Building method of GRG wood grain suspended ceiling and wood grain suspended ceiling

By building the conversion layer keel and embedded parts on the top of the building, combined with the use of angle steel and C-clips, the problem of precision control of high-altitude GRG ceiling installation is solved, and a high-precision and beautiful installation effect is achieved.

CN118756887AInactive Publication Date: 2024-10-11SHANGHAI BUILDING DECORATION ENG GRP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410999007.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-10-11
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When installing GRG ceilings in a high-altitude environment, it is difficult to ensure installation accuracy and splicing consistency, resulting in large deviations in the shape after splicing.

Method used

By building the transfer layer keel on the top of the building, pre-embedding the embedded parts and angle steel, using bolts and welding to fix the GRG board, and adjusting the distance between the board seams through C-type clamps to ensure consistent spacing between the boards, and perform unified caulking to ensure the appearance. Aesthetics.

Benefits of technology

It achieves high-precision installation of GRG ceilings, reducing the difficulty of installation. Through the preliminary connection of embedded parts and angle steel, the position of the panels is adjusted to ensure uniform caulking of the joint positions, which improves the aesthetic appearance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756887A_ABST
    Figure CN118756887A_ABST
Patent Text Reader

Abstract

The invention relates to a building method of a GRG wood grain suspended ceiling and the wood grain suspended ceiling. During building, the building method comprises the steps that 1, a transfer layer keel is built; 2, the GRG plate is embedded with the embedded part, and the flange edge is arranged on the edge of the GRG plate; 3, the embedded parts and the angle steel are fixedly connected through bolts, and after the GRG plates are positioned, the angle steel and the transfer layer keels are fixedly welded; 4, repeating the steps 2-3 to mount the next adjacent GRG plate; 5, the flange edges of the adjacent GRG plates are clamped through C-shaped clamps, the distance of plate joints between the GRG plates is adjusted, and the connecting positions of the embedded parts and the angle steel bolts are welded and fixed; 6, the rest adjacent GRG boards are installed adjacent to the installed GRG boards according to the steps 2-5; 7, after all the GRG plates are installed, joints of the GRG plates are subjected to joint filling treatment; and 8, performing wood grain decoration on the surface of the GRG board. After the GRG plate is installed below the transfer layer steel frame through the embedded part and the angle steel, the GRG plate is adjusted in place; and the C-shaped clamp is used for fine adjustment of the spacing, so that the mounting precision of the GRG plate is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building decoration, and in particular to a construction method of a GRG wood grain ceiling and a wood grain ceiling. Background Art

[0002] GRG, also known as glass fiber reinforced gypsum composite board, is a new type of decorative material with good waterproof and decorative properties, as well as good impact resistance and sound and light properties. It is widely used in public buildings such as theaters and concert halls.

[0003] Generally, the height between the ground inside theaters and concert halls and the top buildings is very high, which can reach tens of meters. If GRC materials are used over a large area, they must be divided into several areas for installation separately. Therefore, GRC materials need to be installed at high altitudes, and the accuracy of splicing and installation of GRC materials after installation must be guaranteed. Otherwise, the GRC shape will have large deviations after splicing.

[0004] Existing technologies such as the content disclosed in "Concert Hall GRG Ceiling and Wall Construction Technology" Xue Jianfang, Dou Tongkuan, Feng Chao, Wei Jinlei, Building Construction Vol. 38 No. 4" use channel steel as a hanger welded to the top steel structure, with a φ10mm hanger, and the subsequent GRC board uses the previously installed GRG board as a horizontal support point. The setting of the channel steel avoids the deviation of the hanger during the subsequent GRG board installation and positioning process. Summary of the invention

[0005] In order to perform precision control of GRC ceiling installation at high altitude and reduce the difficulty of installation, the present invention provides a construction method of a GRC wood grain ceiling and a wood grain ceiling. The technical purpose of the present invention is achieved through the following technical solutions:

[0006] On one hand, the present invention provides a method for constructing a GRG wood grain ceiling, and also provides a GRG wood grain ceiling constructed according to the method, the method comprising:

[0007] Step 1: Build the transfer layer keel on the top of the building;

