Connection line power distribution method and device, electronic equipment and computer readable storage medium
By building a pre-solving model for operation plan and generating predicted planned power, the problem of uncertainty in new energy output and load demand in the power distribution of the contact line is solved, and the safety and economicality of power grid operation are improved.
Patent Information
- Application Number
- CN202410989830.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-01
AI Technical Summary
The existing connection line power distribution method is difficult to cope with the uncertainty of new energy output and load demand, resulting in deviations from the actual operation and the lack of costly operation and safety and stability of the power grid.
By obtaining the basic data of the power grid to be optimized, a pre-solving model for the operation plan is constructed, and the sum of the network-saving operating costs and deviation penalty items is minimized as the goal, the predicted planned power of each contact line is generated, and the contact line power is performed based on the predicted planned power Allocation, ensure that the allocation plan meets the rated power threshold and conducts a safe check of the trend.
It improves the accuracy of the power distribution of the contact line, reduces the possible operational constraints overreach during the planning process, and improves the safety and economicality of power grid operation.
Smart Images

Figure CN118889423A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of electricity spot market clearing plans, and in particular relates to a tie line power distribution method, device, electronic equipment and computer-readable storage medium. Background Art
[0002] In the power market, the interconnection line is the line for power transmission between power grids. The power exchange plan between power grids through the interconnection line is called the port plan. After the grid-level dispatching agency issues the port plan for the AC interconnection line, the provincial dispatching agency needs to decompose the total exchange power of the port plan and distribute it to each interconnection line, and then use this as the boundary to develop the provincial dispatching plan. It is crucial to distribute power to each interconnection line so that it can adapt to the complex situation in the actual power system to ensure the safe and efficient operation of the power system.
[0003] However, existing methods mainly rely on historical data and experience for power allocation, which makes it difficult to cope with uncertainties such as renewable energy output and load demand, resulting in deviations between allocation plans and actual operating conditions, and unable to ensure low-cost operation and safe and stable power grid operation. Summary of the invention
[0004] The embodiments of the present invention provide a tie line power distribution method, device, electronic device and storage medium, which can improve the accuracy of tie line power distribution, avoid large deviations between the distribution plan and the actual operation situation, and thus ensure low-cost operation and safe and stable operation of the power grid.
[0005] An embodiment of the present invention provides a method for allocating interconnection line power, comprising: obtaining basic data of a power grid to be optimized; wherein the basic data includes: the planned total exchange power of the outlet for the next day, the power parameters corresponding to the provincial day-ahead scheduling plan, and the preliminary planned power of each interconnection line.
[0006] Based on the basic data, an operation plan pre-solution model is constructed with the goal of minimizing the sum of provincial network operation cost and deviation penalty term, wherein the deviation penalty term is used to characterize the deviation between the tie line distribution power and the historical flow.
[0007] Based on the basic data, the constraints of the operation plan pre-solution model are constructed. Under the constraints of the operation plan pre-solution model, the operation plan pre-solution model is solved to generate the predicted planned power of each interconnection line when the sum of the provincial network operation cost and the deviation penalty term is minimized.
[0008] The interconnection line power is distributed according to the predicted planned power.
[0009] Furthermore, the preliminary planned power of each interconnection line is obtained in the following manner.
[0010] For each tie line, the transmission power data of the tie line in the historical operation period is obtained.
[0011] The proportion of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period is calculated to obtain the historical period power ratio of the tie line among all tie lines.
[0012] For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
[0013] Furthermore, performing tie line power allocation according to the predicted planned power includes:
[0014] For each tie line, determine one by one whether the predicted planned power meets the rated power threshold requirement of the current tie line. After all predicted planned powers have been determined, if it is determined that there are tie lines that exceed the corresponding rated power threshold, repeat the adjustment operation until the planned powers of all tie lines meet the corresponding rated power threshold requirements, and obtain the final planned power of each tie line.
[0015] The interconnection line power is allocated according to the final planned power of each interconnection line.
[0016] The adjustment operation includes:
[0017] All tie lines whose current planned power exceeds the corresponding rated power threshold are extracted as tie lines to be processed.
[0018] Among the tie lines to be processed, the tie lines to be processed that exceed the rated power threshold the most are selected as selected tie lines.
[0019] The power difference of the excess portion of the selected tie line is calculated, and the current planned power of the selected tie line is adjusted to its rated power threshold.
[0020] The selected tie lines after adjustment are added to the processed tie line set.
[0021] According to the current planned power of the remaining tie lines except the processed tie line set, the total planned power of the remaining tie lines is calculated.
