Central heating energy-saving control device

By using a high-pressure sealed box in the central heating system to prevent water leakage between the heat exchanger's hot drain port and the conveying pipeline, the problem of waste of water resources caused by internal pressure difference is solved, and the energy-saving effect is achieved.

CN118896320APending Publication Date: 2024-11-05HUANENG LANZHOU XINQU THERMAL POWER CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411130186.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

In the central heating system, the internal pressure difference between the high-temperature drain port of the heat exchanger and the conveying pipeline leads to water seepage, resulting in cold water loss and waste of water resources.

Method used

A centralized heating energy-saving control device including a first high-pressure sealed box and a heat exchanger box is designed, and a first lower box and a first upper box are arranged at the heat exchanger heat drain port and the entrance pipe interface, and Inject high-pressure gas so that the internal pressure is greater than the pressure between the hot drain and the inlet pipe, and use high-pressure gas to prevent water leakage.

Benefits of technology

It effectively prevents water leakage between the heat exchanger's hot drain outlet and the inlet pipe, reduces the waste of water resources, and improves the energy-saving effect of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118896320A_ABST
    Figure CN118896320A_ABST
Patent Text Reader

Abstract

The centralized heating energy-saving control device is characterized in that a first high-pressure sealing box comprises a first lower box body and a first upper box body, the first upper box body is arranged at the top of the first lower box body, and a first air inlet connector is arranged on the side, away from the first upper box body, of the first lower box body; a first exhaust connector is arranged on the side, away from the first lower box body, of the first upper box body. A first lower box body and a first upper box body wrap a joint of a hot water outlet of a heat exchanger and a home-entry pipeline, and high-pressure gas is injected into the first lower box body and the first upper box body, so that the gas in the first lower box body and the first upper box body is larger than the internal pressure between the hot water outlet and the home-entry pipeline; the device can solve the problems that a gap is formed between a high-temperature drainage connector and a conveying pipeline due to internal pressure, water seepage occurs in the long-time use process, and cold water loss is caused by water seepage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of centralized heating and relates to a centralized heating energy-saving control device. Background Art

[0002] Central heating refers to the way in which steam and hot water generated by centralized heat sources are supplied to a city (town) or part of a region through a pipeline network for production, heating and living. Central heating is one of the basic infrastructures of modern cities and an important facility of urban public utilities.

[0003] Central heating is generally composed of a heating station, a heat exchange station and a user end. The heating station heats water through a boiler and transports it to the heat exchange station. The cold water at the user end exchanges heat with the hot water at the heating station through the heat exchange station. After the heat exchange, the cold water becomes hot water and is transported to the user end for heating. In this process, the heat exchange station plays an important role. The heat exchange station exchanges heat between the heating end and the user end through a heat exchanger. Four interfaces are provided on the heat exchanger, namely, a high-temperature water inlet interface and a low-temperature interface connected to the heating station, and a cold water interface and a high-temperature drainage interface connected to the user end. After the heat exchange, the cold water is discharged from the high-temperature drainage interface and transported to the user end. Since the water heats up after the heat exchange, an increased internal pressure is formed at the high-temperature drainage interface and the transportation pipeline connected to the high-temperature drainage interface. The internal pressure will cause a gap to be formed between the high-temperature drainage interface and the transportation pipeline. Water seepage will occur during long-term use, and water seepage will cause the loss of cold water. Therefore, cold water needs to be replenished frequently, resulting in a waste of water resources. Summary of the invention

[0004] The purpose of the present invention is to overcome the shortcomings of the above-mentioned prior art and provide a centralized heating energy-saving control device, which can prevent the internal pressure from causing a gap to form between the high-temperature drainage interface and the delivery pipeline, and cause water seepage during long-term use, thereby causing the problem of cold water loss.

[0005] To achieve the above object, the present invention discloses a centralized heating energy-saving control device, comprising a heat exchanger and a first high-pressure sealed box arranged on a heat drain port of the heat exchanger, wherein the first high-pressure sealed box comprises a first lower box body and a first upper box body, wherein the first upper box body is arranged on the top of the first lower box body, a first air inlet joint is arranged on a side of the first lower box body away from the first upper box body, and a first air exhaust joint is arranged on a side of the first upper box body away from the first lower box body;

[0006] The first lower box body and the first upper box body are covered at the interface between the hot water outlet of the heat exchanger and the house inlet pipe, and high-pressure gas is injected into the first lower box body and the first upper box body, so that the gas in the first lower box body and the first upper box body is greater than the internal pressure between the hot water outlet and the house inlet pipe.

