Project construction multi-target optimization method considering carbon emission whole life cycle evaluation

By constructing a low-carbon and economic benefit evaluation index system for power grid infrastructure, combined with the entropy weight method and quantum particle swarm algorithm, the multi-objective optimization problem of carbon emissions and economic benefits in power grid project construction has been solved, and the systematization of the entire life cycle has been achieved. Evaluation and comprehensive benefit optimization improve the scientificity and feasibility of decision-making.

CN118780745AActive Publication Date: 2024-10-15STATE GRID FUJIAN POWER ELECTRIC CO ECONOMIC RESEARCH INSTITUTE +1

Patent Information

Application Number
CN202410715698.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2024-10-15
Estimated Expiration
2044-06-04

AI Technical Summary

Technical Problem

Carbon emission assessment and multi-objective optimization decision-making during the entire life cycle of power grid infrastructure construction projects face problems such as data complexity, limitations of evaluation methods, strong subjectivity in weight determination, and low efficiency of optimization algorithms. It is difficult to fully consider carbon emissions with existing technology. and balance of economic benefits.

Method used

A multi-objective optimization method for project construction that considers the full life cycle assessment of carbon emissions is proposed. By constructing an evaluation index system for low-carbon benefits and economic benefits, combining the entropy weight method and the laboratory method to calculate the weight, the QPSO quantum particle swarm algorithm and small The habitat genetic algorithm is used to solve the optimization model and achieve the optimal ranking of the comprehensive benefits of the project.

Benefits of technology

It achieves systematic evaluation from a full life cycle perspective and scientific and reasonable weight distribution, improves the solution efficiency and quality of multi-objective optimization, ensures the comprehensive optimality and decision-making feasibility of the project, and supports scientific decision-making in green power grid construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780745A_ABST
    Figure CN118780745A_ABST
Patent Text Reader

Abstract

The invention relates to a project construction multi-target optimization method considering carbon emission full-life cycle evaluation, which comprises the following steps of: firstly, analyzing system composition of power grid infrastructure, and combining construction engineering characteristics and low-carbon evaluation contents of the power grid infrastructure; constructing a whole-life-cycle carbon emission evaluation index system and a power grid infrastructure economic benefit evaluation index system; respectively calculating the subjective weight and objective weight of each evaluation index by using an entropy weight method and a laboratory method; the method comprises the following steps: constructing a combined weight optimization model considering subjective weight and objective weight, solving the combined weight optimization model based on a QPSO quantum particle swarm optimization algorithm, calculating the combined weight of each evaluation index, setting constraint conditions, and constructing a multi-target optimization model based on economic benefit and low-carbon benefit optimization. And solving the multi-objective optimization model by using a niche genetic algorithm to obtain a project construction scheme with optimal comprehensive benefits, and realizing project optimization and sorting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of project optimization and sorting, and in particular relates to a multi-objective optimization method for project construction considering full life cycle evaluation of carbon emissions. Background Art

[0002] In the current context of global energy structure transformation, as a bridge connecting energy production and consumption, the green and intelligent upgrade of grid infrastructure construction is particularly important. Grid companies are faced with the dual challenges of ensuring safe and reliable power supply and significantly reducing carbon emissions. Therefore, from the perspective of the entire life cycle, scientifically evaluating the carbon footprint of grid infrastructure construction projects and optimizing decisions on this basis have become urgent needs for the development of the industry.

[0003] Technology development trends:

[0004] 1. Digital transformation: The rapid development of digital technologies, such as the Internet of Things, big data, and artificial intelligence, has provided new tools and methods for intelligent operation and maintenance, energy consumption monitoring, and carbon emission management of power grid infrastructure, promoting the improvement of management efficiency and accuracy.

[0005] 2. Low-carbon technology integration: The application of new materials, new energy technologies, and the development of smart grids and microgrids provide technical support for reducing carbon emissions during grid construction and operation.

[0006] 3. Promotion of green finance: With the improvement of the green finance system, financial products such as green credit and green bonds have provided financial support for low-carbon power grid construction projects, prompting projects to pay more attention to environmental friendliness during design and implementation.

[0007] Challenges

[0008] 1. Difficulty in data acquisition and processing: The carbon emissions of power grid construction projects over their entire life cycle involve a large amount of complex data, including material production, transportation, construction, operation and maintenance, and other links. Accurate acquisition and efficient processing of data is a major challenge.

[0009] 2. Conflict of multiple objectives: While pursuing economic benefits, we must also take into account multiple objectives such as environmental protection and social responsibility. How to find the best balance among these objectives is a complex decision-making problem.

[0010] 3. Limitations of evaluation and optimization methods: Traditional evaluation methods and optimization models are often unable to fully cope with the complexity, dynamics and uncertainty of power grid construction projects, especially the lack of intelligent optimization algorithms that can effectively integrate multi-source information and process high-dimensional data.

[0011] Defects of the prior art:

[0012] 1. Limitations of the evaluation system: Most existing evaluation methods focus on a single dimension, such as only paying attention to economic benefits or environmental impacts, and lack a comprehensive consideration of carbon emissions throughout the life cycle of power grid construction projects.

[0013] 2. The determination of weights is highly subjective: When constructing a multi-objective optimization model, the determination of indicator weights often relies on subjective methods such as expert scoring, lacking a balance between scientificity and objectivity.

[0014] 3. Efficiency and effectiveness of optimization algorithms: Traditional optimization algorithms are prone to fall into local optimal solutions when dealing with complex, high-dimensional multi-objective optimization problems, and the search efficiency is low, making it difficult to fully explore the diversity of the solution space.

