Subway station accessory structure construction method

By using short and long casings to fix the steel bars in the wind pavilion construction of the subway station, avoiding the removal of the enclosure piles, and combining the water connection box and water stop steel plate, the problems of low construction efficiency and long construction period of the subway station's auxiliary structure are solved, and the construction period of the subway station's auxiliary structure is achieved. More efficient construction and waterproofing effects.

CN118880931APending Publication Date: 2024-11-01CCFEB CIVIL ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411018243.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The construction efficiency of the subway station's ancillary structure is low and the construction period is long. Especially when the wind pavilion is constructed, the removal of the enclosure piles increases the construction period, and the enclosure piles cannot be removed during the construction of the section shield, which extends the overall construction period.

Method used

Install short and long guards on the enclosure piles of the roof, bottom plate and side wall of the wind pavilion, and the steel bars are welded and fixed to the guard to avoid reserved post-pouring tape construction. After the roof plate of the wind pavilion reaches its strength, cut the hole piles to make it possible to make The long casing forms a hole, and a water connection box and water stop steel plate are installed to improve the waterproof effect.

Benefits of technology

There is no need to reserve the post-watering belt for construction, which shortens the construction period, reduces the removal of the enclosure piles, improves the construction efficiency, and improves the waterproofing effect of the wind pavilion of the subway station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880931A_ABST
    Figure CN118880931A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of an accessory structure of a subway station, which belongs to the field of civil construction and comprises the following steps: S1, constructing a fender post, lowering the fender post, and mounting two short pile casings on the fender post in the range of a ventilation pavilion top plate and a ventilation pavilion bottom plate; in the fender posts at the position of the ventilation pavilion side wall, a long pile casing is installed at the interval of a preset number of fender posts, and the fender posts without the long pile casing form hole piles; s2, a station middle plate and a ventilation pavilion bottom plate are constructed, reinforcing steel bars of the station middle plate are welded to the long pile casings, and reinforcing steel bars of the ventilation pavilion bottom plate are welded to the short pile casings on the lower side; s3, station side walls and ventilation pavilion side walls are constructed, and steel bars of the station side walls and the ventilation pavilion side walls are welded to the long pile casings; s4, construction of a station main body top plate and a ventilation pavilion top plate; and S5, after the ventilation pavilion top plate reaches the strength, the hole piles are cut off. The construction efficiency of the subway station accessory structure can be improved, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of civil engineering, and in particular to a construction method for an auxiliary structure of a subway station. Background Art

[0002] Rapid construction methods for subways in suburban areas are urgently needed for suburban development. Suburbs also provide vast construction sites, which are a necessary but not sufficient condition for rapid construction. Therefore, optimization is also needed in design and technology to achieve rapid construction of subways in suburban areas.

[0003] When constructing wind shelters attached to urban subway stations, the construction method of pre-reserved post-casting strips or pre-reserved post-casting strips plus corbels is often used. The retaining piles will occupy a certain construction space during the construction process, especially when constructing the bottom plate, side wall and top plate of the wind shelter, which requires a larger operating space. During the construction of these post-casting strips, some retaining piles need to be removed or cut in order to carry out subsequent pouring work to connect the new and old concrete structures. In addition, the construction of wind shelters is usually carried out in sections, which means that the retaining piles need to be removed in batches at different stages to ensure the space and operational convenience of the construction area. Due to the large number of retaining piles at the junction of the wind shelter and the main structure, the removal of the retaining piles increases the construction period. In addition, during the interval shield construction, the retaining piles, as the stress-bearing part of the gantry crane track beam, cannot be removed. It is necessary to wait until the shield construction is completed before the retaining piles can be removed, which also prolongs the overall construction period.

[0004] In order to improve the construction efficiency of subway station ancillary structures, a new construction method is needed. Summary of the invention

[0005] The invention provides a construction method for an accessory structure of a subway station, so as to solve the technical problems of low construction efficiency and long construction period of the accessory structure of a subway station.

