Load aggregator rolling operation optimization method and system
Through the load aggregator rolling operation optimization method, the implicit Euler format linearized air conditioning model is combined with multiple constraint optimization to solve the problem of insufficient performance of the air conditioning regulation strategy and achieve more efficient load management and regulation.
Patent Information
- Application Number
- CN202411224466.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
It is difficult to effectively improve the performance of air-conditioning control strategies with existing technology, especially in the face of uncertainty in outdoor temperature and market environment. The control strategies are not complex and flexible enough.
The load aggregator rolling operation optimization method is used to establish a second-order thermal parameter model of the controllable air-conditioning load by receiving air-conditioning related data, and linearize it using the implicit Euler format, combined with a variety of optimization constraints (such as power balance, storage energy, renewable energy and user thermal comfort constraints), and output the rolling operation optimization results of the load aggregator.
It significantly improves the effectiveness and robustness of the load aggregator's operation strategy, improves the performance of the air conditioning control strategy, and can handle multiple uncertain factors more accurately.
Smart Images

Figure CN118761233A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of energy optimization operation, and in particular to a method and system for optimizing the rolling operation of a load aggregator. Background Art
[0002] Growing environmental problems and energy crises have put forward greater demands for more efficient and economical load operation methods. Air-conditioning loads have the characteristics of thermal energy storage and controllability, and are important flexible resources in the distribution system. However, how to transform this flexible load into an actual controllable resource is a key technical challenge. The operating characteristics of the air-conditioning load are described by a set of nonlinear ordinary differential-algebraic equations. Transitional simplification will affect the degree of participation of the air-conditioning load in the operation and regulation process, but the modeling accuracy and complexity of the balanced air-conditioning load are still faced. On the other hand, the current control strategy considering controllable air-conditioning loads essentially utilizes the adjustable characteristics of user thermal comfort. However, the uncertainty factors in actual operation, such as outdoor temperature, market environment, etc., will significantly affect the performance of the air-conditioning regulation strategy. This feature is often overlooked in existing research. Summary of the invention
[0003] The technical problem to be solved by the present invention is how to improve the performance of air conditioning control strategy.
[0004] In a first aspect, the purpose of the present invention can be achieved by the following technical solution: a method for optimizing the rolling operation of a load aggregator, the method comprising the following steps: Receiving air conditioning related data, inputting the air conditioning related data into a pre-established second-order thermal parameter model of a controllable air conditioning load, linearizing the second-order thermal parameter model using an implicit Euler format, and obtaining a linearized second-order thermal parameter model; The pre-established load aggregator operation optimization model takes minimizing the operating cost as the goal, obtains the objective function, sets multiple optimization constraints, combines the optimization uncertainty of the linearized second-order thermal parameter model, solves the objective function of the load aggregator operation optimization model, and outputs the load aggregator rolling operation optimization result.
[0005] In combination with the first aspect, in certain implementations of the first aspect, the method further includes: the pre-established second-order thermal parameter model of the controllable air-conditioning load is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w ( t )for t The wall dimension of the moment; T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; or for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in t The switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status.
[0006] In combination with the first aspect, in some implementations of the first aspect, the method further includes: the process of linearizing the second-order thermal parameter model using the implicit Euler format to obtain the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, T ind,init , T a,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively.
[0007] In combination with the first aspect, in some implementations of the first aspect, the method further includes: the pre-established load aggregator operation optimization model takes minimizing the operation cost as the goal, and obtains an objective function, which can be obtained: (11) In the formula, P b,k ( t )and P s,k ( t ) are respectively the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F For the total operating cost.
[0008] In combination with the first aspect, in certain implementations of the first aspect, the method also includes: the multiple optimization constraints include: power balance constraints, aggregator and main grid transaction constraints, energy storage constraints, renewable energy constraints, air conditioning load constraints and user thermal comfort constraints.
