Safety production intelligent anti-misoperation mobile platform for power enterprise

By integrating multiple management systems into the operation ticket management system of power companies, intelligent monitoring and forced locking of electrical equipment operations are realized, which solves the problems of insufficient error prevention and intelligent processing in the existing technology and significantly reduces the cost of power equipment. The safety hazards of operation ensure the safety and accuracy of operation.

CN118757664APending Publication Date: 2024-10-11SHANDONG CHUANGDE SOFTWARE TECH
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202410799206.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-20
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The existing operation ticket management system of electric power companies has deficiencies in error prevention and intelligent processing, especially in multi-dimensional sensory data fusion and safety management and control, resulting in a high risk of misoperation, and traditional paper operation tickets cannot meet the needs of modern power companies. The information needs of the industry.

Method used

An intelligent error-proof mobile platform for safe production is designed for electric power enterprises, which integrates the docking operation standardization system, comprehensive management system, lock management system, access control management system, network management system, video management system, operation ticket management system and simulation The graph management system, through the interconnection and intelligent means of these systems, can realize forced locking and real-time monitoring of the operation of electrical equipment to ensure the correctness and safety of the operation sequence.

Benefits of technology

It effectively reduces safety hazards in the operation of electrical equipment, ensures the safety and accuracy of operations, avoids misoperations due to improper operation sequences, realizes intelligent, comprehensive and precise control of electrical equipment, and improves the safety of the power industry. production level.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118757664A_ABST
    Figure CN118757664A_ABST
Patent Text Reader

Abstract

The invention discloses a safety production intelligent anti-misoperation mobile platform for a power enterprise. The platform comprises a docking operation standardization system, a comprehensive management system, a simulated diagram system, a lock management system, an access control management system, a network management system, a video management system, an operation ticket management system, a simulated diagram management system and a mobile terminal management system. Wherein the lock management system, the access control management system, the network management system, the video management system, the operation ticket management system, the simulated diagram management system and the mobile terminal management system are integrated in a unified manner; the docking operation standardization system, the comprehensive management system, the simulated diagram system, the lock management system, the access control management system, the network management system, the video management system, the operation ticket management system, the simulated diagram management system and the mobile terminal management system communicate with one another. The electronic operation anti-misoperation system of the conventional power distribution room is upgraded and perfected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power safety, and in particular to an intelligent anti-error mobile platform for safe production of electric power enterprises. Background Art

[0002] There are few studies and applications on electrical operation ticket management systems abroad. Judging from the currently available information resources, foreign countries have relatively simple considerations on the implementation of operation tickets, and there are fewer types of operations, especially in terms of error prevention and simple implementation of operation tickets. The earliest operation ticket management was developed by Taka Shi Abe et al. in Japan based on the Virgo expert system. In the process of implementing the professional library, the descriptive language of data description was mainly used to implement one by one, and the types of dispatching operations were relatively simple, with only two basic operations such as power outage and power transmission, and there were fewer types, so the operation ticket processing process they considered in terms of error prevention and intelligence was not yet sound.

[0003] Compared with foreign countries, the existing operation ticket management system of most domestic thermal power companies still adopts the traditional application mode of handwritten paper operation tickets. Some power grid companies or power generation companies have been developing and using electronic operation tickets. However, in recent years, with the rapid development of big data technology, Internet of Things technology, and mobile communication technology, various industries are now integrating and innovating around the Internet, which not only helps product upgrades, but also promotes the combination of new technologies and production, and promotes the improvement of information technology.

[0004] Some domestic thermal power companies are gradually transitioning from paper operation tickets to electronic operation tickets, but only a few companies are integrating electronic operation tickets based on multi-dimensional perception data, and remain on the basis of a single information source. The invention of the integrated platform for power operation safety control based on multi-dimensional perception data fusion and full-process safety control of operation tickets is rarely used in China. The invention effectively uses physical, institutional, and technological control methods to prevent the occurrence of misoperation, implement safety management requirements, achieve closed-loop management of safe production, prevent related accidents, ensure the safety of on-site operations, and ultimately provide protection for personal and equipment safety. For the above problems, there may already be technical means to solve them in the existing technology, but this case wants to provide an alternative or replacement technical solution. Summary of the invention

[0005] The technical solution of the present invention to achieve the above-mentioned purpose is: an intelligent anti-error mobile platform for safe production of power enterprises, the platform comprising: a docking operation standardization system, an integrated management system, a simulation diagram system, a lock management system, a door access management system, a network management system, a video management system, an operation ticket management system, a simulation diagram management system and a mobile terminal management system;

[0006] Among them, the lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system are uniformly integrated;

[0007] The docking operation standardization system, integrated management system, simulation diagram system, lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system communicate with each other.

[0008] Preferably, it comprises: a mounting wall and a detection box, wherein the detection box is mounted on the mounting wall through a rapid detection adjustment structure, and the inner side of the detection box is mounted on the detection structure;

[0009] The rapid detection and adjustment structure comprises: a vertical and horizontal screw module, a horizontal moving plate, a concave circular ring block, a rotating circular ring block, a rotating driving machine, two pairs of circular ring limit tubes, a plurality of circular ring sleeves, a plurality of circular ring lifting limit rings, two pairs of lifting circular ring electromagnets, a plurality of circular ring set magnets, a locking assembly and a vertical adjustment assembly;

[0010] The longitudinal and transverse screw module is installed on the installation wall surface, the horizontal movable plate is installed on the movable end of the longitudinal and transverse screw module, the concave circular ring block is installed on the horizontal movable plate, the rotating circular ring block is inserted on the inner side of the concave circular ring block through a bearing, the rotating drive motor is installed on the inner side of the concave circular ring block, and the driving end of the rotating drive motor is connected to the rotating circular ring block, two pairs of the circular ring sleeves are installed in parallel on the rotating circular ring block, a number of the circular ring sleeves are respectively movably inserted on the inner sides of the two pairs of the circular ring limiting tubes, a number of the circular ring lifting and limiting rings are respectively installed on a number of the circular ring sleeves and the two pairs of the circular ring limiting tubes, two pairs of the lifting circular ring electromagnets are respectively installed on the two pairs of the circular ring limiting tubes, a number of the circular ring set magnets are respectively installed on a number of the circular sleeves, the locking assembly is installed on the two pairs of the circular ring limiting tubes, and the vertical adjustment assembly is installed on the two pairs of the circular sleeves.