[0006] According to one aspect of the present invention, a method for constructing an auxiliary structure of a subway station is provided, comprising the following steps: S1, constructing retaining piles, lowering retaining piles, installing two short casings on the retaining piles in the range of the wind pavilion top plate and the wind pavilion bottom plate; installing a long casing at intervals of a preset number of retaining piles in the retaining piles at the wind pavilion side wall position, and the retaining piles without the long casing installed form opening piles;

[0007] S2, construction of the station middle plate and wind pavilion bottom plate. The steel bars of the station middle plate are welded to the long casing, and the steel bars of the wind pavilion bottom plate are welded to the short casing on the lower side.

[0008] S3, construction of station side walls and wind pavilion side walls. The steel bars of the station side walls and wind pavilion side walls are welded on the long casing;

[0009] S4, construction of the station main roof and wind pavilion roof. The steel bars of the station main roof are welded to the long casing, and the steel bars of the wind pavilion roof are welded to the short casing on the upper side.

[0010] S5. After the roof of the wind pavilion reaches sufficient strength, the opening piles are cut off to form an opening between the long casings. The retaining piles installed with the long casings become part of the opening wall.

[0011] Optionally, in step S1, steel bars are used in both the long casing and the short casing to connect the steel cages of the retaining piles.

[0012] Optionally, after step S5, the method further includes step S6 of installing a water receiving box on the cross section of the hole pile.

[0013] Optionally, in step S1, the number and spacing of the hole piles are determined according to the wind pavilion opening clearance, so that the spacing between adjacent long casings is not less than the wind pavilion opening clearance width.

[0014] Optionally, in step S1, a retaining pile of a long casing is installed, and the center of the pile is aligned with the center of the side wall.

[0015] Optionally, in step S2, a transverse waterstop steel plate is provided between the station center plate and the station side wall, and a water-swellable waterstop strip is installed on the upper side of the transverse waterstop steel plate.

[0016] Optionally, in step S2, a longitudinal waterstop steel plate is provided along the long casing, the longitudinal waterstop steel plate is located between the wind pavilion top plate and the wind pavilion bottom plate, and water-expandable waterstop strips close to the concrete are installed on both sides of the longitudinal waterstop steel plate.

[0017] Optionally, in step 1, the top end of the short protective tube on the upper side exceeds the preset length of the wind pavilion top plate, the bottom end of the short protective tube on the lower side exceeds the preset length of the wind pavilion bottom plate, the top end of the long protective tube exceeds the preset length of the wind pavilion top plate, and the bottom end of the long protective tube exceeds the preset length of the wind pavilion bottom plate.

[0018] Optionally, in step S3, a waterstop steel plate is provided between the side wall of the station and the side wall of the wind shelter, and water-expanding waterstop strips are fixedly installed on the left and right sides of the waterstop steel plate by round steel.

[0019] Optionally, in steps S2 to S4, the construction of the auxiliary structure close to the construction range of the shield gantry crane is not carried out simultaneously with the operation of the gantry crane.

[0020] In summary, the present application includes at least one of the following beneficial technical effects:

[0021] 1. By setting long and short casings on some retaining piles, during the construction of the wind pavilion of the subway station, the steel cages of the wind pavilion top plate, wind pavilion bottom plate, station side wall, wind pavilion side wall, station main body top plate, and station middle plate can be directly welded and fixed on the long and short casings, without the need to adopt the construction method of reserving post-cast strips. In this way, during the construction of the station wind pavilion, it is not necessary to remove the retaining piles to provide construction space for the post-cast strip construction, thereby improving the construction efficiency and shortening the construction period;

[0022] 2. The retaining piles with long casings installed become part of the opening wall and do not need to be removed. Only the opening piles need to be cut off, which reduces the work of removing the retaining piles after the wind pavilion structure is completed, and further shortens the construction period;

[0023] 3. The waterproof effect of the subway station wind shelter can be improved by installing water collection boxes, water-stop steel plates and water-swelling water-stop strips.

[0024] In addition to the above-described purposes, features and advantages, the present invention has other purposes, features and advantages. The present invention will be further described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0026] Figure 1 This is the bottom plate diagram of the wind pavilion of the present invention;

[0027] Figure 2 Figure 1 Section 1-1;

[0028] Figure 3 This is a cross-sectional view of the side wall retaining piles of the wind pavilion of the present invention;

[0029] Figure 4 This is a cross-sectional view of the bottom plate, top plate and guard piles of the wind pavilion of the present invention;

[0030] Figure 5 It is the reinforcement tie diagram in the long casing and the short casing of the present invention.

