Unit load scheduling method and system considering power grid energy interaction

By acquiring the energy storage capacity and historical transaction volume of energy storage devices, and combining the matching coefficients of electricity spot trading entities and weather data, an economic optimization model was constructed, which solved the problem of unstable energy interaction in the power grid and achieved stability and economic optimization of unit load dispatch.

CN118783433APending Publication Date: 2024-10-15HANGZHOU YINGJI POWER TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411006752.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the electricity spot market, the market-based floating electricity price may be lower than the generation cost of the generating units, leading to instability in grid energy interaction and affecting the stability and economy of unit operation.

Method used

By acquiring the energy storage capacity and historical electricity volume of the unit's energy storage device, the matching coefficient of the electricity spot trading entity is determined. Combined with weather data to predict electricity volume and price, an economic optimization model is constructed to generate unit load dispatching strategies in order to achieve a balance between electricity and heat supply and demand.

Benefits of technology

It improved the operational stability and economy of the generating units under different electricity price environments, optimized the electricity utilization period, and improved the efficiency of power grid energy interaction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118783433A_ABST
    Figure CN118783433A_ABST
Patent Text Reader

Abstract

The invention provides a unit load scheduling method and system considering power grid energy interaction, and belongs to the technical field of data processing, and the method specifically comprises the steps: determining the power transaction prediction electric quantity and prediction electricity price of a matched transaction main body in different time periods through the weather data in a day-ahead stage, determining an electric energy utilization time period and electric energy utilization prediction electric quantity of the electric energy utilization time period on the basis of the electric power transaction prediction electric quantity and the prediction electricity price of the matched transaction main body in different time periods, and determining electric energy utilization prediction electric quantity of the electric energy utilization time period on the basis of the electric energy utilization prediction electric quantity of different electric energy utilization time periods and electric energy and heat energy supply and demand balance as a constraint condition; and load scheduling strategies of the unit in different time periods are generated by taking economic optimization as a target, so that the economical efficiency and the reliability of unit operation are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of load scheduling, and in particular relates to a method and system for unit load scheduling considering power grid energy interaction. Background Art

[0002] With the rapid development of the electricity spot market, electricity prices have gradually shifted from fixed prices to market-based floating prices. In some extreme cases, market-based floating prices may even be lower than the power generation cost of the unit. Therefore, under the above premise, how to achieve electric energy interaction with the power grid and improve the operating stability and economy of the unit has become a technical problem that needs to be solved urgently.

[0003] In response to the above technical problems, the present invention provides a method and system for unit load scheduling that takes power grid energy interaction into consideration. Summary of the Invention

[0004] A unit load scheduling method considering grid energy interaction specifically includes: S1: Obtain the energy storage capacity of the energy storage device of the unit, and determine the matching coefficient of the power spot trading entity of the unit based on the deviation between the historical transaction power and the energy storage capacity and the transaction price of the historical transaction power. When the matching coefficient of the power spot trading entity meets the requirements, proceed to the next step; S2 takes the electricity spot trading entities that meet the matching coefficient requirements as potential trading entities, uses the energy storage capacity of the energy storage device as a constraint, obtains the matching status of the historical trading electricity of the potential trading entities in different historical trading periods, and determines the matching trading entity of the unit based on the matching coefficient of the potential trading entity; S3 uses weather data to determine the power transaction forecast and electricity price of the matching transaction subjects in different time periods during the day-ahead phase, and determines the power utilization period and the power utilization forecast during the power utilization period based on the power transaction forecast and electricity price of the matching transaction subjects in different time periods; S4 generates load dispatching strategies for the units in different periods of time based on the predicted power consumption in different periods of power utilization, with the balance of power and heat supply and demand as a constraint, and with economic optimization as a goal.

[0005] A further technical solution is that the historical transaction electricity volume is determined based on the historical transaction data of the electricity spot trading entity.

[0006] A further technical solution is that the method for determining the matching coefficient of the power spot trading entity of the unit is: The average value of the historical transaction volume of the electricity spot trading subject at different time periods on different dates is used as the reference transaction volume; Determining the transaction matching coefficients on different dates based on the deviations between the reference transaction electricity and the energy storage capacity on different dates and the average values ​​of the transaction electricity prices on different dates; The matching coefficient between the power spot trading entity and the unit is determined by the transaction matching coefficients on different dates.

[0007] A further technical solution is that the matching coefficient between the electricity spot trading entity and the unit ranges from 0 to 1, wherein the larger the matching coefficient between the electricity spot trading entity and the unit, the higher the degree of matching between the electricity spot trading entity and the unit.

