Manufacturing equipment and manufacturing method for permanent and temporary combined balcony guardrail

By introducing rotating turntable and vacuum suction cup technology into the balcony guardrail production equipment, the problems of low drilling machine drill bit replacement efficiency and difficulty in debris cleaning are solved, efficient drilling and cleaning are achieved, and construction efficiency and safety are improved.

CN118768602APending Publication Date: 2024-10-15THE FIRST CONSTR ENG COMPANY LTD OF CHINA CONSTR SECOND ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410704575.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-03
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Existing drilling machines have low bit replacement efficiency during the drilling process, resulting in reduced work efficiency, and drilling debris is difficult to clean, affecting construction safety and material utilization.

Method used

A Yonglin integrated balcony guardrail production equipment including a fixed workbench, a rotating motor, a hydraulic telescopic rod and a vacuum suction cup is designed. The rotating turntable realizes rapid drill bit replacement, and the rotating worktable and vacuum suction cup are used to realize automatic cleaning of debris. Allows two members to be drilled simultaneously.

Benefits of technology

It improves the working efficiency of the drilling machine, enables quick replacement of drill bits and quick cleaning of debris, and enhances construction safety and material utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118768602A_ABST
    Figure CN118768602A_ABST
Patent Text Reader

Abstract

The invention discloses manufacturing equipment and a manufacturing method for a permanent and temporary combined balcony guardrail, and relates to the technical field of guardrail manufacturing equipment.The manufacturing equipment specifically comprises a fixed workbench and a collecting box, the top of the fixed workbench is connected with a moving rod through a translation structure, and the top of the moving rod is connected with a rotating rod through a second rotating motor; the other end of the rotating rod is connected with a drill bit structure through a first hydraulic telescopic rod, the side, close to the drill bit structure, of the fixed workbench is movably connected with a rotating workbench, and a first workpiece limiting structure and a second workpiece limiting structure are arranged on the rotating workbench. According to the manufacturing equipment and method for the permanent and temporary combined balcony guardrail, through the arrangement of the rotary workpiece table and the workpiece limiting structure I, a rod piece after drilling and the rotary workpiece table can rotate at the same time, so that chippings remaining on the rod piece and the rotary workpiece table can fall into a collecting box under the action of gravity, rapid cleaning of the chippings is achieved, and the production efficiency is improved. And the splicing of the rod pieces and the use of the equipment are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of guardrail manufacturing equipment, and in particular to a manufacturing equipment and a manufacturing method for a permanent and temporary combined balcony guardrail. Background Art

[0002] In residential building construction projects, temporary guardrails without vertical bars are often installed on the balcony to ensure the safety of construction workers. After the completion and acceptance of the construction, it is often necessary to remove the temporary guardrails without vertical bars and then install permanent guardrails with vertical bars. This method requires the temporary guardrails embedded in the cement floor to be removed, and then the permanent guardrails are embedded in the cement. The temporary guardrails are removed and abandoned, resulting in material waste and other effects. In addition, reinstalling the permanent guardrails after the completion of the project will destroy the integrity of the ground and walls to a certain extent, which is not conducive to the overall safety of the building. In response to this problem, a permanent and temporary combined balcony guardrail is proposed in the prior art. As shown in the scheme disclosed in the authorized patent document with application number CN202021707823.5, this type of balcony guardrail requires drilling holes in the rod body that constitutes the guardrail during the production process, and multiple different holes need to be drilled on the guardrail.

[0003] At present, a drilling machine is usually used to drill holes in the rod body that constitutes the guardrail. In the prior art, some solutions for drilling machines for guardrail processing are also disclosed, such as the solution disclosed in the authorized patent document with application number CN202222700246.2. This type of drilling machine is only equipped with one drill bit, so when drilling different holes, it is necessary to remove the drill bit and then install a drill bit that is compatible with the drilling. The efficiency of drill bit replacement is low, which reduces the working efficiency of the drilling machine. At the same time, during the drilling process, drilling debris will fall into the rod and on the workbench. During the transfer of the rod, the debris in the inner cavity of the rod is easy to scatter everywhere, which is not conducive to cleaning. The debris splashed everywhere on the workbench is also not conducive to cleaning, and only one rod can be drilled at a time, which reduces work efficiency. Based on this, the present application proposes a manufacturing device and a manufacturing method for a permanent and temporary combined balcony guardrail. Summary of the invention

[0004] The present invention provides a manufacturing device and a manufacturing method for a permanent and temporary combined balcony guardrail, which solves the problem that the drill bit replacement efficiency is low and the working efficiency of the drilling machine is reduced as mentioned in the above background technology; during the drilling process, drilling debris will fall into the rod and the workbench, and during the transfer of the rod, the debris in the inner cavity of the rod is easy to scatter everywhere, which is not conducive to cleaning, and the debris splashed everywhere on the workbench is also not conducive to cleaning, and only one rod can be drilled at a time, which reduces the working efficiency.

