Construction method for preventing road base from gathering water

By setting up road concrete U-shaped sinks and permeable concrete cushions in old concrete roads, combining the original road gravel and asphalt mixture, an all-inclusive structure is formed, which solves the problem of water disturbance and improves road stability and transformation quality , achieving zero water accumulation effect.

CN118880685APending Publication Date: 2024-11-01CHINA MCC17 GRP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411119161.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

In the renovation of old concrete roads with heavy traffic loads and abundant water areas, the water disturbance problem has a serious impact on the quality of road transformation. The existing methods are costly and have a long construction period, making it difficult to effectively solve the quality hazards caused by uneven settlement.

Method used

The road concrete U-shaped sink and permeable concrete cushion are used to combine the original road gravel and asphalt mixture to form an all-inclusive structure to achieve the separation of water inside the road, and use the water barrier to guide the outside of the rainwater to reduce water accumulation.

Benefits of technology

It has achieved the reduction or elimination of water disturbance problems in the renovation of old concrete roads, improved the stability of the road structure, reduced the costs caused by uneven settlement, improved the quality of the transformation, and ensured the zero-water accumulation function of the road.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880685A_ABST
    Figure CN118880685A_ABST
Patent Text Reader

Abstract

The invention discloses the field of resource utilization of old concrete pavements, and belongs to the field of resource utilization of old concrete pavements in road engineering. A fully-wrapped structure is formed by the paved asphalt pavement, the water insulation belt and the road concrete U-shaped water insulation groove, the road structure layer is separated from water on the original ground on the two sides, the water insulation belt and the side gutter apron permeable concrete cushion layer are used for guiding infiltrated rainwater flowing to the road side from the pavement to the outer side of the road, and a simple and rapid dewatering structure is formed. The low-polymer water-based function of a road structure is achieved, the stability of a road structure layer of old pavement transformation is ensured, differential settlement caused by factors such as underground water is reduced, and disturbance and reflection cracks on the road are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of resource utilization of old concrete pavements in road engineering, and specifically relates to a construction method for preventing water accumulation in a road base. Background Art

[0002] Old concrete roads under heavy traffic loads are prone to pavement cracking and need to be renovated frequently. The old concrete should be crushed above the base and new concrete should be laid to supplement the structure.

[0003] If the road is located in an area with abundant rainfall, water disturbance will seriously affect the quality of road reconstruction during the reconstruction of old concrete roads. In the past, methods such as well point dewatering and foundation deepening and replacement treatment were costly and had a long construction period. How to economically and high-quality reduce or eliminate the quality risks caused by water disturbance during the reconstruction of old concrete roads with heavy traffic loads and abundant water areas is a difficult problem.

[0004] Therefore, a construction method for preventing water accumulation in a road base as mentioned in the present invention is needed. Summary of the invention

[0005] The purpose of the present invention is to provide a construction method for preventing water from gathering in a road base, so as to solve the problems raised in the above-mentioned background technology, so as to achieve the purpose of enhancing the stability of the road structure and reducing or eliminating uneven settlement.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] A construction method for preventing water from gathering in a road base comprises the following steps:

[0008] Step 1: First, crush the old concrete pavement according to the normal method and process it into graded concrete blocks with a diameter not greater than 40 cm;

[0009] A trench is excavated on the original road to the top elevation of the original roadbed, and the crushed concrete blocks of the original concrete pavement and part of the old cement-stabilized crushed stone materials of the original road base are reserved, and the remaining old cement-stabilized crushed stone materials of the original road base are transported to the stockpile yard for processing;

[0010] Step 2: After the original roadbed is leveled, compaction is performed using a roller;

[0011] Then, a formwork is set up on the top surface of the original roadbed after leveling and compaction, and after the formwork is completed, pouring is performed to form a U-shaped watertight ditch for road concrete;

[0012] Size requirements:

[0013] The thickness of the formed bottom plate of the road concrete U-shaped watertight ditch shall not be less than 15cm;

[0014] The side plate height of the road concrete U-shaped watertight ditch shall be increased to the top surface of the renovated pavement base after forming, and the thickness of the side plate shall not be less than 25cm;

[0015] Step 3: When pouring the side plate, a water barrier is added on the inner side of the road at the top of the side plate. The water barrier covers half of the height and leaves the other half outside the U-shaped water barrier of the road concrete.

