Leakage treatment method for supporting sleeve of gas holder and gas holder
By controlling the gas content and raising the piston assembly when the gas cabinet is under maintenance, and installing a liner to seal the corrosion damage of the support casing, the problem of leakage of the support casing in the gas cabinet is solved and the safety and efficiency of gas storage are ensured.
Patent Information
- Application Number
- CN202410890253.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-07-04
AI Technical Summary
The support casing in the gas cabinet leaks due to gas corrosion, which affects the gas storage operation.
By controlling the carbon monoxide and oxygen content in the cabinet to be lower than the preset values during maintenance, the piston assembly is raised to separate the piston bottom plate from the cabinet, the concrete dam brace and piston brace are installed, the concrete dam brace is removed, and the Liners are embedded within the support casing to seal corrosion damage.
It effectively solved the problem of gas leakage, ensured the storage operation of the gas cabinet under normal working conditions, eliminated the risk of explosion in advance, and completed the damage treatment of the support casing.
Smart Images

Figure CN118775737A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of gas cabinet maintenance, and in particular to a method for handling leakage of a supporting sleeve of a gas cabinet and a gas cabinet. Background Art
[0002] Gas holders, such as two-stage rubber membrane sealed gas holders, are mainly used for the storage of converter gas in the steel and metallurgical industry. They participate in the online operation of the gas pipeline network and play a role in shaving peaks and filling valleys in the generation and utilization of converter gas.
[0003] The gas tank mainly includes a tank body and a piston assembly, a T-type assembly, an inner membrane and an outer membrane in the tank body. The T-type assembly is located above the piston assembly. The piston assembly mainly includes a piston bottom plate, a piston fence, a concrete dam and a support sleeve. The support sleeve is vertically penetrated in the concrete dam and is used to install a concrete dam support rod inside it when it is in the maintenance state. The concrete dam is installed in the piston fence, and the piston bottom plate is installed at the bottom of the concrete dam. The T-type assembly mainly includes a T-type baffle. The T-type baffle is connected and sealed with the side wall plate of the tank body through the outer membrane, and the T-type baffle is connected and sealed with the piston bottom plate through the inner membrane. When gas, such as coal gas, enters the inner membrane and outer membrane in the tank body from the air inlet of the tank body, the inner membrane and outer membrane can expand in a rolling manner, causing the piston assembly to rise first, and then drive the T-type baffle to rise.
[0004] The gas flows from the air inlet of the cabinet to the outer membrane through the bottom of the concrete dam and enters the supporting sleeve. As the gas cabinet operates for a long time, the steel structure components in contact with the gas, such as the supporting sleeve, will be corroded and damaged, causing the gas to flow upward from the corroded and damaged parts of the supporting sleeve through the gaps in the concrete dam to enter the top of the piston assembly, causing gas leakage, thereby affecting the gas cabinet's storage operation of the gas. Summary of the invention
[0005] The problem solved by the invention is how to solve the problem of gas leakage caused by gas corrosion and damage of the supporting sleeve in the gas cabinet.
[0006] In order to solve the above problems, in a first aspect, the present invention provides a method for handling leakage of a support sleeve of a gas tank, wherein the gas tank comprises a tank body and a piston assembly, wherein the piston assembly comprises a piston bottom plate, a concrete dam, a support sleeve and a liner, wherein the concrete dam is arranged on the piston bottom plate, the support sleeve is penetrated through the concrete dam, the liner is embedded in the support sleeve, and the top and bottom ends of the liner are respectively corresponding to the flange of the support sleeve and the piston bottom plate and are sealed and connected;
[0007] The leakage treatment method comprises the following steps:
[0008] When the energy storage cabinet is switched to the maintenance state, the carbon monoxide content and the oxygen content in the cabinet are controlled to be lower than the corresponding gas preset values respectively by replacement;
[0009] Raising the piston assembly so that the piston bottom plate is separated from the cabinet bottom plate of the cabinet body to a preset height difference;
[0010] A concrete dam support rod is installed in each of the support sleeves, and a plurality of piston support rods are installed below the piston bottom plate, and the piston assembly is lowered so that the concrete dam support rod and the piston support rod fall to the cabinet bottom plate;
[0011] The concrete dam is raised, the concrete dam support rod is removed from the concrete dam, and the liner is assembled in the support sleeve, so that the top end of the liner is sealed and connected to the flange of the support sleeve, and the bottom end of the liner is sealed and connected to the piston bottom plate.
[0012] Optionally, the step of raising the concrete dam, removing the support sleeve and the concrete dam support rod from the concrete dam, assembling the liner in the support sleeve, and sealingly connecting the top end of the liner with the flange of the support sleeve and the bottom end of the liner with the piston bottom plate comprises:
[0013] Installing a lifting device below the concrete dam and around the support rods of the concrete dam to lift up the concrete dam so that the support rods of the concrete dam no longer bear the pressure of the concrete dam;
[0014] removing the concrete dam support rods in the concrete dam;
[0015] The liner is embedded in the interior of the support sleeve; the top end of the liner is sealed to the flange of the support sleeve, and the bottom end of the liner is sealed to the piston bottom plate;
[0016] Cutting a portion of the top end of the liner that extends beyond the flange of the support sleeve;
[0017] The concrete dam support rod is inserted into the liner from top to bottom, and the concrete dam support rod is connected to the flange of the support sleeve through fasteners.
[0018] Optionally, the step of raising the concrete dam, removing the concrete dam support rod from the concrete dam, assembling the liner in the support sleeve, and sealingly connecting the top end of the liner with the flange of the support sleeve and the bottom end of the liner with the piston bottom plate further comprises:
[0019] Before embedding the liner in the support sleeve, the interior of the support sleeve is cleaned.
[0020] Optionally, after the concrete dam support rod and the piston support rod are lowered to the cabinet bottom plate, an inspection door provided on the side wall plate of the cabinet is opened to perform a safety inspection on the internal environment of the cabinet.
[0021] Optionally, when the energy storage cabinet is switched to the maintenance state, controlling the carbon monoxide content and the oxygen content in the cabinet to be lower than corresponding gas preset values by replacement means includes:
[0022] Stopping the operation of the gas tank to switch to the maintenance state;
[0023] By replacing coal gas with nitrogen, the content of carbon monoxide in the cabinet is controlled to be lower than a first gas preset value;
[0024] By replacing nitrogen with air, the oxygen content in the cabinet is controlled to be lower than a second gas preset value.
[0025] Optionally, the energy storage cabinet further includes an air inlet pipeline, an air outlet pipeline, a nitrogen pipeline, a first vent pipe and a second vent pipe, wherein the first vent pipe is arranged on the cabinet, the air inlet pipeline and the air outlet pipeline are respectively connected to different second vent pipes, and the air inlet pipeline, the air outlet pipeline and the nitrogen pipeline are respectively connected to the cabinet;
[0026] The replacing coal gas with nitrogen to control the carbon monoxide content in the cabinet to be lower than the first gas preset value comprises:
[0027] Opening the first vent pipe and the second vent pipe;
[0028] Filling nitrogen into the cabinet through the nitrogen pipeline, replacing the coal gas with the nitrogen, discharging the coal gas from the first vent pipe, and discharging the coal gas from the second vent pipe through the gas outlet pipeline;
[0029] Close the first vent pipe and the second vent pipe, and raise the piston assembly to allow the nitrogen in the cabinet to be fully mixed with the residual gas;
[0030] Open the first vent pipe and the second vent pipe, discharge the gas fully mixed with nitrogen and residual coal gas from the first vent pipe, and discharge it from the second vent pipe through the gas outlet pipeline until the carbon monoxide content in the cabinet is lower than the first gas preset value.