[0008] Step 2: transport the finished GRG board to the installation area, embed the embedded parts on the back of the GRG board, and set the flange edge on the edge of the GRG board;

[0009] Step 3: Fix the embedded parts and angle steel by bolts, then move the GRG board to the installation position, and after positioning the GRG board, weld the angle steel and the transfer layer keel;

[0010] Step 4: Repeat steps 2-3 to install the next GRG board adjacent to the first GRG board;

[0011] Step 5: Clamp the flange edges of adjacent GRG plates with C-type clamps, adjust the distance between the plate seams of the GRG plates, weld and fix the embedded parts and angle steels with bolts, and remove the C-type clamps;

[0012] Step 6: Install the remaining adjacent GRG boards adjacent to the installed GRG boards according to the methods of steps 2-5;

[0013] Step 7: After all GRG boards are installed, caulking the joints of the GRG boards;

[0014] Step 8: Carry out wood grain decoration on the surface of GRG board.

[0015] Furthermore, when processing the GRG board, it is shaped through a customized mold, and the GRG slurry is poured into the mold layer by layer. After each layer of slurry is added, a layer of fiberglass felt cloth is laid to ensure that each layer of fiberglass felt cloth is penetrated by the GRG slurry, and the number of layers of fiberglass felt cloth is not less than 6 layers.

[0016] Furthermore, after the second layer of glass fiber felt is laid, embedded parts are pre-embedded and installed. The embedded parts are T-shaped embedded parts, and glass fiber felt is added at the installation position of the embedded parts for reinforcement.

[0017] Furthermore, after the GRG board is processed, it will undergo pre-assembly inspection, and after passing the inspection, it will be shaped and cleaned.

[0018] Furthermore, the length of the angle steel is 100-1000 mm, a waist-shaped hole is set at the position where the embedded part is connected to the angle steel, and the bolt passes through the waist-shaped hole to be connected to the angle steel.

[0019] Furthermore, before the caulking process is performed in step 7, elastic gaskets are filled between the flange edges of adjacent GRG plates, and the flange edges are fixed and locked by means of counter-screws, which pass through the elastic gaskets.

[0020] Furthermore, when performing the caulking treatment, fill the caulking material and glass fiber to smooth the seam, fill the seam, and then use glass fiber tape to smooth the joint. After the caulking material is dry, GRG adhesive is applied all over and scraped flat; then the joint is smoothed with glass fiber tape again, and GRG adhesive is applied all over and scraped flat again.

[0021] Furthermore, after the elastic gasket and the counter-screws are installed, the flange edge is also covered with a docking material for reinforcement.

[0022] Furthermore, in step 8, the lower surface of the installed GRG board is putty-scraped and leveled, and after the putty is dried, a primer is sprayed to seal it, and then veneer glue is applied or wood grain paint is applied.

[0023] Compared with the prior art, the beneficial effect of the present invention lies in that, after the GRG plate is installed under the steel frame of the transfer layer through the angle steel through the preliminary connection between the embedded parts and the angle steel, the connection between the angle steel and the embedded parts is adjusted to adjust the GRG plate into place; the spacing between adjacent GRG plates is fine-tuned by using C-clamps to ensure the installation accuracy of the GRG plates, and the joints are uniformly caulked to ensure the aesthetic appearance. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the installation of the GRG wood grain ceiling in the present invention.

[0025] Figure 2 It is a schematic diagram of the joint position of the GRG board in the present invention.

[0026] In the figure, 1. Transfer layer keel; 2. GRG plate; 3. Embedded parts; 4. Angle steel; 5. Flange edge; 6. Elastic gasket; 7. Counter-knocking screws; 8. Dock bang. DETAILED DESCRIPTION

[0027] The technical solution of the present invention is further described below in conjunction with specific embodiments:

[0028] A method for constructing a GRG wood grain ceiling, such as Figure 1 As shown, the method includes:

[0029] Step 1: Build a transfer layer keel 1 on the top of the building;

[0030] Step 2: transport the finished GRG board to the installation area, embed the embedded parts on the back of the GRG board, and set the flange edge 5 on the edge of the GRG board 2;

