By coupling the hydrodynamic model and radar rainfall data, a comprehensive urban watershed drainage model is constructed, which solves the accuracy and computational efficiency problems of waterlogging risk prediction under complex heavy rains in the existing technology, and achieves rapid and accurate early warning of waterlogging risk at the scale of large cities.
Patent Information
- Application Number
- CN202410856063.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-10-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing urban waterlogging prediction and early warning technology is difficult to accurately predict waterlogging risks when dealing with complex heavy rains. The calculation efficiency is low, it is difficult to achieve real-time simulation on a large city scale, and it fails to fully consider rain patterns and rainfall spatial distribution characteristics.
A waterlogging risk early warning method for the urban comprehensive watershed drainage area based on the hydrodynamic model is adopted. By coupling the one-dimensional river hydrodynamic model, the urban watershed hydrological model, the one-dimensional pipeline model and the two-dimensional surface model, an urban comprehensive watershed drainage model is constructed, combined with radar rainfall Forecast data and dynamically extract comprehensive indicators of rainfall characteristics to achieve rapid and accurate early warning of flood risks at the scale of large cities.
It improves the accuracy and precision of waterlogging risk identification, realizes rapid identification and early warning of waterlogging risk on a large city scale, can improve the real-time and repeatability of early warning while retaining the refinement of simulation results, and is suitable for a variety of complex rainfall scenarios. .
Smart Images

Figure CN118865633A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of urban waterlogging monitoring, and in particular to a waterlogging risk early warning method for urban-scale drainage areas based on a hydrodynamic model. Background Art
[0002] After a long period of development, urban waterlogging prediction and early warning technology has gradually developed from the original single surface water flow simulation, one-dimensional underground pipe network model for pipe network overflow and surface runoff simulation, etc., to an urban comprehensive watershed drainage model that comprehensively considers the coupling of one-dimensional pipelines, urban watershed hydrology, river networks and two-dimensional surfaces, and achieves a fine description of pipeline water flow and surface water flow, and can achieve a fine simulation of ground waterlogging area and depth. However, the direct external factor driving urban waterlogging is also the most important factor - the treatment of heavy rain is very rough, using a single rain gauge as an input condition, without considering the impact of rainfall characteristics such as rain type and rainfall duration on waterlogging risk, and the fine scale of rainfall input does not match the fine scale of the hydrodynamic model.
[0003] Complex rainfall patterns and spatial distribution characteristics will significantly affect urban hydrological and hydrodynamic processes, and thus affect the severity of urban waterlogging disasters and their regional differences, easily causing serious waterlogging disasters in local areas. The single rainfall input in traditional urban waterlogging prediction methods is usually difficult to accurately predict the waterlogging risk under complex rainstorm characteristics. Therefore, more refined rainfall data and more complex model methods are needed to simulate urban waterlogging.
[0004] The hydrological and hydrodynamic methods currently used in urban waterlogging prediction and warning technologies require high-precision data and clear physical mechanisms, involve a large number of detailed simulations, and are computationally complex, especially for two-dimensional surface models. The equation-solving algorithm and the number of grids will seriously affect the computational efficiency. The huge amount of computation required for urban refined flood models makes it difficult to achieve real-time simulation calculations for waterlogging warnings at the scale of large cities, and cannot meet the needs of real-time waterlogging warnings.
[0005] CN108182543A discloses a refined grid waterlogging forecasting method, comprising the following steps: (1) taking the pipe network drainage partition as the unit and the underlying surface type as the basis for gridding the urban area; (2) establishing an SCS model if there is a river basin in the grid area, and establishing an SWMM model if there is no river basin in the grid area; (3) using the SCS model and the SWMM model to respectively calculate the grid area runoff and the overflow of the overflow node under the current urban heavy rain, and inputting the overflow data as a parameter into the LISFLOOD-FP model to simulate the urban flooding range, water depth and flooding process.
[0006] This invention divides the urban area into multiple grids, selects different models for calculation, and improves the accuracy of waterlogging forecast. However, this method has not yet involved the processing of complex rainfall, including the embodiment of characteristics such as rain type and rainfall spatial distribution in the model, and is difficult to apply to waterlogging forecasts under various complex rainfall situations. In addition, this method is highly dependent on high-resolution terrain, land use, river vector and other data, and has high requirements for the spatialization of the CN (Curve Number) parameters in the SCS model in urban areas, which affects the accuracy of the forecast. Secondly, when processing large-scale urban data, refined grid division and multi-model calculations will require greater computing resources and affect the effectiveness of the forecast. Therefore, the real-time performance of this method is not enough in urban-scale forecasts. Summary of the invention
[0007] In order to solve the problem of low accuracy and precision in identifying urban waterlogging risks at the scale of large cities, the present invention provides an urban-scale drainage area waterlogging risk early warning method based on a hydrodynamic model. The method can achieve rapid and accurate early warning of urban waterlogging risks without sacrificing the simulation accuracy of the physical processes inside the model and the prediction accuracy of the results.