[0009] In combination with the first aspect, in some implementations of the first aspect, the method further includes: the power balance constraint and the aggregator and main network transaction constraint are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) express t The moment k Uncontrollable load of a load aggregator; P s,k ( t ) express t The moment k The amount of electricity sold by load aggregators to the main grid; P b,k ( t ) express t The moment k The amount of electricity purchased by a load aggregator from the main grid; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator; S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature.
[0010] In combination with the first aspect, in some implementations of the first aspect, the method further includes: a process of solving the objective function of the load aggregator operation optimization model and outputting a load aggregator rolling operation optimization result: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, e represents the prediction error of the uncertainty variable; e rd , e a , e b , e d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), Pd,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), C b,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( ) 、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( ) 、C b,2 ( ) 、P d,2 ( ),Right now: (twenty one) (twenty two) (twenty three) (twenty four) Will - The optimization result at time 1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for -1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1 Optimize the resulting wall temperature at all times; for -1 hour optimization of indoor temperature Spend; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula, F t During the rolling optimization process t The operating cost at the moment is solved by solving the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and we get The running status distribution at the moment. After the solution is completed, judge Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established.
[0011] In a second aspect, in order to achieve the above-mentioned object, the present invention discloses a load aggregator rolling operation optimization system, comprising: A model linearization module is used to receive air conditioning related data, input the air conditioning related data into a pre-established second-order thermal parameter model of a controllable air conditioning load, and linearize the second-order thermal parameter model using an implicit Euler format to obtain a linearized second-order thermal parameter model; The rolling operation optimization module is used to obtain the objective function of the pre-established load aggregator operation optimization model with the goal of minimizing the operation cost, set multiple optimization constraints, and combine the optimization uncertainty of the linearized second-order thermal parameter model to solve the objective function of the load aggregator operation optimization model, and output the load aggregator rolling operation optimization result.
[0012] In conjunction with the second aspect, in certain implementations of the second aspect, the system further includes: a second-order thermal parameter model of the controllable air-conditioning load pre-established in the model linear module is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w ( t )for t The wall dimension of the moment; T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; or for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in tThe switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status; The implicit Euler format is used in the model linear module to linearize the second-order thermal parameter model. The process of obtaining the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, T ind,init , T a,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively; The load aggregation business operation optimization model pre-established in the rolling operation optimization module takes minimizing the operation cost as the goal, and obtains the objective function, which can be obtained: (11) In the formula, P b,k ( t )and P s,k ( t ) are the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F is the total operating cost; The various optimization constraints in the rolling operation optimization module include: power balance constraints, aggregator and main network transaction constraints, energy storage constraints, renewable energy constraints, air conditioning load constraints and user thermal comfort constraints; The power balance constraints within the rolling operation optimization module and the transaction constraints between aggregators and the main network are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) express t The moment k Uncontrollable load of a load aggregator; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator; S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature; The rolling operation optimization module solves the objective function of the load aggregator operation optimization model and outputs the process of obtaining the load aggregator rolling operation optimization result: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, e represents the prediction error of the uncertainty variable; e rd , e a , e b , e d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), P d,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), Cb,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( ) 、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( ) 、C b,2 ( ) 、P d,2 ( ),Right now: (twenty one) (twenty two) (twenty three) (twenty four) Will - The optimization result at time 1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for - 1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1Optimize the resulting wall temperature at all times; for -1 Optimize the resulting indoor temperature at all times; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula, F t During the rolling optimization process t The operating cost at the moment is solved by solving the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and we get The running status distribution at the moment is solved. After the solution is completed, it is judged Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established.
