Intelligent construction site system based on BIM
By using BIM technology, AI, and the Internet of Things in the smart construction site system to create 3D models and real-time monitoring, the problems of unintuitive display, difficulty in finding material sources, and difficulty in adjusting construction tasks in the smart construction site system are solved, achieving high efficiency on the construction site. Management and safety are improved, reducing costs and the risk of project delays.
Patent Information
- Application Number
- CN202410600071.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-15
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing smart construction site systems deal with the problems of unintuitive two-dimensional display, difficulty in finding the source of materials when the material quality is unqualified, inconvenience in adjusting construction tasks, and delays in construction schedules. They fail to effectively solve the problems of opaque labor information, low utilization of equipment resources, and high construction costs. problem.
A BIM-based smart construction site system is used to collect real-life image data through drones to create 3D models, perform collision detection and dynamic adjustment, and realize construction site personnel safety management, safety monitoring, material tracking and project quality scoring. Combining AI and IoT technologies, Monitor and optimize construction progress and quality in real time.
It improves the management level and safety of the construction site, reduces construction costs, ensures precise control of materials and timely completion of construction tasks, avoids extension of the construction period, and enhances construction quality and safety management.
Smart Images

Figure CN118761722A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction site management, and in particular to a BIM-based smart construction site system. Background Art
[0002] With the development of science and technology, intelligent management based on big data has been deeply applied to all walks of life. Taking the construction industry as an example, some scholars have proposed a smart construction site system to manage the construction site. The Chinese patent with application number 202210839857.7 discloses "a smart construction site system based on BIM, the system includes a BIM platform established based on the BIM model and a personnel management module connected to the BIM platform, the personnel management module is used to generate the operation trajectory of the workers; the system also includes a construction equipment management module for monitoring the operation status of the construction equipment; a security module for monitoring abnormal intrusion information at the construction site; a weather forecast module for monitoring meteorological information and issuing early warnings; a video management module for monitoring the construction site scene; a dangerous engineering management module for monitoring the status of foundation pit buildings; and a project node monitoring module for monitoring project progress data. The present invention uses BIM technology to intelligently monitor the construction site, and visually integrates the management of the smart construction site in the BIM platform, effectively improving the management level, construction efficiency and safety of the construction site and reducing the construction cost."
[0003] This comparison document only solves the traditional construction site management model, which often leads to problems such as opaque labor personnel information, untimely information transmission, and low resource utilization of large-scale construction equipment, which in turn leads to delays in construction period, unnecessary investment and waste. The current smart construction site system can better solve the above problems in the construction process of rail transit vehicle bases. However, with the gradual deepening of the application of smart construction sites, the problem of non-intuitive two-dimensional display has gradually emerged. It does not take into account the inconvenience of finding the source of materials when the construction quality is unqualified due to material quality. After the BIM model is created, the model needs to be adjusted synchronously according to the adjustment of the engineering drawings. When the construction tasks of the day are not completed, the construction tasks of the next day need to be adjusted to avoid extension of the construction period. Summary of the invention
[0004] The purpose of the present invention is to provide a BIM-based smart construction site system to solve the problems raised in the above background technology.
[0005] To achieve the above-mentioned object, the present invention provides the following technical solutions: a BIM-based smart construction site system, comprising a BIM model creation unit, wherein the BIM model creation unit is used to perform 3D modeling of the real scene of the construction site based on real-scene image data collected by a drone and engineering drawings, thereby creating a BIM model, and to perform collision detection based on the created BIM model, and to check the engineering drawings and make adjustments based on the inspection results;
[0006] A construction site personnel safety management unit, which is used to perform real-name management and identity recognition on workers entering the construction site, thereby preventing irrelevant people from entering the construction site, and to monitor the physical condition of the workers at work, while monitoring the movement trajectory of the workers, so as to supervise the workers and prevent them from entering risk areas;
[0007] A construction site safety management unit, which is used to detect abnormal behavior of operators and avoid extreme weather risks based on environmental monitoring and weather forecast results, and issue warning information when environmental data in the construction site exceeds the warning threshold;
[0008] A construction site material management unit, which is used to collect and store material information in the construction site warehouse, track and manage the materials in use, and collect and manage relevant information on mechanical equipment in the construction site, and continuously update it as the project progresses;
[0009] The engineering management unit is used to allocate daily construction tasks based on a preset construction period, inspect the construction quality after the daily construction tasks are completed, and score various data of the construction site based on the contents of the smart construction site assessment form after all construction tasks are completed.
