification; and calculate the link time of the cable car for each material transportation link based on the characteristic value time of the cable car.

[0112] In one embodiment of the present invention, the full-time position information is obtained based on detecting the real-time position data of the cable car; the link identification submodule may include the following units:

[0113] A characteristic value moment acquisition unit is used to acquire real-time position data of the cable crane; the real-time position data includes a plurality of position data points, each position data point is used to indicate the current spatial coordinates and elevation data of the cable crane at each moment when the cable crane is in operation; wherein each position data point carries a timestamp; in response to the current spatial coordinates and elevation data indicated by the target position data point satisfying a preset condition, the timestamp carried by the target position data point is used as the characteristic value moment of the cable crane.

[0114] In one embodiment of the present invention, the material transport link includes a tank stabilization link, a material loading link, a tank lifting link, a lifting link, a positioning link, a material unloading link and a return link; the link identification submodule may include the following units:

[0115] The link time acquisition unit is used to calculate the time difference of the cable machine from the start time of releasing the can to the start time of loading, so as to obtain the link time of the cable machine in the can stabilizing link; and / or, calculate the time difference of the cable machine from the start time of loading to the end time of loading, so as to obtain the link time of the cable machine in the loading link; and / or, calculate the time difference of the cable machine from the end time of loading to the start time of lifting, so as to obtain the link time of the cable machine in the can lifting link; and / or, calculate the time difference of the cable machine from the start time of lifting to the start time of alignment, so as to obtain the link time of the cable machine in the lifting link; and / or, calculate the time difference of the cable machine from the start time of alignment to the start time of unloading, so as to obtain the link time of the cable machine in the alignment link; and / or, calculate the time difference of the cable machine from the start time of unloading to the end time of unloading, so as to obtain the link time of the cable machine in the unloading link; and / or, calculate the time difference of the cable machine from the end time of unloading to the start time of releasing the can, so as to obtain the link time of the cable machine in the return link.

[0116] In one embodiment of the present invention, the efficiency analysis module 1002 may include the following submodules:

[0117] An efficiency analysis submodule is used to monitor whether the time point of each material transport link of the cable crane during operation is in line with expectations based on the characteristic value moment; and / or, to monitor whether the link time of each material transport link of the cable crane during operation is within a reasonable range based on the link time; and / or, to evaluate the operating efficiency of the cable crane in each material transport link based on the characteristic value moment and the link time.

[0118] In one embodiment of the present invention, the security analysis module 1003 may include the following submodules:

[0119] The safety analysis submodule is used to obtain the cable crane hook running trajectory, construction equipment location information, construction warehouse surface information and high slope information; use the safety analysis model to perform safety analysis based on the cable crane hook running trajectory, construction equipment location information, construction warehouse surface information and high slope information to obtain a safety spacing control index.

[0120] In one embodiment of the present invention, the cable crane hook running track is used to indicate the real-time position of the cable crane main and auxiliary towers; the construction equipment position information is used to indicate the real-time position of the cable crane hook; the construction warehouse surface information includes warehouse surface design information and pouring progress information; the high slope information includes slope coordinate information;

[0121] The security analysis submodule may include the following units:

[0122] A safety index acquisition unit is used to construct a cable crane main cable straight line based on the real-time positions of the cable crane main and auxiliary towers, and obtain the cable crane hook swing amplitude value by analyzing the cable crane main cable straight line and the real-time position of the cable crane hook; and / or, construct an envelope diagram of the cable crane operation area based on the cable crane hook swing amplitude value and the real-time position of the cable crane hook through the safety analysis model; and / or, obtain the pouring start and end elevation information of the current warehouse through the safety analysis model based on the pouring progress of each dam section in the pouring progress information; obtain the starting and ending elevation information of the warehouse surface from the volume of each strip during the warehouse surface pouring process in the pouring progress information, and obtain the starting and ending elevation information of the warehouse surface design information. The current pouring elevation information is obtained by estimating the volume of material cut for each strip; wherein the pouring start and end elevation information is used to indicate the boundary of the construction warehouse surface, and the current pouring elevation information is used to indicate the elevation of the construction warehouse surface; and / or, the high slope is gridded by the safety analysis model based on the slope coordinate information and a preset cable crane safety spacing control strategy to obtain grid information for the slope; the safety analysis model is used to perform real-time analysis of the cable crane safety spacing based on the cable crane hook swing amplitude value, the cable crane operation area envelope diagram, the construction warehouse surface elevation and boundary, and the grid information for the slope to obtain a safety spacing control index.