[0005] The present invention provides the following technical solutions: a manufacturing device for a permanent and temporary combined balcony guardrail, comprising a fixed workbench and a collection box, wherein the top of the fixed workbench is connected to a moving rod through a translation structure, the top of the moving rod is connected to a rotating rod through a rotating motor 2, the other end of the rotating rod is connected to a drill structure through a hydraulic telescopic rod 1, a rotating workbench is movably connected to a side of the fixed workbench close to the drill structure, a double-headed ball screw is movably connected to the rotating workbench, the outer rings at both ends of the double-headed ball screw are both threadedly connected to support rods, the other end of one of the support rods is provided with a workpiece limiting structure 1, the other end of the other support rod is provided with a workpiece limiting structure 2, and the collection box is located on a side of the rotating workbench away from the workpiece limiting structure 1;

[0006] The drill structure comprises a sealed shell fixedly connected to the bottom of a hydraulic telescopic rod, a turntable is movably connected to the inner cavity of the sealed shell, a hydraulic telescopic rod is evenly arranged at the bottom of the turntable, a moving block is movably connected to the bottom of the hydraulic telescopic rod, a processing drill is arranged at the bottom of the moving block, and a signal receiver is arranged at one side of the moving block, a through hole adapted to the processing drill is arranged at one side of the bottom of the sealed shell, a rotating block adapted to the moving block is movably connected to the top of the through hole, and a signal generator adapted to the signal receiver is arranged at the bottom of the inner cavity of the rotating block;

[0007] The workpiece limiting structure 1 includes a first rotating shaft movably connected to a support rod, a vacuum pump 2 and a turntable 2 fixedly connected to the first rotating shaft, a fixed sleeve is evenly fixed on one side of the turntable 2 close to the first rotating shaft, a hydraulic telescopic rod 3 is connected to the inner cavity of the fixed sleeve by bolts, an inner suction cup adapted to the workpiece is fixed to the output end of the hydraulic telescopic rod 3, a vacuum pump 1 is fixed to the other end of the hydraulic telescopic rod 3, the inner suction cup is connected to the air inlet end of the vacuum pump 1 through a vacuum tube 1, a positioning vacuum suction cup adapted to the outer diameter of the workpiece is evenly fixed to the other end of the turntable 2, and the positioning vacuum suction cup is connected to the air inlet end of the vacuum pump 2 through a vacuum tube 2;

[0008] The workpiece limiting structure 2 includes a second rotating shaft movably connected to another support rod and a turntable 3 fixedly connected to the second rotating shaft, another fixed sleeve is evenly fixed on the side of the turntable 3 close to the second rotating shaft, a hydraulic telescopic rod 4 is fixed in the inner cavity of the other fixed sleeve, the other end of the hydraulic telescopic rod 4 is fixedly connected to a support block, and a positioning block adapted to the workpiece is evenly fixed on the other end of the turntable 3.

[0009] Preferably, a rotating rod is movably connected to the middle of the rotating workbench near one end of the collecting box, and the other end of the rotating rod is movably connected to the fixed workbench. A rotating motor is fixed on the fixed workbench, and the end of the output shaft of the rotating motor is fixedly connected to the other end of the rotating rod.

[0010] Preferably, a second rotating motor is fixedly connected to the top of the moving rod, and a terminal end of an output shaft of the second rotating motor is fixedly connected to an end of the rotating rod away from the first hydraulic telescopic rod.

[0011] Preferably, a rotating motor three is fixedly connected to the bottom of the inner cavity of the sealed shell, the end of the output shaft of the rotating motor three is fixedly connected to the middle of the bottom of the turntable one, a rotating motor four is fixedly connected to the inner cavity of the sealed shell, the end of the output shaft of the rotating motor four is fixedly connected to a gear, the outer ring of the rotating block is fixedly connected to a gear ring, and the gear is meshed with the gear ring.

[0012] Preferably, a connecting block is movably connected to the middle of the top of the moving block, and the top of the connecting block is fixedly connected to the bottom of the second hydraulic telescopic rod.

[0013] Preferably, the workpiece limiting structure one also includes a rotating motor four, and the end of the output shaft of the rotating motor four is fixedly connected to the end of the first rotating shaft away from the turntable two; the workpiece limiting structure two also includes a rotating motor five, and the end of the output shaft of the rotating motor five is fixedly connected to the end of the second rotating shaft away from the turntable three.

[0014] Preferably, the first rotating shaft is a hollow structure, the vacuum pump 2 is located in the inner cavity of the first rotating shaft, the side wall of the first rotating shaft is evenly provided with air inlet and outlet holes, the turntable 2 is provided with an air duct, one end of the air duct is in contact with the air inlet end of the positioning vacuum suction cup, and the other end of the air duct is fixedly connected to one end of the vacuum tube 2 away from the air inlet end of the vacuum pump 2.

[0015] Preferably, one end of both the vacuum tube 1 and the vacuum tube 2 is provided with an electric ball valve.

[0016] Preferably, a support plate is fixed to one side of the fixed workbench close to the rotating workbench, and when the rotating workbench is in a horizontal state, the support plate supports the rotating workbench.

[0017] A method for manufacturing a permanent and temporary combined balcony guardrail, comprising the following steps:

[0018] Step 1: The staff adjusts the distance between the workpiece limiting structure 1 and the workpiece limiting structure 2 according to the needs, so that the distance between the turntable 2 and the turntable 3 is not greater than the length of the rod for producing the permanent and temporary combined balcony guardrail, and adjusts the positions of the positioning vacuum suction cup and the positioning block according to the needs, so that the positioning vacuum suction cup and the positioning block for lifting the workpiece are adapted to the rod;

[0019] Step 2: The staff puts one end of the rod for producing the permanent and temporary combined balcony guardrail on the matching positioning block, and the other end of the rod on the matching positioning vacuum suction cup, and starts the rotating motor 2. The operation of the rotating motor 2 shortens the distance between the two support rods until the turntable 2 and the turntable 3 are tightly fitted with the end of the workpiece, and the turntable 2 and the turntable 3 are used to clamp and fix the workpiece;