[0031] Legend:

[0032] 1. Guarding piles; 2. Wind pavilion bottom plate; 3. Wind pavilion side walls; 4. Short casing; 5. Waterstop steel plate; 6. Wind pavilion top plate; 7. Station top plate; 8. Station side walls; 9. Station middle plate; 10. Long casing; 11. Steel bars. DETAILED DESCRIPTION

[0033] The embodiments of the present invention are described in detail below with reference to the accompanying drawings. However, the present invention can be implemented in many different ways as defined and covered below.

[0034] The following is combined with Figure 1-5 This application is described in further detail.

[0035] The embodiment of the present application discloses a method for constructing an auxiliary structure of a subway station.

[0036] Reference Figure 1 and Figure 2 , the construction method of the subway station auxiliary structure includes the following steps:

[0037] S1, construction of retaining piles 1, lowering retaining piles 1, installing two short casings 4 on the retaining piles 1 in the range of the wind pavilion top plate 6 and the wind pavilion bottom plate 2; in the retaining piles 1 at the position of the wind pavilion side wall 3, a long casing 10 is installed at intervals of a preset number of retaining piles 1, and the retaining piles 1 without the long casing 10 installed form a hole pile. Specific operation: lowering retaining piles 1, installing two short casings 4 on the retaining piles 1 in the range of the wind pavilion top plate 6 and the wind pavilion bottom plate 2. In the retaining piles 1 at the position of the wind pavilion side wall 3, a long casing 10 is installed at intervals of a preset number of retaining piles 1, and the retaining piles 1 without the long casing 10 installed form a hole pile. Short casings 4 are installed to fix the steel bars of the wind pavilion top plate 6 and the bottom plate, improving the stability and efficiency of the construction of the top plate and the bottom plate. Long casings 10 are installed to fix the steel bars of the station main structure and the wind pavilion side wall 3, ensuring the firmness of the side wall and the continuity of the overall structure. The hole piles are used to prepare for the hole after the subsequent wind pavilion top plate 6 is completed, thereby reducing the workload of later demolition.

[0038] S2, the station middle plate 9 and the wind pavilion bottom plate 2 are constructed. The steel bars of the station middle plate 9 are welded to the long casing 10, and the steel bars of the wind pavilion bottom plate 2 are welded to the short casing 4 on the lower side. According to the design drawings, the steel bars required for the station middle plate 9 and the wind pavilion bottom plate 2 are prepared to ensure that the length, diameter and number of the steel bars meet the design requirements. Then, the steel bars of the station middle plate 9 are welded to the long casing 10. During the welding process, it is necessary to ensure that the connection between the steel bars and the casing is firm and the welding points are uniform to ensure the uniformity of the force of the steel bars and the integrity of the structure. Next, the steel bars of the wind pavilion bottom plate 2 are welded to the short casing 4 on the lower side. It is also necessary to ensure the quality and firmness of the welding to prevent loosening or breaking at the welding point. After the welding is completed, the welding points are inspected and processed to ensure that there are no welding defects, and the steel bars are subjected to necessary anti-corrosion treatment. This construction method has multiple functions. First, by welding the steel bars to the casing, a stable steel skeleton is formed, which provides a solid foundation support and ensures the stability and bearing capacity of the station middle plate 9 and the wind pavilion bottom plate 2.

[0039] S3, station side wall 8 and wind pavilion side wall 3 are constructed, and the steel bars of the station side wall 8 and wind pavilion side wall 3 are welded to the long casing 10. By welding the steel bars to the long casing 10, a stable steel skeleton is formed, which provides a solid foundation support and ensures the stability and bearing capacity of the station side wall 8 and wind pavilion side wall 3.

[0040] S4, the station main roof and wind pavilion roof 6 are constructed. The steel bars of the station main roof are welded to the long casing 10, and the steel bars of the wind pavilion roof 6 are welded to the upper short casing 4. By welding the steel bars to the long casing 10 and the short casing 4, a stable steel skeleton is formed, providing a solid foundation support, ensuring the stability and bearing capacity of the station main roof and wind pavilion roof 6.

