Hydraulic tunnel lining follow-up construction method
Through multi-layer simultaneous excavation and alternating left and right construction methods, the problems of poor surrounding rock stability and difficult construction period control during hydraulic tunnel construction were solved, safe and efficient construction under complex geological conditions was achieved, and the construction period was significantly shortened.
Patent Information
- Application Number
- CN202410909212.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-10-01
AI Technical Summary
In the construction of hydraulic tunnels, conventional methods have poor stability of the surrounding rock under extremely adverse geological conditions, which poses safety risks and makes it difficult to control the construction period, resulting in prolonged lining concrete construction and affecting construction efficiency.
Multi-layer synchronous excavation technology and left and right alternating construction methods are adopted to simultaneously carry out floor concrete pouring and tunnel face excavation support to ensure the continuity and safety of the construction channel and shorten the construction period.
On the premise of ensuring construction safety, the construction period of the hydraulic tunnel lining is greatly shortened, the construction efficiency is improved, and the construction needs are adapted to complex geological conditions.
Smart Images

Figure CN118728398A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground tunnel excavation support construction, and in particular to a hydraulic tunnel lining follow-up construction method. Background Art
[0002] In the field of water conservancy and hydropower engineering, underground cavern construction basically starts with cavern excavation and support, and then tunnel lining concrete construction is carried out after the tunnel is through. Especially for large hydraulic fracture caverns, the method is to first excavate the first layer, then the second and third layers, and finally carry out lining construction. This construction sequence reserves sufficient time for the deformation of the tunnel surrounding rock, which can ensure that the surrounding rock is in a basically stable state before the construction of the cavern lining concrete, effectively reducing the occurrence of lining cracking. However, in some cases, conventional hydraulic tunnel construction methods have certain disadvantages. Hydraulic tunnels are mainly gate tunnels. After excavation, the stress structure and stability of hydraulic tunnels are far inferior to those of highway tunnels. Under extremely unfavorable geological conditions such as poor surrounding rock conditions and water gushing, the long-term exposure of surrounding rock poses a great safety risk. In addition, conventional hydraulic tunnel construction methods have a great impact on the construction period. In conventional hydraulic tunnel construction, lining concrete construction is a key task for key lines, which is not conducive to the control of the total construction period. Summary of the invention
[0003] The present invention aims to solve one of the technical problems in the related art at least to a certain extent.
[0004] To this end, an embodiment of the present invention proposes a hydraulic tunnel lining follow-up construction method which has the advantages of ensuring construction safety while compressing the construction period.
[0005] According to the hydraulic tunnel lining follow-up construction method of the embodiment of the present invention, the hydraulic tunnel lining follow-up construction method comprises the following steps:
[0006] The cavern is constructed synchronously on multiple layers, and the cavern is divided into the first layer, the second layer and the protective layer. After the first layer is excavated for a preset distance, the second layer is excavated for a preset distance, and then the protective layer is excavated. The excavation height of the second layer is calculated according to the width, and the cycle excavation length is calculated according to the preset longitudinal slope ratio. The second layer of the lower branch tunnel side half is excavated first, and the other half of the upper branch tunnel is used as the upper traffic channel. After the lower branch tunnel side half is excavated to meet the traffic conditions, the second layer of the upper branch tunnel side half is excavated, and the lower branch tunnel side half is used as the lower traffic channel. The protective layer excavation is completed by staggered excavation;
[0007] The lining construction is followed up, the left and right sections are alternately formed into a construction channel, and the bottom plate concrete pouring operation and the heading face excavation and support operation are carried out simultaneously.
[0008] The method for following up the construction of the lining of a hydraulic tunnel according to an embodiment of the present invention has the advantage of ensuring construction safety while compressing the construction period. The present application has the following advantages: using multi-layer synchronous excavation technology, the upper cavern and the lower cavern are excavated and supported simultaneously, and the excavation and support of the lower cavern does not occupy the linear construction period, creating conditions for the early construction of the subsequent lining concrete; the left and right division method enables the bottom plate concrete and the side top arch concrete to follow up in time, and the lining is closed into a ring in time, which can compress the construction period under the premise of ensuring construction safety. It solves the problem of hydraulic tunnels following up the excavation and support operations under the conditions of complex geological conditions and tight construction period, and greatly compresses the construction period under the premise of ensuring construction safety.
[0009] In some embodiments, the width of the construction access road is first determined, and then the trench excavation depth is calculated;
[0010] The calculation formula for trench excavation depth is: H = (B-2×B Road) / 0.5
[0011] Where: H—trench excavation depth, unit: m;
[0012] B—cavern width, in m, design value;
[0013] B Road - Width of upper and lower construction access roads, in meters.