[0007] A first sealing ring is arranged at the groove of the side wall of the first lower box body, and the first sealing ring is a semicircular sealing ring. A second sealing ring is arranged at the groove of the side wall of the first upper box body, and the second sealing ring is a semicircular sealing ring. The second sealing ring and the first sealing ring are combined into a circular sealing ring.

[0008] A first connection block is disposed around the side wall of the first lower box body, and a second connection block is disposed around the side wall of the first upper box body, and the second connection block is connected to the first connection block.

[0009] A heat exchange box is arranged at the low-temperature drain outlet of the heat exchanger, and the heat exchange box includes a second lower box body, a second upper box body and a spiral heat exchange tube. The second upper box body is arranged on the top of the second lower box body, and the spiral heat exchange tube is arranged in the second lower box body and the second upper box body. The two ends of the spiral heat exchange tube pass through the bottom of the second lower box body and the top of the second upper box body respectively.

[0010] The side walls of the second lower box are surrounded by third connection blocks, the inner cavity of the second lower box is provided with a first spiral connection groove, the inner cavity bottom of the second lower box is provided with a first connection hole, and the side walls of the third connection block are surrounded by sealing grooves.

[0011] A fourth connecting block is arranged around the side wall of the second upper box body, and the fourth connecting block is connected to the third connecting block. A second spiral connecting groove is opened in the inner cavity of the second upper box body, and the second spiral connecting groove matches the first spiral connecting groove. A second connecting hole is opened at the top of the inner cavity of the second upper box body. A sealing block is arranged around the side wall of the third connecting block, and the sealing block matches the sealing groove.

[0012] The spiral heat exchange tube includes a spiral tube, a second air inlet connector and a second exhaust connector. The spiral tube matches the first spiral connecting groove and the second spiral connecting groove. The spiral tube is arranged in the second lower box body and the second upper box body through the first spiral connecting groove and the second spiral connecting groove. The second air inlet connector is arranged at the air inlet end of the spiral tube, and the second air inlet connector matches the second connecting hole. The second exhaust connector is arranged at the exhaust end of the spiral tube, and the second exhaust connector matches the first connecting hole.

[0013] An air pump is connected between the heat exchange box and the first high-pressure sealed box, the air inlet end of the air pump is connected to the second exhaust joint, and the exhaust end of the air pump is connected to the first air inlet joint.

[0014] A second high-pressure sealed box is provided at the cold end water inlet of the heat exchanger, the second high-pressure sealed box comprises a third lower box body and a third upper box body, the third upper box body is provided on the top of the third lower box body;

[0015] A third sealing ring is arranged at the groove of the side wall of the third lower box, and the third sealing ring is a semicircular sealing ring. A third air inlet joint is arranged at the bottom of the third lower box, and a fifth connecting block is arranged around the side wall of the third lower box. The third air inlet joint is connected to the first exhaust joint through a pipeline.

[0016] A fourth sealing ring is arranged at the groove on the side wall of the third upper box body, and the fourth sealing ring is a semicircular sealing ring. The fourth sealing ring and the third sealing ring are combined into a full-circular sealing ring. A third exhaust joint is arranged on the top of the third upper box body, and the third exhaust joint is connected to the second air intake joint through a pipe. Sixth connecting blocks are arranged around the side walls of the third upper box body, and the sixth connecting block is connected to the fifth connecting block.

[0017] A preheating box is provided at the cold end water inlet of the heat exchanger, and the preheating box comprises a fourth lower box body and a fourth upper box body, and the fourth upper box body is provided on the top of the fourth lower box body;

[0018] A fifth sealing ring is provided at the groove of the side wall of the fourth lower box, and the fifth sealing ring is a semicircular sealing ring. A seventh connecting block is provided around the side wall of the fourth lower box, and a fourth air inlet connector is provided at the bottom of the fourth lower box, and the fourth air inlet connector is connected to the exhaust end of the air pump through a pipeline;

[0019] A sixth sealing ring is arranged at the groove on the side wall of the fourth upper box body, and the sixth sealing ring is a semicircular sealing ring. The sixth sealing ring and the fifth sealing ring are combined into a full-circle sealing ring. An eighth connecting block is arranged around the side wall of the fourth upper box body, and the eighth connecting block is connected to the seventh connecting block. A fourth exhaust joint is arranged on the top of the fourth upper box body, and the fourth exhaust joint is connected to the second air intake joint through a pipe.