[0123] In one embodiment of the present invention, the security indicator acquisition unit may include the following subunits:

[0124] A safety index acquisition subunit is used to predict the operation area of ​​the cable crane based on the change of the main cable straight line position of the cable crane main cable straight line and the maximum cable crane swing amplitude value in the cable crane hook swing amplitude value; use the predicted operation area of ​​the cable crane and the envelope diagram of the cable crane operation area to obtain the distance between adjacent cable cranes; wherein, the distance between adjacent cable cranes is used to indicate the minimum distance between the boundaries of the adjacent cable crane operation areas; use the minimum distance between the boundaries of the adjacent cable crane operation areas to determine whether there is a collision risk between adjacent cable cranes;

[0125] And / or, determining the position information of the cable crane hoisting and return trip based on the cable crane hook swing amplitude value, analyzing and obtaining the distance between the cable crane and the slope based on the position information of the cable crane hoisting and return trip and the slope coordinate information in the grid information for the slope; using the distance between the cable crane and the slope to predict whether there is a collision risk when the cable crane is running at this elevation;

[0126] And / or, based on the elevation and boundary of the construction warehouse surface, the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section are obtained; based on the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section, the height difference between the hook of the cable crane and the high dam block below the cable crane is predicted; the height difference between the hook of the cable crane and the high dam block below the cable crane is used to judge whether the height difference between the cable crane and the high dam section meets the safety spacing requirement;

[0127] And / or, based on the elevation and boundary of the construction warehouse surface, the real-time position information of the cable crane entering the alignment link and the warehouse surface boundary coordinate information are obtained; based on the real-time position information of the cable crane entering the alignment link and the warehouse surface boundary coordinate information, the horizontal distance between the cable crane and the preset template is analyzed and obtained; the horizontal distance between the cable crane and the template is used to predict whether there is a risk of collision between the cable crane and the preset template;

[0128] And / or, based on the cable crane alignment and material unloading link position information, and the warehouse surface casting elevation and construction equipment position information, predict the distance between the cable crane and the casting surface and construction equipment; use the distance between the cable crane and the casting surface and construction equipment to determine whether there is a collision risk between the cable crane and the casting surface and construction equipment.

[0129] In one embodiment of the present invention, it also involves an efficiency index dynamic rating model and an early warning control model, wherein the safety index is a safety distance control index; the early warning module 1004 may include the following submodules:

[0130] The early warning submodule is used to use the efficiency index dynamic calibration model to set the control index threshold of the current silo casting efficiency process; and use the early warning management and control model to push early warning prompt information for the operation status of the cable car based on the control index threshold, the efficiency index and the safety distance control index.

[0131] In one embodiment of the present invention, the early warning submodule may include the following units:

[0132] The index threshold setting unit is used to determine the cable crane efficiency reference value; the reference value is used to reflect the efficiency level of each current casting dam section; based on the cable crane efficiency reference value, a control index threshold divided according to a preset level is constructed.

[0133] In one embodiment of the present invention, the indicator threshold setting unit may include the following subunits:

[0134] The indicator threshold setting subunit is used to obtain historical monitoring data and calibrate the cable crane efficiency benchmark value based on the historical monitoring data using a piecewise weight method; and / or, according to the cable crane transportation distance and casting bin characteristics of each dam section, use a similar dam section analogy method to calibrate the cable crane efficiency benchmark value.