[0013] Beneficial effects of the present invention: In view of the uncertain factors in the actual operation of air conditioners, such as outdoor temperature, market environment, etc., the present invention accurately establishes a dynamic model of controllable air-conditioning load and uses rolling optimization to deal with multiple uncertainties, effectively improving the effectiveness and robustness of the load aggregator's operation strategy and significantly improving the performance of the air-conditioning control strategy. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, for those skilled in the art, other drawings can be obtained based on these drawings without creative work. Figure 1 It is a flow chart of the load aggregator rolling operation optimization method of the present invention; Figure 2 Schematic diagrams of two groups of uncontrollable load curves used in an embodiment of the present invention; Figure 3 Schematic diagram of the rolling optimization process of the total operating cost in an embodiment of the present invention; Figure 4 It is a composition diagram of the load aggregator rolling operation optimization system of the present invention; Figure 5 It is a structural diagram of the load aggregator rolling operation optimization system of the present invention. DETAILED DESCRIPTION
[0015] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0016] Embodiment 1: The following is an introduction to the relevant terms involved in the embodiments of the present application: The implicit Euler method, also known as the backward Euler method, is a method of numerical solution based on implicit formulas. Implicit formulas cannot be solved directly, and generally require the use of the explicit Euler formula to obtain the initial value, and then use the implicit Euler formula to iteratively solve. Therefore, the implicit formula is more complex than the explicit formula, but has better stability.
[0017] like Figure 1 As shown, a method for optimizing the rolling operation of a load aggregator comprises the following steps: S101: receiving air-conditioning related data, inputting the air-conditioning related data into a pre-established second-order thermal parameter model of a controllable air-conditioning load, linearizing the second-order thermal parameter model using an implicit Euler format, and obtaining a linearized second-order thermal parameter model; Among them, the pre-established second-order thermal parameter model of the controllable air-conditioning load is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w ( t )for t The wall temperature at the moment;T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; or for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in t The switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status.
[0018] Furthermore, the implicit Euler format is used to linearize the second-order thermal parameter model, and the process of obtaining the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, T ind,init , Ta,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively.
[0019] S102: For a pre-established load aggregator operation optimization model, the operation cost is minimized to obtain an objective function, multiple optimization constraints are set, and the objective function of the load aggregator operation optimization model is solved in combination with the optimization uncertainty of the linearized second-order thermal parameter model, and the load aggregator rolling operation optimization result is output.
[0020] Among them, the pre-established load aggregator operation optimization model takes minimizing the operation cost as the goal, and obtains the objective function, which can be obtained: (11) In the formula, P b,k ( t )and P s,k ( t ) are respectively the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively the load aggregators in t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F For the total operating cost.
[0021] Furthermore, the various optimization constraints include: power balance constraints, aggregator and main grid transaction constraints, energy storage constraints, renewable energy constraints, air conditioning load constraints, and user thermal comfort constraints.
[0022] In this embodiment, the power balance constraints and the transaction constraints between the aggregator and the main network are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) expresst The moment k Uncontrollable load of a load aggregator; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator; S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature.
[0023] Specifically, the objective function of the load aggregator operation optimization model is solved, and the process of outputting the load aggregator rolling operation optimization result is obtained: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, e represents the prediction error of the uncertainty variable; e rd , e a , e b , e d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), P d,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), C b,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( )、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( ) 、C b,2 ( ) 、P d,2 ( ),Right now: (twenty one) (twenty two) (twenty three) (twenty four) Will - The optimization result at time 1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for - 1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1 Optimize the resulting wall temperature at all times; for -1 Optimize the resulting indoor temperature at all times; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula,F t During the rolling optimization process t Solve the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and obtain The running status distribution at the moment. After the solution is completed, judge Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established.
[0024] Specifically, the present invention is further described below by way of embodiments: Embodiment 2: In the second aspect, as Figure 4 As shown, in order to achieve the above-mentioned purpose, the present invention discloses a load aggregator rolling operation optimization system, comprising: The model linearization module 11 is used to receive air conditioning related data, input the air conditioning related data into a pre-established second-order thermal parameter model of a controllable air conditioning load, and linearize the second-order thermal parameter model using an implicit Euler format to obtain a linearized second-order thermal parameter model; The rolling operation optimization module 12 is used to obtain the objective function of the pre-established load aggregator operation optimization model with the goal of minimizing the operation cost, set multiple optimization constraints, combine the optimization uncertainty of the linearized second-order thermal parameter model, solve the objective function of the load aggregator operation optimization model, and output the load aggregator rolling operation optimization result.
