- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2024-10-08
AI Technical Summary
The conventional drilling method in the prior art has a short fracturing distance in one cycle during rock tunnel excavation, and is easy to damage the surrounding rock of the tunnel, and cannot meet the long-distance weakening requirements.
The directional long drilling method is adopted, which includes constructing multiple directional long drilling holes in the axial direction of the rock tunnel. The boundary holes are hydraulically cut close to the edge of the tunnel, and the middle holes are hydraulically fractured to form hydraulic cutting seams and complex cracks and seams to ensure cracks. It will not expand into the surrounding rocks of the tunnel to avoid damage.
It achieves one-cycle construction to meet long-distance weakening, improves excavation speed and efficiency, avoids damage to surrounding rocks, and forms an effective rock weakening effect.
Smart Images

Figure CN118745902A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal collection, and in particular to a rock stratum hydraulic weakening method used in rock tunnel excavation. Background Art
[0002] Rock tunnels are tunnels where the rock area accounts for all or most of the excavation face. In rock tunnel excavation, when the rock hardness is greater and the integrity is better, the excavation speed will be slow and the equipment will be more damaged.
[0003] In the prior art, hydraulic fracturing is usually used to pre-crack and weaken the rock tunnel in advance to increase the speed of rock tunnel excavation.
[0004] However, using conventional drilling methods, the distance of one cycle of fracturing is short and it is easy to damage the surrounding rock of the tunnel. Summary of the invention
[0005] The present invention provides a rock stratum hydraulic weakening method for rock tunnel excavation, which is used to solve the defect of short one-cycle fracturing distance in conventional drilling methods in the prior art, and realizes long-distance weakening by one-cycle construction using directional long holes.
[0006] The present invention provides a method for hydraulically weakening rock formations used in rock tunnel excavation, comprising: Obtain structural data of rock tunnels and determine the excavation section; On the excavation section, a plurality of directional long drill holes are constructed along the axial direction of the rock tunnel; wherein the directional long drill holes include boundary holes and middle holes, and the boundary holes are close to the edge of the rock tunnel; Based on the boundary hole, hydraulic cutting is performed; Based on the intermediate pores, hydraulic fracturing is performed.
[0007] According to a method for hydraulic weakening of rock formations in rock tunnel excavation provided by the present invention, the steps include constructing a plurality of directional long boreholes along the axial direction of the rock tunnel on the excavation section; wherein the directional long boreholes include boundary holes and middle holes, and the boundary holes near the edge of the rock tunnel include: Each side of the rock tunnel includes at least one boundary hole.
[0008] According to a method for hydraulic weakening of rock formations in rock tunnel excavation provided by the present invention, the steps include constructing a plurality of directional long boreholes along the axial direction of the rock tunnel on the excavation section; wherein the directional long boreholes include boundary holes and middle holes, and the boundary holes near the edge of the rock tunnel include: The middle holes have multiple rows, and the multiple middle holes in the same row are arranged at equal intervals.
[0009] According to a method for hydraulic weakening of rock formations in rock tunnel excavation provided by the present invention, the steps of constructing a plurality of directional long boreholes along the axial direction of the rock tunnel on the excavation section include: A large torque directional drilling machine is used to construct a plurality of the directional long boreholes on the excavation section.
[0010] According to a method for hydraulic weakening of rock formations used in rock tunnel excavation provided by the present invention, the steps of hydraulic cutting based on the boundary hole include: In the boundary hole, a hydraulic directional cutting device is introduced through a high-pressure water injection pipe, and high-pressure water is injected to perform backward hydraulic cutting along the edge of the rock tunnel to form a hydraulic cut.
[0011] According to a method for hydraulic weakening of rock formations used in rock tunnel excavation provided by the present invention, the steps include: hydraulic cutting based on the boundary hole to form a hydraulic cut, and also include: By controlling the cutting time, it is ensured that the hydraulic cutting reaches the boundary of the rock tunnel and does not exceed the tunnel section.
[0012] According to a method for hydraulic weakening of rock strata used in rock tunnel excavation provided by the present invention, the steps are based on the boundary hole, hydraulic cutting is performed to form hydraulic cuts, and the length of the hydraulic cuts is several meters.