[0011] Preferably, the locking assembly comprises: a plurality of side wall telescopic sleeves, a plurality of side wall convex telescopic blocks, a plurality of side wall sleeve springs, a plurality of side wall circular ring magnets and a plurality of side wall circular ring electromagnets;

[0012] Several of the side wall telescopic sleeves are respectively inserted into the two pairs of the circular ring limiting tubes in a cross shape, several of the side wall convex telescopic blocks are respectively movably inserted into the inner sides of several of the side wall telescopic sleeves, several of the side wall sleeve springs are respectively sleeved on several of the side wall convex telescopic blocks, several of the side wall circular ring magnets are respectively installed on several of the side wall convex telescopic blocks, several of the side wall circular ring electromagnets are respectively installed on several of the side wall telescopic sleeves, and several of the circular sleeves are respectively provided with telescopic openings.

[0013] Preferably, the vertical adjustment assembly comprises: a concave scanning support block, a pair of vertical scanning axes, a vertical scanning driver, a pair of arc concave slideways, a pair of arc convex slide blocks, a pair of arc limit axes, a pair of arc telescopic blocks, two pairs of arc friction plates, a pair of friction magnets and a pair of friction electromagnets;

[0014] The concave scanning support block is installed on two pairs of the circular sleeves, a pair of the vertical scanning axes are respectively inserted on both sides of the detection box, and a pair of the vertical scanning axes are inserted on the concave scanning support block, the vertical scanning drive machine is installed on the concave scanning support block, and the driving end of the vertical scanning drive machine is connected to the vertical scanning axis, a pair of the circular arc concave slideways are respectively installed on the inner sides of the concave scanning support block, a pair of the circular arc convex sliders are respectively installed on both sides of the detection box, and a pair of the circular arc convex sliders are respectively movably inserted Installed on the inner side of a pair of the arc concave slideways, a pair of the arc limit shafts are respectively movably inserted on the inner side of a pair of the arc concave slideways, and a pair of the arc limit shafts are respectively movably inserted on a pair of the arc convex sliders, a pair of the arc concave slideways are respectively provided with convex expansion grooves, two pairs of the arc friction plates are respectively installed on a pair of the arc convex sliders and the inner sides of a pair of the convex expansion grooves, a pair of the friction magnets are respectively installed on a pair of the arc friction plates, and a pair of the friction electromagnets are respectively installed on the inner sides of a pair of the convex expansion grooves.

[0015] Preferably, the detection structure comprises: two pairs of warning lights, a plurality of detectors, a plurality of fixed set blocks, two pairs of nuts, a pair of chargers, a pair of magnetic chargers, a battery and a face recognition camera;

[0016] The two pairs of warning lights are inserted into the detection box in parallel, and a plurality of detectors and a plurality of fixed mounting blocks are respectively and interchangeably mounted on the two pairs of warning lights. The two pairs of warning lights are provided with thread grooves, and the two pairs of nuts are respectively mounted on the two pairs of thread grooves, and the installation is on the detection box.

[0017] Preferably, an infrared sensor is provided on the detection box.

[0018] Preferably, the docking operation standardization system automatically synchronizes the operation ticket to the integrated platform, provides mobile terminals and dedicated APPs, enables the mobile terminals to execute the operation tickets without distinction, and realizes hot ticketing involving complex operations such as equipment start and stop on the basis of the original system, integrating all operation tickets into one.

[0019] Preferably, the integrated management system uses a mobile terminal to implement access control and recording of staff entering and exiting the distribution room. The system calls the video surveillance probe that can monitor the positioning area based on the positioning information, and realizes multi-directional real-time monitoring of the execution process of the electrical operation ticket through video, recording, etc. through multi-system linkage, and displays the status of on-site equipment, the status of operators, and the progress of work in real time.

[0020] Preferably, the simulation diagram system can instantly view the equipment status information, realize data interaction with PI real-time data, and alarm when the equipment status is inconsistent; combined with the access control system, it can realize temporary authorization of operators to prevent irrelevant personnel from entering the operation area and accidentally touching the equipment; on the basis of the existing electrical operation QR code anti-error, an intelligent lock with communication function is added, and the lock is opened and closed in sequence according to the operation ticket sequence, and it also has refusal to open and alarm prompts.

[0021] Through the superposition of the above technologies, forced locking is implemented for on-site operations to ensure that operators operate electrical equipment according to established safety operating procedures that meet the requirements, thereby achieving the purpose of error prevention; avoiding misoperation of various electrical equipment caused by improper operating sequence.

[0022] Preferably, the lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system are used to display the status of on-site equipment, operator status, operation ticket progress, etc. in real time. After the operation task is completed, data synchronization is completed with one click and backfilled to the normalized operation system.

[0023] Compared with the prior art, the intelligent anti-error mobile platform for safe production of power enterprises produced by using the technical solution of the present invention uses electronic information technology and Internet of Things technology to standardize electrical operations, which is an upgrade and improvement of the conventional distribution room electronic operation anti-error system, and creates a precedent for truly intelligent, comprehensive and precise control of the electrical operation execution process. It effectively uses physical and technical control methods to prevent the occurrence of misoperation, implements safety management requirements, realizes closed-loop management of safe production, prevents related accidents, ensures the safety of distribution room operations, and ultimately provides protection for personal and equipment safety. The economic and social benefits that will be generated make it necessary to promote it in the power industry.

