An integrated platform system of a unitized formwork and a material placing machine and a construction method thereof
By designing an integrated platform system of unit mold frames and fabric machines, the problem of insufficient bearing of traditional hydraulic climbing molds is solved, and the construction safety and efficiency is improved. It is suitable for construction of ultra-high-rise buildings with a height of less than 250 meters.
Patent Information
- Application Number
- CN202411420724.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-12
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2044-10-12
AI Technical Summary
In the construction of ultra-high-rise buildings with a height below 250 meters, the load-bearing capacity of the traditional hydraulic climbing mold cannot meet the requirements of the fabric machine, resulting in the mold frame body periodically shaking during the fabric process, affecting construction safety.
An integrated platform system of unitary mold frame and cloth machine is designed, including unitary mold frame, climbing mechanism and cloth machine support device. It is connected to the core cylinder structure through embedded bolts to support the tripod frame and hydraulic power system to ensure that The lateral stability of the mold frame and independent climbing and fabric are achieved through retractable beef legs and locking devices to avoid shaking and conduction.
It improves construction safety and efficiency, ensures the independent operation of the mold frame and the fabric machine, avoids construction quality and safety hazards, and is suitable for vertical concrete structure construction at a height of less than 250 meters.
Smart Images

Figure CN118933331B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction equipment, and in particular to an integrated platform system of a unit formwork and a placing machine suitable for vertical concrete structure construction of high-rise buildings / structures and a construction method thereof. Background Art
[0002] In the construction of super-high-rise buildings / structures over 250 meters in height using reinforced concrete core tube + steel structure outer frame or reinforced concrete core tube + giant column structure, large-scale full-function integrated formwork platforms have obvious construction advantages. However, for super-high-rise buildings / structures below 250 meters in height, their comprehensive advantages are greatly reduced. The core tubes of super-high-rise buildings / structures below 250 meters in height generally adopt a mode of synchronous construction of horizontal and vertical structures, which cannot provide working space for large-scale integrated formwork platforms. Therefore, the construction of buildings / structures below 250 meters in height mostly adopts relatively light formworks such as hydraulic climbing formwork or integral lifting scaffolding.
[0003] As a necessary means for the construction of super-high-rise buildings / structures, it is of great significance that the concrete placing boom can be integrated with the formwork platform. However, the load-bearing capacity of the overall lifting scaffolding not only cannot meet the requirements of integration with the concrete placing boom, but also cannot meet the needs of lifting with large formwork. The load-bearing capacity of the traditional hydraulic climbing formwork can meet the weight of a small concrete placing boom. However, setting the concrete placing boom on the top of the hydraulic climbing formwork will cause the formwork frame to shake periodically with the concrete placing boom during the concrete placing process, which will have a certain impact on the safety of the formwork frame. Therefore, it is necessary to develop a rationally constructed, safe and efficient integrated platform system of unit formwork and concrete placing boom. Summary of the invention
[0004] Aiming at the problem that the existing material placing machine will cause the formwork frame to shake periodically with the material placing machine during the material placing process, thus affecting the safety of the formwork frame, the purpose of the present invention is to provide an integrated platform system of a unit formwork and a material placing machine and a construction method thereof.
[0005] The technical solution adopted by the present invention to solve the technical problem is: an integrated platform system of a unitized formwork and a material placing machine, comprising: a unitized formwork, a climbing mechanical device, a material placing machine support device and a material placing machine;
[0006] The unit formwork is arranged in the inner cavity of the core tube structure to be cast, and includes a main platform with a circular cross section, an operating formwork and a supporting formwork. The operating formwork is erected and connected to the top of the main platform, and the supporting formwork is hung at the bottom of the main platform. The hollow inner cavities of the main platform, the operating formwork and the supporting formwork are interconnected, and are used to install a placing machine support device and a placing machine.
[0007] The climbing mechanical device includes a plurality of wall attachment devices connected to the inner wall of the core tube structure, a supporting tripod connected to the wall attachment devices, a guide rail, a climbing shoe device and a hydraulic power system. The plurality of wall attachment devices are connected to the shear wall connecting beam of the core tube structure through embedded bolts. The top of the supporting tripod is connected to the wall attachment device, and the bottom thereof is against the inner wall of the core tube structure. The main platform of the unit formwork is connected to the supporting tripod, and the climbing oil cylinder of the climbing shoe device is connected to the hydraulic power system.
[0008] The concrete placing boom support device is arranged in the hollow inner cavity of the unit formwork, and comprises a load-bearing main beam, a supporting drum frame and a retractable corbel. The supporting drum frame is vertically arranged and connected to the top of the load-bearing main beam, the concrete placing boom is connected to the top of the supporting drum frame, the load-bearing main beam is detachably connected to the bottom of the main platform of the unit formwork, and the retractable corbels connected to both sides of the load-bearing main beam are buckled in the reserved holes of the core tube structure.
