Beam supporting and column moving transformation method

Through the joist-column transformation method, the problem of insufficient headroom in house reinforcement is solved, the use area of ​​the house is increased and the reasonable bearing capacity of the structure is achieved, and the problems of complex construction and high cost in the existing technology are avoided.

CN118774445AActive Publication Date: 2024-10-15CHINA ENFI ENG CORP +1

Patent Information

Application Number
CN202411100016.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-10-15
Estimated Expiration
2044-08-12

AI Technical Summary

Technical Problem

During house reinforcement and renovation, existing technology requires the removal of columns when the headroom is insufficient, resulting in changes in the structural stress system. The construction is complex and costly, and may affect the usable area and bearing capacity of the house.

Method used

The joist-column transformation method is used to move the original structural columns by building first and then demolishing them. The new frame columns and the original frame columns jointly bear the load. The original frame columns are cut off and removed to reduce the scope and cost of reinforcement and maintain the net height of the house. And the usable area remains unchanged.

Benefits of technology

It achieves house reinforcement with small renovation scope, low cost and short construction period, maintains the rationality of the force transmission path and bearing capacity of the structure, and avoids the emergence of vertical irregular structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774445A_ABST
    Figure CN118774445A_ABST
Patent Text Reader

Abstract

The invention discloses a beam supporting and column moving transformation method which comprises the following steps: determining an original frame column to be transformed and a beam supported by the original frame column as an original frame beam, determining a pre-transformation position of the original frame column, and constructing a new frame column at the pre-transformation position, the column head of the new frame column is connected with the column head of the original frame column, so that the new frame column and the original frame column jointly bear the load transmitted by the original frame beam, the original frame column is cut off, the cut-off position of the original frame column is located on the lower portion of the connecting part of the original frame column and the new frame column, and the cut-off position of the original frame column is located on the lower portion of the connecting part of the original frame column and the new frame column. And the part, located below the cut-off position, of the original frame column is dismantled. According to the beam supporting and column moving transformation method, the workload is only newly built columns and reinforced column heads, the transformation range is small, construction is simple and reliable, cost is low, and the construction period is short. Original frame beams and original frame columns do not need to be reinforced, the clear height and the usable area of the house are not changed, and follow-up use is not affected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building repair, and in particular to a beam support and column shifting reconstruction method. Background Art

[0002] When reinforcing and renovating a house, if there is insufficient headroom, the relevant technical solution is to remove the columns that affect the usable space and reinforce the adjacent components according to the force requirements. This solution often changes the force system of the original structure, and the structure needs to be reinforced before it can be used normally.

[0003] According to the solutions of related technologies, other components of the original structure, such as frame beams and frame columns, need to be reinforced after the columns are pulled out. The reinforcement method is often complicated, the scope of transformation is large, the cost is high, the construction period is long, and the effect after reinforcement is often directly related to the quality of construction. If the reinforcement quality is unqualified, it will directly affect the bearing capacity of the structure.

[0004] Strengthening the frame beam by enlarging the cross section with concrete or adding steel sections underneath will increase the cross section of the beam, reduce the net height of the house, and affect subsequent use. Strengthening the frame column by enlarging the cross section with concrete or enclosing steel will increase the cross section of the column, reduce the usable area of ​​the house, and affect subsequent use.

[0005] In addition, the column-pulling reconstruction involves the conversion of vertical components in the force transmission path, which is vertically irregular, the structural system is not entirely reasonable, the force transmission path is complex, and the design and construction are relatively complicated. Summary of the invention

[0006] The present invention aims to solve one of the technical problems in the related art at least to a certain extent.

[0007] To this end, an embodiment of the present invention proposes a beam-supporting column-shifting reconstruction method, which uses a build-first-then-demolition method to translate the original structural columns, thereby increasing the usable area of ​​the room and meeting the use requirements.

[0008] The beam-supporting column-shifting reconstruction method according to the embodiment of the present invention comprises:

[0009] Determine the original frame columns to be renovated, and the beams supported by the original frame columns are the original frame beams;

[0010] Determine the pre-reconstruction position of the original frame column, and construct a new frame column at the pre-reconstruction position;

[0011] Connecting the column heads of the new frame columns to the column heads of the original frame columns, so that the new frame columns and the original frame columns can bear the load transmitted by the original frame beams together;

[0012] Cutting off the original frame column, wherein the cutting position of the original frame column is located at the lower part of the connection part between the original frame column and the new frame column;

[0013] The portion of the original frame column located below the cut-off position is removed.