[0016] Step 4: After the road concrete U-shaped watertight groove is maintained and its strength reaches the standard, the original concrete pavement crushed concrete blocks are filled in the road concrete U-shaped watertight groove to form a backfill base layer;

[0017] Step 5, the old cement-stabilized crushed stone of the original road base in the stockpile yard is added and mixed according to the mix ratio to form a 5% water-stabilized layer with the old cement-stabilized crushed stone;

[0018] Transport it to the site, spread it on the backfill base, compact it and perform maintenance;

[0019] Step 6: After the maintenance is completed, the side flat stone construction is carried out; first, the side flat stone permeable concrete cushion is laid, and the permeable concrete is used as a drainage structure for rainwater seepage at the edge of the road surface;

[0020] Then lay and install the side flat stones;

[0021] Step 7: After the construction is completed, the pavement mixing layer and the asphalt mixture pavement are paved;

[0022] When paving the asphalt mixture pavement, bury the top of the half-height water barrier reserved on the top of the side plate of the road concrete U-shaped water barrier into the asphalt mixture pavement for compaction;

[0023] The asphalt mixture pavement, water barrier strips, and road concrete U-shaped water barrier form a fully enclosed structure, separating the road structure layer from the water bodies on the original ground on both sides;

[0024] Water-blocking strips and side-flat stone permeable concrete cushion layers are used to direct rainwater that seeps down the road surface to the outside of the road, forming a simple and rapid drainage structure and achieving the zero-water accumulation function of the road structure.

[0025] In a further technical solution, in step 4, the old cement-stabilized crushed stone material of the original road base is used to fill the seams and level it until it is dense as the backfill base of the renovated road, and after the backfill is completed, it is rolled and compacted.

[0026] In a further technical solution, in step 1, the ratio of the spare old cement-stabilized crushed stone of the original road base and the old cement-stabilized crushed stone of the original road base in the stockpile is (10-30%): (70-90%).

[0027] In a further technical solution, the water barrier passes through the asphalt mixture pavement, the mixed layer and the road concrete U-shaped water barrier.

[0028] In a further technical solution, the mixed layer includes an asphalt permeable layer and a slurry seal layer, and the asphalt permeable layer is located below the slurry seal layer.

[0029] In a further technical solution, the top of the U-shaped water-blocking trough of the road concrete is consistent with the top height of the 5% water-stabilizing layer prepared by adding old cement-stabilized crushed stone materials;

[0030] The top height of the side flat stone permeable concrete is consistent with the top height of the mixed layer.

[0031] Beneficial Effects

[0032] The present invention is suitable for the reconstruction of old concrete pavements in rain-rich areas, where water seepage from the roadside enters the pavement base, resulting in insufficient water-repellent capacity of the structure, leading to uneven settlement, and reducing the impact of water disturbance on the road. It is simple to operate, safe and feasible, and has guaranteed quality. It can greatly save the expenditure cost caused by differential settlement and improve the reconstruction quality of old concrete pavements. The present invention sets a U-shaped water-blocking trough in road concrete to achieve a waterproof structure inside the road, and uses the graded concrete blocks of the original road and the old cement-stabilized crushed stone materials of the original road base to set up a backfill subbase. Installing a water-blocking strip and an asphalt permeable layer and a slurry seal on the top can achieve relatively good water separation, and the permeable concrete cushion layer can achieve a good water-conducting effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0034] Figure 1 It is a cross-sectional view of the construction method for preventing water accumulation in the road base according to the present invention.

[0035] In the figure: 1. Original roadbed; 2. U-shaped concrete watertight ditch on the road; 3. Backfill base layer; 4. Adding old cement-stabilized crushed stone to make a 5% water-stabilizing layer; 5. Asphalt mixture pavement; 6. Asphalt permeable layer and slurry seal layer; 7. Watertight strip; 8. Side flat stone; 9. Side flat stone permeable concrete cushion layer. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0037] The application principle of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0038] Example 1

[0039] See also Figure 1 As shown, an embodiment of the present invention provides a construction method for preventing water accumulation in a road base, comprising the following steps:

[0040] Step 1: First, crush the old concrete pavement according to the normal method and process it into graded concrete blocks with a diameter not greater than 40 cm;

[0041] A trench is excavated on the original road to the top elevation of the original roadbed 1, and the crushed concrete blocks of the original concrete pavement and part of the old cement-stabilized crushed stone materials of the original road base are reserved, and the remaining old cement-stabilized crushed stone materials of the original road base are transported to the stockpile yard for processing;