[0014] In some embodiments, for permanent works, a mobile trestle is used for full-width casting, and the cast surface is paved with sandless concrete for protection.
[0015] In some embodiments, a layer of HDPE geomembrane is laid first, and then C15 sandless concrete is laid.
[0016] In some embodiments, the thickness of the C15 sandless concrete is 10 to 15 cm.
[0017] In some embodiments, for non-permanent projects, the bottom slab concrete is poured in left and right sections, and vehicles first pass through the uncast half. After the concrete of the cast half of the bottom slab reaches the designed strength, traffic is opened, and then the other half of the bottom slab is constructed.
[0018] In some embodiments, the uncast half of the L-shaped wall forms the foundation for the lined trolley and reinforced trolley track.
[0019] In some embodiments, two warehouse bottom plates are reserved without casting every 50 meters for vehicles to turn around.
[0020] In some embodiments, a traveling lining trolley is used to control the distance between the side arch lining and the excavation face to be about 300m. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1It is a schematic diagram of the upper and lower construction access roads of the hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0022] Figure 2 It is a half-construction schematic diagram of a construction access road of a hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0023] Figure 3 It is a schematic diagram of the left and right circular advancement of the construction access road of the hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0024] Figure 4 It is a schematic diagram of the side view layout of a movable trestle of a hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0025] Figure 5 1 is a schematic diagram of a top view layout of a movable trestle for a hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0026] Figure 6 It is a schematic diagram of traffic organization for full-width casting of a movable trestle according to a hydraulic tunnel lining follow-up construction method in an embodiment of the present invention.
[0027] Figure 7 It is a schematic diagram of the bottom plate division of the hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0028] Figure 8 It is a traffic organization diagram for pouring the right floor plate and opening the left floor to traffic in the hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention.
[0029] Fig. 9 It is a schematic diagram of traffic organization after the right bottom plate of the hydraulic tunnel lining follow-up construction method in an embodiment of the present invention is poured for 100m.
[0030] Fig.10 It is a traffic organization diagram of the left-side advance pouring of the hydraulic tunnel lining follow-up construction method according to an embodiment of the present invention. DETAILED DESCRIPTION
[0031] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0032] According to the hydraulic tunnel lining follow-up construction method of the embodiment of the present invention, the hydraulic tunnel lining follow-up construction method comprises the following steps:
[0033] The cavern is constructed in multiple layers synchronously. The cavern is divided into the first layer, the second layer and the protective layer. After the first layer is excavated for a preset distance, the second layer is excavated for a preset distance, and the protective layer is excavated. The excavation height of the second layer is calculated according to the width, and the cycle excavation length is calculated according to the preset longitudinal slope ratio. The flow chart of the multi-layer synchronous excavation of the cavern plane and the step section diagram are drawn. First, the second layer of the half-radius on the side of the lower branch tunnel is excavated, and the other half of the upper branch tunnel is used as the upper traffic channel. The blasting excavation is carried out according to the trench open excavation, and the slag is discharged twice; the preset distance can be 100m.
[0034] After the lower branch tunnel side half is excavated to the condition of traffic, the second layer of the upper branch tunnel side half is excavated and the lower branch tunnel side half is used as the lower traffic channel, and the protective layer is excavated by staggered excavation;
[0035] The reserved settlement is set before the multi-layer synchronous construction of the cavern, that is, the settlement or deformation caused by the surrounding rock load is taken into account during the period from the assembly of the tunnel support to the completion of the lining, which also refers to the amount of advance improvement compared to the design position. The size of the reserved settlement is controlled by factors such as geology, excavation method, support structure and material, and the time from excavation to lining. The increase in the design index of the reserved settlement provides the necessary conditions for the secondary lining of the hydraulic tunnel to follow up the excavation and support of the face.
[0036] The lining construction is followed up, the left and right sections are alternately formed into a construction channel, and the bottom plate concrete pouring operation and the heading face excavation and support operation are carried out simultaneously.
[0037] like Figures 1 to 3 As shown, the road is first formed by trenching and blasting to form upper and lower construction access roads, and the right half is drilled and blasted and slag removed. The left and right sides are circulated to push the construction access road forward in turn, and finally the excavation of the lower cavern is completed. During the process, there is always a road connecting the upper cavern and the lower cavern of the diversion tunnel to ensure the synchronous construction of the upper and lower layers of the diversion tunnel.
[0038] The hydraulic tunnel lining follow-up construction method according to the embodiment of the present invention has the advantages of ensuring construction safety while shortening the construction period.
[0039] In some embodiments, the width of the construction access road is first determined, and then the trench excavation depth is calculated;
[0040] The calculation formula for trench excavation depth is: H = (B-2×B Road) / 0.5
[0041] Where: H—trench excavation depth, unit: m;
[0042] B—cavern width, in m, design value;
[0043] B Road - Width of upper and lower construction access roads, in meters.