[0020] The present invention has the following beneficial effects:

[0021] During specific operation, the centralized heating energy-saving control device described in the present invention covers the interface between the hot water outlet of the heat exchanger and the house inlet pipe through the first lower box body and the first upper box body, and injects high-pressure gas into the first lower box body and the first upper box body, so that the gas in the inner cavity of the first lower box body and the first upper box body is greater than the internal pressure between the hot water outlet and the house inlet pipe. The high pressure is used to prevent water leakage between the hot water outlet of the heat exchanger and the house inlet pipe, thereby reducing the waste of water resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a structural schematic diagram of the present invention;

[0023] Figure 2 It is a structural schematic diagram of the first high-pressure sealing box in the present invention;

[0024] Figure 3 It is a structural schematic diagram of the heat exchange box in the present invention;

[0025] Figure 4 It is a structural schematic diagram of the second lower box body in the present invention;

[0026] Figure 5 It is a structural schematic diagram of the second upper box body in the present invention;

[0027] Figure 6 It is a schematic diagram of the structure of the spiral heat exchange tube in the present invention;

[0028] Figure 7 It is a structural schematic diagram of the second high-pressure sealing box in the present invention;

[0029] Figure 8 It is a structural schematic diagram of the preheating box in the present invention;

[0030] Fig. 9 It is a schematic diagram of the arrangement of the fourth lower box body and the fourth air intake connector in the present invention.

[0031] Among them, 100 is a first high-pressure sealed box, 110 is a first lower box, 111 is a first sealing ring, 112 is a first air inlet joint, 113 is a first connecting block, 120 is a first upper box, 121 is a second sealing ring, 122 is a first exhaust joint, 123 is a second connecting block, 200 is a heat exchange box, 210 is a second lower box, 211 is a third connecting block, 212 is a first spiral connecting groove, 213 is a first connecting hole, 214 is a sealing groove, 220 is a second upper box, 221 is a fourth connecting block, 222 is a second spiral connecting groove, 223 is a second connecting hole, 224 is a sealing block, 230 is a spiral heat exchange tube, 231 It is a spiral tube, 232 is the second air inlet connector, 233 is the second exhaust connector, 300 is an air pump, 400 is a second high-pressure sealing box, 410 is a third lower box body, 411 is a third sealing ring, 412 is a third air inlet connector, 413 is a fifth connecting block, 420 is a third upper box body, 421 is a fourth sealing ring, 422 is a third exhaust connector, 423 is a sixth connecting block, 500 is a preheating box, 510 is a fourth lower box body, 511 is a fifth sealing ring, 512 is a seventh connecting block, 513 is a fourth air inlet connector, 520 is a fourth upper box body, 521 is a sixth sealing ring, 522 is an eighth connecting block, and 523 is a fourth exhaust connector. DETAILED DESCRIPTION

[0032] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiment of the present invention. Obviously, the described embodiment is only an embodiment of a part of the present invention, not all embodiments, and is not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concepts disclosed in the present invention. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present invention.

[0033] The accompanying drawings show schematic diagrams of structures according to embodiments disclosed in the present invention. These figures are not drawn to scale, and some details are magnified and some details may be omitted for the purpose of clear expression. The shapes of various regions and layers shown in the figures and the relative sizes and positional relationships therebetween are only exemplary, and may deviate in practice due to manufacturing tolerances or technical limitations, and those skilled in the art may additionally design regions / layers with different shapes, sizes, and relative positions according to actual needs.

[0034] Embodiment 1

[0035] The present invention provides a centralized heating energy-saving control device, which is covered between the hot water outlet of the heat exchanger and the interface of the household pipe by the first lower box 110 and the first upper box 120, and high-pressure gas is injected into the first lower box 110 and the first upper box 120, so that the gas in the first lower box 110 and the first upper box 120 is greater than the internal pressure between the hot water outlet and the household pipe, and the high pressure is used to prevent water leakage between the hot water outlet of the heat exchanger and the household pipe, thereby reducing the waste of water resources. Please refer to Figure 1 , including a first high-pressure sealing box 100;