[0025] In combination with the second aspect, in some implementations of the second aspect, the system further includes: a second-order thermal parameter model of the controllable air-conditioning load pre-established in the model linear module 11 is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w (t )for t The wall dimension of the moment; T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; or for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in t The switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status; The implicit Euler format is used in the model linearization module 11 to linearize the second-order thermal parameter model. The process of obtaining the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, Tind,init , T a,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively; The load aggregation business operation optimization model pre-established in the rolling operation optimization module 12 takes minimizing the operation cost as the goal, and obtains the objective function, which can be obtained: (11) In the formula, P b,k ( t )and P s,k ( t ) are respectively the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F is the total operating cost; The various optimization constraints in the rolling operation optimization module 12 include: power balance constraints, aggregator and main grid transaction constraints, energy storage constraints, renewable energy constraints, air conditioning load constraints and user thermal comfort constraints; The power balance constraints in the rolling operation optimization module 12 and the transaction constraints between the aggregator and the main network are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) express t The moment k Uncontrollable load of a load aggregator; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator;S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature; The rolling operation optimization module 12 solves the objective function of the load aggregator operation optimization model and outputs the process of obtaining the load aggregator rolling operation optimization result: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, e represents the prediction error of the uncertainty variable; e rd , e a , e b , e d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), P d,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), C b,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( ) 、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( )、C b,2 ( ) 、P d,2 ( ),Right now: (twenty one) (twenty two) (twenty three) (twenty four) Will - The optimization result at time 1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for - 1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1 Optimize the resulting wall temperature at all times; for -1 Optimize the resulting indoor temperature at all times; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula, F t During the rolling optimization process t Solve the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and obtain The running status distribution at the moment. After the solution is completed, judge Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established. Figure 5 Take the system shown in the figure as an example, the load curve of rolling update is as follows Figure 2 As shown in Figure 2, the running cost of rolling optimization is Figure 3 shown.
[0026] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present disclosure. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0027] The above shows and describes the basic principles, main features and advantages of the present disclosure. Those skilled in the art should understand that the present disclosure is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present disclosure. Without departing from the spirit and scope of the present disclosure, the present disclosure may have various changes and improvements, and these changes and improvements fall within the scope of the present disclosure to be protected.
Claims
1. A method for optimizing the rolling operation of a load aggregator, It is characterized in that The following steps are involved: Receiving air conditioning related data, inputting the air conditioning related data into a pre-established second-order thermal parameter model of a controllable air conditioning load, linearizing the second-order thermal parameter model using an implicit Euler format, and obtaining a linearized second-order thermal parameter model; The pre-established load aggregator operation optimization model takes minimizing the operating cost as the goal, obtains the objective function, sets multiple optimization constraints, combines the optimization uncertainty of the linearized second-order thermal parameter model, solves the objective function of the load aggregator operation optimization model, and outputs the load aggregator rolling operation optimization result.
2. A method for optimizing the rolling operation of a load aggregator according to claim 1, It is characterized in that The pre-established second-order thermal parameter model of the controllable air-conditioning load is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w ( t )for t The wall dimension of the moment; T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; η for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in t The switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status.
3. A method for optimizing the rolling operation of a load aggregator according to claim 2, It is characterized in that The process of linearizing the second-order thermal parameter model using the implicit Euler format to obtain the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, T ind,init , T a,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively.
4. A method for optimizing the rolling operation of a load aggregator according to claim 3, It is characterized in that The pre-established load aggregator operation optimization model aims to minimize the operation cost, and obtains the objective function: (11) In the formula, P b,k ( t )and P s,k ( t ) are the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F For the total operating cost.
5. A method for optimizing the rolling operation of a load aggregator according to claim 4, It is characterized in that The multiple optimization constraints include: power balance constraints, aggregator and main grid transaction constraints, renewable energy constraints, energy storage constraints, air conditioning load constraints and user thermal comfort constraints.
