Power transmission and transformation project carbon emission checking method and system
By determining the carbon emission verification model and calculating the carbon emission factor in the power transmission and transformation project, combined with multi-level data statistics, the problems of information acquisition limitations and data lag in the existing technology are solved, and the carbon emissions of the main equipment of the transmission line are realized. Accurate display of data flow and improvement of statistical efficiency.
Patent Information
- Application Number
- CN202410742391.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-11
- Publication Date
- 2024-10-11
AI Technical Summary
The existing technology has limitations in information acquisition and lag in energy statistical data in carbon emission verification of power transmission and transformation projects. It is difficult to accurately count primary energy consumption data, which affects the accuracy and promotion and application of carbon emission accounting.
Provide a carbon emission verification method and system for power transmission and transformation projects. By determining the carbon emission verification model, collecting carbon emission activity data at the data boundary, calculating carbon emission factors, and calculating the total carbon emissions based on these factors, it combines engineering construction, electrical Main equipment and office models perform multi-level data statistics to visually display typical results.
It breaks through the limitations of information acquisition, avoids the lag of energy statistical data, improves the statistical efficiency of primary energy consumption data, solves the problem of statistical efficiency differences in carbon emission data among energy consuming enterprises, and realizes the carbon emission analysis of main equipment of transmission lines. Accurate representation of emissions data flows.
Smart Images

Figure CN118761489A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of carbon emissions, and in particular to a method and system for verifying carbon emissions of power transmission and transformation projects. Background Art
[0002] Electricity accounts for about 20% of final energy consumption. Due to the spatial mismatch of my country's power resources, long-distance power transmission is an important part of the power cost structure, and large-scale regional power transmission has achieved the optimal allocation of energy resources. In the future, the total electricity consumption of the whole society and the scale of inter-provincial and inter-regional power transmission will continue to grow, and the construction of power transmission and transformation projects has greatly promoted the scale of power transmission. On the one hand, the power energy system can accept more renewable energy and reduce the emission of greenhouse gases and atmospheric pollutants; on the other hand, the power transmission network improves the security of the power grid and the utilization level of thermal power generating units, thereby reducing the pressure on the entire power energy system to reduce emissions. As a result, large-scale power transmission will change the development mode of regional energy use and carbon emissions in the future. Therefore, in the context of the continued expansion of the construction of power transmission and transformation projects, the carbon emission verification of AC transmission line projects is the key to clarifying the source of carbon emissions in the project, and it is also an important means to explore carbon emission reduction in power transmission and transformation projects.
[0003] At present, the existing technologies include: 1) a method and system for carbon emission accounting of transformer products, which obtains the allocation coefficient through multi-dimensional computing power and performs carbon emission accounting on multi-level carbon source data to obtain the accounting results, and corrects the carbon emission accounting results based on the intelligent accounting analysis model and gives the product carbon optimization plan, thereby improving the accuracy of carbon emission accounting of transformer products; its data acquisition is based on computing power acquisition, and it fails to clearly distinguish the material flow and energy flow information in each construction link, and the network crawling information is quite different, and the workload of manual screening in the later stage is large; 2) a method and device for determining carbon footprint based on the industrial Internet, equipment and medium, which uses the identification resolution system of the industrial Internet to identify and resolve the carbon data identification corresponding to the stage with carbon data, so as to obtain the carbon emission accounting results of transformer products. And obtain information on each stage of carbon emissions; 3) A method and device for determining product carbon emissions based on blockchain, which receives product data information and uses a carbon emissions calculation model to determine the carbon emissions results, and uses blockchain to store and keep confidential information to improve the accuracy of emission results; However, most product construction links and data information are not published, and the reliability of the data is questionable; 4) A product carbon footprint accounting model and service platform construction method, which inputs the product and field data and background data of each stage to be accounted for through the data receiving end, and calculates the product carbon emissions based on the basic database; However, this method has the process of inputting information and models, and then recalculating, which increases the accounting workload, and the data retrieval process should have been omitted in the one-time input process.