[0031] Optionally, replacing nitrogen with air to control the oxygen content in the cabinet to be lower than a second gas preset value includes:
[0032] Connect the air blowing device to the cabinet, and open the first vent pipe and the second vent pipe;
[0033] The blower is controlled to operate, air is blown into the cabinet, nitrogen is replaced by air, the nitrogen is discharged from the first vent pipe, and the nitrogen is discharged from the second vent pipe through the air outlet pipeline until the oxygen content in the cabinet is lower than the preset value of the second gas.
[0034] Optionally, the energy storage cabinet further includes an air inlet valve and an air outlet valve, wherein the air inlet valve is arranged on the air inlet pipeline, and the air outlet valve is arranged on the air outlet pipeline;
[0035] The step of stopping the operation of the gas holder to switch to the maintenance state includes:
[0036] The gas holder is stopped from operating, and the air inlet valve and the air outlet valve are closed, so that the gas holder is switched to the maintenance state.
[0037] Optionally, the energy storage cabinet further includes a nitrogen valve and a first blind plate, the nitrogen pipeline is connected to the cabinet, the nitrogen valve is arranged on the nitrogen pipeline, and the first blind plate is detachably installed on one end of the nitrogen pipeline close to the cabinet;
[0038] Raising the piston assembly so that the piston bottom plate is separated from the cabinet bottom plate of the cabinet body to a preset height difference comprises:
[0039] Close the nitrogen valve and install the first blind plate at one end of the nitrogen pipeline close to the cabinet;
[0040] Air is filled into the cabinet body through an air blowing device to raise the piston assembly until the piston bottom plate is separated from the cabinet bottom plate of the cabinet body to the preset height difference.
[0041] The beneficial effect of the leakage treatment method of the support sleeve of the gas cabinet of the present invention is that when the support sleeve in the piston assembly is corroded and worn, it can be treated in the following manner, for example, the energy storage cabinet is first switched to the maintenance state, at which time the content of the mixed gas in the cabinet, such as carbon monoxide and oxygen, can be controlled by replacement to be lower than the corresponding gas preset values, thereby effectively reducing the risk of explosion caused by the carbon monoxide and oxygen contents exceeding the respective corresponding gas preset values in the subsequent steps, and the explosion hazard is eliminated in advance accordingly; then the piston assembly is raised, so that the piston bottom plate is separated from the cabinet bottom plate of the cabinet to a preset height difference, so that maintenance personnel can enter the area between the piston bottom plate and the cabinet bottom plate, thereby providing working space for subsequent steps; then the maintenance personnel can embed and install concrete dam support rods in each support sleeve in the space between the piston bottom plate and the cabinet bottom plate of the cabinet, and install multiple piston support rods at intervals below the piston bottom plate, and then the piston assembly is lowered so that the concrete dam support rod and the piston support rod fall to the cabinet bottom plate, so that the concrete dam and the piston support rod can be respectively checked by the concrete dam support rod and the piston support rod. The bottom plate is used for support; then the concrete dam can be partially lifted up by the jacking device, so that the concrete dam support rods no longer bear the pressure of the concrete dam, thereby facilitating the removal of the concrete dam support rods from the inside of the support sleeve in the concrete dam. At this time, the concrete dam support rods will not interfere with the assembly of the liner in the support sleeve. Subsequently, the top and bottom ends of the liner are respectively corresponding to the flange of the support sleeve and the piston bottom plate to achieve the fixed installation operation of the liner, so as to shield the corroded and damaged parts of the support sleeve from the inside of the support sleeve through the liner. In other words, , the liner and the supporting sleeve can be equivalent to the undamaged supporting sleeve, so as to effectively solve the problem of gas leakage in the later energy storage cabinet under normal working conditions, and then ensure the gas storage operation of the gas cabinet, so as to complete the damage treatment operation of one supporting sleeve; then refer to the above steps to assemble other liners inside the supporting sleeves at other positions to realize the damage treatment operation of the supporting sleeves at other positions, and finally remove the concrete dam support rod and the piston support rod, so as to prepare for the subsequent energy storage cabinet to switch from the above maintenance state to the working state.
[0042] In a second aspect, the present invention provides a gas cabinet, comprising a cabinet body and a piston assembly, wherein the piston assembly comprises a piston bottom plate, a concrete dam, a support sleeve and a liner, wherein the concrete dam is arranged on the piston bottom plate, the support sleeve is passed through the concrete dam, the liner is embedded in the support sleeve, and the top and bottom ends of the liner are respectively sealed and connected to the flange of the support sleeve and the piston bottom plate.
[0043] Since the gas holder adopts the leakage treatment method for the supporting sleeve of the gas holder, the gas holder at least has all the technical effects of the leakage treatment method for the supporting sleeve of the gas holder, which will not be described in detail here. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] Figure 1 It is a schematic diagram of the cross-sectional structure of a gas tank in the prior art;
[0045] Figure 2 It is a partial structural schematic diagram of a piston assembly in the prior art;
[0046] Figure 3 It is a schematic flow chart of a method for handling leakage of a supporting sleeve of a gas cabinet according to an embodiment of the present invention;
[0047] Figure 4 This is one of the partial structural schematic diagrams of the piston assembly in the embodiment of the present invention;
[0048] Figure 5 This is a second schematic diagram of a partial structure of a piston assembly in an embodiment of the present invention;
[0049] Figure 6 This is a schematic diagram of the structure of nitrogen filling into a cabinet in an embodiment of the present invention;
[0050] Figure 7 This is a schematic diagram of the structure of air entering the cabinet in an embodiment of the present invention;
[0051] Figure 8 It is a structural schematic diagram of the piston assembly when the energy storage cabinet is in operation according to an embodiment of the present invention;
[0052] Fig. 9 for Figure 1 A schematic diagram of the enlarged structure at A in the middle;
[0053] Fig.10 for Figure 1 Schematic diagram of the enlarged structure at point B in the middle.
[0054] Description of reference numerals:
[0055] 1-cabinet body; 11-cabinet bottom plate; 2-piston assembly; 21-piston bottom plate; 22-piston fence; 23-concrete dam; 24-support sleeve; 241-flange; 25-inner membrane; 26-liner; 27-fastener; 28-second blind plate; 29-piston corrugated plate; 3-T-type assembly; 31-T-type baffle; 311-T-type fence; 312-T-type corrugated plate; 32-outer membrane; 4-inlet pipeline; 5-outlet pipeline; 6-first vent pipe; 7-second vent pipe; 8-inlet valve; 9-outlet valve; 10-blowing device; 12-concrete dam support rod; 13-nitrogen pipeline. DETAILED DESCRIPTION
[0056] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. Although certain embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be interpreted as being limited to the embodiments described herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present invention. It should be understood that the drawings and embodiments of the present invention are only for exemplary purposes and are not intended to limit the scope of protection of the present invention.