[0008] A further technical solution is that when the matching coefficient of the electricity spot trading entity does not meet the requirements, the electricity spot trading entity will not be used as the trading entity of the unit.

[0009] A further technical solution is that the method for determining the load dispatching strategy of the unit in different time periods is: Based on the predicted amount of electricity utilization in different electricity utilization periods, and with the balance of electricity and heat supply and demand as the constraint condition, Construct economic functions based on electricity price and electricity output, heat price and heat output; Based on the predicted amount of electricity utilization in different electricity utilization periods, with the balance of supply and demand of electricity and heat energy as a constraint condition, and with the maximization of the economic function as the goal, an optimization model is constructed to determine the load output of the unit in different periods; The load dispatching strategies of the units in different time periods are generated based on the load outputs of the units in different time periods.

[0010] On the other hand, an embodiment of the present application provides a unit load scheduling system that considers grid energy interaction, adopting the above-mentioned unit load scheduling method that considers grid energy interaction, characterized by specifically including: Matching coefficient evaluation module, transaction subject screening module, power utilization evaluation module, and scheduling strategy output module; The matching coefficient evaluation module is responsible for obtaining the energy storage capacity of the energy storage device of the unit, and determining the matching coefficient of the power spot trading subject of the unit based on the deviation between the historical transaction power and the energy storage capacity and the transaction price of the historical transaction power; The trading subject screening module is responsible for selecting electricity spot trading subjects whose matching coefficients meet the requirements as potential trading subjects, obtaining the matching status of the historical trading electricity of potential trading subjects in different historical trading periods based on the energy storage capacity of the energy storage device as a constraint, and determining the matching trading subject of the unit based on the matching coefficients of the potential trading subjects; The power utilization evaluation module is responsible for determining the power transaction forecast and power price of the matching transaction subjects in different time periods by using weather data in the day-ahead stage, and determining the power utilization period and the power utilization forecast in the power utilization period based on the power transaction forecast and power price of the matching transaction subjects in different time periods; The scheduling strategy output module is responsible for generating the load scheduling strategy of the unit in different time periods based on the predicted power utilization in different power utilization periods, with the balance of power and heat supply and demand as the constraint condition, and with economic optimization as the goal.

[0011] On the other hand, an embodiment of the present application provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed in a computer, the computer is caused to execute the above-mentioned unit load scheduling method considering grid energy interaction. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the specific embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0013] Figure 1 This is a flow chart of a unit load scheduling method considering grid energy interaction according to Example 1.

[0014] Figure 2 A flow chart of a method for determining a matching coefficient of a power spot trading entity of a generating unit; Figure 3 This is a flow chart of a method for determining an electric energy utilization period. DETAILED DESCRIPTION

[0015] To make the objectives, technical solutions, and advantages of the embodiments of the present invention more clear, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of them. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0016] Example 1 To solve the above problems, according to one aspect of the present invention, Figure 1 As shown, a unit load scheduling method considering grid energy interaction is provided, which specifically includes: S1: Obtain the energy storage capacity of the energy storage device of the unit, and determine the matching coefficient of the power spot trading entity of the unit based on the deviation between the historical transaction power and the energy storage capacity and the transaction price of the historical transaction power. When the matching coefficient of the power spot trading entity meets the requirements, proceed to the next step; S2 takes the electricity spot trading entities that meet the matching coefficient requirements as potential trading entities, uses the energy storage capacity of the energy storage device as a constraint, obtains the matching status of the historical trading electricity of the potential trading entities in different historical trading periods, and determines the matching trading entity of the unit based on the matching coefficient of the potential trading entity; S3 uses weather data to determine the power transaction forecast and electricity price of the matching transaction subjects in different time periods during the day-ahead phase, and determines the power utilization period and the power utilization forecast during the power utilization period based on the power transaction forecast and electricity price of the matching transaction subjects in different time periods; S4 generates load dispatching strategies for the units in different periods of time based on the predicted power consumption in different periods of power utilization, with the balance of power and heat supply and demand as a constraint, and with economic optimization as a goal.

[0017] Furthermore, the historical transaction electricity volume is determined based on historical transaction data of the electricity spot trading entity.