[0135] In an embodiment of the present invention, the control index threshold is obtained according to preset levels, and the preset levels include a preset first level, a preset second level, and a preset third level; the early warning submodule may include the following units:

[0136] An early warning unit is used to push the early warning prompt information in real time when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset first level; and / or, when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset second level, push the early warning prompt information regularly; and / or, when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset third level, push the early warning prompt information in batches; wherein the preset first level is higher than the preset second level, and the preset second level is higher than the preset third level.

[0137] In an embodiment of the present invention, the cable crane monitoring device provided by the embodiment of the present invention obtains the full-time position information of the cable crane through the cable crane monitoring device, and obtains the material transportation link information of the cable crane based on the full-time position information through the link identification model. The obtained material transportation link information may include characteristic value time and link time, and then obtain the efficiency index according to the characteristic value time and / or link time through the efficiency analysis model, and obtain the safety index of the cable crane during operation through the safety analysis model. The safety index can be a safety distance control index, which is mainly used to indicate whether there is a collision risk and whether the safety distance requirements are met, so as to warn the operation status of the cable crane based on the efficiency index and safety distance control index obtained by analysis. By obtaining the full-time position information of the cable crane, the use process of the cable crane is monitored in real time based on the link identification model, the efficiency analysis model, and the safety analysis model, and the corresponding information is output for the management personnel to manage the cable crane, thereby realizing the early warning of the operation status of the cable crane.

[0138] As for the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0139] An embodiment of the present invention further provides an electronic device, including:

[0140] It includes a processor, a memory, and a computer program stored in the memory and capable of running on the processor. When the computer program is executed by the processor, the various processes of the above-mentioned cable machine monitoring method embodiment are implemented, and the same technical effect can be achieved. To avoid repetition, it will not be repeated here.

[0141] An embodiment of the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the various processes of the above-mentioned cable machine monitoring method embodiment are implemented, and the same technical effect can be achieved. To avoid repetition, it will not be repeated here.

[0142] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0143] It should be understood by those skilled in the art that the embodiments of the present invention can be provided as methods, devices, or computer program products. Therefore, the embodiments of the present invention can take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the embodiments of the present invention can take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.

[0144] The embodiments of the present invention are described with reference to the flowcharts and / or block diagrams of the methods, terminal devices (systems), and computer program products according to the embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of the processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing terminal device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing terminal device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0145] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing terminal device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce a manufactured product including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0146] These computer program instructions can also be loaded onto a computer or other programmable data processing terminal device so that a series of operating steps are executed on the computer or other programmable terminal device to produce a computer-implemented process, thereby providing instructions for executing on the computer or other programmable terminal device to implement the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0147] Although the preferred embodiments of the present invention have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the embodiments of the present invention.

[0148] Finally, it should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of relevant data must comply with the relevant laws, regulations and standards of relevant countries and regions, and provide corresponding operation entrances for users to choose to authorize or refuse.

[0149] It should also be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or terminal device including the elements.

[0150] The above describes in detail a cable machine monitoring method, a cable machine monitoring device, a corresponding electronic device and a corresponding computer-readable storage medium provided by the present invention. Specific examples are used herein to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea. At the same time, for those skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as a limitation on the present invention.