[0042] Step 2, after the original roadbed 1 is leveled, compaction is performed using a roller;

[0043] Then, a formwork is set up on the top surface of the original roadbed 1 after being leveled and compacted, and after the formwork is set up, pouring is performed to form a road concrete U-shaped watertight ditch 2;

[0044] Size requirements:

[0045] The thickness of the formed bottom plate of the road concrete U-shaped watertight ditch 2 shall not be less than 15 cm;

[0046] The side plate height of the road concrete U-shaped watertight ditch 2 is increased to the top surface of the renovated road base after forming, and the thickness of the side plate is not less than 25cm;

[0047] Step 3, when casting the side plate, a water barrier 7 is cast on the inner side of the road at the top of the side plate, and the water barrier 7 is buried half of the height, and the other half is reserved to the outside of the road concrete U-shaped water barrier 2;

[0048] Step 4, after the road concrete U-shaped watertight ditch 2 is maintained and its strength reaches the standard, fill the original concrete pavement crushed concrete blocks in the road concrete U-shaped watertight ditch 2 to form a backfill base layer 3; use the old cement-stabilized crushed stone material of the original road base layer to fill the seams and level them until they are dense as the backfill base layer 3 of the renovated road, and roll and compact them after the backfilling is completed.

[0049] Step 5, the old cement-stabilized crushed stone of the original road base in the stockpile yard is added and mixed according to the mix ratio to prepare a 5% water-stabilized layer 4 with the old cement-stabilized crushed stone;

[0050] Transport to the site, spread on the backfill base 3, compact and maintain;

[0051] Step 6, after the maintenance is completed, the side flat stone 8 is constructed; first, the side flat stone permeable concrete cushion layer 9 is laid, and the permeable concrete is used as a drainage structure for rainwater seepage at the edge of the road surface;

[0052] Then lay and install the side flat stone 8;

[0053] Step 7, after the construction is completed, the pavement mixture layer 6 and the asphalt mixture pavement 5 are paved;

[0054] When the asphalt mixture pavement 5 is paved, the top of the water barrier 7 with half the height reserved on the top of the side plate of the road concrete U-shaped water barrier 2 is buried in the asphalt mixture pavement 5 for compaction;

[0055] The paved asphalt mixture pavement 5, water barrier strip 7, and road concrete U-shaped water barrier 2 form a full-enclosed structure, and the road structure layer is separated from the water bodies on the original ground on both sides;

[0056] The water barrier 7 and the flat stone permeable concrete cushion 9 are used to guide the rainwater flowing from the road surface to the outside of the road, forming a simple and fast drainage structure, and realizing the zero water accumulation function of the road structure.

[0057] In step 1, the ratio of the spare old cement-stabilized crushed stone of the original road base and the old cement-stabilized crushed stone of the original road base in the stockpile yard is (10-30%): (70-90%).

[0058] The water barrier 7 passes through the asphalt mixture pavement 5, the mixed layer and the road concrete U-shaped water barrier 2.

[0059] The mixed layer includes an asphalt permeable layer and a slurry seal layer, wherein the asphalt permeable layer is located below the slurry seal layer. The asphalt permeable layer is a thin layer that penetrates the surface of the base layer by pouring emulsified asphalt, coal tar or liquid asphalt on the base layer. It is mainly used for interlayer treatment between the lower layer and the base layer. The slurry seal layer is a thin layer formed by mixing appropriately graded emulsified asphalt, coarse and fine aggregates, water, fillers (such as cement, lime, fly ash, stone powder, etc.) and additives according to the designed ratio using mechanical equipment to form a slurry mixture, and then paving it on the original road surface. The asphalt permeable layer is located below the slurry seal layer, that is, between the base layer and the asphalt surface layer. The permeable layer is first laid on the base layer to enhance the adhesion between the base layer and the subsequent asphalt surface layer and form a waterproof layer.

[0060] In a further technical solution, the top of the U-shaped water-blocking ditch 2 of the road concrete is consistent with the top height of the 5% water-stabilizing layer 4 made by adding old cement-stabilized crushed stone materials;

[0061] The top height of the side flat stone permeable concrete 9 is consistent with the top height of the mixed layer 6.

[0062] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.

