Power grid risk processing method and electronic equipment

Through automated analysis of risk warning notices and grid ledger information, a drone inspection plan was generated, which solved the problem that special inspection plan formulation in the existing technology depends on experience and low efficiency of manual inspection, and achieved efficient and timely grid risks Processing and comprehensive inspection ensure the safe operation of the power grid.

CN118889670APending Publication Date: 2024-11-01GUANGDONG POWER GRID CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410897640.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing grid risk treatment methods rely on manual acquisition and analysis of key information in risk warning notices, resulting in inefficiency and lack of scientificity. Special patrol plans rely on the experience of dispatchers, and manual patrols are limited by physical strength and weather conditions. , the timeliness and comprehensiveness of the inspection cannot be ensured.

Method used

Through automated acquisition of key information in risk warning notices, combining power grid ledger information to determine the target location and historical operating parameters of the faulty components, generate a special patrol plan, and determine the drone inspection time period based on weather information to control the drone Perform special tour missions.

Benefits of technology

It realizes efficient handling of power grid risks, ensures the timeliness and comprehensiveness of patrols, improves the safety and efficiency of power grid operations, and reduces manual errors and weather restrictions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118889670A_ABST
    Figure CN118889670A_ABST
Patent Text Reader

Abstract

The invention discloses a power grid risk processing method and electronic equipment. The method comprises the steps that when it is detected that a risk early warning notice is issued, key information in the risk early warning notice is acquired, target position information corresponding to a fault element is determined according to the key information and power grid ledger information, and a special patrol plan of the fault element is generated based on the position information and a preset processing period; obtaining historical operation parameters of the fault component and time information corresponding to the historical operation parameters, and determining at least two special patrol time periods corresponding to the special patrol plan based on the historical operation parameters and the time information; and according to weather information of the target position information in the at least two special patrol time periods, determining a target patrol time period from the at least two special patrol time periods, and controlling the unmanned aerial vehicle to go to the target position in the target patrol time period to execute a special patrol task corresponding to the special patrol plan. High-efficiency processing of power grid risks is realized, timeliness and comprehensiveness of routing inspection are ensured, and safe operation of a power grid is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid inspection, and in particular to a method for processing power grid risks and electronic equipment. Background Art

[0002] In the existing grid risk handling methods, when the grid monitoring system detects a risk warning, it usually uses manual methods to obtain key information in the risk warning notice, which mainly includes the identification of the faulty component and the possible fault type. Then, the grid dispatcher will combine the grid ledger information, manually determine the approximate location of the faulty component through paper maps or electronic maps, and formulate a special patrol plan based on the dispatcher's experience and grid operation rules.

[0003] The implementation of special patrol plans usually relies on manual inspections, where inspectors need to go to the location of the faulty component for inspection according to the scheduled time and route. However, this method has obvious shortcomings: first, the process of manually obtaining key information and determining location information is inefficient and prone to errors; second, the formulation of special patrol plans relies on the experience of dispatchers, lacking scientificity and accuracy; finally, the manual inspection method is limited by the physical strength of inspectors and weather conditions, and cannot ensure the timeliness and comprehensiveness of the inspection. Summary of the invention

[0004] The present invention provides a method for processing power grid risks and electronic equipment to achieve efficient processing of power grid risks, ensure the timeliness and comprehensiveness of inspections, and guarantee the safe operation of the power grid.

[0005] According to one aspect of the present invention, a method for processing power grid risks is provided, comprising:

[0006] When it is detected that a risk warning notice is issued, key information in the risk warning notice is obtained, wherein the key information is information associated with the faulty component;

[0007] Determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and generate a special patrol plan for the faulty component based on the location information and a preset processing cycle;

[0008] Acquire historical operating parameters of the faulty component and time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information;

[0009] According to the weather information of the target location information within at least two of the special patrol time periods, a target patrol time period is determined from the at least two special patrol time periods, and the UAV is controlled to go to the target location within the target patrol time period to perform the special patrol task corresponding to the special patrol plan.

