Anti-leakage structure for pipeline penetrating part of underground garage roof and construction technology of anti-leakage structure

Through the multi-layer construction process of fine stone anti-cracking slightly expanded waterproof concrete, leak-proofing agent, asphalt ointment, steel casing and other materials, the leakage problem of the underground garage roof pipe passing through is solved, and a stronger waterproof effect is achieved. and construction quality to ensure rapid water drainage and waterproof performance.

CN118774174AInactive Publication Date: 2024-10-15CHINA MCC17 GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410940020.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Leakage often occurs at the location where pipes pass through the roof of underground garages. The existing waterproof and anti-leakage structure is insufficient, resulting in failure after disturbance and unable to effectively prevent water leakage.

Method used

Materials such as fine stone anti-cracking micro-expansion waterproof concrete, leak-proofing king, asphalt ointment and steel casing are used, combined with multi-layer construction technology to ensure the sealing strength and waterproofing effect between the pipeline and the steel casing, and the addition of water-stopping steel plates To enhance the connection strength and achieve rapid drainage through the flow slope design of the asphalt paste.

Benefits of technology

Significantly improves the waterproof and anti-leakage performance of the underground garage roof pipe passing through, ensuring construction quality and waterproofing effect, extending the path of leaking water, ensuring that water can flow away quickly, and effectively preventing water leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774174A_ABST
    Figure CN118774174A_ABST
Patent Text Reader

Abstract

The invention discloses an underground garage top plate pipeline penetrating part anti-seepage structure and a construction technology thereof, and relates to the technical field of underground garages. The underground garage top plate pipeline penetrating part anti-seepage structure comprises a leveling layer, an underground garage top plate is arranged below the leveling layer, a water stop steel plate is arranged in the underground garage top plate, a pipeline is arranged on the underground garage top plate in a penetrating mode, and fine stone anti-crack micro-expansion waterproof concrete is arranged on the surface of the pipeline. According to the underground garage top plate pipeline penetrating part anti-seepage structure and the construction technology thereof, the upper portion and the lower portion of a gap between a pipeline and a steel sleeve are blocked through two materials, and the blocking strength of the gap between the pipeline and the steel sleeve is guaranteed through fine stone anti-crack micro-expansion waterproof concrete on the lower portion; and the waterproof effect of plugging the gap between the pipeline and the steel sleeve is guaranteed through plugging of the upper plugging agent. And each material is constructed twice, so that the construction quality is effectively ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of underground garages, and in particular to an anti-leakage structure for a pipe passing through a roof of an underground garage and a construction process thereof. Background Art

[0002] After domestic underground garages are put into use, leakage often occurs at the pipe-through parts. In order to avoid such problems, various construction companies pay special attention to the waterproof and anti-leakage treatment of the pipe-through parts on the roof of underground garages. However, many years of engineering practice have shown that this part is still a frequent site for water leakage. The main reason is that the anti-leakage structure of the pipe-through parts on the roof of underground garages is too simple. When disturbance occurs at this part, the original waterproof structure fails, resulting in leakage. Based on the above problems, the present invention hopes to provide an anti-leakage structure for the pipe-through parts on the roof of underground garages and its construction process, so as to improve the waterproof and anti-leakage performance of the pipe-through parts on the roof of underground garages. Summary of the invention

[0003] 1. Technical issues to be resolved

[0004] In view of the deficiencies in the prior art, the present invention provides an anti-leakage structure for a pipe passing portion on a roof of an underground garage and a construction process thereof, thereby solving the problems existing in the prior art.

[0005] (II) Technical solution

[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: an anti-leakage structure for the pipe passing part of the underground garage roof, comprising a leveling layer, an underground garage roof is arranged below the leveling layer, a water-stop steel plate is arranged inside the underground garage roof, a pipe is penetrated through the underground garage roof, fine stone anti-crack micro-expansive waterproof concrete is arranged on the surface of the pipe, asphalt paste is arranged above the fine stone anti-crack micro-expansive waterproof concrete, a steel casing is arranged on the fine stone anti-crack micro-expansive waterproof concrete, and a leak-proof king is arranged on the asphalt paste.

[0007] Preferably, the fine stone anti-cracking micro-expansion waterproof concrete is provided with a concrete chamfer, and the surface of the concrete chamfer is provided with a roll material waterproof additional layer, an outer roll material waterproof and a mesh painted waterproof protective layer in sequence from the inside to the outside.

[0008] Preferably, a reinforced fine stone concrete waterproof protective layer is provided on the fine stone anti-cracking micro-expansion waterproof concrete.

[0009] A construction process for an anti-leakage structure for a pipe passing through a roof of an underground garage, comprising the anti-leakage structure for a pipe passing through a roof of an underground garage as described above, and the specific operations are as follows:

[0010] Step 1: Pre-embed the steel casing. The steel casing is pre-embedded before the construction of the underground garage roof, and a water-stop steel plate is set in the middle of the underground garage roof.

[0011] Step 2: When pouring concrete for the underground garage roof, the original concrete slurry is leveled and polished to form a leveling layer.