[0010] Preferably, the BIM model creation unit includes a construction site real-scene data acquisition module and a BIM model generation module. The construction site real-scene data acquisition module is used to take panoramic photos of the construction site through a drone and analyze and extract the original landform features of the construction site. The BIM model generation module is used to establish a BIM model of the construction site through Smart3D technology based on the real-scene image data and engineering drawing information obtained in the construction site real-scene data acquisition module.
[0011] Preferably, the BIM model creation unit also includes a collision detection module and a dynamic adjustment module. The collision detection module is used to perform collision detection on the BIM model so as to detect unreasonable collision parts in the engineering drawings. The dynamic adjustment module is used to adjust the engineering drawings according to the detection results of the collision detection module. The BIM model can also be adjusted in time according to changes in the engineering drawings to achieve real-time maintenance of the BIM model.
[0012] Preferably, the construction site personnel safety management unit includes a construction site personnel information identification module and a worker physical condition monitoring module. The construction site personnel information identification module is used to register various identity information of the staff in the construction site, and upload the registered information to the constructed database for storage, and identify the staff through facial recognition technology when the staff enters the construction site, and if the recognition result is correct, the YOLO detection technology is used to detect whether the staff are wearing their equipment neatly, and when it is detected that the staff are not wearing their equipment neatly, the staff is reminded by voice broadcast until it is detected that the staff are wearing their equipment neatly. The worker physical condition monitoring module is used to monitor the physical condition of the staff through the smart bracelet worn by the staff, and send alarm information in time when an abnormality occurs.
[0013] Preferably, the construction site personnel safety management unit also includes a construction site risk source update module and a construction site personnel trajectory generation module. The construction site risk source update module is used to collect risk source information found in the construction site according to the construction progress, and timely update and adjust the risk area of the construction site. When the staff approaches the risk area, an alarm is issued through the smart safety helmet worn by the staff to remind the staff to pay attention to safety. The construction site personnel trajectory generation module obtains the location information of the staff in real time through RFID positioning technology, processes and analyzes the collected location information, and displays it on an electronic map, thereby presenting the activity trajectory of the staff.
[0014] Preferably, the construction site safety management unit includes an abnormal behavior detection module, a weather risk avoidance module and a construction site environment monitoring module. The abnormal behavior detection module detects and analyzes the behavior of the construction site staff through the installed full-site coverage and all-weather working cameras, in conjunction with the AI analysis software, so as to judge whether the staff has any illegal work behavior, and when it is judged that the staff has illegal work behavior, the staff is promptly reminded to stop the illegal work behavior through voice broadcast, and the facial image and violation of the staff are recorded, and when there is an illegal behavior that the AI analysis software cannot determine, artificial remote recognition is used for auxiliary judgment. The weather risk avoidance module is used to adjust the construction tasks when the weather forecast result is extreme weather such as typhoon, heavy rain, high temperature, etc., so as to avoid the risk of extreme weather. The construction site environment monitoring module is used to monitor the specific data of PM2.5, PM10, noise, temperature and humidity, and wind speed, and when the monitoring value exceeds the set warning threshold, the warning information is pushed to the management personnel, and the specific information is displayed on the LED display screen installed in the construction site, and the warning threshold is set according to national specifications and local standards.
[0015] Preferably, the construction site material management unit includes a material management module and a mechanical equipment management module. The material management module is used to upload relevant information of materials to a database for storage, and establish a material relationship chain including suppliers, consignees, models, quantities, prices, etc. in the database, and update material prices in real time. Based on the BIM model, the entity's engineering quantity is counted, and then the types and quantities of materials required for the engineering quantity in each stage are counted to ensure accurate control of materials. Through the Internet of Things technology, the entire use process of materials in the construction site is located and tracked, so as to ensure that the materials can arrive at the construction site safely and on time. The mechanical equipment management module is used to upload relevant information of mechanical equipment used in the construction process in the construction site to the database for storage, including the model and operator of the mechanical equipment, and it is continuously updated as the project progresses, and the problems and maintenance conditions found during the staff's inspection of the mechanical equipment are uploaded to the database to characterize the specific conditions of the corresponding mechanical equipment.
