Intelligent laying method, system, medium and equipment for photovoltaic module
By identifying and utilizing the open space around the area to be installed for pre-installation of purlins and torque tubes of photovoltaic modules, the problem of low efficiency of traditional installation methods is solved and efficient installation of photovoltaic modules is achieved.
Patent Information
- Application Number
- CN202410906347.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-10-18
AI Technical Summary
The traditional installation method of photovoltaic modules is bottom-up, which means that the installation process needs to be carried out in a certain order and cannot be divided into multiple solutions that can be carried out simultaneously, resulting in low installation efficiency.
By obtaining information about the area to be installed and photovoltaic modules, distribution and assembly information is generated, surrounding open areas are identified, pre-installation areas are set, the installation process is split into pre-installation of purlins and torque tubes, and ground pile installation is completed simultaneously to improve installation efficiency.
It significantly improves the installation efficiency of photovoltaic modules, reduces on-site manpower and improves installation efficiency.
Smart Images

Figure CN118798428A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of photovoltaic modules, and in particular to an intelligent laying method, system, medium and equipment for photovoltaic modules. Background Art
[0002] Generally, the construction process of a photovoltaic station includes the layout and construction of ground piles, the installation of brackets, the delivery of photovoltaic modules, the docking and fixing of photovoltaic modules and brackets, etc. In the actual installation process, the installation of photovoltaic modules involves the installation of purlins, torque tubes, and ground piles. The traditional installation method is bottom-up installation, that is, first laying ground piles at the installation site, then fixing the torque tubes and purlins, and finally placing photovoltaic modules on the purlins manually or by a robotic arm.
[0003] However, this method has the following problems: since the traditional installation method is bottom-up installation, the entire installation process needs to be carried out in a certain order, and the installation process cannot be broken down into multiple solutions that can be carried out simultaneously. Once an installation problem occurs in a certain link, the installation efficiency will be slowed down, making the installation efficiency of the entire photovoltaic module low. Summary of the invention
[0004] In view of the above problems, the present invention provides a method, system, medium and equipment for intelligent laying of photovoltaic components, which solves the problem of low efficiency of existing installation methods.
[0005] To achieve the above objectives, in a first aspect, the present invention provides a method for intelligently laying photovoltaic modules, comprising:
[0006] Acquire information about the area to be installed, where the information about the area to be installed includes area shape information, area length information, and area width information of the area where the photovoltaic components need to be installed;
[0007] Obtaining photovoltaic module information, the photovoltaic module information includes the size information of a single photovoltaic module that needs to be installed currently;
[0008] Generate distribution information and assembly information of photovoltaic modules in the current installation area according to the information of the installation area and the photovoltaic module information, the distribution information includes the arrangement direction, arrangement quantity and total quantity of photovoltaic modules, and the assembly information includes the number of stations and station categories required for the current photovoltaic modules to complete pre-installation within a preset time period, and the station categories include purlin installation stations and torque tube installation stations;
[0009] Generate first area information according to the assembly information, the first area information including the area occupied by the workstations under the current number of workstations;
[0010] Acquire a terrain image of the area to be installed in real time, and extract all vacant area information and traffic path information except the area to be installed from the terrain image, wherein the vacant area information includes size information and geographic coordinate information of the vacant area;
[0011] Generate a planned path between each open space area and the area to be installed according to the traffic path information; and
[0012] Acquire second area information of a plurality of vacant land areas;
[0013] Sorting the multiple planned paths according to a preset sorting method, obtaining second area information of the open space area corresponding to the planned path ranked first, and determining whether the second area information is greater than the first area information;
[0014] If yes, the current empty area is recorded as a pre-installation area, and assembly configuration information is generated according to the assembly information and the pre-installation area, where the assembly configuration information includes a station layout in the pre-installation area;
[0015] If not, obtain the second area information of the open space area corresponding to the second planned path, add the second area information of the second open space area and the second area information of the first open space area to obtain the third area information, and determine whether the third area information is greater than the first area information;
[0016] If the third area information is greater than the first area information, the second-ranked vacant area and the first-ranked vacant area are both recorded as pre-installation areas, and assembly configuration information is generated based on the assembly information and the pre-installation area. The assembly configuration information includes the work station layout within the pre-installation area.
[0017] In some embodiments, generating the distribution information and assembly information of the photovoltaic components in the current area to be installed according to the information of the area to be installed and the information of the photovoltaic components includes:
[0018] Obtain a preset time segment, where the preset time segment is the installation duration of the photovoltaic components;
[0019] Generate purlin installation strategy, torque tube installation strategy and ground pile installation strategy according to the total number of photovoltaic modules and the preset time period;
[0020] The purlin installation strategy includes the number of purlin installation stations and the first floor space of a single purlin installation station, the torque tube installation strategy includes the number of torque tube installation stations and the second floor space of a single torque tube installation station, and the ground pile installation strategy includes the number of ground pile installation stations in the current area to be installed and the arrangement of the ground piles;
[0021] Assembly information is generated according to the purlin installation strategy and the torque tube installation strategy.
[0022] In some embodiments, generating a purlin installation strategy, a torque tube installation strategy, and a ground pile installation strategy according to the total number of photovoltaic modules and a preset time period includes:
[0023] Obtain the total number of photovoltaic modules, and generate the total number of purlins, the total number of torque tubes, and the total number of ground piles according to the total number of photovoltaic modules;
[0024] Obtaining a first installation time corresponding to installing the required purlins on a single photovoltaic module, and recording the photovoltaic module after the required purlins are installed on the single photovoltaic module as a first pre-installed component;
[0025] Obtain a second installation time corresponding to the installation of the required torque tube on a single first pre-installed component, and record the first pre-installed component after the single installation of the required torque tube as the second pre-installed component;
[0026] Obtaining a third installation time corresponding to the installation of a single second pre-installed component on a ground pile;
[0027] The first installation time, the second installation time and the third installation time are added together to obtain a total installation time for completing the installation of a single photovoltaic module in the area to be installed, and the total installation time is recorded as a fourth installation time;
[0028] Dividing the preset time segment and the fourth installation time, the number of photovoltaic modules installed at a single purlin installation station, a single torque tube installation station, and a single ground pile installation station is obtained, which is recorded as a first installation number;
[0029] Obtaining a first installation multiple of the photovoltaic components according to the total number of photovoltaic components and the first installation number, and obtaining a second installation multiple between the first installation time and the second installation time;
[0030] The number of purlin installation stations, the number of torque tube installation stations and the number of ground pile installation stations are generated according to the first installation multiple and the second installation multiple.