[0012] Step 3: Install the pipes through the ceiling of the underground garage.

[0013] Step 4: Pour fine stone anti-cracking and micro-expansion waterproof concrete in two layers in the lower part / range of the gap between the pipeline and the steel casing.

[0014] Step 5: The gap between the pipeline and the steel casing is sealed with two layers of plugging king on the upper part / range, and the upper surface of the second layer of plugging should be high inside and low outside, with a water flow slope ≥%.

[0015] Step 6: Pour concrete chamfers at the junction of the steel casing and the leveling layer (underground garage roof surface layer 13).

[0016] Step 7: Construction of waterproofing of steel casing and underground garage roof. First, construct the additional layer of waterproofing, which is required to be wider than the inner corner (250) mm, and then construct the outer waterproofing layer, which is divided into two layers.

[0017] Step 8: Seal the upper surface with asphalt paste.

[0018] Step 9: Construction of reinforced fine stone concrete waterproof protective layer on the roof of the underground garage.

[0019] Step 10: Hang a mesh on the steel casing and paint a waterproof protective layer. The mesh is an alkali-resistant mesh cloth.

[0020] (III) Beneficial effects

[0021] The present invention provides an anti-leakage structure for the pipe passing part of the roof of an underground garage and its construction process. It has the following beneficial effects:

[0022] The anti-leakage structure and construction technology of the underground garage roof pipe passing part, the gap between the pipe and the steel casing is blocked with two materials, the lower fine stone anti-crack micro-expansion waterproof concrete ensures the blocking strength of the gap between the pipe and the steel casing; the upper leak-proof plugging ensures the waterproof effect of the gap between the pipe and the steel casing. Each material is constructed twice to effectively ensure the construction quality;

[0023] The water-stop steel plate is set in the middle of the structural plate to increase the connection strength between the steel casing and the roof of the underground garage, and greatly increase the path of water leakage, which has a good waterproof effect;

[0024] Asphalt paste is added to the upper surface of the plug and combined with the second layer of plugging, the upper surface should be high inside and low outside with a water flow slope of ≥20%. In this way, when water encounters water on the upper part, the water can flow away quickly, playing a good role in drainage and waterproofing. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the structure of the present invention.

[0026] Figure numerals: 1. Steel casing, 2. Water-stop steel plate, 3. Pipeline, 4. Fine stone anti-cracking and micro-expanding waterproof concrete, 5. Leak-proof king, 6. Concrete chamfer, 7. Additional layer of rolled waterproofing, 8. Outer layer of rolled waterproofing, 9. Asphalt paste, 10. Reinforced fine stone concrete waterproofing protective layer, 11. Mesh painting waterproofing protective layer, 12. Underground garage roof, 13. Leveling layer. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] See also Figure 1 The present invention provides a technical solution: an anti-leakage structure for a pipe passing through a part of an underground garage roof, comprising a leveling layer 13, an underground garage roof 12 is arranged below the leveling layer 13, a water-stop steel plate 2 is arranged inside the underground garage roof 12, a pipe 3 is arranged through the underground garage roof 12, a fine stone anti-crack micro-expansion waterproof concrete 4 is arranged on the surface of the pipe 3, an asphalt paste 9 is arranged above the fine stone anti-crack micro-expansion waterproof concrete 4, a steel casing 1 is arranged on the fine stone anti-crack micro-expansion waterproof concrete 4, and a leak-proof king 5 is arranged on the asphalt paste 9;

[0029] A concrete chamfer 6 is arranged on the fine stone anti-crack micro-expansion waterproof concrete 4, and a roll waterproof additional layer 7, an outer roll waterproof 8 and a mesh painted waterproof protective layer 11 are arranged on the surface of the concrete chamfer 6 in sequence from the inside to the outside;

[0030] A reinforced fine stone concrete waterproof protective layer 10 is provided on the fine stone anti-cracking micro-expansion waterproof concrete 4;

[0031] A construction process for an anti-leakage structure for a pipe passing through a roof of an underground garage, comprising the anti-leakage structure for a pipe passing through a roof of an underground garage, and the specific operations are as follows:

[0032] Step 1: pre-embed the steel casing 1. The steel casing 1 is pre-embedded before the construction of the underground garage roof 12, and a water-stop steel plate 2 is set in the middle of the underground garage roof 12.

[0033] Step 2: During the pouring of concrete for the underground garage roof 12, the original concrete slurry is leveled and polished to form a leveling layer.

[0034] Step 3: Install pipe 3 through the underground garage roof 12.

[0035] Step 4: Pour the fine stone anti-cracking micro-expansion waterproof concrete 4 in two layers within the lower 2 / 3 of the gap between the pipeline 3 and the steel casing 1.

[0036] Step 5: The upper 1 / 3 of the gap between the pipeline 3 and the steel casing 1 is sealed with a leak-proof king 5 in two layers, and the upper surface of the second layer should be high inside and low outside, with a water flow slope ≥ 20%.

[0037] Step 6: pouring concrete chamfer 6 at the junction of steel casing 1 and top plate surface layer 13 of underground garage at leveling layer.