[0016] Preferably, the engineering management unit includes a construction task allocation module and a construction progress management module. The construction task allocation module is used to calculate the objective function related to the designed construction period and cost, and its specific calculation formula is as follows:
[0017]
[0018] Where MinimizeF cost represents the cost, D represents the total number of construction processes, c trepresents the daily indirect cost, T represents the construction period, x i Represents the cost of process i, a and b represent different preset proportional factors, i represents process i, calculates the construction period information, and allocates daily construction tasks based on the construction period information. The construction progress management module is used for after the daily construction tasks are completed, the inspectors check the completion of the construction tasks of the day, and upload the inspection data of the day to the database, score the data according to the scoring criteria of the smart construction site assessment form, and when the inspection result is not completed, the corresponding area in the BIM model is marked in red, and the reasons for the incomplete task are summarized by asking the on-site staff, and the construction tasks of the next day are adjusted. The adjustment method is to add the unfinished part of the construction tasks of the day on the original basis. When the inspection result is completed ahead of schedule, the corresponding area in the BIM model is marked in green.
[0019] Preferably, the engineering management unit includes a construction quality inspection module, which is used for inspectors to inspect the construction quality while checking the completion of the day's construction tasks. When quality problems occur, the module sends rectification tasks to the person in charge of the inspection area by taking photos with mobile phones and filling in the quality problems, investigates the causes of the quality problems, and when the causes of the quality problems are related to the quality of materials, holds the suppliers accountable based on the relationship chain constructed in the database, and after the rectification tasks are completed, sends the rectified photos to the inspectors for review, and when the review fails, sends the rectification tasks to the person in charge of the inspection area again until the review is qualified.
[0020] Preferably, the engineering management unit further includes a construction site evaluation module, and the construction site evaluation module 504 is used to score the construction site according to the assessment content and scoring criteria of the smart construction site assessment form after all construction tasks are completed, so as to obtain the total score of the construction site, and calculate the final score of the construction site through the smart construction site evaluation algorithm, and the specific calculation formula is as follows:
[0021]
[0022] In the formula, Q represents the final score of the construction site, K represents the total score of the construction site, m represents the mth time of scoring the inspection data, N represents the total number of times the inspection data is scored, and S m It represents the total score of the mth inspection data, and the construction site is evaluated based on the calculated result. When the calculated result is less than 70, it is evaluated as unqualified; when 70≤calculated result<80, it is evaluated as qualified; when 80≤calculated result<90, it is evaluated as good; when 90≤calculated result, it is evaluated as excellent.
[0023] Compared with the prior art, the beneficial effects of the present invention at least include: the present invention proposes a BIM-based smart construction site system, wherein a BIM model is created by a set BIM model creation unit, and collision detection is performed on the BIM model, so as to detect unreasonable collision parts in the engineering drawings, and the engineering drawings are adjusted based on the detection results, and the BIM model is adjusted synchronously, the physical condition of the staff is monitored by the set construction site personnel safety management unit, and the risk area of the construction site is updated and adjusted in time, and an early warning reminder is issued when the activity trajectory of the staff approaches the risk area, the behavior of the on-site staff of the construction site is detected and analyzed by the set construction site safety management unit, and the risk avoidance of extreme weather is achieved based on the weather forecast results, and the environmental information of the construction site is monitored at the same time, and a relationship chain related to the materials is established by the set construction site material management unit, and the materials are located and tracked for subsequent search, and accurate management and control of the materials is ensured, and the completion status of the daily construction tasks is displayed on the BIM model by the set engineering management unit, and when the construction tasks are not completed, the construction tasks of the next day are adjusted, thereby avoiding the extension of the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the overall process of an embodiment of the present invention;
[0025] Figure 2 A schematic diagram of a unit flow chart for creating a BIM model according to an embodiment of the present invention;
[0026] Figure 3 This is a schematic diagram of the process of the construction site personnel safety management unit according to an embodiment of the present invention;
[0027] Figure 4 This is a schematic diagram of the construction site safety management unit process according to an embodiment of the present invention;
[0028] Figure 5 This is a schematic diagram of the construction site material management unit process according to an embodiment of the present invention;
[0029] Figure 6 The figure is a flow chart of the engineering management unit according to an embodiment of the present invention.