6. A method for optimizing the rolling operation of a load aggregator according to claim 5, It is characterized in that The power balance constraints and aggregator and mainnet transaction constraints are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) express t The moment k Uncontrollable load of a load aggregator; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator; S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature.
7. A method for optimizing the rolling operation of a load aggregator according to claim 4, It is characterized in that The process of solving the objective function of the load aggregator operation optimization model and outputting the load aggregator rolling operation optimization result: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, ε represents the prediction error of the uncertainty variable; ε rd , ε a , ε b , ε d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), P d,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), C b,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( ) 、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( ) 、C b,2 ( ) 、P d,2 ( ),Right now: (21) (22) (23) (24) Will The optimization result at time -1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for - 1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1 Optimize the resulting wall temperature at all times; for -1 Optimize the resulting indoor temperature at all times; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula, F t During the rolling optimization process t The operating cost at the moment is solved by solving the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and we get The running status distribution at the moment is solved. After the solution is completed, it is judged Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established.
8. A load aggregator rolling operation optimization system, It is characterized in that include: A model linearization module is used to receive air conditioning related data, input the air conditioning related data into a pre-established second-order thermal parameter model of a controllable air conditioning load, and linearize the second-order thermal parameter model using an implicit Euler format to obtain a linearized second-order thermal parameter model; The rolling operation optimization module is used to obtain the objective function of the pre-established load aggregator operation optimization model with the goal of minimizing the operation cost, set multiple optimization constraints, and combine the optimization uncertainty of the linearized second-order thermal parameter model to solve the objective function of the load aggregator operation optimization model, and output the load aggregator rolling operation optimization result.
9. A load aggregator rolling operation optimization system according to claim 8, It is characterized in that The second-order thermal parameter model of the controllable air conditioning load pre-established in the model linear module is as follows: (1) (2) (3) (4) (5) (6) In the formula, C a and C w are the heat storage coefficients of indoor air and wall respectively; T ind ( t )for t The indoor temperature at the moment; T w ( t )for t The wall dimension of the moment; T a ( t )for t The outdoor temperature at the time; R ind is the thermal resistance of the building; R ind-w is the thermal resistance between the indoor environment and the wall; R w-a is the thermal resistance between the wall and the outdoor environment; Q a-ind ( t )for t The amount of heat exchange between the outdoor environment and the indoor environment at all times; Q w-ind ( t ) for t The heat exchange between the indoor environment and the wall at all times; Q a-w ( t ) for t The heat exchange between the outdoor environment and the wall at all times; η for the energy efficiency of air conditioning; P rated is the rated energy consumption of the air conditioner; Q ACL ( t ) is the cooling energy consumption of the air conditioner; S ACL ( t ) is the air conditioner in t The switch status at the moment, S ACL ( t )=1 means the air conditioner is on, otherwise S ACL ( t ) = 0, where equations (1) and (2) correspond to the energy conservation equations of indoor temperature and wall, and equations (3) to (6) correspond to the changes in heat exchange caused by ambient temperature and switch status; The implicit Euler format is used in the model linear module to linearize the second-order thermal parameter model. The process of obtaining the linearized second-order thermal parameter model is as follows: (7) (8) (9) (10) Among them, ∆ t To adjust the time interval, T ind,init , T a,init , T w,init are the initial values of indoor temperature, outdoor temperature and wall temperature respectively.