[0063] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A construction method for preventing water from gathering in the road base. It is characterized in that The following steps are involved: Step 1: First, crush the old concrete pavement according to the normal method and process it into graded concrete blocks with a diameter not greater than 40 cm; A trench is excavated on the original road to the top elevation of the original roadbed (1), and the crushed concrete blocks of the original concrete road surface and a small amount of old cement-stabilized crushed stone materials of the original road base are reserved, and the remaining old cement-stabilized crushed stone materials of the original road base are transported to a stockpile site for processing; Step 2, after the original roadbed (1) is leveled, compaction is performed using a roller; Then, a formwork is set up on the top surface of the original roadbed (1) after being leveled and compacted, and after the formwork is set up, pouring is performed to form a road concrete U-shaped watertight trough (2); Size requirements: The thickness of the formed bottom plate of the road concrete U-shaped watertight trough (2) is not less than 15 cm; The side plate height of the road concrete U-shaped watertight ditch (2) is increased to the top surface of the renovated road base after forming, and the thickness of the side plate is not less than 25 cm; Step 3, when casting the side plate, a water barrier (7) is cast on the inner side of the road at the top of the side plate, and the water barrier (7) is buried half of the height, and the other half is reserved to the outside of the road concrete U-shaped water barrier (2); Step 4, after the road concrete U-shaped watertight groove (2) is cured and its strength reaches the standard, the original concrete road surface crushed concrete blocks are filled in the road concrete U-shaped watertight groove (2) to form a backfill base layer (3); Step 5, the old cement-stabilized crushed stone material of the original road base in the stockpile yard is added and mixed according to the mix ratio to prepare a 5% water-stabilized layer (4) with the old cement-stabilized crushed stone material; Transport to the site, lay on the backfill base (3), compact and maintain; Step 6, after the maintenance is completed, the side flat stone (8) is constructed; first, a side flat stone permeable concrete cushion layer (9) is laid, and permeable concrete is used as a drainage structure for rainwater seepage at the edge of the road surface; Then lay and install the side flat stones (8); Step 7, after the construction is completed, the pavement mixing layer (6) and the asphalt mixture pavement (5) are paved; When the asphalt mixture pavement (5) is paved, the top of the water barrier strip (7) with half the height reserved on the top of the side plate of the road concrete U-shaped water barrier (2) is buried in the asphalt mixture pavement (5) for compaction; The paved asphalt mixture pavement (5), the water barrier strip (7), and the road concrete U-shaped water barrier (2) form a fully enclosed structure, and the road structure layer is separated from the water bodies on the original ground on both sides; The water-blocking strip (7) and the flat stone permeable concrete cushion layer (9) are used to guide the rainwater that flows from the road surface to the road side to the outside of the road, thereby forming a simple and fast water-draining structure and realizing the zero-water-collecting function of the road structure.

2. A construction method for preventing water accumulation in a road base according to claim 1, It is characterized in that In step 4, the old cement-stabilized crushed stone material of the original road base is used to fill the gaps and level until it is dense as the backfill base (3) of the renovated road, and after the backfill is completed, it is rolled and compacted.

3. A construction method for preventing water accumulation in a road base according to claim 1, It is characterized in that In step 1, the ratio of the spare old cement-stabilized crushed stone of the original road base and the old cement-stabilized crushed stone of the original road base in the stockpile yard is (10-30%): (70-90%).

4. A construction method for preventing water accumulation in a road base according to claim 1, It is characterized in that The water barrier strip (7) passes through the asphalt mixture pavement (5), the mixed layer and the road concrete U-shaped water barrier (2).

5. A construction method for preventing water accumulation in a road base according to claim 1, It is characterized in that The mixed layer comprises an asphalt permeable layer and a slurry seal layer, wherein the asphalt permeable layer is located below the slurry seal layer.

6. A construction method for preventing water accumulation in a road base according to claim 1, It is characterized in that The top of the U-shaped road concrete watertight ditch (2) is consistent with the top height of the 5% water-stabilizing layer (4) prepared by adding old cement-stabilized crushed stone materials; The top height of the side flat stone permeable concrete (9) is consistent with the top height of the mixed layer (6).

Citation Information

Patent Citations

  • Construction method for improving hydrophobic capacity of road structure

    CN116377790A

  • Construction method for improving stability of road structure and reducing water gathering property

    CN117449157A

  • Permeable concrete road and construction method thereof

    CN118308932A

  • U-shaped groove structure of prefabricated side wall of cast-in-place bottom plate of underpass road

    CN213978405U

  • Method for forming the roadbed of a ballasted track

    JP6170268B1