[0057] The Z axis in the drawings represents the vertical direction, that is, the up and down position, and the positive direction of the Z axis represents the top, and the reverse direction of the Z axis represents the bottom; the X axis in the drawings represents the horizontal direction, and is designated as the left and right position, and the positive direction of the X axis represents the right side, and the reverse direction of the X axis represents the left side. It should also be noted that the aforementioned Z axis, Y axis, and X axis are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation to the present invention.
[0058] The term "including" and its variations used in this document are open inclusions, that is, "including but not limited to"; the term "based on" means "based at least in part on"; the term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one other embodiment"; the term "some embodiments" means "at least some embodiments"; the term "optionally" means "optional embodiments". The relevant definitions of other terms will be given in the following description. It should be noted that the concepts of "first", "second", etc. mentioned in the present invention are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.
[0059] It should be noted that the modifications of "one" and "plurality" mentioned in the present invention are illustrative rather than restrictive, and those skilled in the art should understand that, unless otherwise clearly indicated in the context, it should be understood as "one or more".
[0060] In the related art, gas holders such as two-stage rubber membrane sealed gas holders are mainly used for the storage of converter gas in the iron and steel metallurgical industry, participate in the online operation of the gas pipeline network, and play a role in peak shaving and valley filling in the generation and utilization of converter gas.
[0061] Combination Figure 1 , Fig. 9 and Fig.10As shown, the gas tank mainly includes a cabinet body 1 and a piston assembly 2, a T-type assembly 3, an inner membrane 25 and an outer membrane 32 in the cabinet body 1, and the T-type assembly 3 is located above the piston assembly 2; a first relief pipe 6 is also provided outside the side wall of the cabinet body 1, and a first relief valve is provided on the first relief pipe 6. The piston assembly 2 mainly includes a piston bottom plate 21, a piston fence 22, a concrete dam 23, a support sleeve 24 and a piston corrugated plate 29, and the support sleeve 24 is vertically penetrated in the concrete dam. 23, used for installing the concrete dam support rod 12 inside during maintenance, the concrete dam 23 is installed in the piston fence 22, the piston bottom plate 21 is installed at the bottom of the concrete dam 23, and the piston corrugated plate 29 is arranged on the side of the piston fence 22 close to the side wall plate of the cabinet 1; the T-type assembly 3 mainly includes a T-type baffle 31, the T-type baffle 31 and the side wall plate of the cabinet 1 are connected and sealed by an outer membrane 32, and the T-type baffle 31 and the piston bottom plate 21 are connected and sealed by an inner membrane 25. An air inlet is provided at the bottom end of the side wall of the cabinet 1.
[0062] The gas in the cabinet 1 is usually stored in the space between the bottom of the concrete dam 23 and the cabinet bottom plate 11 , inside the inner membrane 25 , and inside the outer membrane 32 .
[0063] The gas can enter the inner membrane 25 and the outer membrane 32 from the following paths. For example, the gas enters the space between the bottom of the concrete dam 23 and the cabinet bottom plate 11, and the support sleeve 24 from the air inlet of the cabinet 1, and then flows into the inner membrane 25 and the outer membrane 32 in the cabinet 1. The inner membrane 25 bulges first, and the inner membrane 25 is close to the piston corrugated plate 29 on the piston fence 22. With the addition of gas in the cabinet 1, when the gas pressure (gas pressure) is greater than the weight of the piston assembly 2, under the action of the gas pressure, the inner membrane 25 bulges first, and the inner membrane 25 is close to the piston corrugated plate 29 on the piston fence 22. Under the action, the inner membrane 25 rolls upward, and the piston base plate 21 and the piston fence 22 arranged on the piston base plate 21 rise synchronously with the inner membrane 25. At this time, the inner membrane 25 rolls toward the T-shaped baffle 31; as the gas pressure in the cabinet 1 continues to increase, the piston assembly 2 continues to move upward, and drives the T-shaped baffle 31 and the outer membrane 32 to rise. Then, when the T-shaped baffle 31 rises to a certain height, the T-shaped baffle 31 will touch the first relief valve on the first relief pipe 6 to discharge the gas in the cabinet 1 through the first relief pipe 6.
[0064] in, Figure 1 In the embodiment, before the gas enters the cabinet 1, the piston bottom plate 21 of the piston assembly 2 can be close to the cabinet bottom plate 11 of the cabinet 1. At this time, the piston assembly 2 and the T-type assembly 3 are close to the bottom of the cabinet 1 and are adjacent to the piston assembly 2. Figure 1 When the T-shaped baffle 31 rises to approach the top limit position in the cabinet 1, the T-shaped baffle 31 will touch the first relief valve on the first relief pipe 6. At this time, the piston assembly 2 and the T-shaped assembly 3 are in the vicinity. Figure 1 Indicated by dotted line.
[0065] Combination Figure 2 As shown in FIG. 1 , the gas flows from the gas inlet of the cabinet 1 to the outer membrane 32 through the bottom of the concrete dam and enters the support sleeve 24. As the gas cabinet is operated for a long time, the steel structure components in contact with the gas, such as the support sleeve 24, will be corroded and damaged (see FIG. 1 ). Figure 2 As a result, the gas will flow upward from the corroded and damaged part of the support sleeve 24 through the gap of the concrete dam 23 to enter the space between the top of the piston assembly 2 and the top plate of the cabinet 1, causing gas leakage, thereby affecting the gas storage operation of the gas tank.
[0066] In view of the problems existing in the above-mentioned related technologies, this embodiment provides a method for handling leakage of a supporting sleeve of a gas cabinet.
[0067] like Figure 1 and Fig. 9 As shown, an embodiment of the present invention provides a method for handling leakage of a support sleeve of a gas tank, the gas tank includes a cabinet body 1 and a piston assembly 2, the piston assembly 2 includes a piston bottom plate 21, a concrete dam 23, a support sleeve 24 and a liner 26, the concrete dam 23 is arranged on the piston bottom plate 21, the support sleeve 24 is penetrated by the concrete dam 23, the liner 26 is embedded in the support sleeve 24, and the top and bottom ends of the liner 26 are respectively corresponding to the flange of the support sleeve 24 and the piston bottom plate 21 for sealing connection.
[0068] Combination Figure 3 As shown, the leakage treatment method comprises the following steps:
[0069] S1. When the energy storage cabinet is switched to the maintenance state, the carbon monoxide content and the oxygen content in the cabinet body 1 are controlled to be lower than the corresponding gas preset values by replacement;
[0070] S2, raising the piston assembly 2 so that the piston bottom plate 21 is separated from the cabinet bottom plate 11 of the cabinet body 1 to a preset height difference;
[0071] S3, installing a concrete dam support rod 12 in each of the support sleeves 24, installing multiple piston support rods below the piston bottom plate 21, and lowering the piston assembly 2 so that the concrete dam support rod 12 and the piston support rod fall to the cabinet bottom plate 11;
[0072] S4, raise the concrete dam 23, remove the concrete dam support rod 12 from the concrete dam 23, assemble the liner 26 into the support sleeve 24, make the top end of the liner 26 sealedly connected to the flange 241 of the support sleeve 24, and the bottom end of the liner 26 sealedly connected to the piston bottom plate 21.
