BIM-based project management method and system
Through the BIM-based project management method, multiple BIM models are built for project simulation and data coordination, which solves the problems of poor cost control effects and low management efficiency caused by complex engineering projects, and realizes cost control and efficient management throughout the process.
Patent Information
- Application Number
- CN202411238140.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2044-09-05
AI Technical Summary
The prior art cannot effectively deal with the problems of poor cost control effects and low management efficiency caused by the complexity of engineering projects, especially in project management of multiple construction branches.
Through BIM-based project management methods, connect to project management databases, build multiple BIM models, conduct project simulations to obtain quality and cost data, generate judgment results, and coordinate through cloud coordination management module to achieve cross-stage data interoperability and Management plan synchronization.
The cost control of the whole process is realized, the efficiency and accuracy of project management is improved, and the barriers that models and data cannot be used at all stages of cost and technology are not interoperable, making project management more convenient, intuitive and efficient.
Smart Images

Figure CN118761742B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction project management, and in particular to a project management method and system based on BIM. Background Art
[0002] Project management is a comprehensive process involving the planning, organization, command, coordination, control and supervision of projects. Its goal is to maximize the profits of the enterprise while ensuring effective control of the quality, safety, progress and cost of the project. Due to the large amount of data, the involvement of many departments and positions, the difficulty of corresponding decomposition, the complexity of consumption and fund payment, etc., project cost control is the focus and difficulty of project management. The existing project management methods cannot meet the growing management needs, resulting in poor cost control effect and low project management accuracy.
[0003] BIM technology is a digital tool used in engineering design, construction and management. It integrates various relevant information of the project through parameter models, and shares and transmits them in the whole life cycle of project planning, operation and maintenance, so that engineering and technical personnel can correctly understand and efficiently respond to various building information. The BIM data format is usually used to pursue the superposition and maximization of the overall value of the project, which is conducive to strengthening the cost control of the whole process and improving the accuracy of project management. Summary of the invention
[0004] This application provides a BIM-based project management method and system to solve the technical problems in the prior art such as poor project cost control, low management efficiency and accuracy due to the increasing complexity of engineering projects.
[0005] In a first aspect of the present application, a BIM-based project management method is provided, the method comprising: connecting to a project management database of a target engineering project, obtaining multiple project basic data sets of multiple construction divisions, and constructing multiple BIM models based on a BIM system and in combination with the multiple project basic data sets; performing project simulation based on the multiple BIM models, and obtaining multiple project simulation results of a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation engineering progress; judging whether the multiple simulation quality data are qualified and the degree of unqualifiedness according to preset construction standards in the multiple construction divisions, and generating multiple quality judgment results; judging the multiple simulation cost data according to preset construction budgets in the multiple construction divisions, and generating multiple cost judgment results; encrypting and transmitting the multiple quality judgment results and the multiple cost judgment results to the cloud, and performing coordination management using a construction coordination management module in the cloud to generate a first management plan; performing synchronization management on the multiple simulation engineering progresses using a progress synchronization management module in the cloud to generate a second management plan; transmitting the first management plan and the second management plan to the multiple construction divisions, and performing project management on the multiple construction divisions.
[0006] The second aspect of the present application provides a BIM-based project management system, the system comprising: a BIM model construction module, the BIM model construction module is used to connect to the project management database of the target engineering project, obtain multiple project basic data sets of multiple construction divisions, and build multiple BIM models based on the BIM system and in combination with the multiple project basic data sets; a project simulation result acquisition module, the project simulation result acquisition module is used to perform project simulation based on the multiple BIM models, and obtain multiple project simulation results at a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation project progress; a simulation quality judgment module, the simulation quality judgment module is used to judge whether the multiple simulation quality data are qualified and the degree of unqualifiedness in the multiple construction divisions according to preset construction standards. Judgment, generate multiple quality judgment results; simulation cost judgment module, the simulation cost judgment module is used to judge the multiple simulation cost data locally in the multiple construction branches according to the preset construction budget, and generate multiple cost judgment results; a first management plan generation module, the first management plan generation module is used to encrypt and transmit the multiple quality judgment results and the multiple cost judgment results to the cloud, use the construction coordination management module on the cloud to coordinate and manage, and generate a first management plan; a second management plan generation module, the second management plan generation module is used to use the progress synchronization management module on the cloud to synchronize the progress of the multiple simulation projects and generate a second management plan; a project management module, the project management module is used to transmit the first management plan and the second management plan to the multiple construction branches, and perform project management on the multiple construction branches.
[0007] One or more technical solutions provided in this application have at least the following technical effects or advantages:
[0008] The BIM-based project management method provided in the present application constructs multiple BIM models based on multiple construction divisions to perform project simulation, and performs simulation quality and simulation cost judgments to generate multiple quality judgment results and multiple cost judgment results, coordinates and manages them, generates a first management plan, synchronously manages the simulated project progress, generates a second management plan, and performs project management according to the first management plan and the second management plan. This solves the technical problems in the prior art that the project cost control effect is poor, the management efficiency and accuracy are low due to the complexity trend of engineering projects, breaks the barrier that the models and data of the cost and technology stages cannot be used interchangeably, and realizes the extension and connection of BIM applications from a single stage to cross-stages, making the whole process management of the project more convenient, intuitive and efficient, and realizing the technical effect of realizing whole process cost control through BIM and improving project management efficiency and accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0010] Figure 1 A schematic diagram of a BIM-based project management method flow chart provided in an embodiment of the present application;
[0011] Figure 2 A schematic diagram of a process for generating multiple cost judgment results in a BIM-based project management method provided in an embodiment of the present application;
[0012] Figure 3 A schematic diagram of a process for obtaining first simulation cost data of a first construction section in a BIM-based project management method provided in an embodiment of the present application;
[0013] Figure 4 A schematic diagram of the BIM-based project management system structure provided in an embodiment of the present application.