[0036] See also Figure 1-2The first high-pressure sealed box 100 includes a first lower box body 110 and a first upper box body 120. The first upper box body 120 is arranged on the top of the first lower box body 110. A first air inlet connector 112 is arranged on the side of the first lower box body 110 away from the first upper box body 120. A first exhaust connector 122 is arranged on the side of the first upper box body 120 away from the first lower box body 110. There are four interfaces on the heat exchanger in the heat exchange station, two of which are connected to the heating station, and the other two interfaces are connected to the user end. Among them, the two interfaces connected to the heating station are respectively a high-temperature water inlet interface and a low-temperature interface. The heating station heats the water and transports it to the high-temperature water inlet interface through a pipeline, and then enters the heat exchanger through the high-temperature water inlet interface and connects to the user end. The cold water at the user end is heat exchanged, and the water with lowered temperature after heat exchange enters the delivery pipe through the low-temperature interface and flows back to the heating station for heating, and then circulates back to the heat exchange station. The two interfaces connected to the user end are the cold water interface and the high-temperature drainage interface. The cold water at the user end enters the heat exchanger through the cold water interface and exchanges heat with the hot water provided by the heating station. The cold water is heated after heat exchange, and the heated water is discharged from the high-temperature drainage interface into the delivery pipe and then delivered to the user end to provide heat to the user. The water after heating the user is cooled down and then delivered to the cold water interface through the delivery pipe again, and enters the heat exchanger through the cold water interface for heat exchange, so as to circulate and provide heat to the user. The first lower box 110 and the first upper box 120 are the same size. The hollow rectangular box body of the present invention is a hollow rectangular box body, the first upper box body 120 covers the top of the first lower box body 110 to form a sealed box body, the box body formed by the first upper box body 120 and the first lower box body 110 is coated on the connection between the high-temperature drainage interface of the heat exchanger and the delivery pipeline, and the connection between the first lower box body 110 and the first upper box body 120 and the high-temperature drainage interface and the delivery pipeline is sealed, the first air inlet joint 112 is integrally formed on the side of the first lower box body 110 away from the first upper box body 120, the first exhaust joint 122 is integrally formed on the side of the first upper box body 120 away from the first lower box body 110, and the side of the first air inlet joint 112 away from the first lower box body 110 is equipped with a pumping device, through the pumping device and the first An air inlet joint 112 is used in cooperation to pump air into the space between the first lower box body 110 and the first upper box body 120. A pressure relief valve is installed on the side of the first air inlet joint 112 away from the first upper box body 120 through a flange connection. Before use, the threshold of the pressure relief valve is set so that the threshold of the pressure relief valve is greater than the internal pressure between the high-temperature drainage interface and the delivery pipeline. Air is pumped into the space between the first lower box body 110 and the first upper box body 120 through the air pumping device, so that the space between the first lower box body 110 and the first upper box body 120 is in a high-pressure state, and the pressure value is greater than the internal pressure between the high-temperature drainage interface and the delivery pipeline. The external high pressure is used to prevent water from leaking from the connection between the high-temperature drainage interface and the delivery pipeline, thereby saving water resources.When the pressure inside the first lower box 110 and the first upper box 120 is greater than the threshold value set by the pressure relief valve, the pressure between the first lower box 110 and the first upper box 120 is relieved through the pressure relief valve until the pressure inside the space between the first lower box 110 and the first upper box 120 is less than the pressure relief threshold value of the pressure relief valve.

[0037] See also Figure 1-2 A first sealing ring 111 is provided at the groove of the side wall of the first lower box 110, and the first sealing ring 111 is a semicircular sealing ring. A second sealing ring 121 is provided at the groove of the side wall of the first upper box 120, and the second sealing ring 121 is a semicircular sealing ring. The second sealing ring 121 and the first sealing ring 111 are combined into a full-circular sealing ring. A first connecting block 113 is provided around the side wall of the first lower box 110, and a second connecting block 213 is provided around the side wall of the first upper box 120, and the second connecting block 213 is connected to the first connecting block 113. Arc grooves are provided on the left and right sides of the first lower box 110, and arc grooves are also provided on the left and right sides of the first upper box 120. The arc groove on the first lower box 110 can be connected with the arc groove on the first upper box 120 to form a complete circular groove. The first sealing ring 111 is embedded in the arc groove on the first lower box 110, and the second sealing ring 121 is embedded in the arc groove on the first lower box 110. In the arc groove on the first upper box body 120, the first sealing ring 111 and the second sealing ring 121 are connected to the high-temperature drainage interface and the delivery pipeline respectively, and the space between the first lower box body 110 and the first upper box body 120 is sealed by the first sealing ring 111 and the second sealing ring 121, the first connecting block 113 is integrally formed at the top of the outer wall of the first lower box body 110, and the second connecting block 123 is integrally formed at the bottom of the outer wall of the first upper box body 120, the top of the first connecting block 113 contacts the bottom of the second connecting block 123, and the first connecting block 113 and the second connecting block 123 are sealed, and the second connecting block 123 is detachably mounted on the first connecting block 113 by bolts, and the first upper box body 120 is mounted on the top of the first lower box body 110 through the second connecting block 123 and the first connecting block 113, and the first lower box body 110 and the first upper box body 120 are sealed.