[0015] 4. Insufficient project optimization and decision-making support: Existing technologies fail to effectively combine engineering practice with comprehensive consideration of economic and low-carbon benefits, especially fail to fully utilize modern intelligent optimization algorithms to efficiently process and prioritize large-scale project data. Summary of the invention

[0016] In order to solve the above technical problems, the present invention proposes a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions.

[0017] The technical solution of the present invention is as follows:

[0018] On the one hand, the present invention proposes a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, comprising the following steps:

[0019] Analyze the system composition of power grid infrastructure, and build a low-carbon benefit evaluation index system for power grid infrastructure and an economic benefit evaluation index system for power grid infrastructure in combination with the characteristics of power grid infrastructure construction projects and low-carbon evaluation content;

[0020] Based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure, the subjective weight and objective weight of each evaluation index are calculated using the entropy weight method and laboratory method.

[0021] Construct a combined weight optimization model that considers subjective weight and objective weight, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weight of each evaluation index;

[0022] Set constraints and build a multi-objective optimization model based on the best economic and low-carbon benefits;

[0023] The microhabitat genetic algorithm is used to solve the multi-objective optimization model, obtain the project construction plan with the best comprehensive benefits, and realize the optimal ranking of projects.

[0024] As a preferred implementation, the multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, the steps of analyzing the system composition of the power grid infrastructure, combining the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content, and constructing the low-carbon benefit evaluation index system of the power grid infrastructure and the economic benefit evaluation index system of the power grid infrastructure:

[0025] The whole life cycle of power grid infrastructure construction projects is divided into different stages, including planning stage, design stage, construction stage, operation stage and dismantling and recycling stage;

[0026] According to the characteristics of each stage, a number of corresponding carbon emission evaluation indicators are set.

[0027] As a preferred implementation, the multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, the steps of using the entropy weight method and the laboratory method to calculate the subjective weight and objective weight of each evaluation index are specifically as follows:

[0028] The subjective weight of each evaluation index is calculated using the DEMATEL decision test and evaluation test method; the following steps are included:

[0029] Determine the mutual influence between each evaluation indicator through questionnaire / expert scoring, and build an initial influence matrix based on the mutual influence between each evaluation indicator;

[0030] Perform standard normalization on the initial influence matrix O to obtain the normalized matrix WN, the formula is as follows:

[0031]

[0032] Where r is the normalized number of indicators, O bh is the element in the bth row and hth column;

[0033] Calculate the comprehensive impact matrix T, the formula is as follows:

[0034]

[0035] Where I is the unit matrix, WN p is the pth normalized matrix;

[0036] The comprehensive influence matrix is ​​used to calculate the various parameter values ​​of each indicator, including the influence value D, the influence value C, the centrality value D+C, and the cause value DC. The calculation formulas for the influence value D and the influence value C are as follows:

[0037]

[0038] In the formula, e and f represent two interacting evaluation indicators;

[0039] Normalize the centrality value D+C or the cause value DC so that the sum of the centrality value D+C or the cause value DC of each evaluation index is 1, and use the normalized centrality value D+C or the cause value DC as the subjective weight vector of each evaluation index;

[0040] The entropy weight method is used to calculate the objective weight of each evaluation index, including the following steps:

[0041] Normalize the data of each evaluation indicator to ensure that the data values ​​of each evaluation indicator are at the same level;

[0042] For each evaluation index, calculate the proportion of each sample data value to the total data value of the evaluation index to obtain the probability distribution of each evaluation index;

[0043] The information entropy of each evaluation indicator is calculated based on its probability distribution, and the information utility value is calculated through the information entropy of each evaluation indicator. Each information utility value is normalized so that the sum of the normalized information utility values ​​corresponding to each evaluation indicator is 1, and the normalized information utility value is used as the objective weight of the corresponding evaluation indicator.

[0044] As a preferred implementation, the multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, the steps of solving the combined weight optimization model based on the QPSO quantum particle swarm algorithm are specifically as follows:

[0045] Set the initial parameters, including population size, learning factor, maximum number of iterations, initial speed, number of indicators, and inertia weight;

[0046] An initial population is generated, wherein each particle in the initial population represents a combined weight configuration of an evaluation index, wherein the combined weight configuration is generated by adjusting the subjective weight and the objective weight of the corresponding evaluation index, and an initial position and an initial velocity of each particle are randomly generated;

[0047] The fitness of each particle in the initial population is calculated to find the global optimal particle and the individual optimal particle, where the fitness function is configured as the error function between the actual carbon emission evaluation value and the carbon emission prediction value calculated based on each evaluation index and the corresponding combination weight;

[0048] Update the global optimal position and historical optimal position of the particle based on the fitness value of each particle;

[0049] Eliminate the particle with the lowest fitness, and update the particle speed and position based on the fitness value;

[0050] Update the global optimal particle and the individual optimal particle;

[0051] Repeat the above steps until the maximum number of iterations is reached or the convergence condition is met, the optimization ends, and the current combined weight configuration of each particle is output as the combined weight of the corresponding evaluation index.