[0044] Specifically, the step slope ratio is 1:0.5, determined according to the exposed length of the side wall anchor rods, the width of the mechanical equipment and the safety distance. The excavation width of the cave is 14.6m, the thickness of the temporary support is 0.2m, the upper and lower construction access roads in the cave are designed to be 5.5m, 64.0m long, with a slope of 10%, and the road step slope ratio is 1:0.5.
[0045] In some embodiments, for permanent works, a mobile trestle is used for full-width casting, and the cast surface is paved with sandless concrete for protection.
[0046] Specifically, Figures 4 to 6 As shown, for permanent projects such as spillway tunnels, a mobile trestle is used for full-width casting, a mobile trestle is set up for bottom slab concrete construction, and the mobile trestle is used for passage of the face excavation and support equipment, ensuring that the bottom slab concrete pouring operation and the face excavation and support operation are carried out simultaneously.
[0047] In some embodiments, a layer of HDPE geomembrane is laid first, and then C15 sandless concrete is laid.
[0048] Specifically, the concrete of the bottom slab of a hydraulic tunnel is a permanent structural surface and needs to be protected. First, HDPE geomembrane is laid, and then C15 sandless concrete is laid to facilitate later removal. Sandless concrete, as a protective layer of the bottom slab concrete, can prevent the bottom slab concrete from being damaged by vehicles or other construction equipment during construction. Geomembrane can reduce the bonding between sandless concrete and bottom slab concrete.
[0049] In some embodiments, the thickness of the C15 sandless concrete is 10 to 15 cm.
[0050] Specifically, the thickness of the sandless concrete needs to be able to withstand the load of vehicles and equipment during construction, while also considering the extreme load conditions that may occur during construction. When the thickness is 10 to 15 cm, it can withstand the load and protect the bottom slab concrete below, while also being convenient and economical to construct.
[0051] In some embodiments, for non-permanent projects, the bottom slab concrete is poured in left and right sections, and vehicles first pass through the uncast half. After the concrete of the cast half of the bottom slab reaches the designed strength, traffic is opened, and then the other half of the bottom slab is constructed.
[0052] Specifically, Figures 7 to 10 As shown, for non-permanent projects such as diversion tunnels, the bottom slab concrete is poured in left and right sections, and the traffic organization is as follows:
[0053] The whole section protective layer is exposed;
[0054] The right floor slab and the left L wall were cast, and the left side was opened to traffic;
[0055] After the right floor slab is poured for 100m, the warehouse that has reached the design strength is opened to traffic, and a transverse passage is laid at the end. The traffic route is changed to: the right floor slab that has reached the design strength - transverse passage - the left floor slab that has not been poured;
[0056] The left side slab concrete and the right side L wall are being constructed, and the right side is about 100m ahead of the left side. The traffic route is changed to: the left side has reached the design strength slab - transverse channel - the right side has not cast the slab;
[0057] After the bottom plate is advanced in full width for about 100m in a cycle, the lining trolley starts to carry out the side and top arch lining;
[0058] Maintain a circular working space of 100m long upper steps - 100m long lower steps - 100m long cast bottom plate - lined side top arch.
[0059] In some embodiments, the uncast half of the L-shaped wall forms the foundation for the lined trolley and reinforced trolley track.
[0060] Specifically, the solution of casting L-shaped walls to form the foundation of the lining trolley and the steel trolley track can ensure that the side and top arch lining construction has the conditions for timely follow-up and guarantee the construction progress.
[0061] In some embodiments, two warehouse bottom plates are reserved without casting every 50 meters for vehicles to turn around.
[0062] In some embodiments, a traveling lining trolley is used to control the distance between the side arch lining and the excavation face to be about 300m.
[0063] Specifically, the traveling lining trolley is brought into the site about 2 months after the excavation and support. The distance between the side arch lining and the excavation face is controlled at 300m, which can ensure construction safety and improve construction quality. Delaying the excavation and support for a certain period of time can reduce the impact of the stress release of the surrounding rock of the newly excavated tunnel section on the lining construction, and waiting for the stress to be redistributed before carrying out construction to reduce risks. Controlling the distance between the lining and the excavation face helps to ensure the quality of the lining, ensures the stability of the surrounding rock, and ensures the quality of the lining. It can ensure the orderly connection between the lining operation and the excavation operation, and avoid construction interruptions caused by delayed lining.
[0064] Example 1, Project Overview: A hydropower station is mainly used for power generation and is a Class II large (2) project. The normal water level is 2545m, and the total storage capacity is 141 million m 3 The power station has an installed capacity of 750MW, an average annual power generation of 3.375 billion kWh, and an annual installed capacity utilization of 4,500 hours.