[0020] Step 3, the processing drill bit adapted to the workpiece moves to the outside of the sealed housing through the through hole, the extension and retraction of the hydraulic telescopic rod 1 can change the height of the processing drill bit, the rotation of the rotary motor 4 can drive the rotary block to rotate, and the rotary block can drive the processing drill bit to rotate through the moving block. The coordinated use of the hydraulic telescopic rod 1 and the rotary motor 4 can realize the processing drill bit to drill the workpiece, and during the drilling process, if the processing drill bit needs to be replaced, the hydraulic telescopic rod 2 located above the rotary block is retracted until the exposed processing drill bit moves to the top of the rotary block, the rotary motor 3 drives the turntable 1 to rotate, and the rotation of the turntable 1 changes the position of the processing drill bit until the corresponding processing drill bit moves to the top of the rotary block, the rotary block rotates, and the rotation of the rotary block drives the signal generator to rotate until the signal receiver located above the signal generator receives the signal, so as to realize the alignment of the rotary block and the moving block, and the hydraulic telescopic rod 2 is extended, the processing drill bit can be exposed, and the processing drill bit can be quickly replaced;

[0021] Step 4: The translation structure works. The translation structure works to change the position of the processing drill bit so that the processing drill bit can drill holes at different positions of the workpiece. During the drilling process, the rotary motor 4 and the rotary motor 5 rotate simultaneously to change the drilling position of the workpiece.

[0022] Step 5: After drilling, the debris remaining inside the rod and the debris on the workpiece table are cleaned. If the rod is a solid structure, the rotary motor 4 and the rotary motor 5 drive the workpiece to rotate so that the drilling part of the workpiece faces downward, and the debris left in the drilled hole is dumped out; if the rod is a tubular structure, the vacuum pump 2 works, and the operation of the vacuum pump 2 makes the processed workpiece and the positioning vacuum suction cup negatively connected, the double-headed ball screw rotates, so that the positioning block is separated from the rod, and the rotary motor 1 rotates, and the rotary motor 1 drives the rotary table to rotate, and the rotary table and the debris remaining inside the tubular rod fall into the miscellaneous collection box under the action of gravity, so that the rod and the rotary table are cleaned at the same time;

[0023] Step 6. Remove the drilled rods and use bolts to assemble the rods into a permanent and temporary balcony guardrail.

[0024] Compared with the prior art, the present invention has the following beneficial effects:

[0025] 1. The manufacturing equipment and manufacturing method of the permanent and temporary combined balcony guardrail can change the position of the processing drill bit by rotating the turntable through the setting of the drill bit structure, so that the processing drill bit does not need to be disassembled and assembled when the equipment is used, and the processing drill bit can be quickly replaced, thereby improving the working efficiency of the manufacturing equipment.

[0026] 2. The manufacturing equipment and method of the permanent and temporary combined balcony guardrail, through the setting of a rotating worktable and a workpiece limiting structure, the rod and the rotating worktable can rotate at the same time after the drilling is completed, so that the debris remaining on the rod and the rotating worktable can fall into the collection box under the action of gravity, thereby realizing rapid cleaning of the debris and facilitating the splicing of the rods and the use of the equipment.

[0027] 3. The manufacturing equipment and method of the permanent and temporary combined balcony guardrail can fix two nested rods at the same time through the arrangement of the inner suction cup, the support block, the positioning vacuum suction cup and the positioning block, so that the two rods for making the permanent and temporary combined balcony guardrail can be drilled at the same time, thereby improving the drilling efficiency of the rods and further improving the manufacturing efficiency of the permanent and temporary combined balcony guardrail. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a front schematic diagram of the structure of the present invention;

[0029] Figure 2 The structure of the present invention Figure 1 Front view schematic diagram;

[0030] Figure 3 The structure of the present invention Figure 1 Back diagram;

[0031] Figure 4 This is a schematic diagram of the bottom of the drill bit structure of the present invention;

[0032] Figure 5 This is a schematic diagram of the internal structure of the drill bit of the present invention;

[0033] Figure 6 This is a schematic diagram of the structural connection block of the present invention;

[0034] Figure 7 It is a schematic diagram of the rotating block of the structure of the present invention;

[0035] Figure 8 A schematic diagram of a workpiece limiting structure of the present invention;

[0036] Fig. 9 The structure of the present invention Figure 8 Back diagram;

[0037] Fig.10 This is a schematic diagram of the second workpiece limiting structure of the present invention;

[0038] Fig.11 It is a schematic cross-sectional view of the first rotation axis of the structure of the present invention.

[0039] In the figure: 1. Fixed workbench; 2. Rotating workbench; 3. Translation ball screw; 4. Rotating motor 1; 5. Moving rod; 6. Rotating motor 2; 7. Rotating rod; 8. Hydraulic telescopic rod 1; 9. Sealed housing; 10. Support plate; 11. Rotating motor 2; 12. Support rod; 13. Rotating motor 4; 14. Collection box; 15. Double-headed ball screw; 16. Hydraulic telescopic rod 3; 17. Rotating motor 5; 18. Rotating motor 1; 19. Positioning vacuum suction cup; 20. Processing drill bit; 21. Rotating motor 3 ; 22. Turntable one; 23. Hydraulic telescopic rod two; 24. Moving block; 25. Rotating motor four; 26. Gear; 27. Rotating block; 28. Gear ring; 29. ​​Signal receiver; 30. Connecting block; 31. Signal generator; 32. Hydraulic telescopic rod four; 33. Support block; 34. Through hole; 35. Positioning block; 36. Fixed sleeve; 37. Turntable two; 38. First rotating axis; 39. Vacuum pump one; 40. Inner suction cup; 41. Turntable three; 42. Vacuum pump two; 43. Vacuum tube two; 44. Air duct. DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] The present invention provides a manufacturing device for a permanent and temporary combined balcony guardrail, comprising a fixed workbench 1, the top translation structure of the fixed workbench 1 is connected to a moving rod 5, in some embodiments of the present application, the translation structure comprises a translation ball screw 3 movably connected to the top of the fixed workbench 1, the outer ring of the translation ball screw 3 is threadedly connected to a translation ball nut, the translation ball nut is fixedly connected to the moving rod 5, through the setting of the translation ball screw 3, the rotation of the translation ball screw 3 can make the nut move in the direction where the translation ball screw 3 is located, and the translation ball nut drives the moving rod 5 to move during the movement process, changing the position of the moving rod 5 on the fixed workbench 1. A rotating motor 14 is fixed to one side of the fixed workbench 1, the end of the output shaft of the rotating motor 14 is fixedly connected to the end of the translation ball screw 3 through a reducer, and through the setting of the rotating motor 14, the rotation of the rotating motor 14 can drive the translation ball screw 3 fixedly connected thereto to rotate.