[0014] Explanation of the accompanying drawings: BIM model construction module 11, project simulation result acquisition module 12, simulation quality judgment module 13, simulation cost judgment module 14, first management solution generation module 15, second management solution generation module 16, project management module 17. DETAILED DESCRIPTION
[0015] This application provides a BIM-based project management method to solve the technical problems in the prior art such as poor project cost control, low management efficiency and accuracy due to the increasing complexity of engineering projects.
[0016] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0017] It should be noted that the terms "first", "second", etc. in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product, or server that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or modules that are not clearly listed or inherent to these processes, methods, products, or devices.
[0018] Embodiment 1
[0019] like Figure 1 As shown, the present application provides a BIM-based project management method, the method comprising:
[0020] P10: Connect to the project management database of the target engineering project, obtain multiple project basic data sets of multiple construction divisions, and build multiple BIM models based on the BIM system and the multiple project basic data sets;
[0021] Specifically, the target engineering project has multiple construction divisions, and each construction division has a separate construction scope, construction period requirements and resource allocation. Managing multiple construction divisions separately can improve project management efficiency and accuracy. By connecting to the project management database of the target engineering project, multiple project basic data sets of multiple construction divisions are extracted from the project management database. The project basic data may include design drawings, material lists, construction schedules, cost budgets, etc. The extracted data is cleaned and sorted, and then imported into the BIM system. In the BIM system, the imported project basic data sets are used to build models, including the construction of civil engineering models, electromechanical equipment models, pipeline models, etc. of buildings, and multiple BIM models corresponding to multiple construction divisions are obtained.
[0022] For example, the GTJ quantity calculation model can be imported into BIMMAKE software for component processing, so as to quickly obtain the construction BIM model. After fine-tuning the construction BIM model, it can be exported to Revit software for use, from the original one-model-for-multiple-use basis to the one-model-to-end comprehensive management, reducing repeated modeling and realizing more practical applications of quantity calculation models in the construction stage.
[0023] P20: Performing project simulation based on the multiple BIM models to obtain multiple project simulation results at a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation project progress;
[0024] Optionally, select appropriate construction simulation software or plug-in, and use the multiple BIM models to perform project simulation, set the parameters required for simulation according to project requirements and actual conditions, such as construction methods, material properties, staffing, etc., import the constructed multiple BIM models into the simulation software for simulation, and extract multiple project simulation results of the first time node from the simulation software, including multiple simulation quality data of multiple construction divisions, multiple simulation cost data, and multiple simulation project progress as basic data for project feasibility evaluation.
[0025] P30: In the multiple construction divisions, judging whether the multiple simulation quality data are qualified and the degree of unqualified according to the preset construction standards, and generating multiple quality judgment results;
[0026] It should be understood that the construction quality standards within the industry or enterprise are collected and organized into preset construction standards applicable to this project, and the simulation quality data of each construction division is extracted from the project simulation results. In each construction division, the simulation quality data is judged one by one according to the preset construction standards to determine whether each simulation quality data meets the requirements of the preset construction standards and whether it is qualified. For unqualified simulation quality data, the degree of unqualifiedness is further determined, such as slightly unqualified, moderately unqualified or seriously unqualified, thereby forming multiple quality judgment results for multiple construction divisions.
[0027] P40: In the multiple construction divisions, judging the multiple simulation cost data according to the preset construction budget, and generating multiple cost judgment results;
[0028] Further, such as Figure 2 As shown, step P40 of the embodiment of the present application also includes:
[0029] P41: Acquire first simulation cost data of the first construction division, wherein the first simulation cost data includes total cost data, as well as raw material cost data, labor cost data, and other cost data;
[0030] P42: When the total cost data meets the total budget in the preset construction budget, the surplus cost is obtained and a surplus cost judgment result is generated;
[0031] P43: Otherwise, compare the raw material cost data, labor cost data, and other cost data with the raw material budget, labor budget, and other budget in the preset construction budget respectively;
[0032] P44: If the difference between any cost data item in the comparison result and the budget exceeds the difference threshold, an investigation instruction is generated to conduct an expenditure investigation on the cost item;
[0033] P45: Otherwise, the excess part will be added to the missing part, and the remaining missing part will be used as the missing cost to generate the missing cost judgment result.
[0034] Optionally, based on the design data, the engineering budget of the target engineering project is obtained and used as the preset construction budget. The multiple simulated cost data are judged with reference to the preset construction budget to obtain the cost control judgment results of each construction section, that is, to determine whether the construction cost of the project is within the budget.
[0035] Specifically, the first simulation cost data of the first construction division is obtained, including total cost data, as well as raw material cost data, labor cost data, and other cost data. The total cost data, that is, the sum of the raw material cost data, labor cost data, and other cost data, can reflect the estimated cost situation of the first construction division at the simulation time node.
[0036] Furthermore, the total cost data of the first construction division is compared with the total budget in the preset construction budget. If the total cost data meets the requirements of the total budget, that is, the total cost is within the budget, the surplus cost is calculated to generate a surplus cost judgment result. The surplus cost refers to the unused part of the budget, which can reflect the construction division's potential in cost control.