[0009] The integrated platform system of the unitized formwork and the concrete placing machine of the present invention comprises a climbing mechanism and a unitized formwork arranged in the inner cavity of the core tube structure to be cast, a concrete placing machine support device and a concrete placing machine arranged in the hollow inner cavity of the unitized formwork, a plurality of wall attachment devices of the climbing mechanism are connected to the core tube structure by embedded bolts, the top of the supporting tripod is connected to the wall attachment device, and the bottom thereof is against the inner wall of the core tube structure, the main platform of the unitized formwork is supported by the supporting tripod to ensure the lateral stability of the unitized formwork, the two climbing shoes of the climbing shoe device are buckled on the guide rail and can be alternately lifted along the guide rail to drive the entire integrated platform system to climb, and transfer the load during the climbing process to the concrete structure that has been cast; the supporting drum frame of the concrete placing machine support device is vertically arranged and connected to the top of the load-bearing main beam, the concrete placing machine is connected to the top of the supporting drum frame, and the load-bearing main beam is detachably connected to the main platform of the unitized formwork. At the bottom, the retractable brackets connected to both sides of the load-bearing main beam are buckled into the reserved openings of the core tube structure; the integrated platform system adopts a modular structure, and each module can be assembled flexibly, which can provide a construction platform with good closure, integrity and safety for formwork erection, steel bar binding and concrete pouring construction, and each module is remotely controlled by the operating system to realize intelligent construction; the unit formwork and the support device of the concrete placing boom are set up in a split type and detachably connected, leaving a safe anti-collision space between each other, further improving the construction safety; under the climbing condition, the unit formwork drives the concrete placing boom and the support device of the concrete placing boom to climb as a whole, improving the construction efficiency and construction safety; under the construction condition, the support device of the concrete placing boom and the unit formwork are independent of each other and do not interfere with each other. The shaking of the concrete placing boom under the spreading condition will not cause the shaking of the unit formwork, ensuring the construction quality and avoiding safety hazards. The integrated platform system is particularly suitable for the construction of vertical concrete structures of super-high-rise buildings / structures below 250 meters.
[0010] Furthermore, the fabric boom support device also includes a plurality of locking devices arranged at the bottom of the main platform, the locking devices include a hanger and a locking cylinder, the hanger is a U-shaped frame formed by a horizontal bar and two vertical bars, and the ends of the vertical bars are provided with ear plates vertically connected thereto, the locking cylinder is fixed to the top of the horizontal bar of the hanger, the locking cylinder is connected to the hydraulic power system, one end of a plurality of fastening bolts passes through the ear plates of the vertical bars and the main platform and are locked and fixed by nuts, the hanger is sleeved on the load-bearing main beam, and a gap is left between the load-bearing main beam and the locking cylinder located at the bottom thereof.
[0011] Furthermore, the supporting tripod includes a crossbeam, a column, an oblique brace, a machine position hanging plate and a movable supporting foot. The machine position hanging plate and the movable supporting foot are respectively fixed to the two ends of the column. The machine position hanging plate is bolted to the crossbeam, and the two ends of the oblique brace are respectively hinged to the ends of the crossbeam and the column. The machine position hanging plate is buckled on the wall attachment device, and the movable supporting foot is against the inner wall of the core tube structure.
[0012] Furthermore, the diagonal brace adopts an electric screw telescopic structure or a hydraulic telescopic structure.
[0013] Furthermore, the sum of the maximum shaking deformations of the unit mold frame and the supporting tube frame is less than the gap between the two. Assuming that the maximum shaking deformation value of the unit mold frame is A, the maximum shaking deformation value of the supporting tube frame is B, and the gap between the two is Z, the following requirements must be met: A+B<Z+k, where k is a safety distance parameter.
[0014] Furthermore, the climbing shoe device includes a guide rail, two climbing shoes and a climbing cylinder. The two climbing shoes are respectively connected to the two ends of the climbing cylinder. The guide rail is inserted into the wall attachment device and the movable supporting legs, and is supported on the cast concrete structure. The two climbing shoes of the climbing shoe device are buckled on the guide rail and reciprocate under the drive of the hydraulic cylinder, driving the guide rail and the unit formwork to climb alternately.
[0015] Furthermore, a template system is arranged between the unit formwork and the supporting cylinder frame, and the template system adopts any one of a full steel large template, an aluminum alloy large template, and a steel frame wooden large template.