[0014] The beam-supporting column-moving reconstruction method of the embodiment of the present invention only requires the construction of new columns and the reinforcement of column heads, with a small reconstruction scope, simple and reliable construction, low cost and short construction period. There is no need to reinforce the original frame beams and original frame columns, the net height of the house and the usable area of ​​the house are not changed, and the subsequent use is not affected.

[0015] Furthermore, the present invention does not change the force transmission path of the original structure, does not change the original structural system, does not have a vertical conversion component on the force transmission path, does not belong to a vertical irregular structure, and the structural system is reliable and reasonable.

[0016] In some embodiments, the capital of the new frame column is a corbel capital, and the retained portion of the original frame column is located within the capital of the new frame column.

[0017] In some embodiments, the peripheral wall surface of the retained portion of the original frame column and the peripheral wall surface of the column head of the new frame column are parallel to each other, and the vertical distance between the two is greater than or equal to 100 mm.

[0018] In some embodiments, the cross-section of the retained portion of the original frame column is parallel to the bottom slope of the capital of the new frame column, and the vertical distance between the two is greater than or equal to 200 mm, and the angle between the bottom slope of the capital of the new frame column and the wall surface of the column body intersecting therewith is 135°.

[0019] In some embodiments, the top surface of the column head of the new frame column is located above the bottom surface of the original frame beam, and the vertical distance between the two is greater than or equal to 150 mm.

[0020] In some embodiments, before constructing the new frame column, the column head of the original frame column is pre-processed to install a plurality of connecting pieces on the column head of the original frame column;

[0021] During the construction of the new frame column, the column head of the original frame column is connected to the column head of the new frame column through the connecting piece, so that the force applied to the original frame column is transferred to the new frame column through the connecting piece.

[0022] In some embodiments, the pretreatment of the original frame column includes:

[0023] A plurality of through holes are provided on the column head of the original frame column, wherein the through holes extend in the horizontal direction, and the plurality of through holes are spaced apart in the vertical direction;

[0024] The plurality of connecting members correspond to the plurality of through holes one by one, and the connecting members include an I-beam and a plurality of tie bars. The I-beam and the plurality of tie bars are passed through the corresponding through holes, and grouting is performed in the through holes.

[0025] In some embodiments, the construction process of the new frame column includes:

[0026] Constructing the reinforcement of the new frame column, wherein the reinforcement of the corbel of the new frame column surrounds the column head of the original frame column;

[0027] Binding a plurality of the tie steel bars to the longitudinal steel bars of the new frame column;

[0028] The new frame column and the capital of the original frame column are integrally cast so that the capital of the original frame column serves as a part of the capital of the new frame column.

[0029] In some embodiments, before cutting off the original frame column, a supporting tool is installed at the bottom of the original frame beam.

[0030] In some embodiments, after removing the portion of the original frame column below the cut-off position, the section of the retained portion of the original frame column is cast. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a schematic diagram of the original frame column of the present invention.

[0032] Figure 2 It is a schematic diagram of the original frame column after pretreatment of the present invention.

[0033] Figure 3 yes Figure 2 Schematic diagram of the cross section shown at AA.

[0034] Figure 4 It is a schematic diagram of the new frame column of the present invention and the original frame column.

[0035] Figure 5 yes Figure 4 Schematic diagram of the cross section shown at BB in the figure.

[0036] Figure 6 yes Figure 4 Schematic diagram of the cross section shown at CC.

[0037] Figure 7 yes Figure 4 Schematic diagram of the cross section shown at DD in the figure.

[0038] Figure 8 It is a schematic diagram of the present invention after cutting off the original frame column.

[0039] Reference numerals:

[0040] Original frame column 1, retained part 101, part to be removed 102,

[0041] Through hole 11, I-beam 12, tie steel bar 13,

[0042] Original frame beam 2,

[0043] New frame column 3, part to be poured 301. DETAILED DESCRIPTION

[0044] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0045] The following describes the beam support column shifting reconstruction method according to an embodiment of the present invention in conjunction with the accompanying drawings.

[0046] like Figures 1 to 8 As shown, the beam-supporting column-shifting reconstruction method according to an embodiment of the present invention comprises:

[0047] The original frame column 1 to be renovated in the house is determined, and the beam supported by the original frame column 1 is the original frame beam 2, that is, the beam connected to the column head of the original frame column 1 is the original frame beam 2. At this time, the original frame column 1 bears the load transferred by the original frame beam 2.

[0048] Determine the pre-reconstruction position of the original frame column 1, and build a new frame column 3 at the pre-reconstruction position. It should be noted that the straight-line distance between the position of the new frame column 3 and the position of the original frame column 1 is within 2m.