[0073] Specifically, the preset gas value refers to the carbon monoxide and oxygen content in the cabinet 1 that will not cause explosion risk in subsequent operations after the gas in the cabinet 1 is replaced. The preset height difference means that after the piston assembly 2 is raised relative to the cabinet bottom plate 11, the distance or height between the piston bottom plate 21 and the cabinet bottom plate 11 meets the condition that "maintenance personnel can smoothly enter under the piston bottom plate 21, and can install the concrete dam support rod 12 on the support sleeve 24, and the piston support rod is installed under the piston bottom plate 21".
[0074] The above step S4 involves the step of installing the liner 26 in the support sleeve 24, specifically the step of installing the liner 26 in one of the support sleeves 24. The support sleeves 24 at different positions of the entire piston assembly 2 can all refer to the above step S4 to assemble the liner 26.
[0075] In this embodiment, when the support sleeve 24 in the piston assembly 2 is corroded and worn, it can be handled in the following manner, for example, the energy storage cabinet is first switched to the maintenance state, at which time the mixed gas in the cabinet body 1, such as the carbon monoxide content and the oxygen content, can be controlled by replacement to be lower than the corresponding gas preset values, thereby effectively reducing the risk of explosion caused by the carbon monoxide and oxygen contents exceeding the respective corresponding gas preset values in the subsequent steps, and accordingly eliminating the explosion hazard in advance; then the piston assembly 2 is raised to separate the piston bottom plate 21 from the cabinet bottom plate 11 of the cabinet body 1 to a preset height difference, so as to facilitate the entry of maintenance personnel. The area between the piston bottom plate 21 and the cabinet bottom plate 11 is provided with a working space for the subsequent steps; then the maintenance personnel can embed and install the concrete dam support rod 12 in each support sleeve 24 in the space between the piston bottom plate 21 and the cabinet bottom plate 11 of the cabinet body 1, install multiple piston support rods at intervals below the piston bottom plate 21, and then lower the piston assembly 2 so that the concrete dam support rod 12 and the piston support rod fall to the cabinet bottom plate 11, so that the concrete dam 23 and the piston bottom plate 21 can be supported by the concrete dam support rod 12 and the piston support rod respectively; then the concrete dam 23 and the piston bottom plate 21 can be supported by the jacking device. The earth dam 23 is partially lifted up, so that the concrete dam support rod 12 no longer bears the pressure of the concrete dam 23, which helps to remove the concrete dam support rod 12 from the inside of the support sleeve 24 in the concrete dam 23. At this time, the concrete dam support rod 12 will not interfere with the assembly of the liner 26 in the support sleeve 24. Then, the top and bottom ends of the liner 26 are sealed and connected with the flange 241 of the support sleeve 24 and the piston bottom plate 21 respectively to realize the fixed installation operation of the liner 26, so as to shield the corroded and damaged parts of the support sleeve 24 from the inside of the support sleeve 24 through the liner 26. In other words, the liner The tube 26 and the support sleeve 24 can be equivalent to the undamaged support sleeve 24, thereby effectively solving the problem of gas leakage in the later energy storage cabinet under normal working conditions, and further ensuring the gas storage operation of the gas cabinet, thereby completing the damage treatment operation of one support sleeve 24; then, referring to the above steps, assemble other liner tubes 26 inside the support sleeve 24 at other positions in the piston assembly to achieve the damage treatment operation of the support sleeve 24 at other positions, and finally remove the concrete dam support rod 12 and the piston support rod, thereby preparing for the subsequent energy storage cabinet to switch from the above-mentioned maintenance state to the working state.
[0076] Optionally, S4, raising the concrete dam 23, removing the support sleeve 24 and the concrete dam support rod 12 from the concrete dam 23, assembling the liner 26 into the support sleeve 24, and sealingly connecting the top end of the liner 26 to the flange 241 of the support sleeve 24, and sealingly connecting the bottom end of the liner 26 to the piston bottom plate 21, comprises:
[0077] S41, installing a jacking device below the concrete dam 23 and around the concrete dam support rod 12 to lift the concrete dam 23 so that the concrete dam support rod 12 is no longer under the pressure of the concrete dam 23;
[0078] S42, removing the concrete dam support rod 12 in the concrete dam 23;
[0079] S43, embedding the liner 26 inside the support sleeve 24; sealingly connecting the top end of the liner 26 to the flange 241 of the support sleeve 24, and sealingly connecting the bottom end of the liner 26 to the piston bottom plate 21;
[0080] S44, cutting the portion of the top end of the liner 26 that exceeds the flange 241 of the support sleeve 24;
[0081] S45, inserting the concrete dam support rod 12 into the liner 26 from top to bottom, and connecting the concrete dam support rod 12 to the flange 241 of the support sleeve 24 via fasteners 27.
[0082] Specifically, in step S41, when a damaged support sleeve needs to be processed, a jacking device can be installed below the concrete dam 23 where the support sleeve 24 is located. The jacking device can be set on one side of the concrete dam support rod 12, so that the concrete dam 23 where the support sleeve 24 is located can be lifted up by the jacking device, so that the concrete dam support rod 12 at this location no longer bears the downward pressure of the concrete dam 23, so that the maintenance personnel can more easily and smoothly remove the support sleeve 24 and the concrete dam support rod 12 on the side of the jacking device in the subsequent steps. The jacking device is a device that can lift the concrete dam 23, for example, it can be a jack, an electric push rod, etc.
[0083] In step S42, since the concrete dam 23 is lifted up by the lifting device, the bottom of the concrete dam support rod 12 is away from the cabinet bottom plate. At this time, the concrete dam support rod 12 no longer bears the pressure of the concrete dam 23, so the corresponding concrete dam support rod 12 can be removed from the inside of the support sleeve of the concrete dam 23, thereby facilitating the installation of the liner 26 in the support sleeve 24 in the subsequent steps.
[0084] Combination Figure 4As shown, a flange 241 is provided at the outer edge of the top end of the support sleeve 24, and the support sleeve 24 and the flange 241 can be an integral structure; in step S43, the liner 26 is embedded in the interior of the support sleeve 24, so as to shield the damaged part of the support sleeve 24 from the inner side of the support sleeve 24 through the liner 26; the top end of the liner 26 is sealedly connected to the flange 241 of the support sleeve 24, so as to realize the fixed connection between the top end of the liner 26 and the top flange of the support sleeve 24; the bottom end of the liner 26 is sealedly connected to the piston bottom plate 21, and the bottom end of the liner 26 is welded and fixed to the bottom end of the support sleeve 24, which not only realizes the fixed connection between the bottom end of the liner 26 and the piston bottom plate 21, but also prevents the gas from leaking upward from the gap between the liner 26 and the bottom end of the support sleeve 24 through the corrosion and damage of the support sleeve 24 and the internal gap of the concrete dam 23 to the top of the piston assembly 2.
[0085] A sleeve opening is provided on the piston bottom plate 21 , and the bottom end of the liner 26 can be sealed and connected to the sleeve opening of the piston bottom plate 21 by welding to achieve a fixed connection between the liner 26 and the piston bottom plate 21 .
[0086] In step S44, the portion of the top end of the liner 26 that extends beyond the flange of the support sleeve 24 is cut to avoid interference with the connection between the concrete dam support rod 12 and the support sleeve 24 in subsequent steps; wherein, the cut portion of the top end of the liner 26 can also be polished smooth with a polishing tool to facilitate a tighter connection between the concrete dam support rod 12 and the support sleeve 24 in subsequent steps.