[0004] As can be seen from the above, in the existing technology, except for specific products, most of the models for carbon emission accounting are obtained through network information, and their matching and accuracy are difficult to ensure. In addition, the data statistics of related products are often based on macro data statistics, and most of them are converted according to primary energy consumption. The data obtained are difficult to clearly define the characteristics of carbon emissions, which limits the actual promotion and application. Summary of the invention
[0005] The purpose of the present invention is to overcome the limitations of carbon emission information acquisition in the prior art and to avoid the lag of energy statistical data, thereby improving the statistical efficiency of primary energy consumption data. In order to achieve the above purpose, the present invention provides a method and system for verifying carbon emissions in power transmission and transformation projects.
[0006] In a first aspect, an embodiment of the present invention provides a method for verifying carbon emissions of a power transmission and transformation project, comprising:
[0007] Determine the carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project;
[0008] Determining the data boundary of the carbon emission verification model according to the type of the carbon emission verification model, wherein the type includes at least an engineering construction model and an electrical main equipment model;
[0009] Collecting carbon emission activity data of the data boundary, and determining a carbon emission factor corresponding to the data boundary based on the carbon emission activity data;
[0010] The carbon emission amount of each carbon emission verification model is calculated according to the carbon emission factor, and the total carbon emission amount is calculated based on the carbon emission amount.
[0011] Preferably, the data boundary of the engineering construction model includes a design model data boundary and a construction model data boundary, and the construction model data boundary includes a building engineering model data boundary and an installation engineering model data boundary;
[0012] The data boundary of the main electrical equipment model includes a transformer model data boundary and a GIS model data boundary.
[0013] Preferably, the total carbon emissions are obtained using the following formula:
[0014] C=C1+C2+C3
[0015] Among them, C represents the total carbon emissions, C1 represents the carbon emissions of the engineering construction model, C2 represents the carbon emissions of the main electrical equipment model, and C3 represents the carbon emissions of the office model.
[0016] Preferably, the carbon emissions of the engineering construction model are obtained using the following formula:
[0017] C1=CD +C S
[0018] Among them, C1 represents the carbon emissions of the engineering construction model, C D represents the carbon emissions consumed by the design model data boundary of the engineering construction model, C S Represents the carbon emissions consumed by the construction model data boundary of the engineering construction model.
[0019] Preferably, the carbon emissions consumed by the construction model data boundary of the engineering construction model are obtained using the following formula:
[0020] C S =C 建筑 +C 安装
[0021] Among them, C S represents the carbon emissions consumed by the construction model data boundary of the engineering construction model, C 建筑 The carbon emissions consumed by the construction model data boundary, C 安装 The carbon emissions consumed by the installation engineering model data boundary representing the construction model data boundary.
[0022] Preferably, the carbon emissions consumed by the construction model data boundary of the construction model data boundary are obtained by using the following formula:
[0023] C 建筑 =C E1 +C M1
[0024] Among them, C 建筑 The carbon emissions consumed by the construction model data boundary, C E1 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model, C M1 Represents the total carbon emissions of material flows consumed by the data boundary of the building engineering model;
[0025] The total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model are obtained using the following formula:
[0026]
[0027] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
[0028] Preferably, the carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary are obtained by using the following formula:
[0029] C 安装 =C E2 +C M2
[0030] Among them, C 安装 The carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary, C E2 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model, C M2 Represents the total carbon emissions of material flows consumed by the data boundary of the installation engineering model;
[0031] The total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model are obtained using the following formula:
[0032]
[0033] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
[0034] Preferably, the following formula is used to obtain the carbon emissions of electric energy consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary:
[0035]
[0036] Among them, C E Indicates the carbon emissions of electric energy consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, E j represents the electric energy consumed in the jth electric energy consumption stage, EF e represents the carbon emission factor of electric energy, num1 represents the number of electric energy consumption stages;
[0037] The carbon emissions of materials consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary are obtained using the following formula:
[0038]
[0039] Among them, C M Indicates the carbon emissions of materials consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, Mj represents the amount of material consumed by the jth material, EF j represents the carbon emission factor of the jth material, and num2 represents the material consumption quantity.