[0030] In the figure: 100, BIM model creation unit; 101, construction site real scene data acquisition module; 102, BIM model generation module; 103, collision detection module; 104, dynamic adjustment module; 200, construction site personnel safety management unit; 201, construction site personnel information identification module; 202, worker physical condition monitoring module; 203, construction site risk source update module; 204, construction site personnel trajectory generation module; 300, construction site safety management unit; 301, abnormal behavior detection module; 302, weather risk avoidance module; 303, construction site environment monitoring module; 400, construction site material management unit; 401, material management module; 402, machinery and equipment management module; 500, project management unit; 501, construction task allocation module; 502, construction progress management module; 503, construction quality inspection module; 504, construction site evaluation module. DETAILED DESCRIPTION
[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] See also Figure 1-6 , the present invention provides a technical solution: a BIM-based smart construction site system, including a BIM model creation unit 100, the BIM model creation unit 100 is used to perform 3D modeling of the real scene of the construction site based on real-scene image data collected by a drone and engineering drawings, thereby creating a BIM model, and perform collision detection based on the created BIM model, check the engineering drawings and make adjustments based on the inspection results;
[0033] The construction site personnel safety management unit 200 is used to perform real-name management and identity recognition on the staff entering the construction site, thereby preventing irrelevant people from entering the construction site, and monitoring the physical condition of the staff at work, while monitoring the movement trajectory of the staff, so as to supervise the staff and prevent the staff from entering the risk area;
[0034] The construction site safety management unit 300 is used to detect abnormal behaviors of operators, and avoid extreme weather risks based on environmental monitoring and weather forecast results, and issue warning information when environmental data in the construction site is higher than the warning threshold;
[0035] The construction site material management unit 400 is used to collect and store material information in the construction site warehouse, track and manage the used materials, and collect and manage the relevant information of the mechanical equipment in the construction site, and continuously update it as the project progresses;
[0036] The engineering management unit 500 is used to allocate daily construction tasks based on a preset construction period, inspect the construction quality after the daily construction tasks are completed, and score various data of the construction site based on the contents of the smart construction site assessment form after all construction tasks are completed.
[0037] The BIM model creation unit 100 includes a construction site real scene data collection module 101 and a BIM model generation module 102. The construction site real scene data collection module 101 is used to take panoramic photos of the construction site through a drone and analyze and extract the original landform features of the construction site. The BIM model generation module 102 is used to establish a BIM model of the construction site through Smart3D technology based on the real scene image data and engineering drawing information obtained in the construction site real scene data collection module 101;
[0038] The BIM model creation unit 100 also includes a collision detection module 103 and a dynamic adjustment module 104. The collision detection module 103 is used to perform collision detection on the BIM model so as to detect unreasonable collision parts in the engineering drawings. The dynamic adjustment module 104 is used to adjust the engineering drawings according to the detection results of the collision detection module 103. The BIM model can also be adjusted in time according to the changes in the engineering drawings to achieve real-time maintenance of the BIM model.