[0016] In addition, the present invention also provides a construction method of an integrated platform system of a unitized formwork and a material placing boom, the steps of which are as follows:
[0017] S1: The integrated platform system of the unitized formwork and the concrete placing machine is installed in the inner cavity of the cast core tube structure, the integrated platform system is attached to the cast core tube structure of the N-1th layer, the concrete structure to be cast on the Nth layer is cured and the formwork is removed, and the wall attachment device is installed on the inner wall of the cast concrete structure of the Nth layer, and the steel bars are tied to the concrete structure to be cast on the N+1th layer;
[0018] S2: The climbing shoe device drives the guide rail to climb to the Nth layer of the poured concrete structure, and removes the wall attachment device on the wall of the N-2th layer of the poured concrete structure; after the reinforcement of the N+1th layer of the planned poured concrete structure is tied, the locking cylinder of the locking device is controlled to lift up, so that the main platform of the unitized formwork and the load-bearing main beam of the placing boom support device are locked and fixed, and the climbing mechanical device drives the unitized formwork, the placing boom support device and the placing boom to climb to the Nth layer in place synchronously, and then the locking cylinder is released, and the retractable bracket of the load-bearing main beam of the placing boom support device is buckled in the reserved hole of the Nth layer of the poured concrete structure, and the unitized formwork and the supporting tripod are supported on the wall attachment device on the Nth layer of the poured concrete structure wall;
[0019] S3: close the mold for the N+1th layer of concrete structure to be cast, cast the concrete for the N+1th layer of concrete structure to be cast through the concrete placing boom, and remove the formwork after the concrete of the N+1th layer of concrete structure is cured;
[0020] S4: Repeat steps S2 and S3 until the concrete pouring construction of the building core tube structure is completed layer by layer, where N is a natural number.
[0021] The construction method of the integrated platform system of the unitized formwork and the concrete placing boom of the present invention comprises the following steps: first, the integrated platform system is installed in the inner cavity of the cast core tube structure, the climbing shoe device drives the guide rail to climb to the Nth layer of the cast concrete structure, after the reinforcement binding of the concrete structure to be cast on the N+1th layer is completed, the locking cylinder of the locking device is controlled to be lifted, so that the main platform of the unitized formwork and the load-bearing main beam of the concrete placing boom support device are locked and fixed, after the climbing mechanical device drives the unitized formwork, the concrete placing boom support device and the concrete placing boom to synchronously climb to the Nth layer and put them in place, the locking cylinder is released, the retractable bracket of the load-bearing main beam of the concrete placing boom support device is buckled in the reserved hole of the concrete placing boom support device on the Nth layer, and the unitized formwork and the support three are locked and fixed. The corner frame is supported by a wall attachment device on the wall of the Nth layer of poured concrete structure, the N+1th layer of concrete structure to be poured is molded, and the concrete pouring of the N+1th layer of concrete structure to be poured is carried out by a placing boom. The formwork is removed after the concrete is cured, and this process is repeated until the concrete pouring construction of the building core tube structure is completed layer by layer. With the construction method of the present invention, under the climbing condition, the unit formwork drives the placing boom and the placing boom support device to climb as a whole, thereby improving the construction efficiency and construction safety. Under the construction condition, the placing boom support device and the unit formwork are independent of each other and do not interfere with each other. The shaking of the placing boom under the placing condition will not cause the shaking of the unit formwork, thereby ensuring the construction quality and avoiding safety hazards.
[0022] Furthermore, in the step S2: when the integrated platform system performs a climbing operation, the locking device locks the main platform of the unitary formwork and the load-bearing main beam of the fabric placing machine support device, and the hydraulic power system drives the climbing cylinder to extend and retract, driving the upper and lower climbing boots of the climbing mechanism to perform pre-lifting, so that one of the upper and lower climbing boots is supported on the guide rail, and the entire integrated platform system is lifted for a distance, so that the retractable brackets on both sides of the load-bearing main beam are separated from the lower surface of the reserved hole of the core tube structure. At this time, the hydraulic power system temporarily maintains pressure and locks, and after the retractable brackets retract, the hydraulic power system continues to drive the upper and lower climbing boots to continue to perform alternating operations, driving the entire integrated platform system to perform a lifting operation; after the integrated platform system is lifted to a certain height, the retractable brackets are controlled to be inserted into the reserved hole, the locking device is released, the main platform is separated from the load-bearing main beam, the hydraulic power system performs an oil return operation, the integrated platform system is lowered, the retractable brackets are seated in the reserved hole, and the climbing mechanism exits the operation.
[0023] Furthermore, in step S3: when the N+1th layer of concrete structure to be cast is molded, the integrated platform system is completely closed, and the operating formwork of the unit formwork is provided with a hanging formwork beam and a hanging formwork device, the bottom of the hanging formwork beam is connected to the slideway, the pulley on the top of the hanging formwork device is embedded in the slideway, and the hook at the bottom is connected to the formwork system. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 A plan view of an embodiment of an integrated platform system of a unitized formwork frame and a material placing machine of the present invention;
[0025] Figure 2 for Figure 1 AA section view;
[0026] Figure 3 It is a structural schematic diagram of a supporting tripod in one embodiment of the present invention;
[0027] Figure 4 It is a structural schematic diagram of a locking device in one embodiment of the present invention;
[0028] Figure 5 This is a schematic structural diagram of a wall attachment device according to an embodiment of the present invention;
[0029] Figures 6 to 11 It is a schematic diagram of each step of the construction method of the integrated platform system of the unit formwork and the material placing boom of the present invention.