[0024] The present invention can effectively reduce potential safety hazards in the maintenance and operation of power equipment. Power equipment operation is a high-risk, routine job. Currently, many major safety accidents have occurred in power maintenance work, causing serious economic losses and casualties. Through the integrated platform for power operation safety management and control, it is possible to effectively reduce the misoperation of power equipment operators, reduce potential safety hazards, and ensure the safe and smooth execution of work tasks. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 This is a schematic diagram of the main structure of an intelligent anti-error mobile platform for safe production in power enterprises described in the present invention.

[0026] Figure 2 This is a side structural schematic diagram of an intelligent anti-error mobile platform for safe production in power enterprises described in the present invention.

[0027] Figure 3 for Figure 1 A partial enlarged view of "A".

[0028] Figure 4 for Figure 1 A partial enlarged view of "B".

[0029] In the figure: 1. detection box; 2. vertical and horizontal screw module; 3. horizontal moving plate; 4. concave circular ring block; 5. rotating circular ring block; 6. rotating drive machine; 7. circular ring limit tube; 8. circular ring sleeve; 9. circular ring lifting limit ring; 10. lifting circular ring electromagnet; 11. circular ring set magnet; 12. side wall telescopic sleeve; 13. side wall convex telescopic block; 14. side wall set spring; 15. side wall circular ring magnet; 16. side wall circular ring electromagnet; 17. concave scanning support block; 18. vertical scanning axis; 19. vertical scanning drive machine; 20. arc concave slideway; 21. arc convex slider; 22. arc limit shaft; 23. arc telescopic block; 24. arc friction plate; 25. friction magnet; 26. friction electromagnet. DETAILED DESCRIPTION

[0030] Through the personnel in this field, all the electrical components in this case are connected to their corresponding power supplies through wires, and a suitable controller should be selected according to the actual situation to meet the control requirements. The specific connection and control sequence should refer to the following working principle, and the electrical connection between the electrical components is completed in the order of working in sequence. The detailed connection means are well-known technologies in this field. The following mainly introduces the working principle and process, and does not explain the electrical control.

[0031] Example 1

[0032] A safe production intelligent anti-error mobile platform for power enterprises, the platform comprises: a docking operation standardization system, an integrated management system, a simulation diagram system, a lock management system, a door access management system, a network management system, a video management system, an operation ticket management system, a simulation diagram management system and a mobile terminal management system; wherein the lock management system, the door access management system, the network management system, the video management system, the operation ticket management system, the simulation diagram management system and the mobile terminal management system are integrated; the docking operation standardization system, the integrated management system, the simulation diagram system, the lock management system, the door access management system, the network management system, the video management system, the operation ticket management system, the simulation diagram management system and the mobile terminal management system communicate with each other; the docking operation standardization system automatically synchronizes the operation ticket to the integrated platform, provides mobile terminals and special APPs, realizes the non-differential execution of operation tickets by mobile terminals, realizes hot ticket tickets involving complex operations such as equipment start and stop on the basis of the original system, and integrates all operation tickets; the integrated management system realizes the access control management and recording of staff entering and leaving the distribution room for mobile terminals, and the system calls the video surveillance probe that can monitor the positioning area according to the positioning information, and The system linkage realizes multi-dimensional real-time monitoring of the execution process of the electrical operation ticket, such as video and audio recording, and displays the on-site equipment status, operator status and work progress in real time; the simulation diagram system can instantly view the equipment status information, realize data interaction with PI real-time data, and alarm when the equipment status is inconsistent; combined with the access control system, temporary authorization of operators is realized to prevent irrelevant personnel from entering the operation area and accidentally touching the equipment; on the basis of the existing electrical operation QR code error prevention, intelligent locks with communication functions are added to realize the opening and closing of locks in sequence according to the operation ticket sequence, and at the same time have refusal to open and alarm prompts; through the superposition of the above technologies, forced locking is implemented for on-site operations to ensure that operators operate electrical equipment according to the established safety operating procedures that meet the requirements, so as to achieve the purpose of error prevention; avoid various electrical equipment misoperations caused by improper operation sequence; the lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system are used to display the on-site equipment status, operator status, operation ticket progress and other conditions in real time. After the operation task is completed, data synchronization is completed with one click and backfilled to the normalized operation system.

[0033] The main key technical applications of this invention are:

[0034] Intelligent ticket receiving: docking with the standardized operation system, automatically synchronizing the operation ticket to the integrated platform, providing mobile terminals and dedicated APPs, and realizing the execution of operation tickets without difference on mobile terminals. Based on the original system, hot tickets involving complex operations such as equipment start and stop are realized, integrating all operation tickets.

[0035] Process supervision: The mobile terminal realizes the access control and recording of staff entering and leaving the distribution room. The system calls the video surveillance probe that can monitor the positioning area according to the positioning information. Through the linkage of multiple systems, it realizes multi-dimensional real-time monitoring of the execution process of the electrical operation ticket, such as video and recording, and displays the status of on-site equipment, the status of operators and the progress of work in real time.

[0036] Combined with the permitted time for job management, it has an active overdue reminder function to monitor the entire operation process in space and time.

[0037] Preventing errors in operation: Upgrade and optimize the simulation diagram system, instantly view the equipment status information, realize data interaction with PI real-time data, and alarm when the equipment status is inconsistent; combine with the access control system to realize temporary authorization of operators to prevent irrelevant personnel from entering the operation area and accidentally touching the equipment; on the basis of the existing electrical operation QR code to prevent errors, add smart locks with communication functions, realize the opening and closing of locks in sequence according to the operation ticket sequence, and have refusal to open and alarm prompts.

[0038] Through the superposition of the above technologies, forced locking is implemented for on-site operations to ensure that operators operate electrical equipment according to established safety operating procedures that meet the requirements, thereby achieving the purpose of error prevention; avoiding various electrical equipment misoperations caused by improper operating sequences.

[0039] Operation and maintenance integration: lock management, access control management, network management, video management, operation ticket management, simulation diagram management and mobile terminal management are unified and integrated, and PC and mobile terminals are efficiently synchronized. Real-time display of on-site equipment status, operator status, operation ticket progress, etc. After the operation task is completed, one-click data synchronization is completed and backfilled to the normalized operation system.