[0031] In some embodiments, a terrain image of the area to be installed is acquired in real time, and all vacant area information and traffic path information except the area to be installed are extracted from the terrain image;
[0032] Taking the area to be installed as the center and the preset size as the radius, the size information of the terrain image corresponding to the area to be installed is obtained;
[0033] Controlling the image acquisition unit to acquire a plurality of initial images according to the size information of the terrain image;
[0034] Preprocessing multiple initial images and fusing the preprocessed initial images to form a terrain image, wherein the preprocessing includes image denoising, image enhancement and image registration;
[0035] The terrain image is input into the YOLO algorithm model, and the output result of the YOLO algorithm model is a set of object features;
[0036] Classify the object feature set to obtain open space area information and traffic path information.
[0037] In some embodiments, generating a planned path between each vacant area and the area to be installed according to the traffic path information includes:
[0038] Obtaining geographic coordinate information of the open space area and recording it as first geographic coordinate information;
[0039] Obtaining geographic coordinate information of the area to be installed, and recording it as second geographic coordinate information;
[0040] Inputting the first geographic coordinate information, the second geographic coordinate information and the traffic path information into the trained neural network model, the output result of the neural network model is the initial planned path between the first geographic coordinate and the second geographic coordinate;
[0041] The initial planned path is input into the A* algorithm model for path optimization. The output result of the A* algorithm model is the optimized initial planned path. The optimized initial planned path is recorded as the planned path between the current open space area and the area to be installed.
[0042] In some embodiments, the neural network model is trained by:
[0043] Build a basic neural network model;
[0044] Input sample training data into the basic neural network model, the sample training data is a sample image and sample traffic path information in the sample database, and the sample image includes a sample to-be-installed area and a sample vacant area;
[0045] The basic neural network model is repeatedly trained until the accuracy of the basic neural network model reaches a preset threshold, and the basic neural network model whose accuracy reaches the preset threshold is recorded as a trained neural network model.
[0046] In some embodiments, assembly configuration information is generated according to the assembly information and the pre-installation area, and the assembly configuration information includes a station layout in the pre-installation area including:
[0047] The number of purlin installation stations and the number of torque tube installation stations are grouped according to the second installation multiple to obtain a plurality of photovoltaic module pre-installation station groups;
[0048] Obtain the number of pre-installation areas, and if the number of pre-installation areas is greater than 2, obtain second area information of each pre-installation area;
[0049] Calculate the multiple relationship between each second area information and a single photovoltaic module pre-installation station group, and record it as a third installation multiple;
[0050] Generating a workstation layout of a photovoltaic module pre-installation workstation group in a current pre-installation area according to a third installation multiple;
[0051] Generate assembly configuration information based on multiple station layouts.
[0052] In a second aspect, the present invention further provides an intelligent photovoltaic module laying system, the system comprising a service end, an image acquisition unit, a first container, a second container, a conveying track and a transfer vehicle, the service end being used to execute the method described in the first aspect; the image acquisition unit establishes a communication connection with the service end, and is used to collect a terrain image of the area to be installed; at least one purlin installation station is provided in the first container; at least one torque tube installation station is provided in the second container; the conveying track is arranged between the first container and the second container, and the conveying track is detachably connected to the first container and the second container respectively; the transfer vehicle is connected to the output end of the second container, and the transfer vehicle is used to move the pre-installed photovoltaic modules from the pre-installation area to the area to be installed, so as to complete the installation of the photovoltaic modules.
[0053] In a third aspect, the present invention further provides a computer-readable storage medium storing computer program instructions, which implement the method described in the first aspect when executed by a processor.
[0054] In a fourth aspect, the present invention further provides an electronic device, comprising a memory and a processor, wherein the memory is used to store one or more computer program instructions, wherein the one or more computer program instructions are executed by the processor to implement the method described in the first aspect.
[0055] Different from the prior art, in the above technical scheme, the installation process of photovoltaic modules in the area to be installed is divided into purlin installation and torque tube installation, and the terrain image of the area to be installed is obtained, the open space area around the area to be installed is identified, and the pre-installation process of the photovoltaic modules is set. The purlin installation and torque tube installation of the photovoltaic modules are placed in the open space area. At this time, the installation of the ground piles can be completed simultaneously in the area to be installed. After the pre-installation of the photovoltaic modules is completed, the pre-installed photovoltaic modules are directly installed and connected to the ground piles in the area to be installed, which reduces the manpower required to install the photovoltaic modules on the bracket at the construction site, and significantly improves the installation efficiency of the photovoltaic modules.
[0056] The above-mentioned records related to the content of the invention are only an overview of the technical solution of the present invention. In order to enable ordinary technicians in the field to more clearly understand the technical solution of the present invention, and then implement it according to the text of the specification and the contents recorded in the drawings, and in order to make the above-mentioned purpose and other purposes, features and advantages of the present invention easier to understand, the following is a description in combination with the specific implementation mode of the present invention and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0057] The drawings are only used to illustrate the principles, implementations, applications, features and effects of the specific embodiments of the present invention and other related contents, and shall not be considered as limiting the present invention.
[0058] In the drawings of the specification:
[0059] Figure 1 This is a diagram of the first step of the laying method according to a specific embodiment of the present invention;
[0060] Figure 2 It is a diagram of the second step of the laying method according to a specific embodiment of the present invention;
[0061] Figure 3 A schematic diagram of a pre-installation area of a laying method according to a specific embodiment of the present invention;
[0062] Figure 4 This is a schematic diagram of a laying system according to a specific embodiment of the present invention;
[0063] Figure 5 A schematic diagram of an electronic device according to a specific embodiment of the present invention;
[0064] Figure 6 It is a first framework diagram of a laying method according to a specific embodiment of the present invention;
[0065] Figure 7 It is a second framework diagram of the laying method described in a specific embodiment of the present invention.
[0066] The reference numerals in the above drawings are described as follows:
[0067] 1. Laying system;
[0068] 11. Server;
[0069] 12. Image acquisition unit;
[0070] 13. First container;
[0071] 14. Second container;
[0072] 15. Conveyor track;
[0073] 16. Transfer vehicle;
[0074] 2. Electronic equipment;
[0075] 21. Memory;
[0076] 22. Processor;
[0077] 3. Area to be installed;
[0078] 4. Pre-installation area;
[0079] 5. Open space area. DETAILED DESCRIPTION
[0080] In order to explain in detail the possible application scenarios, technical principles, specific schemes that can be implemented, and the purposes and effects of the present invention, the following is a detailed description in combination with the specific embodiments listed and the accompanying drawings. The embodiments described herein are only used to more clearly illustrate the technical solutions of the present invention, and are therefore only used as examples, and cannot be used to limit the scope of protection of the present invention.