[0030] The numbers in the figure are as follows:
[0031] Core tube structure 1; formwork system 2; steel bar 3; main platform 11; operating formwork 12; supporting formwork 14; supporting tripod 20; crossbeam 21; column 23; machine position hanging plate 24; movable supporting foot 25; diagonal brace 26; guide rail 31; climbing shoe device 32; wall attachment device 41; load-bearing main beam 51; supporting cylinder frame 52; hanger 54; locking cylinder 56; placing machine 60; DETAILED DESCRIPTION
[0032] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the drawings are all in very simplified form and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. For the convenience of description, the "upper" and "lower" described below are consistent with the upper and lower directions of the drawings, but this cannot be a limitation of the technical solution of the present invention.
[0033] Combination Figures 1 to 5 The integrated platform system of the unitized formwork and the material placing machine of the present invention is described, which comprises: the unitized formwork, the climbing mechanism, the material placing machine support device and the material placing machine 60;
[0034] The unit formwork is arranged in the inner cavity of the core tube structure 1 to be cast, and comprises a main platform 11 with a circular cross section, an operating formwork 12 and a supporting formwork 14. The operating formwork 12 is erected and connected to the top of the main platform 11. The operating formwork 12 is divided into two layers from top to bottom, namely, a reinforcement operation layer and a template operation layer, which are used to provide a safe operation platform for construction personnel to tie steel bars 3 and set up templates. The supporting formwork 14 is suspended at the bottom of the main platform 11 as an equipment operation layer. The hollow inner cavities of the main platform 11, the operating formwork 12 and the supporting formwork 14 are interconnected, and are used to install a supporting device and a placing machine 60. The gap between the periphery of the unit formwork and the core tube structure 1 to be cast is used to install the template system 2.
[0035] The climbing mechanical device includes a plurality of wall attachment devices 41 connected to the inner wall of the core tube structure 1, a supporting tripod 20 connected to the wall attachment device 41, a guide rail 31, a climbing shoe device 32 and a hydraulic power system. The plurality of wall attachment devices 41 are connected to the shear wall connecting beam of the core tube structure 1 through embedded bolts. The top of the supporting tripod 20 is connected to the wall attachment device 41, and the bottom thereof is against the inner wall of the core tube structure 1. The main platform 11 of the unit formwork is connected to the supporting tripod 20. Two climbing shoes of the climbing shoe device 32 are buckled on the guide rail 31, and the climbing oil cylinder of the climbing shoe device 32 is connected to the hydraulic power system. During the climbing process, the two climbing shoes of the climbing shoe device 32 can be alternately lifted along the guide rail 31 to drive the entire integrated platform system to climb.
[0036] The material placing machine support device is arranged in the hollow inner cavity of the unit formwork, and includes a load-bearing main beam 51, a supporting drum frame 52 and a retractable corbel. The supporting drum frame 52 is vertically arranged and connected to the top of the load-bearing main beam 51, and the material placing machine 60 is connected to the top of the supporting drum frame 52. The load-bearing main beam 51 is detachably connected to the bottom of the main platform 11 of the unit formwork, and the retractable corbels connected to both sides of the load-bearing main beam 51 are snapped into the reserved holes of the core tube structure 1, wherein the retractable corbels can be in the form of hydraulically driven, motor-driven screw retractable mechanism, hand-cranked screw retractable mechanism and gear rack sliding mechanism, etc., which are not limited here.