[0087] S45. The concrete dam support rod 12 can be divided into two parts, one part is basically a disc structure, and the other part is basically a cylindrical structure. The concrete dam support rod 12 is passed through the liner 26 from top to bottom. Specifically, the disc structure of the concrete dam support rod 12 is connected to the flange 241 of the support sleeve 24 through a fastener 27, and the cylindrical structure of the concrete dam support rod 12 is coaxially passed through the interior of the liner 26. The bottom end of the concrete dam support rod 12 can be connected to the piston bottom plate, so that the concrete dam support rod 12 and the flange 241 of the support sleeve 24 are fixed in a manner to facilitate the support of the concrete dam 23 with the liner 26 already installed in the support sleeve 24 through the concrete dam support rod 12, so as to complete the processing of the damaged support sleeve 24 there, thereby avoiding the sinking problem of the area where the liner has been installed when the liner is installed in the support sleeve at other positions in the subsequent steps.
[0088] Among them, the above steps S41 to S45 involve the steps of installing the liner 26 in the support sleeve 24, specifically the steps of installing the liner 26 in one of the support sleeves 24, and the piston assembly may include a plurality of concrete dams 23, and the plurality of concrete dams 23 may be arranged in a basically circular shape around the central axis of the cabinet, and at least one support sleeve may be arranged in each concrete dam 23. Therefore, the installation of the liner inside the support sleeve of the concrete dams 23 at other positions may refer to the above steps S41 to S45.
[0089] Optionally, S4, raising the concrete dam 23, removing the concrete dam support rod 12 from the concrete dam 23, assembling the liner 26 into the support sleeve 24, so that the top end of the liner 26 is sealedly connected to the flange 241 of the support sleeve 24, and the bottom end of the liner 26 is sealedly connected to the piston bottom plate 21, further includes:
[0090] Before the liner 26 is embedded in the support sleeve 24 , the interior of the support sleeve 24 is cleaned.
[0091] It should be noted that by cleaning the inner wall of the support sleeve 24, the inner wall of the support sleeve 24 is made smooth to prevent the support sleeve 24 and the liner 26 inside it from being unable to be coaxial due to the uneven inner wall of the support sleeve 24, thereby improving the accuracy and stability of the liner 26 installed in the support sleeve 24.
[0092] Optionally, after the concrete dam support rod 12 and the piston support rod are lowered to the cabinet bottom plate 11 , the inspection door provided on the side wall plate of the cabinet body 1 is opened to perform a safety inspection on the internal environment of the cabinet body 1 .
[0093] Specifically, an inspection door is provided at the side wall of the cabinet 1 to facilitate maintenance personnel to enter the interior of the cabinet 1 after the concrete dam support rod 12 and the piston support rod are lowered to the cabinet bottom plate 11, so as to conduct a safety inspection of the internal environment of the cabinet 1 to determine whether the safety conditions for subsequent operations are met.
[0094] Optionally, S1, when the energy storage cabinet is switched to the maintenance state, controlling the carbon monoxide content and the oxygen content in the cabinet 1 to be lower than the corresponding gas preset values by replacement means includes:
[0095] S11, stopping the operation of the gas holder to switch to the maintenance state;
[0096] S12, replacing coal gas with nitrogen to control the carbon monoxide content in the cabinet 1 to be lower than a first gas preset value;
[0097] S13, replacing nitrogen with air to control the oxygen content in the cabinet 1 to be lower than a second gas preset value.
[0098] Specifically, in step S11, the gas holder is stopped from running, for example, the gas holder may be shut down, so as to switch the gas holder to a maintenance state.
[0099] In step S12, the coal gas is replaced by nitrogen, in other words, nitrogen is allowed to enter the cabinet 1 to discharge the original coal gas in the cabinet 1. At this time, the content of carbon monoxide in the mixed gas in the cabinet 1 can be effectively reduced until the content of carbon monoxide in the cabinet 1 is lower than the first gas preset value, thereby eliminating the risk of explosion and gas poisoning in subsequent operations due to the carbon monoxide content in the coal gas in the cabinet 1 exceeding the first gas preset value.
[0100] In step S13, nitrogen is replaced by air, in other words, air is allowed to enter the cabinet 1 to discharge the nitrogen in the cabinet 1. At this time, the oxygen content in the mixed gas in the cabinet 1 can be effectively reduced until the oxygen content in the cabinet 1 is lower than the preset value of the second gas, thereby eliminating the risk of nitrogen asphyxiation in subsequent operations due to the oxygen content in the cabinet 1 exceeding the preset value of the second gas.
[0101] Among them, the first gas preset value refers to the content of carbon monoxide in the mixed gas in the cabinet 1 that will not cause an explosion, for example, when the carbon monoxide content is lower than 24ppm, the nitrogen replacement gas is qualified, and in subsequent operations, there will be no explosion risk due to the carbon monoxide content lower than 24ppm; the second gas preset value refers to the content of oxygen in the mixed gas in the cabinet 1 that will not cause an explosion of carbon monoxide, for example, when the oxygen content is greater than 19.5%, the nitrogen replacement gas is qualified.
[0102] Optionally, combined Figure 6 As shown, the energy storage cabinet further includes an air inlet pipeline 4, an air outlet pipeline 5, a nitrogen pipeline 13, a first vent pipe 6 and a second vent pipe 7, wherein the first vent pipe 6 is arranged on the cabinet body 1, the air inlet pipeline 4 and the air outlet pipeline 5 are respectively connected to different second vent pipes 7, and the air inlet pipeline 4, the air outlet pipeline 5 and the nitrogen pipeline 13 are respectively connected to the cabinet body 1;
[0103] S12, the step of replacing coal gas with nitrogen to control the carbon monoxide content in the cabinet 1 to be lower than a first gas preset value comprises:
[0104] S121, opening the first vent pipe 6 and the second vent pipe 7;
[0105] S122, filling nitrogen into the cabinet 1 through the nitrogen pipeline 13, replacing the coal gas with the nitrogen, and discharging the coal gas from the first vent pipe 6, and from the second vent pipe 7 through the gas outlet pipeline 5;
[0106] S123, closing the first vent pipe 6 and the second vent pipe 7, and raising the piston assembly 2 to allow the nitrogen in the cabinet 1 to be fully mixed with the residual gas;
[0107] S124, open the first vent pipe 6 and the second vent pipe 7, discharge the gas fully mixed with nitrogen and residual gas from the first vent pipe 6, and discharge it from the second vent pipe 7 through the gas outlet pipe 5, until the carbon monoxide content in the cabinet 1 is lower than the first gas preset value.