[0081] Reference to "embodiment" herein means that the specific features, structures or characteristics described in conjunction with the embodiment may be included in at least one embodiment of the present invention. The word "embodiment" appearing in various places in the specification does not necessarily refer to the same embodiment, nor does it particularly limit its independence or association with other embodiments. In principle, in the present invention, as long as there is no technical contradiction or conflict, the various technical features mentioned in each embodiment can be combined in any way to form a corresponding implementable technical solution.
[0082] Unless otherwise defined, the technical terms used herein have the same meanings as those generally understood by those skilled in the art to which the present invention belongs; the use of relevant terms herein is only for describing specific embodiments and is not intended to limit the present invention.
[0083] In the description of the present invention, the term "and / or" is an expression used to describe the logical relationship between objects, indicating that three relationships may exist, for example, A and / or B, which means: A exists, B exists, and A and B exist at the same time. In addition, the character " / " in this article generally indicates that the objects before and after are in a logical relationship of "or".
[0084] In the present invention, terms such as "first" and "second" are merely used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship of quantity, priority or sequence between these entities or operations.
[0085] Without further restrictions, in the present invention, the words "include", "comprises", "has" or other similar open-ended expressions used in sentences are intended to cover non-exclusive inclusion. These expressions do not exclude the presence of additional elements in the process, method or product including the elements, so that the process, method or product including a series of elements may include not only those limited elements, but also other elements not explicitly listed, or also include elements inherent to such process, method or product.
[0086] Similar to the understanding in the Examination Guidelines, in the present invention, expressions such as "greater than", "less than", "exceed" and the like are understood to exclude the number itself; expressions such as "above", "below", "within" and the like are understood to include the number itself. In addition, in the description of the embodiments of the present invention, the meaning of "multiple" is more than two (including two), and similar expressions related to "multiple" are also understood in this way, such as "multiple groups", "multiple times", etc., unless otherwise clearly and specifically limited.
[0087] In the description of the embodiments of the present invention, the space-related expressions used, such as "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "vertical", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc., indicate the orientation or position relationship based on the orientation or position relationship shown in the specific embodiments or drawings, and are only for the convenience of describing the specific embodiments of the present invention or facilitating the reader's understanding, and do not indicate or imply that the referred device or component must have a specific position, a specific orientation, or be constructed or operated in a specific orientation, and therefore cannot be understood as a limitation on the embodiments of the present invention.
[0088] Unless otherwise expressly specified or limited, in the description of the embodiments of the present invention, the terms such as "install", "connect", "connect", "fix", "set" and the like used should be understood in a broad sense. For example, the "connection" can be a fixed connection, a detachable connection, or an integrated setting; it can be a mechanical connection, an electrical connection, or a communication connection; it can be a direct connection, or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For those skilled in the art of the technical field to which the present invention belongs, the specific meanings of the above terms in the embodiments of the present invention can be understood according to the specific circumstances.
[0089] See also Figures 1 to 3 , Figure 6 and Figure 7 In a first aspect, this embodiment provides a method for intelligently laying photovoltaic modules, comprising:
[0090] S101, obtaining information of the area to be installed, the information of the area to be installed including area shape information, area length information and area width information of the area where the photovoltaic modules need to be installed; and obtaining photovoltaic module information, the photovoltaic module information including size information of a single photovoltaic module currently to be installed;
[0091] S102, generating distribution information and assembly information of photovoltaic modules in the current area to be installed according to the information of the area to be installed and the information of photovoltaic modules, wherein the distribution information includes the arrangement direction, arrangement quantity and total quantity of photovoltaic modules, and the assembly information includes the number of stations and station types required for the current photovoltaic modules to complete pre-installation within a preset time period, wherein the station types include purlin installation stations and torque tube installation stations;
[0092] S103, generating first area information according to the assembly information, the first area information including the area occupied by the workstations under the current number of workstations;
[0093] S104, acquiring in real time a terrain image of the area to be installed, and extracting all vacant area information and traffic path information except the area to be installed from the terrain image, wherein the vacant area information includes size information and geographic coordinate information of the vacant area;
[0094] S105, generating a planned path between each open space area and the area to be installed according to the traffic path information; and obtaining second area information of the plurality of open space areas;
[0095] S106, sorting the multiple planned paths according to a preset sorting method, obtaining second area information of the open space area corresponding to the planned path ranked first, and determining whether the second area information is greater than the first area information;
[0096] S107, if yes, record the current vacant area as a pre-installation area, generate assembly configuration information according to the assembly information and the pre-installation area, the assembly configuration information including the station layout in the pre-installation area;
[0097] S108, if not, obtaining the second area information of the open space area corresponding to the second planned path, adding the second area information of the second open space area to the second area information of the first open space area to obtain third area information, and determining whether the third area information is greater than the first area information;
[0098] S109. If the third area information is greater than the first area information, the second-ranked empty space area and the first-ranked empty space area are both recorded as pre-installation areas, and assembly configuration information is generated according to the assembly information and the pre-installation areas. The assembly configuration information includes the workstation layout in the pre-installation area.
[0099] In step S101, the information of the area to be installed can be understood as the size of the area for installing photovoltaic modules, corresponding to Figure 3 The area to be installed in the photovoltaic module can be obtained by map survey or remote sensing image recognition. The photovoltaic module information can be understood as the size information of a single photovoltaic module, that is, the size information of the photovoltaic module to be installed in the area to be installed. It should be noted that when there are multiple photovoltaic modules of different sizes, the photovoltaic module information includes the size information of all photovoltaic modules to be installed in the current area to be installed.
[0100] In step S102, distribution information and assembly information are generated according to the information of the area to be installed and the information of the photovoltaic modules. The distribution information here can be understood as the arrangement and distribution data of the photovoltaic modules in the area to be installed, which is generated by matching the size of the area to be installed with the size of the photovoltaic modules. Figure 3 In the rectangular area to be installed shown, the arrangement interval, number of rows and quantity of photovoltaic modules are all distribution information. The assembly information is the number of stations and station types required for all photovoltaic modules in the current area to be installed to complete the pre-installation within the preset time period. The preset time period here is manually input. In some application scenarios that require installation time, the preset time period corresponds to the total time required for the current photovoltaic modules to be installed. For example, if the preset time period is 24 hours and the number of days is 2 days, it means that there are 24 hours in total in two days to install photovoltaic modules. The server can obtain the number of stations required to install photovoltaic modules according to the preset time period.