[0013] According to a method for hydraulic weakening of rock formations used in rock tunnel excavation provided by the present invention, the steps are based on the intermediate hole and hydraulic fracturing is performed, including: A hydraulic fracturing device is introduced into the middle hole using a high-pressure water injection pipe and fracturing is performed to form a crack network in the middle of the tunnel section.
[0014] According to a method for hydraulic weakening of rock formations in rock tunnel excavation provided by the present invention, the steps include: using a high-pressure water injection pipe to send a hydraulic fracturing device into the middle hole, and fracturing to form a crack network in the middle of the tunnel section, including: The fracturing adopts backward stage-by-stage fracturing.
[0015] According to a method for hydraulic weakening of rock formations in rock tunnel excavation provided by the present invention, the steps include: using a high-pressure water injection pipe to send a hydraulic fracturing device into the middle hole, and fracturing to form a crack network in the middle of the tunnel section, including: Taking the middle hole as the center, fracturing is performed in multiple circumferential directions to form the fracture network.
[0016] The method for hydraulic weakening of rock strata in rock tunnel excavation provided by the present invention comprises the following steps: on the excavation section, a plurality of directional long drill holes are constructed along the axial direction of the rock tunnel, wherein the boundary holes are close to the edge of the rock tunnel, and one cycle of construction during directional long drilling can meet the requirements of long-distance weakening; hydraulic cutting is performed based on the boundary holes, and the cut seams formed at the boundary of the tunnel section ensure that the cracks will not extend into the tunnel surrounding rock when hydraulic fracturing is performed in the subsequent intermediate holes, thereby avoiding damage to the surrounding rock; hydraulic fracturing is performed based on the intermediate holes, and a complex crack network is formed in the rock stratum, thereby effectively weakening the rock. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 It is a schematic flow chart of a rock weakening method for rock tunnel excavation provided by the present invention.
[0019] Figure 2 It is a schematic diagram of the excavation section provided by the present invention.
[0020] Figure 3 It is a side view of the rock tunnel provided by the present invention.
[0021] Figure 4 It is a front view of the distribution of hydraulic slits provided by the present invention.
[0022] Figure 5 It is a side view of the distribution of the hydraulic slits provided by the present invention.
[0023] Figure 6 This is a front view of the distribution of the hydraulic fracturing cracks provided by the present invention.
[0024] Figure 7 It is a side view of the distribution of the hydraulic fracturing cracks provided by the present invention.
[0025] Reference numerals: 1. Rock tunnel; 2. Boundary hole; 3. Middle hole; 4. Hydraulic cutting; 5. Fracture network. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] Combine the following Figure 1-Figure 7 The present invention is described as a method for hydraulic weakening of rock formations used in rock tunneling.
[0028] Figure 1 This is one of the flow diagrams of the rock stratum hydraulic weakening method for rock tunnel excavation provided by the present invention, such as Figure 1 , Figure 2 and Figure 3 As shown, the method includes the following: Step 101: Acquire structural data of the rock tunnel 1 and determine the excavation section.
[0029] In the above steps, the detailed structural data of the rock tunnel can be obtained through geological exploration equipment and technology. According to the structural data, the specific cross-section position of the excavation is determined and the excavation path is planned.
[0030] Step 102: construct multiple directional long drill holes along the axial direction of the rock tunnel 1 on the excavation section; wherein the directional long drill holes include boundary holes 2 and middle holes 3, the boundary holes 2 are close to the edge of the rock tunnel 1, and the middle holes 3 are located in the area surrounded by the boundary holes 2.
[0031] Among them, the length, diameter and spacing of the boreholes should be precisely designed according to the properties of the rock and excavation requirements.
[0032] Step 103: Perform hydraulic cutting based on the boundary hole 2.
[0033] Inject high-pressure water into the boundary hole 2, and use the impact and shear force of the water flow to cut the rock. Hydraulic cutting can effectively reduce the hardness of the rock and create more favorable conditions for subsequent excavation work. By controlling the pressure and flow of the water flow, the cutting effect is ensured while avoiding unnecessary damage to the surrounding rocks.