[0022] For the remaining tie lines outside the processed tie line set, on the basis of the corresponding current planned power, the power difference of the excess part of the selected tie line is allocated according to the proportion of each remaining tie line in the total planned power of the remaining tie lines, so as to obtain the updated planned power of each remaining tie line.
[0023] Furthermore, after allocating the tie line power according to the predicted planned power, the method further includes:
[0024] A provincial grid day-ahead dispatching plan model is constructed based on the interconnection line power distribution. After the model is solved, the results are checked for power flow safety to ensure that relevant operation constraints within the province are feasible.
[0025] Furthermore, the operation plan pre-solving model is specifically:
[0026]
[0027] Among them, F is the objective function; T is the total number of scheduling periods; N g is the number of conventional units; N w is the number of new energy units; N TL is the number of inter-provincial contact lines; C g,t is the unit power generation cost of the conventional unit in period t; C w,t P is the unit power abandonment cost of the new energy station in period t; g,t is the planned output of the conventional unit in period t; P c,w,t is the abandoned power of the new energy unit in period t; α g,t is the operating state variable of the conventional unit in period t; α g,t-1 is the operating state variable of the conventional unit in the period t-1; Q g is the startup cost of conventional units; P TL,t is the planned power of the TL-th tie line in period t; is the real power of the TLth tie line during the historical operation period t; M TL,t is the penalty factor for the tie line power deviation.
[0028] Furthermore, the constraints of the operation plan pre-solution model include:
[0029] Provincial grid power balance constraints, tie line port planned power balance constraints, key section safety constraints, positive and negative reserve capacity constraints, unit maximum and minimum adjustable constraints, unit ramp constraints, unit start and stop constraints;
[0030] The provincial grid power balance constraint is: Among them, P w,t is the planned output of the new energy unit in period t, P L,t is the load demand of the provincial grid in period t.
[0031] The power balance constraint of the tie line port plan is: Among them, N q is the number of contact line openings; Γ q is the set of contact lines involved in the qth port plan; P q,t is the planned power of the interconnection line port q in period t.
[0032] The safety constraints of the critical section are:
[0033]
[0034] Among them, S k,max is the limit value of the kth safety constraint; N l is the number of nodes l where the load is located; A k,l A is the power transfer distribution factor of the load node l for the kth safety constraint; k,TL A is the power transfer distribution factor of the node where the tie line TL is located for the kth safety constraint; k,g A is the power transfer distribution factor of the node where the conventional unit is located for the kth safety constraint; k,w is the power transfer distribution factor of the node where the new energy station is located for the kth safety constraint; P l,t is the load demand of the load node l in period t.
[0035] The positive and negative spare capacity constraints are:
[0036]
[0037] Among them, RU t is the positive reserve demand of the provincial network in period t; RD t is the negative reserve demand of the provincial network in period t; g,max The maximum technical output of conventional units; P g,min It is the minimum technical output of conventional units.
[0038] The maximum and minimum adjustable constraints of the unit are: P g,max ≥P g,t ≥P g,min .
[0039] The unit climbing constraint is: in, It is the ramp power limit of conventional units; is the down-slope power limit of conventional units; P g,t-1 It is the planned output of the conventional unit in the t-1 period.
[0040] The unit start and stop constraints are:
[0041]
[0042] Among them, m g,s is the minimum continuous downtime of conventional units; m g,o is the minimum continuous startup time of the conventional unit, and τ is any time in the scheduling period.
[0043] Based on the above method embodiment, the present invention provides a corresponding device embodiment.
[0044] An embodiment of the present invention provides a tie line power distribution device, comprising: a basic data acquisition module, a model construction module, a constraint construction module, a planned power solution module and a power distribution module;
[0045] The basic data acquisition module is used to acquire the basic data of the power grid to be optimized; wherein the basic data includes: the planned total exchange power of the outlets for the next day, the power parameters corresponding to the provincial day-ahead dispatching plan, and the preliminary planned power of each interconnection line.
[0046] The model building module is used to build an operation plan pre-solution model based on the basic data with the goal of minimizing the sum of provincial network operation cost and deviation penalty term; wherein the deviation penalty term is used to characterize the deviation between the interconnection line distribution power and the historical flow.
[0047] The constraint building module is used to build the constraint conditions of the operation plan pre-solution model based on the basic data.
[0048] The planned power solving module is used to solve the operation plan pre-solving model under the constraints of the operation plan pre-solving model to generate the predicted planned power of each interconnection line when the sum of the provincial network operation cost and the deviation penalty term is minimized.
[0049] The power allocation module is used to allocate the power of the interconnection line according to the predicted planned power.