[0052] As a preferred implementation, in the multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, the step of setting constraints and constructing a multi-objective optimization model based on the optimal economic benefit and low-carbon benefit is:

[0053] Construct a multi-objective optimization method for project construction that considers the full life cycle evaluation of carbon emissions, including the economic investment benefit score and low-carbon benefit score of a single project, which can derive the total economic investment benefit score and low-carbon benefit score of all selected power grid infrastructure projects;

[0054] And it is constructed based on the grid investment scale constraint set. The specific formula is as follows:

[0055]

[0056] Among them, M o is the economic benefit score of item o, N o is the low-carbon benefit score of item o; maxQM is the highest sum of the economic benefit scores of all projects; maxQN is the highest sum of the low-carbon benefit scores of all projects;

[0057]

[0058] Where: C rn The construction investment for the first investment project of the power grid; C max is the maximum investment amount of the power grid; where: a rn =0 or 1 represents whether the item is selected; SN is the number of evaluation samples.

[0059] As a preferred implementation, the multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, the microhabitat genetic algorithm is used to solve the multi-objective optimization model to obtain the project construction plan with the best comprehensive benefits, and the steps for realizing the project optimization sorting are specifically as follows:

[0060] Initialization: Randomly generate the initial population, each individual contains the values ​​of multiple objective functions, which represent different optimization goals of the multi-objective optimization problem;

[0061] Evaluation: Use the evaluation function or objective function of the multi-objective optimization problem to calculate the fitness of each individual;

[0062] Microhabitat division: Divide the population into multiple microhabitats based on individual characteristics, including the degree of proximity of solutions and the value of the objective function;

[0063] Selection, crossover and mutation: Perform competitive selection operations in each microhabitat to select the best individuals in each microhabitat; perform crossover and mutation operations on the selected best individuals to generate a new generation of individuals and increase population diversity;

[0064] Update the population: add the newly generated individuals to the population, replacing some individuals in the old population;

[0065] Check termination conditions: Check whether the results meet the iteration termination conditions, including reaching the preset number of iterations and the quality of the solution no longer improving;

[0066] Result output: Select representative solutions from the non-dominated solution set in the evolution process as Pareto frontier solution output and use it as the preferred ranking of projects.

[0067] On the other hand, the present invention also provides a multi-objective optimization system for project construction considering the full life cycle evaluation of carbon emissions, comprising:

[0068] The indicator system construction module analyzes the system composition of the power grid infrastructure, combines the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content, and constructs the low-carbon benefit evaluation indicator system of the power grid infrastructure and the economic benefit evaluation indicator system of the power grid infrastructure;

[0069] The weight calculation module calculates the subjective weight and objective weight of each evaluation index based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure using the entropy weight method and the laboratory method;

[0070] The weight optimization module is used to construct a combined weight optimization model that considers subjective weights and objective weights, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weights of each evaluation index;

[0071] The optimization model building module is used to set constraints and build a multi-objective optimization model based on the optimal economic benefits and low-carbon benefits;

[0072] The decision-making module uses the microhabitat genetic algorithm to solve the multi-objective optimization model, obtain the project construction plan with the best comprehensive benefits, and realize the optimal ranking of projects.

[0073] As a preferred implementation, the decision module uses a niche genetic algorithm to solve a multi-objective optimization model to obtain a project construction plan with the best comprehensive benefits. The specific steps for achieving project optimization are:

[0074] Initialization: Randomly generate the initial population, each individual contains the values ​​of multiple objective functions, which represent different optimization goals of the multi-objective optimization problem;

[0075] Evaluation: Use the evaluation function or objective function of the multi-objective optimization problem to calculate the fitness of each individual;

[0076] Microhabitat division: Divide the population into multiple microhabitats based on individual characteristics, including the degree of proximity of solutions and the value of the objective function;

[0077] Selection, crossover and mutation: Perform competitive selection operations in each microhabitat to select the best individuals in each microhabitat; perform crossover and mutation operations on the selected best individuals to generate a new generation of individuals and increase population diversity;

[0078] Update the population: add the newly generated individuals to the population, replacing some individuals in the old population;

[0079] Check termination conditions: Check whether the results meet the iteration termination conditions, including reaching the preset number of iterations and the quality of the solution no longer improving;

[0080] Result output: Select representative solutions from the non-dominated solution set in the evolution process as Pareto frontier solution output and use it as the preferred ranking of projects.

[0081] On the other hand, the present invention also provides an electronic device having a computer program stored thereon, which, when executed by a processor, implements a multi-objective optimization method for project construction that considers the full life cycle evaluation of carbon emissions as described in any embodiment of the present invention.

[0082] On the other hand, the present invention also provides a computer-readable medium for storing one or more programs. When the one or more programs are executed by the one or more processors, the one or more processors implement a multi-objective optimization method for project construction that considers the full life cycle evaluation of carbon emissions as described in any embodiment of the present invention.

[0083] The present invention has the following beneficial effects:

[0084] 1. Full life cycle perspective: The constructed carbon emission evaluation index system comprehensively covers all stages of grid infrastructure construction, including planning, design, construction, operation and decommissioning, ensuring the systematicness and completeness of the evaluation.

[0085] 2. Scientific weight allocation: By combining the entropy weight method with the laboratory method, it not only takes into account the objective importance of the indicators, but also integrates the expert experience, realizes the scientific integration of subjective and objective weights, and improves the accuracy of the evaluation.

[0086] 3. Innovation of quantum-inspired optimization algorithm: The introduction of the QPSO algorithm uses the concept of quantum bits to enhance the global search capability and diversity of the particle swarm algorithm, effectively solves the local optimal problem in multi-objective optimization, and improves the efficiency and quality of the solution.