[0008] To achieve the above object, the technical solution adopted by the present invention is:
[0009] A method for early warning of waterlogging risk in urban-scale drainage areas based on a hydrodynamic model, comprising the following steps:
[0010] S1, the city's one-dimensional river hydrodynamic model, urban watershed hydrological model, one-dimensional pipeline model and two-dimensional surface model are coupled to construct an urban comprehensive watershed drainage model, the model parameters are verified and calibrated, and early warning zones are delineated;
[0011] On the basis of water system drainage zoning, for urban built-up areas, adjacent areas within the same water system drainage zone with the same municipal rainwater drainage system and administrative division are divided into the same early warning zone;
[0012] S2, conduct sensitivity experiments on rainstorm scenarios and urban drainage and flood prevention capabilities for the urban integrated watershed drainage model, build a waterlogging risk assessment system for waterlogging depth and waterlogging time, analyze the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and obtain rainfall characteristic comprehensive indicators for each warning zone;
[0013] S3, based on the grid data of radar rainfall prediction, establish the mapping relationship between the forecast surface rainfall and the warning zone, dynamically extract the comprehensive index of rainfall characteristics corresponding to the warning zone, and realize the transformation from grid rainfall to comprehensive index of rainfall characteristics;
[0014] S4, coupling the above three steps, constructs a rapid early warning model for urban-scale waterlogging risk, and implements dynamic waterlogging risk warning issuance for each warning zone.
[0015] The present invention constructs a refined urban comprehensive watershed drainage model, couples a one-dimensional river hydrodynamic model, an urban watershed hydrological model, a one-dimensional pipeline model and a two-dimensional surface model to construct an urban comprehensive watershed drainage model, performs terrain correction in key areas, and constructs a set of comprehensive indicator systems for waterlogging risk including rainfall type, rainfall amount and duration based on the sensitivity test results of rainfall scenarios with rainfall characteristics such as rainfall type, rainfall amount and rainfall duration in the urban comprehensive watershed drainage model. Finally, an early warning system that couples radar-estimated grid rainfall with early warning zone rainfall and early warning zone comprehensive indicators is developed to achieve rapid identification of urban waterlogging risks and dynamic issuance of early warnings.
[0016] After the sensitivity analysis of the urban comprehensive watershed drainage model, the present invention corresponds the rainfall characteristics comprehensive index system to the waterlogging risk level, which has the advantages of high accuracy, comprehensive consideration, strong predictability and good repeatability. The waterlogging simulation model can simulate various hydrological processes such as hydrological cycle, surface runoff, groundwater flow, etc., and can conduct a more comprehensive and accurate analysis of waterlogging risks, avoiding the shortcomings of analysis based on experience or simplified models. The model also takes into account multiple factors such as topography, geomorphology, hydrology, geology and rainfall, and the evaluation results are more comprehensive and systematic;
[0017] The model of the present invention can simulate and predict future rainwater runoff, which is conducive to formulating countermeasures in advance. The parameters in the model can be updated and optimized according to actual new data to obtain corresponding reliable indicator thresholds, which has strong repeatability and is convenient for long-term use.
[0018] Preferably, in S1, the present invention uses Infoworks ICM watershed drainage software to couple a one-dimensional river hydrodynamic model, an urban watershed hydrological model, a one-dimensional pipeline model and a two-dimensional surface model to construct an urban comprehensive watershed drainage model.
[0019] Preferably, the one-dimensional river hydrodynamic model is to establish a model for the main river and important tributaries to reflect the dynamic changes of the water level boundary at the end of the pipe network and the impact on the pipe network system, and consider the water section and historical measurement data as the basis for analysis to build the model.
[0020] Preferably, the urban watershed hydrological model includes watershed rainwater collection, rainfall runoff generation and confluence models;
[0021] When the catchment area of the basin is 50km 2 The instantaneous unit line method is used above, and the catchment area of the basin is less than 50km 2 Adopt the inference formula method;
[0022] The rainfall runoff is divided into non-built-up areas and built-up areas. The non-built-up areas use the front-loss and back-loss method, and the built-up areas use the fixed runoff coefficient method.
[0023] Preferably, the front-loss and back-loss method is specifically as follows: net rain after deducting the front-loss from the rainfall begins to participate in surface runoff, pipe network runoff and river runoff after it is generated. The front-loss includes filling, vegetation interception, evaporation, infiltration, etc.
[0024] Preferably, the infiltration is calculated using the Horton formula, the Green-Ampter formula or the SCS CN (Curve Number) method, and the Horton formula is further preferred, which can be specifically expressed as follows:
[0025] f(t)=fc+(f0-fc)e-βt
[0026] Where f(t) is the infiltration rate at the current moment (mm / h); f0 is the initial infiltration rate (mm / h); fc is the stable infiltration rate (mm / h); β is the Horton attenuation coefficient, which reflects the decreasing characteristics of soil infiltration rate; t is time.
[0027] In the fixed runoff coefficient method, the underlying surface is divided into five categories: green space, roof, water body, road, and other land, and the runoff coefficient of each built-up area is between 0.6 and 0.7.
[0028] The confluence model adopts the SWMM nonlinear reservoir model. When optimizing the confluence, the sub-region division should be taken into consideration, and each sub-basin is considered as shown in the figure, and each confluence sub-region is divided into a permeable area and an impermeable area, and the impermeable area is further divided into an impermeable area without depressions and an impermeable area with depressions.