[0041] S5, after the wind pavilion roof 6 reaches the required strength, the hole piles are cut off to form a hole between the long casings 10, and the retaining piles 1 with the long casings 10 installed become part of the hole wall. This includes using professional cutting equipment to cut the hole piles at a predetermined position, removing them from the overall structure, so that a hole that meets the design specifications is formed between the long casings 10. Then, after the hole is formed, check the stability and integrity of the long casings 10 and the surrounding structures, and continue construction after ensuring that there are no errors. By cutting off the hole piles, the necessary passage space is reserved, so that the retaining piles 1 with the long casings 10 installed become part of the hole wall. This construction method has multiple functions. Firstly, it optimizes the space utilization by cutting off unnecessary piles, making the structure of the opening area more reasonable and compact; secondly, the opening formed between the long casings 10 ensures the design size and functional requirements of the passage, meeting the needs of subsequent construction and operation; at the same time, retaining the retaining piles 1 with the long casings 10 installed as part of the opening wall avoids excessive demolition and reconstruction at key locations, reduces construction complexity and risks, and further shortens the construction period.

[0042] After step S5, step S6 is also included, in which a water receiving box is installed on the cross section of the hole pile. The specific operation is to first prepare the installation position of the water receiving box on the cross section exposed after the hole pile is cut off, and then select a water receiving box of suitable size and material, accurately fix it on the cross section of the hole pile, ensure its firm connection by bolts or welding, and seal the edge of the water receiving box with sealing materials to prevent water seepage. The role of installing the water receiving box in this way is to effectively collect and guide water flow, prevent water from penetrating into the structure, thereby protecting the waterproof performance of the underground structure. The water receiving box can play a role in guiding and draining water during the rainy season or when the groundwater level rises, and avoid erosion and damage to the underground station structure caused by accumulated water; at the same time, the installation of the water receiving box can also make the drainage system more perfect, ensure smooth drainage, and reduce maintenance costs; in addition, the water receiving box can also slow down the water flow speed, avoid the scouring of the cross section of the hole pile by the water flow, and further protect the stability and durability of the structure.

[0043] In step S1, the number and spacing of the hole piles are determined according to the wind pavilion opening clearance, so that the spacing between adjacent long casings 10 is not less than the wind pavilion opening clearance width. In the design stage, the clearance width of the wind pavilion opening is first measured and determined, and then the specific number and spacing of the hole piles are calculated and arranged according to this width. During installation, the hole piles and long casings 10 are lowered to a predetermined depth in strict accordance with the calculation results to ensure that the spacing between adjacent long casings 10 meets the design requirements. The role of this arrangement is to ensure that the hole space of the wind pavilion meets the design requirements, avoid affecting subsequent construction and structural functions due to too small spacing, and ensure the accuracy and standardization of construction. By reasonably arranging the hole piles and long casings 10, not only can sufficient space be provided for the construction of the wind pavilion top plate 6 and the bottom plate, but also when the hole piles are cut off after the wind pavilion top plate 6 reaches strength, a hole that meets the design specifications can be formed, thereby simplifying subsequent construction steps, avoiding repeated adjustments or demolition operations, and improving construction efficiency.

[0044] In step S1, the retaining pile 1 of the long casing 10 is installed, and the pile center is aligned with the side wall center. By aligning the pile center with the side wall center, the uniform distribution of structural force can be ensured, and the stability and safety of the overall structure can be improved; secondly, this precise alignment method helps the smooth progress of subsequent construction steps, so that the station body and the side wall of the wind pavilion can be accurately connected to the long casing 10, thereby ensuring the quality of steel bar welding and concrete pouring.

[0045] Reference Figure 3 and Figure 4 In step S2, a transverse waterstop steel plate 5 is arranged between the station middle plate 9 and the station side wall 8, and a water-swelling waterstop strip is installed on the upper side of the transverse waterstop steel plate 5. First, the transverse waterstop steel plate 5 is precisely arranged between the station middle plate 9 and the side wall to ensure that its position and angle meet the design requirements, and then the water-swelling waterstop strip is installed on the upper side of the waterstop steel plate 5. The waterstop strip will swell after contacting water, filling the surrounding gaps to achieve a sealing effect. The main function of this setting is to improve the waterproof performance of the structure. The transverse waterstop steel plate 5 acts as a physical barrier to block water penetration, while the water-swelling waterstop strip will expand rapidly when it comes into contact with water, further filling and sealing possible water seepage paths. The double waterproof design effectively prevents groundwater from infiltrating through the gap between the station middle plate 9 and the side wall, protects the station structure from water damage, extends the service life of the structure, and improves the safety and reliability of the entire subway station.