[0040] Preferably, the carbon emissions of the electrical main equipment model are obtained using the following formula:
[0041] C2=C E3 +C M3
[0042] Among them, C2 represents the carbon emissions of the main electrical equipment model, C E3 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the electrical main equipment model, C M3 Indicates the total carbon emissions of material flows consumed by the data boundary of the electrical main equipment model;
[0043] The following formula is used to obtain the total carbon emissions of coal, oil and gas consumed within the data boundary of the electrical main equipment model:
[0044]
[0045] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i represents the lower calorific value of the i-th energy source, and n represents the number of energy types;
[0046] The carbon emissions of the office model are obtained using the following formula:
[0047]
[0048] Among them, C3 represents the carbon emissions of the office model, E i represents the i-th energy consumption for office use, EF ei represents the carbon emission factor of the i-th energy consumption, and m represents the amount of energy consumption used in the office.
[0049] In a second aspect, an embodiment of the present invention provides a carbon emission verification system for a power transmission and transformation project, which is applicable to the carbon emission verification method as described above, and includes:
[0050] A carbon emission verification model determination module is used to determine the carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project;
[0051] A data boundary determination module, used to determine the data boundary of the carbon emission verification model according to the type of the carbon emission verification model, wherein the type includes at least an engineering construction model and an electrical main equipment model;
[0052] A carbon emission factor determination module, configured to collect carbon emission activity data of the data boundary, and determine the carbon emission factor corresponding to the data boundary based on the carbon emission activity data;
[0053] The total carbon emission calculation module is used to calculate the carbon emissions of each carbon emission verification model according to the carbon emission factor, and calculate the total carbon emissions based on the carbon emissions.
[0054] Compared with the prior art, the method and system for verifying carbon emissions of power transmission and transformation projects in the embodiment of the present invention have the following beneficial effects: it integrates most typical power transmission and transformation project models, and combines the energy usage statistics in each link with calculations, so as to form a carbon emission data stream for the main equipment of the transmission line, and intuitively display typical example results, breaking through the limitations of previous information acquisition, avoiding the lag of energy statistical data, and solving the problem of statistical efficiency differences of primary energy consumption data by energy-consuming enterprises. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 It is a flow chart of a method for verifying carbon emissions of a power transmission and transformation project according to an embodiment of the present invention;
[0056] Figure 2 This is a data boundary diagram of a carbon emission verification model for a power transmission and transformation project according to an embodiment of the present invention;
[0057] Figure 3 It is a data boundary diagram of a building engineering model according to an embodiment of the present invention;
[0058] Figure 4 It is a data boundary diagram of an installation engineering model according to an embodiment of the present invention;
[0059] Figure 5 is a data boundary schematic diagram of a transformer model according to an embodiment of the present invention;
[0060] Figure 6 This is a data boundary diagram of the GIS model according to an embodiment of the present invention;
[0061] Figure 7 It is a structural schematic diagram of a carbon emission verification system for a power transmission and transformation project according to an embodiment of the present invention. DETAILED DESCRIPTION
[0062] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0063] like Figure 1 As shown, an embodiment of the present invention provides a method for verifying carbon emissions of a power transmission and transformation project, comprising the steps of:
[0064] S1. Determine the carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project;
[0065] The scope of carbon emission verification for power transmission and transformation projects can mainly refer to the three scopes of carbon emission accounting, especially the part related to electricity. Specifically, it includes:
[0066] 1) Direct greenhouse gas emissions
[0067] This part mainly focuses on greenhouse gas emissions directly generated during the operation of the power transmission and transformation project itself, such as emissions from fuel combustion or physical and chemical production processes of equipment (such as transformers, switch stations, etc.). However, since the power transmission and transformation project itself does not directly involve the process of fuel combustion to generate electricity, the emissions in this part are relatively small, and may mainly be concentrated in the small amount of emissions during the maintenance and operation of the equipment.