[0037] Furthermore, if the total cost data does not meet the requirements of the total budget, that is, the total cost exceeds the budget range, the raw material cost data, labor cost data and other cost data are compared with the corresponding budget items in the preset construction budget, and the cost items that exceed the budget are screened out. If it is found that the difference between any cost data and the budget exceeds the set difference threshold, it means that there is abnormal or unreasonable expenditure in this cost, then an investigation instruction is generated to conduct an expenditure investigation on the cost item to find out the reasons for the abnormal expenditure, including whether there is waste, miscalculation or poor management, so as to take timely measures to correct it.
[0038] If the comparison results of all cost items do not exceed the difference threshold, but the total cost still exceeds the total budget, the part exceeding the budget will be supplemented to the part lacking the budget to balance the various costs. If there are still cost items that cannot meet the budget requirements after supplementation, the remaining lacking part will be regarded as the lacking cost, and the lacking cost judgment result will be generated as a reference for cost control optimization.
[0039] Further, such as Figure 3 As shown, step P41 of the embodiment of the present application also includes:
[0040] P41-1: When the first quality judgment result is unqualified, obtain a first unqualified degree;
[0041] P41-2: When the first unqualified degree exceeds a preset unqualified degree, a rework instruction is generated, and based on the rework instruction, the first BIM model is controlled to perform a rework simulation to generate a rework cost;
[0042] P41-3: When the first unqualified degree does not exceed the preset unqualified degree, a construction improvement instruction is generated, and the first BIM model is controlled to perform a construction improvement simulation based on the construction improvement instruction, and a construction improvement cost is generated according to the construction improvement simulation result;
[0043] P41-4: Add the rework cost or the construction improvement cost to the first simulation cost data.
[0044] It should be understood that when the first quality judgment result is unqualified, that is, the simulated quality of the first construction section does not meet the preset construction standards, the first degree of unqualifiedness is further obtained. The first degree of unqualifiedness is a quantitative indicator used to measure the severity of non-compliance with quality standards. According to the preset unqualified degree level classification, the specific level of the first degree of unqualifiedness can be determined.
[0045] Furthermore, when the first unqualified degree exceeds the preset unqualified degree, indicating that the construction division has serious quality problems, a rework instruction is generated, and the first BIM model is controlled according to the rework instruction to perform a rework simulation, including repair, replacement or reconstruction, and the rework cost is obtained.
[0046] Furthermore, when the first unqualified degree does not exceed the preset unqualified degree, that is, although there are quality problems in the current construction division, it has not reached the level that requires rework, a construction improvement instruction is generated, and based on the construction improvement instruction, the first BIM model is controlled to perform a construction improvement simulation, including improving the construction plan, strengthening quality control, and then re-constructing the simulation, obtaining the construction improvement simulation results, and generating the construction improvement cost based on the construction improvement simulation results.
[0047] Furthermore, the rework cost and the construction improvement cost are both additional expenses in the construction process. Adding the rework cost or the construction improvement cost to the first simulation cost data can more comprehensively reflect the cost situation of the construction division and provide more accurate cost forecasting and decision-making basis.
[0048] Furthermore, step P41-3 of the embodiment of the present application also includes:
[0049] P41-31: Generate a construction improvement space according to the construction requirements, wherein the construction improvement space includes a construction process adjustment space, a spare construction material library, a spare construction equipment library, and a construction personnel library, wherein the construction personnel library includes a plurality of ordinary workers, a plurality of technicians, and a plurality of administrators;
[0050] P41-32: Obtain current construction data as original construction decision;
[0051] P41-33: Use the first BIM model to simulate the original construction decision, and based on the construction improvement quality evaluation function, perform quality evaluation on the simulation result to obtain the original construction improvement quality evaluation value;
[0052] P41-34: Taking the original construction decision as the starting point, backtracking search is performed in the construction improvement space to extract the first construction improvement decision;
[0053] P41-35: Use the first BIM model to simulate the first construction improvement decision, and based on the construction improvement quality evaluation function, perform quality evaluation on the simulation result to obtain a first construction improvement quality evaluation value;
[0054] P41-36: If the first construction improvement quality evaluation value is greater than the original construction improvement quality evaluation value, the first construction improvement decision is used to replace the original construction decision as the current optimal construction improvement decision;
[0055] P41-37: Otherwise, continue to use the original construction decision as the current optimal construction improvement decision;
[0056] P41-38: Continue to iterate and optimize in the construction improvement space until the preset constraint conditions are met, stop iterating, and output the current optimal construction improvement decision at that time as the construction improvement plan;
[0057] P41-39: Based on the construction improvement plan, a construction improvement simulation is performed on the first BIM model to generate a construction improvement simulation result.
[0058] In a possible embodiment of the present application, a construction improvement space is generated according to the construction requirements of the project, and the construction improvement space includes a construction operation process adjustment space, a spare construction material library, a spare construction equipment library, and a construction personnel library. The construction personnel library includes a plurality of ordinary workers, a plurality of technicians, and a plurality of administrators. The composition of the construction personnel can be adjusted through the construction personnel library, for example, by adding administrators or technicians, to improve the management level.
[0059] Furthermore, the current construction data is obtained and used as the original construction decision. The original construction decision is simulated using the first BIM model to predict the construction quality and cost of the original construction decision, that is, the simulation results are obtained. Based on the simulation results, corresponding parameters are obtained and substituted into the construction improvement quality evaluation function for quality evaluation to obtain the original construction improvement quality evaluation value.