Claims

1. A cable crane monitoring method, It is characterized in that Applied to cable crane monitoring equipment, involving link identification model, efficiency analysis model and safety analysis model, the method includes: Acquire the full-time position information of the cable crane, and acquire the material transportation link information of the cable crane based on the full-time position information through the link identification model; the material transportation link information includes characteristic value time and link time; the characteristic value time is used to indicate the key moment of the cable crane in different operation stages; Obtaining an efficiency index according to the characteristic value moment and / or the link time through the efficiency analysis model; The safety index of the cable car during operation is obtained through the safety analysis model; the safety index is a safety distance control index, and the safety distance control index is used to indicate whether there is a collision risk and whether the safety distance requirement is met; Providing an early warning of the operation status of the cable car according to the efficiency index and the safety distance control index; Among them, it also involves an efficiency index dynamic rating model and an early warning management and control model, the safety index is a safety spacing control index; the early warning of the operation status of the cable crane according to the efficiency index and the safety spacing control index includes: setting the control index threshold of the current bin casting efficiency process through the efficiency index dynamic rating model; pushing early warning prompt information for the operation status of the cable crane based on the control index threshold, the efficiency index and the safety spacing control index through the early warning management and control model; The control index threshold value of the current bin pouring efficiency process is set by the efficiency index dynamic calibration model, including: determining the cable crane efficiency reference value by the efficiency index dynamic calibration model; the reference value is used to reflect the efficiency level of each current pouring dam section; based on the cable crane efficiency reference value, constructing the control index threshold value divided according to the preset level; The method of determining the cable crane efficiency benchmark value through the efficiency index dynamic calibration model includes: obtaining historical monitoring data through the efficiency index dynamic calibration model, and calibrating the cable crane efficiency benchmark value based on the historical monitoring data by using a piecewise weight method; and / or calibrating the cable crane efficiency benchmark value by using a similar dam section analogy method according to the cable crane transportation distance and casting bin characteristics of each dam section through the efficiency index dynamic calibration model.

2. The method according to claim 1, It is characterized in that The obtaining of the material transport link information of the cable car based on the full-time position information through the link identification model includes: Obtaining the characteristic value moment of the cable car based on the full-time position information through the link identification model; The link time of the cable crane for each material transportation link is calculated based on the characteristic value of the cable crane.

3. The method according to claim 2, It is characterized in that The full-time position information is obtained based on detecting the real-time position data of the cable car; the characteristic value moment of the cable car is obtained based on the full-time position information through the link identification model, including: Acquiring the real-time position data of the cable crane through the link identification model; the real-time position data includes a plurality of position data points, each of which is used to indicate the current spatial coordinates and elevation data of the cable crane at each moment when the cable crane is in operation; wherein each position data point carries a timestamp; In response to the current spatial coordinates and elevation data indicated by the target position data point satisfying a preset condition, the timestamp carried by the target position data point is used as the characteristic value moment of the cable car.

4. The method according to claim 2, It is characterized in that The material transportation process includes tank stabilization, loading, lifting, hoisting, alignment, unloading and return. The link time of the cable machine for each material transportation link is calculated based on the characteristic value of the cable machine, including: Calculate the time difference between the start time of the cable crane releasing the tank and the start time of the cable crane loading, and obtain the link time of the cable crane in the tank stabilization link; and / or, calculating the time difference between the start time and the end time of the cable machine for loading, and obtaining the link time of the cable machine in the loading link; And / or, calculating the time difference between the time when the cable crane ends loading and the time when the lifting starts, to obtain the link time of the cable crane in the tank lifting link; And / or, calculating the time difference between the start time of hoisting of the cable crane and the start time of alignment, and obtaining the link time of the cable crane in the hoisting link; And / or, calculating the time difference between the start time of alignment of the cable crane and the start time of unloading, and obtaining the link time of the cable crane in the alignment link; And / or, calculating the time difference between the start time and the end time of the cable machine in unloading, and obtaining the link time of the cable machine in the unloading link; And / or, the time difference between the end of unloading and the start of can placement of the cable crane is calculated to obtain the link time of the cable crane in the return link.

5. The method according to claim 1, It is characterized in that The obtaining of the efficiency index according to the characteristic value moment and / or the link time by the efficiency analysis model includes: Through the efficiency analysis model, whether the time point of each material transport link of the cable crane during operation is in line with expectations is monitored based on the characteristic value moment; and / or, whether the link time of each material transport link of the cable crane during operation is within a reasonable range is monitored based on the link time; and / or, the operating efficiency of the cable crane in each material transport link is evaluated based on the characteristic value moment and the link time.