[0037] The integrated platform system of the unitized formwork and the concrete placing machine of the present invention comprises a climbing mechanism and a unitized formwork arranged in the inner cavity of the core tube structure 1 to be cast, a concrete placing machine support device and a concrete placing machine 60 arranged in the hollow inner cavity of the unitized formwork, a plurality of wall attachment devices 41 of the climbing mechanism are connected to the core tube structure 1 by embedded bolts, the top of the supporting tripod 20 is connected to the wall attachment device 41, and the bottom thereof is against the inner wall of the core tube structure 1, the main platform 11 of the unitized formwork is supported by the supporting tripod 20 to ensure the lateral stability of the unitized formwork, the two climbing shoes of the climbing shoe device 32 are buckled on the guide rail 31 and can be alternately lifted along the guide rail 31, driving the entire integrated platform system to climb, and transferring the load during the climbing process to the concrete structure that has been cast; the supporting drum frame 52 of the concrete placing machine support device is vertically arranged and connected to the top of the load-bearing main beam 51, the concrete placing machine 60 is connected to the top of the supporting drum frame 52, and the load-bearing main beam 51 is detachably connected to the supporting drum frame 52. The retractable brackets connected to the bottom of the main platform 11 of the unitized formwork and the two sides of the load-bearing main beam 51 are buckled in the reserved opening of the core tube structure 1; the integrated platform system adopts a modular structure, and each module is flexible to assemble, which can provide a construction platform with good sealing, integrity and safety for the construction of formwork erection, steel bar 3 binding and concrete pouring, and each module is remotely controlled by the operating system to realize intelligent construction; the unitized formwork and the supporting device of the fabricator are split and detachably connected, leaving a safe anti-collision space between each other, further improving the construction safety; under the climbing condition, the unitized formwork drives the fabricator 60 and the supporting device of the fabricator to climb as a whole, improving the construction efficiency and construction safety; under the construction condition, the supporting device of the fabricator and the unitized formwork are independent of each other and do not interfere with each other. The shaking of the fabricator 60 under the fabric condition will not cause the shaking of the unitized formwork, ensuring the construction quality and avoiding safety hazards. The integrated platform system is particularly suitable for the construction of vertical concrete structures of super-high-rise buildings / structures below 250 meters.
[0038] like Figure 4As shown, the supporting device of the material placing machine also includes a plurality of locking devices arranged at the bottom of the main platform 11, and the locking devices include a hanger 54 and a locking cylinder 56. The hanger 54 is a U-shaped frame formed by connecting a crossbar and two vertical bars, and the ends of the vertical bars are provided with ear plates vertically connected thereto. The locking cylinder 56 is fixed to the top of the crossbar of the hanger 54, and the locking cylinder 56 is connected to the hydraulic power system; one end of a plurality of fastening bolts passes through the ear plates of the vertical bars and the main platform 11 and is locked and fixed by nuts. The hanger 54 is sleeved on the load-bearing main beam 51, and a certain gap is left between the load-bearing main beam 51 and the locking cylinder 56 located at the bottom thereof, so as to provide a telescopic space for the locking cylinder 56. The locking cylinder 56 can be a cylinder or an electric screw. During the climbing stage of the integrated platform system, the locking cylinder 56 is locked to lock the main platform 11 and the load-bearing main beam 51, so that the unitized formwork can drive the fabric crane 60 to climb synchronously; under the construction condition of the integrated platform system, the fabric crane 60 and the unitized formwork are independent of each other and do not interfere with each other. The shaking of the fabric crane 60 under the fabric condition will not cause the shaking of the unitized formwork, thereby ensuring construction safety.
[0039] like Figure 3 As shown, the support tripod 20 includes a crossbeam 21, a column 23, a diagonal brace 26, a machine position hanging plate 24 and a movable support foot 25. The machine position hanging plate 24 and the movable support foot 25 are respectively fixed to the two ends of the column 23, the machine position hanging plate 24 is bolted to the crossbeam 21, and the two ends of the diagonal brace 26 are respectively hinged to the ends of the crossbeam 21 and the column 23 to form a triangular stable support structure; the machine position hanging plate 24 is buckled to the wall attachment device 41, and the movable support foot 25 is against the inner wall of the core tube structure 1. The verticality of the support tripod 20 is adjusted by adjusting the length of the movable support foot 25. More preferably, the diagonal brace 26 adopts an electric screw telescopic structure or a hydraulic telescopic structure, which is convenient for construction personnel to accurately adjust the verticality of the support tripod 20.
[0040] like Figure 5 This is a structural diagram of the wall-attaching device 41. The inner wall of the core tube structure 1 is provided with embedded bolts, and the wall-attaching device 41 is anchored to the inner wall of the core tube structure 1 through the embedded bolts. The specific structure and connection relationship of the wall-attaching device 41 are existing technical contents and will not be repeated here.
[0041] like Figure 2 As shown, the gap between the unit formwork and the support drum frame 52 of the supporting device of the fabric placing machine should be deformed by the mechanical parameters of the unit formwork and the support drum frame 52 in the specific project, and the sum of the maximum shaking deformation of the unit formwork and the support drum frame 52 should be less than the gap between the two. Assuming that the maximum shaking deformation value of the unit formwork is A, the maximum shaking deformation value of the support drum frame 52 is B, and the gap between the two is Z, the following requirements must be met: A+B<Z+k, where k is a safety distance parameter.