[0040] Specifically, the operating system provided by the present invention has an autonomous editing module and a template selection module, wherein:

[0041] Self-editing module: After the operation ticket is synchronized to this system, fill in the risk level analysis card according to the content of the operation ticket.

[0042] Template selection module: The approved risk level analysis card can be provided to the operator in the form of a template for writing and use.

[0043] The operation ticket can only be issued after the operator has filled in the risk level analysis card, which is sent to the integrated platform in electronic form. When using the mobile terminal for operation, the operation can only be completed after all inventions are filled in.

[0044] While the operation risk level analysis card is digitized, it can be expanded and edited according to actual needs, ultimately realizing the functions of mobile terminal confirmation, WEB terminal synchronous display and query.

[0045] All electrical operation tickets are equipped with a pre- and post-switching operation inspection card, which is integrated with the operation ticket to achieve a one-ticket-one-card design. The pre- and post-switching operation inspection card is fixed. After all operations are completed, the contents of the switching operation inspection card need to be filled in item by item.

[0046] While the inspection cards before and after the switching operation are digitized, they can be expanded and edited according to actual needs, ultimately realizing the functions of mobile terminal confirmation, WEB terminal synchronous display and query.

[0047] Since all operation tickets in the standardized operation system do not have the ticket-in-ticket function, it is necessary to customize and add it in the integrated system to realize the combination of ticket-in-ticket functions (package ticket);

[0048] For example, in an operation ticket, the fifth task is: Start induced draft fan A. The entire operation process of starting induced draft fan A is automatically realized on the mobile terminal according to the keyword:

[0049] By associating fixed data (keywords), the ticket-in-ticket function of the invention is automatically implemented on the mobile terminal. The operation items and keywords are provided by the owner, covering about 50 operation items. The ticket-in-ticket function should have a dedicated identification and configuration page to facilitate keyword identification of operation data and editing of ticket-in-ticket content.

[0050] After the ticket-in-ticket passes the intelligent identification of the integrated system, it will be issued to the same mobile terminal along with the main ticket, and quick issuance and automatic synchronization are guaranteed. The operated content will not be backfilled in the standardized operation system.

[0051] While the ticket-in-ticket function is realized electronically, it can be expanded and edited according to actual needs, and ultimately realize the functions of mobile terminal confirmation, WEB terminal synchronous display and query.

[0052] The integrated system not only covers the electrical operation ticket of the intelligent error prevention control platform, but also needs to be expanded to the thermal machine operation ticket. The thermal machine operation ticket and the electrical switching operation ticket are basically the same in operation, but the following contents are optimized and improved on the current basis.

[0053] Because the operation time of thermal machinery operation tickets may be long (such as when starting the unit), some operations cannot be completed within one shift and need to be performed across shifts. When performing across shifts, the operation ticket should be re-approved. Since this function is not available in the normalized operation system, the circulation and approval of the operation ticket should be realized in the integrated platform. The approved operation ticket will be continued to be executed by the next shift (sent to the same mobile terminal), the risk level analysis card will be re-filled, and the operation content will continue to be executed.

[0054] When an abnormal situation occurs during the operation, it is necessary to stop and check or perform other operations immediately. The PC and mobile terminals can realize the manual pause function. After the pause, the operation ticket stops operating. It can only be resumed normally after unlocking the pause on the PC terminal and confirming the QR code on the mobile terminal.

[0055] In some important operations of the electrical operation ticket, such as the use of the electric tester. First, check that the electric tester is intact on the electrical equipment, and then test the equipment to be powered off. It is strictly forbidden to execute the next operation without Q-point confirmation. When issuing the standardized system operation ticket, the operation items that require Q-point confirmation will be specially marked, and the integrated system will identify them simultaneously. The operation items that require Q-point confirmation are forced to call the video recording function of the mobile device. The operator sends the Q-point confirmation content to the PC in the control room in the form of a video. After the manager confirms the video clip, he will sign the electronic signature on the PC handwriting board (supports touch screen or mouse signing function), and then proceed to the next step; non-compliant ones will be returned, and the operator will continue to upload the video. When there is no network or relevant personnel are on site, sign on the local mobile terminal. Ensure the mutual exclusivity of the two implementation methods.

[0056] Functions such as risk level analysis card and Q point confirmation require remote signature function, and a handwriting tablet is provided on the PC to realize the electronic signature function of touch screen or mouse.

[0057] The completed operation tickets are evaluated on the PC side. The administrator can adjust the authority of the evaluator, and all personnel information is connected to the standardized operation system (the owner communicates and obtains the connection conditions of the standardized operation personnel), and is refreshed regularly. The evaluation content is saved in the integrated platform, and the data is not sent back to the standardized operation system, but customized queries can be performed based on the evaluation results.

[0058] Provides operation ticket query and statistics functions for operation ticket query or monthly query statistics.

[0059] (1) Organize the statistical information of operation ticket query results according to the organization method of department-work group-year and month.

[0060] (2) Provide the function of exporting operation ticket query results and statistical results.

[0061] (3) Operation ticket statistics conditions include:

[0062] a) Statistics can be collected on a monthly, quarterly or annual basis, and the statistical time period can be set arbitrarily.

[0063] b) Statistics can be collected by operator and guardian.

[0064] c) Statistics can be collected based on the specified keywords.

[0065] d) Number of operation tasks.

[0066] e) For unexecuted operation tickets, only the number of operation tasks is counted.

[0067] The anti-mislocking devices currently used on site are replaced with smart locks, which have no power supply (passive locks). Customized unlocking software matching the smart locks is developed, and the corresponding control locks are matched through the device information in the operation ticket. The software has unlocking and query functions.

[0068] When the operation ticket is issued, the lock opening authority, operation start / end time, and operation step sequence corresponding to the device / switch / reversing switch in the operation ticket are synchronized to the smart lock management module through keyword setting and identification. At the same time, the unlocking authority is updated to the mobile device (synchronized within the dedicated wireless network, supporting unlocking in offline state), thereby realizing unlocking of the mobile device.