[0101] In step S103, first area information is generated according to the assembly information, where the first area information can be understood as the floor space of all workstations;
[0102] In step S104, it is necessary to obtain in real time the terrain image of the area to be installed, where the terrain image of the area to be installed can be understood as the terrain image around the area to be installed, the terrain image can be a remote sensing image or image information collected by other image acquisition equipment, and all the open space area information and traffic path information except the current area to be installed are extracted from the terrain image, and the open space area information includes the size information and geographic coordinate information of the open space area. The open space area here can be understood as a platform building or flat landform with a vehicle or large equipment placed thereon.
[0103] In step S105, a planned path between each open space area and the area to be installed is generated based on the traffic path information. Specifically, the traffic path information is the existing road information available for vehicles to pass through. This step can facilitate the selection and decision of the subsequent open space areas. At the same time, the second area information of multiple open space areas is obtained. It should be noted that one open space area corresponds to one second area information, and multiple open space areas correspond to their own second area information respectively. The values of the second area information can be different.
[0104] In step S106, multiple planned paths are sorted according to a preset sorting method, where the preset sorting method can be understood as a screening condition for judging the pros and cons of the planned paths. The purpose of sorting is to screen out the optimal planned path, and the preset sorting method can have a variety of different angles. For example, if the optimal path in the planned path is screened from the perspective of the shortest path, the open space area corresponding to the planned path with the shortest distance to the installation area is preferred; if the screening is performed from the perspective of path flatness, the open space area corresponding to the planned path with a large proportion of asphalt roads or highways in the planned path is preferred; if the screening is performed from the perspective of fewer path turning directions, the open space area corresponding to the planned path with the most straight lines in the planned path is preferred. The specific preset sorting method can be selected or adjusted according to actual needs, and this embodiment does not set a limit to this. After sorting multiple planned paths according to the preset sorting method, the second area information of the open space area corresponding to the planned path ranked first is selected to determine whether the second area information is greater than the first area information. That is, step S106 can screen the open space area to screen out the open space area of the stations that can accommodate the number of stations in the assembly information, and use it as the pre-installation area.
[0105] In step S107, if the second area information is greater than the first area information, that is, the current vacant area can be laid out with the number of workstations that matches the number recorded in the assembly information, then the current vacant area is recorded as a pre-installation area, and assembly configuration information is generated based on the pre-installation area and the assembly information. Here, the assembly configuration information includes the workstation layout of multiple workstations in the pre-installation area.
[0106] In step S108, if the second area information is smaller than the first area information, it means that the current open space area cannot accommodate the number of workstations recorded in the assembly information, and it is necessary to sequentially obtain the second area information of the open space area corresponding to the second planned path, and add the second area information of the open space area arranged in the first place with the second area information arranged in the second place, record the calculation result as the third area information, and then judge whether the third area information is greater than the first area information. If the third area information is still smaller than the first area information, continue to obtain the second area information corresponding to the open space area of the third planned path, continue to perform the addition operation, and then compare the addition result with the first area information until a final result greater than the first area information is obtained. In other words, when the first open space area does not meet the laying conditions of the workstation, the workstations can be distributed through multiple open space areas to meet the workstation requirements for pre-installation of photovoltaic components on site.
[0107] In step S109, it is shown that when the third area information is greater than the first area information, the vacant land area of the planned path arranged in the first position and the vacant land area of the planned path arranged in the second position are both recorded as pre-installation areas, and work stations are laid in the pre-installation areas to perform the pre-installation steps of the photovoltaic components.
[0108] Specific combination Figure 3 To understand: Figure 3 There are two pre-installation areas 4, multiple open space areas 5 and an area to be installed 3, wherein the area to be installed 3 is the installation location of the final photovoltaic components, and the number of pre-installation areas 4 is two. Purlin installation stations and torque tube installation stations can be laid in the two pre-installation areas 4 to realize the pre-installation of photovoltaic components.
[0109] It should be noted that this embodiment divides the on-site installation of photovoltaic modules into two parts. The first part is the installation of ground piles, that is, ground piles need to be laid in the area to be installed, and the ground piles are finally connected to the brackets of the photovoltaic modules. The second part is the pre-installation of photovoltaic modules, which includes the pre-installation of purlins and the pre-installation of torque tubes. The installation sequence is to pre-install purlins on the photovoltaic modules first, and then pre-install torque tubes on the photovoltaic modules. Finally, the photovoltaic modules with purlins and torque tubes installed are transported to the area to be installed for installation, so as to save the overall installation process of the photovoltaic modules.
[0110] In this embodiment, the pre-installation area is set up so that when the photovoltaic components are pre-installed, the installation operation of the ground piles can be carried out simultaneously in the area to be installed, thereby improving the installation efficiency. In this process, the pre-installation area needs to be screened. In this embodiment, the open space area around the area to be installed is used to evaluate and screen the open space area to obtain the selected pre-installation area, and then the pre-installation station is laid in the pre-installation area to realize the on-site pre-installation process of the photovoltaic components. After the installation is completed, the photovoltaic components can be directly moved to the area to be installed to complete the installation, thereby improving the installation efficiency of the photovoltaic components.
[0111] See also Figure 2 In some embodiments, generating the distribution information and assembly information of the photovoltaic components in the current area to be installed according to the information of the area to be installed and the information of the photovoltaic components includes:
[0112] S201, obtaining a preset time segment, where the preset time segment is the installation duration of the photovoltaic module;
[0113] S202, generating a purlin installation strategy, a torque tube installation strategy, and a ground pile installation strategy according to the total number of photovoltaic modules and a preset time period;
[0114] The purlin installation strategy includes the number of purlin installation stations and the first floor space of a single purlin installation station, the torque tube installation strategy includes the number of torque tube installation stations and the second floor space of a single torque tube installation station, and the ground pile installation strategy includes the number of ground pile installation stations in the current area to be installed and the arrangement of the ground piles;
[0115] S203: Generate assembly information according to the purlin installation strategy and the torque tube installation strategy.
[0116] In this embodiment, the preset time segment is the installation time of the photovoltaic module, and the purlin installation strategy, torque tube installation strategy and ground pile installation strategy are generated according to the total number of photovoltaic modules and the preset time segment. Furthermore, the purlin installation strategy also includes the automated control logic in a single purlin installation station, the allocation and docking of production capacity between the purlin installation station and the torque tube installation station, the torque tube installation strategy also includes the automated control logic of a single torque tube installation station, and the allocation and docking of production capacity between the torque tube installation station and the photovoltaic module in the area to be installed, and the ground pile installation strategy can be understood as the position index and production capacity index for laying the ground piles.