6. The method according to claim 1, It is characterized in that The obtaining of the safety index of the cable car during operation by the safety analysis model includes: The cable crane monitoring device is used to obtain the cable crane hook running track, construction equipment location information, construction warehouse surface information and high slope information; The safety analysis model is used to perform safety analysis based on the cable crane hook operation trajectory, the construction equipment location information, the construction warehouse surface information and the high slope information to obtain a safety spacing control index.

7. The method according to claim 6, It is characterized in that The cable crane hook running track is used to indicate the real-time position of the main and auxiliary towers of the cable crane; the construction equipment position information is used to indicate the real-time position of the cable crane hook; the construction warehouse surface information includes warehouse surface design information and pouring progress information; the high slope information includes slope coordinate information; The safety analysis model is used to perform safety analysis based on the cable crane hook running trajectory, the construction equipment location information, the construction warehouse surface information and the high slope information to obtain a safety spacing control index, including: The main cable straight line of the cable crane is constructed based on the real-time positions of the main and auxiliary towers of the cable crane by the safety analysis model, and the swing amplitude value of the cable crane hook is obtained by analyzing the main cable straight line of the cable crane and the real-time position of the cable crane hook; And / or, constructing an envelope diagram of the cable crane operation area based on the cable crane hook swing amplitude value and the cable crane hook real-time position through the safety analysis model; And / or, the pouring start and end elevation information of the current bin is obtained by judging the pouring progress of each dam section in the pouring progress information through the safety analysis model; the current pouring elevation information is obtained by using the bin surface design information and estimating the pouring volume of each strip during the bin surface pouring process in the pouring progress information; wherein the pouring start and end elevation information is used to indicate the boundary of the construction bin surface, and the current pouring elevation information is used to indicate the elevation of the construction bin surface; And / or, the high slope is gridded to obtain grid information for the slope based on the slope coordinate information and a preset cable crane safety spacing control strategy through the safety analysis model; The safety analysis model is used to perform real-time analysis of the safety distance of the cable crane based on the swing amplitude of the cable crane hook, the envelope diagram of the cable crane operation area, the elevation and boundary of the construction warehouse surface, and the grid information of the slope to obtain the safety distance control index.

8. The method according to claim 7, It is characterized in that The safety analysis model is used to perform real-time analysis of the safety distance of the cable crane based on the cable crane hook swing amplitude, the cable crane operation area envelope, the construction warehouse surface elevation and boundary, and the grid information of the slope to obtain the safety distance control index, including: The safety analysis model is used to predict the operation area of ​​the cable crane based on the change of the main cable straight line position of the cable crane main cable straight line and the maximum cable crane swing amplitude value in the cable crane hook swing amplitude value; the predicted operation area of ​​the cable crane and the envelope diagram of the cable crane operation area are used to obtain the distance between adjacent cable cranes; wherein, the distance between adjacent cable cranes is used to indicate the minimum distance between the boundaries of the adjacent cable crane operation areas; the minimum distance between the boundaries of the adjacent cable crane operation areas is used to determine whether there is a collision risk between adjacent cable cranes; And / or, determining the position information of the cable crane hoisting and return trip based on the cable crane hook swing amplitude through the safety analysis model, and analyzing and obtaining the distance between the cable crane and the slope based on the position information of the cable crane hoisting and return trip and the slope coordinate information in the grid information for the slope; using the distance between the cable crane and the slope to predict whether there is a collision risk when the cable crane is running at this elevation; And / or, obtaining the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section based on the elevation and boundary of the construction warehouse surface through the safety analysis model, and predicting the height difference between the hook of the cable crane and the high dam block below the cable crane based on the real-time elevation information of the cable crane in the lifting link and the casting elevation information of each dam section; using the height difference between the hook of the cable crane and the high dam block below the cable crane to judge whether the height difference between the cable crane and the high dam section meets the safety spacing requirement; And / or, obtaining the real-time position information of the cable crane entering the alignment link and the warehouse surface boundary coordinate information based on the elevation and boundary of the construction warehouse surface through the safety analysis model, and analyzing and obtaining the horizontal distance between the cable crane and the preset template based on the real-time position information of the cable crane entering the alignment link and the warehouse surface boundary coordinate information; using the horizontal distance between the cable crane and the template to predict whether there is a collision risk between the cable crane and the preset template; And / or, the safety analysis model is used to predict the distance between the cable crane and the casting surface and the construction equipment based on the cable crane alignment and material unloading link position information, and the warehouse surface casting elevation and construction equipment position information; the distance between the cable crane and the casting surface and the construction equipment is used to determine whether there is a collision risk between the cable crane and the casting surface and the construction equipment.