[0018] Specifically, such as Figure 2 As shown, the method for determining the matching coefficient of the power spot trading entity of the unit is: The average value of the historical transaction volume of the electricity spot trading subject at different time periods on different dates is used as the reference transaction volume; Determining the transaction matching coefficients on different dates based on the deviations between the reference transaction electricity and the energy storage capacity on different dates and the average values ​​of the transaction electricity prices on different dates; The matching coefficient between the power spot trading entity and the unit is determined by the transaction matching coefficients on different dates.

[0019] It can be understood that the matching coefficient between the electricity spot trading entity and the unit ranges from 0 to 1, wherein the larger the matching coefficient between the electricity spot trading entity and the unit, the higher the degree of matching between the electricity spot trading entity and the unit.

[0020] Furthermore, when the matching coefficient of the electricity spot trading entity does not meet the requirements, the electricity spot trading entity will not be used as the trading entity of the unit.

[0021] It should also be noted that the method for determining the matching coefficient of the power spot trading entity of the unit is: The average value of the historical transaction volume of the electricity spot trading subject at different time periods on different dates is used as the reference transaction volume; Obtain the deviation between the reference transaction power and the energy storage capacity on different dates, and use the deviation to determine when the electricity spot market entity has a deviation date: When the number of the deviation dates does not meet the requirement, it is determined that the matching coefficient of the power spot trading entity does not meet the requirement; When the number of the deviation dates meets the requirement, the transaction deviation coefficient of the electricity spot trading subject is determined according to the deviation between the reference transaction power and the energy storage capacity on different deviation dates; when the transaction deviation coefficient of the electricity spot trading subject does not meet the requirement, it is determined that the matching coefficient of the electricity spot trading subject does not meet the requirement; When the transaction deviation coefficient of the electricity spot entity meets the requirements or the electricity spot entity does not have a deviation date: Obtaining the deviation between the reference transaction electricity volume and the energy storage capacity on different dates, and determining the transaction matching coefficients on different dates in combination with the average values ​​of the transaction electricity prices on different dates; when there are dates on which the transaction matching coefficients do not meet the requirements, the dates on which the transaction matching coefficients do not meet the requirements are used as matching deviation dates; and when the number of matching deviation dates does not meet the requirements, determining that the matching coefficient of the electricity spot trading entity does not meet the requirements; When the number of matching deviation dates meets the requirement, the matching coefficient deviation of the power spot trading subject is determined by using the number of matching deviation dates and the transaction matching coefficients of different matching deviation dates; when the matching coefficient deviation of the power spot trading subject does not meet the requirement, it is determined that the matching coefficient of the power spot trading subject does not meet the requirement; When the matching coefficient deviation of the power spot transaction subject meets the requirement, the matching coefficient between the power spot transaction subject and the unit is determined by the transaction matching coefficients on different dates.

[0022] Furthermore, when the matching coefficient between the electricity spot trading entity and the unit is greater than a preset matching coefficient threshold, the electricity spot trading entity is determined to be a potential trading entity.

[0023] Specifically, the method for determining the matching transaction subject of the unit is as follows: Based on the average value of the historical transaction power of the potential transaction subjects on different dates, which is used as the average daily transaction power, the potential transaction subjects are divided into different transaction subject groups with the energy storage capacity of the energy storage device as a constraint condition; Determine the average value of the historical transaction power of the transaction subject group in different historical transaction periods, and use it as the average transaction power; Determine the group matching coefficient between the group of transaction entities and the unit based on the deviation between the average transaction power of different historical transaction periods and the energy storage capacity of the energy storage device and the transaction electricity price; Obtaining matching coefficients of different potential transaction entities in the transaction entity group, and determining a comprehensive matching coefficient of the transaction entity group by combining the transaction entity group with the group matching coefficient of the unit; An optimal transaction group is determined based on the comprehensive matching coefficient, and potential transaction entities of the optimal transaction group are used as matching transaction entities of the unit.

[0024] Furthermore, determining the optimal transaction group based on the comprehensive matching coefficient specifically includes: The group of trading entities with the largest comprehensive matching coefficient is regarded as the optimal trading group.