[0087] 4. Maximization of comprehensive benefits: The constructed multi-objective optimization model not only considers economic benefits, but also low-carbon benefits. It is solved through a microhabitat genetic algorithm to ensure the comprehensive optimality of the project optimization scheme. At the same time, it takes into account actual constraints such as investment scale, thereby enhancing the practicality and feasibility of decision-making.

[0088] 5. Project optimization ranking and decision support: The proposed framework can not only obtain the optimal construction plan, but also provide decision makers with intuitive comparative analysis through ranking, which helps the scientific decision-making and sustainable development of green power grid construction projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0089] Figure 1 is a schematic diagram of a method flow chart of Embodiment 1 of the present invention; DETAILED DESCRIPTION

[0090] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0091] It should be understood that the step numbers used in this document are only for convenience of description and are not intended to limit the order in which the steps are executed.

[0092] It should be understood that the terms used in the present specification are only for the purpose of describing specific embodiments and are not intended to limit the present invention. As used in the present specification and the appended claims, unless the context clearly indicates otherwise, the singular forms "a", "an" and "the" are intended to include plural forms.

[0093] The terms “include” and “comprising” indicate the presence of described features, integers, steps, operations, elements and / or components, but do not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or combinations thereof.

[0094] The term "and / or" means and includes any and all possible combinations of one or more of the associated listed items.

[0095] Embodiment 1:

[0096] In order to make the purpose, technical solutions and advantages of the present invention more clear, the following will be combined with the specific embodiments of the present application and refer to the attached Figure 1 , clearly and completely describe the technical solution of the present invention.

[0097] In order to solve the problems of the prior art, the present invention proposes a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, comprising the following steps:

[0098] Step S101: Analyze the system composition of the power grid infrastructure, and build a low-carbon benefit evaluation index system for the power grid infrastructure and an economic benefit evaluation index system for the power grid infrastructure in combination with the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content.

[0099] The following is the construction of the low-carbon benefit evaluation index system for the entire life cycle of the project:

[0100] As an important part of the national energy system, the construction and operation of power grid infrastructure projects are not only related to the safe and stable supply of energy, but also a key area of ​​national carbon emission management. From project planning to final dismantling and recycling, each stage is accompanied by the generation of carbon footprints, and the sources and intensity of carbon emissions at different stages vary.

[0101] Planning stage: Although direct carbon emissions are relatively low at this stage, decisions such as project scale, site selection, and energy supply methods have a huge impact on carbon emissions throughout the entire life cycle. Reasonable planning can avoid unnecessary transformation and duplication of construction in the future and reduce long-term carbon emissions.

[0102] Design stage: Selecting low-carbon materials, optimizing design solutions, and considering energy efficiency and the integration of renewable energy are crucial to reducing carbon emissions during the construction and operation stages. Decisions made during the design stage have a decisive impact on overall carbon emissions.

[0103] Construction phase: Carbon emissions in this phase mainly come from material production and transportation, construction machinery operations, and on-site energy consumption. Optimizing the construction process, using low-carbon building materials, and improving construction efficiency can effectively reduce carbon emissions in this phase.

[0104] Operational stage: Energy consumption during grid operation is a continuous source of carbon emissions, including losses in substations and transmission lines, and maintenance activities. Improving energy efficiency, adopting smart grid technology, and optimizing dispatching strategies can significantly reduce carbon emissions during the operational period.

[0105] Demolition and recycling stage: The dismantling and material recycling of power grid facilities after retirement will also generate carbon emissions, but through efficient recycling strategies, this part of carbon emissions can be minimized and resource circulation can be achieved.

[0106] Based on the above analysis, a comprehensive evaluation index system was constructed, covering key indicators such as the forward-looking nature of planning, the low-carbon nature of design, the greenness of construction, the energy efficiency ratio of operation, and the circular economy of dismantling and recycling, aiming to guide and measure the low-carbonization process of power grid infrastructure construction projects. The indicators of each stage are both independent and interrelated, and together constitute a full life cycle low-carbon benefit evaluation index system.

[0107]

[0108] The economic benefit evaluation index system of power grid infrastructure refers to the existing evaluation index system of power grid, including the following first-level indicators: investment benefit, operation benefit, and social benefit. Investment benefit includes the following second-level indicators: investment payback period, net present value of capital, internal rate of return, and investment rate of return; operation benefit includes the following second-level indicators: operating cost, operation reliability index, load service capacity, and power supply quality; social benefit includes the following second-level indicators: employment creation, local tax contribution, electricity price preferential policy, and social stability contribution.

[0109] Step S102: Based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure, the subjective weight and objective weight of each evaluation index are calculated using the entropy weight method and the laboratory method.

[0110] The DEMATEL decision-making test and evaluation test method calculates the subjective weight of each evaluation indicator; it includes the following steps:

[0111] Determine the mutual influence between each evaluation indicator through questionnaire / expert scoring, and build an initial influence matrix based on the mutual influence between each evaluation indicator;

[0112] Perform standard normalization on the initial influence matrix O to obtain the normalized matrix WN, the formula is as follows:

[0113]

[0114] Where r is the normalized number of indicators, O bh is the element in the bth row and hth column;

[0115] Calculate the comprehensive impact matrix T, the formula is as follows:

[0116]

[0117] Where I is the unit matrix, WN p is the pth normalized matrix;

[0118] The comprehensive influence matrix is ​​used to calculate the various parameter values ​​of each indicator, including the influence value D, the influence value C, the centrality value D+C, and the cause value DC. The calculation formulas for the influence value D and the influence value C are as follows:

[0119]

[0120]

[0121] In the formula, e and f represent two interacting evaluation indicators;

[0122] Normalize the centrality value D+C or the cause value DC so that the sum of the centrality value D+C or the cause value DC of each evaluation index is 1, and use the normalized centrality value D+C or the cause value DC as the subjective weight vector of each evaluation index;

[0123] The entropy weight method calculates the objective weight of each evaluation index; it includes the following steps:

[0124] The evaluation model is: suppose that h evaluation indicators are used to decide and evaluate f candidate solutions. ul : The estimated value of the evaluation index u of the candidate solution l. ul * : The ideal value of the evaluation index u. ul * The value varies depending on the characteristics of the evaluation index. For profitability indicators, x ul * The larger the better; for loss indicators (inverse indicators), x ul * The smaller the better (it can also be converted into a positive indicator first).

[0125] Define x ul For x u * Proximity D ul :

[0126]

[0127] D ul Normalization:

[0128]

[0129] Overall entropy: The entropy E of f candidate solutions evaluated by h evaluation indicators is:

[0130]

[0131] Overall entropy when the metric is independent of the solution:

[0132] If the relative importance of the evaluation index is independent of the candidate options, the entropy is calculated by the following formula:

[0133]

[0134] Where:

[0135] In this way, the uncertainty of the relative importance of the evaluation index u to the decision evaluation of the alternatives can be determined by the following conditional entropy.

[0136] Conditional entropy of evaluation index u

[0137]

[0138] From the extreme value of entropy, we know that That is, du1≈du2≈…dul. The closer they are to being equal, the greater the conditional entropy, and the greater the uncertainty of the evaluation index in the evaluation decision of the alternatives.

[0139] By normalizing the above formula, we can obtain the entropy value that represents the importance of the evaluation decision of the evaluation index u.

[0140]

[0141] Step S103: construct a combined weight optimization model that takes into account subjective weights and objective weights, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weights of various evaluation indicators.

[0142] The PSO algorithm is a random search algorithm based on group collaboration. In each iterative search process, the random particles in the group use tracking two "extreme values" to find the optimal solution. Suppose the size of a certain group is N, and in the D-dimensional search space, the position of particle i in the tth generation is Speed The individual's best historical position is The global optimal position of the tth generation The optimal solution formula is:

[0143]

[0144] Where: c1, c2 are learning factors; r1, r2 are random numbers uniformly distributed between [0, 1]; k is the current number of iterations, I tera is the maximum number of iterations, ω is the inertia weight, and as the iterations are calculated, the maximum ω max Linearly decreases to ω min .

[0145] At present, the particle swarm algorithm has been applied in many fields, but when dealing with complex models, the algorithm is easy to fall into the local optimal problem, that is, the "premature problem". In view of the obvious shortcomings of the particle swarm algorithm in dealing with complex problems, in order to avoid the algorithm from falling into the local optimal during the iteration process, the quadratic interpolation factor is introduced to improve it, and the QPSO algorithm is proposed. This improvement improves the optimization speed of the algorithm, improves the algorithm's computational efficiency, and enhances the global optimization ability, thereby improving the practicality of the algorithm in the optimization application of the transmission network reserve project library. The essence of the QPSO algorithm is to introduce the quadratic interpolation operator into the particle swarm algorithm, so that it improves the convergence speed and computational efficiency of the algorithm, and then finds the global optimal position of the model, that is:

[0146]

[0147] The point generated by the above formula is the point in D-dimensional space through p l 、p j and p g The quadratic surface minimum point of the three points, so the global optimal position generated by iteration is always selected in the above formula. The global optimal position of the tth generation is p g =(p g1 ,p g2 ,...,p gD ), randomly select two positions p from the individual's historical optimal position l 、p j , and l,j≠g. Among them, e is a very small positive number that makes d not zero.

[0148] Let Q i =(q i1 ,q i2 ,...,q iD ), i=1,2,...,N, then:

[0149]

[0150] The QPSO algorithm process is as follows.

[0151] 1. For population size n, learning factors c1, c2, and maximum number of iterations I tera , initial speed v, index number D, inertia weight and other parameters are set;

[0152] 2. Generate the initial population and randomly generate the initial position and initial velocity

[0153] 3. Calculate the fitness of the initial particles and find the global optimal particle g best and the individual optimal particle P best ;

[0154] 4. Update the particle's historical optimal position P i and the global optimal position P g ;

[0155] 5. Eliminate the particle with the lowest fitness and update the particle's velocity v and particle's position x;

[0156] 6. Update the global optimal particle and the individual optimal particle;

[0157] 7. Repeat steps 3 to 6. If the maximum number of iterations I is reached tera And the convergence conditions are met, the algorithm optimization ends, and the combined weighting weights are output.

[0158] Step: S104: Set constraints and build a multi-objective optimization model based on the best economic benefits and low-carbon benefits; where:

[0159] Construct a multi-objective optimization model for project construction that takes into account the full life cycle evaluation of carbon emissions, including the economic investment benefit score and low-carbon benefit score of a single project. This can derive the total economic investment benefit score and low-carbon benefit score of all selected power grid infrastructure projects.

[0160] And it is constructed based on the grid investment scale constraint set. The specific formula is as follows:

[0161]

[0162] Among them, M o is the economic benefit score of item o, N o is the low-carbon benefit score of item o; maxQM is the highest sum of the economic benefit scores of all projects; maxQN is the highest sum of the low-carbon benefit scores of all projects;

[0163]

[0164] Where: C rn The construction investment for the first investment project of the power grid; C max is the maximum investment amount of the power grid; where: a rn =0 or 1 represents whether the item is selected; SN is the number of evaluation samples.