[0029] Preferably, the one-dimensional pipeline model mainly receives surface runoff, which is then modeled by the rainwater network after passing through the pipe network. The drainage network model includes underground pipelines, inspection wells, and drainage outlets.
[0030] Preferably, a high-precision digital elevation model is used in the two-dimensional surface model for data extraction, and the two-dimensional grids of potential flood-prone areas are encrypted, mainly including underpasses of roads, local low-lying areas, etc. A larger grid density is used for areas with higher terrain and no flooding in previous years.
[0031] Preferably, after coupling in S1, the steps are as follows: obtaining the medium waterlogging risk points of the model after coupling, and checking, correcting and supplementing the waterlogging risk points of the urban integrated watershed drainage model according to historical waterlogging data.
[0032] The present invention adopts the waterlogging event list of the urban management department in the past three years, and uses historical waterlogging data in areas where the data is semi-missing or missing to correct and supplement the waterlogging risk points in the model, thereby expanding the forecast area and improving the accuracy of the model.
[0033] Preferably, the parameter verification and calibration of the model in S1 can be based on the relevant regulations of the local city, such as the verification and calibration of the parameters in the model according to the "Procedures for the Construction and Application of Mathematical Models for Urban Waterlogging Prevention and Control Systems", including the use of multiple groups of measured long-duration rainstorms to test the accuracy of the model, with the help of measured hydrological stations, the accuracy assessment indicators include peak water level, peak time and flow (water level) process; the model is calibrated again with the help of historical data such as historical road section waterlogging records.
[0034] Preferably, in S1, the forecast area is divided into early warning zones; the early warning zones are used as the smallest units of early warning objects;
[0035] The specific steps of early warning zoning include: dividing water system zones, dividing municipal rainwater drainage systems, and making corrections based on other factors such as topography and administrative boundaries.
[0036] The early warning zoning is based on the water system drainage zoning. For the urban built-up area, adjacent areas within the same water system drainage zoning, municipal rainwater discharge system and administrative divisions are divided into the same early warning zone.
[0037] Preferably, when dividing the warning zones, factors such as the topography, water system, hydrogeology, water level of the discharge area and administrative divisions of the drainage area are taken into consideration, and an area is divided into several warning zones. The division can be made in reference to the relevant drainage and flood control plans that have been issued locally.
[0038] Preferably, when dividing the warning zones, the warning zones that are too large are divided, and the warning zones that are too small are merged to optimize the warning zone division; this can improve the operability of the warning and the sensitivity of the response analysis.
[0039] Preferably, in S2, the present invention constructs a waterlogging risk assessment system by conducting sensitivity tests on designed rainstorm scenarios and urban drainage and waterlogging prevention capabilities, analyzes the correlation characteristics of rainfall, rainfall type, rainfall duration and waterlogging risk level, and obtains comprehensive indicators of rainfall characteristics for each warning zone.
[0040] S2 specifically includes the following steps: designing sensitivity tests on urban integrated watershed drainage models for waterlogging simulation under different rainfall scenarios, constructing a waterlogging risk assessment system for waterlogging depth and duration, analyzing the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and using the values of rainfall characteristic comprehensive indicators of each warning zone that meet the judgment criteria for waterlogging warning in the simulation results of the urban integrated watershed drainage model as the thresholds of rainfall characteristic comprehensive indicators for each risk level.
[0041] The classification criteria of the warning levels in the waterlogging risk assessment system include waterlogging depth, waterlogging time and waterlogging area;
[0042] The specific standards for the classification of waterlogging risk warning levels include: classification based on the depth of water accumulation of 15 cm. When the depth of water accumulation is 15 cm, the water will not submerge the road curbs and will not affect the passage of pedestrians and motor vehicles, and it is set as a risk-free zone;
[0043] When the depth of water accumulation is 15cm<h≤30cm, it will cause minor disaster losses and is set as a low-risk area;
[0044] When the depth of water accumulation is 30cm<h≤50cm, it will cause a certain degree of disaster losses and is set as a medium risk area;
[0045] When the water depth h>50cm, it will cause a greater degree of disaster losses and is set as a high-risk area;
[0046] Preferably, the indicators included in the comprehensive rainfall characteristic index are rainfall recurrence period, rainfall duration and rainfall type.
[0047] Preferably, a quantitative study is conducted on the comprehensive indicators of rainfall characteristics of waterlogging warning levels. Based on the above-mentioned waterlogging risk level classification standards, a model simulation method is used to determine the numerical values or classifications of waterlogging warning rainfall, rainfall type, and rainfall duration for each warning zone. It is worth noting that the simulation results are easily affected by factors such as terrain accuracy, pipe network defects, and underlying surface. Before promotion and application, different rainfall scenarios need to be designed to gradually correct the thresholds of the comprehensive rainfall indicators for waterlogging warnings.
[0048] Preferably, in S3, based on the grid data of radar rainfall prediction, establishing a mapping relationship between the forecast surface rainfall and the warning partition specifically includes the steps of: determining the latitude and longitude information of the radar forecast grid points; matching the grid points with the warning partitions, establishing a mapping relationship between the forecast surface rainfall and the warning partitions, and if any grid point cannot be matched within the warning partition, matching the grid point closest to the center point of the partition.