[0108] Specifically, the air inlet pipe 4 is a pipe for the gas to enter the cabinet 1, the air outlet pipe 5 is a pipe for the gas to be discharged from the cabinet 1, and the nitrogen pipe 13 is a pipe for the nitrogen to enter the cabinet 1. The first vent pipe 6 is arranged on the cabinet 1 (see Figure 1 As shown in FIG. 1 , the first vent pipe 6 can be connected to the outer membrane 32 in the T-type assembly 3 so that nitrogen replaces the coal gas, so as to discharge the coal gas in the cabinet 1 from the first vent pipe 6. The number of the first vent pipe 6 is at least one. The number of the second vent pipes 7 is multiple, for example, at least one second vent pipe 7 can be respectively provided on the air inlet pipeline 4 and the air outlet pipeline 5. A first vent valve is provided on the first vent pipe 6, and a second vent valve is provided on the second vent pipe 7. An air inlet valve 8 is provided on the air inlet pipeline 4, and an air outlet valve 9 is provided on the air outlet pipeline 5.
[0109] In step S121, before nitrogen is charged into the cabinet 1, the first vent pipe 6 and the second vent pipe 7 are opened first, which is beneficial for increasing the number of vent pipes opened when nitrogen is charged into the cabinet 1 later, so as to improve the gas discharge efficiency in the cabinet 1 under the action of nitrogen and the reliability of nitrogen replacement of gas; for example, the first vent pipe 6 can be opened by opening the first vent valve, and the second vent pipe 7 can be opened by opening the second vent valve.
[0110] In step S122, see Figure 6 As shown, one end of the nitrogen pipeline 13 is connected to the cabinet 1, and the other end of the nitrogen pipeline 13 can be connected to the nitrogen cabinet, so that the nitrogen in the nitrogen cabinet can enter the cabinet 1 through the nitrogen pipeline 13, and a part of the original coal gas in the cabinet 1 is discharged from the first vent pipe 6 through the outer membrane 32 by replacing the coal gas with nitrogen, and the other part of the coal gas is discharged from the second vent pipe 7 through the gas outlet pipeline 5, so as to realize the process of replacing the original coal gas in the cabinet 1 with nitrogen.
[0111] In step S123, the coal gas is replaced by nitrogen in the above steps, and the carbon monoxide content of the coal gas in the cabinet 1 may still be higher than the first gas preset value. Therefore, the first relief valve can be closed to close the first relief pipe 6, and the second relief valve can be closed to close the second relief pipe 7; then the piston assembly 2 is raised to fully mix the nitrogen in the cabinet 1 with the residual coal gas by compression, thereby providing conditions for better discharge of the residual coal gas in subsequent steps.
[0112] In step S124, the first vent pipe 6 and the second vent pipe 7 are then opened to discharge a portion of the nitrogen and residual gas fully mixed in the cabinet 1 directly from the first vent pipe 6 through the outer membrane 32, and the other portion is discharged from the second vent pipe 7 through the gas outlet pipeline 5, so as to further ensure that the carbon monoxide content in the cabinet 1 is lower than the preset value of the first gas, and accordingly ensure the qualified probability of the nitrogen replacement gas operation.
[0113] Among them, carbon monoxide sensors can be installed at the first vent pipe 6 and the second vent pipe 7 to detect the content of carbon monoxide discharged from the first vent pipe 6 and the second vent pipe 7 to determine whether it is lower than the first gas preset value. If the carbon monoxide content is lower than the first gas preset value, it is determined that the nitrogen gas replacement operation is qualified.
[0114] Optionally, S13, replacing nitrogen by air to control the oxygen content in the cabinet 1 to be lower than a second gas preset value includes:
[0115] S131, connecting the air blowing device 10 to the cabinet 1, and opening the first venting pipe 6 and the second venting pipe 7;
[0116] S132, control the blowing device 10 to work, rush air into the cabinet 1, replace nitrogen with air, discharge the nitrogen from the first vent pipe 6, and discharge from the second vent pipe 7 through the air outlet pipe 5, until the oxygen content in the cabinet 1 is lower than the preset value of the second gas.
[0117] Specifically, in step S131, Figure 7 As shown, the blowing device 10, such as a blower, is connected to the cabinet 1, and then the first vent pipe 6 and the second vent pipe 7 are opened. This is beneficial for increasing the number of vent pipes opened when air enters the cabinet 1 later, so as to improve the discharge efficiency of nitrogen in the cabinet 1 and the reliability of air replacing nitrogen under the action of air; for example, the first vent pipe 6 can be opened by opening the first vent valve, and the second vent pipe 7 can be opened by opening the second vent valve.
[0118] In step S132, the blower 10 is then controlled to work, so that the air outside the cabinet 1 enters the interior of the cabinet 1 through the blower 10, and in a manner of replacing coal gas with nitrogen, a part of the nitrogen in the previous step in the cabinet 1 is discharged from the first vent pipe 6 through the outer membrane 32 by using air, and the other part of the nitrogen is discharged from the second vent pipe 7 through the outlet pipe 5, until the oxygen content in the cabinet 1 is lower than the preset value of the second gas, so as to realize the process of replacing the nitrogen in the cabinet 1 with air.
[0119] Among them, oxygen sensors can also be installed at the first vent pipe 6 and the second vent pipe 7 to detect the content of oxygen discharged from the first vent pipe 6 and the second vent pipe 7 to determine whether it is lower than the second gas preset value. If the oxygen content is lower than the second gas preset value, it is determined that the air replacement nitrogen operation is qualified.
[0120] Optionally, the energy storage cabinet further includes an air inlet valve 8 and an air outlet valve 9, wherein the air inlet valve 8 is arranged on the air inlet pipeline 4, and the air outlet valve 9 is arranged on the air outlet pipeline 5;
[0121] S11, stopping the operation of the gas holder to switch to the maintenance state includes:
[0122] The gas holder is stopped from operating, and the air inlet valve 8 and the air outlet valve 9 are closed, so that the gas holder is switched to the maintenance state.
[0123] Specifically, the gas holder is stopped from running, and the air inlet valve 8 and the air outlet valve 9 are closed first, which not only switches the gas holder from the normal state to the maintenance state, but also prevents the gas from directly overflowing from the air outlet pipeline 5 in the early stage of nitrogen replacement of the gas.
[0124] Optionally, the energy storage cabinet further includes a nitrogen valve and a first blind plate, the nitrogen pipeline 13 is in communication with the cabinet 1, the nitrogen valve is arranged on the nitrogen pipeline 13, and the first blind plate is detachably installed on one end of the nitrogen pipeline 13 close to the cabinet 1;
[0125] S2, raising the piston assembly 2 so that the piston bottom plate 21 is separated from the cabinet bottom plate 11 of the cabinet body 1 to a preset height difference, including:
[0126] S21, closing the nitrogen valve, and installing the first blind plate at one end of the nitrogen pipeline 13 close to the cabinet;
[0127] S22, filling air into the cabinet 1 through the air blowing device 10 to raise the piston assembly 2 until the piston bottom plate 21 is separated from the cabinet bottom plate 11 of the cabinet 1 to a preset height difference.
[0128] Specifically, in step S21, after the air replaces the nitrogen and it is qualified, the nitrogen valve needs to be closed, and the first blind plate needs to be installed at one end of the nitrogen pipeline 13 close to the cabinet, wherein the first blind plate is located on the side of the nitrogen valve facing the cabinet 1, so that the nitrogen cabinet connected to the nitrogen pipeline 13 can be completely disconnected from the cabinet 1 through the first blind plate.