[0039] The construction site personnel safety management unit 200 includes a construction site personnel information identification module 201 and a worker physical condition monitoring module 202. The construction site personnel information identification module 201 is used to register various identity information of the workers in the construction site, and upload the registered information to the constructed database for storage, and identify the workers by facial recognition technology when the workers enter the construction site, and use YOLO detection technology to detect whether the workers are wearing their equipment neatly when the recognition result is correct, and remind the workers by voice broadcast when it is detected that the workers are not wearing their equipment neatly, until it is detected that the workers are wearing their equipment neatly, and the worker physical condition monitoring module 202 is used to monitor the physical condition of the workers through the smart bracelets worn by the workers, and send alarm information in time when abnormalities occur;
[0040] The construction site personnel safety management unit 200 also includes a construction site risk source update module 203 and a construction site personnel trajectory generation module 204. The construction site risk source update module 203 is used to collect risk source information found in the construction site according to the construction progress, and timely update and adjust the risk area of the construction site. When the staff approaches the risk area, the smart safety helmet worn by the staff will sound an alarm to remind the staff to pay attention to safety. The construction site personnel trajectory generation module 204 obtains the position information of the staff in real time through RFID positioning technology, processes and analyzes the collected position information, and displays it on an electronic map, thereby presenting the activity trajectory of the staff;
[0041] The construction site safety management unit 300 includes an abnormal behavior detection module 301, a weather risk avoidance module 302 and a construction site environment monitoring module 303. The abnormal behavior detection module 301 detects and analyzes the behavior of the construction site workers through the installed full-site coverage and all-weather working cameras, in conjunction with the AI analysis software, so as to judge whether the workers have any illegal work behaviors, and when it is judged that the workers have illegal work behaviors, the workers are reminded to stop the illegal work behaviors in time through voice broadcast, and the facial images and illegal situations of the workers are recorded, and the AI analysis software is unable to detect the abnormal behavior. When illegal behaviors are detected, artificial remote identification is used for auxiliary judgment. The weather risk avoidance module 302 is used to adjust the construction tasks when the weather forecast results are extreme weather such as typhoons, heavy rains, high temperatures, etc., so as to avoid the risks of extreme weather. The construction site environment monitoring module 303 is used to monitor the specific data of PM2.5, PM10, noise, temperature, humidity and wind speed, and when the monitoring value exceeds the set warning threshold, the warning information is pushed to the management personnel, and the specific information is displayed on the LED display screen installed in the construction site at the same time, and the warning threshold is set according to national specifications and local standards;
[0042] The construction site material management unit 400 includes a material management module 401 and a mechanical equipment management module 402. The material management module 401 is used to upload relevant information of materials to the database for storage, and establish a material relationship chain including suppliers, consignees, models, quantities, prices, etc. in the database, and update the material prices in real time. Based on the BIM model, the entity's engineering quantity is counted, and then the types and quantities of materials required for the engineering quantity at each stage are counted to ensure accurate control of materials. Through the Internet of Things technology, the entire use process of materials in the construction site is located and tracked, so as to ensure that the materials can arrive at the construction site safely and on time. The mechanical equipment management module 402 is used to upload relevant information of mechanical equipment used in the construction process in the construction site to the database for storage, including the model and operator of the mechanical equipment, and is continuously updated as the project progresses. Problems and maintenance conditions found during the staff's inspection of the mechanical equipment are uploaded to the database to characterize the specific conditions of the corresponding mechanical equipment;
[0043] The project management unit 500 includes a construction task allocation module 501 and a construction progress management module 502. The construction task allocation module 501 is used to calculate the objective function related to the designed construction period and cost. The specific calculation formula is as follows:
[0044]
[0045] Where MinimizeF cost represents the cost, D represents the total number of construction processes, c t represents the daily indirect cost, T represents the construction period, x i represents the cost of process i, a and b represent different preset proportional factors, i represents process i, calculates the construction period information, and allocates the daily construction tasks based on the construction period information. The construction progress management module 502 is used for the inspection personnel to inspect the completion of the construction tasks of the day after the daily construction tasks are completed, and upload the inspection data of the day to the database, and score the data according to the scoring standard of the smart construction site assessment form. When the inspection result is not completed, the corresponding area in the BIM model is marked in red, and the reasons for the incomplete task are summarized by asking the on-site staff, and the construction tasks of the next day are adjusted. The adjustment method is to add the unfinished part of the construction tasks of the day on the original basis. When the inspection result is completed ahead of schedule, the corresponding area in the BIM model is marked in green;
[0046] The engineering management unit 500 includes a construction quality inspection module 503. The construction quality inspection module 503 is used for the inspectors to inspect the construction quality while inspecting the completion of the construction tasks of the day. When quality problems occur, the inspectors take photos with their mobile phones and fill in the quality problems. The module sends rectification tasks to the person in charge of the inspection area, investigates the causes of the quality problems, and when the causes of the quality problems are related to the quality of the materials, holds the supplier accountable based on the relationship chain constructed in the database. After the rectification tasks are completed, the photos after rectification are sent to the inspectors for review. When the review fails, the rectification tasks are sent to the person in charge of the inspection area again until the review passes.