[0050] Furthermore, the basic data acquisition module acquires the preliminary planned power of each tie line in the following manner:
[0051] For each tie line, the transmission power data of the tie line in the historical operation period is obtained.
[0052] The proportion of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period is calculated to obtain the historical period power ratio of the tie line among all tie lines.
[0053] For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
[0054] Based on the above method embodiment, the present invention provides a corresponding electronic device embodiment.
[0055] An embodiment of the present invention provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the interconnection line power distribution method described in any one of the above method embodiments can be implemented.
[0056] Based on the above method embodiment, the present invention provides a corresponding computer-readable storage medium embodiment.
[0057] An embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed by a processor, the interconnection line power distribution method described in any one of the above method embodiments can be implemented.
[0058] Compared with the prior art, the present invention has the following beneficial effects:
[0059] The present invention constructs an operation plan pre-solution model and the constraints of the model based on the basic data of the power system, and then solves the model under the above constraints to generate the predicted planned power of each interconnection line when the sum of the provincial network operation cost and the deviation penalty term is minimized. Finally, the interconnection line power is allocated according to the predicted planned power. Compared with the prior art, the method of the present invention better considers the complex power grid operation constraints and conditions, provides a more scientific allocation strategy, reduces the problem of operating constraint exceeding the limit that may occur in the planning process, and improves the accuracy of interconnection line power allocation, thereby improving the safety of power grid operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] Figure 1 It is a flow chart of a tie line power distribution method provided in one embodiment of the present invention.
[0061] Figure 2 It is a schematic diagram of a provincial network system load forecast curve and a total power curve of planned transmission provided by an embodiment of the present invention.
[0062] Figure 3 It is a schematic diagram of a flow chart of distributing tie line power according to the predicted planned power of each tie line provided by an embodiment of the present invention.
[0063] Figure 4 It is a flowchart of an adjustment operation provided by an embodiment of the present invention.
[0064] Figure 5 It is a flow chart of a tie line power distribution method provided by another embodiment of the present invention.
[0065] Figure 6 It is a schematic diagram of a power curve of a tie line after power is allocated according to the allocation strategy of scenario 1 provided by an embodiment of the present invention.
[0066] Figure 7 This is a schematic diagram of power flow information of a line constraint exceeding a limit provided by an embodiment of the present invention.
[0067] Figure 8 It is a schematic diagram of the deviation comparison between the decomposition result and the historical transmission power of a tie line provided by an embodiment of the present invention.
[0068] Fig. 9 It is a schematic diagram of the deviation comparison between the decomposition result of another tie line provided by an embodiment of the present invention and the historical transmission power.
[0069] Fig.10 It is a schematic diagram for comparing a planned power value and a constraint limit value provided in an embodiment of the present invention.
[0070] Fig.11 It is a structural schematic diagram of a tie line power distribution device provided in one embodiment of the present invention. DETAILED DESCRIPTION
[0071] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0072] like Figure 1 As shown, an embodiment of the present invention provides a tie line power distribution method, which at least includes the following steps:
[0073] Step S1, obtaining basic data of the power grid to be optimized; wherein the basic data includes: the planned total exchange power of the outlets for the next day, the power parameters corresponding to the provincial day-ahead dispatching plan, and the preliminary planned power of each interconnection line.
[0074] Specifically, in the present invention, the power parameter data corresponding to the provincial day-ahead dispatch plan include: T total number of dispatch periods, N g Number of conventional units, N w The number of new energy units, N TL The number of inter-provincial contact lines, C g,t The unit power generation cost of conventional units in period t, C w,t The unit power abandonment cost of the new energy station in period t, Q g The startup cost of conventional units, P L,t The load demand of the provincial grid in period t, P w,t The planned output of the new energy unit in period t, N q The number of tie-line openings, Γ qThe set of contact lines involved in the qth port plan, P q,t The planned power of the tie line port q in period t, S k,max The limit value of the kth safety constraint, N l The number of nodes l where the load is located, A k,l The power transfer distribution factor of the load node l for the kth safety constraint, A k,TL The power transfer distribution factor of the node where the tie line TL is located for the kth safety constraint, A k,g The power transfer distribution factor of the node where the conventional unit is located for the kth safety constraint, A k,w The power transfer distribution factor of the node where the new energy station is located for the kth safety constraint, P l,t The load demand of node l in period t, RU t The positive reserve demand and RD of the provincial network in period t t The negative reserve demand of the provincial network in the t period, P g,max The maximum technical output of conventional units, P g,min Minimum technical output of conventional units, Ramp-up power limit of conventional units, Down-slope power limit of conventional units, m g,s Minimum continuous downtime of conventional units, m g,o The minimum continuous start-up time of conventional units and the rated power threshold of each interconnection line.