[0129] In step S22, the blowing device 10, such as a blower, is connected to the cabinet 1 through a pipeline, so that when the blowing device 10 is in working state, the air outside the cabinet 1 is sent into the interior of the cabinet 1, for example, into the endothelial membrane 25, so that the piston assembly 2 is raised until the piston bottom plate 21 is separated from the cabinet bottom plate 11 of the cabinet 1 to a preset height difference, so as to ensure that the piston bottom plate 21 is completely separated from the cabinet bottom plate 11, thereby facilitating maintenance personnel to enter the bottom of the piston assembly 2 to perform corresponding operations in subsequent steps.
[0130] Among them, in step S41 to S45 in step S4, the installation of the liner 26 in the support sleeve 24 can be completed, specifically, the step of installing the liner 26 in one of the support sleeves 24, and then, referring to steps S41 to S45, the liner 26 can be assembled inside the support sleeves 24 at other positions, so as to realize the processing operation of assembling the liner 26 inside all the support sleeves 24 respectively; then, the piston assembly 2 can be raised to a certain height by filling air into the cabinet 1 through the air blowing device 10, so as to facilitate maintenance personnel to enter the area between the piston bottom plate 21 and the cabinet bottom plate 11, remove the concrete dam support rod 12 in each liner 26, and remove the piston support rod under the piston bottom plate 21; combined with Figure 8 As shown, the piston assembly 2 further includes a second blind plate 28, which is installed above the support sleeve 24, and the second blind plate 28 can be fixedly connected to the flange 241 of the support sleeve 24 by a fastener 27 (combined with Figure 8 As shown), the liner 26 is sealed from above through the second blind plate 28 to prevent the gas from leaking from the top of the liner 26 to the top of the piston assembly 2 in the subsequent working state, thereby completing the maintenance work of the internal installation liner 26 of all the supporting sleeves 24 in the gas tank.
[0131] After the above leakage treatment operation is completed, the gas holder can be restored to the working operation state from the above maintenance state by referring to the following method. For example, after the above maintenance operation is completed, the maintenance personnel inspect the above maintenance operation; after the acceptance is qualified, the maintenance personnel withdraw from the cabinet 1 and close the inspection door on the side wall of the cabinet 1; then open the first vent pipe 6 on the cabinet 1 to make the piston assembly 2 drop to the cabinet bottom plate 11; then open the air inlet pipeline 4 and the air outlet pipeline 5, and replace the air with nitrogen, for example, fill the cabinet 1 with nitrogen through a nitrogen cabinet to replace the air in the above steps. Part of the air in the cabinet 1 is discharged from the first vent pipe 6, and the other part is discharged from the second vent pipe 7 through the air outlet pipe 5. At this time, the oxygen content in the cabinet 1 is detected. If the oxygen content in the cabinet 1 is lower than 1%, it is judged that the nitrogen replacement of air is qualified; finally, the nitrogen is replaced by coal gas. For example, the coal gas enters the interior of the cabinet 1 through the air inlet pipe 4 to discharge the nitrogen in the cabinet 1 from the first vent pipe 6 and the second vent pipe 7. At this time, an explosion test can be performed on the cabinet 1. If the coal gas can be ignited, it is judged that the coal gas replacement of nitrogen is qualified, thereby completing the above-mentioned preliminary preparations for the gas cabinet to be put into operation.
[0132] Another embodiment of the present invention provides a gas cabinet, which can be obtained by adopting the leakage treatment method of the support sleeve of the above-mentioned gas cabinet, including a cabinet body 1 and a piston assembly 2, the piston assembly 2 including a piston bottom plate 21, a concrete dam 23, a support sleeve 24 and a liner 26, the concrete dam 23 is arranged on the piston bottom plate 21, the support sleeve 24 is penetrated by the concrete dam 23, the liner 26 is embedded in the support sleeve 24, and the top and bottom ends of the liner 26 are respectively corresponding to the flange of the support sleeve 24 and the piston bottom plate 21 for sealing connection.
[0133] Specifically, combined Figure 5 and Fig. 9 As shown, the gas tank also includes an inner membrane 25 and an outer membrane 32, and the piston assembly 2 also includes a piston fence 22, a fastener 27, a second blind plate 28 and a piston corrugated plate 29, wherein the concrete dam 23 is installed inside the piston fence 22, and the support sleeve 24 is vertically penetrated in the concrete dam 23 (see Figure 5 As shown), the liner 26 is inserted into the interior of the support sleeve 24, and the two are coaxially arranged. The bottom end of the liner 26 and the bottom end of the support sleeve 24 are sealed and connected to the sleeve opening of the piston bottom plate 21. A second blind plate 28 is provided on the top end of the support sleeve 24. At this time, the second blind plate 28 can be fixedly connected to the flange of the support sleeve 24 through a fastener 27 (see Figure 8 As shown), the top of the liner 26 is sealed by the second blind plate 28 to prevent the gas from leaking from the top of the liner 26 to the top of the piston assembly 2 when the gas cabinet is in operation; the endothelial membrane 25 is located between the piston fence 22 and the side wall of the cabinet 1.
[0134] The gas cabinet further comprises a T-type assembly 3, which mainly comprises a T-type baffle 31, and the T-type baffle 31 comprises a T-type fence 311 and a T-type corrugated plate 312, wherein the T-type assembly 3 is arranged above the piston assembly 2, and the T-type corrugated plate 312 is arranged on the side of the T-type fence 311 facing the side wall plate of the cabinet body 1, and the T-type baffle 31 is connected and sealed with the side wall plate of the cabinet body 1 through an outer membrane 32 (see Fig.10 As shown), the T-shaped baffle 31 and the piston bottom plate 21 are connected and sealed via an endothelial membrane 25.
[0135] The beneficial effects of the gas cabinet of this embodiment compared with the prior art are the same as the leakage treatment method of the supporting sleeve of the gas cabinet described above, which will not be described in detail here.
[0136] Although the present invention is disclosed as above, the protection scope of the present invention is not limited thereto. Those skilled in the art may make various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications will fall within the protection scope of the present invention.
Claims
1. A method for treating leakage of a supporting sleeve of a gas tank, characterized in that: The gas tank comprises a tank body (1) and a piston assembly (2), wherein the piston assembly (2) comprises a piston bottom plate (21), a concrete dam (23), a support sleeve (24) and a liner (26), wherein the concrete dam (23) is arranged on the piston bottom plate (21), the support sleeve (24) is penetrated through the concrete dam (23), the liner (26) is embedded in the support sleeve (24), and the top end and the bottom end of the liner (26) are respectively corresponding to the flange (241) of the support sleeve (24) and the piston bottom plate (21) and are sealed and connected; The leakage treatment method comprises the following steps: When the energy storage cabinet is switched to the maintenance state, the carbon monoxide content and the oxygen content in the cabinet (1) are controlled to be lower than the corresponding gas preset values respectively by replacement; Raising the piston assembly (2) so that the piston bottom plate (21) is separated from the cabinet bottom plate (11) of the cabinet body (1) to a preset height difference; A concrete dam support rod (12) is installed in each of the support sleeves (24), and a plurality of piston support rods are installed below the piston bottom plate (21), and the piston assembly (2) is lowered so that the concrete dam support rod (12) and the piston support rod fall to the cabinet bottom plate (11); The concrete dam (23) is raised, the concrete dam support rod (12) is removed from the concrete dam (23), and the liner (26) is assembled in the support sleeve (24), so that the top end of the liner (26) is sealedly connected to the flange (241) of the support sleeve (24), and the bottom end of the liner (26) is sealedly connected to the piston bottom plate (21).