[0038] See also Figure 1-6A heat exchange box 200 is arranged at the low-temperature drain outlet of the heat exchanger. The heat exchange box 200 includes a second lower box body 210, a second upper box body 220 and a spiral heat exchange tube 230. The second upper box body 220 is arranged on the top of the second lower box body 210. The middle part of the spiral heat exchange tube 230 is arranged in the second lower box body 210 and the second upper box body 220. The two ends of the spiral heat exchange tube 230 pass through the bottom of the second lower box body 210 and the top of the second upper box body 220 respectively. A third connecting block 211 is arranged around the side wall of the second lower box body 210. A first spiral connecting groove 212 is provided in the inner cavity of the second lower box body 210. A first connecting hole 213 is provided at the bottom of the inner cavity of the second lower box body 210. A sealing groove 214 is provided around the side wall of the third connecting block 211. The side wall of the second upper box body 220 is provided with a fourth connecting block 221, and the fourth connecting block 221 is connected to the third connecting block 211. The inner cavity of the second upper box body 220 is provided with a second spiral connecting groove 222, and the second spiral connecting groove 222 matches the first spiral connecting groove 212. A second connecting hole 223 is provided at the top of the inner cavity of the second upper box body 220. The side wall of the third connecting block 211 is provided with a sealing block 224, and the sealing block 224 matches the sealing groove 214. The spiral heat exchange tube 230 includes a spiral tube 231, a second air inlet connector 232 and a second exhaust connector 233. The spiral tube 231 matches the first spiral connecting groove 212 and the second spiral connecting groove 222. The spiral tube 231 passes through the first spiral connecting groove 212 and The second spiral connecting groove 222 is arranged in the second lower box body 210 and the second upper box body 220, the second air inlet joint 232 is arranged at the air inlet end of the spiral tube 231, the second air inlet joint 232 matches the second connecting hole 223, the second exhaust joint 233 is arranged at the exhaust end of the spiral tube 231, the second exhaust joint 233 matches the first connecting hole 213, the air pump 300 is connected to the first high-pressure sealed box 100 through a pipeline, the air inlet end of the air pump 300 is connected to the second exhaust joint 233 through a pipeline, the exhaust end of the air pump 300 is connected to the first air inlet joint 112 through a pipeline, the spiral tube 231 matches the first spiral connecting groove 212 and the second spiral connecting groove 222 respectively, and the spiral tube 231 is connected to the first The spiral connection groove 212 and the second spiral connection groove 222 are embedded between the second lower box 210 and the second upper box 220. The second air inlet joint 232 is sleeved on the delivery pipe connected to the low-temperature interface on the heat exchanger. The delivery pipe at this location is specially treated. The delivery pipe at this location is composed of three parts, namely, insulation pipes at both ends and a short section of pipe made of high thermal conductivity material matching the length of the spiral tube 231. The spiral tube 231 is connected to the pipe made of high thermal conductivity material for heat exchange to heat the gas injected into the inner cavity of the spiral tube 231. The second lower box 210 and the second upper box 220 are both made of insulation material to avoid temperature leakage. The third connection block 211 is integrally formed on the top of the outer wall of the second lower box 210.The sealing groove 214 is provided at the top of the third connecting block 211, the fourth connecting block 221 is integrally formed at the bottom of the outer wall of the second upper box body 220, the sealing block 224 is integrally formed at the bottom of the fourth connecting block 221, the sealing block 224 is inserted into the inner cavity of the sealing groove 214, the sealing block 224 and the sealing groove 214 are sealed, the fourth connecting block 221 corresponds to the third connecting block 211, the fourth connecting block 221 is detachably mounted on the third connecting block 211 by the use of bolts and nuts, the second upper box body 220 is mounted on the second lower box body 210 by the use of the fourth connecting block 221 and the third connecting block 211, the second lower box body 210 and the second upper box body 220 are covered on the conveying pipeline, the second lower box body 210 and the second upper box body 220 are both sealed with the conveying pipeline, the second air inlet joint 232 and the second exhaust joint 23 3 are respectively integrated on the air inlet end and the air outlet end of the spiral tube 231, the second air inlet joint 232 matches the second connection hole 223, the second air inlet joint 232 penetrates the second connection hole 223 and is plugged into the outer side of the second upper box 220, the second air inlet joint 232 and the second connection hole 223 are sealed, the second exhaust joint 233 matches the first connection hole 213, the second exhaust joint 233 penetrates the first connection hole 213 and is plugged into the outer side of the second lower box 210, the second exhaust joint 233 and the first connection hole 213 are sealed, the second exhaust joint 233 is connected to the air pump 300 through a pipeline, the gas in the inner cavity of the spiral tube 231 is heated after heat exchange with the delivery pipeline and is delivered to the inner cavity of the first lower box 110 and the first upper box 120 through the air pump 300, and the high-temperature drainage interface on the heat exchanger and the delivery pipeline are kept warm.