[0165] Step S105: Solve the model based on the microhabitat genetic algorithm to obtain a project construction plan that takes into account the best comprehensive benefits and achieve project optimization sorting.

[0166] Niche Genetic Algorithm (NGA) is an improved algorithm developed on the basis of traditional genetic algorithm, which is particularly suitable for solving multi-objective optimization problems. It introduces the concept of "niche" to imitate the mechanism of biological populations in nature competing for survival in different ecological environments to maintain the diversity of the population and avoid premature convergence, so as to more effectively search for the Pareto frontier solution of multi-objective optimization problems.

[0167] The specific solution process is as follows:

[0168] (1) Input system data, parameter values ​​and variable values. The input microhabitat genetic algorithm parameters include the size of the individual population, the number of genes contained in the individual, the crossover rate, the mutation rate and the maximum genetic generation.

[0169] (2) Use binary to encode chromosomes.

[0170] (3) Randomly generate initial population household seals.

[0171] (4) Verify constraints.

[0172] (5) Calculate the fitness function value of each chromosome in the population. In order to minimize the total risk of the objective function described and adapt to the characteristics of the genetic algorithm to seek the maximum value, its fitness function is:

[0173]

[0174] F=R+μW

[0175] In the formula,

[0176] GF—fitness function;

[0177] F—corrected value of the objective function;

[0178] F max —For a given larger constant, the maximum value of the objective function F obtained so far can be selected or obtained based on experimental data.

[0179] W—Network overload capacity (MW).

[0180] (6) Arrange the chromosomes in descending order according to their fitness function values, and remember the first LK chromosomes (M <LK)。

[0181] (7) Perform proportional selection operation on the population P(tv) to obtain P′(tv). The fitness function value proportional method is used as the selection strategy to implement the selection operation.

[0182] (8) Perform a single-point crossover operation on P′(tv) to obtain P″(tv). The crossover operation can change the topologies of two networks, thereby obtaining new structures. The basic steps to achieve crossover are as follows:

[0183] 1) Select parental chromosomes: The process is as follows: Repeat the following process from ai = 1 to LK: Generate a random number r from [0, 1] ai , if r ai ≤P C , then select chromosome ai as a parent for crossover. Here, P C is the crossover rate, usually between 0.6 and 0.9, which reflects the idea of information exchange in nature.

[0184] 2) Select a crossover point: Use one-point crossover. The specific operation is to randomly select a crossover point in a chromosome, and two chromosomes exchange parts before or after this point to generate new chromosomes.

[0185] (9) Perform a two-point mutation operation on P″(tv) to obtain P″′(tv).

[0186] (10) Calculate the fitness of P″′(tv).

[0187] (11) Perform the niche elimination algorithm. Combine the LK chromosomes obtained in step (9) and the M chromosomes memorized in step (6) to obtain a new population containing (LK + M) chromosomes. For these (LK + M) chromosomes, calculate the Hamming distance between two chromosomes; X ai and X aj according to the following calculation formula:

[0188]

[0189] When ||X ai - X aj || < DL (L is the specified distance), compare the fitness values of chromosomes X ai and X aj , and impose a penalty function on the chromosome with the lower fitness: F min(X ai , X aj ) = Penalty.

[0190] (12) Arrange the new fitness values of the (N + M) chromosomes in descending order and memorize the first M chromosomes.

[0191] (13) Implement the elitist strategy.

[0192] (14) Determine whether the termination condition is met. If the termination condition is met, go to step (15), otherwise update the evolutionary generation counter Gen = Gen + 1, take the first N chromosomes in the arrangement of step (11) as the new next generation population and then go to step (7).

[0193] (15) Decode and output the optimization calculation results. Output several chromosomes with the highest or second highest fitness function values, and decode and restore them into the optimal plan for the power grid project.

[0194] Embodiment 2:

[0195] This embodiment provides a multi-objective optimization system for project construction considering the full life cycle evaluation of carbon emissions, including:

[0196] The indicator system construction module analyzes the system composition of the power grid infrastructure, combines the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content, and constructs a low-carbon benefit evaluation indicator system for the power grid infrastructure and an economic benefit evaluation indicator system for the power grid infrastructure; this module is used to implement the function of step S101 in Example 1, which will not be repeated here.

[0197] The weight calculation module, based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure, uses the entropy weight method and the laboratory method to calculate the subjective weight and objective weight of each evaluation index respectively; this module is used to implement the function of step S102 in Example 1, which will not be repeated here.

[0198] The weight optimization module is used to construct a combined weight optimization model that takes into account subjective weights and objective weights, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weights of various evaluation indicators; this module is used to implement the function of step S103 in Example 1, which will not be repeated here.

[0199] The optimization model construction module is used to set constraints and construct a multi-objective optimization model based on the best economic benefits and low-carbon benefits; this module is used to implement the function of step S104 in Example 1, which will not be repeated here.

[0200] The decision-making module uses a niche genetic algorithm to solve a multi-objective optimization model, obtains a project construction plan with the best comprehensive benefits, and realizes project optimization sorting; this module is used to realize the function of step S105 in Example 1, which will not be repeated here.