[0047] The engineering management unit 500 also includes a construction site evaluation module 504. The construction site evaluation module 504 is used to score the construction site according to the assessment content and scoring criteria of the smart construction site assessment form after all construction tasks are completed, so as to obtain the total score of the construction site, and calculate the final score of the construction site through the smart construction site evaluation algorithm. The specific calculation formula is as follows:
[0048]
[0049] In the formula, Q represents the final score of the construction site, K represents the total score of the construction site, m represents the mth time of scoring the inspection data, N represents the total number of times the inspection data is scored, and S m It represents the total score of the mth inspection data, and the construction site is evaluated based on the calculated result. When the calculated result is less than 70, it is evaluated as unqualified; when 70≤calculated result<80, it is evaluated as qualified; when 80≤calculated result<90, it is evaluated as good; when 90≤calculated result, it is evaluated as excellent.
[0050] Working principle: The construction site is photographed panoramically through the construction site real-scene data acquisition module 101, and the BIM model of the construction site is established through the BIM model generation module 102 according to the real-scene image data and engineering drawing information obtained in the construction site real-scene data acquisition module 101. The BIM model is subjected to collision detection through the collision detection module 103, and the engineering drawings are adjusted according to the detection results of the collision detection module 103 through the dynamic adjustment module 104. The BIM model can also be adjusted in time according to the changes in the engineering drawings to achieve real-time maintenance of the BIM model. The various identity information of the staff in the construction site is registered through the construction site personnel information identification module 201, and the identity of the staff is identified when the staff enters the construction site. The physical condition of the staff is monitored through the worker physical condition monitoring module 202, and an alarm message is sent in time when an abnormality occurs. The risk source information found in the construction site is collected according to the construction progress through the construction site risk source update module 203, and the risk area of the construction site is updated and adjusted in time. The location information of the staff is obtained in real time through the construction site personnel trajectory generation module 204, and the collected The location information of the workers is processed and analyzed, and displayed on the electronic map, thereby presenting the activity trajectory of the workers. The behavior of the workers on the construction site is detected and analyzed through the abnormal behavior detection module 301. The risk avoidance of extreme weather is achieved through the weather risk avoidance module 302. The environmental data is monitored through the construction site environment monitoring module 303. The material management module 401 establishes a material relationship chain including suppliers, consignees, models, quantities, prices, etc., and the types and quantities of materials required for the engineering volume at each stage are counted to ensure accurate control of materials. The entire use process of materials in the construction site is located and tracked, so as to ensure that the materials can arrive at the construction site safely and on time. The relevant information of the machinery and equipment used in the construction process in the construction site is uploaded to the database for storage through the machinery and equipment management module 402. The daily construction tasks are allocated through the construction task allocation module 501. The completion of the construction tasks of the day is checked through the construction progress management module 502. The construction quality is checked through the construction quality inspection module 503. The construction site is evaluated through the construction site evaluation module 504.
[0051] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0052] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A BIM-based smart construction site system, characterized by: The method comprises a BIM model creation unit (100), wherein the BIM model creation unit (100) is used to perform 3D modeling of a real scene of a construction site based on real-scene image data collected by a drone and engineering drawings, thereby creating a BIM model, and to perform collision detection based on the created BIM model, check the engineering drawings and make adjustments based on the check results; A construction site personnel safety management unit (200), the construction site personnel safety management unit (200) is used to perform real-name management and identity recognition on workers entering the construction site, thereby preventing irrelevant people from entering the construction site, and monitoring the physical condition of the workers at work, while monitoring the movement trajectory of the workers, so as to supervise the workers and prevent them from entering risk areas; A construction site safety management unit (300), the construction site safety management unit (300) is used to detect abnormal behavior of operators, and to avoid extreme weather risks based on environmental monitoring and weather forecast results, and to issue a warning message when environmental data in the construction site is higher than a warning threshold; A construction site material management unit (400), the construction site material management unit (400) is used to collect and store material information in a construction site warehouse, and to track and manage the materials in use, and to collect and manage relevant information on mechanical equipment in the construction site, and to continuously update it as the project progresses; The engineering management unit (500) is used to allocate daily construction tasks based on a preset construction period, inspect the construction quality after the daily construction tasks are completed, and score various data of the construction site based on the contents of the smart construction site assessment form after all construction tasks are completed.