[0034] Step 104: hydraulic fracturing is performed based on the middle hole 3.
[0035] Inject high-pressure water into the middle hole 3, and use the pressure of the water flow to create cracks in the rock. Hydraulic fracturing can further weaken the rock and improve the excavation efficiency. It is also necessary to accurately control the pressure and flow of the water flow to ensure the fracturing effect while avoiding excessive impact on the surrounding rocks.
[0036] Therefore, the rock stratum hydraulic weakening method provided by the present invention for rock tunnel excavation, compared with conventional short-hole fracturing, can be constructed in one cycle by directional drilling, and can meet the needs of long-distance weakening. After the boundary hole 2 is hydraulically cut, a cut is formed on the roadway section, ensuring that the cracks will not extend into the surrounding rock of the roadway when the intermediate hole 3 is hydraulically fractured, thereby avoiding damage to the surrounding rock. Based on the fracturing of the intermediate hole 3, a crack network is formed, which effectively weakens the rock.
[0037] In addition, it should be noted that during the excavation process, the rock weakening effect and excavation progress can be monitored in real time, and the parameters of the hydraulic operation can be adjusted based on the feedback data.
[0038] like Figure 4 and Figure 5 As shown, in a feasible embodiment of the present invention, in step 102, the rock tunnel 1 is a square tunnel, and each side of the rock tunnel 1 includes at least one boundary hole 2. The purpose of this arrangement is to ensure that an annular hydraulic cut 4 is formed around the tunnel to ensure that the cracks will not extend into the tunnel surrounding rock when the subsequent intermediate hole 3 is hydraulically fractured, thereby avoiding damage to the surrounding rock.
[0039] See again Figure 4 As shown, in a feasible embodiment of the present invention, in step 102, the intermediate holes 3 have multiple rows, and each row of intermediate holes 3 extends along the axial direction of the tunnel. Such an arrangement can ensure that different areas of the tunnel can be effectively weakened.
[0040] The middle holes 3 of two adjacent rows can be arranged correspondingly, that is, a hole in one row corresponds to a hole in an adjacent row in the transverse direction. This corresponding arrangement can further enhance the effect of weakening the rock formation, especially when there are potential cracks or weak planes in the rock formation.
[0041] The multiple middle holes 3 in each row are arranged at equal intervals. This ensures that the rock layer can be uniformly weakened in the cross section of the tunnel. The size of the spacing should be determined according to the hardness of the rock, the development of cracks and the excavation requirements. The number of middle holes 3 should also be determined according to the size of the tunnel and the expected weakening effect. Generally, the more holes there are, the better the weakening effect, but it will also increase the construction cost and time.
[0042] It should be noted that during the construction of drilling holes, the accuracy and quality of the drilling holes should be ensured to avoid unnecessary damage to the surrounding rocks. In particular, in the area between the boundary hole and the middle hole, special attention should be paid to avoid the generation of cracks or broken zones. In addition, the wastewater and waste residue generated during the drilling process should be properly handled to avoid pollution to the environment. At the same time, the construction site should strengthen safety management to ensure the personal safety of the staff.
[0043] In a feasible embodiment of the present invention, in step 102, a large torque directional drilling machine is used to construct multiple directional long boreholes on the excavation section. The large torque directional drilling machine has the characteristics of high torque and low speed, and can effectively perform drilling operations in harder formations. In addition, the large torque directional drilling machine is usually equipped with a hydraulic drive system to ensure stability and reliability, making the drilling process more accurate and controllable.
[0044] The diameter, length and spacing of directional long boreholes can be precisely designed according to the specific rock properties, tunnel dimensions and excavation requirements.
[0045] like Figure 5 As shown, in a feasible embodiment of the present invention, in step 103, a hydraulic directional cutting device is introduced into the boundary hole 2 using a high-pressure water injection pipe, wherein the hydraulic directional cutting device is a device specifically used for cutting cracks in rocks, usually including a nozzle and a corresponding control system, and can accurately direct the water flow to achieve efficient cutting. Then, high-pressure water is injected, and the high-pressure water is ejected at a very high speed through the nozzle in the device to form a strong water flow, which has extremely high kinetic energy and can quickly form cracks in the rock.