[0042] like Figure 2 and Figure 3 As shown, the climbing boot device 32 includes a guide rail 31, two climbing boots and a climbing oil cylinder. The two climbing boots are respectively connected to the two ends of the climbing oil cylinder, and from top to bottom are an upper climbing boot and a lower climbing boot. The guide rail 31 is inserted into the wall attachment device 41 and the movable support leg, and supported on the cast concrete structure. The upper climbing boot and the lower climbing boot of the climbing boot device 32 are buckled on the guide rail 31. The upper climbing boot and the lower climbing boot reciprocate under the drive of the hydraulic oil cylinder, driving the guide rail 31 and the unit formwork to climb alternately. The specific structure and connection relationship of the climbing mechanical device are the existing technical content and will not be repeated here.
[0043] A template system 2 is arranged between the unit formwork and the supporting cylinder frame 52. The template system 2 can adopt a full steel large template, an aluminum alloy large template, a steel frame wooden large template, etc.
[0044] Combination Figures 6 to 11 The construction method of the integrated platform system of the unitized formwork and the material placing boom of the present invention is described, and the specific steps are as follows:
[0045] S1: Figure 6 As shown, the integrated platform system of the unit formwork and the concrete placing machine is installed in the inner cavity of the cast core tube structure 1, the integrated platform system is attached to the cast core tube structure 1 of the N-1th layer, the concrete structure to be cast on the Nth layer is cured and the formwork is removed, and the wall attachment device 41 is installed on the inner wall of the cast concrete structure of the Nth layer, and the steel bars 3 are tied to the concrete structure to be cast on the N+1th layer; the construction personnel located at the formwork operation layer of the Nth layer perform the formwork pushing operation, and the construction personnel located at the steel bar tying operation layer of the N+1 layer perform the steel bar 3 tying operation without interfering with each other;
[0046] S2: Figure 7 As shown, the climbing shoe device 32 drives the guide rail 31 to climb a distance of one floor height, that is, to the Nth floor of the poured concrete structure, and removes the wall attachment device 41 on the wall of the N-2th floor of the poured concrete structure; Figure 8 As shown, after the steel bars 3 of the concrete structure to be poured on the N+1th layer are tied, the locking cylinder 56 of the locking device is controlled to be lifted, so that the main platform 11 of the unitized formwork is locked and fixed with the load-bearing main beam 51 of the supporting device of the concrete placing machine. After the climbing mechanical device drives the unitized formwork, the supporting device of the concrete placing machine and the concrete placing machine 60 to climb to the Nth layer in place synchronously, the locking cylinder 56 is released, and the retractable bracket of the load-bearing main beam 51 of the supporting device of the concrete placing machine 60 is buckled in the reserved hole of the poured concrete structure of the Nth layer, and the unitized formwork and the supporting tripod 20 are supported on the wall attachment device 41 on the wall of the poured concrete structure of the Nth layer, completing the force system conversion between the supporting tripod 20 and the load-bearing main beam 51;
[0047] S3: Fig. 9 and Fig.10As shown, the N+1th layer of concrete structure to be cast is molded, and the concrete of the N+1th layer of concrete structure to be cast is cast by the concrete placing machine 60, and the template is removed after the concrete of the N+1th layer of concrete structure is cured;
[0048] S4: Fig.11 As shown, steps S2 and S3 are repeated until the concrete pouring construction of the building core tube structure 1 is completed layer by layer, wherein N is a natural number.
[0049] The construction method of the integrated platform system of the unitized formwork and the concrete placing boom of the present invention comprises the following steps: first, the integrated platform system is installed in the inner cavity of the cast core tube structure 1, the climbing shoe device 32 drives the guide rail 31 to climb to the Nth layer of the cast concrete structure, and after the steel bars 3 of the concrete structure to be cast on the N+1th layer are tied, the locking cylinder 56 of the locking device is controlled to be lifted, so that the main platform 11 of the unitized formwork and the load-bearing main beam 51 of the concrete placing boom support device are locked and fixed, and after the climbing mechanical device drives the unitized formwork, the concrete placing boom support device and the concrete placing boom 60 to climb to the Nth layer in place synchronously, the locking cylinder 56 is released, and the retractable bracket of the load-bearing main beam 51 of the concrete placing boom support device is buckled in the reserved hole of the cast concrete structure on the Nth layer, and the unitized formwork is The wall attachment device 41 is supported on the wall of the Nth layer of poured concrete structure by the supporting tripod 20, the N+1th layer of the planned concrete structure is molded, and the concrete pouring of the N+1th layer of the planned concrete structure is carried out by the concrete placing boom 60. The formwork is removed after the concrete is cured, and this process is repeated until the concrete pouring construction of the building core tube structure 1 is completed layer by layer; by adopting the construction method of the present invention, under the climbing condition, the unit formwork drives the concrete placing boom 60 and the concrete placing boom support device to climb as a whole, thereby improving the construction efficiency and construction safety; under the construction condition, the concrete placing boom support device and the unit formwork are independent of each other and do not interfere with each other. The shaking of the concrete placing boom 60 under the spreading condition will not cause the shaking of the unit formwork, thereby ensuring the construction quality and avoiding safety hazards.