[0038] Step 7: Waterproofing of steel casing 1 and underground garage roof 12. First, construct additional waterproofing layer 7, requiring the width of additional waterproofing layer 7 to exceed 250mm of the inner corner, and then construct outer waterproofing layer 8, which is divided into two layers.

[0039] Step 8: Use the leak stopper 5 to seal the upper surface with asphalt paste 9 to close the construction.

[0040] Step nine: Construction of reinforced fine stone concrete waterproof protective layer 10 on the roof 12 of the underground garage.

[0041] Step 10: A waterproof protective layer 11 is constructed by painting a mesh on the steel casing 1, and the mesh is an alkali-resistant mesh cloth.

[0042] In summary, the anti-leakage structure and construction process of the underground garage roof pipe passing part, the gap between the pipe and the steel casing is blocked with two materials at the top and bottom. The lower fine stone anti-crack micro-expansion waterproof concrete ensures the blocking strength of the gap between the pipe and the steel casing; the upper leak-proof plugging ensures the waterproof effect of the gap between the pipe and the steel casing. Each material is constructed twice to effectively ensure the construction quality;

[0043] The water-stop steel plate is set in the middle of the structural plate to increase the connection strength between the steel casing and the roof of the underground garage, and greatly increase the path of water leakage, which has a good waterproof effect;

[0044] Asphalt paste is added to the upper surface of the plug and combined with the second layer of plugging, the upper surface should be high inside and low outside with a water flow slope of ≥20%. In this way, when water encounters water on the upper part, the water can flow away quickly, playing a good role in drainage and waterproofing.

[0045] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0046] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A leakage-proof structure for a pipe-through-point on the roof of an underground garage, comprising a leveling layer (13), Features: An underground garage roof (12) is arranged below the leveling layer (13), a water-stopping steel plate (2) is arranged inside the underground garage roof (12), a pipeline (3) is arranged through the underground garage roof (12), a fine stone anti-cracking micro-expansion waterproof concrete (4) is arranged on the surface of the pipeline (3), asphalt grease (9) is arranged above the fine stone anti-cracking micro-expansion waterproof concrete (4), a steel casing (1) is arranged on the fine stone anti-cracking micro-expansion waterproof concrete (4), and a leak-proofing agent (5) is arranged on the asphalt grease (9).

2. According to claim 1, an anti-leakage structure for pipes passing through the roof of an underground garage, Features: The fine stone anti-cracking micro-expansion waterproof concrete (4) is provided with a concrete chamfer (6), and the surface of the concrete chamfer (6) is provided with a roll material waterproof additional layer (7), an outer layer of roll material waterproof (8) and a mesh painted waterproof protective layer (11) in sequence from the inside to the outside.

3. The anti-leakage structure for the pipe passing through the roof of an underground garage according to claim 1, Features: A reinforced fine-stone concrete waterproof protective layer (10) is provided on the fine-stone anti-cracking micro-expansion waterproof concrete (4).

4. A construction process for anti-leakage structure of underground garage roof pipe penetration part, Features: The anti-leakage structure for the pipe passing through the roof of the underground garage according to claim 1 is specifically operated as follows: Step 1: pre-embed the steel casing (1). The steel casing (1) is pre-embedded before the construction of the underground garage roof (12), and a water-stop steel plate (2) is set in the middle of the steel casing (1) on the underground garage roof (12). Step 2: During the concrete pouring construction of the underground garage roof (12), the original concrete slurry is leveled and polished to form a leveling layer. Step 3: Install the pipe (3) through the underground garage roof (12). Step 4: Fine stone anti-cracking micro-expansion waterproof concrete (4) is poured in two layers within the lower part (2) / (3) of the gap between the pipeline (3) and the steel casing (1). Step 5: The gap between the pipeline (3) and the steel casing (1) is sealed with a leak-proof plug (5) in two layers, and the upper surface of the second layer should be higher inside and lower outside, with a water flow slope of ≥ (20)%. Step 6: pouring concrete chamfer (6) at the junction of the steel casing (1) and the leveling layer (underground garage roof surface layer 13). Step 7: Construction of waterproofing with roll material on steel casing (1) and underground garage roof (12). First, construct the additional layer of waterproofing with roll material (7), which is required to have a width exceeding the inner corner (250) mm, and then construct the outer layer of waterproofing with roll material (8), which is divided into two layers. Step 8: Use the leak stopper (5) to seal the upper surface with asphalt paste (9) to complete the construction. Step 9: Construction of a reinforced fine stone concrete waterproof protective layer (10) on the underground garage roof (12). Step 10: A waterproof protective layer (11) is constructed by painting a mesh on the steel casing (1), wherein the mesh is an alkali-resistant mesh cloth.

Citation Information

Patent Citations

  • Floor board pipeline waterproof structure

    CN202532026U

  • Waterproof structure for pipeline penetrating garage top plate

    CN217601894U

  • Underground outer wall pipeline plugging structure

    CN221145577U

  • Waterproof treatment method for root of pipeline through wall or floor

    WO2022143062A1