Transformer management method and system based on RCM, electronic equipment and storage medium

The transformer status prediction model based on the LSTM algorithm solves the problem of inaccurate evaluation of transformer operating status under traditional management methods, realizes scientific transformer fault prediction and maintenance planning, and improves maintenance efficiency and power system stability.

CN118761441APending Publication Date: 2024-10-11이너 몽골리아 일렉트릭 파워 그룹 컴퍼니 리미티드 이너 몽골리아 일렉트릭 파워 리서치 인스티튜트 브랜치
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410809798.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-11

Smart Images

  • Figure CN118761441A_ABST
    Figure CN118761441A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides an RCM-based transformer management method and system, electronic equipment and a storage medium, and belongs to the field of transformer detection. The transformer management method comprises the following steps: acquiring operation data of a current transformer, and preprocessing the operation data to obtain target operation data; and inputting the target operation data into a pre-constructed transformer state prediction model, so that the transformer state prediction model predicts the operation state of the transformer in a period of time in the future, and the pre-constructed transformer state prediction model is constructed based on an LSTM algorithm. According to the technical scheme, the prediction model is constructed by adopting the LSTM algorithm, the long-term dependency relationship in the data can be captured, and the prediction accuracy is improved; by predicting the operation state of the transformer, potential faults can be found in advance, and a scientific basis is provided for maintenance and management of the transformer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of transformer detection, and in particular to a transformer management method, system, electronic device and storage medium based on RCM. Background Art

[0002] With the increasing demand for electricity and the continuous expansion of the power grid, the reliability, stability and safety of transformers are crucial to the stable operation of the power system.

[0003] Traditional transformer management usually relies on fixed maintenance cycles, such as regular overhauls. However, this approach cannot accurately reflect the actual operating status and health of the transformer. Some transformers may experience performance degradation or failures in advance due to factors such as operating environment and load changes, and regular maintenance may not be able to detect these problems in time. Excessive maintenance of transformers in good operating condition not only increases maintenance costs, but may also cause unnecessary damage to the transformer itself. At the same time, for transformers that really need maintenance, insufficient maintenance may cause failures, further affecting the stable operation of the power system. Moreover, traditional transformer management often lacks sufficient data support, making it difficult to accurately assess the operating status of the transformer. This results in maintenance decisions often relying on experience rather than scientific analysis, increasing the uncertainty and risk of decision-making. When a transformer fails, traditional management methods usually take a long time to troubleshoot and repair the fault. This not only prolongs the power outage time, but may also affect the operation of the entire power system. Summary of the invention

[0004] The purpose of the embodiments of the present invention is to provide a transformer management method, system, electronic device and storage medium based on RCM, which are used to completely or at least partially solve the problems existing in the above-mentioned prior art.

[0005] In order to achieve the above object, an embodiment of the present invention provides a transformer management method based on RCM, comprising:

[0006] Collecting the operating data of the current transformer and preprocessing the operating data to obtain target operating data;

[0007] The target operating data is input into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operating state of the transformer in a future period of time, wherein the pre-built transformer state prediction model is constructed based on the LSTM algorithm.

[0008] Optionally, collecting the operating data of the current transformer and preprocessing the operating data to obtain target operating data includes:

[0009] The operating data of the current transformer is at least cleaned and normalized to eliminate noise and outliers and obtain target operating data, wherein the operating data at least includes key parameters such as voltage, current, temperature and load rate.

[0010] The process of pre-building a transformer state prediction model based on the LSTM algorithm includes:

[0011] Collect the pre-processed historical operation data of the transformer;

[0012] Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer;

[0013] According to the characteristics of the transformer's historical operating data, the learning rate, batch size, and number of iterations of the transformer state prediction model are set;

[0014] The transformer state prediction model is trained using the preprocessed historical operation data of the transformer, and the parameters of the transformer state prediction model are continuously optimized and adjusted until the model converges.