[0069] The equipment information in the execution sequence of the electrical operation ticket is matched with the lock information. When the mobile terminal receives the operation ticket, it also receives the lock opening authority and the switch sequence. After the operation is completed, the lock must be closed. The mobile terminal uses the lock status query function to judge. If the lock is not opened or closed in sequence, the program automatically alarms and prohibits the next operation. The execution steps of the lock appear during the operation, which need to be specially marked.

[0070] The mobile terminal has effective time control over the opening of the lock, starting from the operation ticket and ending at the operation ticket. The mobile terminal does not have the unlocking function outside the time period. According to the actual situation, you can configure a smart unlocking terminal (universal key) with administrator unlocking authority.

[0071] It has NFC contact unlocking function and good rain and dustproof capabilities. The style includes 200 smart padlocks (long handle, short handle). In addition to obtaining lock information, the smart lock management module can also realize lock grouping, lock temporary authorization and other functions.

[0072] The offline operation of the distribution room in Phase IV, where access control has been deployed, is relatively stable, but the online effect is poor; the products are from 15 years ago and do not support network communication. Due to long-term operation, access control equipment is damaged and replaced every year. The switch room without access control is unevenly distributed and far away from the Phase IV centralized control room. There is a long-term lack of access control, which poses a great safety hazard.

[0073] This plan involves replacing all access control systems, which involves equipment procurement and on-site construction work: Renovating the access control systems of 26 power distribution rooms / switch rooms. All access control systems will be replaced with integrated access control systems with card swiping and face recognition functions.

[0074] The access control system control software is integrated with the integrated platform for power operation safety management and control based on multi-dimensional perception data fusion to obtain access control system control permissions. The access control management module can adjust personnel permissions online and support data interaction. The door opening and closing information of the access control system can be found in the system. When the operation ticket execution area does not match the access control of the corresponding distribution room / switch room, the room cannot be entered and information notification or alarm is realized on the mobile terminal to prevent going to the wrong area.

[0075] The access control system supports the divided authority control for normal inspection and electrical operation. Normal inspection uses IC card contact to open the room door (consistent with the current situation), and electrical operation uses face recognition to open the room door. The door opening mode can be customized.

[0076] The original Phase IV video surveillance system network hard disk recorder has poor stability due to its uninterrupted operation all year round. There are 18 channels of video signals missing, and the 18 channels of video need to be restored during the monitoring upgrade. During this monitoring equipment upgrade, a 128-channel network hard disk recorder (including hard disk) needs to be added.

[0077] In addition to being consistent with the original anti-error intelligent management and control platform in terms of functionality, the biggest optimization and upgrade is that all client devices can now browse without plug-ins when calling videos.

[0078] Other video access forms: Since the present invention only involves four phases of video, some videos are in the Sky Eye system or the first, second and third phases of hard disk video recorders, and the design uses a network cable to directly connect the hard disk video recorder to obtain it. (There are network deployment issues in obtaining local images)

[0079] Mobile terminal registration management: through registration management, determine the working permissions of mobile terminals and devices, and logically bind them with the PC terminal to form an operation group.

[0080] Mobile terminal network connection status management: Status management is used to determine whether the mobile terminal is connected to the operating network, whether the operation ticket can be downloaded, and whether it can interact with the background in real time.

[0081] Real-time audio communication: Establish a real-time voice interface between the mobile terminal and the operation console, and play the sound from the operation console.

[0082] Q-point remote confirmation: supports real-time video recording on mobile terminals to transmit on-site conditions.

[0083] Time synchronization: When using the mobile terminal for on-site operations, each operation can automatically generate an operation time, and automatic alarm prompts and lock operations in case of missing items or skipping items to prevent missing items or skipping items. (Applicable to electrical operation tickets, thermal engine operation tickets are improved according to actual conditions to meet actual needs on site)

[0084] QR code error prevention: When the operation ticket reaches this step, the QR code scanner is automatically called to scan the QR code image to confirm that the key operation location and equipment object information are correct before the next step can be performed to prevent the wrong interval and the wrong operation of the equipment. When the wrong QR code is scanned, the system prompts an error warning.

[0085] Unlocking function: When unlocking is required during the execution of the operation ticket, the smart lock is contacted to realize the unlocking function. Locks that do not meet the unlocking conditions cannot be opened and an alarm prompts, forcing the mobile terminal to perform a second confirmation.

[0086] Take photos and send back: Take photos of the equipment operation information and send it back in real time for later inquiry.

[0087] Setting function: The setting function mainly includes real-time intercom switch and IP setting function.

[0088] Operations on mobile terminals have the function of offline operation when there is no network coverage, and data can be transmitted back in time when reaching the wireless coverage area.

[0089] Voice recording: During on-site operation, the mobile terminal automatically turns on the recording function to record the entire operation ticket reading and recitation process, and the operation cannot be interrupted manually before it is completed. After the operation ticket is executed, the recording is uploaded to the server to facilitate the tracing of the historical operation process. (The voice recording function automatically ends when the operation ticket is paused or during the shift)

[0090] Due to the restrictions of the on-site network and security, the error prevention simulation system cannot communicate with the EMS production system in real time, resulting in the current error prevention simulation system being an information island. The integrated platform design uses PI real-time data as a reference to judge and analyze the error prevention simulation system and perform real-time online position comparison.

[0091] Optimize the anti-error simulation system. Only after the simulation in the system is passed and the operation is performed in the correct order, can the operation be opened. (Manual judgment) The initial status of all equipment is completed by manual alignment, and the equipment alignment is correct before it is put into use. The status of the equipment, switches, and knife switches of the anti-error simulation system is transmitted to the integrated platform in real time through the power-specific interface.

