Method for penetrating steel columns of metallurgical technically-improved factory building through multiple layers of floor slabs under wet and soft foundation condition

By using the method of embedding permanent steel formwork and segmented construction under wet and soft ground conditions, the problem of difficulty in constructing steel columns passing through multi-floor slabs and the risk of water leakage in metallurgical plant buildings was solved, and high-quality steel column foundation installation and Improved construction operability.

CN118774441AActive Publication Date: 2024-10-15SHANGHAI BAOYE GRP CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411020554.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-10-15
Estimated Expiration
2044-07-29

AI Technical Summary

Technical Problem

Under wet and soft ground conditions, it is difficult to construct metallurgical plant steel columns through multi-story floors, and there is a risk of water leakage. Traditional construction methods cannot guarantee the quality of foundation formation, and the operation technology is difficult.

Method used

Embedding permanent steel formwork and segmented construction methods are adopted, including measurement and positioning, dismantling equipment, excavation of foundation pits, tying steel bars, hoisting steel pipe piles, pouring concrete, steel column foundation construction and hoisting, and combining with a 300t crawler crane for steel column hoisting. , and perform secondary grouting and waterproofing treatments.

Benefits of technology

It effectively reduces the technical difficulty of construction, improves construction operability, ensures the molding quality of the steel column foundation, reduces the risk of water leakage, and improves the reliability and safety of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774441A_ABST
    Figure CN118774441A_ABST
Patent Text Reader

Abstract

The invention relates to a method for penetrating steel columns of a metallurgical technically-improved plant through multi-layer floor slabs under the condition of a wet soft foundation. The method comprises the steps that the penetrating position of each layer of steel columns is measured and positioned; pipelines and equipment influencing installation are dismantled; pipeline and equipment finished product protection work in the point location influence range is well dismantled, and a positioning point roof is dismantled; binding foundation steel bars in the excavation position of the foundation pit, and hoisting and inserting a steel pipe pile containing studs from the breaking position; after the steel pipe piles are installed and positioned, negative first-layer foundation concrete is poured; constructing a layer of steel column foundation; hoisting the steel column; and recovering the structure of the dismantled part, and performing waterproof work on the first-layer bottom plate and the roof at the steel column penetrating position. According to the installation method for the wet and soft foundation metallurgy technical improvement engineering plant steel pipe column penetrating through the multi-layer floor slab, through the permanent steel formwork embedding and segmented construction mode, on the premise that the construction quality is guaranteed, the technical difficulty is greatly reduced, and construction is more operable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of metallurgical plant reconstruction, in particular to a method for passing steel columns of a metallurgical technical reconstruction plant through multi-layer floor slabs under a wet and soft foundation. Background Art

[0002] A steel plant in a certain region expanded its original factory building due to industrial upgrading. According to the drawings, the steel columns of the expanded factory building passed through the roof of the original dephosphorization water pump room and the first floor slab, and were located on the newly built foundation of the underground first floor. After checking the original geological survey report, the phreatic water level at the construction location is buried at a depth of about 0.50 to 1, and the groundwater is extremely abundant. The location of the steel column foundation pit belongs to the ②2nd layer of clay silt mixed with silty clay and the ②3-2nd layer of clay silt mixed with silty clay, which have obvious thixotropic and rheological properties. The soil strength is easily reduced under the action of dynamic force, and local landslides and soil flow are very likely to occur. During construction, due to the limited working space in the pump room, it is difficult to ensure the forming quality of the steel column foundation under such geological conditions according to the traditional construction method of laying cushion layers, tying steel bars, supporting formwork, pouring concrete, removing formwork, backfilling earth, and restoring the negative first floor slab. After the construction is completed, there is a risk of seepage and leakage at the joint between the negative first floor slab of the pump room and the steel column foundation. The opening space on the roof and floor slab is narrow. The steel column is hoisted through two floors of floor slabs and inserted into the foundation cup continuously, and the operation technology is extremely difficult. Summary of the invention

[0003] The purpose of the present invention is to propose a method for installing steel columns of a metallurgical technical transformation project plant through multi-layer floor slabs under soft foundation conditions, which can effectively solve the above-mentioned problems by burying permanent steel formwork and segmented construction, while ensuring the construction quality, greatly reducing the technical difficulty and making the construction more operational.

[0004] In order to achieve the above object, the present invention is achieved in the following ways: A method for passing a steel column of a metallurgical technical transformation plant through a multi-layer floor slab under a wet and soft foundation, comprising: Step 1: Measure and locate the insertion position of steel columns on each floor, and determine the pipelines and equipment that affect the installation based on the positioning; Step 2: Remove the pipelines and equipment that affect the installation, relocate the equipment, and restore the pipelines by rerouting them; Step 3: Protect the pipelines and equipment products within the impact range of the demolition point, demolish the roof and the first floor slab of the positioning point, demolish the basement floor according to the newly added foundation range, excavate the foundation pit and drain the excavated foundation pit. At the same time, clean up the demolished construction waste and excavated earth; Step 4: Tie foundation steel bars inside the excavated foundation pit, connect the steel bars with the basement floor steel bars, and hoist and insert the steel pipe piles with bolts inside from the broken position. The steel pipe piles are at a height of one layer from the bottom of the foundation steel formwork to the top of the top plate. Step 5: After the steel pipe piles are installed and positioned, pour the negative first floor foundation concrete; Step 6: construct a layer of steel column foundation; Step 7: Steel column hoisting operation; after the steel column is installed and adjusted in place, the cup mouth is grouted for the second time, and the safety protection measures can be removed only after the grouting strength reaches the requirement; Step 8: Restore the structure of the demolished part and waterproof the bottom plate and roof at the location where the steel columns are inserted.