[0075] In a preferred embodiment, the preliminary planned power of each tie line can be obtained by:
[0076] For each tie line, the transmission power data of the tie line in the historical operation period is obtained.
[0077] The proportion of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period is calculated to obtain the historical period power ratio of the tie line among all tie lines.
[0078] For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
[0079] Preferably, in the present invention, the transmission power data of the tie line during the historical operation period includes: The actual transmission power of the TLth tie line during the t period of historical operation. After obtaining the transmission power data of all tie lines during the historical operation period, calculate the sum of the transmission power data of all tie lines during the historical operation period. Then, for each tie line, calculate its proportion to the sum of the transmission power data of all tie lines during the historical operation period, and obtain the power ratio of each tie line in all tie lines during the historical period. Finally, multiply the power ratio of each tie line in all tie lines by the total exchange power of the next day's plan to obtain the preliminary planned power of the tie line.
[0080] The total exchange power of the next day's plan, the power parameters corresponding to the provincial day-ahead dispatch plan, the transmission power data of the tie line during the historical operation period, M TL,t The penalty factors for tie-line power deviation are all known data obtained from the power system.
[0081] The P mentioned in the invention g,t The planned output of conventional units in period t, P g,t-1 The planned output of conventional units in period t-1, P c,w,t The abandoned power of new energy units, α g,t The operating state variables of the conventional unit in period t, α g,t-1 The operating state variables of the conventional unit in the t-1 period, P TL,t The data items of the planned power of the TL-th tie line in period t are all unknown data items and are calculated in the subsequent process of solving the operation plan pre-solution model.
[0082] In a preferred embodiment of the present invention, a provincial grid system load forecast curve and a port planned total power exchange curve (both of which are the basic data) are as follows: Figure 2 shown.
[0083] Step S2: Based on the basic data, an operation plan pre-solution model is constructed with the goal of minimizing the sum of provincial network operation cost and deviation penalty term, wherein the deviation penalty term is used to characterize the deviation between the tie line distribution power and the historical flow.
[0084] Specifically, in a preferred embodiment, the optimization goal of the operation plan pre-solution model is to minimize the sum of the provincial network operation cost and the deviation penalty item. The provincial network operation cost includes the cost of the provincial network day-ahead plan and the power abandonment cost; the deviation penalty item is specifically the deviation penalty item between the tie line allocation power and the historical flow, so the operation plan pre-solution model is specifically:
[0085]
[0086] Among them, F is the objective function; T is the total number of scheduling periods; N g is the number of conventional units; Nw is the number of new energy units; N TL is the number of inter-provincial contact lines; C g,t is the unit power generation cost of the conventional unit in period t; C w,t P is the unit power abandonment cost of the new energy station in period t; g,t is the planned output of the conventional unit in period t; P c,w,t is the abandoned power of the new energy unit in period t; α g,t is the operating state variable of the conventional unit in the period t (in this preferred embodiment, the operating state variable of the conventional unit takes the value of 1 when it is running in the period, and takes the value of 0 when it is shut down in the period); α g, t-1 is the operating state variable of the conventional unit in the t-1 period (in this preferred embodiment, the operating state variable of the conventional unit takes a value of 1 when it is running in the period, and takes a value of 0 when it is shut down in the period); Q g is the startup cost of conventional units; P TL,t is the planned power of the TL-th tie line in period t; is the real power of the TLth tie line during the historical operation period t; M TL,t is the penalty factor for the tie line power deviation (in this preferred embodiment, the penalty factor is 1000000).
[0087] Preferably, the provincial grid operation cost includes the cost of the provincial grid's day-ahead plan and the cost of power abandonment, and the deviation penalty item includes the difference between the current planned power of each interconnection line and the actual power in the same historical operating period.
[0088] Step S3, constructing the constraint conditions of the operation plan pre-solution model based on the basic data; solving the operation plan pre-solution model under the constraint conditions of the operation plan pre-solution model to generate the predicted planned power of each interconnection line when the sum of the provincial network operation cost and the deviation penalty term is minimized.
[0089] Specifically, in a preferred embodiment, allocating the power of the tie line by considering the constraints of the provincial network operation in advance can enable the power system to better cope with the uncertainty of new energy output and load demand, reduce the problem of operating constraint exceeding the limit that may occur during the planning process, and thus improve the safety and economy of the power grid operation. The constraints of the operation plan pre-solution model include:
[0090] Provincial grid power balance constraints, interconnection line planned power balance constraints, key section safety constraints, positive and negative spare capacity constraints, unit maximum and minimum adjustable constraints, unit climbing constraints, and unit start and stop constraints.