[0015] Optionally, the transformer state prediction model predicts the operating state of the transformer in the future according to the following formula:

[0016] O t =σ(W 0 [h t-1 ,x t ]+b 0 )

[0017] h t =o t *tan h(C t )

[0018] In the formula, O t is the input coefficient, σ represents the sigmoid function, W 0 Weight, b 0 represents the bias coefficient, h t-1 is the output of the transformer state prediction model for the transformer operation data input at time t-1, x t represents the transformer operation data input into the transformer state prediction model at the current time t, h t is the output of the transformer state prediction model for the transformer operation data input at time t, tanh represents the tanh function, C t Indicates the status of the information that is retained.

[0019] Optionally, the transformer management method further includes:

[0020] According to the prediction results of the transformer status prediction model, early warning of potential transformer failures is issued, and the maintenance priority of the transformer is determined according to the severity and probability of the failure;

[0021] A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

[0022] On the other hand, the present invention also provides a transformer management system based on RCM, comprising:

[0023] A collection unit, used for collecting the operation data of the current transformer and preprocessing the operation data to obtain target operation data;

[0024] A prediction unit is used to input the target operating data into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operating state of the transformer in a future period of time, wherein the pre-built transformer state prediction model is constructed based on an LSTM algorithm.

[0025] Optionally, the transformer management system further includes a construction unit, configured to:

[0026] Collect the pre-processed historical operation data of the transformer;

[0027] Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer;

[0028] According to the characteristics of the transformer's historical operating data, the learning rate, batch size, and number of iterations of the transformer state prediction model are set;

[0029] The transformer state prediction model is trained using the preprocessed historical operation data of the transformer, and the parameters of the transformer state prediction model are continuously optimized and adjusted until the model converges.

[0030] Optionally, the transformer management system further includes an early warning unit, which is used to:

[0031] According to the prediction results of the transformer status prediction model, early warning of potential transformer failures is issued, and the maintenance priority of the transformer is determined according to the severity and probability of the failure;

[0032] A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

[0033] On the other hand, the present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned transformer management method when executing the program.

[0034] On the other hand, the present invention further provides a non-transitory computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the steps of the transformer management method described above when executed by a processor.

[0035] Through the above technical solution, the LSTM algorithm is used to build a prediction model, which can capture the long-term dependencies in the data and improve the accuracy of the prediction. By predicting the operating status of the transformer, potential faults can be discovered in advance, providing a scientific basis for the maintenance and management of the transformer.

[0036] Other features and advantages of the embodiments of the present invention will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The accompanying drawings are used to provide a further understanding of the embodiments of the present invention and constitute a part of the specification. Together with the following specific implementations, they are used to explain the embodiments of the present invention, but do not constitute a limitation on the embodiments of the present invention. In the accompanying drawings:

[0038] Figure 1 is an implementation flow chart of a transformer management method based on RCM provided by an embodiment of the present invention;

[0039] Figure 2 It is a structural diagram of a transformer management system based on RCM provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0040] The specific implementation of the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present invention, and is not used to limit the embodiment of the present invention.

[0041] See also Figure 1 As shown, it is an implementation flow chart of a transformer management method based on RCM provided by an embodiment of the present invention, including the following execution steps:

[0042] Step 100: Collect operating data of the current transformer and pre-process the operating data to obtain target operating data.

[0043] Specifically, when executing step 100, the following steps can be specifically performed: at least data cleaning and normalization processing are performed on the operating data of the current transformer to eliminate noise and outliers, and obtain target operating data, wherein the operating data at least includes key parameters such as voltage, current, temperature and load rate.

[0044] Step 101: input the target operation data into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operation state of the transformer in a future period of time.

[0045] Among them, the pre-built transformer state prediction model is built based on the LSTM algorithm.

[0046] In some implementations, the process of pre-building a transformer state prediction model based on the LSTM algorithm includes the following steps:

[0047] S1: Collect the historical operation data of the transformer after preprocessing;

[0048] S2: Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer;

[0049] S3: According to the characteristics of the historical operation data of the transformer, the learning rate, batch size and number of iterations of the transformer state prediction model are set;

[0050] S4: Using the preprocessed historical operation data of the transformer to train the transformer state prediction model, and continuously optimizing and adjusting the parameters of the transformer state prediction model until the model converges.