[0068] 2) Indirect greenhouse gas emissions from electricity generation
[0069] This is the focus of the carbon emission verification of power transmission and transformation projects. This part covers the greenhouse gas emissions generated by the purchased electricity used in power transmission and transformation projects. For power transmission and transformation projects, purchased electricity is mainly used for equipment operation, lighting, ventilation, etc. Therefore, the source and quality of purchased electricity (such as whether it comes from clean energy) will directly affect the emissions in this part. When conducting the verification of this part, it is necessary to consider the losses in the power transmission and distribution process, as well as the emissions generated by the upstream activities of power suppliers (such as power production).
[0070] 3) Indirect emissions from various activities in the upstream and downstream of the value chain
[0071] For power transmission and transformation projects, this part of emissions may include emissions from upstream and downstream activities related to project construction, equipment procurement, maintenance, etc. However, these emissions are usually not directly included in the scope of carbon emission verification of power transmission and transformation projects unless they have a significant impact on the overall carbon emissions of the project.
[0072] In general, when conducting carbon emission verification for power transmission and transformation projects, this embodiment mainly focuses on the second part of emissions, that is, indirect greenhouse gas emissions generated by purchased electricity. At the same time, emissions from the first and third parts are also considered, but their weights may be relatively low.
[0073] Furthermore, the carbon emission verification model of this embodiment includes at least an engineering construction model and an electrical main equipment model.
[0074] S2. Determine the data boundary of the carbon emission verification model according to the type of the carbon emission verification model;
[0075] Specifically, Figure 2As shown, the types include at least an engineering construction model and an electrical main equipment model; the data boundary of the engineering construction model includes a design model data boundary and a construction model data boundary, and the construction model data boundary includes a building engineering model data boundary and an installation engineering model data boundary; the data boundary of the electrical main equipment model includes a transformer model data boundary and a GIS model data boundary.
[0076] Furthermore, if Figure 3 As shown, the construction engineering model data boundary includes the main production engineering model data boundary, the auxiliary production engineering model data boundary and the single engineering model data boundary related to the site; the main production engineering model data boundary includes the main production buildings, distribution device buildings, water supply systems and fire protection systems; the auxiliary production engineering model data boundary includes auxiliary production buildings, station area buildings, station area greening and special structures; the single engineering model data boundary related to the site includes foundation treatment, off-site roads, construction precipitation and temporary construction.
[0077] Specifically, the data boundaries of the main production building model include the main control and communication building, relay room and station power distribution device room; the data boundaries of the main control and communication building model include general civil engineering, water supply and drainage, heating, ventilation and air conditioning and lighting; the data boundaries of the relay room model include 500kV relay room, 220kV relay room and main transformer 35kV relay room; the data boundaries of the station power distribution device room model include 500kV station power distribution room and station power distribution device room. The data boundary of the distribution equipment building model includes the main transformer system, support structure and equipment foundation, station transformer system, low-voltage capacitor, cable trench, low-voltage reactor, lightning rod tower and fence and floor part; the data boundary of the main transformer system model includes support structure and foundation, main transformer equipment foundation, main transformer oil pit and pebbles, firewall and accident oil pool; the data boundary of the support structure and equipment foundation model includes 500kV frame and foundation, 500kV equipment support and foundation, 220kV frame and foundation, 220kV equipment support and foundation and 35kV equipment support and foundation; the data boundary of the station transformer system model includes firewall, accident oil pool and station transformer equipment and foundation. The data boundary of the water supply system model includes the station area domestic water pipeline. The data boundary of the fire protection system model includes the station area fire protection pipeline, fire protection equipment, special fire protection system, fire protection pool, accident oil discharge system, foam fire protection room, rain shower valve room and station area fire protection pipeline.
[0078] Specifically, the auxiliary production building model data boundary includes the guardhouse. The station area building model data boundary includes the guardhouse, station area roads and squares, station area drainage, site leveling, station area roads and squares, walls and gates; the station area drainage model data boundary includes drainage pipes, manholes, sewage regulation pools, sewage treatment equipment and sewage reuse pools. The station area greening model data boundary includes station area greening and other parts. The special structure model data boundary includes retaining walls and retaining walls, flood control drainage ditches, slope protection and off-site slope protection.