[0031] Step 3, fix the embedded part 3 and the angle steel 4 by bolts, then move the GRG plate 2 to the installation position, and after positioning the GRG plate 2, weld the angle steel 4 and the transfer layer keel 1;

[0032] Step 4: Repeat steps 2-3 to install the next GRG board adjacent to the first GRG board;

[0033] Step 5: Clamp the flange edges of adjacent GRG plates with C-type clamps, adjust the distance between the plate seams of the GRG plates, weld and fix the embedded parts 3 and the angle steel 4 at the bolted joints, and remove the C-type clamps;

[0034] Step 6: Install the remaining adjacent GRG boards adjacent to the installed GRG boards according to the methods of steps 2-5;

[0035] Step 7: After all GRG boards are installed, caulking the joints of the GRG boards;

[0036] Step 8. Carry out wood grain decoration on the surface of GRG board. Wood grain decoration can be pasted veneer or painted with wood grain paint. Before wood grain decoration, putty should be scraped on the lower surface of the installed GRG board. After the putty is dry, spray primer to seal it, and then attach it with wood veneer glue or paint it with wood grain paint.

[0037] When processing GRG boards, they are shaped through customized molds, and the GRG slurry is poured into the mold layer by layer. After each layer of slurry is added, a layer of fiberglass felt is laid to ensure that each layer of fiberglass felt is penetrated by the GRG slurry. The number of layers of fiberglass felt is not less than 6.

[0038] Specifically, one third of the GRG slurry is poured into the mold to form a surface slurry layer, and the surface slurry layer is smoothed;

[0039] Then lay the first layer of glass fiber felt, put the cut glass fiber felt on the surface slurry layer, and press the first layer of glass fiber felt to make the GRG slurry penetrate the first layer of glass fiber felt;

[0040] Then lay the second layer of GRG slurry, spread and smooth the second layer of GRG slurry, and then lay the second layer of glass fiber felt cloth;

[0041] After the second layer of glass fiber felt is laid, the embedded parts are placed. The embedded parts are T-shaped hot-dip galvanized embedded parts. One side of the T-shaped panel is placed on the second layer of glass fiber felt. In order to increase the strength of the embedded parts installation position, part of the glass fiber felt is covered at the T-shaped panel for local reinforcement.

[0042] Then repeatedly lay GRG slurry and glass fiber felt cloth, requiring GRG slurry and glass fiber felt cloth to be laid alternately, and the number of layers of fiber felt cloth shall not be less than 6. The layer of glass fiber felt cloth here is not a layer in the strict physical sense. Each layer of glass fiber can be a layer in the physical sense, or several layers can be superimposed as one layer. The area of ​​the last layer of glass fiber felt cloth matches the mold, and the last layer of glass fiber covers the whole. The previous layers of glass fiber can be fragmented glass fiber. Press the last layer of glass fiber felt cloth to make the GRG slurry penetrate and spread the penetrated GRG slurry evenly.

[0043] After demoulding, the GRG board is trimmed and repaired, and after drying, it is pre-assembled and inspected. After passing the inspection, it is shaped and cleaned.

[0044] The length of the angle steel is 100-1000mm. The position where the embedded parts connect to the angle steel is provided with waist-shaped holes, and the bolts are connected to the angle steel through the waist-shaped holes. After the angle steel is welded to the transfer layer steel frame, the GRG plate can be fine-tuned horizontally, and the flange edges of the adjacent GRG plates can be clamped by C-shaped clamps to adjust the spacing between the GRG plates. After the adjustment is completed, the position of the bolts is welded.

[0045] like Figure 2 As shown, before the caulking process is performed in step 7, elastic gaskets 6 are filled between the flange edges 5 of adjacent GRG boards. The elastic gaskets 6 are such as cork sheets, and the flange edges 5 are fixed and locked by counter-screws 7. The counter-screws 7 pass through the elastic gaskets. After the elastic gaskets 6 and the counter-screws 7 are installed, the flange edges 5 are also coated with a docking material for reinforcement to form a docking 8. The docking material is formed by mixing gypsum powder, glass fiber and water dedicated to GRG. The docking can improve the overall rigidity and bending resistance of the GRG board.