[0117] Among them, the assembly information is formed by extracting and sorting relevant data from the purlin installation strategy and the torque tube installation strategy.
[0118] Specifically, in some embodiments, generating a purlin installation strategy, a torque tube installation strategy, and a ground pile installation strategy according to the total number of photovoltaic modules and a preset time period includes:
[0119] Obtain the total number of photovoltaic modules, and generate the total number of purlins, the total number of torque tubes, and the total number of ground piles according to the total number of photovoltaic modules;
[0120] Obtaining a first installation time corresponding to installing the required purlins on a single photovoltaic module, and recording the photovoltaic module after the required purlins are installed on the single photovoltaic module as a first pre-installed component;
[0121] Obtain a second installation time corresponding to the installation of the required torque tube on a single first pre-installed component, and record the first pre-installed component after the single installation of the required torque tube as the second pre-installed component;
[0122] Obtaining a third installation time corresponding to the installation of a single second pre-installed component on a ground pile;
[0123] The first installation time, the second installation time and the third installation time are added together to obtain a total installation time for completing the installation of a single photovoltaic module in the area to be installed, and the total installation time is recorded as a fourth installation time;
[0124] Dividing the preset time segment and the fourth installation time, the number of photovoltaic modules installed at a single purlin installation station, a single torque tube installation station, and a single ground pile installation station is obtained, which is recorded as a first installation number;
[0125] Obtaining a first installation multiple of the photovoltaic components according to the total number of photovoltaic components and the first installation number, and obtaining a second installation multiple between the first installation time and the second installation time;
[0126] The number of purlin installation stations, the number of torque tube installation stations and the number of ground pile installation stations are generated according to the first installation multiple and the second installation multiple.
[0127] This embodiment shows the specific generation process of the purlin installation strategy, the torque tube installation strategy and the ground pile installation strategy. It should be noted that the number of purlin installation stations and the number of torque tube installation stations here depend on the time required for the photovoltaic module to complete the pre-installation. Under the premise of this idea, it is necessary to first obtain the first installation time corresponding to the installation of the required purlins on a single photovoltaic module, and obtain the second installation time corresponding to the installation of the torque tube on the first pre-installed component, and obtain the third installation time required for the installation of a single second pre-installed component on the ground pile. The first installation time, the second installation time and the third installation time are accumulated to obtain the installation time required to install a single photovoltaic module, which is recorded as the fourth installation time.
[0128] In this embodiment, the preset time segment has a multiple relationship with the fourth installation time, that is, the number of photovoltaic modules that can be installed when only one purlin installation station, one torque tube installation station and one ground pile installation station are required within the preset time period is also the multiple value. The first installation multiple of the photovoltaic modules is obtained according to the total number of photovoltaic modules and the first installation number, and because there is a sequence relationship between the purlin installation and the torque tube installation, it is necessary to further obtain the multiple relationship between the first installation time and the second installation time, that is, the production capacity of the purlin installation station and the production capacity of the torque tube installation station are expressed by the multiple relationship of time. Finally, the number of purlin installation stations, the number of torque tube installation stations and the number of ground pile installation stations are generated according to the first installation multiple and the second installation multiple.
[0129] In some embodiments, assembly configuration information is generated according to the assembly information and the pre-installation area, and the assembly configuration information includes a station layout in the pre-installation area including:
[0130] The number of purlin installation stations and the number of torque tube installation stations are grouped according to the second installation multiple to obtain a plurality of photovoltaic module pre-installation station groups;
[0131] Obtain the number of pre-installation areas, and if the number of pre-installation areas is greater than 2, obtain second area information of each pre-installation area;
[0132] Calculate the multiple relationship between each second area information and a single photovoltaic module pre-installation station group, and record it as a third installation multiple;
[0133] Generating a workstation layout of a photovoltaic module pre-installation workstation group in a current pre-installation area according to a third installation multiple;
[0134] Generate assembly configuration information based on multiple station layouts.
[0135] In this embodiment, the number of pre-installation areas is determined. When there is only one pre-installation area, it can be directly divided according to the area occupied by the pre-installation station group. When there are multiple pre-installation areas, it is necessary to calculate the multiple relationship between the second area information corresponding to each pre-installation area and the pre-installation station group of a single photovoltaic module, and then multiple third installation multiples can be obtained. The number of third installation multiples is consistent with the number of pre-installation areas. This embodiment realizes the distribution of multiple pre-installation station groups in the pre-installation area, which can achieve more efficient on-site layout to meet the installation requirements of photovoltaic modules.
[0136] In some embodiments, a terrain image of the area to be installed is acquired in real time, and all vacant area information and traffic path information except the area to be installed are extracted from the terrain image;
[0137] Taking the area to be installed as the center and the preset size as the radius, the size information of the terrain image corresponding to the area to be installed is obtained;
[0138] Controlling the image acquisition unit to acquire a plurality of initial images according to the size information of the terrain image;
[0139] Preprocessing multiple initial images and fusing the preprocessed initial images to form a terrain image, wherein the preprocessing includes image denoising, image enhancement and image registration;
[0140] The terrain image is input into the YOLO algorithm model, and the output result of the YOLO algorithm model is a set of object features;
[0141] Classify the object feature set to obtain open space area information and traffic path information.
[0142] Furthermore, this embodiment shows a specific process for extracting vacant area information and traffic path information based on a terrain image. In this embodiment, the size information of the terrain image can be understood as the size of a circular range with a preset distance as the radius and the center of the area to be installed, as the size information of the terrain image. An image acquisition signal is generated according to the size information of the terrain image, and the image acquisition unit is controlled to acquire multiple initial images. Here, the image acquisition unit can be a device with a camera function such as a drone, a remote sensing satellite, or a camera. The unprocessed image acquired by the image acquisition unit is recorded as the initial image.
[0143] The initial image after acquisition needs to be preprocessed. Specifically, the preprocessing includes image denoising, image enhancement, and image registration to reduce interference factors and make the subsequent terrain image recognition results more accurate. After the initial image is preprocessed, multiple initial images need to be fused. Existing image fusion algorithms can be used to generate terrain images.
[0144] The terrain image is input into the YOLO algorithm model. Here, the YOLOV8 algorithm model can be used to annotate and identify the terrain image, obtain multiple object features containing annotation information, and present the multiple object features in the form of a set.
[0145] The extracted multiple object features can be classified by setting a classifier to obtain the required open space area information and traffic path information.