[0065] The diversion tunnel has a gate-type cross-section, which is a pressure tunnel with a typical cross-section size of 12m×14m (width×height) and a tunnel length of 796.03m. The diversion tunnel pile number is 0+000.00~0+025.00, which is the inlet gradient section. The excavation section is 20.20m×19.05m (width×height) and gradually changes to 16.20m×18.05m (width×height), which is Class V surrounding rock.
[0066] Implementation status: The diversion tunnel project started on January 20, 2019 and was completed on May 30, 2021. The large cavern of the diversion tunnel of a hydropower station was excavated in three layers, with the first layer excavation height of 7.9m, the second layer excavation height of 6.4m, and the third layer excavation height of 2.0m. The second layer excavation height is 6.4m, and radial groove excavation is adopted. The upper and lower construction access roads in the tunnel are designed to be 5.5m, 64.0m long, with a slope of 10%, and the road step slope ratio is 1:0.5. On December 26, 2020, the diversion tunnel was successfully diverted.
[0067] Example 2, Project Overview: The entrance of the L5 tunnel of a hydropower station passes under the mixed accumulation of GS Village, a poor geological body. The tunnel enters from the loose accumulation of the Quaternary system at the foot of the slope, and the physical and mechanical properties of loose rocks are poor. Due to the terrain conditions of the entrance of the L5 tunnel on the left bank, the shallow buried section of the tunnel entrance passes under the GS Village entrance road. The intersection of the L5 highway tunnel and the village entrance road is K0+068 (the tunnel design elevation is 2115.28m), the design elevation of the village entrance road is 2128m, the burial depth is 12.72 meters, and the burial depth above the arch is 5.5 meters. At the same time, the tunnel section K0+075~K0+100 passes under residential houses, the tunnel design elevation is 2116 meters, the residential house design elevation is 2136 meters, the burial depth is 20 meters, and the burial depth above the arch is 12.5 meters.
[0068] Implementation status: The construction of L5 tunnel started on December 26, 2023. The tunnel entrance shallow buried section with poor geological conditions adopted the lining follow-up construction plan. The lining concrete construction started at the end of February 2024. The heading passed through the poor geological GS mixed accumulation at the end of March 2024. The lining construction of the poor geological shallow buried section was completed in April 2024. The heading excavation support was followed up synchronously with the bottom plate and side arch lining to ensure construction safety.
[0069] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0070] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0071] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0072] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0073] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0074] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are illustrative and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.
Claims
1. A hydraulic tunnel lining follow-up construction method, characterized in that: The following steps are involved: The cavern is constructed synchronously on multiple layers, and the cavern is divided into the first layer, the second layer and the protective layer. After the first layer is excavated for a preset distance, the second layer is excavated for a preset distance, and then the protective layer is excavated. The excavation height of the second layer is calculated according to the width, and the cycle excavation length is calculated according to the preset longitudinal slope ratio. The second layer of the lower branch tunnel side half is excavated first, and the other half of the upper branch tunnel is used as the upper traffic channel. After the lower branch tunnel side half is excavated to meet the traffic conditions, the second layer of the upper branch tunnel side half is excavated, and the lower branch tunnel side half is used as the lower traffic channel. The protective layer excavation is completed by staggered excavation; The lining is constructed in a follow-up manner, and the left and right sections are alternately used to form a construction channel. The bottom plate concrete pouring operation and the face excavation and support operation are carried out simultaneously.
2. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: First determine the width of the construction access road, then calculate the trench excavation depth; The calculation formula for trench excavation depth is: H = (B-2×B Road) / 0.5 Where: H—trench excavation depth, unit: m; B—cavern width, in m, design value; B Road - Width of upper and lower construction access roads, in meters.
3. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: For permanent works, mobile trestles are used for full-width casting and the cast surface is protected by paving with sandless concrete.
4. The hydraulic tunnel lining follow-up construction method according to claim 3 is characterized in that: First lay a layer of HDPE geomembrane, and then lay C15 sandless concrete.
5. The hydraulic tunnel lining follow-up construction method according to claim 4 is characterized in that: The thickness of C15 sandless concrete is 10 to 15 cm.
6. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: For non-permanent projects, the bottom slab concrete is poured in two sections, left and right. Vehicles first pass through the uncast half. After the concrete of the cast half of the bottom slab reaches the design strength, traffic is opened, and then the other half of the bottom slab is constructed.
7. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: The uncast half of the L-shaped wall forms the foundation for the lining trolley and reinforced trolley track.
8. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: Two warehouse bottom slabs are reserved every 50m without pouring for vehicles to turn around.
9. The hydraulic tunnel lining follow-up construction method according to claim 1 is characterized in that: A traveling lining trolley is used to control the distance between the side arch lining and the excavation face to be around 300m.