[0060] Furthermore, starting from the original construction decision, a backtracking search is performed in the construction improvement space to find possible improvement solutions, such as extracting a first construction improvement decision, that is, a potential optimization solution based on current data and spatial constraints, through a search algorithm. Similarly, the first construction improvement decision is simulated using the first BIM model, and corresponding parameters are collected according to the simulation results, substituted into the construction improvement quality evaluation function for quality evaluation, and the first construction improvement quality evaluation value is obtained.
[0061] Furthermore, if the first construction improvement quality assessment value is greater than the original construction improvement quality assessment value, the first construction improvement decision will replace the original construction decision as the current optimal construction improvement decision, otherwise, the original construction decision will continue to be used as the current optimal construction improvement decision. Similarly, the iterative optimization is continued in the construction improvement space until the preset constraints are met, for example, the preset number of times is reached, the iteration is stopped, and the current optimal construction improvement decision at that time is output as the final construction improvement plan. Based on the construction improvement plan, the first BIM model is simulated for construction improvement to generate construction improvement simulation results.
[0062] Furthermore, step P41-33 of the embodiment of the present application also includes:
[0063] P41-331: Use the first BIM model to simulate the original construction decision, and during the simulation process, record safety accidents and safety hazards in the construction simulation as the first simulation result;
[0064] P41-332: After the simulation is completed, the simulated construction time is obtained as the second simulation result, and the simulated resource utilization efficiency is obtained as the third simulation result;
[0065] P41-333: According to the preset construction standard, the simulation data is judged whether it is qualified, and the fourth simulation result is generated;
[0066] P41-334: normalizing the first simulation result, the second simulation result, the third simulation result, and the fourth simulation result, and performing quality assessment on the normalized results based on the construction improvement quality assessment function to obtain the original construction improvement quality assessment value;
[0067] Wherein, the construction improvement quality evaluation function is as follows:
[0068] ;
[0069] in, is the construction improvement quality evaluation value of the i-th construction decision, is the safety hazard factor, is the construction time coefficient, is the resource utilization efficiency coefficient, , , are weights respectively, and the sum is 1, The result of judging whether the result is qualified or not is 1 if the result is qualified and 0 if the result is unqualified.
[0070] Optionally, the specific process of using the first BIM model to simulate the original construction decision and conducting quality assessment on the simulation result based on the construction improvement quality assessment function may be: using the first BIM model to simulate the original construction decision, and during the simulation process, recording safety accidents and safety hazards in the construction simulation as the first simulation result, that is, as the first quality assessment parameter. Furthermore, after the simulation is completed, the simulated construction time is obtained as the second simulation result, that is, the second quality assessment parameter, and the simulated resource utilization efficiency is obtained as the third simulation result, that is, the third quality assessment parameter.
[0071] Furthermore, the simulation data is judged to be qualified according to the preset construction standards, for example, the preset construction standards such as construction quality requirements, safety standards, and environmental protection requirements are judged to generate a fourth simulation result, that is, a fourth quality assessment parameter.
[0072] Furthermore, the first simulation result, the second simulation result, the third simulation result, and the fourth simulation result are normalized, that is, the simulation results of different dimensions and units are converted into comparable unified scales, and the normalized multiple simulation results are substituted into the construction improvement quality assessment function for quality assessment calculation to obtain the original construction improvement quality assessment value. Among them, the construction improvement quality assessment function is: ; is the construction improvement quality evaluation value of the i-th construction decision. The larger the evaluation value, the better the corresponding construction decision. is the safety hazard factor, is the construction time coefficient, is the resource utilization efficiency coefficient, , , are weights respectively, and the sum is 1, The result of judging whether the result is qualified or not is 1 if the result is qualified and 0 if the result is unqualified.
[0073] Furthermore, step P41-34 of the embodiment of the present application also includes:
[0074] P41-341: Randomly generate optimal construction decisions, the generation of the optimal construction decisions is based on the following random formula: ;
[0075] in, represents the i-th optimization item of the optimal construction decision P, Represents the jth optimization sub-item of the i-th optimization item of the optimal construction decision P, i=1,2,3,4, j=1,2,3...N, N represents the number of j-th optimization sub-item, represents the lower bound of the jth optimization item, Represents the upper bound of the jth optimization sub-item, U is a uniformly distributed random function;
[0076] P41-342: Using the random formula, the original construction decision is initialized. The original construction decision is: ;
[0077] P41-343: Generate numbers a and b, where both a and b are random numbers between 0 and 1;
[0078] P41-344: When a<b, the optimal construction decision Elements of optimization and original construction decisions The elements at the same position in the same construction are exchanged to generate a new decision as the first construction improvement decision;
[0079] P41-345: When a ≥ b, the optimal construction decision is abandoned .
[0080] Specifically, starting from the original construction decision, backtracking search is performed in the construction improvement space, and the specific process of extracting the first construction improvement decision may be: writing a random formula: ;in, represents the i-th optimization item of the optimal construction decision P, Represents the jth optimization sub-item of the i-th optimization item of the optimal construction decision P. The number of optimization items i=1, 2, 3, 4 corresponds to the construction improvement space. The construction improvement space includes a construction process adjustment space, a spare construction material library, a spare construction equipment library, and a construction personnel library. There are 4 in total. j=1, 2, 3...N, where N represents the number of the jth optimization sub-item. represents the lower bound of the jth optimization item, It represents the upper bound of the j-th optimization item, and U is a uniformly distributed random function.