[0049] Preferably, the dynamic extraction of the comprehensive index of rainfall characteristics of the warning zone in S3 specifically includes: extracting the rainfall process line L of the warning zone from all grid forecasts under the same forecast time limit at the target time, obtaining the index of the accumulated rainfall, rainfall duration and rainfall type during the rainfall process according to the rainfall process line L, and obtaining the comprehensive index of rainfall characteristics of each warning zone;
[0050] Preferably, the above three steps are coupled in S4, and a rapid early warning model of waterlogging risk level is developed using Python program to realize dynamic waterlogging risk early warning release for each early warning zone.
[0051] Preferably, in order to address the single rainfall input problem that is prevalent in current urban waterlogging risk prediction and early warning technologies, the rainfall return period and rainfall duration are extracted from the predicted rainfall process, and a more refined description of the rainfall input problem is adopted for the rainfall type to solve the rainfall input and its coupling with the model and improve the prediction accuracy.
[0052] Preferably, the process of constructing a rapid early warning model comprises the steps of:
[0053] (1) traversing and determining the forecast files of all grids under the same forecast time limit at the target time; the forecast time limit ranges from 5 minutes to 180 minutes;
[0054] (2) For the forecast file under the forecast time t, the area rainfall is corrected by using the area weighting method based on the grid data of the ith warning zone to obtain the corrected area rainfall;
[0055] (3) Traverse the forecast files of all sub-areas under all forecast time periods, and calculate the rainfall process line L of each sub-area according to the surface rainfall data of each sub-area according to the forecast time period;
[0056] (4) The accumulated rainfall, rainfall duration, and rainfall type during the rainfall process are determined based on the rainfall process line L, and the actual surface rainfall threshold is obtained to construct a rapid early warning model for urban-scale waterlogging risk.
[0057] Furthermore, the radar forecast grids are set with a distribution of 0.01*0.01°, and the extrapolated forecast products are used as the basis for short-term warning of urban waterlogging levels. The surface rainfall in the radar network grid corresponding to each warning zone is calculated, and the surface rainfall time series is organized into a rainfall process line according to the forecast time from small to large (15min~180min). The rain type distribution in each warning area is determined, and the actual surface rainfall threshold of the corresponding duration and rain type is extracted.
[0058] Further preferably, the rainfall type is judged by the ratio of the time when the rainfall peak value is located to the entire rainfall duration, including the front type, the center type and the rear peak type; the front type means that the rainfall peak value is at <1 / 3 of the entire rainfall duration, the center type is at 1 / 3 to 2 / 3, and the rear peak type is at >2 / 3; the duration includes 30min, 60min and 120min, and the actual surface rainfall threshold of the i-th warning zone is obtained;
[0059] Preferably, the correction method for correcting the area rainfall using the area weighted method is specifically expressed as:
[0060] Pr=∑Po,i*Ai / ∑Ai
[0061] Where Po represents the observed precipitation, Pr represents the corrected surface rainfall, and Ai represents the area represented by the grid point.
[0062] The specific steps for implementing dynamic waterlogging risk warning for each warning zone in S4 include:
[0063] The actual rainfall threshold of the ith warning zone is compared with the threshold indicators of different risk levels. When the actual rainfall threshold is less than the threshold, there is no waterlogging risk; if it is greater, the waterlogging risk level is determined.
[0064] Repeat the above steps to traverse all warning zones to obtain the risk level of each warning zone;
[0065] Waterlogging warnings are issued based on time, drainage divisions, rainfall, and waterlogging levels, and forecast information for each hour is released in real time.
[0066] Compared with the prior art, the present invention has the following beneficial effects:
[0067] (1) The present invention creatively applies the urban comprehensive watershed drainage model, constructs and extracts the rainfall characteristic comprehensive index corresponding to the waterlogging warning level of the warning zone through a static model, and constructs a dynamic waterlogging risk warning model through a program based on the comprehensive index. This achieves a solution that does not sacrifice simulation accuracy and precision, and solves the problem of rapid identification and prediction of waterlogging risks at the scale of large cities while retaining the refinement of simulation results.
[0068] (2) Based on the sensitivity test research of designed rainfall scenarios with different rainfall amounts, rainfall types, rainfall durations, etc. in the urban integrated watershed drainage model, the present invention constructs a comprehensive indicator system integrating rainfall characteristics such as rainfall amounts, rainfall types, rainfall durations, etc., solves the problem of imprecise rainfall characteristic characterization, and improves the accuracy of urban waterlogging risk prediction.
[0069] (3) The present invention realizes the coupling of grid rainfall forecast products and waterlogging warning models based on warning zones, and realizes the dynamic waterlogging warning release for each warning zone at the scale of a large city, which can be well integrated with the emergency management process on the urban management side. BRIEF DESCRIPTION OF THE DRAWINGS
[0070] Figure 1 It is a schematic flow chart of the method for early warning of waterlogging risk in urban-scale drainage areas based on a hydrodynamic model of the present invention.
[0071] Figure 2 This is a generalized diagram of the rainwater pipe network model of a certain city in the embodiment.
[0072] Figure 3 This is a generalized diagram of the one-dimensional river hydrodynamic model of a certain city in the embodiment.