9. The method according to claim 1, It is characterized in that The control index threshold is obtained according to preset levels, and the preset levels include a preset first level, a preset second level, and a preset third level; the early warning prompt information for early warning of the operation status of the cable car is pushed based on the control index threshold, the efficiency index, and the safety distance control index through the early warning management and control model, including: When the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset first level, the early warning prompt information is pushed immediately; and / or, when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset second level, the early warning prompt information is pushed regularly; and / or, when the efficiency index and the safety distance control index reach the control index threshold corresponding to the preset third level, the early warning prompt information is pushed in batches; The preset first level is higher than the preset second level, and the preset second level is higher than the preset third level.

10. A monitoring device for a cable crane, It is characterized in that Applied to cable crane monitoring equipment, involving link identification model, efficiency analysis model and safety analysis model, the device includes: A link identification module, used to obtain the full-time position information of the cable crane, and obtain the material transportation link information of the cable crane based on the full-time position information through the link identification model; the material transportation link information includes the characteristic value moment and link time; An efficiency analysis module, used to obtain an efficiency index according to the characteristic value moment and / or the link time by using the efficiency analysis model; A safety analysis module, used to obtain the safety index of the cable car during operation by using the safety analysis model; the safety index is a safety distance control index, and the safety distance control index is used to indicate whether there is a collision risk and whether the safety distance requirement is met; An early warning module is used to warn the operation status of the cable crane according to the efficiency index and the safety distance control index; wherein, it also involves an efficiency index dynamic rating model and an early warning management and control model, and the safety index is a safety distance control index; the early warning of the operation status of the cable crane according to the efficiency index and the safety distance control index includes: setting a control index threshold of the current bin casting efficiency process through the efficiency index dynamic rating model; pushing early warning prompt information for warning the operation status of the cable crane based on the control index threshold, the efficiency index and the safety distance control index through the early warning management and control model; The setting of the control index threshold of the current bin pouring efficiency process by the efficiency index dynamic calibration model includes: determining the cable crane efficiency reference value by the efficiency index dynamic calibration model; the reference value is used to reflect the efficiency level of each current pouring dam section; based on the cable crane efficiency reference value, constructing the control index threshold divided according to the preset level; The method of determining the cable crane efficiency benchmark value through the efficiency index dynamic calibration model includes: obtaining historical monitoring data through the efficiency index dynamic calibration model, and calibrating the cable crane efficiency benchmark value based on the historical monitoring data by using a piecewise weight method; and / or calibrating the cable crane efficiency benchmark value by using a similar dam section analogy method according to the cable crane transportation distance and casting bin characteristics of each dam section through the efficiency index dynamic calibration model.

11. An electronic device, It is characterized in that include: A processor, a memory, and a computer program stored in the memory and capable of running on the processor, wherein when the computer program is executed by the processor, the cable machine monitoring method according to any one of claims 1 to 9 is implemented.