2. The BIM-based smart construction site system according to claim 1, characterized in that: The BIM model creation unit (100) comprises a construction site real-scene data acquisition module (101) and a BIM model generation module (102), wherein the construction site real-scene data acquisition module (101) is used to take panoramic photos of the construction site through an unmanned aerial vehicle and analyze and extract the original landform features of the construction site, and the BIM model generation module (102) is used to establish a BIM model of the construction site through Smart3D technology based on the real-scene image data and engineering drawing information acquired in the construction site real-scene data acquisition module (101).
3. The BIM-based smart construction site system according to claim 1, characterized in that: The BIM model creation unit (100) further comprises a collision detection module (103) and a dynamic adjustment module (104); the collision detection module (103) is used to perform collision detection on the BIM model so as to detect unreasonable collision parts in the engineering drawings; the dynamic adjustment module (104) is used to adjust the engineering drawings according to the detection result of the collision detection module (103); and can also timely adjust the BIM model according to changes in the engineering drawings, thereby realizing real-time maintenance of the BIM model.
4. The BIM-based smart construction site system according to claim 1, characterized in that: The construction site personnel safety management unit (200) comprises a construction site personnel information recognition module (201) and a worker physical condition monitoring module (202). The construction site personnel information recognition module (201) is used to register various identity information of workers in the construction site, and upload the registered information to a constructed database for storage. When the workers enter the construction site, the identity of the workers is recognized by using facial recognition technology. If the recognition result is correct, the YOLO detection technology is used to detect whether the workers are wearing their equipment neatly. If it is detected that the workers are not wearing their equipment neatly, the workers are reminded by voice broadcast until it is detected that the workers are wearing their equipment neatly. The worker physical condition monitoring module (202) is used to monitor the physical condition of the workers through the smart bracelets worn by the workers, and send alarm information in time when abnormalities occur.
5. The BIM-based smart construction site system according to claim 1, characterized in that: The construction site personnel safety management unit (200) further comprises a construction site risk source update module (203) and a construction site personnel trajectory generation module (204). The construction site risk source update module (203) is used to collect risk source information found in the construction site according to the construction progress, and timely update and adjust the risk area of the construction site. When the staff approaches the risk area, an alarm is issued through the smart safety helmet worn by the staff to remind the staff to pay attention to safety. The construction site personnel trajectory generation module (204) obtains the position information of the staff in real time through RFID positioning technology, processes and analyzes the collected position information, and displays it on an electronic map, thereby presenting the activity trajectory of the staff.
6. The BIM-based smart construction site system according to claim 1, characterized in that: The construction site safety management unit (300) comprises an abnormal behavior detection module (301), a weather risk avoidance module (302) and a construction site environment monitoring module (303). The abnormal behavior detection module (301) detects and analyzes the behavior of construction site workers through cameras installed to cover the entire site and work around the clock, in conjunction with AI analysis software, so as to determine whether the workers have any illegal work behaviors. When it is determined that the workers have illegal work behaviors, the workers are promptly reminded to stop the illegal work behaviors through voice broadcasting, and the facial images and illegal situations of the workers are recorded. When AI analysis occurs, When the software cannot determine the violation, manual remote identification is used to assist in the judgment. The weather risk avoidance module (302) is used to adjust the construction tasks when the weather forecast results are extreme weather such as typhoons, heavy rains, high temperatures, etc., so as to achieve risk avoidance of extreme weather. The construction site environment monitoring module (303) is used to monitor the specific data of PM2.5, PM10, noise, temperature and humidity, and wind speed, and when the monitoring value exceeds the set warning threshold, the warning information is pushed to the management personnel, and the specific information is displayed on the LED display screen installed in the construction site. The warning threshold is set according to national specifications and local standards.