[0081] Furthermore, the random formula is used to initialize the original construction decision, and the original construction decision is defined as First, randomly generate a and b, where a and b are both random numbers between 0 and 1. When a<b, the optimal construction decision Elements of optimization and original construction decisions The elements in the same position are exchanged to generate a new decision, and the new decision is used as the first construction improvement decision. When a ≥ b, the optimal construction decision is discarded. Continue to generate random numbers until the first construction improvement decision is obtained.
[0082] P50: encrypting and transmitting the multiple quality judgment results and the multiple cost judgment results to the cloud, and using the construction coordination management module on the cloud to perform coordination management to generate a first management plan;
[0083] It should be understood that the multiple quality judgment results and the multiple cost judgment results are encrypted and transmitted to the cloud, and the construction coordination management module in the cloud performs coordination and management. The construction coordination management module can perform a comprehensive analysis based on the received quality judgment results and cost judgment results, taking into account various construction factors and resource constraints, including optimization of the construction process, adjustment of resource allocation, cost control measures, etc., to generate a first management plan for construction quality and results control.
[0084] P60: Using the progress synchronization management module in the cloud, synchronously manage the progress of the multiple simulation projects and generate a second management plan;
[0085] Specifically, the simulated project progress data of multiple simulated projects are collected, including progress information of each construction stage, such as completion percentage, critical path, progress deviation, etc., and the simulated project progress data is transmitted to the cloud. The progress of the multiple simulated projects is synchronously managed through the progress synchronization management module in the cloud. The progress synchronization management module is a system specially used to manage and coordinate the progress of multiple projects. It can update, compare and analyze the uploaded progress data in real time to ensure the coordination and consistency between the progress of each simulated project, and use the optimization algorithm in the module to optimize and adjust the construction progress to obtain a second management plan. The second management plan can better manage and control the construction progress to ensure that the project can proceed smoothly according to the predetermined goals and requirements.
[0086] P70: Transmit the first management plan and the second management plan to the multiple construction divisions, and perform project management on the multiple construction divisions.
[0087] Exemplarily, the first management plan and the second management plan are transmitted to the multiple construction divisions, and each construction division refers to the corresponding quality, cost and progress control measures in the first management plan and the second management plan to carry out divisional construction to ensure that the construction quality, cost and progress meet expectations. Exemplarily, relevant data is collected through BIM business management, sorted and analyzed, and an enterprise quota library is formed to improve the speed, efficiency and accuracy of bidding project quotations, and to achieve effective prevention of cost risks of bidding projects. Improve construction efficiency and quality, and reduce construction costs and risks.
[0088] Furthermore, the embodiment of the present application further includes step P80, and step P80 further includes:
[0089] P81: Based on the first management scheme and the second management scheme, the multiple BIM models are used to perform construction simulation, and multiple expected quality data, multiple expected cost data, and multiple expected project progress are collected;
[0090] P82: When at the first time node, data collection is performed on the multiple construction divisions to obtain multiple actual quality data, multiple actual cost data, and multiple actual project progress data;
[0091] P83: comparing the plurality of expected quality data and the plurality of expected cost data with the plurality of actual quality data and the plurality of actual cost data, and adjusting the first management scheme when the comparison deviation does not satisfy a first preset comparison deviation;
[0092] P84: Compare multiple expected project progresses with multiple actual project progresses, and when the comparison deviation does not meet the second preset comparison deviation, adjust the second management plan.
[0093] It should be understood that, with reference to the first management plan and the second management plan, the multiple BIM models are used to perform construction simulation, and thereby multiple expected quality data, multiple expected cost data, and multiple expected project progress data are collected as expected construction results.
[0094] Furthermore, in the actual construction process, when the project is at the first time node, such as every week, every month or at the end of a key construction phase, data collection is performed on multiple construction divisions, including collecting multiple actual quality data, multiple actual cost data, and multiple actual project progress data.
[0095] Furthermore, a difference comparison is performed between multiple expected quality data and multiple expected cost data and multiple actual quality data and multiple actual cost data. When the comparison deviation does not meet the first preset comparison deviation, it means that the actual project quality and cost control do not meet the expected standards. In this case, the first management plan is adjusted by optimizing resource allocation, improving construction processes or taking other measures to reduce deviations and improve construction quality and cost control effects.
[0096] Furthermore, multiple expected project progresses are compared with multiple actual project progresses. When the comparison deviation does not meet the second preset comparison deviation, that is, the actual project progress does not meet the expected project progress, the second management plan is adjusted by adjusting the construction plan, optimizing the construction schedule or taking other measures to ensure that the construction progress meets expectations.
[0097] Therefore, the management plan is adjusted by comparing the construction simulation based on the BIM model with the actual construction data to achieve more accurate construction management and optimization.
[0098] In summary, the embodiments of the present application have at least the following technical effects:
[0099] This application uses the project basic data sets of multiple construction divisions to construct multiple BIM models for project simulation, generates multiple quality judgment results and multiple cost judgment results through simulated quality and simulated cost judgment, coordinates and manages the multiple quality judgment results and multiple cost judgment results to generate a first management plan, generates a second management plan through the synchronous management of simulated project progress, and performs project management according to the first management plan and the second management plan.