2. The method for handling leakage of a support sleeve of a gas tank according to claim 1, characterized in that: The step of raising the concrete dam (23), removing the support sleeve (24) and the concrete dam support rod (12) from the concrete dam (23), assembling the liner (26) into the support sleeve (24), and sealingly connecting the top end of the liner (26) to the flange (241) of the support sleeve (24), and sealingly connecting the bottom end of the liner (26) to the piston bottom plate (21) comprises: A lifting device is installed below the concrete dam (23) and around the concrete dam support rod (12) to lift up the concrete dam (23) so that the concrete dam support rod (12) no longer bears the pressure of the concrete dam (23); Removing the concrete dam support rod (12) in the concrete dam (23); The liner (26) is embedded in the interior of the support sleeve (24); the top end of the liner (26) is sealedly connected to the flange (241) of the support sleeve (24), and the bottom end of the liner (26) is sealedly connected to the piston bottom plate (21); Cutting the portion of the top end of the liner (26) that exceeds the flange (241) of the support sleeve (24); The concrete dam support rod (12) is inserted into the liner (26) from top to bottom, and the concrete dam support rod (12) is connected to the flange (241) of the support sleeve (24) via a fastener (27).
3. The method for handling leakage of a support sleeve of a gas tank according to claim 2, characterized in that: The method of raising the concrete dam (23), removing the concrete dam support rod (12) from the concrete dam (23), assembling the liner (26) into the support sleeve (24), and sealingly connecting the top end of the liner (26) to the flange (241) of the support sleeve (24), and sealingly connecting the bottom end of the liner (26) to the piston bottom plate (21) further comprises: Before the liner (26) is embedded in the interior of the support sleeve (24), the interior of the support sleeve (24) is cleaned.
4. The method for handling leakage of a support sleeve of a gas tank according to claim 1, characterized in that: After the concrete dam support rod (12) and the piston support rod are lowered to the cabinet bottom plate (11), the inspection door provided on the side wall plate of the cabinet body (1) is opened to perform a safety inspection on the internal environment of the cabinet body (1).
5. The method for handling leakage of a support sleeve of a gas tank according to claim 1, characterized in that: When the energy storage cabinet is switched to the maintenance state, controlling the carbon monoxide content and the oxygen content in the cabinet (1) to be lower than the corresponding gas preset values by replacement means includes: Stopping the operation of the gas tank to switch to the maintenance state; By replacing coal gas with nitrogen, the carbon monoxide content in the cabinet (1) is controlled to be lower than a first gas preset value; By replacing nitrogen with air, the oxygen content in the cabinet (1) is controlled to be lower than a second gas preset value.
6. The method for handling leakage of a support sleeve of a gas tank according to claim 5, characterized in that: The energy storage cabinet further comprises an air inlet pipeline (4), an air outlet pipeline (5), a nitrogen pipeline (13), a first venting pipe (6) and a second venting pipe (7); the first venting pipe (6) is arranged on the cabinet body (1); the air inlet pipeline (4) and the air outlet pipeline (5) are respectively connected to different second venting pipes (7); the air inlet pipeline (4), the air outlet pipeline (5) and the nitrogen pipeline (13) are respectively connected to the cabinet body (1); The step of replacing coal gas with nitrogen to control the carbon monoxide content in the cabinet (1) to be lower than a first gas preset value comprises: Opening the first vent pipe (6) and the second vent pipe (7); Filling nitrogen into the cabinet (1) through the nitrogen pipeline (13), displacing the coal gas with the nitrogen, discharging the coal gas from the first vent pipe (6), and discharging the coal gas from the second vent pipe (7) through the gas outlet pipeline (5); The first vent pipe (6) and the second vent pipe (7) are closed, and the piston assembly (2) is raised to allow the nitrogen in the cabinet (1) to be fully mixed with the residual coal gas; The first vent pipe (6) and the second vent pipe (7) are opened, and the gas fully mixed with the nitrogen and the residual coal gas is discharged from the first vent pipe (6), and discharged from the second vent pipe (7) through the gas outlet pipeline (5), until the carbon monoxide content in the cabinet (1) is lower than the first gas preset value.
7. The method for handling leakage of a support sleeve of a gas tank according to claim 6, characterized in that: Controlling the oxygen content in the cabinet (1) to be lower than a second gas preset value by replacing nitrogen with air comprises: Connecting the air blowing device (10) to the cabinet (1), and opening the first venting pipe (6) and the second venting pipe (7); The blower device (10) is controlled to operate, and air is blown into the cabinet (1), and the nitrogen is replaced by air, and the nitrogen is discharged from the first discharge pipe (6), and is discharged from the second discharge pipe (7) through the air outlet pipeline (5), until the oxygen content in the cabinet (1) is lower than the preset value of the second gas.
8. The method for handling leakage of a support sleeve of a gas tank according to claim 6, characterized in that: The energy storage cabinet further comprises an air inlet valve (8) and an air outlet valve (9), wherein the air inlet valve (8) is arranged on the air inlet pipeline (4), and the air outlet valve (9) is arranged on the air outlet pipeline (5); The step of stopping the operation of the gas holder to switch to the maintenance state includes: The gas holder is stopped from operating, and the air inlet valve (8) and the air outlet valve (9) are closed, so that the gas holder is switched to the maintenance state.
9. The method for handling leakage of a support sleeve of a gas tank according to claim 6, characterized in that: The energy storage cabinet further comprises a nitrogen valve and a first blind plate, the nitrogen pipeline (13) is in communication with the cabinet (1), the nitrogen valve is arranged on the nitrogen pipeline (13), and the first blind plate is detachably mounted on one end of the nitrogen pipeline (13) close to the cabinet (1); Raising the piston assembly (2) so that the piston bottom plate (21) is separated from the cabinet bottom plate (11) of the cabinet body (1) to a preset height difference comprises: The nitrogen valve is closed, and the first blind plate is installed at one end of the nitrogen pipeline (13) close to the cabinet; Air is injected into the cabinet (1) through an air blowing device (10) to raise the piston assembly (2) until the piston bottom plate (21) is separated from the cabinet bottom plate (11) of the cabinet (1) to the preset height difference.
10. A gas cabinet, characterized in that: The invention comprises a cabinet (1) and a piston assembly (2), wherein the piston assembly (2) comprises a piston bottom plate (21), a concrete dam (23), a support sleeve (24) and a liner (26), wherein the concrete dam (23) is arranged on the piston bottom plate (21), the support sleeve (24) is penetrated through the concrete dam (23), the liner (26) is embedded in the support sleeve (24), and the top end and the bottom end of the liner (26) are respectively corresponding to the flange (241) of the support sleeve (24) and the piston bottom plate (21) and are sealed and connected.
Citation Information
Patent Citations
Method for dismounting tank top system of thin oil sealing-type dry-type gas tank
CN101684885A
Blast furnace gas pipe leakage stopping device and method
CN110953437A
Lining pipe and repairing method thereof
CN115875533A
Oil-leakage prevention manhole for side board of thin-oil sealing gas cabinet
CN202188295U
Gas chamber nitrogen gas replacement firebreak device
CN205173969U