[0039] See also Figure 1-7A second high-pressure sealed box 400 is arranged at the water inlet of the cold end of the heat exchanger. The second high-pressure sealed box 400 includes a third lower box body 410 and a third upper box body 420. The third upper box body 420 is arranged on the top of the third lower box body 410. A third sealing ring 411 is arranged at the side wall groove of the third lower box body 410. The third sealing ring 411 is a semicircular sealing ring. A third air inlet connector 412 is arranged at the bottom of the third lower box body 410. A fifth connecting block 413 is arranged around the side wall of the third lower box body 410. The third air inlet connector 412 is connected to the first exhaust connector 122 through a pipeline. A fourth sealing ring 421 is arranged at the side wall groove of the third upper box body 420. The fourth sealing ring 421 The fourth sealing ring 421 and the third sealing ring 411 are combined into a full-circle sealing ring. The third upper box body 420 is provided with a third exhaust joint 422 on the top, and the third exhaust joint 422 is connected to the second air inlet joint 232 through a pipeline. The side wall of the third upper box body 420 is provided with a sixth connecting block 423 around, and the sixth connecting block 423 is connected to the fifth connecting block 413. The structure of the second high-pressure sealed box 400 is the same as that of the first high-pressure sealed box 100, except that the second high-pressure sealed box 400 is installed on the cold water interface and the delivery pipeline on the heat exchanger, and the connection method between the second high-pressure sealed box 400 and the cold water interface and the delivery pipeline on the heat exchanger is the same as that of the first high-pressure sealed box. 100 is connected in the same manner as the high-temperature drainage pipe and the delivery pipe, which will not be described in detail here. Here, only the connection structure between the second high-pressure sealed box 400 and the first high-pressure sealed box 100 and the heat exchange box 200 is simply described. The third air inlet joint 412 is connected to the pressure relief valve on the first exhaust joint 122 through a pipe. The excess gas in the inner cavity of the first lower box body 110 and the first upper box body 120 is transported to the inner cavity of the third lower box body 410 and the third upper box body 420 through a pipe to perform high-pressure sealing on the cold water interface and the delivery pipe connection to avoid water seepage. Because the gas in the inner cavity of the first lower box body 110 and the first upper box body 120 is connected to the low The high-temperature gas after heat exchange in the delivery pipeline at the temperature interface, therefore, the gas delivered to the inner cavity of the third lower box body 410 and the third upper box body 420 can preheat the water passing through the cold water section at its own temperature and the temperature formed under high pressure, thereby improving the heat exchange efficiency of the cold water, and a pressure relief valve is also installed on the end of the third exhaust joint 422 away from the third upper box body 420 to prevent the pressure in the inner cavity of the third lower box body 410 and the third upper box body 420 from being too high. The pressure relief valve on the third exhaust joint 422 is connected to the second air inlet joint 232 through a pipeline, and the excess gas in the inner cavity of the third lower box body 410 and the third upper box body 420 enters the inner cavity of the spiral tube 231 through the pressure relief valve for circulation heat exchange.