[0046] High-pressure water performs backward hydraulic cutting along the edge of the rock tunnel 1. Reverse cutting means starting from a certain edge of the tunnel and gradually retreating while cutting continuous cracks. This cutting method ensures that cracks are formed along the edge of the tunnel, thereby effectively weakening the rock. With the continuous action of high-pressure water, the rock is gradually cut near the boundary hole 2, and eventually one or more continuous hydraulic cuts are formed. These hydraulic cuts not only weaken the overall strength of the rock, but also provide more space and more contact surfaces for subsequent rock formation weakening work.
[0047] Furthermore, in step 103, by controlling the cutting time, it is ensured that the hydraulic cutting reaches the boundary of the rock tunnel 1 and does not exceed the tunnel section. The cutting time is a key factor affecting the cutting depth. When performing hydraulic cutting, it is necessary to pre-calculate or test the appropriate cutting time based on parameters such as the hardness of the rock, the diameter of the borehole, and the pressure of the high-pressure water. By accurately controlling the cutting time, it can be ensured that the cutting depth just reaches the boundary of the rock tunnel, thereby avoiding unnecessary damage to the rock outside the tunnel.
[0048] During the cutting process, the cutting depth and the boundary position of the rock tunnel should be monitored in real time. This can be achieved by using special monitoring equipment or systems, such as laser rangefinders, cameras, etc. By accurately controlling the cutting time and monitoring the cutting depth in real time, it can be ensured that the hydraulic cutting reaches the boundary of the rock tunnel and does not exceed the tunnel section. This can not only improve the excavation efficiency, but also reduce the risk of damage to the surrounding rocks, creating better conditions for subsequent rock weakening work.
[0049] Among them, the length of the hydraulic cutting seam 4 is several meters, and one cycle of hydraulic cutting construction can meet the long-distance weakening, thereby improving the excavation efficiency.
[0050] like Figure 6 and Figure 7 As shown, in a feasible embodiment of the present invention, in step 104, a hydraulic fracturing device is introduced into the middle hole 3 using a high-pressure water injection pipe. The hydraulic fracturing device is a device specially designed to create cracks inside the rock. It usually includes seals and valves that can withstand high pressure and a control system that can accurately control the fracturing process. Once the hydraulic fracturing device is introduced into the middle hole 3 and positioned, fracturing begins, forming cracks in the middle of the tunnel section. These cracks will expand inside the rock to form a complex crack network, namely, a crack network 5.
[0051] Furthermore, fracturing adopts backward stage-by-stage fracturing, which means starting from a certain point in the wellbore and fracturing in stages in the direction away from the wellhead. Each stage of fracturing is independent, and by precisely controlling the injection volume, pressure and time of the fracturing fluid, cracks are formed in the rock at the predetermined position.
[0052] Furthermore, in step 104, with the middle hole 3 as the center, fracturing is performed in multiple directions in the circumference to form a fracture network. First, the hydraulic fracturing device is accurately sent into the middle hole 3 and fixed in position to ensure that the fracturing operation starts from the middle hole 3, is triggered from the center of the middle hole 3, and is simultaneously fracturing in multiple directions in the circumference. This is usually achieved by precisely controlling multiple nozzles or fracture inducers in the fracturing device to ensure that the cracks can expand evenly in different directions. During the fracturing process, it is necessary to closely monitor the expansion of the cracks to ensure that they expand in the predetermined direction and do not exceed the predetermined range. As the fracturing proceeds, cracks in multiple directions will be intertwined inside the rock to form a complex fracture network, i.e., a fracture network. This fracture network will effectively increase the permeability of the rock and facilitate subsequent weakening agent injection or other engineering operations.
[0053] In summary, the present invention provides a rock weakening method for rock tunnel excavation. Compared with conventional short-hole fracturing, one-cycle construction can meet long-distance weakening when using directional long drilling, and after the boundary hole 2 is hydraulically cut, a cut is formed in the tunnel section, ensuring that the cracks will not extend into the tunnel surrounding rock during the subsequent hydraulic fracturing of the middle hole 3, thereby avoiding damage to the surrounding rock. The middle hole 3 is subjected to large-flow backward segmented fracturing to form a complex crack network in the rock formation, thereby effectively weakening the rock.