[0100] Through the integrated management model, the barriers that prevent models and data from being interchangeable at different stages of cost and technology are broken, and the extension and penetration of BIM applications from a single stage to cross-stages is achieved, making the whole process management of the project more convenient, intuitive and efficient, and achieving the technical effect of realizing full-process cost control through BIM and improving project management efficiency and accuracy.
[0101] Embodiment 2
[0102] Based on the same inventive concept as the BIM-based project management method in the aforementioned embodiment, Figure 4 As shown, the present application provides a BIM-based project management system, and the system and method embodiments in the present application embodiments are based on the same inventive concept. The system includes:
[0103] A BIM model building module 11, the BIM model building module 11 is used to connect to the project management database of the target engineering project, obtain multiple project basic data sets of multiple construction divisions, and build multiple BIM models based on the BIM system and in combination with the multiple project basic data sets;
[0104] A project simulation result acquisition module 12, wherein the project simulation result acquisition module 12 is used to perform project simulation based on the multiple BIM models, and acquire multiple project simulation results at a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation project progress;
[0105] A simulation quality judgment module 13, wherein the simulation quality judgment module 13 is used to judge whether the plurality of simulation quality data are qualified and the degree of unqualified in the plurality of construction divisions according to preset construction standards, and generate a plurality of quality judgment results;
[0106] A simulation cost judgment module 14, wherein the simulation cost judgment module 14 is used to judge the plurality of simulation cost data locally in the plurality of construction divisions according to a preset construction budget, and generate a plurality of cost judgment results;
[0107] A first management solution generation module 15, which is used to encrypt and transmit the multiple quality judgment results and the multiple cost judgment results to the cloud, and use the construction coordination management module in the cloud to perform coordination management to generate a first management solution;
[0108] A second management solution generating module 16, the second management solution generating module 16 is used to synchronously manage the progress of the plurality of simulated projects using a progress synchronization management module in the cloud, and generate a second management solution;
[0109] The project management module 17 is used to transmit the first management plan and the second management plan to the multiple construction divisions, and perform project management on the multiple construction divisions.
[0110] Furthermore, the simulation cost determination module 14 is further configured to perform the following steps:
[0111] Acquire first simulation cost data of the first construction division, wherein the first simulation cost data includes total cost data, raw material cost data, labor cost data, and other cost data;
[0112] When the total cost data meets the total budget in the preset construction budget, the surplus cost is obtained and a surplus cost judgment result is generated;
[0113] Otherwise, the raw material cost data, labor cost data, and other cost data are compared with the raw material budget, labor budget, and other budgets in the preset construction budget respectively;
[0114] If the difference between any cost data item in the comparison result and the budget exceeds the difference threshold, an investigation instruction is generated to conduct an expenditure investigation on the cost item;
[0115] Otherwise, the excess part will be added to the missing part, and the remaining missing part will be used as the missing cost to generate the missing cost judgment result.
[0116] Furthermore, the simulation cost determination module 14 is further configured to perform the following steps:
[0117] When the first quality judgment result is unqualified, obtaining a first unqualified degree;
[0118] When the first unqualified degree exceeds a preset unqualified degree, a rework instruction is generated, and based on the rework instruction, the first BIM model is controlled to perform a rework simulation to generate a rework cost;
[0119] When the first unqualified degree does not exceed the preset unqualified degree, generating a construction improvement instruction, controlling the first BIM model to perform a construction improvement simulation based on the construction improvement instruction, and generating a construction improvement cost according to the construction improvement simulation result;
[0120] The rework cost or the construction improvement cost is added to the first simulation cost data.
[0121] Furthermore, the simulation cost determination module 14 is further configured to perform the following steps:
[0122] Generate a construction improvement space according to the construction requirements, wherein the construction improvement space includes a construction process adjustment space, a spare construction material library, a spare construction equipment library, and a construction personnel library, wherein the construction personnel library includes a plurality of ordinary workers, a plurality of technicians, and a plurality of administrators;
[0123] Obtain current construction data as original construction decision;
[0124] Using the first BIM model to simulate the original construction decision, and based on the construction improvement quality evaluation function, performing quality evaluation on the simulation result to obtain the original construction improvement quality evaluation value;
[0125] Taking the original construction decision as a starting point, performing a backtracking search in the construction improvement space to extract a first construction improvement decision;
[0126] Using the first BIM model to simulate the first construction improvement decision, and based on the construction improvement quality evaluation function, performing a quality evaluation on the simulation result to obtain a first construction improvement quality evaluation value;
[0127] If the first construction improvement quality assessment value is greater than the original construction improvement quality assessment value, the first construction improvement decision is used to replace the original construction decision as the current optimal construction improvement decision;
[0128] Otherwise, continue to use the original construction decision as the current optimal construction improvement decision;
[0129] Continue to iterate and optimize in the construction improvement space until the preset constraint conditions are met, then stop iterating and output the current optimal construction improvement decision at that time as the construction improvement plan;
[0130] Based on the construction improvement plan, a construction improvement simulation is performed on the first BIM model to generate a construction improvement simulation result.
[0131] Furthermore, the simulation cost determination module 14 is further configured to perform the following steps:
[0132] The optimal construction decision is generated randomly, and the optimal construction decision is generated according to the following random formula:
[0133] ;
[0134] in, represents the i-th optimization item of the optimal construction decision P, Represents the jth optimization sub-item of the i-th optimization item of the optimal construction decision P, i=1,2,3,4, j=1,2,3...N, N represents the number of j-th optimization sub-item, represents the lower bound of the jth optimization item, Represents the upper bound of the jth optimization sub-item, U is a uniformly distributed random function;
[0135] The random formula is used to initialize the original construction decision, which is: ;
[0136] Generate numbers a and b, where both numbers a and b are random numbers between 0 and 1;
[0137] When a<b, the optimal construction decision Elements of optimization and original construction decisions The elements at the same position in the same construction are exchanged to generate a new decision as the first construction improvement decision;
[0138] When a≥b, the optimal construction decision is abandoned. .