[0025] It is understandable that the method for determining the matching transaction subject of the unit is: Based on the average value of the historical transaction electricity of potential transaction entities on different dates, which is used as the average daily transaction electricity, and with the energy storage capacity of the energy storage device as a constraint, the potential transaction entities are divided into different transaction entity groups. If there is a date in which the deviation between the average daily transaction electricity and the energy storage capacity of a transaction entity group does not meet the requirement, it is determined that the potential transaction entities in the transaction entity group cannot be simultaneously matched as transaction entities; When the deviations between the average daily transaction power of the trading entity group on different dates and the energy storage capacity meet the requirements: Determine the average value of the historical transaction power of the transaction subject group in different historical transaction periods, and use it as the average transaction power; Determine the group decomposition matching coefficient between the transaction subject group and the unit on different dates based on the deviation between the average transaction power of different historical transaction periods and the energy storage capacity of the energy storage device and the transaction electricity price; When the number of dates for which the group decomposition matching coefficient does not meet the requirement is not within the preset date quantity range, it is determined that the potential transaction subjects of the transaction subject group cannot be simultaneously used as matching transaction subjects; When the number of dates on which the group decomposition matching coefficient does not meet the requirements is within a preset date range, the group matching coefficient is determined based on the group decomposition matching coefficients of the transaction subject group and the unit on different dates. When the group matching coefficient does not meet the requirements, it is determined that the potential transaction subjects of the transaction subject group cannot be simultaneously used as matching transaction subjects; When the group matching coefficient meets the requirements, obtaining the matching coefficients of different potential transaction entities in the transaction entity group, and combining the group matching coefficients of the transaction entity group and the unit to determine the comprehensive matching coefficient of the transaction entity group; An optimal transaction group is determined based on the comprehensive matching coefficient, and potential transaction entities of the optimal transaction group are used as matching transaction entities of the unit.

[0026] Furthermore, the predicted electricity trading volume and predicted electricity price of the matching transaction subject are determined based on the average value of the electricity trading volume and the average value of the predicted electricity price on weather-similar dates, wherein the weather-similar dates are determined based on the weather data.

[0027] It should be noted that if Figure 3 As shown, the method for determining the electric energy utilization period is: Obtaining the predicted power transaction quantity and predicted electricity price of the matching transaction subject in a specific period, and determining the power utilization matching coefficient between the matching transaction subject and the unit in the specific period based on the predicted power transaction quantity and predicted electricity price; The time period matching coefficient is determined according to the power utilization matching coefficient between different matching transaction subjects and the unit in a specific time period, and the power utilization time period is determined using the time period matching coefficient.

[0028] Furthermore, when the time period matching coefficient of the specific time period meets the requirement, the specific time period is determined to be the electric energy utilization time period.

[0029] It is understandable that the method for determining the power utilization period is: Obtain the predicted electricity transaction amount of the matching transaction subject in a specific time period, and use the deviation between the predicted total electricity transaction amount of different matching transaction subjects and the energy storage capacity to determine whether the specific time period belongs to an available time period; if so, proceed to the next step; if not, determine that the specific time period does not belong to an electricity utilization time period; Determining valid trading entities among the matched trading entities using the predicted power transaction amount, and determining that the specific time period does not belong to the power utilization time period when the number of the valid trading entities does not meet the requirement; When the number of valid trading entities meets the requirement, the predicted total electricity volume of the valid trading entities is obtained, and when the deviation between the predicted total electricity volume of the valid trading entities and the energy storage capacity is not within a preset electricity volume deviation range, it is determined that the specific time period does not belong to the electricity utilization period; When the deviation between the predicted total power volume of the power transaction of the valid trading subject and the energy storage capacity is within a preset power volume deviation range, the power utilization matching coefficient between the matching trading subject and the unit in a specific time period is determined based on the predicted power volume of the power transaction and the predicted electricity price; when the number of matching trading subjects whose power utilization matching coefficients meet the requirements does not meet the requirements, it is determined that the specific time period does not belong to the power utilization period; When the number of matching transaction entities whose power utilization matching coefficients meet the requirements meets the requirements, the time period matching coefficient is determined according to the power utilization matching coefficients of different matching transaction entities and the unit in a specific time period, and the power utilization time period is determined using the time period matching coefficient.

[0030] Furthermore, the method for determining the predicted amount of electric energy utilization is: Determining a power utilization matching coefficient between the matching transaction subject and the unit in a specific period based on the power transaction predicted quantity and predicted electricity price; The electric energy utilization matching coefficient is used to determine a reliable transaction subject among the matched transaction subjects, and the electric energy utilization forecast amount for the specific time period is determined based on the power transaction forecast amount of the reliable transaction subject.