10. A load aggregator rolling operation optimization system according to claim 9, It is characterized in that The load aggregation business operation optimization model pre-established in the rolling operation optimization module takes the minimization of operation cost as the goal, and obtains the objective function, and obtains: (11) In the formula, P b,k ( t )and P s,k ( t ) are respectively the load aggregators in t Time passes k Each node buys and sells electricity to the main network; C b,k ( t )and C s,k ( t ) are respectively t Time passes k The price at which each node buys and sells electricity to the main network; N a is the number of aggregated loads; N t To control the number of intervals; F is the total operating cost; The various optimization constraints in the rolling operation optimization module include: power balance constraints, aggregator and main network transaction constraints, energy storage constraints, renewable energy constraints, air conditioning load constraints and user thermal comfort constraints; The power balance constraints within the rolling operation optimization module and the transaction constraints between aggregators and the main network are as follows: (12) (13) (14) (15) In the formula, P d,k ( t ) express t The moment k Uncontrollable load of a load aggregator; P g,k ( t ) express t The moment k The discharge capacity of the energy storage of each load aggregator; S grid,k ( t ) express t The moment k The interaction status between each load aggregator and the main network; P PV,k ( t ) express t The moment k PV power of each load aggregator; Indicates k The maximum interaction power between a load aggregator and the main network; The renewable energy constraint is: (16) In the formula, P PV,rated,k For the k The rated power of the PV of each load aggregator; I rd,k ( t )for t Light intensity at the time; For the k The rated irradiance of the PV panels of the load aggregators; The energy storage constraint is: (17) (18) In the formula, and is the maximum discharge and charge power of the energy storage; S BESS ( t )for t The charging and discharging status of energy storage at all times; W BESS ( t )for t The capacity of energy storage at any time; is the maximum capacity of energy storage; The air conditioning load constraints are formulas (7) to (10); The user thermal comfort constraint is: (19) In the formula, and is the lower and upper limits of the indoor temperature; and are the lower and upper limits of the wall temperature; The rolling operation optimization module solves the objective function of the load aggregator operation optimization model and outputs the process of obtaining the load aggregator rolling operation optimization result: Initialize the parameters and generate the true value of the uncertainty data as follows: (20) In the formula, ε represents the prediction error of the uncertainty variable; ε rd , ε a , ε b , ε d They are the prediction errors of light intensity, ambient temperature, electricity purchase price and uncontrollable load respectively; Data1 represents the set of predicted values of uncertain variables in the day-ahead stage, and Data2 represents the precise values of uncertain variables in the real-time operation stage; I rd,1 ( t ), T a,1 ( t ), C b,1 ( t ), P d,1 ( t ) are the predicted values of sunlight intensity, ambient temperature, electricity price and uncontrollable load in the day-ahead period respectively; I rd,2 ( t ), T a,2 ( t ), C b,2 ( t ), P d,2 ( t ) are the precise values of light intensity, ambient temperature, electricity price and uncontrollable load in the real-time operation stage; set up = +1, change the I rd,1 ( ), T a,1 ( ) 、C b,1 ( ) 、P d,1 ( ) is replaced with the value in Data2 I rd,2 ( ), T a,2 ( ) 、C b,2 ( ) 、P d,2 ( ),Right now: (21) (22) (23) (24) Will - The optimization result at time 1 is added with constraints, namely: (25) In the formula, and They are - 1. Optimize the purchased and sold electricity at the moment; for - 1. The energy storage discharge power obtained by optimization at moment 1; for - 1. The optimized air conditioner switch status at moment 1; for - 1. The energy storage charging and discharging state obtained by optimizing at the moment; for -1 Optimize the resulting wall temperature at all times; for -1 Optimize the resulting indoor temperature at all times; for - 1. The energy storage capacity obtained by optimization at moment 1; for - 1. The interaction status between the load aggregator and the main network obtained by optimization at the moment; Will t < The running cost at the moment is removed from the objective function, that is: (26) In the formula, F t During the rolling optimization process t The operating cost at the moment is solved by solving the optimization problem corresponding to equations (1) to (19) and (25) with equation (26) as the objective function, and we get The running status distribution at the moment is solved. After the solution is completed, it is judged Is it satisfied? > N t -1, if yes, the rolling optimization process ends; if no, the objective function is re-established.
Citation Information
Patent Citations
real time parameter identification method of air-conditioning belonged building second order equivalent thermal parameter model
CN105159085A
Virtual aggregator optimization regulation and control method based on model predictive control
CN116029424A
Method and device for realizing cooperative operation by master-slave game in low-carbon comprehensive energy park
CN117495606A
System frequency modulation method and system for thermostatically controlled load cluster, and electronic device and storage medium
WO2023160110A1