[0073] Figure 4 A schematic diagram of a technical route for constructing a threshold indicator system for different risk levels in an urban area of a certain city in the embodiment.
[0074] Figure 5 Schematic diagram of early warning zones in an urban area of a city in the embodiment.
[0075] Figure 6 It is a schematic diagram of the process of issuing real-time waterlogging warning in the embodiment.
[0076] Figure 7 Schematic diagram of the actual surface rainfall threshold extraction process in the embodiment.
[0077] Figure 8 It is a schematic diagram of the process of issuing real-time waterlogging warning in the embodiment. DETAILED DESCRIPTION
[0078] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with embodiment. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Those skilled in the art can make modifications or equivalent substitutions based on the understanding of the technical scheme of the present invention without departing from the spirit and scope of the technical scheme of the present invention, and all should be included in the protection scope of the present invention.
[0079] Example
[0080] Carry out waterlogging risk warning for a certain city, such as Figure 1 As shown, the method specifically includes the following steps:
[0081] S1, the city's one-dimensional river hydrodynamic model, urban watershed hydrological model, one-dimensional pipeline model and two-dimensional surface model are coupled to construct an urban comprehensive watershed drainage model, the model parameters are verified and calibrated, and early warning zones are delineated;
[0082] On the basis of water system drainage zoning, for urban built-up areas, adjacent areas within the same water system drainage zone with the same municipal rainwater drainage system and administrative division are divided into the same early warning zone;
[0083] The present invention uses Infoworks ICM basin drainage software to couple a one-dimensional river hydrodynamic model, an urban basin hydrological model, a one-dimensional pipeline model and a two-dimensional surface model to construct an urban comprehensive basin drainage model. The software can perform a complete simulation of the urban rainwater circulation system. It can not only simulate the one-dimensional pipe network, but also simulate the water exchange between the pipe network and the two-dimensional surface and river channels. It can simulate the water interaction between the drainage pipe network and the surface and river channels and other receiving water bodies in a relatively realistic manner. It has a stable and powerful drainage system hydraulic calculation engine, rich drainage model building tools, flexible hydraulic status analysis tools and powerful model management functions. The resources used for modeling include pipe networks, rivers, underlying surfaces, terrain, etc.;
[0084] S1-1, build a one-dimensional river hydrodynamic model: the data of the one-dimensional river hydrodynamic model include the river section, river centerline, water surface rate, etc. in the urban area; use the basic data of the river to build the river model, use the cross-section of the water survey results and historical measurement data as the basis for analysis, import them into the model to build a one-dimensional river hydrodynamic model, and the model is generalized as follows Figure 3 shown.
[0085] S1-2, constructing an urban watershed hydrological model: The data of the urban watershed hydrological model include buildings, water systems, green spaces, etc. The urban watershed hydrological model specifically includes watershed rainwater collection, rainfall runoff generation and confluence models;
[0086] When the catchment area of the basin is 50km 2 The instantaneous unit line method is used above, and the catchment area of the basin is less than 50km 2 Adopt the inference formula method;
[0087] The rainfall runoff is divided into non-built-up areas and built-up areas. The non-built-up areas adopt the front-loss and back-loss method, and the built-up areas adopt the fixed runoff coefficient method. In this embodiment, the front-loss and back-loss method is specifically: the net rain after deducting the front-loss from the rainfall begins to participate in surface runoff, pipe network runoff and river runoff after it is generated. The front-loss includes filling, vegetation interception, evaporation, infiltration, etc.
[0088] The infiltration is calculated by the Horton formula, the Green-Ampter formula or the SCS CN (Curve Number) method, and the Horton formula is further preferred, which can be specifically expressed as follows:
[0089] f(t)=fc+(f0-fc)e-βt
[0090] Where f(t) is the infiltration rate at the current moment (mm / h); f0 is the initial infiltration rate (mm / h); fc is the stable infiltration rate (mm / h); β is the Horton attenuation coefficient, which reflects the decreasing characteristics of soil infiltration rate; t is time.
[0091] In the fixed runoff coefficient method for built-up areas, the underlying surface is divided into five categories: green space, roof, water body, road, and other land. The runoff coefficient of each built-up area is between 0.6 and 0.7.
[0092] The confluence model adopts the SWMM nonlinear reservoir model. When confluence is performed, the sub-area division should be considered, and each sub-basin is considered as shown in the figure, and each confluence sub-area is divided into a permeable area and an impermeable area, and the impermeable area is further divided into an impermeable area without depressions and an impermeable area with depressions.
[0093] S1-3, build a one-dimensional pipeline model: The one-dimensional pipeline model data includes the drainage pipes (upstream and downstream elevations, pipe diameters), drainage channels (upstream and downstream elevations, channel width and height dimensions), drainage inspection wells (ground elevation, well bottom elevation), and water outlets (ground elevation, well bottom elevation) obtained through pipeline surveys. The generalized diagram of the rainwater pipe network model in this urban area is shown in the figure below: Figure 2 As shown;
[0094] S1-4, constructing a two-dimensional surface model: The two-dimensional surface model uses a high-precision digital elevation model to extract data, and encrypts the two-dimensional grids of potential flood-prone areas, mainly including road underpasses, local low-lying areas, etc. A smaller grid density is used for areas with higher terrain and no flooding in previous years.