[0031] Specifically, the method for determining the load dispatch strategy of the unit in different time periods is as follows: Based on the predicted amount of electricity utilization in different electricity utilization periods, and with the balance of electricity and heat supply and demand as the constraint condition, Construct economic functions based on electricity price and electricity output, heat price and heat output; Based on the predicted amount of electricity utilization in different electricity utilization periods, with the balance of supply and demand of electricity and heat energy as a constraint condition, and with the maximization of the economic function as the goal, an optimization model is constructed to determine the load output of the unit in different periods; The load dispatching strategies of the units in different time periods are generated based on the load outputs of the units in different time periods.

[0032] Example 2 On the other hand, an embodiment of the present application provides a unit load scheduling system that considers grid energy interaction, adopting the above-mentioned unit load scheduling method that considers grid energy interaction, characterized by specifically including: Matching coefficient evaluation module, transaction subject screening module, power utilization evaluation module, and scheduling strategy output module; The matching coefficient evaluation module is responsible for obtaining the energy storage capacity of the energy storage device of the unit, and determining the matching coefficient of the power spot trading subject of the unit based on the deviation between the historical transaction power and the energy storage capacity and the transaction price of the historical transaction power; The trading subject screening module is responsible for selecting electricity spot trading subjects whose matching coefficients meet the requirements as potential trading subjects, obtaining the matching status of the historical trading electricity of potential trading subjects in different historical trading periods based on the energy storage capacity of the energy storage device as a constraint, and determining the matching trading subject of the unit based on the matching coefficients of the potential trading subjects; The power utilization evaluation module is responsible for determining the power transaction forecast and power price of the matching transaction subjects in different time periods by using weather data in the day-ahead stage, and determining the power utilization period and the power utilization forecast in the power utilization period based on the power transaction forecast and power price of the matching transaction subjects in different time periods; The scheduling strategy output module is responsible for generating the load scheduling strategy of the unit in different time periods based on the predicted power utilization in different power utilization periods, with the balance of power and heat supply and demand as the constraint condition, and with economic optimization as the goal.

[0033] Example 3 On the other hand, an embodiment of the present application provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed in a computer, the computer is caused to execute the above-mentioned unit load scheduling method considering grid energy interaction.

[0034] In the embodiments of the present invention, the term "plurality" refers to two or more, unless otherwise specified. Terms such as "installed," "connected," and "fixed" should be interpreted broadly. For example, "connected" can refer to a fixed connection, a detachable connection, or an integral connection. Those skilled in the art will understand the specific meanings of these terms in the embodiments of the present invention based on specific circumstances.

[0035] In the description of the embodiments of the present invention, it should be understood that the terms "upper" and "lower" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present invention and simplifying the description, rather than indicating or implying that the device or unit referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the embodiments of the present invention.

[0036] Throughout this specification, terms such as "one embodiment" and "a preferred embodiment" mean that the specific features, structures, materials, or characteristics described in conjunction with that embodiment or example are included in at least one embodiment or example of the present invention. In this specification, schematic representations of these terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

[0037] The above is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Those skilled in the art will readily appreciate that various modifications and variations are possible in the present invention. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of the present invention are intended to be within the scope of protection of the present invention.

Claims

1. A method for unit load dispatching considering power grid energy interaction, characterized in that: Specifically include: Obtain the energy storage capacity of the energy storage device of the unit, and determine the matching coefficient of the power spot trading subject of the unit based on the deviation between the historical trading electricity and the energy storage capacity and the trading electricity price of the historical trading electricity. When the matching coefficient of the power spot trading subject meets the requirements, proceed to the next step; The electricity spot trading subject whose matching coefficient meets the requirements is taken as a potential trading subject, and the energy storage capacity of the energy storage device is used as a constraint condition to obtain the matching situation of the historical trading electricity of the potential trading subject in different historical trading periods, and the matching trading subject of the unit is determined in combination with the matching coefficient of the potential trading subject; In the day-ahead stage, the forecasted electricity volume and forecasted electricity price of the matching transaction subjects in different time periods are determined by using weather data, and the electricity utilization period and the forecasted electricity volume of the electricity utilization period are determined based on the forecasted electricity volume and forecasted electricity price of the matching transaction subjects in different time periods; Based on the predicted power consumption in different power utilization periods, with the balance of power and thermal energy supply and demand as constraints, and with economic optimization as the goal, the load dispatching strategy of the unit in different periods is generated.

2. The unit load dispatching method considering grid energy interaction according to claim 1, characterized in that: The historical transaction volume is determined based on the historical transaction data of the power spot transaction entity.