[0091] The provincial grid power balance constraint is: Among them, P w,t is the planned output of the new energy unit in period t, P L,t is the load demand of the provincial grid in period t.
[0092] The power balance constraint of the tie line port plan is: Among them, N q is the number of contact line openings; Γ q is the set of contact lines involved in the qth port plan; P q,t is the planned power of the interconnection line port q in period t.
[0093] The safety constraints of the critical section are:
[0094]
[0095] Among them, S k,max is the limit value of the kth safety constraint; N l is the number of nodes l where the load is located; A k,l A is the power transfer distribution factor of the load node l for the kth safety constraint; k,TL A is the power transfer distribution factor of the node where the tie line TL is located for the kth safety constraint; k,g A is the power transfer distribution factor of the node where the conventional unit is located for the kth safety constraint; k,w is the power transfer distribution factor of the node where the new energy station is located for the kth safety constraint; P l,t is the load demand of the load node l in period t.
[0096] The positive and negative spare capacity constraints are:
[0097]
[0098] Among them, RU t is the positive reserve demand of the provincial network in period t; RD t is the negative reserve demand of the provincial network in period t; g,max The maximum technical output of conventional units; P g,min It is the minimum technical output of conventional units.
[0099] The maximum and minimum adjustable constraints of the unit are: P g,max ≥P g,t ≥P g,min .
[0100] The unit climbing constraint is: in, It is the ramp power limit of conventional units; is the down-slope power limit of conventional units; P g,t-1It is the planned output of the conventional unit in the t-1 period.
[0101] The unit start and stop constraints are:
[0102]
[0103] Among them, m g,s is the minimum continuous downtime of conventional units; m g,o is the minimum continuous startup time of the conventional unit, and τ is any time in the scheduling period. In this preferred embodiment, the running state variable of the conventional unit takes the value of 1 when it is running in the period, and takes the value of 0 when it is shut down in the period.
[0104] Preferably, the preliminary planned power in step S1 is used as the initial value of the operation plan pre-solution model for optimization, where P g,t The planned output of conventional units in period t, P c,w,t The abandoned power of new energy units, α g,t The operating state variables of the conventional unit in period t, α g,t-1 The operating state variables of the conventional unit in the t-1 period, P TL,t The planned power of the TL-th tie line in the t period is the decision variable, with the goal of minimizing the F objective function under the constraints of the operation plan pre-solution model. By continuously adjusting the values of the decision variables, the P when the goal is achieved is solved. TL,t The value of is taken as the predicted planned power of each interconnection line.
[0105] Step S4: Allocate interconnection line power according to the predicted planned power.
[0106] like Figure 3 As shown, in a preferred embodiment, the tie line power is allocated according to the predicted planned power of each tie line, including:
[0107] Step S4.1: for each tie line, determine whether the predicted planned power meets the rated power threshold requirement of the current tie line one by one. After all predicted planned powers are determined, if it is determined that there is a tie line that exceeds the corresponding rated power threshold, the adjustment operation is repeated until the planned powers of all tie lines meet the corresponding rated power threshold requirements, and the final planned power of each tie line is obtained;
[0108] Step S4.2: Allocate the power of the interconnection lines according to the final planned power of each interconnection line.
[0109] like Figure 4 As shown, in a preferred embodiment, the adjustment operation includes:
[0110] Step S4.1.1, extract all tie lines whose current planned power exceeds the corresponding rated power threshold as tie lines to be processed.
[0111] Step S4.1.2: Among the tie lines to be processed, select the tie line to be processed that exceeds the rated power threshold the most as the selected tie line.
[0112] Step S4.1.3, calculate the power difference of the excess part of the selected tie line, and adjust the current planned power of the selected tie line to its rated power threshold. Wherein, when performing the first adjustment operation, the current planned power of the tie line is the predicted planned power.
[0113] Step S4.1.4, adding the selected tie line after adjustment to the processed tie line set.
[0114] Step S4.1.5, calculate the total planned power of the remaining tie lines based on the current planned power of the remaining tie lines except the processed tie line set.
[0115] Step S4.1.6: For the remaining tie lines outside the processed tie line set, on the basis of the corresponding current planned power, the power difference of the excess part of the selected tie line is distributed according to the proportion of each remaining tie line to the total planned power of the remaining tie lines, so as to obtain the updated planned power of each remaining tie line.
[0116] This means that every time an overload is detected, the power of the tie line with the most overload will be adjusted to the upper limit, and the excess will be proportionally distributed to other tie lines that have not exceeded the limit until all tie lines reach a safe operating power level. This process ensures the stability and safety of the tie line network and avoids system problems that may be caused by power overload.