7. The BIM-based smart construction site system according to claim 1, characterized in that: The construction site material management unit (400) includes a material management module (401) and a mechanical equipment management module (402). The material management module (401) is used to upload relevant information of materials to a database for storage, and establish a material relationship chain including suppliers, consignees, models, quantities, prices, etc. in the database, and update the material prices in real time. Based on the BIM model, the entity's engineering quantity is counted, and then the types and quantities of materials required for the engineering quantity at each stage are counted to ensure accurate control of materials. Through the Internet of Things technology, the entire use process of materials in the construction site is located and tracked, so as to ensure that the materials can arrive at the construction site safely and on time. The mechanical equipment management module (402) is used to upload relevant information of mechanical equipment used in the construction process in the construction site to the database for storage, including the model and operator of the mechanical equipment, and is continuously updated as the project progresses. Problems and maintenance conditions found by staff during the inspection of mechanical equipment are uploaded to the database to represent the specific conditions of the corresponding mechanical equipment.
8. The BIM-based smart construction site system according to claim 1, characterized in that: The engineering management unit (500) includes a construction task allocation module (501) and a construction progress management module (502). The construction task allocation module (501) is used to calculate the construction period information through the designed construction period-cost related objective function, and allocate daily construction tasks based on the construction period information. The construction progress management module (502) is used for, after the daily construction task is completed, the inspectors will check the completion status of the construction tasks of the day, upload the inspection data of the day to the database, score the data according to the scoring criteria of the smart construction site assessment form, and when the inspection result is not completed, the corresponding area in the BIM model is marked in red, and the reasons for the incomplete task are summarized by asking the on-site staff, and the construction task of the next day is adjusted. The adjustment method is to add the unfinished part of the construction task on the day on the original basis. When the inspection result is completed ahead of schedule, the corresponding area in the BIM model is marked in green.
9. The BIM-based smart construction site system according to claim 1, characterized in that: The engineering management unit (500) includes a construction quality inspection module (503), which is used for the inspection personnel to inspect the construction quality while inspecting the completion of the construction tasks of the day. When quality problems occur, the inspection personnel take photos with their mobile phones and fill in the quality problems, and send rectification tasks to the person in charge of the inspection area, investigate the causes of the quality problems, and when the causes of the quality problems are related to the quality of materials, hold the supplier accountable based on the relationship chain constructed in the database. After the rectification tasks are completed, the photos of the rectification are sent to the inspectors for review, and when the review fails, the rectification tasks are sent to the person in charge of the inspection area again until the review passes.
10. The BIM-based smart construction site system according to claim 1, characterized in that: The engineering management unit (500) further includes a construction site evaluation module (504), which is used to score the construction site according to the assessment content and scoring criteria of the smart construction site assessment form after all construction tasks are completed, so as to obtain the total score of the construction site, and calculate the final score of the construction site through the smart construction site evaluation algorithm, and evaluate the construction site according to the calculation result. When the calculation result is less than 70, the evaluation is unqualified; when 70≤the calculation result<80, the evaluation is qualified; when 80≤the calculation result<90, the evaluation is good; when 90≤the calculation result, the evaluation is excellent.
Citation Information
Patent Citations
Intelligent construction site information processing method and system based on BIM model and application
CN111241618A
Advanced crossing construction method based on combination of virtual model and real models
CN113450453A
Municipal engineering intelligent construction site management system based on BIM technology
CN117575294A
3-Dimensional Space Information Construction Site Management Platform System for IoT-Based Smart Constuction
KR102170748B1
Cited By
Cross-image-source building construction problem automatic tracking system and method
CN118968423A
Bridge construction dynamic three-dimensional risk area monitoring method and system based on monocular 3D detection algorithm
CN119832492A
House building safety monitoring method and system based on visual inspection
CN121582790A
Safety Monitoring Methods and Systems for Buildings Based on Visual Inspection
CN121582790B
Construction site multi-category material use data association analysis method
CN122694157A