[0010] According to another aspect of the present invention, there is provided a device for processing power grid risk, comprising:

[0011] When it is detected that a risk warning notice is issued, key information in the risk warning notice is obtained, wherein the key information is information associated with the faulty component;

[0012] Determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and generate a special patrol plan for the faulty component based on the location information and a preset processing cycle;

[0013] Acquire historical operating parameters of the faulty component and time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information;

[0014] According to the weather information of the target location information within at least two of the special patrol time periods, a target patrol time period is determined from the at least two special patrol time periods, and the UAV is controlled to go to the target location within the target patrol time period to perform the special patrol task corresponding to the special patrol plan.

[0015] According to another aspect of the present invention, there is provided an electronic device, the electronic device comprising:

[0016] at least one processor; and

[0017] a memory communicatively connected to the at least one processor; wherein,

[0018] The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for processing power grid risks described in any embodiment of the present invention.

[0019] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for processing power grid risks described in any embodiment of the present invention when executed.

[0020] The technical solution of the embodiment of the present invention, when detecting the issuance of a risk warning notice, obtains the key information in the risk warning notice, determines the target location information corresponding to the faulty component according to the key information and the power grid account information, and generates a special patrol plan for the faulty component based on the location information and the preset processing cycle; obtains the historical operating parameters of the faulty component and the time information corresponding to the historical operating parameters, and determines at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information; determines the target inspection time period from the at least two special patrol time periods according to the weather information of the target location information in at least two special patrol time periods, and controls the drone to go to the target location in the target inspection time period to perform the special patrol task corresponding to the special patrol plan. In the technical solution of the present invention, the risk warning notice is automatically analyzed, and a corresponding special patrol plan is formulated, which solves the problem that the formulation of the special patrol plan in the prior art depends on the experience of the dispatcher and lacks scientificity and accuracy; by determining the weather in the special patrol time period, it is ensured that the drone inspection can be effectively executed. The efficient processing of power grid risks is achieved, the timeliness and comprehensiveness of the inspection are ensured, and the safe operation of the power grid is ensured.

[0021] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0023] Figure 1 A flowchart of a method for processing power grid risks provided in Embodiment 1 of the present invention;

[0024] Figure 2 A flowchart of a method for processing power grid risks provided in Embodiment 2 of the present invention;

[0025] Figure 3 A schematic diagram of the structure of a power grid risk processing device provided in Embodiment 3 of the present invention;

[0026] Figure 4 This is a schematic diagram of the structure of an electronic device provided in Embodiment 4 of the present invention. DETAILED DESCRIPTION

[0027] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0028] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0029] Embodiment 1

[0030] Figure 1 This is a flowchart of a method for processing power grid risk provided in the first embodiment of the present invention. This embodiment can be applied to the situation of inspecting faulty equipment in the power grid according to a newly issued risk warning notice. The method can be executed by a power grid risk processing device, which can be implemented in the form of hardware and / or software, and the device can be configured in an electronic device. For example, the electronic device can be equipped with a computer, and the device can be a drone intelligent special patrol system. Figure 1 As shown, the method includes:

[0031] S110. When it is detected that a risk warning notice has been issued, key information in the risk warning notice is obtained.

[0032] The risk warning notice may be a document containing detailed information about the risks in the power grid, and the key information may be information associated with faulty components in the power grid.

[0033] In an embodiment of the present invention, when the issuance of a risk warning notice is detected, key information in the risk warning notice is obtained, including: monitoring the basic risk module of the power grid management platform through an intelligent special patrol system, and when a risk warning notice is monitored, collecting key information in the risk warning notice.

[0034] Among them, the intelligent special patrol system can be a system used to monitor power grid risks and control drones to conduct inspections according to risk conditions; the power grid management platform is a system that comprehensively manages power grid operation, maintenance, monitoring and decision-making; the basic risk module can be understood as a module in the power grid management platform that manages risk-related information. Key information includes at least one of the risk name and number, the substation name and interval double number in the faulty component, the transmission line name, equipment importance, important users, risk start date, risk release date and release date.

[0035] Specifically, when the intelligent special patrol system detects the issuance of a risk warning notice, it will immediately start the information collection process. The intelligent special patrol system will automatically extract key information from the risk warning notice. This information may include the risk name and number, detailed information of the faulty component (such as substation name, interval double numbering, transmission line name), the importance of the equipment, important users that may be affected, the date when the risk starts and ends, and the issuance date of the notice.