[0117] Optionally, in another embodiment, the predicted planned power may be directly used as the final planned power for interconnection line power allocation.
[0118] like Figure 5 As shown, another embodiment of the present invention provides a tie line power distribution method, which, in addition to steps S1-S4 of the above embodiment, also includes the following steps after step S4:
[0119] Step S5: construct a provincial grid day-ahead dispatching plan model based on the tie line power distribution, and after solving the model, perform a power flow safety check on the result to ensure that relevant operation constraints within the province are feasible.
[0120] In order to verify the improvement of the proposed tie-line power allocation method over the traditional power allocation method based on artificial experience and historical values, another embodiment of the present invention conducts a comparative example analysis based on the scenario of a typical operation day of a provincial power grid. In the basic data of a typical operation day, the provincial grid system load forecast curve and the total power curve of the planned transmission of the outlet are as follows: Figure 2 The system load peak and valley values on the expected operation days are 119,000MW and 91,000MW, respectively, with a maximum external transmission power of 28,192MW and a maximum external reception power of 24,581MW.
[0121] Scenario 1: Based on manual experience, the transmission power data of the tie line in the historical operation period is used to calculate the ratio of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period, and the historical period power ratio of the tie line in all tie lines is obtained. According to the historical period power ratio of each tie line, the total power of the port plan on the previous day is allocated to each tie line to complete the power decomposition.
[0122] Scenario 2: According to the above embodiment method, the total power of the port plan is referred to the actual transmission power of each interconnection line during the historical operation period, and the power decomposition is completed by pre-solving the operation plan with the minimization of the sum of the provincial network operation cost and the deviation penalty term as the guide.
[0123] In the case of scenario 1, the total exchange power planned for the day before is allocated to each interconnection line in proportion. Based on the allocation strategy at this time, the power curve of an interconnection line after power allocation is as follows: Figure 6 As shown in the figure, the power allocation at this time is taken as the boundary condition, and the provincial grid day-ahead dispatching plan is compiled based on it. In the day-ahead plan optimization results, there are many monitoring elements in the provincial grid that exceed the safety constraints, including line constraints and main transformer constraints. Figure 7 A schematic diagram of the power flow information of one of the lines with constraint exceeding the limit is listed, where the dotted line is the component constraint limit and the solid line is the component planned power value obtained according to the optimized scheduling plan.
[0124] In the case of scenario 2, referring to the historical transmission power of the inter-provincial interconnection lines in each period, under the boundary conditions of meeting the day-ahead operation constraints, the total power of the Kouzi plan is decomposed into each interconnection line one by one. The deviation comparison between the decomposition results and the historical transmission power of two interconnection lines is shown in the figure below. Figure 8 , Fig. 9 As shown in Figure 2, the solid line is the historical transmission power of the tie line, and the dotted line is the planned power of the tie line to be solved.
[0125] Based on the planned power of the tie line as the boundary condition, the provincial grid day-ahead dispatching plan is compiled. There is no safety constraint exceeding the limit in the day-ahead plan optimization result. The comparison between the planned power value and the constraint limit is as follows: Fig.10As shown in the figure, the dotted line is the component constraint limit, and the solid line is the component planned power value obtained according to the optimized scheduling plan.
[0126] According to the analysis and comparison of the above examples, it can be seen that when the method proposed in the present invention is used to allocate the power of the interconnection line, the planned power values are all within the constraint range, and there is no problem of exceeding the safety constraint limit, which verifies the effectiveness and practicality of the present invention.
[0127] Based on the above method embodiment, the present invention provides a corresponding device embodiment.
[0128] like Fig.11 As shown, an embodiment of the present invention provides a tie line power distribution device, including: a basic data acquisition module 101, a model construction module 102, a constraint construction module 103, a planned power solution module 104, and a power distribution module 105.
[0129] The basic data acquisition module 101 is used to acquire the basic data of the power grid to be optimized; wherein the basic data includes: the planned total exchange power of the outlet for the next day, the power parameters corresponding to the provincial day-ahead dispatching plan, and the preliminary planned power of each interconnection line.
[0130] The model building module 102 is used to build an operation plan pre-solution model based on the basic data with the goal of minimizing the sum of the provincial network operation cost and the deviation penalty term; wherein the deviation penalty term is used to characterize the deviation between the interconnection line distribution power and the historical flow.
[0131] The constraint building module 103 is used to build the constraint conditions of the operation plan pre-solution model based on the basic data.
[0132] The planned power solving module 104 is used to solve the operation plan pre-solving model under the constraints of the operation plan pre-solving model to generate the predicted planned power of each tie line when the sum of the provincial network operation cost and the deviation penalty term is minimized.