[0139] Furthermore, the simulation cost determination module 14 is further configured to perform the following steps:
[0140] Using the first BIM model to simulate the original construction decision, during the simulation process, recording safety accidents and safety hazards in the construction simulation as a first simulation result;
[0141] After the simulation is finished, the simulated construction time is obtained as the second simulation result, and the simulated resource utilization efficiency is obtained as the third simulation result;
[0142] According to the preset construction standard, judging whether the simulation data is qualified or not, and generating a fourth simulation result;
[0143] Normalizing the first simulation result, the second simulation result, the third simulation result, and the fourth simulation result, and performing quality assessment on the normalized results based on the construction improvement quality assessment function to obtain the original construction improvement quality assessment value;
[0144] Wherein, the construction improvement quality evaluation function is as follows:
[0145] ;
[0146] in, is the construction improvement quality evaluation value of the i-th construction decision, is the safety hazard factor, is the construction time coefficient, is the resource utilization efficiency coefficient, , , are weights respectively, and the sum is 1, The result of judging whether the result is qualified or not is 1 if the result is qualified and 0 if the result is unqualified.
[0147] Furthermore, the system also includes:
[0148] A construction simulation module, wherein the construction simulation module is used to perform construction simulation based on the first management scheme and the second management scheme using the multiple BIM models, and collect and obtain multiple expected quality data, multiple expected cost data, and multiple expected project progress;
[0149] A construction data collection module, wherein the construction data collection module is used to collect data from the multiple construction divisions when at the first time node, and obtain multiple actual quality data, multiple actual cost data, and multiple actual project progress;
[0150] a first management scheme adjustment module, the first management scheme adjustment module being used to compare the plurality of expected quality data and the plurality of expected cost data with the plurality of actual quality data and the plurality of actual cost data, and to adjust the first management scheme when the comparison deviation does not satisfy a first preset comparison deviation;
[0151] The second management scheme adjustment module is used to compare multiple expected project progresses with multiple actual project progresses, and when the comparison deviation does not meet the second preset comparison deviation, adjust the second management scheme.
[0152] It should be noted that the above-mentioned sequence of the embodiments of the present application is only for description and does not represent the advantages and disadvantages of the embodiments. And the above-mentioned specific embodiments of this specification are described. In addition, the processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0153] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.
[0154] This specification and the drawings are merely exemplary illustrations of the present application and are deemed to cover any and all modifications, variations, combinations or equivalents within the scope of the present application. Obviously, a person skilled in the art may make various modifications and variations to the present application without departing from the scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the present application and its equivalents, the present application intends to include these modifications and variations.
Claims
1. BIM-based project management method, characterized by: include: Connecting to the project management database of the target engineering project, obtaining multiple project basic data sets of multiple construction divisions, and building multiple BIM models based on the BIM system and combining the multiple project basic data sets; Performing project simulation based on the multiple BIM models to obtain multiple project simulation results at a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation project progress; At the multiple construction divisions, judging whether the multiple simulation quality data are qualified and the degree of unqualified according to the preset construction standards, and generating multiple quality judgment results; At the multiple construction divisions, judging the multiple simulation cost data according to the preset construction budget, and generating multiple cost judgment results; Encrypting and transmitting the multiple quality judgment results and the multiple cost judgment results to the cloud, and using the construction coordination management module on the cloud to perform coordination management to generate a first management plan; Using a progress synchronization management module in the cloud, synchronously manage the progress of the multiple simulated projects and generate a second management plan; Transmitting the first management plan and the second management plan to the multiple construction divisions, and performing project management on the multiple construction divisions; According to the preset construction budget, the plurality of simulation cost data are judged to generate a plurality of cost judgment results, including: Acquire first simulation cost data of the first construction division, wherein the first simulation cost data includes total cost data, raw material cost data, labor cost data, and other cost data; When the total cost data meets the total budget in the preset construction budget, the surplus cost is obtained and a surplus cost judgment result is generated; Otherwise, the raw material cost data, labor cost data, and other cost data are compared with the raw material budget, labor budget, and other budgets in the preset construction budget respectively; If the difference between any cost data item in the comparison result and the budget exceeds the difference threshold, an investigation instruction is generated to conduct an expenditure investigation on the cost item; Otherwise, the excess part is added to the missing part, and the missing part is taken as the missing cost to generate the missing cost judgment result; When the first quality judgment result is unqualified, obtaining a first unqualified degree; When the first unqualified degree exceeds a preset unqualified degree, a rework instruction is generated, and based on the rework instruction, the first BIM model is controlled to perform a rework simulation to generate a rework cost; When the first unqualified degree does not exceed the preset unqualified degree, generating a construction improvement instruction, controlling the first BIM model to perform a construction improvement simulation based on the construction improvement instruction, and generating a construction improvement cost according to the construction improvement simulation result; adding the rework cost or the construction improvement cost to the first simulation cost data; Controlling the first BIM model to perform construction improvement simulation based on the construction improvement instruction includes: Generate a construction improvement space according to the construction requirements, wherein the construction improvement space includes a construction process adjustment space, a spare construction material library, a spare construction equipment library, and a construction personnel library, wherein the construction personnel library includes a plurality of ordinary workers, a plurality of technicians, and a plurality of administrators; Obtain current construction data as original construction