[0079] Specifically, the data boundary of the off-site road model includes road pavement, earthwork, retaining wall, bridge and culvert, and off-site drainage. The data boundary of the temporary construction model includes temporary construction water source.
[0080] Furthermore, if Figure 4 As shown, the installation engineering model data boundary includes the main production engineering model data boundary, the auxiliary production engineering model data boundary and the single project model data boundary related to the site; the main production engineering model data boundary includes the main transformer system, distribution device, reactive power compensation, control and DC system, station power system, cable and grounding, communication and telecontrol system and whole station debugging; the auxiliary production engineering model data boundary includes maintenance and repair equipment; the single project model data boundary related to the site includes the power supply outside the station.
[0081] Specifically, the main transformer system model data boundary includes a 500kV main transformer. The distribution device model data boundary includes indoor distribution devices and outdoor distribution devices; the indoor distribution device model data boundary includes 500kV indoor distribution devices and 220kV indoor distribution devices; the outdoor distribution device model data boundary includes 35kV outdoor distribution devices, 10kV outdoor distribution devices and 35kV outdoor distribution devices. The reactive compensation model data boundary includes low-voltage capacitors and low-voltage reactors; the low-voltage capacitor model data boundary includes 35kV low-voltage capacitors; the low-voltage reactor model data boundary includes 35kV low-voltage reactors. The control and DC system model data boundary includes computer monitoring system, relay protection, DC system and UPS, intelligent auxiliary control system, online monitoring system and auxiliary equipment and facilities; the computer monitoring system model data boundary includes computer monitoring system, intelligent equipment and synchronous clock. The station power system model data boundary includes station transformers, station distribution devices and station area lighting. The data boundary of the cable and grounding model includes the whole station grounding and power cables; the data boundary of the whole station grounding model includes power cables, control cables, cable auxiliary facilities and cable fire protection. The data boundary of the communication and telecontrol system model includes the communication system and the telecontrol and billing system. The data boundary of the whole station debugging model includes subsystem debugging, whole set startup debugging and whole set debugging.
[0082] Specifically, the data boundary of the inspection and repair equipment model includes the off-site communication line. The data boundary of the off-site power supply model includes the off-site power supply line.
[0083] Furthermore, if Figure 5 As shown, the transformer model data boundary includes insulation production, coil winding, oil tank and accessories production, core assembly production, body assembly, lead assembly, final assembly and testing.
[0084] Furthermore, if Figure 6 As shown, the GIS model data boundary includes installation, cleaning, inflation, airtightness inspection and testing.
[0085] It should be noted that the data boundary of the carbon emission verification model in this embodiment can be adjusted according to the actual project.
[0086] S3. Collect carbon emission activity data at the data boundary, and determine the carbon emission factor corresponding to the data boundary based on the carbon emission activity data;
[0087] The sources of carbon emission activity data collection include at least power transmission and transformation project design drawings, construction project quantity lists, installation project quantity lists and engineering quantity quotas. This embodiment collects the boundary resource and energy consumption activity data of the model data of each level of the power transmission and transformation project from the units providing relevant technical information such as power transmission and transformation project design drawings, construction project quantity lists, installation project quantity lists and engineering quantity quotas.
[0088] Furthermore, according to the resource and energy consumption activity data of the model data boundaries at all levels of the power transmission and transformation project, the carbon emission factors corresponding to the model data boundaries at all levels are determined. Among them, the carbon emission factors include cradle-to-gate carbon emission factors and cradle-to-grave carbon emission factors.
[0089] S4. Calculate the carbon emissions of each carbon emission verification model based on the carbon emission factor, and calculate the total carbon emissions based on the carbon emissions.
[0090] Specifically, the total carbon emissions are obtained using the following formula:
[0091] C=C1+C2+C3
[0092] Among them, C represents the total carbon emissions, C1 represents the carbon emissions of the engineering construction model, C2 represents the carbon emissions of the electrical main equipment model, and C3 represents the carbon emissions of the office model. It should be noted that the carbon emissions of the office model mainly involve the carbon emissions generated by the office and travel of personnel.