[0042] The top of the moving rod 5 is fixedly connected to a rotating motor 2 6, the end of the output shaft of the rotating motor 2 6 is fixedly connected to a rotating rod 7, and the rotating rod 7 is in contact with the top of the moving rod 5. Through the setting of the rotating motor 2 6, the rotation of the rotating motor 2 6 can drive the rotating rod 7 fixedly connected thereto to rotate.

[0043] A hydraulic telescopic rod 8 is fixedly connected to the middle of the other end of the rotating rod 7, and a drill bit structure is fixed to the bottom of the hydraulic telescopic rod 8. Through the setting of the hydraulic telescopic rod 8, the extension and retraction of the hydraulic telescopic rod 8 can change the position of the drill bit structure in the vertical direction, and under the action of the rotating motor 26, the position of the drill bit structure in the horizontal plane can be changed.

[0044] The drill bit structure includes a sealed shell 9 fixedly connected to the bottom of a hydraulic telescopic rod 8, a turntable 22 is movably connected to the top of the inner cavity of the sealed shell 9, a rotating motor 3 21 is fixedly connected to the bottom of the inner cavity of the sealed shell 9, and the output shaft end of the rotating motor 3 21 is fixedly connected to the middle of the bottom of the turntable 22 through a reducer. Through the setting of the rotating motor 3 21, the rotation of the rotating motor 3 21 can drive the turntable 22 fixedly connected thereto to rotate.

[0045] The bottom of the turntable 1 22 is evenly and fixedly connected with a hydraulic telescopic rod 23, and the bottom of the hydraulic telescopic rod 23 is fixedly connected with a connecting block 30, and the connecting block 30 is movably connected to the middle part of the top of the moving block 24. Through the setting of the hydraulic telescopic rod 23, the extension and retraction of the hydraulic telescopic rod 23 can change the height of the moving block 24 in the vertical direction, and the rotation of the moving block 24 will not affect the hydraulic telescopic rod 23.

[0046] The bottom of the moving block 24 is fixedly connected with a processing drill bit 20. A through hole 34 adapted to the processing drill bit 20 is provided on one side of the bottom of the sealing housing 9, and a rotating block 27 adapted to the moving block 24 is movably connected to the top of the through hole 34, and a gear ring 28 is fixedly connected to the outer ring of the rotating block 27, and a rotating motor 25 is fixedly connected to the inner cavity of the sealing housing 9, and a gear 26 is fixedly connected to the end of the output shaft of the rotating motor 25, and the gear 26 is meshed with the gear ring 28. Through the setting of the rotating motor 25, the rotation of the rotating motor 25 can drive the gear 26 fixedly connected thereto to rotate, and the gear 26 can drive the rotating block 27 to rotate through the gear ring 28 meshed therewith.

[0047] The inner cavity of the rotating block 27 is adapted to the moving block 24, and a signal receiver 29 is provided on one side of the moving block 24. A signal generator 31 adapted to the signal receiver 29 is provided at the bottom of the inner cavity of the rotating block 27. Through the arrangement of the signal receiver 29 and the signal generator 31, when the signal emitted by the signal generator 31 is received by the signal receiver 29 above it, the moving block 24 and the rotating block 27 are in an aligned state, and the extension of the hydraulic telescopic rod 8 can insert the moving block 24 into the inner cavity of the rotating block 27. The rotation of the rotating block 27 can drive the moving block 24 to rotate, and the moving block 24 drives the processing drill bit 20 fixedly connected thereto to rotate, so as to realize the drilling of the rods for producing the permanent and temporary combined balcony guardrails.

[0048] From the above description of the drill bit structure, it can be seen that when the device is in use, the rotation of the turntable 22 can change the position between two adjacent processing drill bits 20, so that the drill bit can be quickly replaced without disassembling the drill bit, thereby improving the efficiency of drill bit replacement.

[0049] One end of the fixed workbench 1 is movably connected with a rotating rod, and the end of the rotating rod close to the drill bit structure is fixedly connected to a rotating workbench 2, and a rotating motor 18 is fixed on the fixed workbench 1, and the end of the output shaft of the rotating motor 18 is fixedly connected to the other end of the rotating rod through a reducer. Through the setting of the rotating motor 18, the rotation of the rotating motor 18 can drive the rotating rod fixedly connected to it to rotate, and the rotating rod can drive the rotating workbench 2 fixedly connected to it to rotate, and the rotating workbench 2 is located below the processing drill bit 20. During the use of the equipment, the rods for producing the permanent and temporary combined balcony guardrails are processed on the rotating workbench 2. Therefore, when the rotating workbench 2 rotates, the processing debris scattered on the rotating workbench 2 can be separated from the rotating workbench 2 under the action of gravity, so that the debris dropped on the rotating workbench 2 can be quickly cleaned up.