decision; Using the first BIM model to simulate the original construction decision, and based on the construction improvement quality evaluation function, performing quality evaluation on the simulation result to obtain the original construction improvement quality evaluation value; Taking the original construction decision as a starting point, performing a backtracking search in the construction improvement space to extract a first construction improvement decision; Using the first BIM model to simulate the first construction improvement decision, and based on the construction improvement quality evaluation function, performing a quality evaluation on the simulation result to obtain a first construction improvement quality evaluation value; If the first construction improvement quality assessment value is greater than the original construction improvement quality assessment value, the first construction improvement decision is used to replace the original construction decision as the current optimal construction improvement decision; Otherwise, continue to use the original construction decision as the current optimal construction improvement decision; Continue to iterate and optimize in the construction improvement space until the preset constraint conditions are met, then stop iterating and output the current optimal construction improvement decision at that time as the construction improvement plan; Based on the construction improvement plan, performing construction improvement simulation on the first BIM model to generate a construction improvement simulation result; Taking the original construction decision as a starting point, a backtracking search is performed in the construction improvement space to extract the first construction improvement decision, including: The optimal construction decision is generated randomly, and the optimal construction decision is generated according to the following random formula: ; in, represents the i-th optimization item of the optimal construction decision P, Represents the jth optimization sub-item of the i-th optimization item of the optimal construction decision P, i=1,2,3,4, j=1,2,3...N, N represents the number of j-th optimization sub-item, represents the lower bound of the jth optimization item, Represents the upper bound of the jth optimization sub-item, U is a uniformly distributed random function; The random formula is used to initialize the original construction decision, which is: ; Generate numbers a and b, where both numbers a and b are random numbers between 0 and 1; When a<b, the optimal construction decision Elements of optimization and original construction decisions The elements at the same position in the same construction are exchanged to generate a new decision as the first construction improvement decision; When a≥b, the optimal construction decision is abandoned. ; The original construction decision is simulated using the first BIM model, and the quality of the simulation result is evaluated based on the construction improvement quality evaluation function to obtain the original construction improvement quality evaluation value, including: Using the first BIM model to simulate the original construction decision, during the simulation process, recording safety accidents and safety hazards in the construction simulation as a first simulation result; After the simulation is finished, the simulated construction time is obtained as the second simulation result, and the simulated resource utilization efficiency is obtained as the third simulation result; According to the preset construction standard, judging whether the simulation data is qualified or not, and generating a fourth simulation result; Normalizing the first simulation result, the second simulation result, the third simulation result, and the fourth simulation result, and performing quality assessment on the normalized results based on the construction improvement quality assessment function to obtain the original construction improvement quality assessment value; Wherein, the construction improvement quality evaluation function is as follows: ; in, is the construction improvement quality evaluation value of the i-th construction decision, is the safety hazard factor, is the construction time coefficient, is the resource utilization efficiency coefficient, , , are weights respectively, and the sum is 1, To determine whether the result is qualified, the value is 1 if qualified and 0 if unqualified.
2. The method according to claim 1, characterized in that Also includes: Based on the first management scheme and the second management scheme, the multiple BIM models are used to perform construction simulation, and multiple expected quality data, multiple expected cost data, and multiple expected project progress are collected; When at the first time node, data collection is performed on the multiple construction divisions to obtain multiple actual quality data, multiple actual cost data, and multiple actual project progress; Comparing the plurality of expected quality data and the plurality of expected cost data with the plurality of actual quality data and the plurality of actual cost data, and adjusting the first management scheme when the comparison deviation does not satisfy a first preset comparison deviation; Compare the multiple expected project progresses with the multiple actual project progresses, and when the comparison deviation does not meet the second preset comparison deviation, adjust the second management plan.
3. BIM-based project management system, characterized by: For implementing the BIM-based project management method according to any one of claims 1 to 2, the system comprises: A BIM model construction module, wherein the BIM model construction module is used to connect to the project management database of the target engineering project, obtain multiple project basic data sets of multiple construction divisions, and construct multiple BIM models based on the BIM system and in combination with the multiple project basic data sets; A project simulation result acquisition module, wherein the project simulation result acquisition module is used to perform project simulation based on the multiple BIM models, and acquire multiple project simulation results at a first time node, wherein the multiple project simulation results include multiple simulation quality data, multiple simulation cost data, and multiple simulation project progress; A simulation quality judgment module, wherein the simulation quality judgment module is used to judge whether the plurality of simulation quality data are qualified and the degree of unqualified in the plurality of construction divisions according to preset construction standards, and generate a plurality of quality judgment results; A simulation cost judgment module, the simulation cost judgment module is used to judge the multiple simulation cost data locally in the multiple construction branches according to the preset construction budget to generate multiple cost judgment results; A first management solution generation module, the first management solution generation module is used to encrypt and transmit the multiple quality judgment results and the multiple cost judgment results to the cloud, use the cloud-based construction coordination management module to perform coordination management, and generate a first management solution; A second management solution generation module, the second management solution generation module is used to synchronously manage the progress of the multiple simulated projects using the progress synchronization management module on the cloud, and generate a second management solution; A project management module, wherein the project management module is used to transmit the first management plan and the second management plan to the multiple construction divisions, and perform project management on the multiple construction divisions.