[0133] The power allocation module 105 is used to allocate the power of the interconnection line according to the predicted planned power.
[0134] In a preferred embodiment, the basic data acquisition module 101 acquires the preliminary planned power of each tie line in the following manner:
[0135] For each tie line, the transmission power data of the tie line in the historical operation period is obtained.
[0136] The proportion of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period is calculated to obtain the historical period power ratio of the tie line among all tie lines.
[0137] For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
[0138] Another embodiment of the present invention provides an electronic device, comprising at least:
[0139] A memory, a processor, and a computer program stored in the memory and executable on the processor. When the computer program is executed, the interconnection line power distribution method of the present invention can be implemented.
[0140] Another embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed by a processor, the tie line power distribution method of the present invention is implemented.
[0141] It should be noted that the device embodiments described above are merely schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. In addition, in the accompanying drawings of the device embodiments provided by the present invention, the connection relationship between the modules indicates that there is a communication connection between them, which may be specifically implemented as one or more communication buses or signal lines. A person of ordinary skill in the art may understand and implement it without paying any creative effort.
[0142] The computer program includes computer program code, which may be in source code form, object code form, executable file or some intermediate form. The computer-readable storage medium may include: any entity or device, medium, USB flash drive, mobile hard disk, disk, optical disk, computer memory, read-only memory, random access memory, electric carrier signal, telecommunication signal and software distribution medium, etc. that can carry the computer program code. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, computer-readable media do not include electric carrier signals and telecommunication signals. For ease of explanation, the above content only shows the part related to the embodiment of the present invention. For specific technical details not disclosed, please refer to the method part of the embodiment of the present invention. The computer-readable storage medium is non-temporary and can be stored in a storage device formed by various electronic devices, which can realize the execution process recorded in the method of the embodiment of the present invention.
[0143] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0144] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems) and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram and the combination of processes and / or blocks in the flowchart and / or block diagram can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the process in the flowchart. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0145] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0146] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0147] The above is a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications are also considered to be within the scope of protection of the present invention.
Claims
1. A tie line power distribution method, characterized in that: include: Obtaining basic data of the power grid to be optimized; wherein the basic data includes: the planned total exchange power of the next day's outlet, the power parameters corresponding to the provincial day-ahead dispatching plan, and the preliminary planned power of each tie line; Based on the basic data, an operation plan pre-solution model is constructed with the goal of minimizing the sum of provincial network operation cost and deviation penalty term; wherein the deviation penalty term is used to characterize the deviation between the tie line distribution power and the historical power flow; Constructing the constraint conditions of the operation plan pre-solution model based on the basic data; solving the operation plan pre-solution model under the constraint conditions of the operation plan pre-solution model to generate the predicted planned power of each tie line when the sum of the provincial network operation cost and the deviation penalty term is minimized; The interconnection line power is distributed according to the predicted planned power.
2. The tie line power distribution method according to claim 1, characterized in that: The preliminary planned power of each tie line is obtained by: For each tie line, obtain the transmission power data of the tie line in the historical operation period; Calculate the ratio of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period, and obtain the historical period power ratio of the tie line among all tie lines; For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
3. The tie line power distribution method according to claim 1, characterized in that: The performing tie line power distribution according to the predicted planned power comprises: For each tie line, determine whether the predicted planned power meets the rated power threshold requirement of the current tie line one by one. After all predicted planned powers are determined, if it is determined that there is a tie line that exceeds the corresponding rated power threshold, repeat the adjustment operation until the planned powers of all tie lines meet the corresponding rated power threshold requirements, and obtain the final planned power of each tie line; Allocate the power of the interconnection lines according to the final planned power of each interconnection line; The adjustment operation includes: Extract all tie lines whose current planned power exceeds the corresponding rated power threshold as tie lines to be processed; Among the tie lines to be processed, selecting the tie line to be processed that exceeds the rated power threshold the most as the selected tie line; Calculate the power difference of the excess part of the selected tie line, and adjust the current planned power of the selected tie line to its rated power threshold; adding the selected contact line after adjustment into the processed contact line set; Calculate the total planned power of the remaining tie lines according to the current planned power of the remaining tie lines except the processed tie line set; For the remaining tie lines outside the processed tie line set, on the basis of the corresponding current planned power, the power difference of the excess part of the selected tie line is allocated according to the proportion of each remaining tie line in the total planned power of the remaining tie lines, so as to obtain the updated planned power of each remaining tie line.