[0146] In some embodiments, generating a planned path between each vacant area and the area to be installed according to the traffic path information includes:
[0147] Obtaining geographic coordinate information of the open space area and recording it as first geographic coordinate information;
[0148] Obtaining geographic coordinate information of the area to be installed, and recording it as second geographic coordinate information;
[0149] Inputting the first geographic coordinate information, the second geographic coordinate information and the traffic path information into the trained neural network model, the output result of the neural network model is the initial planned path between the first geographic coordinate and the second geographic coordinate;
[0150] The initial planned path is input into the A* algorithm model for path optimization. The output result of the A* algorithm model is the optimized initial planned path. The optimized initial planned path is recorded as the planned path between the current open space area and the area to be installed.
[0151] This embodiment shows the specific generation process of planning path information. Specifically, the geographic coordinate information of the vacant area, the geographic coordinate information of the area to be installed, and the information of the traffic path between the area to be installed and the vacant area are obtained in advance and input into the trained neural network model.
[0152] In some embodiments, the neural network model is trained by:
[0153] Build a basic neural network model;
[0154] Input sample training data into the basic neural network model, the sample training data is a sample image and sample traffic path information in the sample database, and the sample image includes a sample to-be-installed area and a sample vacant area;
[0155] The basic neural network model is repeatedly trained until the accuracy of the basic neural network model reaches a preset threshold, and the basic neural network model whose accuracy reaches the preset threshold is recorded as a trained neural network model.
[0156] The training process of the basic neural network model is illustrated with sample traffic path information and sample images: This embodiment uses a neural network model with deep learning capabilities to extract features from the image data of the sample area to be installed and the sample open space area. Specifically, a pre-trained convolutional neural network model can be used to map the image data to a high-dimensional feature space. Afterwards, a path planning model is trained using the result of feature extraction in combination with the sample traffic path information. The path planning model can be based on a basic model such as a recursive neural network (RNN), a convolutional neural network (CNN) or an attention mechanism. The goal of the model is to learn the relationship between the map and the path to predict the planned path from the sample open space area to the sample area to be installed. Take CNN as an example: select a CNN model pre-trained on a large-scale image dataset, such as VGG, ResNet, Inception, etc. Input the image data of the sample area to be installed and the sample open space area into the model to extract a high-dimensional feature representation; the output of some intermediate layers of the model can be selected as the feature representation. Feature selection methods such as chi-square test, mutual information, etc. can be used to select features that are meaningful for path planning. If the feature dimensionality is high, dimensionality reduction methods such as principal component analysis (PCA) or linear discriminant analysis (LDA) can be used to reduce the features to a lower dimension.
[0157] This embodiment uses a trained path planning model, and inputs the features of the area to be installed and the vacant area obtained by feature extraction into the path planning model. According to the features of the area to be installed and the vacant area, a planned path from each vacant area to the area to be installed is generated. Through the calculation process of the trained neural network model, the input features are processed and combined to obtain the output of the path. The specific calculation process depends on the category of the neural network model used; for example, if a recursive neural network (RNN) model is used, the input features can be recursively passed to the hidden layer of the RNN, and the path can be predicted based on the output of the hidden layer. If a convolutional neural network (CNN) is used, spatial features can be extracted through convolution and pooling operations, and path prediction can be performed through a fully connected layer. The generated planned path may need to be optimized to take into account the actual situation and constraints, and optimization algorithms such as A* algorithm, Dijkstra algorithm, etc. can be used to further optimize the path. According to the results of the path optimization, the planned path from each vacant area to the area to be installed is output, which can be a path image, in which the planned path is represented by different pixel values or colors, or vector data of the path coordinates is provided.
[0158] See also Figure 4In the second aspect, the present embodiment further provides a photovoltaic module intelligent laying system 1, the system includes a service end 11, an image acquisition unit 12, a first container 13, a second container 14, a conveying track 15 and a transfer vehicle 16, the service end 11 is used to execute the method described in the first aspect; the image acquisition unit 12 establishes a communication connection with the service end 11, and is used to collect a terrain image of the area to be installed; at least one purlin installation station is provided in the first container 13; at least one torque tube installation station is provided in the second container 14; the conveying track 15 is arranged between the first container 13 and the second container 14, and the conveying track 15 is detachably connected to the first container 13 and the second container 14 respectively; the transfer vehicle 16 is connected to the output end of the second container 14, and the transfer vehicle 16 is used to move the pre-installed photovoltaic modules from the pre-installation area to the area to be installed to complete the installation of the photovoltaic modules.
[0159] In this embodiment, the service end 11 is also the system backend server, the image acquisition unit 12 can be a drone, a remote sensing satellite or a camera, etc., the first container 13 and the second container 14 can be container structures integrated on a truck, the first container 13 is provided with a purlin installation station, and the second container 14 is provided with a torque tube installation station, so that after the pre-installation area is determined, the first container 13 and the second container 14 can be directly placed in the pre-installation area by means of a truck, a crane, etc., to complete the rapid layout of the purlin installation station and the torque tube installation station, save the installation time of the station, and improve the installation efficiency of the photovoltaic module. The conveying track 15 is set between the first container 13 and the second container 14, so after the installation of the purlin installation station is completed, the first pre-installed part can be directly moved to the torque tube installation station through the conveying track 15 by using the conveying track 15, so as to improve the transportation efficiency. Finally, a transfer vehicle 16 is provided. The transfer vehicle 16 may be a forklift or a vehicle with a platform on the top. The second pre-installed component is placed on the top or fork arm of the vehicle, and then transported to the installation area according to the planned path by the transfer vehicle 16 to complete the installation.
[0160] In a third aspect, this embodiment further provides a computer-readable storage medium on which computer program instructions are stored. When the computer program instructions are executed by a processor, the method described in the first aspect is implemented.
[0161] See also Figure 5 In a fourth aspect, this embodiment further provides an electronic device 2, comprising a memory 21 and a processor 22, wherein the memory 21 is used to store one or more computer program instructions, wherein the one or more computer program instructions are executed by the processor 22 to implement the method described in the first aspect.
[0162] The storage medium / memory 21 includes but is not limited to: RAM, ROM, disk, tape, CD, flash memory, USB flash drive, mobile hard disk, memory card, memory stick, network server storage, network cloud storage, etc. The processor 22 includes but is not limited to CPU (central processing unit 22), GPU (graphics processor 22), MCU (microprocessor 22), etc.