[0036] S120. Determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and generate a special patrol plan for the faulty component based on the location information and a preset processing cycle.

[0037] The target location information may be understood as information indicating the location of the faulty component, for example, the target location information may be geographical location information of the faulty component. The preset processing period refers to a preset processing period for the risk warning notice, for example, the preset processing period is 2 days.

[0038] On the basis of the above technical solution, the target location information corresponding to the faulty component is determined according to the key information and the grid ledger information, including: based on the key information, querying the transmission station ledger and the substation ledger in the ledger query management module of the grid management platform, and determining the target location information corresponding to the faulty component according to the transmission station ledger and the substation ledger.

[0039] Among them, the power grid management platform usually includes multiple modules. The ledger query management module is used to store and manage the ledger information of various equipment in the power grid (such as transformers, transmission lines, etc.). The ledger information usually includes the basic attributes of the equipment, location, and the operation and maintenance management team to which it belongs.

[0040] Specifically, based on the key information, the operation and maintenance management team and location to which the faulty component in the substation account and transmission station account belongs can be found in the account query management module of the power grid management platform. The corresponding entry can be found by searching in the account according to the number or type of the faulty equipment. Then, the location information related to the faulty component can be found in the transmission station account and substation account, such as the substation name, transmission line name, tower number, etc. In addition, the operation and maintenance management team to which the faulty component belongs can also be determined.

[0041] On the basis of the above technical solution, the special patrol plan for the faulty component is generated based on the location information and the preset processing cycle, and also includes: generating at least one special patrol plan through the maintenance management module in the power grid management platform according to the target location information and the preset cycle.

[0042] Specifically, in the maintenance management module of the power grid management platform, one or more special patrol plans are added with the target location information as the work location. The operation date range of the special patrol plan is: within 2 days after the issuance date of the "Risk Warning Notice", and the work content is the inspection of all relevant faulty components in the work location.

[0043] S130. Obtain historical operating parameters of the faulty component and time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information.

[0044] The historical operation parameters refer to the operation data of the faulty component in the historical time period, and the time information may be the time corresponding to the historical operation parameters. The special patrol time period refers to the time period in which the special patrol can be performed.

[0045] In an embodiment of the present invention, the historical operating parameters include a historical maximum load current and a historical second largest load current, and the obtaining of the historical operating parameters of the fault element and the time information corresponding to the historical operating parameters includes: based on an integrated power grid intelligent operation system, obtaining the historical maximum load current and the historical second largest load current of the fault element within a historical period, and determining the time information of the historical maximum load current and the historical second largest load current.

[0046] Specifically, based on the integrated power grid intelligent system, the maximum load current and the historical second-largest load current of the faulty component in the historical period, as well as the time of the historical maximum load current and the historical second-largest load current can be obtained. For example, the intelligent special patrol system collects the specific time of the maximum load current and the second-largest load current of each faulty component in the special patrol plan within 7 days before the start date of the special patrol plan operation in the integrated power grid operation intelligent system.

[0047] In an embodiment of the present invention, determining at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information includes: counting the occurrence frequencies of the historical maximum load current and the historical second largest load current, and determining at least two special patrol time periods based on the occurrence frequencies and the time information.

[0048] Specifically, a statistical analysis is performed on the times of the maximum load current and the second largest load current within the above 7 days, and the two time periods with the highest and second highest frequencies of the maximum load current and the second largest load current of each faulty component within the 7 days are determined as the optimal time period and alternative time period for special patrol on that day.

[0049] S140. Determine a target inspection time period from at least two special inspection time periods based on weather information of the target location information within at least two special inspection time periods, and control the UAV to go to the target location during the target inspection time period to perform the special inspection task corresponding to the special inspection plan.

[0050] In a preferred embodiment, the two special patrol time periods include a first time period and a second time period, and the target inspection time period is determined from at least two special patrol time periods based on the weather information of the target location information in at least two special patrol time periods, including: determining the weather information of the target location information in the first time period, and if the weather information meets the preset take-off condition, determining the first time period as the target inspection time period; if the weather information of the first time period does not meet the preset take-off condition, determining the weather information of the second time period, and when the weather information of the second time period meets the preset take-off condition, using the second time period as the target time period.