[0040] See also Figure 1 and Figure 8-9A preheating box 500 is provided at the water inlet of the cold end of the heat exchanger. The preheating box 500 includes a fourth lower box body 510 and a fourth upper box body 520. The fourth upper box body 520 is arranged on the top of the fourth lower box body 510. A fifth sealing ring 511 is provided at the groove of the side wall of the fourth lower box body 510. The fifth sealing ring 511 is a semicircular sealing ring. A seventh connecting block 512 is provided around the side wall of the fourth lower box body 510. A fourth air inlet connector 513 is provided at the bottom of the fourth lower box body 510. The fourth air inlet connector 513 is connected to the exhaust end of the air pump 300 through a pipeline. A sixth sealing ring 521 is provided at the groove of the side wall of the fourth upper box body 520. The sixth sealing ring 521 is a semicircular sealing ring. The sixth sealing ring 521 is combined with the fifth sealing ring 511 The fourth upper box 520 is provided with an eighth connecting block 522 around the side wall, and the eighth connecting block 522 is connected to the seventh connecting block 512. The top of the fourth upper box 520 is provided with a fourth exhaust joint 523, and the fourth exhaust joint 523 is connected to the second air inlet joint 232 through a pipeline. The fourth upper box 520 is installed on the top of the fourth lower box 510. An installation space is formed between the fourth lower box 510 and the fourth upper box 520, and the space covers the delivery pipeline connected to the cold water interface of the heat exchanger. The delivery pipeline here is the same as the delivery pipeline connected to the low-temperature interface on the heat exchanger, and is also made of two insulation pipes and a short section of high thermal conductivity material matching the length of the fourth lower box 510 and the fourth upper box 520. The heat-conducting pipe is composed of a seventh connecting block 512 integrally formed at the top of the side wall of the fifth sealing ring 511, and the eighth connecting block 522 is integrally formed at the bottom of the side wall of the sixth sealing ring 521. The eighth connecting block 522 is detachably mounted on the top of the fifth sealing ring 511 by bolts. The fourth upper box body 520 is mounted on the top of the fourth lower box body 510 by the cooperation of the eighth connecting block 522 and the fifth sealing ring 511. The fifth sealing ring 511 is embedded in the side wall of the fourth lower box body 510, and the sixth sealing ring 521 is embedded in the side wall of the fourth upper box body 520. The fifth sealing ring 511 and the sixth sealing ring 521 are both connected to the conveying pipeline to seal the inner cavities of the fourth lower box body 510 and the fourth upper box body 520. The fourth air inlet connection The head 513 is integrally formed at the bottom of the fourth lower box 510 on one side near the cold water interface, the fourth air inlet connector 513 is connected to the exhaust end of the air pump 300 through a pipeline, the fourth exhaust connector 523 is integrally formed at the top of the fourth upper box 520 away from the cold water interface, the fourth exhaust connector 523 is connected to the second air inlet connector 232 through a pipeline, and the gas in a high temperature state after heat exchange is transported to the inner cavity of the fourth lower box 510 and the fourth upper box 520 through the air pump 300 to perform heat exchange on the cold water in the delivery pipeline connected to the cold water interface, and preheat the cold water. The preheated water enters the heat exchanger through the cold water interface for heat exchange, thereby increasing the heat exchange rate and being able to utilize the waste heat at the heating end.The utilization rate of energy is improved, and the purpose of energy conservation and emission reduction is achieved. The gas after heat exchange with cold water flows back to the inner cavity of the spiral tube 231 through the fourth exhaust joint 523 for circulating heat exchange, which can continuously preheat the cold water. In order to ensure the preheating effect, a pressure relief valve can also be installed on the fourth exhaust joint 523, so that the inner cavity of the fourth lower box 510 and the fourth upper box 520 is in a high pressure state. The compressed air will generate more heat, which can further increase the temperature of the gas and improve the preheating effect.

[0041] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A centralized heating energy-saving control device, characterized in that: The invention comprises a heat exchanger and a first high-pressure sealed box (100) arranged on a hot water outlet of the heat exchanger, wherein the first high-pressure sealed box (100) comprises a first lower box body (110) and a first upper box body (120), wherein the first upper box body (120) is arranged on the top of the first lower box body (110), a first air inlet joint (112) is arranged on a side of the first lower box body (110) away from the first upper box body (120), and a first air outlet joint (122) is arranged on a side of the first upper box body (120) away from the first lower box body (110); The first lower box body (110) and the first upper box body (120) are used to cover the interface between the hot water discharge port of the heat exchanger and the household pipe.

2. The central heating energy-saving control device according to claim 1, characterized in that: A first sealing ring (111) is arranged at the groove of the side wall of the first lower box body (110), and the first sealing ring (111) is a semicircular sealing ring. A second sealing ring (121) is arranged at the groove of the side wall of the first upper box body (120), and the second sealing ring (121) is a semicircular sealing ring. The second sealing ring (121) and the first sealing ring (111) are combined into a circular sealing ring.

3. The centralized heating energy-saving control device according to claim 1, characterized in that: A first connection block (113) is arranged around the side wall of the first lower box body (110), and a second connection block (213) is arranged around the side wall of the first upper box body (120), and the second connection block (213) is connected to the first connection block (113).