[0093] Furthermore, the carbon emissions of the engineering construction model are obtained using the following formula:
[0094] C1=C D +C S
[0095] Among them, C1 represents the carbon emissions of the engineering construction model, C D represents the carbon emissions consumed by the design model data boundary of the engineering construction model, C S Represents the carbon emissions consumed by the construction model data boundary of the engineering construction model.
[0096] Specifically, the following formula is used to obtain the carbon emissions consumed by the construction model data boundary of the engineering construction model:
[0097] C S =C 建筑 +C 安装
[0098] Among them, C S represents the carbon emissions consumed by the construction model data boundary of the engineering construction model, C 建筑 The carbon emissions consumed by the construction model data boundary, C 安装 The carbon emissions consumed by the installation engineering model data boundary representing the construction model data boundary.
[0099] Furthermore, the carbon emissions consumed by the construction model data boundary of the construction model data boundary are obtained using the following formula:
[0100] C 建筑 =C E1 +C M1
[0101] Among them, C 建筑 The carbon emissions consumed by the construction model data boundary, C E1 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model, C M1 Represents the total carbon emissions of material flows consumed by the data boundary of the building engineering model;
[0102] Specifically, the following formula is used to obtain the total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model:
[0103]
[0104] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
[0105] Furthermore, the carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary are obtained using the following formula:
[0106] C 安装 =C E2 +C M2
[0107] Among them, C 安装 The carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary, C E2 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model, C M2 Represents the total carbon emissions of material flows consumed by the data boundary of the installation engineering model;
[0108] Specifically, the following formula is used to obtain the total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model:
[0109]
[0110] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
[0111] It should be noted that the following formula is used to obtain the carbon emissions of electric energy consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary:
[0112]
[0113] Among them, C E Indicates the carbon emissions of electric energy consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, E j represents the electric energy consumed in the jth electric energy consumption stage, EF e represents the carbon emission factor of electric energy, num1 represents the number of electric energy consumption stages; it can be understood that the carbon emission factor of electric energy EF e is a fixed value;
[0114] The following formula is used to obtain the carbon emissions of materials consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary:
[0115]
[0116] Among them, C MIndicates the carbon emissions of materials consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, M j represents the amount of material consumed by the jth material, EF j represents the carbon emission factor of the jth material, and num2 represents the material consumption quantity.
[0117] Furthermore, the carbon emissions of the main electrical equipment model are obtained using the following formula:
[0118] C2=C E3 +C M3
[0119] Among them, C2 represents the carbon emissions of the main electrical equipment model, C E3 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the electrical main equipment model, C M3 Indicates the total carbon emissions of material flows consumed by the data boundary of the electrical main equipment model;
[0120] Specifically, the following formula is used to obtain the total carbon emissions of coal, oil and gas consumed at the data boundary of the electrical main equipment model:
[0121]
[0122] Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i represents the lower calorific value of the i-th energy source, and n represents the number of energy types;
[0123] Furthermore, the carbon emissions of the office model are obtained using the following formula:
[0124]
[0125] Among them, C3 represents the carbon emissions of the office model, E i represents the i-th energy consumption for office use, EF ei represents the carbon emission factor of the i-th energy consumption, and m represents the amount of energy consumption used in the office.
[0126] This embodiment starts classification calculation from the bottom model data boundary, and gradually performs sum calculation to the higher model data boundary to obtain carbon emissions at each level of classification. Moreover, if the bottom model data boundary does not exist, the data at this level will be automatically classified into the upper model data boundary according to the data number, and so on.
[0127] It should be noted that after step S4, the following steps are also included:
[0128] Based on the calculated carbon emissions, the carbon emissions icon is displayed under each level of title, and the data that accounts for more than 90% and less than 5% under each level of title are marked according to the overall data situation for data verification; at the same time, the data that accounts for less than 1% of the total carbon emissions will be discarded according to the overall data situation.
[0129] Furthermore, according to the verified carbon emissions at each level, a report and carbon emission certificate under each level is generated. The data that accounts for more than 90% and less than 5% under each level are marked in the report, and corresponding carbon emission recommendations are given.