[0046] In step S2, a longitudinal water-stop steel plate 5 is arranged along the long casing 10, and the longitudinal water-stop steel plate 5 is located between the wind pavilion top plate 6 and the wind pavilion bottom plate 2, and water-swellable water-stop strips close to the concrete are installed on both sides of the longitudinal water-stop steel plate 5. The longitudinal water-stop steel plate 5 acts as a continuous barrier, which can effectively prevent water from penetrating through the long casing 10 between the wind pavilion top plate 6 and the wind pavilion bottom plate 2, thereby improving the waterproof performance of the overall structure.

[0047] In step 1, the top end of the short casing 4 on the upper side exceeds the preset length of the wind pavilion top plate 6, the bottom end of the short casing 4 on the lower side exceeds the preset length of the wind pavilion bottom plate 2, the top end of the long casing 10 exceeds the preset length of the wind pavilion top plate 6, and the bottom end of the long casing 10 exceeds the preset length of the wind pavilion bottom plate 2. The preset length is usually determined according to the engineering design requirements, generally about 1 meter. The main function of this design is to ensure that the casing can provide sufficient support and stability and enhance the integrity of the structure.

[0048] In step S3, a waterstop steel plate 5 is arranged between the station side wall 8 and the wind pavilion side wall 3, and water-swelling waterstop strips are fixedly installed on the left and right sides of the waterstop steel plate 5 by round steel. As a physical barrier, the waterstop steel plate 5 can effectively prevent water from penetrating through the gaps between the side walls, and play the role of the first layer of waterproof barrier. Secondly, the water-swelling waterstop strip will expand rapidly after encountering water, filling and sealing the gaps on both sides of the waterstop steel plate 5, further enhancing the waterproof effect. The expansion performance of the waterstop strip ensures that water cannot pass through even if there are tiny cracks or irregular gaps, thereby greatly improving the waterproof performance. The waterstop strip is fixed by round steel to ensure that the waterstop strip will not shift during the construction process, and it is kept close to the concrete in the predetermined position, so that it can fully exert its expansion and sealing effects when it comes into contact with water.

[0049] In steps S2 to S4, the construction of the auxiliary structure close to the construction range of the shield gantry crane is not carried out simultaneously with the operation of the gantry crane. First, by separating the construction of the auxiliary structure from the operation of the gantry crane, the impact of the vibration, impact or displacement of mechanical equipment on the auxiliary structure during the construction process can be effectively avoided, thereby ensuring the construction quality and structural stability. The shield gantry crane will generate large mechanical vibrations during operation, which may have an adverse effect on ongoing processes such as concrete pouring, steel bar welding and structure forming, leading to problems such as structural deformation, loose welding or reduced concrete strength. Secondly, separating the construction and operation time can also improve the safety of construction, reduce mutual interference between workers and equipment, and reduce the risk of accidents.

[0050] Reference Figure 5In step S1, steel bars are used in both the long casing 10 and the short casing 4 to connect the steel cage of the retaining pile 1. The specific operations of this process include first lowering the retaining pile 1 to a predetermined depth, and then installing the casing on the retaining pile 1. Two short casings 4 are installed on the retaining piles 1 in the range of the top plate 6 and the bottom plate of the wind pavilion, and long casings 10 are installed at preset intervals on the retaining piles 1 at the position of the side wall 3 of the wind pavilion. Next, steel bars with a diameter of 20 mm are selected, and the steel bars are inserted into the casing according to the standard of two rows with a spacing of 0.5 m, and the steel bars are fixed in the casing by welding. Then, the steel bars in the casing are tied to the steel cage of the retaining pile 1 to ensure a tight connection between the two. The purpose of this operation is to connect the casing and the steel cage of the retaining pile 1 together through the steel bar tie, so as to form an integrated steel bar network, thereby enhancing the overall stability and seismic performance of the structure; at the same time, the tied steel bars are evenly distributed, which can effectively disperse the external force, improve the bearing capacity of the structure, and prevent structural damage caused by excessive local force; in addition, the steel bar tie ensures the continuity between the retaining pile 1, the long casing 10 and the short casing 4, so that the construction of each part is seamlessly connected, avoiding structural problems caused by disconnection or loosening; this standardized steel bar tie operation also improves the overall construction quality and reduces the need for subsequent maintenance and repair; the casing with pre-installed steel bar tie simplifies the complex operations in the subsequent construction steps, improves the construction efficiency, and shortens the construction period.