[0049] The column head of the new frame column 3 is connected to the column head of the original frame column 1 so that the new frame column 3 and the original frame column 1 can jointly bear the load transferred by the original frame beam 2.

[0050] The original frame column 1 is cut off, and the cutting position of the original frame column 1 is located at the lower part of the connection part between the original frame column 1 and the new frame column 3. That is, the original frame column 1 is cut off from the column head.

[0051] The portion of the original frame column 1 below the cutting position is removed, that is, the column body portion of the original frame column 1 is removed, and the column head portion of the original frame column 1 is retained.

[0052] It is understandable that during the renovation process, the way the force of the house structure is transmitted is that the original frame column 1 first bears the upper load transmitted by the upper original frame beam 2, and then a new frame column 3 is built next to the original frame column 1, and the column head of the original frame column 1 is connected to the column head of the new frame column 3. After the construction of the new frame column 3 is completed, the old and new frame columns jointly bear the upper force. After the original frame column 1 is disconnected, the new frame column 3 bears all the upper force.

[0053] The beam-supporting column-shifting reconstruction method of the embodiment of the present invention adopts the method of building first and then dismantling to translate the original frame column 1, thereby increasing the net space of the house. During the reconstruction process, the new frame column 3 and the original frame column 1 jointly bear the load transmitted by the original frame beam 2, so there is no need to reinforce the original frame beam 2 and the original frame column 1, and the net height and the usable area of ​​the house are not changed, which does not affect the subsequent use.

[0054] Moreover, during the transformation process, the force transmission path and structural system of the original structure are not changed, there are no vertical conversion components in the force transmission path, it does not belong to the vertical irregular structure, and the structural system is reliable and reasonable.

[0055] Therefore, compared with the reconstruction method of the related art, the beam-supporting and column-shifting reconstruction method of the embodiment of the present invention has a small scope of reinforcement and reconstruction, a simple and reliable construction process, low construction cost, and a short construction period.

[0056] In some embodiments, Figure 4 and Figure 8 As shown, the capital of the new frame column 3 is a corbel capital, and the retained portion 101 of the original frame column 1 is located inside the capital of the new frame column 3 .

[0057] Among them, Figure 4 As shown, the dotted line portion of the original frame column 1 is the portion to be removed 102, that is, the column body of the original frame column 1. The solid line portion of the original frame column 1 is the retained portion 101, that is, the column head of the original frame column 1.

[0058] It is understandable that if Figures 4 to 8 As shown, in the beam-supporting column-shifting reconstruction method of the embodiment of the present invention, the column head of the new frame column 3 is designed as a corbel column head, which can provide sufficient support area and evenly distribute the load of the original frame beam 2 to the new frame column 3, so as to better bear the load of the original frame beam 2. The column head of the original frame column 1 serves as a part of the corbel column head of the new frame column 3, ensuring the continuity and stability of the structure during the reconstruction process.

[0059] Alternatively, if Figures 4 to 7 As shown, the cross-sectional area of ​​the corbel of the new frame column 3 is larger than the column head of the original frame column 1, so as to wrap the column head of the original frame column 1. The cross-sectional area of ​​the column shaft of the new frame column 3 is larger than the cross-sectional area of ​​the column shaft of the original frame column 1, so as to ensure a smooth transition between the column shaft of the new frame column 3 and the column head of the new frame column 3, and avoid the sensory incoordination problem of the thin column shaft and the large column head.

[0060] The peripheral wall surface of the retained part 101 of the original frame column 1 is parallel to the peripheral wall surface of the column head of the new frame column 3. In other words, the four horizontal wall surfaces of the original frame column 1 are parallel to the four horizontal wall surfaces of the new frame column 3.

[0061] In addition, the vertical distance between each wall surface of the new frame column 3 and the original frame column 1 is greater than or equal to 100 mm to ensure that the column head of the new frame column 3 reasonably wraps the column head of the original frame column 1 .

[0062] Furthermore, if Figure 4 and Figure 8 As shown, the cross section of the retained portion 101 of the original frame column 1 is parallel to the bottom slope of the column head of the new frame column 3, and the vertical distance between the two is greater than or equal to 200 mm. The top surface of the column head of the new frame column 3 is located above the bottom surface of the original frame beam 2, and the vertical distance between the two is greater than or equal to 150 mm. Thus, it is ensured that the column head of the original frame column 1 is wrapped by the column head of the new frame column 3 in the three-dimensional space of up and down, front and back, left and right, so as to improve the structural integrity and stability of the modified new frame column 3.