[0050] A collecting box 14 is placed on one side of the fixed workbench 1 close to the rotating rod. The collecting box 14 is located below the rotating workbench 2. The collecting box 14 can be used to collect the debris generated during the processing, so as to facilitate the unified processing of the debris.

[0051] A double-headed ball screw 15 is movably connected to the rotating worktable 2, and the outer rings at both ends of the double-headed ball screw 15 are threadedly connected to the support rod 12, and one end of the rotating worktable 2 is fixedly connected to a rotating motor 11, and the end of the output shaft of the rotating motor 11 is fixedly connected to the end of the double-headed ball screw 15 through a reducer. Through the setting of the rotating motor 11, the rotation of the rotating motor 11 can drive the double-headed ball screw 15 fixedly connected thereto to rotate, and the rotation of the double-headed ball screw 15 can make the support rod 12 threadedly connected thereto move in the direction where the double-headed ball screw 15 is located, and the distance between the two support rods 12 can be changed.

[0052] The other end of the support rod 12 away from the collecting box 14 is provided with a workpiece limiting structure 1, which includes a first rotating shaft 38 movably connected to the middle of the other end of the support rod 12, a second turntable 37 and a second vacuum pump 42.

[0053] One end of the first rotating shaft 38 away from the drill bit structure is fixedly connected to a rotating motor 4 13, and the end of the output shaft of the rotating motor 4 13 is fixedly connected to the first rotating shaft 38 through a reducer, and the other end of the first rotating shaft 38 is fixedly connected to a turntable 2 37, and the other end of the turntable 2 37 is evenly fixedly connected to a positioning vacuum suction cup 19. Through the setting of the rotating motor 4 13, the rotation of the rotating motor 4 13 can change the position of the positioning vacuum suction cup 19, so that when the equipment is in use, the workpiece limiting structure 1 can lift and position workpieces of various sizes.

[0054] The inner cavity of the positioning vacuum suction cup 19 is an arc-shaped structure, and the inner diameter of the positioning vacuum suction cup 19 is adapted to the outer diameter of the production rod of the permanent and temporary combined balcony guardrail to be drilled. The first rotating shaft 38 is a hollow structure, and the vacuum pump 42 is located in the inner cavity of the first rotating shaft 38. The side wall of the first rotating shaft 38 is evenly provided with air inlet and outlet holes. The turntable 37 is provided with an air duct 44, one end of the air duct 44 is in contact with the air inlet end of the positioning vacuum suction cup 19, and the other end of the air duct 44 is fixedly connected to the end of the vacuum tube 2 away from the air inlet end of the vacuum pump 2 42, and an electric ball valve is provided at one end of the vacuum tube 2. Through the setting of the vacuum pump 2 42, the operation of the vacuum pump 2 42 can remove the air between the positioning vacuum suction cup 19 and the workpiece in contact with it, so that the workpiece is connected to the positioning vacuum suction cup 19 under negative pressure, thereby fixing the workpiece and facilitating the rotating worktable 2 to drive the workpiece to rotate.

[0055] A fixing sleeve 36 is evenly fixed on one side of the turntable 2 37 close to the first rotating shaft 38, and a hydraulic telescopic rod 3 16 is connected to the inner cavity of the fixing sleeve 36 by bolts. An inner suction cup 40 adapted to the workpiece is fixed to the output end of the hydraulic telescopic rod 3 16, and a vacuum pump 1 39 is fixed to the other end of the hydraulic telescopic rod 3 16. The inner suction cup 40 is connected to the air inlet end of the vacuum pump 1 39 through a vacuum tube 1, and another electric ball valve is provided at one end of the vacuum tube 1, and the inner suction cup 40 and the positioning vacuum suction cup 19 are located at the hydraulic telescopic rod 3 On the same side of 16, through the arrangement of the inner suction cup 40 and the vacuum pump 1, the operation of the vacuum pump 1 can make the inner suction cup 40 and the workpiece in contact with it connected with negative pressure. Therefore, when using the equipment to drill the inner adjustment column and the outer adjustment column of the balcony railing listed in the background technology, the inner adjustment column and the outer adjustment column can be put together, and the positioning vacuum suction cup 19 can be used to fix the outer adjustment column, and the inner suction cup 40 can be used to fix the inner adjustment column, so that the inner adjustment column and the outer adjustment column can be drilled at the same time, thereby improving the drilling efficiency.

[0056] The other end of the support rod 12 close to the collection box 14 is provided with a workpiece limiting structure 2, which includes a second rotating shaft and a rotating motor 5 17 movably connected to the other end of the support rod 12 close to the collection box 14, the rotating motor 5 17 is fixedly connected to the end of the support rod 12 away from the workpiece limiting structure 1, the output shaft end of the rotating motor 5 17 is fixedly connected to the second rotating shaft through a reducer, the other end of the second rotating shaft is fixedly connected to a turntable 3 41, another fixed sleeve 36 is evenly fixed on the side of the turntable 3 41 close to the second rotating shaft, a hydraulic telescopic rod 4 32 is fixed in the inner cavity of the other fixed sleeve 36, the other end of the hydraulic telescopic rod 4 32 is fixedly connected to a support block 33, and the other end of the turntable 3 41 is evenly fixed with a positioning block 35 adapted to the workpiece. By setting the positioning block 35 and the positioning vacuum suction cup 19, the positioning block 35 and the positioning vacuum suction cup 19 can position the end of the workpiece to facilitate the placement of the workpiece. Turntable two and turntable three 41 can clamp and fix the workpiece to facilitate drilling of the workpiece. By setting the hydraulic telescopic rod four 32, the extension of the hydraulic telescopic rod four 32 can change the position of the support block 33 fixedly connected thereto. The coordinated use of the support block 33 and the inner suction cup 40 can achieve the clamping and fixing of the workpiece.