[0051] In some implementations, the transformer state prediction model predicts the operating state of the transformer in the future according to the following formula:

[0052] O t =σ(W 0 [h t-1 ,x t ]+b 0 )

[0053] h t =o t *tan h(C t )

[0054] In the formula, O t is the input coefficient, σ represents the sigmoid function, W 0 Weight, b 0 represents the bias coefficient, h t-1 is the output of the transformer state prediction model for the transformer operation data input at time t-1, x trepresents the transformer operation data input into the transformer state prediction model at the current time t, h t is the output of the transformer state prediction model for the transformer operation data input at time t, tanh represents the tanh function, C t Indicates the status of the information that is retained.

[0055] in, f t =σ(W f ·[h t-1 , X t ]+b f ),i t =σ(W i ·[h t-1 , X t ]+b i ); In the formula, C t Indicates the state of the retained information, h t-1 is the output of the transformer state prediction model for the transformer operation data input at time t-1, x t represents the transformer operation data input into the transformer state prediction model at the current time t, h t is the output of the transformer state prediction model for the transformer operation data input at time t, tanh represents the tanh function, and W c , W i , W f represents the weight, b c , b i , b f represents the bias coefficient, represents the input state, σ represents the sigmoid function, C t-1 represents the information state retained at time t-1, f t represents the forgetting coefficient, i t Represents the input coefficient.

[0056] It should be understood that the transformer state prediction model predicts the operating state of the transformer in the future period of time including the fault probability and fault type of each transformer.

[0057] In some embodiments, the transformer management method further includes: providing an early warning of a potential fault of the transformer according to a prediction result of the transformer state prediction model, and determining a maintenance priority of the transformer according to the severity and probability of occurrence of the fault;

[0058] A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

[0059] The technical effects achieved by this application are as follows:

[0060] The LSTM algorithm is used to build a prediction model, which can capture long-term dependencies in the data and improve the accuracy of the prediction. By predicting the operating status of the transformer, potential faults can be discovered in advance, providing a scientific basis for the maintenance management of the transformer. The maintenance plan is formulated according to the prediction results, which can reasonably allocate maintenance resources and improve maintenance efficiency.

[0061] See also Figure 2 As shown, it is a structural diagram of a transformer management system based on RCM provided by an embodiment of the present invention, including:

[0062] The acquisition unit 200 is used to acquire the operation data of the current transformer and pre-process the operation data to obtain target operation data;

[0063] The prediction unit 201 is used to input the target operating data into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operating state of the transformer in a future period of time, wherein the pre-built transformer state prediction model is constructed based on the LSTM algorithm.

[0064] In some embodiments, see Figure 2 As shown, the transformer management system further includes a construction unit 202, which is used to:

[0065] Collect the pre-processed historical operation data of the transformer;

[0066] Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer;

[0067] According to the characteristics of the transformer's historical operating data, the learning rate, batch size, and number of iterations of the transformer state prediction model are set;

[0068] The transformer state prediction model is trained using the preprocessed historical operation data of the transformer, and the parameters of the transformer state prediction model are continuously optimized and adjusted until the model converges.

[0069] In some embodiments, see Figure 2 As shown, the transformer management system further includes an early warning unit 203, which is used to:

[0070] According to the prediction results of the transformer status prediction model, early warning of potential transformer failures is issued, and the maintenance priority of the transformer is determined according to the severity and probability of the failure;

[0071] A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

[0072] On the other hand, the present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned transformer management method when executing the program.

[0073] On the other hand, the present invention further provides a non-transitory computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the steps of the transformer management method described above when executed by a processor.

[0074] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0075] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0076] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0077] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0078] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0079] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0080] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0081] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0082] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.