[0051] Among them, the first time period may be the optimal time period for special patrol, the second time period may be an alternative time period, and the target time period may be the time period for finally performing the special patrol task determined from the first time period and the second time period.

[0052] Specifically, within the operating date range of the special patrol plan, the best time period for special patrol is selected every day, and the real-time weather conditions of each work location in the drone patrol system are collected. When the conditions for drone take-off are met, instructions are sent to the drone system, and a drone operation work order is generated to carry out special patrol. If the weather during the best time period for special patrol does not meet the take-off conditions, an alternative time period for special patrol is selected. If the alternative time period still does not meet the conditions, the special patrol is abandoned and a new judgment is made the next day until the special patrol mission is finally completed.

[0053] In a preferred embodiment, after receiving the special patrol plan, the drone system performs the patrol and infrared temperature measurement tasks of the faulty equipment. After completing the special patrol, the drone will transmit the visible light and infrared photos taken back to the drone intelligent special patrol system. The system then automatically compares these photos with the original photos in the equipment library to detect any possible abnormalities or defects. If a defect is found, the system will automatically compile an equipment defect list in accordance with the pre-entered defect description format, and automatically generate and report the defect list in the defect module of the power grid management platform. At the same time, the defect list will also be uploaded to the previous special patrol plan. The advantage of this is that the drone can quickly and efficiently complete the patrol and temperature measurement of the equipment, greatly improving the detection efficiency; through photo comparison, the system can quickly identify the abnormalities or defects of the equipment, reducing the time and error of manual detection. Once a defect is found, the system can quickly compile a defect list and report it to ensure that the problem is handled in a timely manner. Uploading the defect list to the special patrol plan is helpful for information integration and subsequent analysis.

[0054] After the special patrol is completed, the intelligent special patrol system will link the special patrol plan to the risk prevention measures before and during the risk period of the Risk Warning Notice. This is to ensure that the special patrol work can be effectively implemented and recorded before and during the risk period of the power grid. Linking the special patrol plan will help to record and trace the subsequent risk management activities, and facilitate analysis and improvement. By introducing the drone system and the intelligent special patrol system, the efficiency and accuracy of power grid risk management have been significantly improved, while strengthening the implementation of preventive measures and the integrity of the risk management process.

[0055] The technical solution of the embodiment of the present invention, when detecting the issuance of a risk warning notice, obtains the key information in the risk warning notice, determines the target location information corresponding to the faulty component according to the key information and the power grid account information, and generates a special patrol plan for the faulty component based on the location information and the preset processing cycle; obtains the historical operating parameters of the faulty component and the time information corresponding to the historical operating parameters, and determines at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information; determines the target inspection time period from the at least two special patrol time periods according to the weather information of the target location information in at least two special patrol time periods, and controls the drone to go to the target location in the target inspection time period to perform the special patrol task corresponding to the special patrol plan. In the technical solution of the present invention, the risk warning notice is automatically analyzed, and a corresponding special patrol plan is formulated, which solves the problem that the formulation of the special patrol plan in the prior art depends on the experience of the dispatcher and lacks scientificity and accuracy; by determining the weather in the special patrol time period, it is ensured that the drone inspection can be effectively executed. The efficient processing of power grid risks is achieved, the timeliness and comprehensiveness of the inspection are ensured, and the safe operation of the power grid is ensured.

[0056] Embodiment 2

[0057] Figure 2 This is a flowchart of a method for handling power grid risks provided in the second embodiment of the present invention. This embodiment is a preferred embodiment of the above embodiment. The specific implementation method can refer to the technical solution of this embodiment. Among them, the technical terms that are the same or corresponding to the above embodiment are not repeated here. Figure 2 As shown, the method includes:

[0058] S210: When it is detected that a risk warning notice has been issued, key information in the risk warning notice is obtained.

[0059] The key information is information associated with the faulty component.

[0060] S220. Determine the current control level of the faulty component based on the key information, and obtain the original control level corresponding to the faulty component in the differentiated operation and maintenance management module of the power grid management platform.

[0061] Among them, the current control level refers to the control level in the key information, and the original control level refers to the control level set previously.

[0062] Specifically, after determining the current control level, it is necessary to obtain the original control level of the faulty component from the differentiated operation and maintenance management module of the power grid management platform. The purpose is to compare the changes in the control level of the faulty component so as to adjust the operation and maintenance strategy according to the actual situation.