[0095] The two-dimensional surface model attribute assignment mainly includes: determining the grid unit's elevation, roughness, correction rate and other parameters. The grid elevation is mainly extracted from high-precision digital terrain DEM (accuracy 5m*5m) data. The measured elevation points are extracted using a 1:500 topographic map in local flood-prone areas, and the average grid elevation in each grid is taken as the elevation of the grid center point. According to different types such as green space, urban living agglomeration area, industrial area, etc., the grid is assigned a corresponding roughness;
[0096] S1-5, the models constructed by S1-1 to S1-4 are coupled and simulated on the ICM platform to construct an urban comprehensive watershed drainage model; this model comprehensively considers factors such as the underlying surface, rainwater pipe network, river channel, topography, etc., and manually verifies the accuracy of factors such as the existing rainwater pipes, river sections, and topography.
[0097] S1-6, parameter verification and calibration of the urban integrated watershed drainage model;
[0098] According to the "Procedures for the Construction and Application of Mathematical Models for Urban Waterlogging Control Systems", after the modeling is completed, the simulation results of the model need to be calibrated and verified to ensure the rationality of the model parameters. The calibration and verification process includes the use of multiple groups of measured rainstorms to test the accuracy of the model. With the help of measured hydrological stations, the accuracy assessment indicators include peak water level, peak time and flow (water level) process; the model is calibrated again with the help of historical data such as historical road section waterlogging records.
[0099] The model rainfall flow process is obtained based on the measured rainfall stations. Based on the comparison between the measured river water level within the model range and the model calculated water level, and considering the lack of flow and liquid level measurement data in the current stormwater pipes, the accuracy of the coupling model is mainly calibrated and verified by comparing the actual survey of flood-prone points with the simulated inundation map, so that the simulation results have a high degree of credibility.
[0100] The urban management department’s waterlogging event lists for the past three years are used, and historical waterlogging data is used in areas where data is semi-missing or missing to correct and supplement the waterlogging risk points in the model, thereby expanding the forecast area and improving the accuracy of the model.
[0101] S1-7, taking into account the topography, pipe network, water system and other factors, different urban waterlogging warning zones are divided, with the warning zone being the smallest unit of the warning object; the warning zones specifically include the following steps: dividing the water system zones, dividing the municipal rainwater drainage system, and making corrections based on other factors such as topography and administrative boundaries.
[0102] First, the early warning zoning is based on the water system drainage zoning. For the urban built-up area, adjacent areas with the same water system drainage zoning, municipal rainwater discharge system and administrative division are divided into the same early warning zone.
[0103] Secondly, when dividing the warning zones, the drainage areas that are too large should be divided, and the drainage areas that are too small should be merged to optimize the warning zones to improve the operability of the warning and the sensitivity of the response analysis.
[0104] Finally, when dividing the early warning zones, factors such as the topography, water system, hydrogeology, water level of the drainage area and administrative divisions of the drainage area are considered to divide an area into several drainage areas with different drainage methods. This part can be divided according to the relevant drainage and flood prevention plans that have been issued locally. Figure 5 shown.
[0105] S2, conduct sensitivity experiments on rainstorm scenarios and urban drainage and flood prevention capabilities for the urban integrated watershed drainage model, build a waterlogging risk assessment system for waterlogging depth and waterlogging time, analyze the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and obtain rainfall characteristic comprehensive indicators for each warning zone;
[0106] Specific steps include: designing different rainfall scenarios to conduct sensitivity tests on urban integrated watershed drainage models to simulate urban waterlogging, building an urban waterlogging risk assessment system for waterlogging depth and duration, analyzing the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and using the value of the rainfall characteristic comprehensive indicators of each warning zone that reaches the judgment standard for waterlogging warning in the simulation results of the urban integrated watershed drainage model as the threshold of the rainfall characteristic comprehensive indicator for each risk level.
[0107] The specific standards for the classification of waterlogging risk warning levels are shown in Table 1, including: according to the water depth of 15 cm, when the water depth is 15 m, the water will not submerge the road curbs and will not affect the passage of pedestrians and motor vehicles, and it is set as a risk-free area;
[0108] When the depth of water accumulation is 15cm<h≤30cm, it will cause minor disaster losses and is set as a low-risk area;
[0109] When the depth of water accumulation is 30cm<h≤50cm, it will cause a certain degree of disaster losses and is set as a medium risk area;
[0110] When the water depth h>50cm, it will cause a greater degree of disaster losses and is set as a high-risk area;
[0111] Table 1 Classification standards for waterlogging risk levels
[0112]
[0113] Note: 1. Cited from the Technical Standard for Urban Waterlogging Prevention and Control (DB33 / T1109-2020);
[0114] 2. The control requirement for water depth is that the water depth of at least one lane in each direction of urban trunk roads shall not exceed the limit value;
[0115] 3. The values in brackets are the requirements for controlling the depth of water accumulation in areas where the surface water velocity exceeds 2m / s;
[0116] 4. The control requirements for water accumulation time and water accumulation depth must be met at the same time.
[0117] The indicators included in the comprehensive rainfall characteristic index are rainfall recurrence period, rainfall duration and rainfall type.