[0005] The method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation is as follows: in step 4, a rectangular steel formwork surrounded by 2.0 thick steel plates with an open top that is equivalent to the size of the excavated foundation is installed at the excavation pit location to isolate water from the inside of the foundation pit. After the steel formwork is installed, foundation steel bars are tied inside, and the steel bars are connected to the basement floor steel bars. The steel pipe piles containing bolts are hoisted from the broken position and inserted into the center of the cross-section of the steel formwork on the negative first layer. The steel pipe piles are at a distance from the bottom of the foundation steel formwork and the top is one layer higher than the top plate.

[0006] In the method for passing the steel columns of the metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation, in step 7, a 300t crawler crane is used to hoist the steel columns. When the steel columns are hoisted, special personnel are arranged to direct on the roof and the first floor to ensure accurate installation and positioning of the steel columns and reduce the hovering operation time. After the steel columns are installed and adjusted in place, the cup mouth is immediately grouted for the second time. The safety protection measures can be removed only after the grouting strength reaches the requirements.

[0007] In the method of passing the steel columns of the metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation, after the installation and positioning of the steel pipe piles in step 5 are completed, the negative first layer foundation concrete is poured. When pouring, concrete is poured into the inner cavity of the steel pipe column on the first layer, and it automatically slides into the negative first layer foundation. After the negative first layer foundation is initially solidified, the concrete pouring work of the inner cavity of the steel pipe column is carried out. When pouring, pay attention to the top reservation to be poured together with the foundation of the steel column of the first layer.

[0008] In the method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under the condition of wet and soft foundation, when constructing a layer of steel column foundation in step 6, first install anchor bars in the cavity of steel pipe piles, then construct foundation steel bars, install formwork, and finally pour concrete. After the strength of concrete reaches the design requirements, the steel column hoisting work is carried out.

[0009] The method for installing steel pipe columns through multi-layer floor slabs in a metallurgical technical transformation project plant on soft foundation proposed in the present invention greatly reduces the technical difficulty and makes the construction more operable while ensuring the construction quality through the embedding of permanent steel formwork and segmented construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 Schematic diagram of steel column location.

[0011] Figure 2 This is a schematic diagram of the steel column installation section. DETAILED DESCRIPTION

[0012] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments in the embodiments of the present application are within the scope of protection requested by the present application.

[0013] like Figure 1 , Figure 2 A method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under a wet and soft foundation, comprising: Step 1: Measure and locate the insertion position of steel columns on each floor, and determine the pipelines and equipment that affect the installation based on the positioning; Step 2: Remove the pipelines and equipment that affect the installation, relocate the equipment, and restore the pipelines by rerouting them; Step 3: Protect the pipelines and equipment products within the impact range of the demolition point, demolish the roof and the first floor slab of the positioning point, demolish the basement floor according to the newly added foundation range, excavate the foundation pit and drain the excavated foundation pit. At the same time, clean up the demolished construction waste and excavated earth; Step 4: Tie foundation steel bars inside the excavated foundation pit, connect the steel bars with the basement floor steel bars, and hoist and insert the steel pipe piles with bolts inside from the broken position. The steel pipe piles are at a height of one layer from the bottom of the foundation steel formwork to the top of the top plate. Step 5: After the steel pipe piles are installed and positioned, pour the negative first floor foundation concrete; Step 6: construct a layer of steel column foundation; Step 7: Steel column hoisting operation; after the steel column is installed and adjusted in place, the cup mouth is grouted for the second time, and the safety protection measures can be removed only after the grouting strength reaches the requirement; Step 8: Restore the structure of the demolished part and waterproof the bottom plate and roof at the location where the steel columns are inserted.

[0014] The method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation is as follows: in step 4, a rectangular steel formwork surrounded by 2.0 thick steel plates with an open top that is equivalent to the size of the excavated foundation is installed at the excavation pit location to isolate water from the inside of the foundation pit. After the steel formwork is installed, foundation steel bars are tied inside, and the steel bars are connected to the basement floor steel bars. The steel pipe piles containing bolts are hoisted from the broken position and inserted into the center of the cross-section of the steel formwork on the negative first layer. The steel pipe piles are at a distance from the bottom of the foundation steel formwork and the top is one layer higher than the top plate.