[0130] The embodiment of the present invention provides a method for verifying carbon emissions of power transmission and transformation projects, which integrates most typical power transmission and transformation project models, and combines the energy usage statistics in each link with calculations, so as to form a data stream of carbon emissions of main equipment of the transmission line, and intuitively display typical example results, breaking through the limitations of previous information acquisition, avoiding the lag of energy statistical data, and solving the problem of statistical efficiency differences of primary energy consumption data by energy-consuming enterprises.
[0131] like Figure 7 As shown, an embodiment of the present invention provides a carbon emission verification system for a power transmission and transformation project, which is applicable to the carbon emission verification method as described above, and includes:
[0132] A carbon emission verification model determination module 1 is used to determine a carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project;
[0133] The data boundary determination module 2 is used to determine the data boundary of the carbon emission verification model according to the type of the carbon emission verification model, and the type includes at least an engineering construction model and an electrical main equipment model;
[0134] A carbon emission factor determination module 3 is used to collect carbon emission activity data at the data boundary and determine the carbon emission factor corresponding to the data boundary based on the carbon emission activity data;
[0135] The total carbon emission calculation module 4 is used to calculate the carbon emission of each carbon emission verification model according to the carbon emission factor, and calculate the total carbon emission based on the carbon emission.
[0136] It should be noted that each module in the above-mentioned carbon emission verification system for power transmission and transformation projects can be fully or partially implemented through software, hardware and their combination. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules. For the specific definition of a carbon emission verification system for power transmission and transformation projects, please refer to the definition of a carbon emission verification method for power transmission and transformation projects above. The two have the same functions and effects, which will not be repeated here.
[0137] In summary, the embodiment of the present invention is a method and system for verifying carbon emissions of power transmission and transformation projects. It integrates most typical power transmission and transformation project models, and combines the energy usage statistics in each link with calculations to form a data stream of carbon emissions from the main equipment of the transmission line, and intuitively displays typical example results. It breaks through the limitations of previous information acquisition, avoids the lag of energy statistical data, and solves the problem of statistical efficiency differences of primary energy consumption data by energy-consuming enterprises.
[0138] Each embodiment in this specification is described in a progressive manner, and the same or similar parts of each embodiment can be directly referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment. It should be noted that the technical features of the above-mentioned embodiments can be combined arbitrarily. In order to make the description concise, all possible combinations of the technical features in the above-mentioned embodiments are not described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0139] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A method for verifying carbon emissions from power transmission and transformation projects. It is characterized in that include: Determine the carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project; Determining the data boundary of the carbon emission verification model according to the type of the carbon emission verification model, wherein the type includes at least an engineering construction model and an electrical main equipment model; Collecting carbon emission activity data of the data boundary, and determining a carbon emission factor corresponding to the data boundary based on the carbon emission activity data; The carbon emission amount of each carbon emission verification model is calculated according to the carbon emission factor, and the total carbon emission amount is calculated based on the carbon emission amount.
2. The carbon emission verification method according to claim 1, It is characterized in that The data boundary of the engineering construction model includes a design model data boundary and a construction model data boundary, and the construction model data boundary includes a building engineering model data boundary and an installation engineering model data boundary; The data boundary of the main electrical equipment model includes a transformer model data boundary and a GIS model data boundary.
3. The carbon emission verification method according to claim 1, It is characterized in that The total carbon emissions are obtained using the following formula: C=C 1 +C 2 +C 3 Among them, C represents the total carbon emissions, C 1 represents the carbon emissions of the engineering construction model, C 2 represents the carbon emissions of the main electrical equipment model, C 3 Represents the carbon emissions of the office model.
4. The carbon emission verification method according to claim 3, It is characterized in that The carbon emissions of the engineering construction model are obtained using the following formula: C 1 =C D +C S Among them, C 1 represents the carbon emissions of the engineering construction model, C D represents the carbon emissions consumed by the design model data boundary of the engineering construction model, C S Represents the carbon emissions consumed by the construction model data boundary of the engineering construction model.