[0054] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for hydraulic weakening of rock formations in rock tunneling, It is characterized in that include: Acquire structural data of the rock tunnel (1) and determine the excavation section; On the excavation section, a plurality of directional long drill holes are constructed along the axial direction of the rock tunnel (1); wherein the directional long drill holes include boundary holes (2) and intermediate holes (3), and the boundary holes (2) are close to the edge of the rock tunnel (1); Based on the boundary hole (2), hydraulic cutting is performed; Based on the intermediate pores (3), hydraulic fracturing is performed.
2. The method for hydraulic weakening of rock formations in rock tunneling according to claim 1, It is characterized in that The step comprises constructing a plurality of directional long boreholes along the axial direction of the rock tunnel on the excavation section; wherein the directional long boreholes include boundary holes (2) and middle holes (3), and the boundary holes (2) near the edge of the rock tunnel (1) include: Each side of the rock tunnel (1) comprises at least one boundary hole (2).
3. The method for hydraulic weakening of rock formations in rock tunneling according to claim 1, It is characterized in that The step comprises constructing a plurality of directional long boreholes along the axial direction of the rock tunnel (1) on the excavation section; wherein the directional long boreholes include boundary holes (2) and intermediate holes (3), and the boundary holes (2) near the edge of the rock tunnel (1) include: The middle holes (3) have multiple rows, and the multiple middle holes (3) in the same row are arranged at equal intervals.
4. The method for hydraulic weakening of rock formations in rock tunneling according to claim 1, It is characterized in that The step of constructing a plurality of directional long boreholes along the axial direction of the rock tunnel (1) on the excavation section comprises: A large torque directional drilling machine is used to construct a plurality of the directional long boreholes on the excavation section.
5. The method for hydraulic weakening of rock formations in rock tunneling according to claim 1, It is characterized in that The steps of performing hydraulic cutting based on the boundary hole (2) include: In the boundary hole (2), a hydraulic directional cutting device is introduced through a high-pressure water injection pipe, and high-pressure water is injected to perform backward hydraulic cutting along the edge of the rock tunnel (1) to form a hydraulic cutting seam (4).
6. The method for hydraulic weakening of rock formations in rock tunneling according to claim 5, It is characterized in that The step of performing hydraulic cutting based on the boundary hole (2) to form a hydraulic cut (4) also includes: By controlling the cutting time, it is ensured that the hydraulic cutting reaches the boundary of the rock tunnel (1) and does not exceed the tunnel section.
7. The method for hydraulic weakening of rock formations in rock tunneling according to claim 5, It is characterized in that The step is based on the boundary hole (2), and hydraulic cutting is performed to form a hydraulic cut seam (4), wherein the length of the hydraulic cut seam (4) is several meters.
8. The method for hydraulic weakening of rock formations in rock tunneling according to claim 6, It is characterized in that The steps of hydraulic fracturing based on the intermediate hole (3) include: A hydraulic fracturing device is introduced into the middle hole (3) using a high-pressure water injection pipe and fracturing is performed to form a crack network (5) in the middle of the tunnel section.
9. The method for hydraulic weakening of rock formations in rock tunneling according to claim 8, It is characterized in that The step of injecting a high-pressure water injection pipe into the middle hole (3) and performing fracturing to form a crack network (5) in the middle of the tunnel section comprises: The fracturing adopts backward stage-by-stage fracturing.
10. The method for hydraulic weakening of rock formations in rock tunneling according to claim 8, It is characterized in that The step is to use a high-pressure water injection pipe to send a hydraulic fracturing device into the middle hole (3) and perform fracturing to form a crack network in the middle of the tunnel section, including: Taking the middle hole (3) as the center, fractures are performed in multiple circumferential directions to form the fracture network (5).
Citation Information
Cited By
Silent cracking agent and hydraulic fracturing coupling directional rock breaking method
CN119352971A
Method for preventing and controlling rock burst of main roadway group through axial kerf fracturing in horizontal hole of top plate
CN119531871A