[0050] In the step S2, when the integrated platform system performs a climbing operation, the locking device locks the main platform 11 of the unit formwork and the load-bearing main beam 51 of the fabric placing machine support device, and the hydraulic power system drives the climbing cylinder to extend and retract, driving the upper and lower climbing boots of the climbing mechanism to perform pre-lifting, so that one of the upper and lower climbing boots is supported on the guide rail 31, and the entire integrated platform system is lifted to a small height, which height can make the retractable brackets on both sides of the load-bearing main beam 51 separate from the lower surface of the reserved hole of the core tube structure 1. At this time, the hydraulic power system temporarily maintains pressure and locks, and after the retractable brackets retract, the hydraulic power system continues to drive the upper and lower climbing boots to continue to perform alternating operations, driving the entire integrated platform system to perform a lifting operation; after the integrated platform system is lifted to a certain height, the retractable brackets are controlled to be inserted into the reserved hole, the locking device is released, the main platform 11 is separated from the load-bearing main beam 51, the hydraulic power system performs an oil return operation, the integrated platform system is lowered, the retractable brackets are seated in the reserved hole, and the climbing mechanism exits the operation.
[0051] like Fig. 9 and Fig.10 As shown, in the step S3, when the N+1th layer to be cast concrete structure is closed, the integrated platform system is completely closed, and a hanging formwork beam is set on the operating formwork 12 of the unit formwork, and the bottom of the hanging formwork beam is connected to the slideway, and the pulley on the top of the hanging formwork device is embedded in the slideway, and the hook at the bottom is connected to the steel formwork, so as to facilitate the sliding operation of the steel formwork.
[0052] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of the claims.
Claims
1. An integrated platform system of a unitized formwork and a material placing machine, characterized in that: include: Unitized formwork, climbing mechanism, concrete placing boom support device and concrete placing boom; The unit formwork is arranged in the inner cavity of the core tube structure to be cast, and includes a main platform with a circular cross section, an operating formwork and a supporting formwork. The operating formwork is erected and connected to the top of the main platform, and the supporting formwork is hung at the bottom of the main platform. The hollow inner cavities of the main platform, the operating formwork and the supporting formwork are interconnected, and are used to install a placing machine support device and a placing machine. The climbing mechanical device includes a plurality of wall attachment devices connected to the inner wall of the core tube structure, a supporting tripod connected to the wall attachment devices, a guide rail, a climbing shoe device and a hydraulic power system. The plurality of wall attachment devices are connected to the shear wall connecting beam of the core tube structure through embedded bolts. The top of the supporting tripod is connected to the wall attachment device, and the bottom thereof is against the inner wall of the core tube structure. The main platform of the unit formwork is connected to the supporting tripod, and the climbing oil cylinder of the climbing shoe device is connected to the hydraulic power system. The concrete placing boom support device is arranged in the hollow inner cavity of the unit formwork, and comprises a load-bearing main beam, a supporting drum frame and a retractable corbel. The supporting drum frame is vertically arranged and connected to the top of the load-bearing main beam, the concrete placing boom is connected to the top of the supporting drum frame, the load-bearing main beam is detachably connected to the bottom of the main platform of the unit formwork, and the retractable corbels connected to both sides of the load-bearing main beam are buckled in the reserved holes of the core tube structure.
2. The integrated platform system of unitized formwork and material placing boom according to claim 1, characterized in that: The supporting device of the concrete placing machine also includes a plurality of locking devices arranged at the bottom of the main platform, the locking devices include a hanger and a locking cylinder, the hanger is a U-shaped frame formed by connecting a horizontal bar and two vertical bars, and the ends of the vertical bars are provided with ear plates vertically connected thereto, the locking cylinder is fixed to the top of the horizontal bar of the hanger, the locking cylinder is connected to the hydraulic power system, one end of a plurality of fastening bolts passes through the ear plates of the vertical bars and the main platform and are locked and fixed by nuts, the hanger is sleeved on the load-bearing main beam, and a gap is left between the load-bearing main beam and the locking cylinder located at the bottom thereof.
3. The integrated platform system of unitized formwork and material placing boom according to claim 1, characterized in that: The supporting tripod includes a crossbeam, a column, an inclined brace, a machine position hanging plate and a movable supporting foot. The machine position hanging plate and the movable supporting foot are respectively fixed to the two ends of the column. The machine position hanging plate is connected with the crossbeam bolts. The two ends of the inclined brace are respectively hinged to the ends of the crossbeam and the column. The machine position hanging plate is buckled on the wall attachment device, and the movable supporting foot is against the inner wall of the core tube structure.