[0063] S230: If the original control level is inconsistent with the current control level, update the original control level based on the current control level.

[0064] S240. Determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and generate a special patrol plan for the faulty component based on the location information and a preset processing cycle.

[0065] Specifically, after the intelligent special patrol system collects the equipment importance (control level) of the faulty component in the "Risk Warning Notice", it will automatically compare it with the original equipment importance of the relatively strained substation equipment and transmission lines in the differentiated operation and maintenance management module of the power grid management platform. If the importance of all substation equipment and transmission lines is consistent with the original one, it will be returned. If the importance of a device or line is inconsistent with the "Risk Warning Notice", then a control level adjustment preparation sheet will be automatically generated in the control level adjustment of the differentiated operation and maintenance management module to adjust the importance of the equipment to be consistent with the "Risk Warning Notice". After the importance adjustment is completed, the latest control level of the equipment will be automatically calculated according to the change in equipment importance and reported to the superior department.

[0066] S250. Obtain historical operating parameters of the faulty component and time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information.

[0067] S260. Determine a target inspection time period from at least two special patrol time periods based on weather information of the target location information within at least two special patrol time periods, and control the UAV to go to the target location during the target inspection time period to perform the special patrol task corresponding to the special patrol plan.

[0068] S270. If the current control level is higher than the original control level, determine whether to add a daily inspection plan and the execution period of the daily inspection plan based on the difference between the risk release date, the risk start date and the preset value of the faulty component.

[0069] Specifically, after the intelligent special patrol system adjusts the control level of the faulty component in the differentiated operation and maintenance management module, if the control level is higher than the original control level, one or more daily patrol plans will be added to the maintenance and repair management module of the power grid management platform according to different control time periods, and ordinary daily patrols will be carried out according to the plan. The calculation rule for the number of new plans is:

[0070] When the control level is adjusted from Level IV to Level III, if (risk relief date - risk start date - 14 days) < 0, no Level III inspection plan for the equipment will be added; if (risk relief date - risk start date - 14 days) > 0, starting from the risk start date, a new Level III inspection plan for the equipment will be added every 14 days, and no new plan will be added if the days are less than 14 days.

[0071] When the control level is adjusted from Level IV to Level II, if (risk relief date - risk start date - 7 days) is less than 0, no Level II inspection plan for the equipment will be added; if (risk relief date - risk start date - 7 days) is greater than 0, a new Level III inspection plan for the equipment will be added every 7 days starting from the risk start date, and no new plan will be added if the period is less than 14 days.

[0072] When the control level is adjusted from Level III to Level II, if (risk relief date - risk start date - 7 days) < 0, no Level II inspection plan for the equipment will be added; if (risk relief date - risk start date - 7 days) > 0, starting from the risk start date, a new Level II inspection plan for the equipment will be added every 7 days, and no new plan will be added if the time is less than 7 days.

[0073] When the control level is adjusted from Level III to Level I, if (risk relief date - risk start date - 1 day) ≤ 0, no Level II inspection plan for the equipment will be added; if (risk relief date - risk start date - 1 day) > 0, starting from the risk start date, a new Level II inspection plan for the equipment will be added every 1 day, and no new plan will be added if the time is less than 1 day.

[0074] When the control level is adjusted from Level II to Level I, if (risk relief date - risk start date - 1 day) ≤ 0, no Level II inspection plan for the equipment will be added; if (risk relief date - risk start date - 1 day) > 0, starting from the risk start date, a new Level II inspection plan for the equipment will be added every 1 day, and no new plan will be added if the time is less than 1 day.

[0075] According to the changes in different control levels, the corresponding rules for increasing the patrol plan are determined. According to the rules, the ordinary daily patrol plan is appropriately increased to facilitate the timely and efficient periodic inspection of components that may have faults in the power grid to ensure the safe operation of the power grid.