[0118] Design multiple precipitation scenarios under different waterlogging risk levels, and use the fixed and revised drainage model to conduct sensitivity experiments on all warning zones one by one; determine the numerical values or classifications of rainfall, rainfall type, and rainfall duration corresponding to different waterlogging risk levels for each warning zone based on the experimental results, and construct a comprehensive indicator system of rainfall characteristics corresponding to different waterlogging risk levels for each warning zone. The technical roadmap for constructing threshold indicators is as follows: Figure 4 shown.
[0119] It is worth noting that the simulation results are easily affected by factors such as terrain accuracy, pipeline network defects, and underlying surface. Before promotion and application, different rainfall scenarios need to be designed to gradually revise the threshold of the comprehensive rainfall index for waterlogging warning.
[0120] S3, in view of the common problem of single rainfall input in the current urban waterlogging risk prediction and early warning technology, refined grid rainfall is used as the basic forecast for waterlogging disaster risk warning in the present invention. Based on the 1*1 km grid rainfall forecast, a mapping relationship between the forecast surface rainfall and the early warning zone is established, and the rainfall characteristics such as rainfall, rainfall duration, rainfall type, etc. of the corresponding early warning zone are dynamically extracted to realize the transformation of grid rainfall into comprehensive indicators of rainfall characteristics.
[0121] S3-1, establish a mapping relationship between grid data and warning partitions, specifically including the following steps: radar forecast grids are set at a distribution of 0.01*0.01° to determine the longitude and latitude information of radar forecast grids; grids are matched with warning partitions. If no grid points can be matched within the warning partition, then the grid points closest to the center of the partition are matched.
[0122] S3-2, specific steps for dynamically extracting rainfall characteristics such as rainfall, rainfall duration, rainfall type, etc. of the corresponding warning zone: Based on the mapping relationship between grid data and warning zones, extract the surface rainfall in the grid forecast corresponding to each warning zone by calculation, and combine the warning zone surface rainfall into a rainfall process line L according to the forecast time; determine the accumulated rainfall, rainfall duration and rainfall type during the rainfall process according to the rainfall process line L; realize the transformation of grid rainfall into comprehensive indicators of rainfall characteristics.
[0123] S4, coupling the above three steps, constructing a rapid early warning model for urban-scale waterlogging risk, and realizing the dynamic waterlogging risk warning for each warning zone. The specific process is as follows: Figure 6 shown.
[0124] S4-1, the process of extracting comprehensive rainfall characteristics indicators is as follows Figure 7 As shown, the steps include:
[0125] S4-1A, based on the radar forecast grid extrapolation forecast product, short-term warning of urban waterlogging level is carried out, the surface rainfall in the radar network grid corresponding to each warning zone is calculated, and the forecast files of all grids under the same forecast time limit at the target time are determined; the forecast time limit ranges from 5 minutes to 180 minutes;
[0126] S4-1B, for the forecast file under the forecast time t, the area weighted method is used to correct the surface rainfall with the grid data of the ith warning zone to obtain the corrected surface rainfall; the correction method of correcting the surface rainfall with the area weighted method is specifically expressed as:
[0127] Pr=∑Po,i*Ai / ∑Ai
[0128] Where Po represents the observed precipitation, Pr represents the corrected surface rainfall, and Ai represents the area represented by the grid point.
[0129] S4-1C, traverse the forecast files Ri(t) of all sub-areas under all forecast time periods, and calculate the rainfall process line L of each sub-area according to the surface rainfall data of each sub-area according to the forecast time period;
[0130] S4-1D, determine the accumulated rainfall, rainfall duration and rainfall type during the rainfall process according to the rainfall process line L, and obtain the actual surface rainfall threshold. The rainfall type is determined by the ratio of the time of the rainfall peak and the entire rainfall duration, including the front type, the center type and the back peak type; the front type means that the rainfall peak is at <1 / 3 of the entire rainfall duration, the center type is at 1 / 3 to 2 / 3, and the back peak type is at >2 / 3; the duration includes 30min, 60min and 120min, and the actual surface rainfall threshold of the i-th warning zone is obtained;
[0131] S4-2, the process of issuing real-time waterlogging warning in the forecast area is as follows Figure 8 As shown, the specific steps include:
[0132] S4-2A, compare the actual rainfall threshold of the ith warning zone with the threshold indicators of different risk levels. When the actual rainfall threshold is less than the threshold, there is no waterlogging risk; if it is greater, the waterlogging risk level is determined;
[0133] S4-2B, repeat step S4-3A, traverse all warning zones to obtain the risk level of each warning zone;
[0134] S4-2C, issues waterlogging warnings based on time, warning zones, rainfall, and waterlogging levels as warning signals, and publishes forecast information for each hour in real time to achieve waterlogging warnings.