5. The carbon emission verification method according to claim 4, It is characterized in that The carbon emissions consumed by the construction model data boundary of the engineering construction model are obtained using the following formula: C S =C 建筑 +C 安装 Among them, C S represents the carbon emissions consumed by the construction model data boundary of the engineering construction model, C 建筑 The carbon emissions consumed by the construction model data boundary, C 安装 The carbon emissions consumed by the installation engineering model data boundary representing the construction model data boundary.
6. The carbon emission verification method according to claim 5, It is characterized in that The carbon emissions consumed by the construction model data boundary of the construction model data boundary are obtained using the following formula: C 建筑 =C E1 +C M1 Among them, C 建筑 The carbon emissions consumed by the construction model data boundary, C E1 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model, C M1 Represents the total carbon emissions of material flows consumed by the data boundary of the building engineering model; The total carbon emissions of coal, oil and gas consumed within the data boundary of the building engineering model are obtained using the following formula: Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
7. The carbon emission verification method according to claim 5, It is characterized in that The carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary are obtained using the following formula: C 安装 =C E2 +C M2 Among them, C 安装 The carbon emissions consumed by the installation engineering model data boundary of the construction model data boundary, C E2 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model, C M2 Represents the total carbon emissions of material flows consumed by the data boundary of the installation engineering model; The total carbon emissions of coal, oil and gas consumed within the data boundary of the installation project model are obtained using the following formula: Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i It represents the lower calorific value of the i-th energy source, and n represents the number of energy types.
8. The carbon emission verification method according to claim 5, It is characterized in that The following formula is used to obtain the carbon emissions of electric energy consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary: Among them, C E Indicates the carbon emissions of electric energy consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, E j represents the electric energy consumed in the jth electric energy consumption stage, EF e represents the carbon emission factor of electric energy, num1 represents the number of electric energy consumption stages; The carbon emissions of materials consumed by the building engineering model data boundary, the installation engineering model data boundary, or the electrical main equipment model data boundary are obtained using the following formula: Among them, C M Indicates the carbon emissions of materials consumed by the building engineering model data boundary, installation engineering model data boundary, or electrical main equipment model data boundary, M j represents the amount of material consumed by the jth material, EF j represents the carbon emission factor of the jth material, and num2 represents the material consumption quantity.
9. The carbon emission verification method according to claim 3, It is characterized in that The carbon emissions of the electrical main equipment model are obtained using the following formula: C 2 =C E3 +C M3 Among them, C 2 represents the carbon emissions of the main electrical equipment model, C E3 represents the total carbon emissions of coal, oil and gas consumed within the data boundary of the electrical main equipment model, C M3 Indicates the total carbon emissions of material flows consumed by the data boundary of the electrical main equipment model; The total carbon emissions of coal, oil and gas consumed within the data boundary of the electrical main equipment model are obtained using the following formula: Among them, F i represents the consumption of the i-th energy, C i represents the potential emission factor of the i-th energy source, B i represents the carbon oxidation rate of the i-th energy source, LCV i represents the lower calorific value of the i-th energy source, and n represents the number of energy types; The carbon emissions of the office model are obtained using the following formula: Among them, C 3 represents the carbon emissions of the office model, E i represents the i-th energy consumption for office use, EF ei represents the carbon emission factor of the i-th energy consumption, and m represents the amount of energy consumption used in the office.
10. A carbon emission verification system for power transmission and transformation projects, applicable to the carbon emission verification method as claimed in any one of claims 1 to 9, It is characterized in that include: A carbon emission verification model determination module is used to determine the carbon emission verification model based on the carbon emission verification scope of the power transmission and transformation project; A data boundary determination module, used to determine the data boundary of the carbon emission verification model according to the type of the carbon emission verification model, wherein the type includes at least an engineering construction model and an electrical main equipment model; A carbon emission factor determination module, configured to collect carbon emission activity data of the data boundary, and determine the carbon emission factor corresponding to the data boundary based on the carbon emission activity data; The total carbon emission calculation module is used to calculate the carbon emissions of each carbon emission verification model according to the carbon emission factor, and calculate the total carbon emissions based on the carbon emissions.