[0057] A support plate 10 is fixed to one side of the fixed workbench 1 close to the rotating workbench 2. When the rotating workbench 2 is in a horizontal state, the support plate 10 supports the rotating workbench 2. That is, when the equipment is in operation, the support plate 10 can support the rotating workbench 2, which is beneficial to improving the stability of the rotating workbench 2.

[0058] The electrical components involved in this application are all prior art, and technicians in this field are familiar with their connection methods. Through these technicians, all the electrical components in this application are connected to their compatible power supplies through wires, and according to the actual situation, a suitable controller is selected to meet the control requirements. The specific connection and control sequence are described below. The electrical connection is completed in a sequential working order, and the detailed connection means are well known in the art. The following mainly introduces the working principle and process, and no further explanation of the electrical control is given.

[0059] The balcony guardrail is manufactured using the above disclosed permanent and temporary combined balcony guardrail manufacturing equipment, comprising the following steps:

[0060] Step 1: The staff adjusts the distance between the workpiece limiting structure 1 and the workpiece limiting structure 2 according to the demand, so that the distance between the turntable 2 37 and the turntable 3 41 is not greater than the length value of the rod for producing the permanent and temporary combined balcony guardrail, and adjusts the positions of the positioning vacuum suction cup 19 and the positioning block according to the demand, so that the positioning vacuum suction cup 19 and the positioning block for lifting the workpiece are adapted to the rod;

[0061] Step 2: The staff puts one end of the rod for producing the permanent and temporary combined balcony guardrail on the matching positioning block 35, and the other end of the rod on the matching positioning vacuum suction cup 19, and starts the rotating motor 11. The operation of the rotating motor 11 shortens the distance between the two support rods 12 until the turntable 37 and the turntable 41 are tightly fitted with the end of the workpiece, and the turntable 37 and the turntable 41 are used to clamp and fix the workpiece;

[0062] Step 3, the processing drill bit 20 adapted to the workpiece is moved to the outside of the sealed shell 9 through the through hole 34, the extension and retraction of the hydraulic telescopic rod 1 8 can change the height of the processing drill bit 20, the rotation of the rotating motor 4 25 can drive the rotating block 27 to rotate, and the rotating block 27 can drive the processing drill bit 20 to rotate through the moving block 24. The coordinated use of the hydraulic telescopic rod 1 8 and the rotating motor 4 25 can realize the processing drill bit 20 to drill the workpiece, and during the drilling process, if the processing drill bit 20 needs to be replaced, the hydraulic telescopic rod 23 located above the rotating block 27 is retracted until it is exposed. The processing drill bit 20 outside moves to the top of the rotating block 27, and the rotating motor 3 21 drives the turntable 1 22 to rotate. The rotation of the turntable 1 22 changes the position of the processing drill bit 20 until the corresponding processing drill bit 20 moves to the top of the rotating block 27. The rotating block 27 rotates, and the rotation of the rotating block 27 drives the signal generator 31 to rotate until the signal receiver 29 located above the signal generator 31 receives the signal, so that the rotating block 27 is aligned with the moving block 24, and the hydraulic telescopic rod 23 is extended, so that the processing drill bit 20 can be exposed, so that the processing drill bit 20 can be quickly replaced;

[0063] Step 4: The translation structure works. The translation structure works to change the position of the processing drill bit 20 so that the processing drill bit 20 can drill holes at different positions of the workpiece. During the drilling process, the rotary motor 4 13 and the rotary motor 5 17 rotate simultaneously to change the drilling position of the workpiece.

[0064] Step 5: After drilling, the debris remaining inside the rod and the debris on the workpiece table are cleaned. If the rod is a solid structure, the rotary motor 4 13 and the rotary motor 5 17 drive the workpiece to rotate so that the drilling part of the workpiece faces downward, and the debris left in the drilled hole is dumped out; if the rod is a tubular structure, the vacuum pump 2 42 is operated, and the operation of the vacuum pump 2 42 makes the processed workpiece and the positioning vacuum suction cup 19 negatively connected, the double-headed ball screw 15 rotates, so that the positioning block is separated from the rod, and the rotary motor 18 rotates, and the rotary motor 18 drives the rotary table 2 to rotate, and the rotary table 2 and the debris remaining inside the tubular rod fall into the miscellaneous collection box 14 under the action of gravity, so that the rod and the rotary table 2 are cleaned at the same time;

[0065] Step 6. Remove the drilled rods and use bolts to assemble the rods into a permanent and temporary balcony guardrail.

[0066] From the above description, it can be known that when the manufacturing equipment is drilling holes in the rods for producing the permanent and temporary combined balcony guardrails, the setting of the drill bit structure can realize the rapid replacement of the processing drill bit, thereby improving the drilling efficiency of the equipment for the permanent and temporary combined balcony guardrails; by setting the rotating motor 1 and the workpiece limiting structure 1, the rotating worktable and the workpiece can be rotated simultaneously, and the debris remaining on both the workpiece and the rotating worktable 2 can fall into the collection box 14 under the action of gravity, thereby improving the debris cleaning efficiency; by setting the inner suction cup, the support block, the positioning vacuum suction cup and the positioning block, the two rods that are nested together can be fixed at the same time, so that the two rods can be drilled at the same time, thereby improving the drilling efficiency of the rods; by setting the rotating motor 2 6, the processing drill bit can be staggered with the rod and the rotating worktable 2, thereby facilitating the rotation of the rotating worktable 2 and the rod.