[0092] Through the customized development interface, obtain the status of electrical professional equipment, switches, and knife switches in the PI real-time database. (Some data cannot be obtained, and the position of the simulation diagram shall prevail)

[0093] The PI data corresponds one-to-one with the anti-error simulation system data, and the abnormal situation of the alignment is monitored in real time through professional status comparison and analysis tools.

[0094] When an alignment abnormality occurs, an alarm is used to prompt the operator to conduct an inspection.

[0095] One diagram for anti-mistake simulation, real-time data, access control, and lock management. Draw a vector diagram consistent with the anti-mistake simulation diagram equipment. The simulation diagram supports plug-in-free browsing and magnification without distortion. Realize online monitoring on PC and mobile terminals.

[0096] Draw a simulation diagram similar to the on-site equipment. Through the changes in the error prevention simulation data, the operating personnel can view the real-time status of the simulation diagram equipment and the current operating status of the on-site equipment by themselves. By comparing and analyzing the two, the operating personnel can be assisted in improving the error prevention effect.

[0097] Access to the real-time data of the PI system to alert operators of positioning anomalies through alarms

[0098] Divide the area according to the location of the distribution room / switch room, and artificially divide the access control, corresponding equipment and lock status to realize online viewing of the area location and access control status.

[0099] According to the anti-error simulation diagram, the corresponding locks are associated. The unlocking sequence is confirmed by the execution sequence of the operation ticket, and the lock number and lock status can be viewed online.

[0100] The operating system is an open source mobile platform - Android version. To meet security and compatibility requirements, the version is no less than Android 8.0. It has NFC function, which can realize short-range data communication and power supply. WIFI version, with high-definition camera;

[0101] Example 2

[0102] The present invention will be described in detail below in conjunction with the accompanying drawings. Figure 1-4As shown, the detection box 1 is installed on the installation wall through a quick detection adjustment structure, and the inner side of the detection box 1 is installed on the detection structure; the quick detection adjustment structure includes: a longitudinal and transverse screw module 2, a horizontal moving plate 3, a concave circular ring block 4, a rotating circular ring block 5, a rotating drive machine 6, two pairs of circular ring limit tubes 7, a plurality of circular ring sleeves 8, a plurality of circular ring lifting limit rings 9, two pairs of lifting circular ring electromagnets 10, a plurality of circular ring set magnets 11, a locking component and a vertical adjustment component; the longitudinal and transverse screw module 2 is installed on the installation wall, the horizontal moving plate 3 is installed on the moving end of the longitudinal and transverse screw module 2, the concave circular ring block 4 It is installed on the horizontal moving plate 3, the rotating ring block 5 is inserted into the inner side of the concave ring block 4 through a bearing, the rotating driving machine 6 is installed on the inner side of the concave ring block 4, and the driving end of the rotating driving machine 6 is connected to the rotating ring block 5, two pairs of the ring sleeves 8 are installed in parallel on the rotating ring block 5, a number of the ring sleeves 8 are respectively movably inserted into the inner sides of the two pairs of the ring limiting tubes 7, a number of the ring lifting limiting rings 9 are respectively installed on the several ring sleeves 8 and the two pairs of the ring limiting tubes 7, two pairs of the lifting ring electromagnets 10 are respectively installed on the two pairs of the ring limiting tubes 7, and a number of the rings The ring-set magnets 11 are respectively installed on several of the circular sleeves 8, the locking components are installed on two pairs of the circular limit tubes 7, and the vertical adjustment components are installed on two pairs of the circular sleeves 8; the locking components include: several side wall telescopic sleeves 12, several side wall convex telescopic blocks 13, several side wall set springs 14, several side wall circular ring magnets 15 and several side wall circular ring electromagnets 16; several side wall telescopic sleeves 12 are respectively inserted into the two pairs of circular limit tubes 7 in a cross shape, several side wall convex telescopic blocks 13 are respectively movably inserted into the inner sides of several side wall telescopic sleeves 12, and several side wall set springs 14 are respectively inserted into the inner sides of several side wall telescopic sleeves 12 in a cross shape. 4 are respectively mounted on a plurality of the side wall convex telescopic blocks 13, a plurality of the side wall circular ring magnets 15 are respectively mounted on a plurality of the side wall convex telescopic blocks 13, a plurality of the side wall circular ring electromagnets 16 are respectively mounted on a plurality of the side wall telescopic sleeves 12, and a plurality of the circular sleeves 8 are respectively provided with telescopic openings; the vertical adjustment assembly comprises: a concave scanning support block 17, a pair of vertical scanning shafts 18, a vertical scanning driver 19, a pair of circular arc concave slideways 20, a pair of circular arc convex sliders 21, a pair of circular arc limiting shafts 22, a pair of circular arc telescopic blocks 23, two pairs of circular arc friction plates 24, a pair of friction magnets 25 and a pair of friction electromagnets 26;The concave scanning support block 17 is installed on two pairs of the circular sleeves 8, a pair of the vertical scanning shafts 18 are respectively inserted on the two sides of the detection box 1, and a pair of the vertical scanning shafts 18 are inserted on the concave scanning support block 17, the vertical scanning driver 19 is installed on the concave scanning support block 17, and the driving end of the vertical scanning driver 19 is connected to the vertical scanning shaft 18, a pair of the arc concave slideways 20 are respectively installed on the inner sides of the concave scanning support block 17, a pair of the arc convex sliders 21 are respectively installed on the two sides of the detection box 1, and a pair of the arc convex sliders 21 are respectively movably inserted on the inner sides of a pair of the arc concave slideways 20, a pair of the arc limiting shafts 22 are respectively movably inserted on the inner sides of a pair of the arc concave slideways 20, and a pair of the arc limiting shafts 22 are respectively movably inserted on the pair of the arc convex sliders 21, a pair of the arc Concave slideway 20 is provided with convex expansion slots, two pairs of circular arc friction plates 24 are respectively installed on the inner side of a pair of circular arc convex slide blocks 21 and a pair of convex expansion slots, a pair of friction magnets 25 are respectively installed on a pair of circular arc friction plates 24, and a pair of friction electromagnets 26 are respectively installed on the inner side of a pair of convex expansion slots; the detection structure includes: two pairs of warning lights, several detectors, several fixed set blocks, two pairs of nuts, a pair of chargers, a pair of magnetic chargers, batteries and face recognition cameras; two pairs of warning lights are inserted in parallel on the detection box 1, several detectors and several fixed set blocks are respectively exchanged and set on the two pairs of warning lights, two pairs of warning lights are provided with threaded grooves, two pairs of nuts are respectively set on the two pairs of threaded grooves, and the detection box 1 is installed; the detection box 1 is provided with an infrared sensor. ;