4. The centralized heating energy-saving control device according to claim 3, characterized in that: A heat exchange box (200) is arranged at the low-temperature drain outlet of the heat exchanger, and the heat exchange box (200) comprises a second lower box body (210), a second upper box body (220) and a spiral heat exchange tube (230), wherein the second upper box body (220) is arranged on the top of the second lower box body (210), and the spiral heat exchange tube (230) is arranged in the second lower box body (210) and the second upper box body (220), and the two ends of the spiral heat exchange tube (230) respectively pass through the bottom of the second lower box body (210) and the top of the second upper box body (220).

5. The centralized heating energy-saving control device according to claim 4, characterized in that: A third connecting block (211) is arranged around the side wall of the second lower box body (210), a first spiral connecting groove (212) is provided in the inner cavity of the second lower box body (210), a first connecting hole (213) is provided at the bottom of the inner cavity of the second lower box body (210), and a sealing groove (214) is provided around the side wall of the third connecting block (211).

6. The centralized heating energy-saving control device according to claim 5, characterized in that: A fourth connecting block (221) is arranged around the side wall of the second upper box body (220), and the fourth connecting block (221) is connected to the third connecting block (211); a second spiral connecting groove (222) is provided in the inner cavity of the second upper box body (220), and the second spiral connecting groove (222) matches the first spiral connecting groove (212); a second connecting hole (223) is provided at the top of the inner cavity of the second upper box body (220); and a sealing block (224) is arranged around the side wall of the third connecting block (211), and the sealing block (224) matches the sealing groove (214).

7. The centralized heating energy-saving control device according to claim 6, characterized in that: The spiral heat exchange tube (230) comprises a spiral tube (231), a second air inlet connector (232) and a second air exhaust connector (233); the spiral tube (231) matches the first spiral connection groove (212) and the second spiral connection groove (222); the spiral tube (231) is arranged in the second lower box (210) and the second upper box (220) through the first spiral connection groove (212) and the second spiral connection groove (222); the second air inlet connector (232) is arranged at the air inlet end of the spiral tube (231); the second air inlet connector (232) matches the second connection hole (223); the second air exhaust connector (233) is arranged at the air exhaust end of the spiral tube (231); the second air exhaust connector (233) matches the first connection hole (213).

8. The centralized heating energy-saving control device according to claim 7, characterized in that: An air pump (300) is connected between the heat exchange box (200) and the first high-pressure sealed box (100), the air inlet end of the air pump (300) is connected to the second exhaust connector (233), and the exhaust end of the air pump (300) is connected to the first air inlet connector (112).

9. The centralized heating energy-saving control device according to claim 8, characterized in that: A second high-pressure sealed box (400) is arranged at the water inlet of the cold end of the heat exchanger, and the second high-pressure sealed box (400) comprises a third lower box body (410) and a third upper box body (420), and the third upper box body (420) is arranged on the top of the third lower box body (410); A third sealing ring (411) is arranged at the groove of the side wall of the third lower box (410), and the third sealing ring (411) is a semicircular sealing ring. A third air inlet connector (412) is arranged at the bottom of the third lower box (410), and a fifth connecting block (413) is arranged around the side wall of the third lower box (410). The third air inlet connector (412) is connected to the first air outlet connector (122) through a pipeline. A fourth sealing ring (421) is arranged at the groove of the side wall of the third upper box body (420); the fourth sealing ring (421) is a semicircular sealing ring; the fourth sealing ring (421) and the third sealing ring (411) are combined to form a full-circular sealing ring; a third exhaust connector (422) is arranged at the top of the third upper box body (420); the third exhaust connector (422) is connected to the second air intake connector (232) through a pipeline; a sixth connecting block (423) is arranged around the side wall of the third upper box body (420); the sixth connecting block (423) is connected to the fifth connecting block (413).

10. A centralized heating energy-saving control device, characterized in that: The invention comprises a heat exchanger and a first high-pressure sealed box (100) arranged on a hot water outlet of the heat exchanger, wherein the first high-pressure sealed box (100) comprises a first lower box body (110) and a first upper box body (120), wherein the first upper box body (120) is arranged on the top of the first lower box body (110), a first air inlet joint (112) is arranged on a side of the first lower box body (110) away from the first upper box body (120), and a first air outlet joint (122) is arranged on a side of the first upper box body (120) away from the first lower box body (110); The first lower box (110) and the first upper box (120) are covered at the interface between the hot water outlet of the heat exchanger and the inlet pipe, and high-pressure gas is injected into the first lower box (110) and the first upper box (120), so that the gas in the first lower box (110) and the first upper box (120) is greater than the internal pressure between the hot water outlet and the inlet pipe.