[0076] The technical solution of the embodiment of the present invention, when detecting the issuance of a risk warning notice, obtains the key information in the risk warning notice, determines the target location information corresponding to the faulty component according to the key information and the power grid account information, and generates a special patrol plan for the faulty component based on the location information and the preset processing cycle; obtains the historical operating parameters of the faulty component and the time information corresponding to the historical operating parameters, and determines at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information; determines the target inspection time period from the at least two special patrol time periods according to the weather information of the target location information in at least two special patrol time periods, and controls the drone to go to the target location in the target inspection time period to perform the special patrol task corresponding to the special patrol plan. In the technical solution of the present invention, the risk warning notice is automatically analyzed, and a corresponding special patrol plan is formulated, which solves the problem that the formulation of the special patrol plan in the prior art depends on the experience of the dispatcher and lacks scientificity and accuracy; by determining the weather in the special patrol time period, it is ensured that the drone inspection can be effectively executed. The efficient processing of power grid risks is achieved, the timeliness and comprehensiveness of the inspection are ensured, and the safe operation of the power grid is ensured.

[0077] Embodiment 3

[0078] Figure 3 This is a schematic diagram of the structure of a power grid risk processing device provided in Embodiment 3 of the present invention. Figure 3 As shown, the device comprises:

[0079] The key information acquisition module 310 is used to acquire key information in the risk warning notice when detecting that the risk warning notice is issued, wherein the key information is information associated with the faulty component;

[0080] A special patrol plan generating module 320 is used to determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and to generate a special patrol plan for the faulty component based on the location information and a preset processing cycle;

[0081] A special patrol time determination module 330 is used to obtain the historical operating parameters of the faulty component and the time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information;

[0082] The special patrol task execution module 340 is used to determine a target patrol time period from at least two special patrol time periods based on weather information of the target location information within at least two of the special patrol time periods, and control the UAV to go to the target location during the target patrol time period to perform the special patrol task corresponding to the special patrol plan.

[0083] Optionally, the key information acquisition module 310 is specifically used to:

[0084] The basic risk module of the power grid management platform is monitored through the intelligent special patrol system, and when a risk warning notice is detected, key information in the risk warning notice is collected;

[0085] The key information includes at least one of the risk name and number, substation name and interval dual number in the faulty component, transmission line name, equipment importance, important users, risk start date, risk relief date and release date.

[0086] Optionally, the special patrol plan generating module 320 includes:

[0087] The target location information determination module is used to query the transmission station ledger and the substation ledger in the ledger query management module of the power grid management platform based on the key information, and determine the target location information corresponding to the faulty component according to the transmission station ledger and the substation ledger.

[0088] Optionally, the special patrol plan generating module 320 further includes:

[0089] The special patrol plan generation submodule is used to generate at least one special patrol plan through the maintenance management module in the power grid management platform according to the target location information and the preset period.

[0090] Optionally, the historical operating parameters include a historical maximum load current and a historical second-largest load current, and the special patrol time determination module 330 includes:

[0091] The acquisition submodule is used to obtain the historical maximum load current and the historical second largest load current of the faulty component within the historical period based on the integrated power grid intelligent operation system, and determine the time information of the historical maximum load current and the historical second largest load current.

[0092] Optionally, the special patrol time determination module 330 includes:

[0093] The special patrol time period determination submodule is used to count the occurrence frequencies of the historical maximum load current and the historical second largest load current, and determine at least two of the special patrol time periods based on the occurrence frequencies and the time information.

[0094] Optionally, the two special patrol time periods include a first time period and a second time period, and the special patrol task execution module 340 is specifically used to:

[0095] Determine the weather information of the target location information in the first time period, and if the weather information meets the preset take-off condition, determine the first time period as the target inspection time period;

[0096] If the weather information of the first time period does not meet the preset take-off condition, the weather information of the second time period is determined, and when the weather information of the second time period meets the preset take-off condition, the second time period is used as the target time period.

[0097] Optionally, the device further includes: an updating module, configured to determine the current control level of the faulty component based on the key information after obtaining the key information in the risk warning notice, and obtain the original control level corresponding to the faulty component in the differentiated operation and maintenance management module of the power grid management platform;

[0098] If the original control level is inconsistent with the current control level, the original control level is updated based on the current control level.

[0099] Optionally, the device further comprises: a daily patrol plan determination module, which is used to:

[0100] If the current control level is higher than the original control level, it is determined whether to increase the daily inspection plan and the execution period of the daily inspection plan based on the difference between the risk relief date, the risk start date and the preset value of the faulty component.