[0067] The standard parts used in the present invention can all be purchased from the market, and special-shaped parts can be customized according to the description in the specification and the drawings. The specific connection methods of each part adopt conventional means such as mature bolts, rivets, welding, etc. in the prior art. Machinery, parts and equipment all adopt conventional models in the prior art and will not be described in detail here. The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field. Although the embodiments of the present invention have been shown and described, it can be understood by ordinary technicians in this field that various changes, modifications, substitutions and modifications can be made to these embodiments without departing from the principle and spirit of the present invention. The scope of the present invention is defined by the attached claims and their equivalents.

Claims

1. A manufacturing device for a permanent and temporary balcony guardrail, comprising a fixed workbench (1) and a collection box (14), characterized in that: The top of the fixed workbench (1) is connected to a moving rod (5) through a translation structure, and the top of the moving rod (5) is connected to a rotating rod (7) through a rotating motor 2, and the other end of the rotating rod (7) is connected to a drill structure through a hydraulic telescopic rod 1 (8), and the fixed workbench (1) is movably connected to a rotating workbench (2) on a side close to the drill structure, and a double-headed ball screw (15) is movably connected to the rotating workbench (2), and the outer rings of both ends of the double-headed ball screw (15) are threadedly connected to support rods (12), and the other end of one of the support rods (12) is provided with a workpiece limiting structure 1, and the other end of the other support rod (12) is provided with a workpiece limiting structure 2, and the collection box (14) is located on a side of the rotating workbench (2) away from the workpiece limiting structure 1; The drill bit structure comprises a sealed shell (9) fixedly connected to the bottom of a hydraulic telescopic rod (8); a turntable (22) is movably connected in the inner cavity of the sealed shell (9); a hydraulic telescopic rod (23) is evenly arranged at the bottom of the turntable (22); a moving block (24) is movably connected at the bottom of the hydraulic telescopic rod (23); a processing drill bit (20) is arranged at the bottom of the moving block (24); a signal receiver (29) is arranged on one side of the moving block (24); a through hole (34) adapted to the processing drill bit (20) is arranged on one side of the bottom of the sealed shell (9); a rotating block (27) adapted to the moving block (24) is movably connected at the top of the through hole (34); a signal generator (31) adapted to the signal receiver (29) is arranged at the bottom of the inner cavity of the rotating block (27); The workpiece limiting structure 1 comprises a first rotating shaft (38) movably connected to a support rod (12), a vacuum pump 2 (42) and a turntable 2 (37) fixedly connected to the first rotating shaft (38); a fixing sleeve (36) is evenly fixed on one side of the turntable 2 (37) close to the first rotating shaft (38); a hydraulic telescopic rod 3 (16) is connected to the inner cavity of the fixing sleeve (36) by bolts; an inner suction cup (40) adapted to the workpiece is fixed to the output end of the hydraulic telescopic rod 3 (16); a vacuum pump 1 (39) is fixed to the other end of the hydraulic telescopic rod 3 (16); the inner suction cup (40) is connected to the air inlet end of the vacuum pump 1 (39) by a vacuum tube 1; a positioning vacuum suction cup (19) adapted to the outer diameter of the workpiece is evenly fixed to the other end of the turntable 2 (37); the positioning vacuum suction cup (19) is connected to the air inlet end of the vacuum pump 2 (42) by a vacuum tube 2 (43); The workpiece limiting structure 2 comprises a second rotating shaft movably connected to another supporting rod (12) and a turntable 3 (41) fixedly connected to the second rotating shaft, another fixed sleeve (36) is evenly fixed on one side of the turntable 3 (41) close to the second rotating shaft, a hydraulic telescopic rod 4 (32) is fixed in the inner cavity of the other fixed sleeve (36), the other end of the hydraulic telescopic rod 4 (32) is fixedly connected to a supporting block (33), and the other end of the turntable 3 (41) is evenly fixed with a positioning block (35) adapted to the workpiece.

2. The manufacturing equipment of a permanent and temporary combined balcony guardrail according to claim 1 is characterized in that: A rotating rod is movably connected to the middle of the rotating workbench (2) near one end of the collecting box (14), and the other end of the rotating rod is movably connected to the fixed workbench (1). A rotating motor (18) is fixed on the fixed workbench (1), and the end of the output shaft of the rotating motor (18) is fixedly connected to the other end of the rotating rod.

3. The manufacturing equipment of a permanent and temporary combined balcony guardrail according to claim 1 is characterized in that: The top of the moving rod (5) is fixedly connected to a second rotating motor (6), and the output shaft end of the second rotating motor (6) is fixedly connected to an end of the rotating rod (7) away from the first hydraulic telescopic rod (8).

4. The manufacturing equipment of the permanent and temporary combined balcony guardrail according to claim 1 is characterized in that: A rotating motor three (21) is fixedly connected to the bottom of the inner cavity of the sealed housing (9), the output shaft end of the rotating motor three (21) is fixedly connected to the middle of the bottom of the turntable one (22), a rotating motor four (25) is fixedly connected to the inner cavity of the sealed housing (9), the output shaft end of the rotating motor four (25) is fixedly connected to a gear (26), the outer ring of the rotating block (27) is fixedly connected to a gear ring (28), and the gear (26) is meshed with the gear ring (28).