[0063] Preferably, the angle between the bottom slope of the column head of the new frame column 3 and the wall surface of the column body intersecting therewith is 135°, so as to improve the stability of the load of the new frame column 3 in transitioning the original frame beam 2 and ensure that the appearance of the reconstructed structure is more harmonious.

[0064] In some embodiments, Figure 2 As shown, before constructing the new frame column 3, the column head of the original frame column 1 is pre-processed so as to install a plurality of connectors on the column head of the original frame column 1, so as to facilitate the subsequent connection of the column head of the original frame column 1 with the column head of the new frame column 3 through the connectors.

[0065] like Figures 4 to 7 As shown, during the construction of the new frame column 3 , the column head of the original frame column 1 is connected to the column head of the new frame column 3 via a connecting piece, so that the force applied to the original frame column 1 is transferred to the new frame column 3 via the connecting piece.

[0066] Alternatively, if Figure 2 As shown, the pretreatment of the original frame column 1 includes:

[0067] A plurality of through holes 11 are provided on the column head of the original frame column 1 at a position adjacent to the original frame beam 2 . The through holes 11 extend in the horizontal direction, and the plurality of through holes 11 are spaced apart in the vertical direction.

[0068] The plurality of connectors correspond to the plurality of through holes 11 one by one, and the connectors include an I-beam 12 and a plurality of tie bars 13. The I-beam 12 and the plurality of tie bars 13 are passed through the corresponding through holes 11, and grouting is performed in the through holes 11. After the grout solidifies, the I-beam 12 and the tie bars 13 are fixed on the column head of the original frame column 1, and the pretreatment operation of the original frame column 1 is completed.

[0069] The distance between the through holes 11 is greater than 500 mm, and the distance between the two ends of the I-beam 12 and the through holes 11 is 175 mm. The length of the tie steel bar 13 is determined according to the steel bar of the column head of the new frame column 3, ensuring that the tie steel bar 13 can be firmly connected with the steel bar of the new frame column 3.

[0070] The beam-supporting column-shifting reconstruction method of the embodiment of the present invention is to dismantle the original frame column 1 and transfer the load it bears to the new frame column 3. In order to achieve a smooth transition of force and ensure the safety of the original house during the reconstruction, two openings are made on the top of the original frame column 1, and an I-beam 12 is added in the holes to achieve a good combination of the new and old columns and the transmission of shear force, so as to achieve a smooth transition of the force in the original frame column 1 to the new frame column 3. Tie steel bars 13 are arranged at the openings to ensure the integrity of the connection between the column head of the original frame column 1 and the bracket of the newly added frame column.

[0071] In some embodiments, the construction process of the new frame column 3 includes:

[0072] First, the reinforcement of the new frame column 3 is constructed, and the reinforcement of the corbel of the new frame column 3 surrounds the column head of the original frame column 1. It should be noted that the corbel of the new frame column 3 needs to wrap the I-beam 12 inside to avoid exposure and affect the appearance.

[0073] Then, a plurality of tie bars 13 are tied to the longitudinal bars of the new frame column 3 .

[0074] Finally, the new frame column 3 and the capital of the original frame column 1 are cast as a whole, so that the capital of the original frame column 1 serves as a part of the capital of the new frame column 3, thereby smoothly transferring the load of the original frame beam 2 to the capital, column body and foundation of the new frame column 3.

[0075] Therefore, after the construction of the new frame column 3 is completed and reaches the designed strength, the original frame column 1 can be cut off to achieve the purpose of supporting the beam and moving the column, which can prevent the overall structural safety problem caused by the sudden change of the force transmission mode.

[0076] In addition, during the construction of the new frame column 3, the integral casting method can ensure the integration of the new and old structures and improve the stability and bearing capacity of the structure. This construction method also reduces the complexity and time of construction.

[0077] In some embodiments, before cutting off the original frame column 1 , a supporting tool is installed at the bottom of the original frame beam 2 .

[0078] It is understandable that before cutting off the original frame column 1, necessary support measures should be taken, such as using jacks or supporting scaffolds to support the bottom of the beam. After disconnecting the original frame column 1, the upper force on the jack or supporting scaffold is gradually unloaded to avoid sudden deformation and displacement of the structure. In addition, the deflection of the frame beam should be monitored throughout the construction process.

[0079] In some embodiments, Figure 8 As shown, after removing the part of the original frame column 1 below the cut-off position, the section of the retained part 101 of the original frame column 1 is cast, and this part is the part to be cast 301, that is, Figure 8 The filling part in .