4. The tie line power distribution method according to claim 1, characterized in that: After allocating the tie line power according to the predicted planned power, the method further includes: A provincial grid day-ahead dispatching plan model is constructed according to the interconnection line power distribution, and after solving the model, the results are checked for power flow safety.
5. The tie line power distribution method according to claim 1, characterized in that: The operation plan pre-solving model is specifically: Among them, F is the objective function; T is the total number of scheduling periods; N g is the number of conventional units; N w is the number of new energy units; N TL is the number of inter-provincial contact lines; C g,t is the unit power generation cost of the conventional unit in period t; C w,t P is the unit power abandonment cost of the new energy station in period t; g,t is the planned output of the conventional unit in period t; P c,w,t is the abandoned power of the new energy unit in period t; α g,t is the operating state variable of the conventional unit in period t; α g,t-1 is the operating state variable of the conventional unit in the period t-1; Q g is the startup cost of conventional units; P TL,t is the planned power of the TL-th tie line in period t; is the real power of the TLth tie line during the historical operation period t; M TL,t is the penalty factor for the tie line power deviation.
6. The tie line power distribution method according to claim 1, characterized in that: The constraints of the operation plan pre-solution model include: Provincial grid power balance constraints, tie line port planned power balance constraints, key section safety constraints, positive and negative reserve capacity constraints, unit maximum and minimum adjustable constraints, unit ramp constraints, unit start and stop constraints; The provincial grid power balance constraint is: Among them, P w,t is the planned output of the new energy unit in period t, P L,t is the load demand of the provincial grid in period t; The power balance constraint of the tie line port plan is: Among them, N q is the number of contact line openings; Γ q is the set of contact lines involved in the qth port plan; P q,t is the planned power of the tie line port q in period t; The safety constraints of the critical section are: Among them, S k,max is the limit value of the kth safety constraint; N l is the number of nodes l where the load is located; A k,l A is the power transfer distribution factor of the load node l for the kth safety constraint; k,TL A is the power transfer distribution factor of the node where the tie line TL is located for the kth safety constraint; k,g A is the power transfer distribution factor of the node where the conventional unit is located for the kth safety constraint; k,w is the power transfer distribution factor of the node where the new energy station is located for the kth safety constraint; P l,t is the load demand of the load node l in period t; The positive and negative spare capacity constraints are: Among them, RU t is the positive reserve demand of the provincial network in period t; RD t is the negative reserve demand of the provincial network in period t; g,max The maximum technical output of conventional units; P g,min Minimum technical output for conventional units; The maximum and minimum adjustable constraints of the unit are: P g,max ≥P g,t ≥P g,min ; The unit climbing constraint is: in, It is the ramp power limit of conventional units; is the down-slope power limit of conventional units; P g,t-1 The planned output of the conventional unit in the t-1 period; The unit start and stop constraints are: Among them, m g,s is the minimum continuous downtime of conventional units; m g,o is the minimum continuous startup time of the conventional unit, and τ is any time in the scheduling period.
7. A tie line power distribution device, characterized in that: include: Basic data acquisition module, model building module, constraint building module, planned power solving module and power allocation module; The basic data acquisition module is used to acquire the basic data of the power grid to be optimized; wherein the basic data includes: the planned total exchange power of the outlet for the next day, the power parameters corresponding to the day-ahead dispatching plan within the province, and the preliminary planned power of each tie line; The model building module is used to build an operation plan pre-solution model based on the basic data with the goal of minimizing the sum of the provincial network operation cost and the deviation penalty term; wherein the deviation penalty term is used to characterize the deviation between the tie line distribution power and the historical power flow; The constraint building module is used to build the constraint conditions of the operation plan pre-solving model based on the basic data; The planned power solving module is used to solve the operation plan pre-solving model under the constraint conditions of the operation plan pre-solving model to generate the predicted planned power of each tie line when the sum of the provincial network operation cost and the deviation penalty term is minimized; The power allocation module is used to allocate the power of the interconnection line according to the predicted planned power.
8. The interconnection line power distribution device according to claim 7, characterized in that: The basic data acquisition module obtains the preliminary planned power of each tie line in the following manner: For each tie line, obtain the transmission power data of the tie line in the historical operation period; Calculate the ratio of the transmission power data of the tie line in the historical operation period to the transmission power data of all tie lines in the historical operation period, and obtain the historical period power ratio of the tie line among all tie lines; For each interconnection line, the power ratio of the historical period is multiplied by the total planned exchange power of the outlet on the next day to obtain the preliminary planned power of the interconnection line.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein: When the processor executes the computer program, the interconnection line power distribution method described in any one of claims 1 to 6 can be implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the interconnection line power distribution method described in any one of claims 1 to 6 can be implemented.