[0201] Embodiment three:

[0202] This embodiment provides an electronic device having a computer program stored thereon. When the computer program is executed by a processor, the method for optimizing project construction with multiple objectives considering the full life cycle evaluation of carbon emissions as described in any embodiment of the present invention is implemented.

[0203] Embodiment 4:

[0204] This embodiment provides a computer-readable medium for storing one or more programs. When the one or more programs are executed by the one or more processors, the one or more processors implement a multi-objective optimization method for project construction that considers the full life cycle evaluation of carbon emissions as described in any embodiment of the present invention.

[0205] In the embodiments of the present application, "at least one" refers to one or more, and "more than one" refers to two or more. "And / or" describes the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B can represent the existence of A alone, the existence of A and B at the same time, and the existence of B alone. Among them, A and B can be singular or plural. The character " / " generally indicates that the previous and next associated objects are in an "or" relationship. "At least one of the following" and similar expressions refer to any combination of these items, including any combination of single or plural items. For example, at least one of a, b and c can be represented by: a, b, c, a and b, a and c, b and c, or a and b and c, where a, b, c can be single or multiple.

[0206] Those of ordinary skill in the art will appreciate that the various units and algorithm steps described in the embodiments disclosed herein can be implemented in a combination of electronic hardware, computer software, and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0207] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0208] In several embodiments provided in the present application, if any function is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (Read-Only Memory; hereinafter referred to as: ROM), random access memory (Random Access Memory; hereinafter referred to as: RAM), disk or optical disk, and other media that can store program codes.

[0209] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions, characterized in that: The following steps are involved: Analyze the system composition of power grid infrastructure, and build a low-carbon benefit evaluation index system for power grid infrastructure and an economic benefit evaluation index system for power grid infrastructure in combination with the characteristics of power grid infrastructure construction projects and low-carbon evaluation content; Based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure, the subjective weight and objective weight of each evaluation index are calculated using the entropy weight method and laboratory method. Construct a combined weight optimization model that considers subjective weight and objective weight, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weight of each evaluation index; Set constraints and build a multi-objective optimization model based on the best economic and low-carbon benefits; The microhabitat genetic algorithm is used to solve the multi-objective optimization model, obtain the project construction plan with the best comprehensive benefits, and realize the optimal ranking of projects.

2. According to claim 1, a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions is characterized in that: In the step of analyzing the system composition of the power grid infrastructure, combining the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content, and constructing the low-carbon benefit evaluation index system of the power grid infrastructure and the economic benefit evaluation index system of the power grid infrastructure: The whole life cycle of power grid infrastructure construction projects is divided into different stages, including planning stage, design stage, construction stage, operation stage and dismantling and recycling stage; According to the characteristics of each stage, a number of corresponding carbon emission evaluation indicators are set.

3. According to claim 1, a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions is characterized in that: The steps of using the entropy weight method and the laboratory method to calculate the subjective weight and objective weight of each evaluation index are specifically as follows: The subjective weight of each evaluation index is calculated using the DEMATEL decision test and evaluation test method; the following steps are included: Determine the mutual influence between each evaluation indicator through questionnaire / expert scoring, and build an initial influence matrix based on the mutual influence between each evaluation indicator; Perform standard normalization on the initial influence matrix O to obtain the normalized matrix WN, the formula is as follows: Where r is the normalized number of indicators, O bh is the element in the bth row and hth column; Calculate the comprehensive impact matrix T, the formula is as follows: Where I is the unit matrix, WN p is the pth normalized matrix; The comprehensive influence matrix is ​​used to calculate the various parameter values ​​of each indicator, including the influence value D, the influence value C, the centrality value D+C, and the cause value DC. The calculation formulas for the influence value D and the influence value C are as follows: In the formula, e and f represent two interacting evaluation indicators; Normalize the centrality value D+C or the cause value DC so that the sum of the centrality value D+C or the cause value DC of each evaluation index is 1, and use the normalized centrality value D+C or the cause value DC as the subjective weight vector of each evaluation index; The entropy weight method is used to calculate the objective weight of each evaluation index, including the following steps: Normalize the data of each evaluation indicator to ensure that the data values ​​of each evaluation indicator are at the same level; For each evaluation index, calculate the proportion of each sample data value to the total data value of the evaluation index to obtain the probability distribution of each evaluation index; The information entropy of each evaluation indicator is calculated based on its probability distribution, and the information utility value is calculated through the information entropy of each evaluation indicator. Each information utility value is normalized so that the sum of the normalized information utility values ​​corresponding to each evaluation indicator is 1, and the normalized information utility value is used as the objective weight of the corresponding evaluation indicator.

4. According to claim 1, a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions is characterized in that: The steps of solving the combined weight optimization model based on the QPSO quantum particle swarm algorithm are specifically as follows: Set the initial parameters, including population size, learning factor, maximum number of iterations, initial speed, number of indicators, and inertia weight; An initial population is generated, wherein each particle in the initial population represents a combined weight configuration of an evaluation index, wherein the combined weight configuration is generated by adjusting the subjective weight and the objective weight of the corresponding evaluation index, and an initial position and an initial velocity of each particle are randomly generated; The fitness of each particle in the initial population is calculated to find the global optimal particle and the individual optimal particle, where the fitness function is configured as the error function between the actual carbon emission evaluation value and the carbon emission prediction value calculated based on each evaluation index and the corresponding combination weight; Update the global optimal position and historical optimal position of the particle based on the fitness value of each particle; Eliminate the particle with the lowest fitness, and update the particle speed and position based on the fitness value; Update the global optimal particle and the individual optimal particle; Repeat the above steps until the maximum number of iterations is reached or the convergence condition is met, the optimization ends, and the current combined weight configuration of each particle is output as the combined weight of the corresponding evaluation index.