Claims

1. A transformer management method based on RCM, characterized in that: include: Collecting the operating data of the current transformer and preprocessing the operating data to obtain target operating data; The target operating data is input into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operating state of the transformer in a future period of time, wherein the pre-built transformer state prediction model is constructed based on the LSTM algorithm.

2. The transformer management method according to claim 1, characterized in that: The collecting of the current transformer operation data and preprocessing the operation data to obtain target operation data includes: The operating data of the current transformer is at least cleaned and normalized to eliminate noise and outliers and obtain target operating data, wherein the operating data at least includes key parameters such as voltage, current, temperature and load rate.

3. The transformer management method according to claim 1, characterized in that: The process of pre-building a transformer state prediction model based on the LSTM algorithm includes: Collect the pre-processed historical operation data of the transformer; Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer; According to the characteristics of the transformer's historical operating data, the learning rate, batch size, and number of iterations of the transformer state prediction model are set; The transformer state prediction model is trained using the preprocessed historical operation data of the transformer, and the parameters of the transformer state prediction model are continuously optimized and adjusted until the model converges.

4. The transformer management method according to claim 1, characterized in that: The transformer state prediction model predicts the operating state of the transformer in the future according to the following formula: ABOUT t =σ(W0[h t-1 ,x t ]+b0) h t =o t *tanh(C t ) In the formula, O t is the input coefficient, σ represents the sigmoid function, W0 is the weight, b0 represents the bias coefficient, h t-1 is the output of the transformer state prediction model for the transformer operation data input at time t-1, x t represents the transformer operation data input into the transformer state prediction model at the current time t, h t is the output of the transformer state prediction model for the transformer operation data input at time t, tanh represents the tanh function, C t Indicates the status of the information that is retained.

5. The transformer management method according to claim 1, characterized in that: The transformer management method further comprises: According to the prediction results of the transformer status prediction model, early warning of potential transformer failures is issued, and the maintenance priority of the transformer is determined according to the severity and probability of the failure; A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

6. A transformer management system based on RCM, characterized in that: include: A collection unit, used for collecting the operation data of the current transformer and preprocessing the operation data to obtain target operation data; A prediction unit is used to input the target operating data into a pre-built transformer state prediction model, so that the transformer state prediction model predicts the operating state of the transformer in a future period of time, wherein the pre-built transformer state prediction model is constructed based on an LSTM algorithm.

7. The transformer management system according to claim 6, characterized in that: The transformer management system further comprises a construction unit, configured to: Collect the pre-processed historical operation data of the transformer; Construct the network structure of the transformer state prediction model, including input layer, hidden layer and output layer; According to the characteristics of the transformer's historical operating data, the learning rate, batch size, and number of iterations of the transformer state prediction model are set; The transformer state prediction model is trained using the preprocessed historical operation data of the transformer, and the parameters of the transformer state prediction model are continuously optimized and adjusted until the model converges.

8. The transformer management system according to claim 6, characterized in that: The transformer management system further comprises an early warning unit, which is used to: According to the prediction results of the transformer status prediction model, early warning of potential transformer failures is issued, and the maintenance priority of the transformer is determined according to the severity and probability of the failure; A corresponding maintenance plan is formulated for transformers with different maintenance priorities, wherein the maintenance plan at least includes maintenance time, maintenance content and maintenance personnel.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps of the transformer management method according to any one of claims 1 to 5 are implemented.

10. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the transformer management method according to any one of claims 1 to 5 are implemented.

Citation Information

Patent Citations

  • Transformer fault prediction method, device and apparatus

    CN110766059A

  • Transformer state maintenance method and equipment taking reliability as center

    CN115792461A

  • Transformer fault prediction method and system

    CN116881806A

  • Moisture diagnosis apparatus for insulator using characteristic of moisture movement in power transformer, and risk evaluation method using characteristic of mois ...

    KR101293404B1

  • Transformer DGA data prediction method based on multi-dimensional time sequence frame convolution lstm

    US20210089900A1