4. The integrated platform system of the unitized formwork and the material placing boom according to claim 3 is characterized by: The diagonal brace adopts an electric screw telescopic structure or a hydraulic telescopic structure.
5. The integrated platform system of unitized formwork and material placing boom according to claim 1, characterized in that: The sum of the maximum shaking deformations of the unit mold frame and the supporting tube frame is less than the gap between the two. Assuming the maximum shaking deformation value of the unit mold frame is A, the maximum shaking deformation value of the supporting tube frame is B, and the gap between the two is Z, the following requirements must be met: A+B<Z+k, where k is a safety distance parameter.
6. The integrated platform system of unitized formwork and material placing boom according to claim 1, characterized in that: The climbing shoe device includes a guide rail, two climbing shoes and a climbing cylinder. The two climbing shoes are respectively connected to the two ends of the climbing cylinder. The guide rail is inserted into the wall attachment device and the movable supporting legs, and is supported on the cast concrete structure. The two climbing shoes of the climbing shoe device are buckled on the guide rail and reciprocate under the drive of the hydraulic cylinder, driving the guide rail and the unit formwork to climb alternately.
7. The integrated platform system of unitized formwork and material placing boom according to claim 1, characterized in that: A template system is arranged between the unit formwork frame and the supporting cylinder frame, and the template system adopts any one of a full steel large template, an aluminum alloy large template, and a steel frame wooden large template.
8. The construction method of the integrated platform system of the unitized formwork and the concrete placing boom according to claim 2, characterized in that: Here are the steps: S1: The integrated platform system of the unitized formwork and the concrete placing machine is installed in the inner cavity of the cast core tube structure, the integrated platform system is attached to the cast core tube structure of the N-1th layer, the concrete structure to be cast on the Nth layer is cured and the formwork is removed, and the wall attachment device is installed on the inner wall of the cast concrete structure of the Nth layer, and the steel bars are tied to the concrete structure to be cast on the N+1th layer; S2: The climbing shoe device drives the guide rail to climb to the Nth layer of the poured concrete structure, and removes the wall attachment device on the wall of the N-2th layer of the poured concrete structure; after the reinforcement of the N+1th layer of the planned poured concrete structure is tied, the locking cylinder of the locking device is controlled to lift up, so that the main platform of the unitized formwork and the load-bearing main beam of the placing boom support device are locked and fixed, and the climbing mechanical device drives the unitized formwork, the placing boom support device and the placing boom to climb to the Nth layer in place synchronously, and then the locking cylinder is released, and the retractable bracket of the load-bearing main beam of the placing boom support device is buckled in the reserved hole of the Nth layer of the poured concrete structure, and the unitized formwork and the supporting tripod are supported on the wall attachment device on the Nth layer of the poured concrete structure wall; S3: close the mold for the N+1th layer of concrete structure to be cast, cast the concrete for the N+1th layer of concrete structure to be cast through the concrete placing boom, and remove the formwork after the concrete of the N+1th layer of concrete structure is cured; S4: Repeat steps S2 and S3 until the concrete pouring construction of the building core tube structure is completed layer by layer, where N is a natural number.
9. The construction method of the integrated platform system of the unitized formwork and the concrete placing boom according to claim 8, characterized in that: In the step S2: when the integrated platform system performs a climbing operation, the locking device locks the main platform of the unit formwork and the load-bearing main beam of the fabric placing machine support device, and the hydraulic power system drives the climbing oil cylinder to extend and retract, driving the upper and lower climbing boots of the climbing mechanical device to perform pre-lifting, so that one of the upper and lower climbing boots is supported on the guide rail, and the entire integrated platform system is lifted for a distance, so that the retractable brackets on both sides of the load-bearing main beam are separated from the lower surface of the reserved hole of the core tube structure. At this time, the hydraulic power system temporarily maintains pressure and locks, and after the retractable brackets are retracted, the hydraulic power system continues to drive the upper and lower climbing boots to continue to perform alternating operations, driving the entire integrated platform system to perform a lifting operation; after the integrated platform system is lifted to a certain height, the retractable brackets are controlled to be inserted into the reserved hole, the locking device is released, the main platform is separated from the load-bearing main beam, the hydraulic power system performs an oil return operation, the integrated platform system is lowered, the retractable brackets are seated in the reserved hole, and the climbing mechanical device exits the operation.
10. The construction method of the integrated platform system of the unitized formwork and the material placing boom according to claim 8, characterized in that: In step S3: when the N+1th layer to be cast concrete structure is closed, the integrated platform system is completely closed, and the operating formwork of the unit formwork is provided with a formwork hanging beam and a formwork hanging device, the bottom of the formwork hanging beam is connected to the slideway, the pulley at the top of the formwork hanging device is embedded in the slideway, and the hook at the bottom is connected to the formwork system.