[0101] The power grid risk processing device provided in the embodiment of the present invention can execute the power grid risk processing method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.

[0102] Embodiment 4

[0103] Figure 4 A schematic diagram of the structure of an electronic device provided for Embodiment 4 of the present invention. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device may also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.), and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.

[0104] like Figure 4 As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.

[0105] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0106] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as a method for processing power grid risks.

[0107] In some embodiments, the method for processing power grid risk may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the method for processing power grid risk described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to execute the method for processing power grid risk in any other appropriate manner (e.g., by means of firmware).

[0108] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0109] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0110] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0111] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0112] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0113] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.

[0114] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0115] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for handling power grid risks, characterized in that: include: When it is detected that a risk warning notice is issued, key information in the risk warning notice is obtained, wherein the key information is information associated with the faulty component; Determine the target location information corresponding to the faulty component according to the key information and the power grid ledger information, and generate a special patrol plan for the faulty component based on the location information and a preset processing cycle; Acquire historical operating parameters of the faulty component and time information corresponding to the historical operating parameters, and determine at least two special patrol time periods corresponding to the special patrol plan based on the historical operating parameters and the time information; According to the weather information of the target location information within at least two of the special patrol time periods, a target patrol time period is determined from the at least two special patrol time periods, and the UAV is controlled to go to the target location within the target patrol time period to perform the special patrol task corresponding to the special patrol plan.

2. The method according to claim 1, characterized in that When the risk warning notice is detected, key information in the risk warning notice is obtained, including: The basic risk module of the power grid management platform is monitored through the intelligent special patrol system, and when a risk warning notice is detected, key information in the risk warning notice is collected; The key information includes at least one of the risk name and number, the substation name and the double number of the interval in the faulty component, the transmission line name, the importance of the equipment, important users, the risk start date, the risk relief date and the release date.

3. The method according to claim 2, characterized in that The determining the target location information corresponding to the faulty component according to the key information and the power grid ledger information includes: Based on the key information, the transmission station ledger and the substation ledger are queried in the ledger query management module of the power grid management platform, and the target location information corresponding to the faulty component is determined according to the transmission station ledger and the substation ledger.

4. The method according to claim 2, characterized in that: The generating of the special patrol plan of the faulty component based on the location information and the preset processing cycle also includes: According to the target location information and the preset period, at least one special patrol plan is generated through the maintenance management module in the power grid management platform.

5. The method according to claim 1, characterized in that The historical operating parameters include a historical maximum load current and a historical second-largest load current, and the acquiring of the historical operating parameters of the faulty component and time information corresponding to the historical operating parameters includes: Based on the integrated power grid intelligent operation system, the historical maximum load current and the historical second largest load current of the faulty component in the historical period are obtained, and the time information of the historical maximum load current and the historical second largest load current is determined.

6. The method according to claim 5, characterized in that The determining, based on the historical operation parameters and the time information, at least two special patrol time periods corresponding to the special patrol plan includes: The occurrence frequencies of the historical maximum load current and the historical second-largest load current are counted, and at least two of the special patrol time periods are determined based on the occurrence frequencies and the time information.

7. The method according to claim 1, characterized in that The two special patrol time periods include a first time period and a second time period, and the target inspection time period is determined from the at least two special patrol time periods according to weather information of the target location information in at least two special patrol time periods, including: Determine the weather information of the target location information in the first time period, and if the weather information meets the preset take-off condition, determine the first time period as the target inspection time period; If the weather information of the first time period does not meet the preset take-off condition, the weather information of the second time period is determined, and when the weather information of the second time period meets the preset take-off condition, the second time period is used as the target time period.

8. The method according to claim 2, characterized in that: After obtaining the key information in the risk warning notice, the following is also included: Determine the current control level of the faulty component based on the key information, and obtain the original control level corresponding to the faulty component in the differentiated operation and maintenance management module of the power grid management platform; If the original control level is inconsistent with the current control level, the original control level is updated based on the current control level.

9. The method according to claim 8, characterized in that Also includes: If the current control level is higher than the original control level, it is determined whether to increase the daily inspection plan and the execution period of the daily inspection plan based on the difference between the risk relief date, the risk start date and the preset value of the faulty component.

10. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for processing power grid risks according to any one of claims 1 to 9.