3. The unit load dispatching method considering grid energy interaction according to claim 1, characterized in that: The method for determining the matching coefficient of the power spot transaction subject of the unit is: The average value of the historical transaction volume of the power spot trading subject at different time periods on different dates is used as the reference transaction volume; Determine the transaction matching coefficients on different dates based on the deviation between the reference transaction electricity and the energy storage capacity on different dates and the average value of the transaction electricity prices on different dates; The matching coefficient between the power spot trading entity and the unit is determined by the transaction matching coefficients on different dates.

4. The unit load dispatching method considering grid energy interaction as claimed in claim 3, characterized in that: The value range of the matching coefficient between the power spot trading entity and the unit is between 0 and 1, wherein the larger the matching coefficient between the power spot trading entity and the unit, the higher the degree of matching between the power spot trading entity and the unit.

5. The unit load dispatching method considering grid energy interaction according to claim 1, characterized in that: When the matching coefficient between the power spot trading subject and the unit is greater than a preset matching coefficient threshold, the power spot trading subject is determined to be a potential trading subject.

6. The unit load dispatching method considering grid energy interaction according to claim 1, characterized in that: The method for determining the matching transaction subject of the unit is: According to the average value of the historical transaction power of the potential transaction subject on different dates, which is used as the average daily transaction power, the potential transaction subject is divided into different transaction subject groups with the energy storage capacity of the energy storage device as a constraint condition; Determine the average value of the historical transaction power of the transaction subject group in different historical transaction periods, and use it as the average transaction power; Determine the group matching coefficient between the transaction subject group and the unit through the deviation between the average transaction power in different historical transaction periods and the energy storage capacity of the energy storage device and the transaction electricity price; Acquire matching coefficients of different potential transaction entities of the transaction entity group, and determine a comprehensive matching coefficient of the transaction entity group by combining the transaction entity group with the group matching coefficient of the unit; The optimal transaction group is determined based on the comprehensive matching coefficient, and the potential transaction subjects of the optimal transaction group are used as the matching transaction subjects of the unit.

7. The method for unit load dispatching considering grid energy interaction according to claim 6, characterized in that: Determining the optimal transaction group based on the comprehensive matching coefficient specifically includes: The group of trading entities with the largest comprehensive matching coefficient is taken as the optimal trading group.

8. The method for unit load dispatching considering grid energy interaction according to claim 1, characterized in that: The predicted electricity trading volume and predicted electricity price of the matching transaction subject are determined based on the average value of the electricity trading volume and the average value of the predicted electricity price on a date with similar weather, wherein the date with similar weather is determined based on the weather data.

9. The unit load dispatching method considering grid energy interaction according to claim 1, characterized in that: The method for determining the electric energy utilization period is: Obtaining the predicted power transaction quantity and predicted electricity price of the matching transaction subject in a specific period, and determining the power utilization matching coefficient between the matching transaction subject and the unit in the specific period based on the predicted power transaction quantity and predicted electricity price; The time period matching coefficient is determined according to the matching coefficient of the electric energy utilization between different matching transaction subjects and the unit in a specific time period, and the electric energy utilization time period is determined using the time period matching coefficient.

10. A unit load dispatching system considering grid energy interaction, adopting a unit load dispatching method considering grid energy interaction as claimed in any one of claims 1 to 9, characterized in that: Specifically include: Matching coefficient evaluation module, transaction subject screening module, power utilization evaluation module, and scheduling strategy output module; The matching coefficient evaluation module is responsible for obtaining the energy storage capacity of the energy storage device of the unit, and determining the matching coefficient of the power spot trading subject of the unit based on the deviation between the historical transaction power and the energy storage capacity and the transaction price of the historical transaction power; The transaction subject screening module is responsible for taking the power spot transaction subject whose matching coefficient meets the requirements as the potential transaction subject, taking the energy storage capacity of the energy storage device as the constraint condition, obtaining the matching situation of the historical transaction electricity of the potential transaction subject in different historical transaction periods, and determining the matching transaction subject of the unit in combination with the matching coefficient of the potential transaction subject; The power utilization evaluation module is responsible for determining the power transaction forecast quantity and forecast electricity price of the matching transaction subjects in different time periods by using weather data in the day-ahead stage, and determining the power utilization period and the power utilization forecast quantity in the power utilization period based on the power transaction forecast quantity and forecast electricity price of the matching transaction subjects in different time periods; The dispatching strategy output module is responsible for generating the load dispatching strategy of the unit in different time periods based on the predicted power utilization in different power utilization periods, with the balance of power and thermal energy supply and demand as constraints, and with economic optimization as the goal.