[0103] According to the attached Figure 1-4It is concluded that the operation of the longitudinal and transverse lead screw module 2 drives the horizontal moving plate 3 on the moving end to move in the longitudinal and transverse directions, and the horizontal moving plate 3 drives the concave circular ring block 4 on it to move in the longitudinal and transverse directions, and the operation of the rotary drive machine 6 inside the concave circular ring block 4 drives the rotating circular ring block 5 on the driving end of the rotary drive machine 6, so that the rotating circular ring block 5 rotates on the inner side of the concave circular ring block 4, and the rotating circular ring block 5 drives the two pairs of circular ring limiting tubes 7 on it to rotate, and the horizontal rotation adjustment is performed through the multiple circular ring sleeves 8 inside the two pairs of circular ring limiting tubes 7, and the multiple circular ring sleeves 8 are telescopically locked by the locking assembly, and the side wall circular ring electromagnets 16 inside the multiple side wall telescopic sleeves 12 are energized, and the The current size on the side wall circular ring electromagnet 16 is changed, and the side wall circular ring magnet 15 is magnetically repelled by the side wall circular ring electromagnet 16. The side wall circular ring magnet 15 drives the side wall convex telescopic block 13 thereon, so that the side wall convex telescopic block 13 is horizontally telescoped along the inner side of the side wall telescopic sleeve 12, and the side wall convex telescopic block 13 is inserted into the inner side of the circular sleeve 8, so as to adjust the number of limit positions of several circular sleeves 8 according to different details, and drive the circular lifting limit rings 9 thereon respectively through several circular sleeves 8, and achieve stable lifting limit position through the cooperation between the circular lifting limit rings 9, so as to change the vertical height of the concave scanning support block 17. When the plurality of circular sleeves 8 are to be retracted, the circular sleeves 8 are lifted and lowered one by one to be magnetically adsorbed and fixed, and the lifting circular electromagnet 10 is energized to make the lifting circular electromagnet 10 generate magnetic adsorption of the plurality of circular set magnets 11, and the lifting circular electromagnet 10 magnetically adsorbs the circular set magnets 11, so that the plurality of circular set magnets 11 on the plurality of circular sleeves 8 are magnetically adsorbed one by one, so as to lift the concave scanning support block 17, and the concave scanning support block 17 drives a pair of vertical scanning shafts 18 thereon to be lifted and lowered, and the pair of vertical scanning shafts 18 drives the detection box 1 thereon to be vertically lifted and lowered, and at the same time, the vertical scanning drive machine 19 is operated to drive The vertical scanning shaft 18 on the driving end of the vertical scanning driver 19 drives the detection box 1 thereon to rotate vertically on the inner side of the concave scanning support block 17 through the vertical scanning shaft 18, and the equipment is scanned and detected through the detection structure inside the detection box 1. The alarms on the two pairs of warning lights are used to issue alarms after the scanning camera completes the scanning. The two pairs of warning lights achieve a continuous warning effect, and the voice recognizer is used to confirm again whether it is an electrician. The charger is charged through a pair of magnetic chargers, the battery is charged through the charger, and the voice recognizer and the face recognition camera are charged through the battery. The entire device has a simple structure, is easy to install, and can be quickly adjusted and easily maintained.

[0104] The above technical solutions only reflect the preferred technical solutions of the technical solutions of the present invention. Some changes that may be made to certain parts thereof by technicians in this technical field all reflect the principles of the present invention and fall within the protection scope of the present invention.

Claims

1. An intelligent anti-error mobile platform for safe production in power enterprises, characterized in that: The platform includes: docking operation standardization system, integrated management system, simulation diagram system, lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system; Among them, the lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system are uniformly integrated; The docking operation standardization system, integrated management system, simulation diagram system, lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system communicate with each other.

2. According to claim 1, a detection device for a safe production intelligent anti-mistaken movement platform for a power enterprise comprises: An installation wall and a detection box, characterized in that the detection box is installed on the installation wall through a rapid detection adjustment structure, and the inner side of the detection box is installed on the detection structure; The rapid detection and adjustment structure comprises: a vertical and horizontal screw module, a horizontal moving plate, a concave circular ring block, a rotating circular ring block, a rotating driving machine, two pairs of circular ring limit tubes, a plurality of circular ring sleeves, a plurality of circular ring lifting limit rings, two pairs of lifting circular ring electromagnets, a plurality of circular ring set magnets, a locking assembly and a vertical adjustment assembly; The longitudinal and transverse screw module is installed on the installation wall surface, the horizontal movable plate is installed on the movable end of the longitudinal and transverse screw module, the concave circular ring block is installed on the horizontal movable plate, the rotating circular ring block is inserted on the inner side of the concave circular ring block through a bearing, the rotating drive motor is installed on the inner side of the concave circular ring block, and the driving end of the rotating drive motor is connected to the rotating circular ring block, two pairs of the circular ring sleeves are installed in parallel on the rotating circular ring block, a number of the circular ring sleeves are respectively movably inserted on the inner sides of the two pairs of the circular ring limiting tubes, a number of the circular ring lifting and limiting rings are respectively installed on a number of the circular ring sleeves and the two pairs of the circular ring limiting tubes, two pairs of the lifting circular ring electromagnets are respectively installed on the two pairs of the circular ring limiting tubes, a number of the circular ring set magnets are respectively installed on a number of the circular sleeves, the locking assembly is installed on the two pairs of the circular ring limiting tubes, and the vertical adjustment assembly is installed on the two pairs of the circular sleeves.