[0080] Specifically, after the construction of the new frame column 3 is completed, a chamfer is made at a 45° angle at 200 mm below the through hole 11 at the lowest layer on the original frame column 1. After cutting off the original frame column 1, the column body of the original frame column 1 is removed. After removal, the cross section is cast. This design can enhance the stability of the modified structure and ensure the long-term safe use of the structure.

[0081] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0082] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0083] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0084] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0085] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0086] Although the above embodiments have been shown and described, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.

Claims

1. A beam-post-shifting reconstruction method, characterized in that: include: Determine the original frame columns to be renovated, and the beams supported by the original frame columns are the original frame beams; Determine the pre-reconstruction position of the original frame column, and construct a new frame column at the pre-reconstruction position; Connecting the column heads of the new frame columns to the column heads of the original frame columns, so that the new frame columns and the original frame columns can bear the load transmitted by the original frame beams together; Cutting off the original frame column, wherein the cutting position of the original frame column is located at the lower part of the connection part between the original frame column and the new frame column; The portion of the original frame column located below the cut-off position is removed.

2. The beam-supporting column-shifting reconstruction method according to claim 1 is characterized in that: The capital of the new frame column is a corbel capital, and the retained portion of the original frame column is located inside the capital of the new frame column.

3. The beam-supporting column-shifting reconstruction method according to claim 2 is characterized in that: The peripheral wall surface of the retained part of the original frame column and the peripheral wall surface of the column head of the new frame column are parallel to each other, and the vertical distance between the two is greater than or equal to 100 mm.

4. The beam-supporting column-shifting reconstruction method according to claim 3 is characterized in that: The cross-section of the retained part of the original frame column is parallel to the bottom slope of the column head of the new frame column, and the vertical distance between the two is greater than or equal to 200 mm. The angle between the bottom slope of the column head of the new frame column and the wall surface of the column body intersecting therewith is 135°.

5. The beam-supporting column-shifting reconstruction method according to claim 4 is characterized in that: The top surface of the column head of the new frame column is located above the bottom surface of the original frame beam, and the vertical distance between the two is greater than or equal to 150 mm.

6. The beam-supporting column-shifting reconstruction method according to any one of claims 2 to 5, characterized in that: Before constructing the new frame column, pre-processing the column head of the original frame column to install a plurality of connecting pieces on the column head of the original frame column; During the construction of the new frame column, the column head of the original frame column is connected to the column head of the new frame column through the connecting piece, so that the force applied to the original frame column is transferred to the new frame column through the connecting piece.

7. The beam-supporting column-shifting reconstruction method according to claim 6 is characterized in that: The pretreatment of the original frame column includes: A plurality of through holes are provided on the column head of the original frame column, wherein the through holes extend in the horizontal direction, and the plurality of through holes are spaced apart in the vertical direction; The plurality of connecting members correspond to the plurality of through holes one by one, and the connecting members include an I-beam and a plurality of tie bars. The I-beam and the plurality of tie bars are passed through the corresponding through holes, and grouting is performed in the through holes.

8. The beam-supporting column-shifting reconstruction method according to claim 7 is characterized in that: The construction process of the new frame column includes: Constructing the reinforcement of the new frame column, wherein the reinforcement of the corbel of the new frame column surrounds the column head of the original frame column; Binding a plurality of the tie steel bars to the longitudinal steel bars of the new frame column; The new frame column and the capital of the original frame column are integrally cast so that the capital of the original frame column serves as a part of the capital of the new frame column.

9. The beam-supporting column-shifting reconstruction method according to claim 8, characterized in that: Before cutting off the original frame column, a supporting tool is installed at the bottom of the original frame beam.

10. The beam-supporting column-shifting reconstruction method according to claim 8, characterized in that: After removing the portion of the original frame column below the cut-off position, the section of the retained portion of the original frame column is cast.

Citation Information

Patent Citations

  • Underground storey-adding underpinning structure utilizing existing building foundation structure and construction method of underground storey-adding underpinning structure

    CN114635580A

  • Structure for adding corbels on reinforced concrete column

    CN203080955U

  • Safety locking module for temporary underpinning support of reinforcing beam

    CN218881693U

  • Transfer method for column

    JP2001059346A

  • Viaduct column replacement method and viaduct column for replacement

    JP2013167049A

Cited By

  • Method for unloading broken column in joist column pulling process

    CN119711790A

  • Construction method for joist and column movement of industrial factory building

    CN122610707A