[0051] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for constructing ancillary structures of a subway station, characterized in that: The steps include: S1, construction of retaining piles (1), lowering the retaining piles (1), installing two short casings (4) on the retaining piles (1) within the range of the wind pavilion top plate (6) and the wind pavilion bottom plate (2); installing a long casing (10) at intervals of a preset number of retaining piles (1) in the retaining piles (1) at the wind pavilion side wall (3), and the retaining piles (1) not installed with the long casing (10) form hole piles; S2, construction of the station middle plate (9) and the wind pavilion bottom plate (2), the steel bars of the station middle plate (9) are welded to the long casing (10), and the steel bars of the wind pavilion bottom plate (2) are welded to the short casing (4) on the lower side; S3, construction of the station side wall (8) and the wind pavilion side wall (3), the steel bars of the station side wall (8) and the wind pavilion side wall (3) are welded to the long casing (10); S4, construction of the station main body roof and the wind pavilion roof (6), the steel bars of the station main body roof are welded to the long casing (10), and the steel bars of the wind pavilion roof (6) are welded to the short casing (4) on the upper side; S5, after the roof (6) of the wind pavilion reaches a certain strength, the hole piles are cut off to form a hole between the long casings (10), and the surrounding piles (1) equipped with the long casings (10) become part of the hole wall.

2. A method for constructing an auxiliary structure of a subway station according to claim 1, characterized in that: In step S1, steel bars (11) are used to tie the long casing (10) and the short casing (4) to connect the steel cage of the retaining pile (1).

3. A method for constructing an auxiliary structure of a subway station according to claim 2, characterized in that: After step S5, the method further includes step S6, installing a water receiving box on the cross section of the hole pile.

4. A method for constructing an auxiliary structure of a subway station according to claim 1, characterized in that: In step S1, the number and spacing of the hole piles are determined according to the wind pavilion opening clearance, so that the spacing between adjacent long casings (10) is not less than the wind pavilion opening clearance width.

5. A method for constructing ancillary structures of a subway station according to claim 4, characterized in that: In step S1, the retaining pile (1) of the long casing (10) is installed, and the center of the pile is aligned with the center of the side wall.

6. A method for constructing an auxiliary structure of a subway station according to claim 1, characterized in that: In step S2, a transverse water-stopping steel plate (5) is arranged between the station middle plate (9) and the station side wall (8), and a water-swelling water-stopping strip is installed on the upper side of the transverse water-stopping steel plate (5).

7. A method for constructing an auxiliary structure of a subway station according to claim 1, characterized in that: In step S2, a longitudinal water-stop steel plate (5) is arranged along the long casing (10), and the longitudinal water-stop steel plate (5) is located between the wind pavilion top plate (6) and the wind pavilion bottom plate (2). Water-swelling water-stop strips that are close to the concrete are installed on both sides of the longitudinal water-stop steel plate (5).

8. A method for constructing ancillary structures of a subway station according to claim 1, characterized in that: In step 1, the top end of the short protective tube (4) located on the upper side exceeds the preset length of the wind pavilion top plate (6), the bottom end of the short protective tube (4) located on the lower side exceeds the preset length of the wind pavilion bottom plate (2), the top end of the long protective tube (10) exceeds the preset length of the wind pavilion top plate (6), and the bottom end of the long protective tube (10) exceeds the preset length of the wind pavilion bottom plate (2).

9. A method for constructing an auxiliary structure of a subway station according to claim 1, characterized in that: In step S3, a water-stop steel plate (5) is arranged between the station side wall (8) and the wind pavilion side wall (3), and water-swellable water-stop strips are fixedly installed on the left and right sides of the water-stop steel plate (5) by means of round steel.

10. A method for constructing ancillary structures of a subway station according to claim 1, characterized in that: In steps S2 to S4, the construction of the auxiliary structure close to the construction range of the shield gantry crane is not carried out simultaneously with the operation of the gantry crane.