3. According to claim 1, a safe production intelligent anti-error mobile platform for power enterprises is characterized in that: The locking assembly comprises: a plurality of side wall telescopic sleeves, a plurality of side wall convex telescopic blocks, a plurality of side wall sleeve springs, a plurality of side wall circular ring magnets and a plurality of side wall circular ring electromagnets; Several of the side wall telescopic sleeves are respectively inserted into the two pairs of the circular ring limiting tubes in a cross shape, several of the side wall convex telescopic blocks are respectively movably inserted into the inner sides of several of the side wall telescopic sleeves, several of the side wall sleeve springs are respectively sleeved on several of the side wall convex telescopic blocks, several of the side wall circular ring magnets are respectively installed on several of the side wall convex telescopic blocks, several of the side wall circular ring electromagnets are respectively installed on several of the side wall telescopic sleeves, and several of the circular sleeves are respectively provided with telescopic openings.

4. According to claim 1, a safe production intelligent anti-error mobile platform for power enterprises is characterized in that: The vertical adjustment assembly comprises: a concave scanning support block, a pair of vertical scanning axes, a vertical scanning driver, a pair of arc concave slideways, a pair of arc convex slide blocks, a pair of arc limit axes, a pair of arc telescopic blocks, two pairs of arc friction plates, a pair of friction magnets and a pair of friction electromagnets; The concave scanning support block is installed on two pairs of the circular sleeves, a pair of the vertical scanning axes are respectively inserted on both sides of the detection box, and a pair of the vertical scanning axes are inserted on the concave scanning support block, the vertical scanning drive machine is installed on the concave scanning support block, and the driving end of the vertical scanning drive machine is connected to the vertical scanning axis, a pair of the circular arc concave slideways are respectively installed on the inner sides of the concave scanning support block, a pair of the circular arc convex sliders are respectively installed on both sides of the detection box, and a pair of the circular arc convex sliders are respectively movably inserted Installed on the inner side of a pair of the arc concave slideways, a pair of the arc limit shafts are respectively movably inserted on the inner side of a pair of the arc concave slideways, and a pair of the arc limit shafts are respectively movably inserted on a pair of the arc convex sliders, a pair of the arc concave slideways are respectively provided with convex expansion grooves, two pairs of the arc friction plates are respectively installed on a pair of the arc convex sliders and the inner sides of a pair of the convex expansion grooves, a pair of the friction magnets are respectively installed on a pair of the arc friction plates, and a pair of the friction electromagnets are respectively installed on the inner sides of a pair of the convex expansion grooves.

5. According to claim 1, a safe production intelligent anti-error mobile platform for power enterprises is characterized in that: The detection structure includes: two pairs of warning lights, a plurality of detectors, a plurality of fixed set blocks, two pairs of nuts, a pair of chargers, a pair of magnetic chargers, a battery and a face recognition camera; The two pairs of warning lights are inserted into the detection box in parallel, and a plurality of detectors and a plurality of fixed mounting blocks are respectively and interchangeably mounted on the two pairs of warning lights. The two pairs of warning lights are provided with thread grooves, and the two pairs of nuts are respectively mounted on the two pairs of thread grooves, and the installation is on the detection box.

6. The intelligent anti-error mobile platform for safe production of electric power enterprises according to claim 1 is characterized in that: The detection box is provided with an infrared sensor.

7. The intelligent anti-error mobile platform for safe production of electric power enterprises according to claim 1 is characterized in that: The docking operation standardization system automatically synchronizes the operation ticket to the integrated platform, provides mobile terminals and dedicated APPs, and enables the mobile terminals to execute the operation tickets without distinction. On the basis of the original system, it realizes hot ticketing involving complex operations such as equipment start and stop, and integrates all operation tickets into one.

8. The intelligent anti-error mobile platform for safe production of electric power enterprises according to claim 1 is characterized in that: The integrated management system uses mobile terminals to implement access control and recording of staff entering and exiting the distribution room. The system calls the video surveillance probe that can monitor the positioning area based on the positioning information, and realizes multi-faceted real-time monitoring of the execution process of the electrical operation ticket, such as video and recording, through multi-system linkage, and displays the status of on-site equipment, the status of operators, and the progress of work in real time.

9. The intelligent anti-error mobile platform for safe production of electric power enterprises according to claim 1 is characterized in that: The simulation chart system can instantly view the equipment status information, realize data interaction with PI real-time data, and alarm when the equipment status is inconsistent; combined with the access control system, it can realize temporary authorization of operators to prevent irrelevant personnel from entering the operation area and accidentally touching the equipment; on the basis of the existing electrical operation QR code anti-error, add intelligent locks with communication functions, realize the opening and closing of locks in sequence according to the operation ticket sequence, and have refusal to open and alarm prompts; Through the superposition of the above technologies, forced locking is implemented for on-site operations to ensure that operators operate electrical equipment according to established safety operating procedures that meet the requirements, thereby achieving the purpose of preventing errors; Avoid misoperation of various electrical equipment due to improper operating sequence.

10. The intelligent anti-error mobile platform for safe production of electric power enterprises according to claim 1 is characterized in that: The lock management system, access control management system, network management system, video management system, operation ticket management system, simulation diagram management system and mobile terminal management system are used to display the status of on-site equipment, the status of operators, the progress of operation tickets, etc. in real time. After the operation task is completed, data synchronization is completed with one click and backfilled to the normalized operation system.

Citation Information

Patent Citations

  • High-efficiency intelligent power distribution monitoring device of power distribution substation

    CN113676645A

  • Book information data storage system

    CN113800166A

  • Power distribution room anti-misoperation management and control system based on Internet of Things technology, and anti-misoperation management and control method thereof

    CN114067470A

  • Intelligent management and control platform combined with eagle eye error prevention

    CN114466036A

  • Camera shooting auxiliary device for electronic information acquisition

    CN116939337A