5. According to claim 1, a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions is characterized in that: In the step of setting constraints and constructing a multi-objective optimization model based on optimal economic benefits and low-carbon benefits: Construct a multi-objective optimization model for project construction that takes into account the full life cycle evaluation of carbon emissions, including the economic investment benefit score and low-carbon benefit score of a single project. This can derive the total economic investment benefit score and low-carbon benefit score of all selected power grid infrastructure projects. And it is constructed based on the grid investment scale constraint set. The specific formula is as follows: Among them, M o is the economic benefit score of item o, N o The low-carbon benefit score for item o; maxQM is the highest sum of the economic benefit scores of each project, and maxQN is the highest sum of the low-carbon benefit scores of each project; Where: C rn The construction investment for the first investment project of the power grid; C max is the maximum investment amount of the power grid; where: a rn =0 or 1 represents whether the item is selected; SN is the number of evaluation samples.

6. According to claim 1, a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions is characterized in that: The steps of solving the multi-objective optimization model by using the microhabitat genetic algorithm to obtain the project construction plan with the best comprehensive benefits and realizing the project optimization sorting are specifically as follows: Initialization: Randomly generate the initial population, each individual contains the values ​​of multiple objective functions, which represent different optimization goals of the multi-objective optimization problem; Evaluation: Use the evaluation function or objective function of the multi-objective optimization problem to calculate the fitness of each individual; Microhabitat division: Divide the population into multiple microhabitats based on individual characteristics, including the degree of proximity of solutions and the value of the objective function; Selection, crossover and mutation: Perform competitive selection operations in each microhabitat to select the best individuals in each microhabitat; perform crossover and mutation operations on the selected best individuals to generate a new generation of individuals and increase population diversity; Update the population: add the newly generated individuals to the population, replacing some individuals in the old population; Check termination conditions: Check whether the results meet the iteration termination conditions, including reaching the preset number of iterations and the quality of the solution no longer improving; Result output: Select representative solutions from the non-dominated solution set in the evolution process as Pareto frontier solution output and use it as the preferred ranking of projects.

7. A multi-objective optimization system for project construction considering the full life cycle evaluation of carbon emissions, characterized in that: include: The indicator system construction module analyzes the system composition of the power grid infrastructure, combines the characteristics of the power grid infrastructure construction project and the low-carbon evaluation content, and constructs the low-carbon benefit evaluation indicator system of the power grid infrastructure and the economic benefit evaluation indicator system of the power grid infrastructure; The weight calculation module calculates the subjective weight and objective weight of each evaluation index based on the low-carbon benefit evaluation index system of power grid infrastructure and the economic benefit evaluation index system of power grid infrastructure using the entropy weight method and the laboratory method; The weight optimization module is used to construct a combined weight optimization model that considers subjective weights and objective weights, solve the combined weight optimization model based on the QPSO quantum particle swarm algorithm, and calculate the combined weights of various evaluation indicators; The optimization model building module is used to set constraints and build a multi-objective optimization model based on the optimal economic benefits and low-carbon benefits; The decision-making module uses the microhabitat genetic algorithm to solve the multi-objective optimization model, obtain the project construction plan with the best comprehensive benefits, and realize the optimal ranking of projects.

8. A multi-objective optimization system for project construction considering the full life cycle evaluation of carbon emissions according to claim 7, characterized in that: The decision module uses a niche genetic algorithm to solve a multi-objective optimization model to obtain a project construction plan with the best comprehensive benefits. The specific steps for achieving project optimization are: Initialization: Randomly generate the initial population, each individual contains the values ​​of multiple objective functions, which represent different optimization goals of the multi-objective optimization problem; Evaluation: Use the evaluation function or objective function of the multi-objective optimization problem to calculate the fitness of each individual; Microhabitat division: Divide the population into multiple microhabitats based on individual characteristics, including the degree of proximity of solutions and the value of the objective function; Selection, crossover and mutation: Perform competitive selection operations in each microhabitat to select the best individuals in each microhabitat; perform crossover and mutation operations on the selected best individuals to generate a new generation of individuals and increase population diversity; Update the population: add the newly generated individuals to the population, replacing some individuals in the old population; Check termination conditions: Check whether the results meet the iteration termination conditions, including reaching the preset number of iterations and the quality of the solution no longer improving; Result output: Select representative solutions from the non-dominated solution set in the evolution process as Pareto frontier solution output and use it as the preferred ranking of projects.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, it implements a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions as described in any one of claims 1 to 6.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, it implements a multi-objective optimization method for project construction considering the full life cycle evaluation of carbon emissions as described in any one of claims 1 to 6.

Citation Information

Patent Citations

  • Power system environmental economy scheduling strategy based on improved gravitational search algorithm

    CN107958424A

  • Automatic power generation control scheduling method based on hybrid algorithm

    CN113991751A

  • Multi-target photovoltaic single-phase grid-connected capacity planning method considering three-phase imbalance

    CN114123294A

  • Power distribution network bearing capacity assessment method for distributed energy equipment

    CN117634923A

  • Optimization method for comprehensive benefit evaluation scheme for water-wind-photovoltaic energy storage multi-energy complementary system

    WO2024082836A1

Cited By

  • Hybrid flow shop scheduling optimization method and system based on equipment green degree sorting

    CN119417184A