[0163] See also Figure 6 and Figure 7 , is a specific application example to facilitate understanding of the above steps:
[0164] In view of the low efficiency of the fully manual photovoltaic laying construction process, this embodiment proposes an intelligent laying solution for pre-installation of photovoltaic modules. The solution is divided into two stages. The first stage is that the AI data center uses advanced surveying methods such as drones to quickly obtain ground survey data of the construction area, and uses AI data models to generate construction layout and planning, mainly outputting the precise number and related coordinates of ground pile construction, the number and installation area of equipment required for photovoltaic modules, and the process model of the entire construction. The second stage is the pre-installation production of photovoltaic modules and their docking with ground piles, etc.: an engineered automated production line is used to pre-install photovoltaic modules and structural parts related to brackets such as purlins and torque tubes; the pre-installed component assembly unit is then transported to the site through a vehicle-mounted platform for docking and installation with ground piles.
[0165] In the first stage, the digital command center, as the main communication node, completes data exchange with each sub-link through the Internet of Things system, ensuring that the entire construction process can proceed in an orderly manner. First, the digital center will layout the surface mapping data of the operation area and complete the basic construction of the power station, including the installation area layout of photovoltaic panels and the area layout of pile construction; then the center's model system calculates and outputs the entire engineering process data; finally, the center is responsible for issuing macro instructions for the entire production, and each link of the production completes the analysis of the instructions and arranges specific production operations. During the production process, each production link will promptly gather production data to the center, which will coordinate and make appropriate and necessary operation corrections.
[0166] In the second stage, the material feeding system includes the photovoltaic module automatic feeding system and the torque tube dispatcher. The forklift forks the photovoltaic pallet onto the photovoltaic pallet conveyor, which is responsible for conveying the photovoltaic modules. When the pallet reaches the robotic arm conveyor station, the centering system on the conveyor line completes the centering of the module on the conveyor line, and the robotic arm completes the unstacking of the photovoltaic module from the pallet. The unstacking module completes the splicing of the purlin and the module at the purlin installation station. The spliced module assembly is transported to the photovoltaic module pre-installation production line by the photovoltaic module track conveyor. At the same time, the torque tube automatic distributor automatically transports the torque tube to the photovoltaic module pre-installation production line. The assembly of the module purlin and the torque tube are assembled and installed at the station of the pre-installation production line to form the final torque tube pre-assembled parts of the module. The pre-assembled parts are transferred to the pre-assembled body transfer platform by the photovoltaic module pre-assembled body flipping conveyor track machine, and finally the pre-assembled body is transported to the site by the transfer vehicle to complete the docking with the ground pile. The work stations involved in this process are all set up in containers with a high degree of modularization. The pre-assembled components are carried by a transfer vehicle, which travels to the location to be installed and completes docking with the ground piles or previously installed torque tubes.
[0167] The Internet of Things networking technology is used to realize the communication of control signals, timing, status data, etc. in the production line monitoring, workstation management, material management and other links in the production process. Different from the traditional method, this embodiment proposes a production link for pre-installation of photovoltaic modules. In this installation production line, the automated installation of photovoltaic modules and their fixed bracket-related structural parts (including torque tubes, purlins and their required fixings) is mainly completed, which is completely different from the traditional method of manually installing the bracket at the ground pile first, and then manually installing the photovoltaic modules. In addition, the relevant stations of the installation production line are set in a container, which is not only convenient for transportation, but also reduces the time for equipment installation and debugging, and can also meet the important needs of wind and rain protection and visual fill lighting. Finally, the pre-assembled components are transported to the construction site by the photovoltaic module intelligent transfer vehicle to complete the automated docking with the ground pile, thereby realizing the installation of multiple photovoltaic modules at one time.
[0168] In the above technical scheme, the installation process of photovoltaic modules in the area to be installed is divided into purlin installation and torque tube installation, and the terrain image of the area to be installed is obtained, the open space area around the area to be installed is identified, and the pre-installation process of the photovoltaic modules is set. The purlin installation and torque tube installation of the photovoltaic modules are placed in the open space area. At this time, the installation of ground piles can be completed simultaneously in the area to be installed. After the pre-installation of the photovoltaic modules is completed, the pre-installed photovoltaic modules are directly installed and connected to the ground piles in the area to be installed, which reduces the manpower required to install the photovoltaic modules on the brackets on the construction site and significantly improves the installation efficiency of the photovoltaic modules.
[0169] Finally, it should be noted that although the above embodiments have been described in the specification and drawings of the present invention, the patent protection scope of the present invention cannot be limited thereby. All technical solutions generated by replacing or modifying equivalent structures or equivalent processes based on the essential concept of the present invention and using the contents recorded in the specification and drawings of the present invention, as well as directly or indirectly implementing the technical solutions of the above embodiments in other related technical fields, are included in the patent protection scope of the present invention.
Claims
1. A method for intelligently laying photovoltaic modules. It is characterized in that include: Acquire information of the area to be installed, wherein the information of the area to be installed includes area shape information, area length information, and area width information of the area where the photovoltaic components need to be installed; Acquire photovoltaic module information, where the photovoltaic module information includes size information of a single photovoltaic module that currently needs to be installed; Generate distribution information and assembly information of photovoltaic components in the current area to be installed according to the information of the area to be installed and the information of photovoltaic components, wherein the distribution information includes the arrangement direction, arrangement quantity and total quantity of photovoltaic components, and the assembly information includes the number of workstations and workstation categories required for the current photovoltaic components to complete pre-installation within a preset time period, wherein the workstation categories include purlin installation workstations and torque tube installation workstations; Generate first area information according to the assembly information, the first area information including the area occupied by the workstations under the current number of workstations; Acquire a terrain image of the area to be installed in real time, and extract all vacant area information and traffic path information except the area to be installed from the terrain image, wherein the vacant area information includes size information and geographic coordinate information of the vacant area; Generate a planned path between each of the vacant area and the area to be installed according to the traffic path information; as well as Acquire second area information of the plurality of vacant land areas; Sorting the plurality of planned paths according to a preset sorting method, obtaining second area information of an open space area corresponding to a first planned path, and determining whether the second area information is greater than the first area information; If yes, the current empty area is recorded as a pre-installation area, and assembly configuration information is generated according to the assembly information and the pre-installation area, wherein the assembly configuration information includes a station layout in the pre-installation area; If not, obtaining the second area information of the open space area corresponding to the second planned path, adding the second area information of the second open space area and the second area information of the first open space area to obtain third area information, and determining whether the third area information is greater than the first area information; If the third area information is larger than the first area information, the second-ranked vacant area and the first-ranked vacant area are both recorded as pre-installation areas, and assembly configuration information is generated according to the assembly information and the pre-installation area, wherein the assembly configuration information includes the work station layout within the pre-installation area.