[0015] In the method for passing the steel columns of the metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation, in step 7, a 300t crawler crane is used to hoist the steel columns. When the steel columns are hoisted, special personnel are arranged to direct on the roof and the first floor to ensure accurate installation and positioning of the steel columns and reduce the hovering operation time. After the steel columns are installed and adjusted in place, the cup mouth is immediately grouted for the second time. The safety protection measures can be removed only after the grouting strength reaches the requirements.

[0016] In the method of passing the steel columns of the metallurgical technical transformation plant through multi-layer floor slabs under the condition of soft foundation, after the installation and positioning of the steel pipe piles in step 5 are completed, the negative first layer foundation concrete is poured. When pouring, concrete is poured into the inner cavity of the steel pipe column on the first layer, and it automatically slides into the negative first layer foundation. After the negative first layer foundation is initially solidified, the concrete pouring work of the inner cavity of the steel pipe column is carried out. When pouring, pay attention to the top reservation to be poured together with the foundation of the steel column of the first layer.

[0017] In the method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under the condition of wet and soft foundation, when constructing a layer of steel column foundation in step 6, first install anchor bars in the cavity of steel pipe piles, then construct foundation steel bars, install formwork, and finally pour concrete. After the strength of concrete reaches the design requirements, the steel column hoisting work is carried out.

[0018] The above are only embodiments provided for the present application and are not intended to limit the present application. Although the present application is described in detail with reference to the embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under a wet and soft foundation, characterized by: include Step 1: Measure and locate the insertion position of steel columns on each floor, and determine the pipelines and equipment that affect the installation based on the positioning; Step 2: Remove the pipelines and equipment that affect the installation, relocate the equipment, and restore the pipelines by rerouting them; Step 3: Protect the pipelines and equipment products within the impact range of the demolition point, demolish the roof and the first floor slab of the positioning point, demolish the basement floor according to the newly added foundation range, excavate the foundation pit and drain the excavated foundation pit. At the same time, clean up the demolished construction waste and excavated earth; Step 4: Tie foundation steel bars inside the excavated foundation pit, connect the steel bars with the basement floor steel bars, and hoist and insert the steel pipe piles with bolts inside from the broken position. The steel pipe piles are at a height of one layer from the bottom of the foundation steel formwork to the top of the top plate. Step 5: After the steel pipe piles are installed and positioned, pour the negative first floor foundation concrete; Step 6: construct a layer of steel column foundation; Step 7: Steel column hoisting operation; after the steel column is installed and adjusted in place, the cup mouth is grouted for the second time, and the safety protection measures can be removed only after the grouting strength reaches the requirement; Step 8: Restore the structure of the demolished part and waterproof the bottom plate and roof at the location where the steel columns are inserted.

2. The method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under soft foundation conditions according to claim 1 is characterized in that: in step 4, a rectangular steel mold surrounded by a 2.0 thick steel plate with an open top that is equivalent to the size of the excavated foundation is installed at the excavation pit location to isolate water from the inside of the foundation pit. After the steel mold is installed, the foundation steel bars are tied inside, and the steel bars are connected to the basement floor steel bars. The steel pipe piles containing bolts are hoisted from the broken position and inserted into the center of the cross-section of the negative first-layer steel mold. The steel pipe piles are at a distance from the bottom of the foundation steel mold and the top is one layer higher than the top plate.

3. The method for passing steel columns through multi-layer floor slabs in a metallurgical technical transformation plant under a wet and soft foundation according to claim 1 is characterized by: In step 7, a 300t crawler crane is used to hoist the steel column. During the hoisting operation, special personnel should be arranged to direct the operation on the roof and the first floor to ensure accurate installation and positioning of the steel column and reduce the hovering operation time. After the steel column is installed and adjusted into place, the cup mouth is grouted for the second time. The safety protection measures can be removed only after the grouting strength reaches the requirement.

4. The method for passing steel columns through multi-layer floor slabs in a metallurgical technical transformation plant under a wet and soft foundation according to claim 1 is characterized by: After the installation and positioning of the steel pipe piles in step 5 is completed, the underground foundation concrete is poured. When pouring, concrete is poured into the inner cavity of the steel pipe column on the first layer, and it automatically slides into the underground foundation. After the underground foundation is initially solidified, the concrete pouring work of the inner cavity of the steel pipe column is carried out. When pouring, pay attention to the top reservation to be poured together with the steel column foundation of the first layer.

5. According to the method for passing steel columns of a metallurgical technical transformation plant through multi-layer floor slabs under soft foundation conditions as described in claim 1, when constructing a layer of steel column foundation in step 6, first install anchor bars in the steel pipe pile cavity, then construct foundation steel bars, install formwork, and finally pour concrete. After the strength of the concrete reaches the design requirements, the steel column hoisting work is carried out.

Citation Information

Patent Citations

  • Reversion construction method of building basement structure

    CN107542108A

  • Reinforcement modification structure and method of construction steel structure

    CN111608414A

  • Clockwise and anticlockwise combined construction method for reinforcement and reconstruction project of multi-story building in urban core area

    CN113090065A

  • Newly-added steel column and reinforcing structure of existing basement top plate

    CN220747764U