Claims
1. A method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model, characterized in that: Includes steps: S1, the city's one-dimensional river hydrodynamic model, urban watershed hydrological model, one-dimensional pipeline model and two-dimensional surface model are coupled to construct an urban comprehensive watershed drainage model, the model parameters are verified and calibrated, and early warning zones are delineated; On the basis of water system drainage zoning, for urban built-up areas, adjacent areas within the same water system drainage zone with the same municipal rainwater drainage system and administrative division are divided into the same early warning zone; S2, conduct sensitivity experiments on rainstorm scenarios and urban drainage and flood prevention capabilities for the urban integrated watershed drainage model, build a waterlogging risk assessment system for waterlogging depth and waterlogging time, analyze the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and obtain rainfall characteristic comprehensive indicators for each warning zone; S3, based on the grid data of radar rainfall prediction, establish the mapping relationship between the forecast surface rainfall and the warning zone, dynamically extract the comprehensive index of rainfall characteristics corresponding to the warning zone, and realize the transformation from grid rainfall to comprehensive index of rainfall characteristics; S4, coupling the above three steps, constructs a rapid early warning model for urban-scale waterlogging risk, and implements dynamic waterlogging risk warning issuance for each warning zone.
2. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1 is characterized in that: The urban watershed hydrological model includes watershed rainwater collection, rainfall runoff generation and confluence models; When the catchment area of the basin is 50km 2 The instantaneous unit line method is used above, and the catchment area of the basin is less than 50km 2 Use the inference formula method; The rainfall runoff is divided into non-built-up areas and built-up areas. The non-built-up areas use the front-loss and back-loss method, and the built-up areas use the fixed runoff coefficient method. The confluence model adopts the SWMM nonlinear reservoir model.
3. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1 is characterized in that: A high-precision digital elevation model is used in the two-dimensional surface model for data extraction, and the two-dimensional grids of potential flood-prone areas are encrypted. A larger grid density is used for areas with higher terrain and no flooding has occurred over the years.
4. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1 is characterized in that: The coupling in S1 includes the following steps: obtaining the medium waterlogging risk points of the model after coupling, and checking, correcting and supplementing the waterlogging risk points of the urban integrated watershed drainage model according to the historical waterlogging data.
5. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1, characterized in that: S2 specifically includes the following steps: designing sensitivity tests on urban integrated watershed drainage models for waterlogging simulation under different rainfall scenarios, constructing a waterlogging risk assessment system for waterlogging depth and duration, analyzing the correlation characteristics between rainfall characteristic comprehensive indicators and waterlogging risk levels, and using the values of rainfall characteristic comprehensive indicators of each warning zone that meet the judgment criteria for waterlogging warning in the simulation results of the urban integrated watershed drainage model as the thresholds of rainfall characteristic comprehensive indicators for each risk level.
6. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1, characterized in that: In S3, based on the grid data of radar rainfall prediction, the mapping relationship between the forecast surface rainfall and the warning partition is established, which specifically includes the following steps: determining the latitude and longitude information of the radar forecast grid points; matching the grid points with the warning partitions, and establishing the mapping relationship between the forecast surface rainfall and the warning partitions. If any grid point cannot be matched within the warning partition, it is matched with the grid point closest to the center point of the partition.
7. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1, characterized in that: The dynamic extraction of comprehensive indicators of rainfall characteristics of the warning zone in S3 specifically includes: extracting the rainfall process line L of the warning zone from all grid forecasts under the same forecast time at the target time, obtaining indicators of accumulated rainfall, rainfall duration and rainfall type during the rainfall process according to the rainfall process line L, and obtaining comprehensive indicators of rainfall characteristics of each warning zone.
8. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1, characterized in that: The above three steps are coupled in S4 to develop a rapid early warning model for waterlogging risk levels and to realize the release of dynamic waterlogging risk warnings for each warning zone.
9. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 1, characterized in that: The process of building a rapid warning model described in S4 includes the following steps: S4-1, traverse and determine the forecast files of all grids under the same forecast time limit at the target time; the forecast time limit ranges from 5 minutes to 180 minutes; S4-2, for the forecast file under the forecast time t, the area rainfall is corrected by the area weighting method with the grid data of the ith warning zone to obtain the corrected area rainfall; S4-3, traverse the forecast files of all sub-areas under all forecast time periods, and calculate the rainfall process line L of each sub-area according to the surface rainfall data of each sub-area according to the forecast time period; S4-4, determine the accumulated rainfall, rainfall duration and rainfall type during the rainfall process according to the rainfall process line L, obtain the actual surface rainfall threshold and construct a rapid early warning model for urban-scale waterlogging risk.
10. The method for early warning of waterlogging risk in urban drainage areas based on a hydrodynamic model according to claim 9, characterized in that: In S4-2, the area weighting method is used to correct the area rainfall, which is specifically expressed as: Pr=∑Po,i*Ai / ∑Ai Where Po represents the observed precipitation, Pr represents the corrected surface rainfall, and Ai represents the area represented by the grid point.
Citation Information
Patent Citations
Urban flood control early warning and forecasting system
CN108320462A
Waterlogging risk prediction method and device
CN111368397A
Method and system for forecasting urban drainage basin flood
CN112785053A
Hydraulic engineering safety management system
CN114139380A
Urban inland inundation prediction method based on big data
CN115169069A
Cited By
Hydraulic runoff modeling method capable of reducing dimensions and simplifying, electronic equipment and storage medium
CN119647341A
Waterlogging and ponding intelligent scheduling method for urban important infrastructure
CN120124904A
Large-scale watershed hydrological modeling method based on variable grids
CN120317033A
A large-scale watershed hydrological modeling method based on variable grids
CN120317033B
Accumulated water detection method, device and equipment and storage medium
CN120496344A