2. The method for intelligently laying photovoltaic modules according to claim 1, It is characterized in that Generating the distribution information and assembly information of the photovoltaic components in the current area to be installed according to the information of the area to be installed and the information of the photovoltaic components includes: Obtaining a preset time segment, where the preset time segment is the installation duration of the photovoltaic module; Generating a purlin installation strategy, a torque tube installation strategy, and a ground pile installation strategy according to the total number of the photovoltaic modules and the preset time period; The purlin installation strategy includes the number of purlin installation stations and a first floor area of a single purlin installation station, the torque tube installation strategy includes the number of torque tube installation stations and a second floor area of a single torque tube installation station, and the ground pile installation strategy includes the number of ground pile installation stations in the current area to be installed and the arrangement of the ground piles; The assembly information is generated according to the purlin installation strategy and the torque tube installation strategy.
3. The intelligent laying method of photovoltaic modules according to claim 2, It is characterized in that Generating a purlin installation strategy, a torque tube installation strategy, and a ground pile installation strategy according to the total number of photovoltaic modules and the preset time period includes: Obtaining the total number of photovoltaic modules, and generating the total number of purlins, the total number of torque tubes, and the total number of ground piles according to the total number of photovoltaic modules; Obtaining a first installation time corresponding to installing the required purlins on a single photovoltaic module, and recording the photovoltaic module after the required purlins are installed on the single photovoltaic module as a first pre-installed component; Obtain a second installation time corresponding to the installation of the required torque tube on a single first pre-installed component, and record the first pre-installed component after the single installation of the required torque tube as the second pre-installed component; Obtaining a third installation time corresponding to the installation of a single second pre-installed component on a ground pile; The first installation time, the second installation time and the third installation time are added together to obtain a total installation time for completing the installation of a single photovoltaic module in the area to be installed, and the total installation time is recorded as a fourth installation time; Performing a division operation on the preset time segment and the fourth installation time to obtain the number of photovoltaic modules installed at a single purlin installation station, a single torque tube installation station, and a single ground pile installation station, which is recorded as a first installation number; Obtaining a first installation multiple of the photovoltaic components according to the total number of photovoltaic components and the first installation number, and obtaining a second installation multiple between the first installation time and the second installation time; The number of purlin installation stations, the number of torque tube installation stations and the number of ground pile installation stations are generated according to the first installation multiple and the second installation multiple.
4. The method for intelligently laying photovoltaic modules according to claim 3, It is characterized in that Acquire a terrain image of the area to be installed in real time, and extract all vacant area information and traffic path information except the area to be installed from the terrain image; Taking the area to be installed as the center and a preset size as the radius, obtaining the size information of the terrain image corresponding to the area to be installed; Controlling an image acquisition unit to acquire a plurality of initial images according to size information of the terrain image; Preprocessing a plurality of initial images, and fusing the preprocessed initial images to form the terrain image, wherein the preprocessing includes image denoising, image enhancement, and image registration; Inputting the terrain image into a YOLO algorithm model, wherein an output result of the YOLO algorithm model is an object feature set; The object feature set is classified to obtain the open space area information and the traffic path information.
5. The intelligent laying method of photovoltaic modules according to claim 4, It is characterized in that Generating a planned path between each of the vacant area and the area to be installed according to the traffic path information includes: The obtaining of geographic coordinate information of the vacant area and recording the information as first geographic coordinate information; Obtaining geographic coordinate information of the area to be installed, and recording it as second geographic coordinate information; Inputting the first geographic coordinate information, the second geographic coordinate information and the traffic path information into a trained neural network model, wherein an output result of the neural network model is an initial planned path between the first geographic coordinate and the second geographic coordinate; The initial planned path is input into the A* algorithm model for path optimization. The output result of the A* algorithm model is the optimized initial planned path. The optimized initial planned path is recorded as the planned path between the current open space area and the area to be installed.
6. The intelligent laying method of photovoltaic modules according to claim 5, It is characterized in that The neural network model is trained in the following way: Build a basic neural network model; Inputting sample training data into the basic neural network model, the sample training data being sample images and sample traffic path information in a sample database, the sample images including a sample to-be-installed area and a sample vacant area; The basic neural network model is repeatedly trained until the accuracy of the basic neural network model reaches a preset threshold, and the basic neural network model whose accuracy reaches the preset threshold is recorded as a trained neural network model.
7. The method for intelligently laying photovoltaic modules according to claim 6, It is characterized in that Assembly configuration information is generated according to the assembly information and the pre-installation area, wherein the assembly configuration information includes a station layout in the pre-installation area including: Grouping the number of the purlin installation stations and the number of the torque tube installation stations according to the second installation multiple to obtain a plurality of photovoltaic module pre-installation station groups; Obtaining the number of the pre-installation areas, and if the number of the pre-installation areas is greater than 2, obtaining second area information of each of the pre-installation areas; Calculate the multiple relationship between each of the second area information and a single photovoltaic component pre-installation station group, and record it as a third installation multiple; Generating a station layout of the photovoltaic component pre-installation station group in the current pre-installation area according to the third installation multiple; The assembly configuration information is generated according to the plurality of workstation layouts.
8. An intelligent photovoltaic module laying system, It is characterized in that The system comprises: A server, the server being used to execute the method according to any one of claims 1 to 7; An image acquisition unit, establishing a communication connection with the server, for acquiring a terrain image of the area to be installed; A first container, wherein at least one purlin installation station is provided in the first container; a second container, wherein at least one torque tube installation station is provided in the second container; A conveying track is arranged between the first container and the second container, and the conveying track is detachably connected to the first container and the second container respectively; A transfer vehicle is connected to the output end of the second container, and is used to move the pre-installed photovoltaic components from the pre-installation area to the area to be installed to complete the installation of the photovoltaic components.
9. A computer-readable storage medium having computer program instructions stored thereon, It is characterized in that The computer program instructions implement the method according to any one of claims 1 to 7 when executed by a processor.
10. An electronic device comprising a memory and a processor, It is characterized in that The memory is used to store one or more computer program instructions, wherein the one or more computer program instructions are executed by the processor to implement the method according to any one of claims 1 to 7.
Citation Information
Cited By
Photovoltaic project construction progress identification method based on unmanned aerial vehicle image and neural network
CN119027069A
Photovoltaic project construction progress recognition method based on UAV images and neural network
CN119027069B
Fixed photovoltaic efficient installation method and photovoltaic support
CN119496446A
Device, system and method for butt joint installation of photovoltaic modules
CN119658327A