[0046] When caulking, fill the caulking material and glass fiber to level the seams, fill the seams completely, and then use glass fiber tape to level the joints. After the caulking material is dry, apply GRG adhesive all over and scrape it flat; then use glass fiber tape to level the joints again, and apply GRG adhesive all over and scrape it flat again.

[0047] This embodiment is only a further explanation of the present invention, not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but as long as it is within the scope of the claims of the present invention, it will be protected by the patent law.

Claims

1. A method for constructing a GRG wood grain ceiling. It is characterized in that The method includes: Step 1: Build the transfer layer keel on the top of the building; Step 2: transport the finished GRG board to the installation area, embed the embedded parts on the back of the GRG board, and set the flange edge on the edge of the GRG board; Step 3, the embedded parts are fixed to the angle steel by bolts, and then the GRG plate is moved to the installation position, and after the positioning of the GRG plate is completed, the angle steel is welded and fixed to the transfer layer keel; Step 4: Repeat steps 2-3 to install the next GRG board adjacent to the first GRG board; Step 5: Clamp the flange edges of adjacent GRG plates with C-type clamps, adjust the distance between the plate seams of the GRG plates, weld and fix the embedded parts and angle steels with bolts, and remove the C-type clamps; Step 6: Install the remaining adjacent GRG boards adjacent to the installed GRG boards according to the methods of steps 2-5; Step 7: After all GRG boards are installed, caulking the joints of the GRG boards; Step 8: Carry out wood grain decoration on the surface of GRG board.

2. A method for constructing a GRG wood grain ceiling according to claim 1, It is characterized in that When processing the GRG board, it is shaped by a customized mold, and the GRG slurry is poured into the mold layer by layer. After each layer of slurry is added, a layer of glass fiber felt cloth is laid to ensure that each layer of glass fiber felt cloth is penetrated by the GRG slurry, and the number of layers of glass fiber felt cloth is not less than 6 layers.

3. A method for constructing a GRG wood grain ceiling according to claim 2, It is characterized in that After the second layer of glass fiber felt is laid, embedded parts are pre-embedded and installed. The embedded parts are T-shaped embedded parts, and glass fiber felt is added at the installation position of the embedded parts for reinforcement.

4. A method for constructing a GRG wood grain ceiling according to claim 1, It is characterized in that After the GRG board is processed, it will be pre-assembled and inspected, and after passing the inspection, it will be shaped and cleaned.

5. The method for constructing a GRG wood grain ceiling according to claim 1, It is characterized in that The length of the angle steel is 100-1000mm, a waist-shaped hole is arranged at the position where the embedded part is connected to the angle steel, and the bolt passes through the waist-shaped hole to be connected to the angle steel.

6. A method for constructing a GRG wood grain ceiling according to claim 1, It is characterized in that Before the caulking process is performed in step 7, elastic gaskets are filled between the flange edges of adjacent GRG plates, and the flange edges are fixed and locked by means of knocking screws, which pass through the elastic gaskets.

7. A method for constructing a GRG wood grain ceiling according to claim 6, It is characterized in that When caulking, fill the caulking material and glass fiber to level the seams, fill the seams completely, and then use glass fiber tape to level the joints. After the caulking material is dry, apply GRG adhesive all over and scrape it flat; then use glass fiber tape to level the joints again, and apply GRG adhesive all over and scrape it flat again.

8. A method for constructing a GRG wood grain ceiling according to claim 6, It is characterized in that After the elastic gasket and the counter-screws are installed, the edge of the flange is also covered with a docking material for reinforcement.

9. The method for constructing a GRG wood grain ceiling according to claim 1, It is characterized in that In step 8, the lower surface of the installed GRG board is putty-scraped and leveled, and after the putty is dried, a primer is sprayed to seal it, and then veneer glue is applied or wood grain paint is applied.

10. A GRG wood grain ceiling, It is characterized in that It is constructed according to the method described in any one of claims 1 to 9.

Citation Information

Patent Citations

  • Lightweight GRG material formula and GRG manufacturing method

    CN104402378A

  • Construction method of large-space waved GRG suspended ceiling

    CN111287456A

  • Construction method of GRG integrated ceiling assembly type module system

    CN117888671A