5. The manufacturing equipment of the permanent and temporary combined balcony guardrail according to claim 1 is characterized in that: The middle part of the top of the moving block (24) is movably connected to a connecting block (30), and the top of the connecting block (30) is fixedly connected to the bottom of the second hydraulic telescopic rod (23).

6. The manufacturing equipment of the permanent and temporary combined balcony guardrail according to claim 1 is characterized in that: The workpiece limiting structure one also includes a rotating motor four (13), and the end of the output shaft of the rotating motor four (13) is fixedly connected to the end of the first rotating shaft (38) away from the turntable two; the workpiece limiting structure two also includes a rotating motor five (17), and the end of the output shaft of the rotating motor five (17) is fixedly connected to the end of the second rotating shaft away from the turntable three (41).

7. The manufacturing equipment of the permanent and temporary combined balcony guardrail according to claim 1 is characterized by: The first rotating shaft (38) is a hollow structure, the vacuum pump 2 (42) is located in the inner cavity of the first rotating shaft (38), and the side wall of the first rotating shaft (38) is evenly provided with air inlet and outlet holes. The turntable 2 (37) is provided with an air duct (44), one end of the air duct (44) is in contact with the air inlet end of the positioning vacuum suction cup (19), and the other end of the air duct (44) is fixedly connected to the end of the vacuum tube 2 away from the air inlet end of the vacuum pump 2 (42); one end of both the vacuum tube 1 and the vacuum tube 2 (43) is provided with an electric ball valve.

8. The manufacturing equipment of the permanent and temporary combined balcony guardrail according to claim 1 is characterized by: A support plate (10) is fixed on one side of the fixed workbench (1) close to the rotating workbench (2); when the rotating workbench (2) is in a horizontal state, the support plate (10) supports the rotating workbench (2).

9. A method for manufacturing a permanent and temporary combined balcony guardrail according to any one of claims 1 to 8, characterized in that: The following steps are involved: Step 1: The staff adjusts the distance between the workpiece limiting structure 1 and the workpiece limiting structure 2 according to the demand, so that the distance between the turntable 2 (37) and the turntable 3 (41) is not greater than the length value of the rod for producing the permanent and temporary combined balcony guardrail, and adjusts the positions of the positioning vacuum suction cup (19) and the positioning block according to the demand, so that the positioning vacuum suction cup (19) and the positioning block for lifting the workpiece are adapted to the rod; Step 2: The staff puts one end of the rod for producing the permanent and temporary combined balcony guardrail on a positioning block (35) adapted thereto, and the other end of the rod on a positioning vacuum suction cup (19) adapted thereto, and starts the second rotating motor (11). The operation of the second rotating motor (11) shortens the distance between the two supporting rods (12) until the second rotating disc (37) and the third rotating disc (41) are closely fitted with the end of the workpiece, and the second rotating disc (37) and the third rotating disc (41) are used to clamp and fix the workpiece; Step 3: The processing drill bit (20) adapted to the workpiece is moved to the outside of the sealed housing (9) through the through hole (34). The extension and retraction of the hydraulic telescopic rod 1 (8) can change the height of the processing drill bit (20). The rotation of the rotating motor 4 (25) can drive the rotating block (27) to rotate. The rotating block (27) can drive the processing drill bit (20) to rotate through the moving block (24). The coordinated use of the hydraulic telescopic rod 1 (8) and the rotating motor 4 (25) can realize the processing drill bit (20) to perform a drilling operation on the workpiece. During the drilling process, if the processing drill bit (20) needs to be replaced, the hydraulic telescopic rod 2 (23) located above the rotating block (27) is retracted until it is exposed to the outside. The processing drill bit (20) moves to the top of the rotating block (27), the rotating motor (21) drives the turntable (22) to rotate, and the rotation of the turntable (22) causes the position of the processing drill bit (20) to change, until the corresponding processing drill bit (20) moves to the top of the rotating block (27), the rotating block (27) rotates, and the rotation of the rotating block (27) drives the signal generator (31) to rotate until the signal receiver (29) located above the signal generator (31) receives the signal, so that the rotating block (27) and the moving block (24) are aligned, and the hydraulic telescopic rod (23) is extended, so that the processing drill bit (20) can be exposed, so that the processing drill bit (20) can be quickly replaced; Step 4: The translation structure works. The translation structure works to change the position of the processing drill bit (20), so that the processing drill bit (20) can drill holes at different positions of the workpiece. During the drilling process, the rotary motor 4 (13) and the rotary motor 5 (17) rotate simultaneously to change the drilling position of the workpiece. Step 5: After drilling, the debris remaining inside the rod and the debris on the workpiece table are cleaned. If the rod is a solid structure, the rotary motor four (13) and the rotary motor five (17) drive the workpiece to rotate so that the drilling part of the workpiece faces downward, and the debris remaining in the drilled hole is dumped out; if the rod is a tubular structure, the vacuum pump two (42) is operated, and the operation of the vacuum pump two (42) causes the processed workpiece to be negatively connected to the positioning vacuum suction cup (19), and the double-headed ball screw (15) rotates to separate the positioning block from the rod, and the rotary motor one (18) rotates, and the rotary motor one (18) drives the rotary table (2) to rotate, and the rotary table (2) and the debris remaining inside the tubular rod fall into the debris collection box (14) under the action of gravity, so that the rod and the rotary table (2) are cleaned at the same time; Step 6. Remove the drilled rods and use bolts to assemble the rods into a permanent and temporary balcony guardrail.